Sie sind auf Seite 1von 2

Project : Proposed Two Storey Building

Location : Babag, Lapu Lapu City


Subject : Bill of Quantities - Architectural Building

Division 04 00 00 Architectural Works - Building


Unit Price
Item Work / Description Unit Quantity Amount
Material Labor Others Total
01 00 Basic Requirements

03 00 Masonry Works
( include stiffiner columns, copping & lintel beams,
joint seal, edges and use of necessary tools /
equipment and all other materials required to
complete the works)

CHB 150mm thick from ground to second floor m2 206.22 180.00 180.00 360.00 74,239.20
Cement Plaster Finish m2 412.44 245.00 50.00 295.00 121,669.80

03 02 LSB material - -
Skimcoat Finish (Interior & Exterior Walls) m2 242.10 63.50 80.00 143.50 34,741.35

-
04 03B. Subtotal - Masonry Works 230,650.35

04 00 Miscellaneous Metal Works


( Include supply,
fabrication,installation,anchor,welding,patching,g
rinding,cleaning and all other required materials,
tools and equipment to complete the works except
painting)

40 01 Stair Railings (Exterior Stairs)


Metals,angle bars,steel plates kgs. 400.00 175.00 70.00 245.00 98,000.00
04 02 Aluminum Composite Panels
Supply & installation of aluminum composite
m2 44.78 1,374.25 1,374.25 61,538.92
panels
Aluminum sub framing lot 1.00 10,000.00 10,000.00
Labor & supervision m2 44.78 128.00 128.00 5,731.84

04 04. Subtotal - Miscellaneous Metal Works 175,270.76

05 00 Doors, Windows and Mirrors


Installation of Doors m2 4.20 2,600.00 1,335.75 3,935.75 16,530.15
Installation of windows m2 38.00 3,000.00 1,335.75 4,335.75 164,758.50
05 00. Subtotal - Doors 181,288.65

06 00 Finishes
06 01 Ceiling works
Gypsum board 12mm in LSF

(Supply and installation of suspended ceiling in


light steel frame including all necessary support
system according to manufacturer's requirements
and provide opening with accessories for access to
utility services as indicated and other required
materials and tools to complete the works)
Gypsum board (ordinary) m2 136.80 270.50 199.50 470.00 64,296.00
06 02 Tile Works
(Installation of OSM tiles and include trim / corner
beads,grout,adhesive and all necessary
materials,tools & equipment required to complete
the works)
to Floor tiles m2 136.80 250.00 199.50 449.50 61,491.60

06 04 Floor Finishes - - -
(Include cleaning,grinding,patching or making
good surfaces ,sealant and all other
materials,tools & equipment to complete the
works) - - -
06 05 Painting Works - -

(Include preparation & making good of surfaces


,patching,sanding,cleaning,neutralizer,prime & top
coats,platforms and all other necessary
materials,tools and equipment required to
complete the works - -
Wall & included structures - -
to interior m2 206.00 160.30 119.70 280.00 57,680.00
to exterior m2 729.68 140.35 139.65 280.00 204,310.40
Ceiling works -
to interior m2 60.00 160.30 119.70 280.00 16,800.00
to exterior m2 100.00 140.35 139.65 280.00 28,000.00

04 06.Subtotal - Finishes 432,578.00

07 00 Roofing
(Supply and installation of roofing sheets rib
type,guttering,flashing and include
fastening,insulation,accessories and other required
materials,tools & equipment necessary to
complete the works)
Pre-painted 0.6mm thk. m2 68.40 498.46 166.15 4,258.89 291,308.39
Flashing Prepainted 0.6mm thk. m2 6.09 381.78 127.26 11,462.22 69,804.92
-
OTHERS 361,113.31
Allow other items for which the contractor
requires payment to comply with all respect
with the provisions of the relevant conditions
of the contract particular specifications and
drawings which are not in the Bills of
Quantities.

A _________________________________ item

B _________________________________ item

C _________________________________ item

04 07. Subtotal - OTHERS -

SUBTOTAL 1,380,901.07

12% VAT 165,708.13

OVERALL TOTAL Total Architetural Works 1,546,609.19

OVERALL TOTAL Total Project Cost 2,377,987.08

Das könnte Ihnen auch gefallen