Beruflich Dokumente
Kultur Dokumente
PROJECT TITLE
FASA 1A:
Revised : 00 (12-May-2020)
CONTENTS
1. PURPOSE ................................................................................................... 3
2. SCOPE OF WORK ...................................................................................... 3
3. REFERENCES SPECIFICATION ................................................................ 3
4. MANPOWER ............................................................................................... 3
5. MATERIAL & EQUIPMENT......................................................................... 4
5.1. MATERIAL ................................................................................................ 4
5.1.1. Bricks ..................................................................................................... 4
5.1.2. Cement & Sand ...................................................................................... 4
5.1.3. Mortar..................................................................................................... 4
5.2. EQUIPMENT............................................................................................. 4
6. WORK FLOW CHART................................................................................. 5
6.1. SETTING OUT .......................................................................................... 5
6.2. SURFACE PREPARATION ...................................................................... 5
6.3. PANTING REBAR, STIFFENER, TIE BEAM & LINTEL BEAM ................. 6
6.3.1. Planting Bar ........................................................................................... 6
6.3.2. Stiffener Column .................................................................................... 8
6.3.3. Tie Beam................................................................................................ 8
6.3.4. Lintel Beam .......................................................................................... 10
6.4. MORTAR MIXING ................................................................................... 12
6.5. BRICK LAYING ....................................................................................... 12
6.6. FORMWORK FOR STIFFENER ............................................................. 15
6.7. CONCRETE CASTING FOR TIE BEAM & STIFFENER......................... 16
7. SAFETY CONTROL .................................................................................. 16
7.1. PPE ......................................................................................................... 16
7.2. BARRICADES & SIGNS ......................................................................... 16
1 Site Manager
4 General Workers
5.1.1. Bricks
All bricks are must to be selected clay brick follow the contract BQ, and to be hard,
sound, well burnt, even and uniform in shape, free from cracks and other defects and
equal to samples deposited with and approved by the supervisor.
5.1.2. Cement & Sand
Cement or equivalent cement shall follow the certain standard, and shall comply with
the requirements of supervisor. Sand shall be the naturally occurring fresh water
sand. Cement and sand either will be stored well. Brand of cement use as per
architect approval cement submission.
5.1.3. Mortar
Materials for mortar are to be measured in properly made and accurate measuring
boxes and to be tested random by supervisor appointing.
Mixing of mortars will normally be carried out with machine driven roller pan mixers of
approved type and size. In exceptional circumstances and where small quantities are
shall be mixed by hand. Mortar that is unused within 2 - 3 hours of mixing shall be
removed from the site.
5.2. EQUIPMENT
Scaffolding platforms, Electric drills, Trowels & Hand tools, Mixer machine, Wheel
barrow, Masonry saw, Masonry square, Long Aluminium straight edge, Spirit level,
Water level, Measuring tape, Plumb bob, Laser level meter.
FORMWROK
FOR TIE CONCRETE
BRICK WALL LAYING CURING
BEAM & CASTING
STIFFINER
Drop plumb bob from concrete ceilling to base slab to determine vertical & horizontal
direction of brick wall to control verticality during build up brick laying.
6.2. SURFACE PREPARATION
Cleaning for RC slab surface shall be carried out before brick wall laying. The wall
base shall be free of dust and contaminant.
When the distance between two RC columns or walls is more than 4.0m, in which
brick wall is built as partition, stiffener is needed at every 4.0m. Stiffener width should
be same to wall thickness. Reinforcement of stiffener for brick wall 100 & 200
thickness is shown as below. The main reinforcement of the stiffener should be
planted into the RC beam/slab by 100mm in depth to ensure sufficient bonding
strength. Rebar for stiffener refer table for half & one brick wall.
Stiffener for 200mm brick wall Alternative reinf. for 100mm brick
If the brick wall height is higher than 4.5m, tie beam should be set to enhance the
integrity of brick-wall, and the position shall be in middle of height or at every 4.5m
from the bottom of brick wall and the main bars shall be planted in RC structure with
100mm anchorage length to ensure sufficient bonding strength.
Detail for tie beam 200mm brick Alternative reinf. for 100mm brick
Lintel beam for door is installed when laying brick wall up to above door frame anchor
to brick wall Min. 150mm (beside horizon frame).
Option 1: RC lintel beam (Concrete)
The detail for RC lintel beam follow structural drawing is show as follow below:
Masonry joint of any two layers of brick shall be staggered and pavement length of
mortar no more than 500mm. Mortar joint shall be filled densely and bound tightly.
Bricks shall be watered 1 day in advance, with moisture content of 10-15%. Dry
bricks cannot be used.
Bricks shall be well wetted before being laid and if the course last laid has become
dried, it is to be wetted before bedding fresh bricks upon it. The walls are to be
carried up evenly in truly horizontal courses so that no one portion is raised more
than 1.00m above another at any one time. Division walls and partitions are to be
properly bonded to main walls. All propounds are to be strictly true and square and
the whole properly bonded together. No closes or bats are to be used except where
necessary for bonding purposes. One brick thick and over shall be built in bond
unless otherwise specified. With one brick thick 200-250 (included plaster) used
double layer (100+100+10mm spacing) should be follow 3 options belows:
The seams of laid bricks shall be straight and smooth. The thick of seam shall be with
minimum 6mm and maximum 10mm. The horizontal seam shall be filled at least 80%
of the full depth. The vertical seam shall be continuously without any gaps. It is not
permitted to water the dry cement after spreading. Test laying segment shall be
made before formally building. The mortar shall plaster on bricks before placing to
form the vertical seam.
Half brick and one brick on edge walling shall be built in stretcher bond. The corner
and connection of brick wall shall be laid at the same time , otherwise, the steps of
the length not less than the height shall be left for later connection.