Sie sind auf Seite 1von 2

ADR continuous notes

Advantages of ADR 2. malice


1. Less time consuming, 3. gross negligence
2. less tedious (b) "ADR Provider" means institutions or persons
3. Less confrontational accredited as mediator, conciliator, arbitrator,
4. More productive of goodwill and lasting neutral evaluator, or any person exercising similar
relationships functions in any Alternative Dispute Resolution
5. Parties are in control system. This is without prejudice to the rights of the
a. Everything is in the hands of the parties to choose nonaccredited individuals to act as
parties, including the proceedings mediator, conciliator, arbitrator, or neutral evaluator
6. Privileged and confidential of their dispute.
a. No records (only with the arbitral
tribunal BUT it cannot be Construction dispute
published) Construction disputes which fall within the original
and exclusive jurisdiction of the Construction
Party autonomy Industry Arbitration Commission (the "Commission")
 Freedom of parties to make arrangements shall include those between or among parties to, or
to resolve their own disputes. who are otherwise bound by, an arbitration
 If there is no agreement, the tribunal will agreement, directly or by reference whether such
have a hand in the arbitration and will parties are project owner, contractor, subcontractor,
conduct it in a manner it deems quantity surveyor, bondsman or issuer of an
appropriate. insurance policy in a construction project.
 Basis: Civil code, Art 1306
Case: DENR vs UCPB The Commission shall continue to exercise original
and exclusive jurisdiction over construction disputes
Discussion although the arbitration is "commercial" pursuant to
The case is unusual because it does not concern Section 21 of this Act.
about construction. The construction or the CIAC
supposedly only governs those construction disputes If a case is filed in court and in is a construction
submitted to them over which there is an arbitration dispute – dismiss the case
agreement.
XPT if parties submit a written agreement to have
That may be the case, but in this case, the parties the case resolved by court instead of CIAC.
specifically picked out the CIAC rules of procedure to
govern their arbitration – even if the dispute is not a Reason: in a construction dispute, the process is
construction dispute The parties actually did not almost complete- CIAC can enforce judgment.
submit to the jurisdiction of CIAC but only borrowed
their rules. In a commercial dispute – even if submitted to an
arbitral institution, such institution has no power to
SC said this is allowed. Since they submitted to the execute its own arbitral award – it has to go to court
rules of CIAC in the governance of their arbitration, for enforcement.
they are governed by such.
If any dispute other than construction– the court
Special ADR rules will not dismiss the case but suspend the
Special rules of court when part of arb proceedings proceedings.
submitted to the court. There are certain arts that
can be submitted for resolution – the remedy is Case: LM Power vs CIAC
similar to provisional remedies. (interim measures of The dispute here is with respect to discrepancies as
protection) to amount of advances and billable accomplishment
of the project – it is a construction dispute and it is
Applies during enforcement of arbitral award or the CIAC which has jurisdiction over the case.
declaration of nullity of the arbitral award.
As to the arbitration proceedings, the procedure Case: Federal Builders vs Power
chosen by the parties will govern the arbitration Here, they had an agreement to arbitrate but
proceeings. unsigned and when the dispute arose, there was a
request for arbitration – even if unsigned, it’s a
Liability of ADR providers source for an agreement to arbitrate.
Sec 5
The ADR providers and practitioners shall have the The council submitted a letter that it agreed to
same civil liability for the Acts done in the arbitrate and asked for extension to file.
performance of then duties as that of public officers
as provided in Section 38 (1), Chapter 9, Book of the Case: Philrock vs CIAC
Administrative Code of 1987. – upon a clear showing It originally started with RTC but dismissed due to an
of : arbitration agreement and submitted to CIAC. To
1. bad faith parties went to CIAC but there were issues as to
ADR continuous notes
inclusion of other officers in the proceedings. When
they could not agree, they withdrew their consent to
arbitrate and went back to the court but the court
did not accept.

Should CIAC resume proceedings? YES


There was an arbitration agreement. Once parties
agree, that vests jurisdiction to the tribunal. The only
thing that will terminate the jurisdiction is UNTIL
AND WHEN IT RENDERS AN AWARD. Jurisdiction is
NOT lost by mere withdrawal of parties.

Can CIAC award damages in this case?


YES.

Power of CIAC is clear-like an RTC has power to


resolve issues, so long as connected with
construction dispute.

It can also award damages based on evidence


presented by parties.

CIAC’s jurisdiction is complete and has power to


enforce its own award. No need to seek intervention
of court.

Can also award interests, atty’s fees and expenses of


litigation, other than damages.

Next time, proceed with mediation.

Assignment: watch a movie – DISCLOSURE


[Michael douglas and Demi moore]

Das könnte Ihnen auch gefallen