Beruflich Dokumente
Kultur Dokumente
IT.06
hat is project controls? Simply defined, it would or engineered dissemination, disposition, and retention of record-
IT.06.1
2003 AACE International Transactions
INFORMATION AND COMMUNICATION The following is a breakdown of some various project deliv-
FLOW CONTROL erables with their respective relation to document management
and project controls.
At the very onset of any project, there is usually a kick-off
meeting. At some point in the meeting, a discussion will ensue on
how and what information will be provided to the team members Studies
so that they can do their work. A project communication and doc- Generally characterized as a feasibility study with a Class 4
ument distribution matrix must be developed either during this estimate and single page summary schedule. It is considered as a
meeting or shortly afterward in another forum. technical corporate document. It is kept in the project files for ref-
Here is a sample list of the various forms of information and erence.
communications that need to be included in this matrix:
IT.06.2
2003 AACE International Transactions
Figure 1
IT.06.3
2003 AACE International Transactions
Figure 2
IT.06.4
2003 AACE International Transactions
Specifications of these documents be monitored and recorded in the project
Considered a technical corporate document. Important to schedule throughout their life cycle. A good document manage-
design development, purchasing, and fabrication. Copies are kept ment system will provide the necessary means to report status.
in the project files.
PROJECT CLOSEOUT
General Arrangements
These drawings are considered to be technical working docu- Project closeout is a two-step process that includes creation of
ments. Schedulers use these to help develop the project schedule. a project completion report and the disposition of the project doc-
Cost engineers find this useful for project cost set-up. Both cur- uments. The responsible parties should include the project man-
rent and previous issue copies are kept in the project files. ager, discipline project leaders, document control clerk, project
secretary, and storage facility coordinator.
The project completion report is the project manager’s
Piping Isometrics responsibility and will include project general information such
These drawings are considered to be technical working docu- as contract number, project title, location, client name, etc. It
ments. Schedulers use these to help develop the project schedule. includes process description, listing of key personnel, contract his-
Used for purchasing fabricated pipe. Both current and previous tory, scope of work, important schedule dates and milestones,
issue copies are kept in the project files. project costs and a critique highlighting problems, workforce
availability, timeliness of client reviews and approvals, expediting,
etc.
Civil Plans, Sections, and Details The document disposition process will be spearheaded by the
These drawings are considered to be technical working docu- project manager. The disposition will be done as outlined by the
ments. Schedulers use these and their issuance information to project file storage procedures. It is common for a project manag-
help develop and maintain the project schedule. Both current er to want to keep everything in storage, but it is imperative from
and previous issue copies are kept in the project files. a space capacity and cost standpoint to follow the procedures
unless the project’s outcome dictates otherwise.
The following is a sample document index with associated
Structural Steel Plans project closeout disposition codes using the list of project deliver-
These drawings are considered to be technical working docu- ables above.
ments. Schedulers use these and their issuance information to Project disposition codes:
help develop and maintain the project schedule. Used for pur-
chasing and fabricating steel. Both current and previous issue • A: Archived using electronic media.
copies are kept in the project files. • AH: Archived using hard copies.
• D: Discard at project closeout.
• O: Original sent to client.
HVAC Plans, Sections, and Details • OX: Original retained in secured area, copy to client.
These drawings are considered to be technical working docu- • P: Discard unless specifically directed by project manager
ments. Schedulers use these and their issuance information to based upon project status.
help develop and maintain the project schedule. Both current • Studies: P
and previous issue copies are kept in the project files. • Project schedules: P
• Project estimates and scope: P
• Piping and instrument diagrams: A,O
Single Line Diagrams • Equipment list: D, AH, B
These drawings are considered to be technical working docu- • Drawing list: D
ments. Schedulers use these and their issuance information to • Tie-in list: D
help develop and maintain the project schedule. Both current • Instrument list: D
and previous issue copies are kept in the project files. • Specifications: D, A
• General arrangements: A,O
• Piping isometrics: A,O
Power Plans • Civil plans, sections, and details: A,O
These drawings are considered to be technical working docu- • Structural steel plans: A,O
ments. Schedulers use these and their issuance information to • HVAC plans, sections, and details: A,O
help develop and maintain the project schedule. Both current • Single line diagrams: A,O
and previous issue copies are kept in the project files. • Power plans: A,O
See Figures 3, 4, 5, and 6.
All of these documents are obviously required for providing Note that combinations of the disposition code can be uti-
effective project controls. They are required to be issued for lized.
approval, design, and/or construction on a timely basis, so as not Realizing that the majority of the above will be represented in
to jeopardize the project schedule. It is imperative that the status both hard and electronic file versions, the ease of retrieval of this
IT.06.5
2003 AACE International Transactions
Specification Approval
Comment
(Retu Resolution
rn
Intra-Discipline Document Control
Cycl
Peer Review Login/Distribution
e)
Figure 3
IT.06.6
2003 AACE International Transactions
D r a wi n g A p p r o v a l
Project Engineer
CAD
Operator
Comment
Resolution
Document
Control
Design Originator
Review
Q & A’s
Design Leader
Q & A’s
Design Leader
Review
CAD
Operator
Inter-discipline (Ret
Review urn
Cycl Design Leader
e)
Checker
Section Manager
Section Manager
Review
Project Engineer
Project Engineer
Review
Document Control
Distribution
Document Control
Release
Figure 4
IT.06.7
2003 AACE International Transactions
Ve n d o r D o c u m e n t A p p r o v a l
Vendor
PE Client PE
(Return Cycle)
PE
(Return Cycle)
Primary Approver
Comment
Resolution
Project Engineer
Document Control
Figure 5
IT.06.8
2003 AACE International Transactions
Technical Package
(includes as required)
• Specifications
• Drawings
Inquiry Requisition
Engineering
Bidders
Q & A’s (Equip. Vendors,
Purchasing
Fabricators,
Subcontractors)
Shop
Simultaneous Copies Inspection
Q & A’s
Purchasing Client
Purchasing
Vendor
Ship
Q & A’s Order
Project Client
(Distribute
Manager Project
d
Commercial Manager Vendor
According Receiving
Evaluation to Invoice Report
Purchasing Document
Technical Distributio Purchase
Evaluation n Matrix - Order
Q & A’s Typically
As Shown) Accounts
Rec./Pay.
Vendor
Fabrication
Figure 6
IT.06.9
2003 AACE International Transactions
data can be realized. If physical storage space is lacking in the
retention area, the hard copies may be discarded. Of course, you
do not want to discard documents such as signed agreements and
the like.
If a project’s status at the end is not desirable and the project
cost and schedule information is retained accordingly, it is easy to
access and rebuild the project if necessary for claims or other liti-
gation.
REFERENCES
IT.06.10