Beruflich Dokumente
Kultur Dokumente
SARAWAK OPERATIONS
WORKPACK
SIGNATU
PERSONNEL NAME POSITION DATE
RE
Mohammad ACSB
PREPARED BY:
Yusmin ENGINEER
ACSB
REVIEWED BY: Azmi Ahmad
MANAGER
M Syakiq Mat PCSB
Sihat ENGINEER
ENDORSED BY:
PCSB
BME Manager
MANAGER
SECTION
APPROVED BY: HEAD
SUMANDAK
OIM
TABLE OF CONTENTS
1 INTRODUCTION
2
1.1 Field Background
2
1.2 Project Background
2
1.3 Equipment Details & Specifications
3
3 MANPOWER LOADING 14
3.1 Manpower List 14
3.2 Organization Chart
14
3.3 PCSB Focal Person
15
3.4 HSE Requirement
15
3.4.1 Toolbox Meeting 15
3.4.2 PTW 15
3.4.3 JHA 15
5 PROJECT DETAILS 21
5.1 Project Schedule
21
2
6 APPENDICES
21
3
1 INTRODUCTION
Temana Platform
g) Shall verify the ACB and MCC panels operation and interlocks.
h) Shall verify the control wiring system against the schematic diagram.
i) Shall inspect and service MCC contactors and circuit breakers for condition,
alignment and correct setting.
j) Shall troubleshoot and rectify any switchgear and MCC having abnormalities.
4
1.3 Equipment Details & Specifications
Lists below show the switchgears and MCC involved during shutdown
maintenance:
5
2 DETAILED WORK SCOPE
6
breaker insulation resistance should be in accordance with
attached appendices table for minimum IR value.
xiv. Clean the area of arc chutes until thoroughly clean and
ensure the arc chutes are clear of contamination and have
no significant damage on grids or ceramics.
xv. Perform cleaning and lubricate the ACB contacts (aux,
finger) and linkages
xvi. Determine IR and contact resistant measurement after
servicing.
xvii. Check on earthing system, alignment and rack condition.
xviii. Report on abnormal findings immediately to PIC.
xix. Check for leftover tools and consumables.
xx. Rack in the breaker to service position.
7
iii. Contractor to confirm no supply from busbar using HV Test
Pen.
iv. Before perform electrical test, ensure the entire load
(breaker, MCC, CT, VT and fuses) to busbar is
disconnected.
v. Compare equipment nameplate data with drawings and
specifications.
vi. Inspect busbar for physical damage and correct connection
in accordance with single-line diagram.
vii. Inspect all bolted electrical connections for high resistance.
viii. Verify tightness of accessible bolted electrical connections
by calibrated torque-wrench method
ix. Measure insulation resistance of each busbar, phase-to-
phase and phase-to-ground for one minute. Insulation-
resistance test voltages and resistance values shall be in
accordance with manufacturer’s published data or
attached table on appendices. Minimum resistance values
are for a nominal 1000 foot busbar run.
x. Perform contact-resistance test on each connection point
of non-insulated busbar. Compare bolted connection
resistances and bus joint resistances to values of similar
connections. Microhm drop values shall not exceed the
high levels of the normal range as
8
current through switches and over current protective
devices.
ii. The temperature of the conductor is above the dew point
of the ambient air. When this is not the case, a moisture
coating will form on the insulation surface and in some
cases will be absorbed by the material.
iii. The surface of the conductor is free from carbon and other
foreign matter that can become conductive on humid
conditions.
iv. Applied voltage is not too high when testing low voltage
system. Too much voltage will damage the insulation.
v. The system under test needs completely discharged to the
ground. The grounding discharge time should be about five
times the testing charge time.
9
iii. Plug one end of the black test lead to the common
terminal on the meter end and touch the test probe to the
ground or another conductor. Sometimes it is helpful to
ground all conductors that are not part of the test.
iv. Plug one end of the red test lead to the volt/ohm terminal
on the meter and connect the test probe to the conductor
to be tested.
v. Press the test button to apply the desired voltage and read
the resistance display on the meter. It could take a few
seconds for the reading to be settled. The higher the
resistance the better.
vi. Test the insulation between phase to phase and phase to
neutral as per checklist.
vii. Keep a dated record of the measured value.
viii. If some of the conductors fail the test, identify the
problems and take necessary actions. Moisture, water and
dirt can create low resistance readings.
10
Figure 2: Connection Diagram of Busbar Insulation Resistance Test
i. Make certain that the circuit breaker is de-energised on both sides, closed
and safety grounded and that local safety regulations are followed.
ii. Ground the test instrument.
iii. Make sure that the test instrument is switched off.
iv. Connect current and sensing cables according to the drawing.
v. Switch the test instrument on.
vi. Set the test current to minimum 100A (according to ANSI C 37.09)
vii. Perform the measurement.
viii. Repeat the test on the different phase.
11
Figure 3: Connection Diagram of Ductor/Contact Resistance Test
12
dead.
ET : 1 hr
13
MCC 15 units MCC
ET : 4 2 units Isolator Switch
hrs
14
thermography on switchgear SG-7510. SB7710 and SB-
7720.
ET : 8 hr
3 MANPOWER LOADING
15
3.2 Organization Chart
17
4 TOOLS & MATERIAL LIST
18
4.2 Lifting Plan
During the turnaround activity, ASAGA team will bring a numbers of boxes
and need a crane service to carry the loads to the platform. The
dimension and estimated weight of the boxes as illustrated below.
ITEM 1
BOX 1: Tools and Test Equipments
ITEM 2
BOX 2: Tools and Test Equipments
19
ITEM 3
BOX 3: Tools and Test Equipments
ITEM 4
BOX 4: Contact Resistance Tester
20
ITEM 5
BOX 5: Plastic Container
ITEM 6
2x Fiber Ladder
21
5 PROJECT DETAILS
22
6 APPENDICES
23