The Rise Residence & Resort Project

PROJECT TITLE

FASA 1A:

I) KONDOTEL B 43 TINGKAT = 629 UNIT

II) KONDOTEL C 41 TINGKAT = 529 UNIT

III) SHOP (RUANG PERIAGAAN) 1 1/2 TINGKAT

IV) PPU 2 TINGKAT = 1 UNIT

V) SSU 2 TINGKAT = 1 UNIT

UNTUK: TETUAN YEASHIN CONSTRUCTION SDN.BHD

METHOD STATEMENT FOR BRICK WALL

Revised : 00 (12-May-2020)

PREPARED BY: CHECKED & APPROVED BY:

China Construction Engineering (S.E.A) Malaysia Sdn. Bhd.


The Rise Residence & Resort Project

CONTENTS

1. PURPOSE ................................................................................................... 3
2. SCOPE OF WORK ...................................................................................... 3
3. REFERENCES SPECIFICATION ................................................................ 3
4. MANPOWER ............................................................................................... 3
5. MATERIAL & EQUIPMENT......................................................................... 4
5.1. MATERIAL ................................................................................................ 4
5.1.1. Bricks ..................................................................................................... 4
5.1.2. Cement & Sand ...................................................................................... 4
5.1.3. Mortar..................................................................................................... 4
5.2. EQUIPMENT............................................................................................. 4
6. WORK FLOW CHART................................................................................. 5
6.1. SETTING OUT .......................................................................................... 5
6.2. SURFACE PREPARATION ...................................................................... 5
6.3. PANTING REBAR, STIFFENER, TIE BEAM & LINTEL BEAM ................. 6
6.3.1. Planting Bar ........................................................................................... 6
6.3.2. Stiffener Column .................................................................................... 8
6.3.3. Tie Beam................................................................................................ 8
6.3.4. Lintel Beam .......................................................................................... 10
6.4. MORTAR MIXING ................................................................................... 12
6.5. BRICK LAYING ....................................................................................... 12
6.6. FORMWORK FOR STIFFENER ............................................................. 15
6.7. CONCRETE CASTING FOR TIE BEAM & STIFFENER......................... 16
7. SAFETY CONTROL .................................................................................. 16
7.1. PPE ......................................................................................................... 16
7.2. BARRICADES & SIGNS ......................................................................... 16

China Construction Engineering (S.E.A) Malaysia Sdn. Bhd.


The Rise Residence & Resort Project

METHOD STATEMENT FOR BRICK WALL


1. PURPOSE
The purpose of this method statement is to carry out the masonry works with clay
brick in compliance with all the required specifications, standards, workmanship and
proper construction procedures.
To outline quality plan or inspection & test required during project implementation.
To carry out safe working environment and comply to the safety requirements.
2. SCOPE OF WORK
This document covers the work for the brick wall:
 Brick wall laying and tie bar to RC structure
 Stiffener, tie beam and lintel beam
3. REFERENCES SPECIFICATION
BS 8000: 1990 Part 2: BS For Workmanship on Building Sites
Part 2: Code Practice For Concrete Work
Part 2.2: Site Work With In-situ & Pre-cast Concrete
BS 8000 3:2001 Part 3: Code Practice For Masonry
BS 5628:2005: Code Practice For the Use Masonry
4. MANPOWER

Item Manpower Descriptions

1 Site Manager

2 Project Engineer / Supervisor / Surveyor/QC Engineer

3 Skill Workers (Brick Worker, Setting Out, Concreter)

4 General Workers

China Construction Engineering (S.E.A) Malaysia Sdn. Bhd.


3
The Rise Residence & Resort Project

5. MATERIAL & EQUIPMENT


5.1. MATERIAL
Item Material Descriptions
1 Clay Bricks
2 Cement Mortar, Exmet
3 Reinforcement R6, T12, 16 & T20, Ties Plate

5.1.1. Bricks

All bricks are must to be selected clay brick follow the contract BQ, and to be hard,
sound, well burnt, even and uniform in shape, free from cracks and other defects and
equal to samples deposited with and approved by the supervisor.
5.1.2. Cement & Sand

Cement or equivalent cement shall follow the certain standard, and shall comply with
the requirements of supervisor. Sand shall be the naturally occurring fresh water
sand. Cement and sand either will be stored well. Brand of cement use as per
architect approval cement submission.
5.1.3. Mortar

Materials for mortar are to be measured in properly made and accurate measuring
boxes and to be tested random by supervisor appointing.
Mixing of mortars will normally be carried out with machine driven roller pan mixers of
approved type and size. In exceptional circumstances and where small quantities are
shall be mixed by hand. Mortar that is unused within 2 - 3 hours of mixing shall be
removed from the site.
5.2. EQUIPMENT
Scaffolding platforms, Electric drills, Trowels & Hand tools, Mixer machine, Wheel
barrow, Masonry saw, Masonry square, Long Aluminium straight edge, Spirit level,
Water level, Measuring tape, Plumb bob, Laser level meter.

China Construction Engineering (S.E.A) Malaysia Sdn. Bhd.


4
The Rise Residence & Resort Project

6. WORK FLOW CHART

SURFACE PLANTING TIE BAR TO RC


SETTING OUT PREPARATION STRUCTRUE & PLANTING STARTER
& BRICK PRE-WET BAR FOR TIE BEAM&STIFFINER

FORMWROK
FOR TIE CONCRETE
BRICK WALL LAYING CURING
BEAM & CASTING
STIFFINER

6.1. SETTING OUT


Survey the center line of brick wall according to the architectural construction
drawings and should be offset by installer.
Checking with door frame location was installed.
Set out the axes line, thickness, elevation level, embedded parts location and
transferred to the structural columns or beams and slabs with visible marks.

Drop plumb bob from concrete ceilling to base slab to determine vertical & horizontal
direction of brick wall to control verticality during build up brick laying.
6.2. SURFACE PREPARATION
Cleaning for RC slab surface shall be carried out before brick wall laying. The wall
base shall be free of dust and contaminant.

China Construction Engineering (S.E.A) Malaysia Sdn. Bhd.


5
The Rise Residence & Resort Project

6.3. PANTING REBAR, STIFFENER, TIE BEAM & LINTEL BEAM


6.3.1. Planting Bar

Option 1: Planter bar to RC structure


The tie bar/dowel bar should be set to bond the brick wall with RC structure. For one
layer wall, single tie bar D6@ 600 should be planted on the RC structure. For double
wall, a couple of tie bars D6@ 600 should be planted on the RC structure.
The planting glue use Greco EP Putty or Hilti 500, the planting depth is Min. 12 D
(D is the diameter of the tie bar). And the tie bar should anchor into the brick wall by
Min. 500mm in length. The tie bar should also be arranged between the stiffener and
brick wall but length anchor can be shorter 500mm (Min .200mm)

Tie bar to RC column(for reference only)

China Construction Engineering (S.E.A) Malaysia Sdn. Bhd.


6
The Rise Residence & Resort Project

Method to plant rebar

Option 2: Use steel sheet plate (Ties plate)


Use steel ties plate/sheet plate thickness 0.12mm, width 12.7mm fixed to RC
structure by steel screw space 600mm.

Steel sheet plate tie (for reference only)

China Construction Engineering (S.E.A) Malaysia Sdn. Bhd.


7
The Rise Residence & Resort Project

6.3.2. Stiffener Column

When the distance between two RC columns or walls is more than 4.0m, in which
brick wall is built as partition, stiffener is needed at every 4.0m. Stiffener width should
be same to wall thickness. Reinforcement of stiffener for brick wall 100 & 200
thickness is shown as below. The main reinforcement of the stiffener should be
planted into the RC beam/slab by 100mm in depth to ensure sufficient bonding
strength. Rebar for stiffener refer table for half & one brick wall.

Stiffener for 200mm brick wall Alternative reinf. for 100mm brick

6.3.3. Tie Beam

If the brick wall height is higher than 4.5m, tie beam should be set to enhance the
integrity of brick-wall, and the position shall be in middle of height or at every 4.5m
from the bottom of brick wall and the main bars shall be planted in RC structure with
100mm anchorage length to ensure sufficient bonding strength.

Detail for tie beam 200mm brick Alternative reinf. for 100mm brick

China Construction Engineering (S.E.A) Malaysia Sdn. Bhd.


8
The Rise Residence & Resort Project

Table detail reinforcement of stiffener & tie beam

China Construction Engineering (S.E.A) Malaysia Sdn. Bhd.


9
The Rise Residence & Resort Project

6.3.4. Lintel Beam

Lintel beam for door is installed when laying brick wall up to above door frame anchor
to brick wall Min. 150mm (beside horizon frame).
Option 1: RC lintel beam (Concrete)
The detail for RC lintel beam follow structural drawing is show as follow below:

Detail for RC lintel beam


The concrete grade for stiffener, tie beam and lintel beam should be G30. Can be mix
on site comply specification during brick works without cube test.

China Construction Engineering (S.E.A) Malaysia Sdn. Bhd.


10
The Rise Residence & Resort Project

Option 2: Steel lintel beam


The detail for RC lintel beam by supplier is show as follow below:

Steel lintel beam (For referfence only)

Lintel bracket connection (If any)

China Construction Engineering (S.E.A) Malaysia Sdn. Bhd.


11
The Rise Residence & Resort Project

6.4. MORTAR MIXING


Mortar shall be mixed in accordance with mix proportion (cement/sand = 1:6). Fully
mix the cement and sand, and then add water and mix them for no less than 2
minutes.
Material preparation for mortar mixing shall be arranged in batches. Constant
material feeding is not allowed. Mortar for masonry shall be mixed well with proper
density.
Mortar shall be used promptly within 2-3 hours after mixing.
6.5. BRICK LAYING
The dimension, strength, and the types of the bricks shall comply with the design and
specifications. The bricks shall be wetted before using.
Brick wall laying shall be carried out with one side plumb line, in accordance with
elevation control line and verticality control line.
The exmet (wire mesh between 2 layers of brick) shall be install with space 4 layers
bricks put 1 layer exmet and the first exmet put at second layer brick from surface
slab (floor level).
Every bottom layer of brick need to put Damp Proof Course (DPC) for horizontal
damp proof course.

Masonry joint of any two layers of brick shall be staggered and pavement length of
mortar no more than 500mm. Mortar joint shall be filled densely and bound tightly.
Bricks shall be watered 1 day in advance, with moisture content of 10-15%. Dry
bricks cannot be used.

China Construction Engineering (S.E.A) Malaysia Sdn. Bhd.


12
The Rise Residence & Resort Project

Bricks shall be well wetted before being laid and if the course last laid has become
dried, it is to be wetted before bedding fresh bricks upon it. The walls are to be
carried up evenly in truly horizontal courses so that no one portion is raised more
than 1.00m above another at any one time. Division walls and partitions are to be
properly bonded to main walls. All propounds are to be strictly true and square and
the whole properly bonded together. No closes or bats are to be used except where
necessary for bonding purposes. One brick thick and over shall be built in bond
unless otherwise specified. With one brick thick 200-250 (included plaster) used
double layer (100+100+10mm spacing) should be follow 3 options belows:

Connection between 2 layer brick wall (double)

The seams of laid bricks shall be straight and smooth. The thick of seam shall be with
minimum 6mm and maximum 10mm. The horizontal seam shall be filled at least 80%
of the full depth. The vertical seam shall be continuously without any gaps. It is not
permitted to water the dry cement after spreading. Test laying segment shall be
made before formally building. The mortar shall plaster on bricks before placing to
form the vertical seam.

The seams of laid bricks(for reference only)

China Construction Engineering (S.E.A) Malaysia Sdn. Bhd.


13
The Rise Residence & Resort Project

Half brick and one brick on edge walling shall be built in stretcher bond. The corner
and connection of brick wall shall be laid at the same time , otherwise, the steps of
the length not less than the height shall be left for later connection.

Juntion at brick wall corner


The space of 150mm between wall and beam bottom shall be reserved, and made up
when the wall body becomes stable and firm. The final layer of brick under the beam
shall be slanted firmly, with mortar fully and densely filled. See diagram below:

China Construction Engineering (S.E.A) Malaysia Sdn. Bhd.


14
The Rise Residence & Resort Project

Detail of masonry under beam

6.6. FORMWORK FOR STIFFENER


Check rebar and dimension before install formwork for stiffener
The formwork for stiffener should be tightened by tie rod and it should be wet by
water before casting concrete.

Formwork for stiffener(For reference only)

China Construction Engineering (S.E.A) Malaysia Sdn. Bhd.


15
The Rise Residence & Resort Project

6.7. CONCRETE CASTING FOR TIE BEAM & STIFFENER


The vibration shall be carried out for the casting of stiffener so as to ensure the
density of concrete and avoid honeycombs.
7. SAFETY CONTROL
Prior to commencement of the works, Main contractor will ensure that technical
specifications of each product were carefully carried out to avoid any problem at site.
7.1. PPE
All required PPE such as helmet and safety shoes shall be provided and maintained
for all workers doing the repair works.
For the purpose of protecting workers eye injury and flying particles, eye protector
such as safety glass, face shield and goggles shall be provided engaged in the
related work.
Mask and rubber gloves are required to workers involved in mixing and application as
per MSDS requirements.
7.2. BARRICADES & SIGNS
Safety and warning signboards in dual language shall be installed.
Barricades shall be erected to isolate the working area with suitable and sufficient
access.
Materials required for this work shall be properly stored and identified at areas
designated for this purpose.
All scaffolding shall be inspected prior to use.