The following activities are carried out for the
various alternatives considered to justify the final
choice of the location of different components of the
River surveys project :
Reservoir surveys
Head works surveys (dams, barrage, weir, etc)
Plant sites and colonies
Canal, branch canals, and water conductor
system
Major canal structures
Power house, switch yard, surge shaft, tail race
tunnel(s), adits, penstocks etc.
The different activities of survey and
investigations which are carried out before
preparing a detailed project report are given
1. Topographical Surveybelow
2. Dam Site
3. Reservoir Area Survey
4. Survey for Power Channel
Engineering Geological
Survey
Surface investigations Sub surface investigations
Ascertaining the regional geology of the area Water tightness of the bed rock is determined
the site specific geological mapping is taken by conducting water pressure tests. These
up by intensive surface traverses of the tests are normally carried out at proposed
project area and also with the aid of aerial dam sites, powerhouse, other caverns and
photographs & satellite imagery, for coverage reservoir locations etc. Drifts are generally
of inaccessible area comprehensively made to explore dam abutments, tunnel
alignments
Natural factors that can not be
denied as other consideration in
build