ID Task Name Duration Start Finish 17 Nov '19 24 Nov '19 1 Dec '19

W T F S S M T W T F S S M T W T F S S M T W T F S
1 FWP P671B 21 days Thu Fri 6/12/19
OVERHAUL 14/11/19
2 V.I on FWP by 1 day Thu Thu
client 14/11/19 14/11/19
3 Clearance check 1 day Thu Fri 15/11/19
on impeller and 14/11/19
bowl

4 Shaft and Bearing 3 days Fri 15/11/19 Sun


Dismantle 17/11/19
5 Vert. Gear Shaft 0.5 days Sat 16/11/19 Sat 16/11/19
R.O
6 Penetrant Test on 0.5 days Sat 16/11/19 Sat 16/11/19
Gears
7 Wearing Ring 5 days Mon Fri 22/11/19
Impeller 18/11/19
Fabrication

8 Wearing Ring 1 day Sat 23/11/19 Sat 23/11/19


Installation
9 Gearbox Shaft 6 days Sun Fri 29/11/19
Fabrication 24/11/19
10 Shaft Balancing 2 days Wed 27/11/19Thu 28/11/19
11 Assembly of Pump 6 days Fri 29/11/19 Fri 6/12/19

12

13 *Demob to
PCLDPE

Task Inactive Task Manual Summary Rollup External Milestone

Prepared By: M.Shalihan Split Inactive Milestone Manual Summary Deadline


Serba Dinamik Sdn Bhd Milestone Inactive Summary Start-only Progress
Review by: Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks