Sie sind auf Seite 1von 70

Republic of the Philippines

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


PANGASINAN 3RD
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE I
Tumana, Rosales, Pangasinan

INDIVIDUAL PROJECT PROFILE


1 . Name of Project : CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL
BUILDING
2 . Location of Contract : Esperanza Integrated School, Sison, Pangasinan
3 . Brief Description of the Project : Construction of Two (2) Storey Four (4) Classroom School Building
with Permits and Clearances Cost, Demolition Cost; 9.50m x 23.00m; Floor tiles at 3 CL
Window and Corridor at 2/F Grilles ; Total Floor Area - 437.00m²; 1.00 m Embankment )
4 . Approved Budget for the Contract : Php 9,836,063.68
5 . Source of Fund : BEFF CY 2017
6 . No. of Calendar Days to Complete : 160 CD
7 . Expected Date to Commence Work :

Item of Work Description Quantity Unit


PART A FACILITIES FOR THE ENGINEER
A. 1. 1. Offices and Laboratory for the Engineer
A.1.1(8) Provision of Field Office for the Engineer (Rental Basis) 5.33 month
PART B OTHER GENERAL REQUIREMENTS
B.3 Permits and Clearances 1.00 L.S.
B.5 Project Billboard/Signboard 3.00 each
B.7 Occupational Safety and Health Program 5.33 month
B.9 Mobilization/Demobilization 1.00 L.S.
PART III CIVIL, MECHANICAL, ELECTRICAL AND
PART A EARTHWORKS
801(1) Removal of Structures and Obstructions 1.00 L.S.
803(1)a Structure Excavation (Common Soil) 196.98 m³
804(1)a Embankment from Structure Excavation 105.37 m³
804(1)b Embankment from Borrow 269.15 m³
804(4) Gravel Fill 33.92 m³
PART B PLAIN AND REINFORCED CONCRETE WORKS
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days) 153.74 m³
902(1)a1 Reinforcing Steel (Deformed, Grade 40) 28,343.22 kgs.
903(2) Formworks and Falseworks 960.52 m²
PART C FINISHINGS AND OTHER CIVIL WORKS
C.1 Termite Control Works
1000(1) Soil Poisoning 115.60 lit
C.2 Masonry Works
1046(2)a1 CHB Non-Load Bearing (including Reinforcing Steel; 100mm) 129.91 m²
1046(2)a2 CHB Non-Load Bearing (including Reinforcing Steel; 150mm) 450.38 m²
C.3 Fabricated Materials
1004(2)a Finishing Hardware (Locksets) 20.00 set
1004(2)g Finishing Hardware (Hinges) 80.00 set
1005(1) Residential Casement (Steel Window) 48.96 m²
1005(5) Grille (Window and Corridor at 2/F) 76.30
1010(4) Wooden Doors 1.00 L.S.
C.4 Finishing Works
1003(1)a1 Ceiling (4.5mm Fiber Cement Board on Metal Frame with Air Vent) 237.86 m²
1003(17) Carpentry and Joinery Works (Blackboard) 1.00 L.S.
1018(1) Glazed Tiles and Trims 71.55 m²
1018(2) Unglazed Tiles 209.05 m²
1021(1)c Plain Cement Finish with Floor Hardener 424.17 m²
1027(1) Plain Cement Plaster Finish 1,833.62 m²
1038(1) Reflective Insulation 315.48 m²
1053(3)a1 38mm dia. G.I.Pipe Railing 33.00 m
1053(3)a2 50mm dia. G.I.Pipe Handrail Fully Welded on Vertical Railing on 19mm bar
73.42
Stiffener m
C.5 Painting Works
1032(1)a Painting Works (Masonry/Concrete) 1,997.26 m²
1032(1)b Painting Works (Wood) 104.49 m²
1032(1)c Painting Works (Steel) 50.14 m²
C.6 Roof Framing and Roofing Works
1003(11)a1 Fiber Cement Fascia Board 47.80 m
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5mm thk. 315.48 m²
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll) 23.90 m
1013(2)b Fabricated Metal Roofing Accessory (Flashing) 26.21 m
1013(2)c Fabricated Metal Roofing Accessory (Gutter) 47.80 m
1047(2)a Structural Steel (Trusses) 2,271.38 kg
1047(2)b Structural Steel (Purlins) 3,687.15 kg
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
PANGASINAN 3RD
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE I
Tumana, Rosales, Pangasinan

INDIVIDUAL PROJECT PROFILE


1 . Name of Project : CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL
BUILDING
2 . Location of Contract : Esperanza Integrated School, Sison, Pangasinan
3 . Brief Description of the Project : Construction of Two (2) Storey Four (4) Classroom School Building
with Permits and Clearances Cost, Demolition Cost; 9.50m x 23.00m; Floor tiles at 3 CL
Window and Corridor at 2/F Grilles ; Total Floor Area - 437.00m²; 1.00 m Embankment )
4 . Approved Budget for the Contract : Php 9,836,063.68
5 . Source of Fund : BEFF CY 2017
6 . No. of Calendar Days to Complete : 160 CD
7 . Expected Date to Commence Work :

Item of Work Description Quantity Unit


1047(6) Metal Structure Accessories (Steel Plates) 277.47 kg
1047(7)b Metal Structure Accessories (Sagrods) 101.34 kg
1047(4) Metal Structure Accessories (Crossbracing) 214.42 kg
1047(3)c Metal Structure Accessories (Turnbuckle) 18.00 pc
1047(1) Structural Steel (Fire Escape) 1.00 L.S.
C.7 Sanitary/Plumbing Works
1001(6)a Catch Basin 12.00 each
1001(8) Sewer Line Works 1.00 L.S.
1001(9) Storm Drainage and Downspout 1.00 L.S.
1002(8) Plumbing Fixtures 1.00 L.S.
1002(28) Cold Water Lines 1.00 L.S.
PART D ELECTRICAL
1100(30) Conduits, Boxes and Fittings 1.00 L.S.
1101(42) Wires and Wiring Devices 1.00 L.S.
1102(27) Panel Load Center, Switch Gear and Panelboards 1.00 L.S.
1103(1) Lighting Fixtures 1.00 L.S.
PART E MECHANICAL WORKS
1202(1) Automatic Water Sprinkler System 1.00 L.S.
1208(1) Fire Alarm System 1.00 L.S.

8 . Minimum Equipment Requirement : Assorted Minor Tools,Backhoe(0.80m³),Dump Truck(12yd³),Plate Compactor(5hp),


Concrete Vibrator,Pumpcrete,One Bagger Mixer,Bar Cutter Single Phase,Bar Bender,
H-Frame 1.7 m x 1.2m set,Shoring Jack 3.8 m full extension,Adjustable U-head Jack,
Adjustable Base Jack,1-1/2"GI Pipex6.0m,1-1/2"GI Pipex3.0m,1-1/2"GI Pipex4.0m,
1-1/2" GI Pipe x 1.0 m,Tie Rodx0.60m,Round Wing Nut,Welding Machine,Cutting
Outfit,

9 . Authorized DPWH Representative : To accompany contractors for site inspection


MARBEN E. NICOLAS

Submitted by:

JONATHAN B. RAMOS
Engineer II
Chief, Planning and Design Section
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
PANGASINAN 3RD
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE I
Tumana, Rosales, Pangasinan
D.O. No. 05 , Series of 2016
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 160 CD
TOTAL
QUANTIT ESTIMATED MARK-UPS in PERCENT TOTAL MARK-UP
ITEM NO. DESCRIPTION UNIT VAT INDIRECT TOTAL COST UNIT COST
Y DIRECT COST OCM PROFIT % VALUE
COST
(9) (10) (11) (12) (13)
(1) (2) (3) (4) (5) (6) (7) (8)
(5) x (8) 5%[(5)+(9)] (9)+(10) (5)+(11) (12)/(3)
PART A FACILITIES FOR THE ENGINEER
A. 1. 1. Offices and Laboratory for the Engineer

A.1.1(8) Provision of Field Office for the Engineer (Rental Basis) 5.33 month 138,666.67 0.00% 8.00% 8.00% 11,093.33 7,488.00 18,581.33 157,248.00 29,484.00

TOTAL OF PART A 157,248.00


PART B OTHER GENERAL REQUIREMENTS
B.3 Permits and Clearances 1.00 L.S. 97,635.46 0.00% 0.00% 0.00% - 4,881.77 4,881.77 102,517.24 102,517.24
B.5 Project Billboard/Signboard 3.00 each 12,463.86 12.00% 8.00% 20.00% 2,492.77 747.83 3,240.60 15,704.47 5,234.82
B.7 Occupational Safety and Health Program 5.33 month 123,641.33 0.00% 8.00% 8.00% 9,891.31 6,676.63 16,567.94 140,209.27 26,289.24
B.9 Mobilization/Demobilization 1.00 L.S. 55,828.36 0.00% 0.00% 0.00% - 2,791.42 2,791.42 58,619.77 58,619.77
TOTAL OF PART B 317,050.75
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
801(1) Removal of Structures and Obstructions 1.00 L.S. 82,851.91 0.00% 0.00% 0.00% - 4,142.60 4,142.60 86,994.50 86,994.50
803(1)a Structure Excavation (Common Soil) 196.98 m³ 45,013.67 12.00% 8.00% 20.00% 9,002.73 2,700.82 11,703.55 56,717.23 287.93
804(1)a Embankment from Structure Excavation 105.37 m³ 15,402.65 12.00% 8.00% 20.00% 3,080.53 924.16 4,004.69 19,407.34 184.18
804(1)b Embankment from Borrow 269.15 m³ 130,181.62 12.00% 8.00% 20.00% 26,036.32 7,810.90 33,847.22 164,028.84 609.43
804(4) Gravel Fill 33.92 m³ 29,588.16 12.00% 8.00% 20.00% 5,917.63 1,775.29 7,692.92 37,281.08 1,099.09
TOTAL OF PART A 364,429.00
PART B PLAIN AND REINFORCED CONCRETE WORKS
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days) 153.74 m³ 623,046.66 12.00% 8.00% 20.00% 124,609.33 37,382.80 161,992.13 785,038.79 5,106.13
902(1)a1 Reinforcing Steel (Deformed, Grade 40) 28,343.22 kgs. 1,345,236.10 12.00% 8.00% 20.00% 269,047.22 80,714.17 349,761.39 1,694,997.48 59.80
903(2) Formworks and Falseworks 960.52 m² 401,542.06 12.00% 8.00% 20.00% 80,308.41 24,092.52 104,400.94 505,943.00 526.74
TOTAL OF PART B 2,985,979.27
PART C FINISHINGS AND OTHER CIVIL WORKS
C.1 Termite Control Works
1000(1) Soil Poisoning 115.60 lit 42,543.73 12.00% 8.00% 20.00% 8,508.75 2,552.62 11,061.37 53,605.10 463.71
Sub-Total C.1 53,605.10
C.2 Masonry Works
CHB Non-Load Bearing (including Reinforcing Steel;
1046(2)a1 129.91 m² 71,290.63 12.00% 8.00% 20.00% 14,258.13 4,277.44 18,535.56 89,826.19 691.45
100mm)
CHB Non-Load Bearing (including Reinforcing Steel;
1046(2)a2 450.38 m² 378,378.12 12.00% 8.00% 20.00% 75,675.62 22,702.69 98,378.31 476,756.43 1,058.56
150mm)
Sub-Total C.2 566,582.62
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
PANGASINAN 3RD
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE I
Tumana, Rosales, Pangasinan
D.O. No. 05 , Series of 2016
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 160 CD
TOTAL
QUANTIT ESTIMATED MARK-UPS in PERCENT TOTAL MARK-UP
ITEM NO. DESCRIPTION UNIT VAT INDIRECT TOTAL COST UNIT COST
Y DIRECT COST OCM PROFIT % VALUE
COST
(9) (10) (11) (12) (13)
(1) (2) (3) (4) (5) (6) (7) (8)
(5) x (8) 5%[(5)+(9)] (9)+(10) (5)+(11) (12)/(3)
C.3 Fabricated Materials
1004(2)a Finishing Hardware (Locksets) 20.00 set 13,000.00 12.00% 8.00% 20.00% 2,600.00 780.00 3,380.00 16,380.00 819.00
1004(2)g Finishing Hardware (Hinges) 80.00 set 5,200.00 12.00% 8.00% 20.00% 1,040.00 312.00 1,352.00 6,552.00 81.90
1005(1) Residential Casement (Steel Window) 48.96 m² 166,548.86 12.00% 8.00% 20.00% 33,309.77 9,992.93 43,302.70 209,851.57 4,286.18
1009(1)a Jalousie Window 24.05 m² 31,103.51 12.00% 8.00% 20.00% 6,220.70 1,866.21 8,086.91 39,190.42 1,629.54
1005(5) Grille (Window and Corridor at 2/F) 76.30 m² 73,206.97 12.00% 8.00% 20.00% 14,641.39 4,392.42 19,033.81 92,240.78 1,208.92
1010(4) Wooden Doors 1.00 L.S. 174,155.66 12.00% 8.00% 20.00% 34,831.13 10,449.34 45,280.47 219,436.13 219,436.13
Sub-Total C.3 583,650.90
C.4 Finishing Works
1003(1)a1 Ceiling (4.5mm Fiber Cement Board on Metal Frame with Air237.86
Vent) m² 226,638.83 12.00% 8.00% 20.00% 45,327.77 13,598.33 58,926.10 285,564.92 1,200.56
1003(17) Carpentry and Joinery Works (Blackboard) 1.00 L.S. 17,071.61 12.00% 8.00% 20.00% 3,414.32 1,024.30 4,438.62 21,510.23 21,510.23
1018(1) Glazed Tiles and Trims 71.55 m² 121,144.69 12.00% 8.00% 20.00% 24,228.94 7,268.68 31,497.62 152,642.31 2,133.37
1018(2) Unglazed Tiles 209.05 m² 331,938.79 12.00% 8.00% 20.00% 66,387.76 19,916.33 86,304.09 418,242.87 2,000.68
1021(1)c Plain Cement Finish with Floor Hardener 424.17 m² 116,827.82 12.00% 8.00% 20.00% 23,365.56 7,009.67 30,375.23 147,203.06 347.04
1027(1) Plain Cement Plaster Finish 1,833.62 m² 325,223.52 12.00% 8.00% 20.00% 65,044.70 19,513.41 84,558.11 409,781.63 223.48
1038(1) Reflective Insulation 315.48 m² 67,241.47 12.00% 8.00% 20.00% 13,448.29 4,034.49 17,482.78 84,724.25 268.56
1053(3)a1 38mm dia. G.I.Pipe Railing 33.00 m 16,474.15 12.00% 8.00% 20.00% 3,294.83 988.45 4,283.28 20,757.43 629.01
1053(3)a2 50mm dia. G.I.Pipe Handrail Fully Welded on Vertical Railing73.42
on 19mm barmStiffener 163,686.16 12.00% 8.00% 20.00% 32,737.23 9,821.17 42,558.40 206,244.56 2,809.11
Sub-Total C.4 1,746,671.27
C.5 Painting Works
1032(1)a Painting Works (Masonry/Concrete) 1,997.26 m² 595,405.46 12.00% 8.00% 20.00% 119,081.09 35,724.33 154,805.42 750,210.88 375.62
1032(1)b Painting Works (Wood) 104.49 m² 28,999.42 12.00% 8.00% 20.00% 5,799.88 1,739.96 7,539.85 36,539.26 349.69
1032(1)c Painting Works (Steel) 50.14 m² 15,991.11 12.00% 8.00% 20.00% 3,198.22 959.47 4,157.69 20,148.80 401.85
Sub-Total C.5 806,898.95
C.6 Roof Framing and Roofing Works
1003(11)a1 Fiber Cement Fascia Board 47.80 m 9,910.85 12.00% 8.00% 20.00% 1,982.17 594.65 2,576.82 12,487.67 261.25
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5mm thk. 315.48 m² 139,248.12 12.00% 8.00% 20.00% 27,849.62 8,354.89 36,204.51 175,452.63 556.15
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll) 23.90 m 5,438.16 12.00% 8.00% 20.00% 1,087.63 326.29 1,413.92 6,852.09 286.70
1013(2)b Fabricated Metal Roofing Accessory (Flashing) 26.21 m 5,963.78 12.00% 8.00% 20.00% 1,192.76 357.83 1,550.58 7,514.36 286.70
1013(2)c Fabricated Metal Roofing Accessory (Gutter) 47.80 m 16,029.04 12.00% 8.00% 20.00% 3,205.81 961.74 4,167.55 20,196.59 422.52
1047(2)a Structural Steel (Trusses) 2,271.38 kg 173,835.90 12.00% 8.00% 20.00% 34,767.18 10,430.15 45,197.33 219,033.23 96.43
1047(2)b Structural Steel (Purlins) 3,687.15 kg 266,355.37 12.00% 8.00% 20.00% 53,271.07 15,981.32 69,252.40 335,607.77 91.02
1047(6) Metal Structure Accessories (Steel Plates) 277.47 kg 19,125.57 12.00% 8.00% 20.00% 3,825.11 1,147.53 4,972.65 24,098.22 86.85
1047(7)b Metal Structure Accessories (Sagrods) 101.34 kg 4,584.66 12.00% 8.00% 20.00% 916.93 275.08 1,192.01 5,776.68 57.00
1047(4) Metal Structure Accessories (Crossbracing) 214.42 kg 11,301.20 12.00% 8.00% 20.00% 2,260.24 678.07 2,938.31 14,239.52 66.41
1047(3)c Metal Structure Accessories (Turnbuckle) 18.00 pc 3,775.26 12.00% 8.00% 20.00% 755.05 226.52 981.57 4,756.83 264.27
1047(1) Structural Steel (Fire Escape) 1.00 L.S. 102,789.13 12.00% 8.00% 20.00% 20,557.83 6,167.35 26,725.17 129,514.30 129,514.30
Sub-Total C.6 955,529.87
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
PANGASINAN 3RD
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE I
Tumana, Rosales, Pangasinan
D.O. No. 05 , Series of 2016
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 160 CD
TOTAL
QUANTIT ESTIMATED MARK-UPS in PERCENT TOTAL MARK-UP
ITEM NO. DESCRIPTION UNIT VAT INDIRECT TOTAL COST UNIT COST
Y DIRECT COST OCM PROFIT % VALUE
COST
(9) (10) (11) (12) (13)
(1) (2) (3) (4) (5) (6) (7) (8)
(5) x (8) 5%[(5)+(9)] (9)+(10) (5)+(11) (12)/(3)
C.7 Sanitary/Plumbing Works
1001(6)a Catch Basin 12.00 each 10,620.50 12.00% 8.00% 20.00% 2,124.10 637.23 2,761.33 13,381.84 1,115.15
1001(8) Sewer Line Works 1.00 L.S. 23,398.44 12.00% 8.00% 20.00% 4,679.69 1,403.91 6,083.59 29,482.03 29,482.03
1001(9) Storm Drainage and Downspout 1.00 L.S. 60,638.99 12.00% 8.00% 20.00% 12,127.80 3,638.34 15,766.14 76,405.12 76,405.12
1002(8) Plumbing Fixtures 1.00 L.S. 282,689.16 12.00% 8.00% 20.00% 56,537.83 16,961.35 73,499.18 356,188.34 356,188.34
1002(28) Cold Water Lines 1.00 L.S. 4,385.07 12.00% 8.00% 20.00% 877.01 263.10 1,140.12 5,525.18 5,525.18
Sub-Total C.7 480,982.51
TOTAL OF PART C 5,193,921.21
PART D ELECTRICAL
1100(30) Conduits, Boxes and Fittings 1.00 L.S. 36,818.79 12.00% 8.00% 20.00% 7,363.76 2,209.13 9,572.88 46,391.67 46,391.67
1101(42) Wires and Wiring Devices 1.00 L.S. 64,679.66 12.00% 8.00% 20.00% 12,935.93 3,880.78 16,816.71 81,496.37 81,496.37
1102(27) Panel Load Center, Switch Gear and Panelboards 1.00 L.S. 25,594.39 12.00% 8.00% 20.00% 5,118.88 1,535.66 6,654.54 32,248.93 32,248.93
1103(1) Lighting Fixtures 1.00 L.S. 46,662.37 12.00% 8.00% 20.00% 9,332.47 2,799.74 12,132.22 58,794.59 58,794.59
TOTAL OF PART D 218,931.56
PART E MECHANICAL WORKS
1202(1) Automatic Water Sprinkler System 1.00 L.S. 466,684.52 12.00% 8.00% 20.00% 93,336.90 28,001.07 121,337.98 588,022.50 588,022.50
1208(1) Fire Alarm System 1.00 L.S. 8,318.56 12.00% 8.00% 20.00% 1,663.71 499.11 2,162.83 10,481.39 10,481.39
TOTAL OF PART E 598,503.89
TOTAL OF PART III 9,361,764.93
TOTAL: NINE MILLION EIGHT HUNDRED THIRTY SIX THOUSAND SIXTY THREE AND 68/100 PESOS Php 9,836,063.68

Prepared By: Submitted by: APPROVED:

JONATHAN B. RAMOS ANDRES M. NICER EMMANUEL W. DIAZ, CESE


Engineer II Engineer IV OIC - Assistant Regional Director
OIC-Chief, Planning&Design Section Asst. District Engineer Concurrent District Engineer
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
PANGASINAN 3RD
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE I
Tumana, Rosales, Pangasinan
FORM POW-2015-01-00

PROGRAM OF WORKS/BUDGET COST

Project : CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL Appropriation : Php 9,885,491.14
BUILDING Source of Fund : BEFF CY 2017
Project ID : Target Start Date :
Location : Esperanza Integrated School, Sison, Pangasinan Total Project Duration : 160 CD
Project Description : Construction of Two (2) Storey Four (4) Classroom School Building
with Permits and Clearances Cost, Demolition Cost; 9.50m x 23.00m; Floor tiles at 3 CL
Window and Corridor at 2/F Grilles ; Total Floor Area - 437.00m²; 1.00 m Embankment )

AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part A Facilities for the Engineer 1.76% 138,666.67
Part B Other General Requirements 3.68% 289,569.02
Part III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
Part A Earthworks 3.85% 303,038.01
Part B Plain and Reinforced Concrete Works (PLS. SEE FORM POW-2015-01C-00) 30.10% 2,369,824.82
Part C Finishing and Other Civil Works 52.36% 4,122,159.69
Part D Electrical Works 2.21% 173,755.21
Part E Mechanical Works 6.03% 475,003.09
Total 100.00% 7,872,016.50

EQUIPMENT: BREAKDOWN OF EXPENDITURES:


DESCRIPTION REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1. Labor 1,548,480.87 A. Total Direct Cost 7,872,016.50
2. Materials 5,695,450.38 B. OCM and Profit 1,495,663.19
3. Rental of Equipment 628,085.25 C. Value Added Tax 468,383.98
4. Provisional Sum/Daywork - D. Total Construction Cost 9,836,063.68
(PLS. SEE FORM POW-2015-01B-00) 5. OCM and Profit 1,495,663.19 E. Eng'g & Administrative Overhead, 0.5% 49,427.46
6. Value Added Tax 468,383.98 F. RROW Acquisition -
7. EAO, 0.5% 49,427.46 G. Physical Reserved (Contingency) -
8. RROW Acquisition -
9. Physical Reserved (Contingency) -
10. TOTAL ESTIMATED COST 9,885,491.14 H. TOTAL ESTIMATED COST 9,885,491.14

Prepared by: Checked/Submitted by: Recommending Approval: APPROVED: CONCURRED:

RAMIL S. ISIT JONATHAN B. RAMOS ANDRES M. NICER EMMANUEL W. DIAZ, CESE Atty. DONATO D. BALDERAS, JR.
Architect II Engineer II Engineer IV OIC- Assistant Regional Director Schools Division Superintendent
Planning and Design Section Chief, Planning and Design Section Asst. District Engineer Concurrent District Engineer
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS EVALUATED
PART A FACILITIES FOR THE ENGINEER
A. 1. 1. Offices and Laboratory for the Engineer
5.33 month 138,666.67 26,000.00 29,484.00
A.1.1(8) Provision of Field Office for the Engineer (Rental Basis)
138,666.67
TOTAL OF PART A
PART B OTHER GENERAL REQUIREMENTS
1.00 L.S. 97,635.46 97,635.46 102,517.24
B.3 Permits and Clearances
3.00 each 12,463.86 4,154.62 5,234.82
B.5 Project Billboard/Signboard
5.33 month 123,641.33 23,182.75 26,289.24
B.7 Occupational Safety and Health Program
1.00 L.S. 55,828.36 55,828.36 58,619.77
B.9 Mobilization/Demobilization
289,569.02
TOTAL OF PART B
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
1.00 L.S. 82,851.91 82,851.91 86,994.50
801(1) Removal of Structures and Obstructions
196.98 m³ 45,013.67 228.52 287.93
803(1)a Structure Excavation (Common Soil)
105.37 m³ 15,402.65 146.18 184.18
804(1)a Embankment from Structure Excavation
269.15 m³ 130,181.62 483.68 609.43
804(1)b Embankment from Borrow
33.92 m³ 29,588.16 872.29 1,099.09
804(4) Gravel Fill
303,038.01
TOTAL OF PART A
PART B PLAIN AND REINFORCED CONCRETE WORKS
153.74 m³ 623,046.66 4,052.48 5,106.13
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
28,343.22 kgs. 1,345,236.10 47.46 59.80
902(1)a1 Reinforcing Steel (Deformed, Grade 40)
960.52 m² 401,542.06 418.05 526.74
903(2) Formworks and Falseworks
2,369,824.82
TOTAL OF PART B
PART C FINISHINGS AND OTHER CIVIL WORKS
C.1 Termite Control Works
115.60 lit 42,543.73 368.03 463.71
1000(1) Soil Poisoning
42,543.73
Sub-Total C.1
C.2 Masonry Works
129.91 m² 71,290.63 548.77 691.45
1046(2)a1 CHB Non-Load Bearing (including Reinforcing Steel; 100mm)
450.38 m² 378,378.12 840.13 1,058.56
1046(2)a2 CHB Non-Load Bearing (including Reinforcing Steel; 150mm)
449,668.74
Sub-Total C.2
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS EVALUATED

C.3 Fabricated Materials


20.00 set 13,000.00 650.00 819.00
1004(2)a Finishing Hardware (Locksets)
80.00 set 5,200.00 65.00 81.90
1004(2)g Finishing Hardware (Hinges)
48.96 m² 166,548.86 3,401.73 4,286.18
1005(1) Residential Casement (Steel Window)
24.05 m² 31,103.51 1,293.29 -
1009(1)a Jalousie Window
76.30 m² 73,206.97 959.46 1,208.92
1005(5) Grille (Window and Corridor at 2/F)
1.00 L.S. 174,155.66 174,155.66 219,436.13
1010(4) Wooden Doors
463,215.00
Sub-Total C.3
C.4 Finishing Works
Ceiling (4.5mm Fiber Cement Board on Metal Frame with Air 237.86 m² 226,638.83 952.82 1,200.56
1003(1)a1
Vent)
1.00 L.S. 17,071.61 17,071.61 21,510.23
1003(17) Carpentry and Joinery Works (Blackboard)
71.55 m² 121,144.69 1,693.15 2,133.37
1018(1) Glazed Tiles and Trims
209.05 m² 331,938.79 1,587.84 2,000.68
1018(2) Unglazed Tiles
424.17 m² 116,827.82 275.43 347.04
1021(1)c Plain Cement Finish with Floor Hardener
1,833.62 m² 325,223.52 177.37 223.48
1027(1) Plain Cement Plaster Finish
315.48 m² 67,241.47 213.14 268.56
1038(1) Reflective Insulation
33.00 m 16,474.15 499.22 629.01
1053(3)a1 38mm dia. G.I.Pipe Railing
50mm dia. G.I.Pipe Handrail Fully Welded on Vertical Railing 73.42 m 163,686.16 2,229.45 2,809.11
1053(3)a2
on 19mm bar Stiffener
1,386,247.04
Sub-Total C.4
C.5 Painting Works
1,997.26 m² 595,405.46 298.11 375.62
1032(1)a Painting Works (Masonry/Concrete)
104.49 m² 28,999.42 277.53 349.69
1032(1)b Painting Works (Wood)
50.14 m² 15,991.11 318.93 401.85
1032(1)c Painting Works (Steel)
640,395.99
Sub-Total C.5
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS EVALUATED
C.6 Roof Framing and Roofing Works
47.80 m 9,910.85 207.34 261.25
1003(11)a1 Fiber Cement Fascia Board
Prepainted Metal Sheets, Long Span, Corrugated, 0.5mm 315.48 m² 139,248.12 441.38 556.15
1014(1)b1
thk.
23.90 m 5,438.16 227.54 286.70
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll)
26.21 m 5,963.78 227.54 286.70
1013(2)b Fabricated Metal Roofing Accessory (Flashing)
47.80 m 16,029.04 335.34 422.52
1013(2)c Fabricated Metal Roofing Accessory (Gutter)
2,271.38 kg 173,835.90 76.53 96.43
1047(2)a Structural Steel (Trusses)
3,687.15 kg 266,355.37 72.24 91.02
1047(2)b Structural Steel (Purlins)
277.47 kg 19,125.57 68.93 86.85
1047(6) Metal Structure Accessories (Steel Plates)
101.34 kg 4,584.66 45.24 57.00
1047(7)b Metal Structure Accessories (Sagrods)
214.42 kg 11,301.20 52.71 66.41
1047(4) Metal Structure Accessories (Crossbracing)
18.00 pc 3,775.26 209.74 264.27
1047(3)c Metal Structure Accessories (Turnbuckle)
1.00 L.S. 102,789.13 102,789.13 129,514.30
1047(1) Structural Steel (Fire Escape)
758,357.04
Sub-Total C.6
C.7 Sanitary/Plumbing Works
12.00 each 10,620.50 885.04 1,115.15
1001(6)a Catch Basin
1.00 L.S. 23,398.44 23,398.44 29,482.03
1001(8) Sewer Line Works
1.00 L.S. 60,638.99 60,638.99 76,405.12
1001(9) Storm Drainage and Downspout
1.00 L.S. 282,689.16 282,689.16 356,188.34
1002(8) Plumbing Fixtures
1.00 L.S. 4,385.07 4,385.07 5,525.18
1002(28) Cold Water Lines
381,732.15
Sub-Total C.7
4,122,159.69
TOTAL OF PART C
PART D ELECTRICAL WORKS
1.00 L.S. 36,818.79 36,818.79 46,391.67
1100(30) Conduits, Boxes and Fittings
1.00 L.S. 64,679.66 64,679.66 81,496.37
1101(42) Wires and Wiring Devices
1.00 L.S. 25,594.39 25,594.39 32,248.93
1102(27) Panel Load Center, Switch Gear and Panelboards
1.00 L.S. 46,662.37 46,662.37 58,794.59
1103(1) Lighting Fixtures
173,755.21
TOTAL OF PART D
PART E MECHANICAL WORKS
1.00 L.S. 466,684.52 466,684.52 588,022.50
1202(1) Automatic Water Sprinkler System
1.00 L.S. 8,318.56 8,318.56 10,481.39
1208(1) Fire Alarm System
475,003.09
TOTAL OF PART E
7,443,780.82
TOTAL OF PART III
7,872,016.50
GRAND TOTAL
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

FORM POW-2015-01B-00

MINIMUM EQUIPMENT REQUIREMENT


Equipment Description Number of Equipment Description Number of
No. Capacity No. Capacity
Equipment Equipment
1 Assorted Minor Tools 1 31
2 Backhoe (0.80 m³) 0.80 m³ 1 32
3 Dump Truck (12 yd³) 12 yd³ 2 33
4 Plate Compactor (5 hp) 5 hp 1 34
5 Concrete Vibrator 2 35
6 Pumpcrete 1 36
7 One Bagger Mixer 1 37
8 Bar Cutter Single Phase 1 38
9 Bar Bender 1 39
10 H-Frame 1.7 m x 1.2m, set 40 40
11 Shoring Jack, 3.8 m full extension 62 41
12 Adjustable U-head Jack, 0.6m 80 42
13 Adjustable Base Jack, 0.6m 80 43
14 1-1/2" GI Pipe x 6.0 m 62 44
15 1-1/2" GI Pipe x 3.0 m 16 45
16 1-1/2" GI Pipe x 4.0 m 32 46
17 1-1/2" GI Pipe x 1.0 m 216 47
18 Tie Rod x 0.60m 278 48
19 Round Wing Nut 558 49
20 Minor Tools (10% of Labor Cost) 0 50
21 Cutting Outfit 1 51
52
53
54
55
56
57
58
59
60
SUB-TOTAL TOTAL 1436 SUB-TOTAL TOTAL 0
TOTAL 1,436
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

FORM POW-2015-01C-00

DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM


DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART A FACILITIES FOR THE ENGINEER
A.1.1. Offices and Laboratory for the Engineer
As Submitted 1.60% 5.33 month 138,666.67 - - 138,666.67 8% 11,093.33 7,488.00 157,248.00
A.1.1(8) Provision of Field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted 138,666.67 - 138,666.67 11,093.33 7,488.00 157,248.00
TOTAL OF PART A
As Evaluated
PART B OTHER GENERAL REQUIREMENTS
As Submitted 1.04% 1.00 L.S. 97,635.46 - - 97,635.46 0% - 4,881.77 102,517.24
B.3 Permits and Clearances
As Evaluated
As Submitted 0.16% 3.00 each 10,485.00 1,798.97 179.90 12,463.86 20% 2,492.77 747.83 15,704.47
B.5 Project Billboard/Signboard
As Evaluated
As Submitted 1.43% 5.33 month 118,048.16 5,593.17 - 123,641.33 8% 9,891.31 6,676.63 140,209.27
B.7 Occupational Safety and Health Program
As Evaluated
As Submitted 0.60% 1.00 L.S. - - 55,828.36 55,828.36 0% - 2,791.42 58,619.77
B.9 Mobilization/Demobilization
As Evaluated
As Submitted 226,168.62 7,392.14 56,008.25 289,569.02 12,384.08 15,097.65 317,050.75
TOTAL OF PART B
As Evaluated
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted 0.88% 1.00 L.S. - 75,319.92 7,531.99 82,851.91 0% - 4,142.60 86,994.50
801(1) Removal of Structures and Obstructions
As Evaluated
As Submitted 0.58% 196.98 m³ - 1,731.45 43,282.22 45,013.67 20% 9,002.73 2,700.82 56,717.23
803(1)a Structure Excavation (Common Soil)
As Evaluated
As Submitted 0.20% 105.37 m³ - 1,882.53 13,520.13 15,402.65 20% 3,080.53 924.16 19,407.34
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted 1.67% 269.15 m³ 90,838.13 4,808.59 34,534.90 130,181.62 20% 26,036.32 7,810.90 164,028.84
804(1)b Embankment from Borrow
As Evaluated
As Submitted 0.38% 33.92 m³ 21,369.60 5,891.06 2,327.51 29,588.16 20% 5,917.63 1,775.29 37,281.08
804(4) Gravel Fill
As Evaluated
As Submitted 112,207.73 89,633.55 101,196.74 303,038.01 44,037.22 17,353.76 364,429.00
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted 7.98% 153.74 m³ 575,004.06 15,758.39 32,284.22 623,046.66 20% 124,609.33 37,382.80 785,038.79
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted 17.23% 28343.22 kgs. 1,125,686.46 142,581.15 76,968.49 1,345,236.10 20% 269,047.22 80,714.17 1,694,997.48
902(1)a1 Reinforcing Steel (Deformed, Grade 40)
As Evaluated
As Submitted 5.14% 960.52 m² 176,500.59 135,906.75 89,134.72 401,542.06 20% 80,308.41 24,092.52 505,943.00
903(2) Formworks and Falseworks
As Evaluated
As Submitted 1,877,191.11 294,246.29 198,387.42 2,369,824.82 473,964.96 142,189.49 2,985,979.27
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted 0.54% 115.60 lit 38,148.00 3,996.12 399.61 42,543.73 20% 8,508.75 2,552.62 53,605.10
1000(1) Soil Poisoning
As Evaluated
As Submitted 38,148.00 3,996.12 399.61 42,543.73 8,508.75 2,552.62 53,605.10
Sub-Total C.1
As Evaluated
C.2 Masonry Works
CHB Non-Load Bearing (including Reinforcing Steel; As Submitted 0.91% 129.91 m² 51,204.03 12,949.90 7,136.70 71,290.63 20% 14,258.13 4,277.44 89,826.19
1046(2)a1
100mm) As Evaluated
CHB Non-Load Bearing (including Reinforcing Steel; As Submitted 4.85% 450.38 m² 294,616.08 54,001.70 29,760.35 378,378.12 20% 75,675.62 22,702.69 476,756.43
1046(2)a2
150mm) As Evaluated
As Submitted 345,820.10 66,951.60 36,897.04 449,668.74 89,933.75 26,980.12 566,582.62
Sub-Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted 0.17% 20.00 set 13,000.00 - - 13,000.00 20% 2,600.00 780.00 16,380.00
1004(2)a Finishing Hardware (Locksets)
As Evaluated
As Submitted 0.07% 80.00 set 5,200.00 - - 5,200.00 20% 1,040.00 312.00 6,552.00
1004(2)g Finishing Hardware (Hinges)
As Evaluated
As Submitted 2.13% 48.96 m² 95,104.80 40,778.24 30,665.82 166,548.86 20% 33,309.77 9,992.93 209,851.57
1005(1) Residential Casement (Steel Window)
As Evaluated
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

FORM POW-2015-01C-00

DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM


DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 0.40% 24.05 m² 16,414.13 13,353.99 1,335.40 31,103.51 20% 6,220.70 1,866.21 39,190.42
1009(1)a Jalousie Window
As Evaluated
As Submitted 0.94% 76.30 m² 59,828.23 7,924.80 5,453.93 73,206.97 20% 14,641.39 4,392.42 92,240.78
1005(5) Grille (Window and Corridor at 2/F)
As Evaluated
As Submitted 2.23% 1.00 L.S. 138,075.00 32,800.60 3,280.06 174,155.66 20% 34,831.13 10,449.34 219,436.13
1010(4) Wooden Doors
As Evaluated
As Submitted 327,622.16 94,857.62 40,735.22 463,215.00 92,643.00 27,792.90 583,650.90
Sub-Total C.3
As Evaluated
C.4 Finishing Works
Ceiling (4.5mm Fiber Cement Board on Metal Frame with As Submitted 2.90% 237.86 m² 141,802.80 77,123.67 7,712.37 226,638.83 20% 45,327.77 13,598.33 285,564.92
1003(1)a1
Air Vent) As Evaluated
As Submitted 0.22% 1.00 L.S. 12,400.00 4,246.92 424.69 17,071.61 20% 3,414.32 1,024.30 21,510.23
1003(17) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 1.55% 71.55 m² 68,717.93 47,660.69 4,766.07 121,144.69 20% 24,228.94 7,268.68 152,642.31
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted 4.25% 209.05 m² 224,714.90 97,476.26 9,747.63 331,938.79 20% 66,387.76 19,916.33 418,242.87
1018(2) Unglazed Tiles
As Evaluated
As Submitted 1.50% 424.17 m² 90,662.10 23,787.03 2,378.70 116,827.82 20% 23,365.56 7,009.67 147,203.06
1021(1)c Plain Cement Finish with Floor Hardener
As Evaluated
As Submitted 4.17% 1833.62 m² 169,518.17 141,550.32 14,155.03 325,223.52 20% 65,044.70 19,513.41 409,781.63
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted 0.86% 315.48 m² 44,719.29 20,474.71 2,047.47 67,241.47 20% 13,448.29 4,034.49 84,724.25
1038(1) Reflective Insulation
As Evaluated
As Submitted 0.21% 33.00 m 13,783.77 984.83 1,705.55 16,474.15 20% 3,294.83 988.45 20,757.43
1053(3)a1 38mm dia. G.I.Pipe Railing
As Evaluated
As Submitted 2.10% 73.42 m 157,700.47 2,191.10 3,794.59 163,686.16 20% 32,737.23 9,821.17 206,244.56
1053(3)a2 50mm dia. G.I.Pipe Handrail Fully Welded on Vertical Railing on 19mm bar Stiffener
As Evaluated
As Submitted 924,019.42 415,495.51 46,732.10 1,386,247.04 277,249.41 83,174.82 1,746,671.27
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted 7.63% 1997.26 m² 242,804.90 320,545.96 32,054.60 595,405.46 20% 119,081.09 35,724.33 750,210.88
1032(1)a Painting Works (Masonry/Concrete)
As Evaluated
As Submitted 0.37% 104.49 m² 8,502.87 18,633.22 1,863.32 28,999.42 20% 5,799.88 1,739.96 36,539.26
1032(1)b Painting Works (Wood)
As Evaluated
As Submitted 0.20% 50.14 m² 6,696.70 8,449.47 844.95 15,991.11 20% 3,198.22 959.47 20,148.80
1032(1)c Painting Works (Steel)
As Evaluated
As Submitted 258,004.47 347,628.65 34,762.87 640,395.99 128,079.20 38,423.76 806,898.95
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted 0.13% 47.80 m 9,084.39 751.32 75.13 9,910.85 20% 1,982.17 594.65 12,487.67
1003(11)a1 Fiber Cement Fascia Board
As Evaluated
As Submitted 1.78% 315.48 m² 108,044.01 28,367.37 2,836.74 139,248.12 20% 27,849.62 8,354.89 175,452.63
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5mm thk.
As Evaluated
As Submitted 0.07% 23.90 m 5,044.02 358.31 35.83 5,438.16 20% 1,087.63 326.29 6,852.09
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll)
As Evaluated
As Submitted 0.08% 26.21 m 5,531.54 392.94 39.29 5,963.78 20% 1,192.76 357.83 7,514.36
1013(2)b Fabricated Metal Roofing Accessory (Flashing)
As Evaluated
As Submitted 0.21% 47.80 m 15,361.01 607.30 60.73 16,029.04 20% 3,205.81 961.74 20,196.59
1013(2)c Fabricated Metal Roofing Accessory (Gutter)
As Evaluated
As Submitted 2.23% 2271.38 kg 133,807.56 9,574.91 30,453.43 173,835.90 20% 34,767.18 10,430.15 219,033.23
1047(2)a Structural Steel (Trusses)
As Evaluated
As Submitted 3.41% 3687.15 kg 220,675.93 12,546.91 33,132.54 266,355.37 20% 53,271.07 15,981.32 335,607.77
1047(2)b Structural Steel (Purlins)
As Evaluated
As Submitted 0.24% 277.47 kg 15,604.36 3,201.10 320.11 19,125.57 20% 3,825.11 1,147.53 24,098.22
1047(6) Metal Structure Accessories (Steel Plates)
As Evaluated
As Submitted 0.06% 101.34 kg 3,298.62 1,169.13 116.91 4,584.66 20% 916.93 275.08 5,776.68
1047(7)b Metal Structure Accessories (Sagrods)
As Evaluated
As Submitted 0.14% 214.42 kg 8,580.12 2,473.71 247.37 11,301.20 20% 2,260.24 678.07 14,239.52
1047(4) Metal Structure Accessories (Crossbracing)
As Evaluated
As Submitted 0.05% 18.00 pc 3,330.00 404.78 40.48 3,775.26 20% 755.05 226.52 4,756.83
1047(3)c Metal Structure Accessories (Turnbuckle)
As Evaluated
As Submitted 1.32% 1.00 L.S. 61,892.95 11,029.00 29,867.17 102,789.13 20% 20,557.83 6,167.35 129,514.30
1047(1) Structural Steel (Fire Escape)
As Evaluated
As Submitted 590,254.52 70,876.78 97,225.74 758,357.04 151,671.41 45,501.42 955,529.87
Sub-Total C.6
As Evaluated
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

FORM POW-2015-01C-00

DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM


DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
C.7 Sanitary/Plumbing Works
As Submitted 0.14% 12.00 each 8,641.56 1,799.04 179.90 10,620.50 20% 2,124.10 637.23 13,381.84
1001(6)a Catch Basin
As Evaluated
As Submitted 0.30% 1.00 L.S. 17,649.00 5,226.76 522.68 23,398.44 20% 4,679.69 1,403.91 29,482.03
1001(8) Sewer Line Works
As Evaluated
As Submitted 0.78% 1.00 L.S. 44,679.00 14,509.08 1,450.91 60,638.99 20% 12,127.80 3,638.34 76,405.12
1001(9) Storm Drainage and Downspout
As Evaluated
As Submitted 3.62% 1.00 L.S. 225,957.40 51,574.32 5,157.43 282,689.16 20% 56,537.83 16,961.35 356,188.34
1002(8) Plumbing Fixtures
As Evaluated
As Submitted 0.06% 1.00 L.S. 3,717.72 606.68 60.67 4,385.07 20% 877.01 263.10 5,525.18
1002(28) Cold Water Lines
As Evaluated
As Submitted 300,644.68 73,715.88 7,371.59 381,732.15 76,346.43 22,903.93 480,982.51
Sub-Total C.7
As Evaluated
As Submitted 2,784,513.36 1,073,522.17 264,124.16 4,122,159.69 824,431.94 247,329.58 5,193,921.21
TOTAL OF PART C
As Evaluated
PART D ELECTRICAL
As Submitted 0.47% 1.00 L.S. 29,384.20 6,758.72 675.87 36,818.79 20% 7,363.76 2,209.13 46,391.67
1100(30) Conduits, Boxes and Fittings
As Evaluated
As Submitted 0.83% 1.00 L.S. 57,123.00 6,869.69 686.97 64,679.66 20% 12,935.93 3,880.78 81,496.37
1101(42) Wires and Wiring Devices
As Evaluated
As Submitted 0.33% 1.00 L.S. 24,259.70 1,213.36 121.34 25,594.39 20% 5,118.88 1,535.66 32,248.93
1102(27) Panel Load Center, Switch Gear and Panelboards
As Evaluated
As Submitted 0.60% 1.00 L.S. 39,166.00 6,814.88 681.49 46,662.37 20% 9,332.47 2,799.74 58,794.59
1103(1) Lighting Fixtures
As Evaluated
As Submitted 149,932.90 21,656.64 2,165.66 173,755.21 34,751.04 10,425.31 218,931.56
TOTAL OF PART D
As Evaluated
PART E MECHANICAL WORKS
As Submitted 5.98% 1.00 L.S. 400,586.00 60,089.57 6,008.96 466,684.52 20% 93,336.90 28,001.07 588,022.50
1202(1) Automatic Water Sprinkler System
As Evaluated
As Submitted 0.11% 1.00 L.S. 6,184.00 1,940.51 194.05 8,318.56 20% 1,663.71 499.11 10,481.39
1208(1) Fire Alarm System
As Evaluated
As Submitted 406,770.00 62,030.08 6,203.01 475,003.09 95,000.62 28,500.19 598,503.89
TOTAL OF PART E
As Evaluated
As Submitted 5,330,615.09 1,541,088.73 572,077.00 7,443,780.82 1,472,185.78 445,798.33 9,361,764.93
TOTAL OF PART III
As Evaluated
As Submitted 100.00% 5,695,450.38 1,548,480.87 628,085.25 7,872,016.50 1,495,663.19 468,383.98 9,836,063.68
GRAND TOTAL
As Evaluated
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : A.1.1(8) Provision of Field Office for the Engineer (Rental Basis)
Unit of Measurement : month
Output - As Submitted : 1.00
Output - As Evaluated :

Designation No. of Person/s No. of Month/s Rate Amount (Php)


A.1 Labor
-
Sub-Total for A.1 - As Submitted -
A.2 Labor

Sub-Total for A.2 - As Evaluated -


Name and Capacity No. of Unit/s No. of Month/s Rate Amount (Php)
B.1 Equipment
-
Sub-Total for B.1 - As Submitted -
B.2 Equipment

Sub-Total for B.2 - As Evaluated -


C.1 Total (A.1 + B.1) - As Submitted -
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output - As Submitted 1.00
D.2 Output - As Evaluated
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted -
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Provision of Field Office for the Engineer
1.00 26000.00 26,000.00
(Rental Basis)
Sub-Total for F.1 - As Submitted 26,000.00
F.2 Materials

Sub-Total for F.2 - As Evaluated -


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 26,000.00
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted % of G.1 -
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated % of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 2,080.00
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 1,404.00
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 29,484.00
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : B.3 Permits and Clearances
Unit of Measurement : L.S.
Output - As Submitted : 1.00
Output - As Evaluated :

Designation No. of Person/s No. of Hour/s Rate Amount (Php)


A.1 Labor
-
Sub-Total for A.1 - As Submitted -
A.2 Labor

Sub-Total for A.2 - As Evaluated -


Name and Capacity No. of Unit/s No. of Hour/s Rate Amount (Php)
B.1 Equipment
-
Sub-Total for B.1 - As Submitted -
B.2 Equipment

Sub-Total for B.2 - As Evaluated -


C.1 Total (A.1 + B.1) - As Submitted -
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output - As Submitted 1.00
D.2 Output - As Evaluated
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted -
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Fire Code Construction Tax L.S. 1.00 97335.46 97,335.46
Hot Works Clearance Fee L.S. 1.00 300.00 300.00
Sub-Total for F.1 - As Submitted 97,635.46
F.2 Materials

Sub-Total for F.2 - As Evaluated -


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 97,635.46
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted % of G.1 -
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated % of G.2 -
I.1 Contractor's Profit (CP) - As Submitted % of G.1 -
I.2 Contractor's Profit (CP) - As Evaluated % of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 4,881.77
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 102,517.24
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : B.5 Project Billboard/Signboard
Unit of Measurement : each
Output - As Submitted : 1.00
Output - As Evaluated :

Designation No. of Person/s No. of Hour/s Rate Amount (Php)


A.1 Labor
Foreman 1 4.00 65.55 262.18
Skilled Laborer 1 4.00 47.62 190.50
Unskilled Laborer 1 4.00 36.75 146.98
Sub-Total for A.1 - As Submitted 599.66
A.2 Labor

Sub-Total for A.2 - As Evaluated -


Name and Capacity No. of Unit/s No. of Hour/s Rate Amount (Php)
B.1 Equipment
Minor tools (10% of Labor Cost) 59.97 59.97

Sub-Total for B.1 - As Submitted 59.97


B.2 Equipment

Sub-Total for B.2 - As Evaluated -


C.1 Total (A.1 + B.1) - As Submitted 659.62
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output - As Submitted 1.00
D.2 Output - As Evaluated
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 659.62
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
a. 8' x 8' Tarpaulin ft2 64.00 20.00 1,280.00
b. Good Lumber (Frames) bd-ft 48.00 45.00 2,160.00
c. Assorted Common Working Nails kg 1.00 55.00 55.00
Sub-Total for F.1 - As Submitted 3,495.00
F.2 Materials

Sub-Total for F.2 - As Evaluated -


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 4,154.62
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 498.55
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 332.37
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 249.28
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 5,234.82
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : B.7 Occupational Safety and Health Program
Unit of Measurement : month
Output per month - As Submitted : 1.00
Output per month - As Evaluated :

Designation No. of Person/s No. of Days/s Monthly Rate Amount (Php)


A.1 Labor
Safety Officer (Part Time) 1 2.00 524.36 1,048.72
Sub-Total for A.1 - As Submitted 1,048.72
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Month/s Monthly Rate Amount (Php)
B.1 Equipment
-
Sub-Total for B.1 - As Submitted -
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 1,048.72
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per month - As Submitted 1.00
D.2 Output per month - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 1,048.72
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
First Aid Kit l.s. 1 1000.00 166.67
Personal Protective Equipment(PPE)
Safety Helmet man-days 2013.00 0.25 503.25
Safety Gloves man-days 2013.00 2.77 5,576.01
Safety Shoes man-days 2013.00 7.67 15,439.71
Signages and Barricades
PPE Signage (4' x 8') set 1.00 506.37 84.40
Safety First (4' x 4') set 1.00 270.87 45.15
Warning Signs (2' x 3') sets 9.00 123.68 185.52
Caution Tape, 100ft roll 1.00 800.00 133.33
Sub-Total for F.1 - As Submitted 22,134.03
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 23,182.75
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted % of G.1 -
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated % of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 1,854.62
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 1,251.87
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 26,289.24
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : B.9 Mobilization/Demobilization
Unit of Measurement : L.S.
Output per month - As Submitted : 1.00
Output per month - As Evaluated :

Designation No. of Person/s No. of Month/s Monthly Rate Amount (Php)


A.1 Labor
-
Sub-Total for A.1 - As Submitted -
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Month/s Monthly Rate Amount (Php)
B.1 Equipment
Mobilization/ Demobilization (0.75% of Civil Works) 55,828.36
Sub-Total for B.1 - As Submitted 55,828.36
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 55,828.36
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per month - As Submitted 1.00
D.2 Output per month - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 55,828.36
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
-
Sub-Total for F.1 - As Submitted -
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 55,828.36
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted % of G.1 -
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated % of G.2 -
I.1 Contractor's Profit (CP) - As Submitted % of G.1 -
I.2 Contractor's Profit (CP) - As Evaluated % of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 2,791.42
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 58,619.77
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 801(1) Removal of Structures and Obstructions
Unit of Measurement : L.S.
Output per month - As Submitted : 1.00
Output per month - As Evaluated :

Designation No. of Person/s No. of Month/s Monthly Rate Amount (Php)


A.1 Labor
Laborer 12 170.79 36.75 75,319.92
Sub-Total for A.1 - As Submitted 75,319.92
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Month/s Monthly Rate Amount (Php)
B.1 Equipment
Minor Tools (10% of Labor Cost) 7,531.99
Sub-Total for B.1 - As Submitted 7,531.99
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 82,851.91
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per month - As Submitted 1.00
D.2 Output per month - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 82,851.91
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
-
Sub-Total for F.1 - As Submitted -
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 82,851.91
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted % of G.1 -
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated % of G.2 -
I.1 Contractor's Profit (CP) - As Submitted % of G.1 -
I.2 Contractor's Profit (CP) - As Evaluated % of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 4,142.60
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 86,994.50
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 803(1)a Structure Excavation (Common Soil)
Unit of Measurement : m³
Output per hour - As Submitted : 20.00
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 1.00 65.55 65.55
Unskilled Laborer 3 1.00 36.75 110.25
Sub-Total for A.1 - As Submitted 175.80
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Backhoe (0.80 m³) 1 1 1537.00 1,537.00
Dump Truck (12 yd³) 2 1 1420.00 2,840.00
Minor Tools (10% of Labor Cost) 17.58
Sub-Total for B.1 - As Submitted 4,394.58
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 4,570.38
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 20.00
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 228.52
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Excavation of Column Footing, WF and FB m³ 1.00 0.00 -
Sub-Total for F.1 - As Submitted -
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 228.52
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 27.42
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 18.28
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 13.71
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 287.93
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 804(1)a Embankment from Structure Excavation
Unit of Measurement : m³
Output per hour - As Submitted : 9.84
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 1.00 65.55 65.55
Unskilled Laborer 3 1.00 36.75 110.25
Sub-Total for A.1 - As Submitted 175.80
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Plate Compactor (5 hp) 1 0.75 123.00 92.25
Backhoe (0.80 m3) 1 0.75 1537.00 1,152.75
Minor Tools (10% of Labor Cost) 17.58
Sub-Total for B.1 - As Submitted 1,262.58
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 1,438.38
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 9.84
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 146.18
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Backfilling of Excavated Materials m³ 1.00 0.00 -
Sub-Total for F.1 - As Submitted -
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 146.18
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 17.54
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 11.69
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 8.77
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 184.18
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 804(1)b Embankment from Borrow
Unit of Measurement : m³
Output per hour - As Submitted : 9.84
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 1.00 65.55 65.55
Unskilled Laborer 3 1.00 36.75 110.25
Sub-Total for A.1 - As Submitted 175.80
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Plate Compactor (5 hp) 1 0.75 123.00 92.25
Backhoe (0.80 m3) 1 0.75 1537.00 1,152.75
Minor Tools (10% of Labor Cost) 17.58
Sub-Total for B.1 - As Submitted 1,262.58
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 1,438.38
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 9.84
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 146.18
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Embankment from Borrow
m³ 1.25 270.00 337.50
(w/ 25% Shrinkage Factor)
Sub-Total for F.1 - As Submitted 337.50
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 483.68
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 58.04
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 38.69
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 29.02
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 609.43
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 804(4) Gravel Fill
Unit of Measurement : m³
Output per hour - As Submitted : 1.20
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 1.00 65.55 65.55
Skilled Laborer 3 1.00 47.62 142.86
Sub-Total for A.1 - As Submitted 208.41
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Plate Compactor 1 0.5 123.00 61.50
Minor Tools (10% of Labor Cost) 20.84
Sub-Total for B.1 - As Submitted 82.34
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 290.75
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 1.20
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 242.29
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Gravel Bedding - G1 (w/ 5% Shrinkage Factor) m³ 1.05 600.00 630.00
Sub-Total for F.1 - As Submitted 630.00
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 872.29
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 104.68
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 69.78
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 52.34
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 1,099.09
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
Unit of Measurement : m³
Output per hour - As Submitted : 3.72
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 1.00 65.55 65.55
Skilled Laborer 2 1.00 47.62 95.24
Unskilled Laborer 6 1.00 36.75 220.50
Sub-Total for A.1 - As Submitted 381.29
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Concrete Vibrator 2 1 91.25 182.50
Pumpcrete 1 0.27 2076.00 560.52
Minor Tools (10% of Labor Cost) 38.13
Sub-Total for B.1 - As Submitted 781.15
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 1,162.44
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 3.72
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 312.48
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Ready Mix Concrete, Class A, 28 days m³ 1.00 3740.00 3,740.00
Sub-Total for F.1 - As Submitted 3,740.00
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 4,052.48
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 486.30
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 324.20
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 243.15
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 5,106.13
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 902(1)a1 Reinforcing Steel (Deformed, Grade 40)
Unit of Measurement : kgs.
Output per hour - As Submitted : 129.094
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 1.00 65.55 65.55
Skilled Laborer 3 1.00 47.62 142.86
Unskilled Laborer 12 1.00 36.75 441.00
Sub-Total for A.1 - As Submitted 649.41
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Bar Cutter Single Phase 1 0.50 219.75 109.88
Bar Bender 1 0.50 351.50 175.75
Minor Tools (10% of Labor Cost) 64.94
Sub-Total for B.1 - As Submitted 350.57
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 999.98
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 129.09
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 7.75
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Deformed Reinforcing Steel (Grade 60/Grade 40) kgs 1.00 37.00 37.00
#16 Tie Wire, 150m/roll kgs 0.015 55.00 0.83
Consumables (5% of Materials Cost) 1.89
Sub-Total for F.1 - As Submitted 39.72
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 47.46
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 5.70
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 3.80
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 2.85
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 59.80
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 903(2) Formworks and Falseworks
Unit of Measurement : m²
Output per hour - As Submitted : 4.50
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Installation and Stripping
Foreman 1 1.56 65.55 102.26
Skilled Laborer 4 1.00 47.62 190.48
Unskilled Laborer 6 1.56 36.75 343.98
Sub-Total for A.1 - As Submitted 636.72
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Area = 205.01 m2
H-Frame 1.7 m x 1.2m, set 40 14 6.08 3,404.80
2 pcs H-frames
4 pcs diagonal cross braces
4 pcs horizontal braces
8 pcs joint pins
Shoring Jack, 3.8 m full extension 62 14 4.50 3,906.00
Adjustable U-head Jack, 0.6m 80 14 0.85 952.00
Adjustable Base Jack, 0.6m 80 14 0.85 952.00
1-1/2" GI Pipe x 6.0 m 62 14 2.50 2,170.00
1-1/2" GI Pipe x 3.0 m 16 14 1.25 280.00
1-1/2" GI Pipe x 4.0 m 32 14 1.75 784.00
1-1/2" GI Pipe x 1.0 m 216 14 0.50 1,512.00
Tie Rod x 0.60m 278 14 1.00 3,892.00
Round Wing Nut 558 14 0.15 1,171.80
Sub-Total for B.1 - As Submitted 19,024.60
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Sub Total (B.1/Area) - As Submitted 92.80
C.2 Sub Total (B.2/Area) - As Evaluated -
D.1 Output per hour - As Submitted 4.50
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 +A.1/D.1) - As Submitted 234.29
E.2 Direct Unit Cost (C.2 + A.2/D.2) - As Evaluated
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Phenolic Board (0.019 x 1.2 x 2.4) - 4 uses pc 0.347 300.00 104.10
Good Lumber - 3 uses bd ft 4.727 15.00 70.91
Consumables (5% of Materials Cost) 8.75
Sub-Total for F.1 - As Submitted 183.76
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 418.05
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 50.17
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 33.44
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 25.08
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 526.74
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1046(2)a1 CHB Non-Load Bearing (including Reinforcing Steel; 100mm)
Unit of Measurement : m²
Output per hour - As Submitted : 3.825
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 1.00 65.55 65.55
Skilled Laborer 2 1.00 47.62 95.24
Unskilled Laborer 3 2.00 36.75 220.50
Sub-Total for A.1 - As Submitted 381.29
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
One-bagger mixer 1 1.00 172.00 172.00
Minor Tools (10% of Labor Cost) 38.13
Sub-Total for B.1 - As Submitted 210.13
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 591.42
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 3.83
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 154.62
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
CHB 4" thk. (100mm) pcs 13.00 10.00 130.00
Portland Cement bags 0.525 240.00 126.00
Sand cu.m. 0.044 500.00 22.00
Reinforcing Steel kgs 3.240 35.00 113.40
#16 G.I. Tie Wire kgs 0.050 55.00 2.75
Sub-Total for F.1 - As Submitted 394.15
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 548.77
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 65.85
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 43.90
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 32.93
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 691.45
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1000(1) Soil Poisoning
Unit of Measurement : lit
Output per hour - As Submitted : 5.40
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 1.00 65.55 65.55
Skilled Laborer 1 1.00 47.62 47.62
Unskilled Laborer 2 1.00 36.75 73.50
Sub-Total for A.1 - As Submitted 186.67
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Minor Tools (10% of Labor Cost) 18.67 18.67
Sub-Total for B.1 - As Submitted 18.67
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 205.34
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 5.40
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 38.03
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Soil Poisoning lit. 1.00 330.00 330.00
Sub-Total for F.1 - As Submitted 330.00
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 368.03
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 44.16
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 29.44
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 22.08
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 463.71
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1046(2)a2 CHB Non-Load Bearing (including Reinforcing Steel; 150mm)
Unit of Measurement : m²
Output per hour - As Submitted : 3.18
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 1.00 65.55 65.55
Skilled Laborer 2 1.00 47.62 95.24
Unskilled Laborer 3 2.00 36.75 220.50
Sub-Total for A.1 - As Submitted 381.29
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
One-bagger mixer 1 1.00 172.00 172.00
Minor Tools (10% of Labor Cost) 38.13
Sub-Total for B.1 - As Submitted 210.13
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 591.42
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 3.18
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 185.98
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
CHB 6" thk. pcs 13.00 12.00 156.00
Portland Cement bags 1.500 240.00 360.00
Sand cu.m. 0.044 500.00 22.00
Reinforcing Steel kgs 3.240 35.00 113.40
#16 G.I. Tie Wire kgs 0.050 55.00 2.75
Sub-Total for F.1 - As Submitted 654.15
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 840.13
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 100.82
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 67.21
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 50.41
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 1,058.56
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1004(2)a Finishing Hardware (Locksets)
Unit of Measurement : set
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
(Labor cost for these items are to be considered/included in the installation of doors, windows, and other fabricated materials.)
Sub-Total for A.1 - As Submitted -
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
-
Sub-Total for B.1 - As Submitted -
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted -
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted -
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Locksets set 1.00 650.00 650.00
Sub-Total for F.1 - As Submitted 650.00
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 650.00
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 78.00
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 52.00
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 39.00
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 819.00
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1004(2)g Finishing Hardware (Hinges)
Unit of Measurement : set
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
(Labor cost for these items are to be considered/included in the installation of doors, windows, and other fabricated materials.)
Sub-Total for A.1 - As Submitted -
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
-
Sub-Total for B.1 - As Submitted -
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted -
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted -
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Cylindrical Hinges set 1.00 65.00 65.00
Sub-Total for F.1 - As Submitted 65.00
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 65.00
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 7.80
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 5.20
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 3.90
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 81.90
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1005(1) Residential Casement (Steel Window)
Unit of Measurement : m²
Output per hour - As Submitted : 0.18
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 1.00 65.55 65.55
Skilled Laborer 1 1.00 47.62 47.62
Unskilled Laborer 1 1.00 36.75 36.75
Sub-Total for A.1 - As Submitted 149.92
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Welding Machine 1 0.25 391 97.75
Minor Tools (10% of Labor Cost) 14.99
Sub-Total for B.1 - As Submitted 112.74
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 262.66
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 0.18
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 1,459.23
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Steel Casement Window m² 1.00 1850.00 1,850.00
Consumables (5% of Materials Cost) 92.50
Sub-Total for F.1 - As Submitted 1,942.50
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 3,401.73
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 408.21
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 272.14
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 204.10
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 4,286.18
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1005(5) Grille (Corridor)
Unit of Measurement : m²
Output per hour - As Submitted : 1.60
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 1.00 65.55 65.55
Skilled Laborer 1 1.00 47.62 47.62
Unskilled Laborer 1 1.44 36.75 53.01
Sub-Total for A.1 - As Submitted 166.18
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Welding Machine 1 0.25 391 97.75
Minor Tools (10% of Labor Cost) 16.62
Sub-Total for B.1 - As Submitted 114.37
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 280.55
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 1.60
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 175.34
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
12 mm x 12 mm square bar kg. 12.56 52.00 653.12
25 x 4 mm flat bar kg. 2.08 52.00 108.16
Consumables (5% of Materials Cost) 22.84
Sub-Total for F.1 - As Submitted 784.12
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 959.46
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 115.14
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 76.76
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 57.57
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 1,208.92
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1009(1)a Jalousie Window
Unit of Measurement : m²
Output per hour - As Submitted : 0.27
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 1.00 65.55 65.55
Skilled Laborer 1 1.00 47.62 47.62
Unskilled Laborer 1 1.00 36.75 36.75
Sub-Total for A.1 - As Submitted 149.92
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment

Minor Tools (10% of Labor Cost) 14.99


Sub-Total for B.1 - As Submitted 14.99
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 164.91
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 0.27
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 610.79
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Jalousie Window m² 1.00 650.00 650.00
Consumables (5% of Materials Cost) 32.50
Sub-Total for F.1 - As Submitted 682.50
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 1,293.29
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 155.19
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 103.46
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 77.60
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 1,629.54
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1010(4) Wooden Door
Unit of Measurement : L.S.
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 140.00 65.55 9,177.00
Skilled Laborer 2 140.00 47.62 13,333.60
Unskilled Laborer 2 140.00 36.75 10,290.00
Sub-Total for A.1 - As Submitted 32,800.60
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Minor Tools (10% of Labor Cost) 3,280.06
Sub-Total for B.1 - As Submitted 3,280.06
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 36,080.66
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 36,080.66
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
D1 - (8 sets 0.9 x 2.40m) Panel door on wooden
jamb w/ fixed clear glass transom and frame (as set 8.00 8000.00 64,000.00
per plan)

D2 - (1 set 0.90 x 2.10m) Hollow core flush door set 1.00 6500.00 6,500.00
on wooden jamb with kick plate (as per plan)
D3 - (6 sets 0.80 x 2.10m) Hollow core flush door
set 6.00 6000.00 36,000.00
on wooden jamb (as per plan)
D4 - (1 set 0.70 x 2.10m) Hollow core flush door
set 1.00 5000.00 5,000.00
on wooden jamb (as per plan)
BD-1 - (5 sets 0.60 x 1.20m) Hollow core flush
set 5.00 4000.00 20,000.00
door on wooden jamb (as per plan)
Consumables (5% of Materials Cost) 6,575.00
Sub-Total for F.1 - As Submitted 138,075.00
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 174,155.66
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 20,898.68
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 13,932.45
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 10,449.34
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 219,436.13
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1003(1)a1 Ceiling (4.5mm Fiber Cement Board on Metal Frame with Air Vent)
Unit of Measurement : m²
Output per hour - As Submitted : 1.243
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 1.00 65.55 65.55
Skilled Laborer 2 2.00 47.62 190.48
Unskilled Laborer 2 2.00 36.75 147.00
Sub-Total for A.1 - As Submitted 403.03
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Minor Tools (10% of Labor Cost) 40.30
Sub-Total for B.1 - As Submitted 40.30
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 443.33
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 1.24
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 356.66
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Fiber Cement Board (4.5mm thk.) pc 0.37 360.00 131.40
Metal Double Furring Channels pc 1.13 130.00 147.03
Metal Carrying Channels pc 0.36 150.00 53.55
Rod Suspension Hanger with adjustment spring pc 1.00 80.00 80.00
Preformed Wire Clip pc 6.00 20.00 120.00
Metal Wall Angle pc 0.24 100.00 23.80
Blind Rivets pc 14.00 1.50 21.00
1" Flat Head Metal Screw pc 4.00 3.00 12.00
Wooden Ceiling Ventilator set 0.030 245.00 7.38
Sub-Total for F.1 - As Submitted 596.16
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 952.82
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 114.34
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 76.23
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 57.17
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 1,200.56
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1003(17) Carpentry and Joinery Works (Blackboard)
Unit of Measurement : L.S.
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Installation
Foreman 1 13.30 65.55 872.12
Skilled Laborer 2 20.00 47.62 1,904.80
Unskilled Laborer 2 20.00 36.75 1,470.00
Sub-Total for A.1 - As Submitted 4,246.92
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Minor Tools (10% of Labor Cost) 424.69
Sub-Total for B.1 - As Submitted 424.69
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 4,671.61
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 4,671.61
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Blackboard set 4.00 3100.00 12,400.00
Sub-Total for F.1 - As Submitted 12,400.00
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 17,071.61
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 2,048.59
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 1,365.73
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 1,024.30
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 21,510.23
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1018(1) Glazed Tiles and Trims
Unit of Measurement : m²
Output per hour - As Submitted : 1.365
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 1.00 65.55 65.55
Skilled Laborer 5 2.00 47.62 476.20
Unskilled Laborer 5 2.00 36.75 367.50
Sub-Total for A.1 - As Submitted 909.25
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Minor Tools (10% of Labor Cost) 90.93
Sub-Total for B.1 - As Submitted 90.93
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 1,000.18
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 1.37
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 732.73
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Glazed Tiles m² 1.050 740.00 777.00
Cement bags 0.325 240.00 78.00
Sand m³ 0.026 500.00 13.13
Tile Grout bags 0.125 240.00 30.00
Tile Adhesive (25 kg) bags 0.143 240.00 34.32
Consumables (3% of Materials Cost) 27.97
Sub-Total for F.1 - As Submitted 960.42
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 1,693.15
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 203.18
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 135.45
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 101.59
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 2,133.37
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1018(2) Unglazed Tiles
Unit of Measurement : m²
Output per hour - As Submitted : 1.95
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 1.00 65.55 65.55
Skilled Laborer 5 2.00 47.62 476.20
Unskilled Laborer 5 2.00 36.75 367.50
Sub-Total for A.1 - As Submitted 909.25
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Minor Tools (10% of Labor Cost) 90.93
Sub-Total for B.1 - As Submitted 90.93
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 1,000.18
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 1.95
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 512.91
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Unglazed Tiles m² 1.050 850.00 892.50
Cement bags 0.325 240.00 78.00
Sand m³ 0.026 500.00 13.13
Tile Grout bags 0.125 240.00 30.00
Tile Adhesive (25 kg) bags 0.125 240.00 30.00
Consumables (3% of Materials Cost) 31.31
Sub-Total for F.1 - As Submitted 1,074.93
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 1,587.84
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 190.54
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 127.03
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 95.27
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 2,000.68
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1027(1) Plain Cement Plaster Finish
Unit of Measurement : m²
Output per hour - As Submitted : 7.125
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 1.00 65.55 65.55
Skilled Laborer 2 2.00 47.62 190.48
Unskilled Laborer 4 2.00 36.75 294.00
Sub-Total for A.1 - As Submitted 550.03
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Minor Tools (10% of Labor Cost) 55.00
Sub-Total for B.1 - As Submitted 55.00
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 605.03
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 7.13
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 84.92
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Portland Cement bags 0.330 240.00 79.20
3
Sand m 0.027 500.00 13.25
Sub-Total for F.1 - As Submitted 92.45
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 177.37
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 21.28
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 14.19
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 10.64
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 223.48
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1021(1)c Plain Cement Finish with Floor Hardener
Unit of Measurement : m²
Output per hour - As Submitted : 5.95
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 1.00 65.55 65.55
Skilled Laborer 1 1.00 47.62 47.62
Unskilled Laborer 3 2.00 36.75 220.50
Sub-Total for A.1 - As Submitted 333.67
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Minor Tools (10% of Labor Cost) 33.37
Sub-Total for B.1 - As Submitted 33.37
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 367.04
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 5.95
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 61.69
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Portland Cement bag 0.726 240.00 174.24
3
Sand m 0.055 500.00 27.50
Floor Hardener bag 0.050 240.00 12.00
Sub-Total for F.1 - As Submitted 213.74
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 275.43
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 33.05
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 22.03
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 16.53
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 347.04
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1038(1) Reflective Insulation
Unit of Measurement : m²
Output per hour - As Submitted : 5.56
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 1.00 65.55 65.55
Skilled Laborer 2 1.75 47.62 166.67
Unskilled Laborer 2 1.75 36.75 128.63
Sub-Total for A.1 - As Submitted 360.85
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Minor Tools (10% of Labor Cost) 36.08
Sub-Total for B.1 - As Submitted 36.08
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 396.93
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 5.56
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 71.39
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Reflective Insulation 10mm thk. m² 1.00 135.00 135.00
Consumables (5% of material cost) 6.75
Sub-Total for F.1 - As Submitted 141.75
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 213.14
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 25.58
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 17.05
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 12.79
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 268.56
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1053(3)a1 38mm dia. G.I.Pipe Railing
Unit of Measurement : m
Output per hour - As Submitted : 6.255
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 1.00 65.55 65.55
Skilled Laborer 1 1.00 47.62 47.62
Unskilled Laborer 2 1.00 36.75 73.50
Sub-Total for A.1 - As Submitted 186.67
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Welding Machine 1 0.75 391.00 293.25
Cutting Outfit 1 0.25 45.45 11.36
Minor Tools (10% of labor cost) 18.67
Sub-Total for B.1 - As Submitted 323.28
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 509.95
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 6.255
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 81.53
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
38 mm dia. G.I. Pipe Sched. 40 x 6m pc 0.330 1200.00 396.00
Welding Rod kg 0.015 120.00 1.80
Consumables (5% of material cost) 19.89
Sub-Total for F.1 - As Submitted 417.69
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 499.22
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 59.91
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 39.94
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 29.95
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 629.01
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1053(3)a2 50mm dia. G.I.Pipe Handrail Fully Welded on Vertical Railing on 19mm bar Stiffener
Unit of Measurement : m
Output per hour - As Submitted : 6.255
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 1.00 65.55 65.55
Skilled Laborer 1 1.00 47.62 47.62
Unskilled Laborer 2 1.00 36.75 73.50
Sub-Total for A.1 - As Submitted 186.67
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Welding Machine 1 0.75 391.00 293.25
Cutting Outfit 1 0.25 45.45 11.36
Minor Tools (10% of labor cost) 18.67
Sub-Total for B.1 - As Submitted 323.28
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 509.95
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 6.255
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 81.53
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
50 mm dia. G.I. Pipe Sched. 40 x 6m pcs 1.000 1700.00 1,700.00
19mm bar kg 6.612 52.00 343.84
Welding Rod kg 0.015 120.00 1.80
Consumables (5% of material cost) 102.28
Sub-Total for F.1 - As Submitted 2,147.92
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 2,229.45
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 267.53
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 178.36
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 133.77
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 2,809.11
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1032(1)a Painting Works (Masonry/Concrete)
Unit of Measurement : m²
Output per hour - As Submitted : 2.10
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 1.00 65.55 65.55
Skilled Laborer 2 1.50 47.62 142.86
Unskilled Laborer 2 1.75 36.75 128.63
Sub-Total for A.1 - As Submitted 337.04
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Minor Tools (10% of Labor Cost) 33.70
Sub-Total for B.1 - As Submitted 33.70
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 370.74
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 2.10
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 176.54
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Concrete Neutralizer gal 0.080 311.00 24.88
Concrete Sealer/Primer gal 0.040 625.00 25.00
Patching Compound gal 0.050 550.00 27.50
Semi Gloss Latex (two coats) gal 0.080 480.00 38.40
Consumables (5% of Materials Cost) 5.79
Sub-Total for F.1 - As Submitted 121.57
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 298.11
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 35.77
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 23.85
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 17.89
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 375.62
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1032(1)b Painting Works (Wood)
Unit of Measurement : m²
Output per hour - As Submitted : 1.89
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 1.00 65.55 65.55
Skilled Laborer 2 1.50 47.62 142.86
Unskilled Laborer 2 1.75 36.75 128.63
Sub-Total for A.1 - As Submitted 337.04
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Minor Tools (10% of Labor Cost) 33.70
Sub-Total for B.1 - As Submitted 33.70
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 370.74
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 1.89
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 196.16
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Glazzing Putty gal 0.050 550.00 27.50
Flat Wall Enamel gal 0.040 600.00 24.00
Enamel Quick Dry gal 0.04 600.00 24.00
Paint Thinner gal 0.01 200.00 2.00
Consumables (5% of Materials Cost) 3.88
Sub-Total for F.1 - As Submitted 81.38
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 277.53
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 33.30
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 22.20
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 16.65
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 349.69
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1032(1)c Painting Works (Steel)
Unit of Measurement : m²
Output per hour - As Submitted : 2.00
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 1.00 65.55 65.55
Skilled Laborer 2 1.50 47.62 142.86
Unskilled Laborer 2 1.75 36.75 128.63
Sub-Total for A.1 - As Submitted 337.04
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Minor Tools (10% of Labor Cost) 33.70
Sub-Total for B.1 - As Submitted 33.70
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 370.74
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 2.00
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 185.37
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Red Oxide Primer gal 0.040 430.00 17.20
Enamel Paint gal 0.100 600.00 60.00
Paint thinner L 0.25 200.00 50.00
Consumables (5% of Materials Cost) 6.36
Sub-Total for F.1 - As Submitted 133.56
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 318.93
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 38.27
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 25.51
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 19.14
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 401.85
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1003(11)a1 Fiber Cement Fascia Board
Unit of Measurement : m
Output - As Submitted : 3.60
Output - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 0.50 65.55 32.78
Skilled Laborer 1 0.50 47.62 23.81
Sub-Total for A.1 - As Submitted 56.59
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Minor Tools (10 % of Labor Cost) 5.66
Sub-Total for B.1 - As Submitted 5.66
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 62.24
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output - As Submitted 3.60
D.2 Output - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 17.29
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
2-12 x 300mm Fiber Cement Board m 1.000 145.00 145.00
1" Metal Screws pc. 12.00 3.00 36.00
Consumables (5% of Materials Cost) 9.05
Sub-Total for F.1 - As Submitted 190.05
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 207.34
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 24.88
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 16.59
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 12.44
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 261.25
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5mm thk.
Unit of Measurement : m²
Output per hour - As Submitted : 2.076
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 1.00 65.55 65.55
Skilled Laborer 1 1.00 47.62 47.62
Unskilled Laborer 2 1.00 36.75 73.50
Sub-Total for A.1 - As Submitted 186.67
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Minor Tools (10% of Labor Cost) 18.67
Sub-Total for B.1 - As Submitted 18.67
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 205.34
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 2.08
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 98.91
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Prepainted Corrugated Metal Sheets ( Long 2
m 1.05 250.00 262.50
Span,0.5mm thk)
J-bolt with washers pc 10.00 7.00 70.00
Consumables (3% of Materials Cost) 9.98
Sub-Total for F.1 - As Submitted 342.48
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 441.38
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 52.97
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 35.31
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 26.48
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 556.15
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll)
Unit of Measurement : m
Output per hour - As Submitted : 10.00
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 1.00 65.55 65.55
Skilled Laborer 1 1.00 47.62 47.62
Unskilled Laborer 1 1.00 36.75 36.75
Sub-Total for A.1 - As Submitted 149.92
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Minor Tools (10% of Labor Cost) 14.99
Sub-Total for B.1 - As Submitted 14.99
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 164.91
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 10.00
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 16.49
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Ridge Roll m 1.05 168.00 176.40
Blind Rivets pc 19.00 1.50 28.50
Consumables (3% of Materials Cost) 6.15
Sub-Total for F.1 - As Submitted 211.05
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 227.54
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 27.30
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 18.20
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 13.65
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 286.70
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1013(2)b Fabricated Metal Roofing Accessory (Flashing)
Unit of Measurement : m
Output per hour - As Submitted : 10.00
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 1.00 65.55 65.55
Skilled Laborer 1 1.00 47.62 47.62
Unskilled Laborer 1 1.00 36.75 36.75
Sub-Total for A.1 - As Submitted 149.92
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Minor Tools (10% of Labor Cost) 14.99
Sub-Total for B.1 - As Submitted 14.99
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 164.91
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 10.00
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 16.49
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Flashing m 1.05 168.00 176.40
Blind Rivets pc 19.00 1.50 28.50
Consumables (3% of Materials Cost) 6.15
Sub-Total for F.1 - As Submitted 211.05
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 227.54
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 27.30
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 18.20
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 13.65
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 286.70
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1013(2)c Fabricated Metal Roofing Accessory (Gutter)
Unit of Measurement : m
Output per hour - As Submitted : 11.80
Output per hour - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 1.00 65.55 65.55
Skilled Laborer 1 1.00 47.62 47.62
Unskilled Laborer 1 1.00 36.75 36.75
Sub-Total for A.1 - As Submitted 149.92
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Minor Tools (10% of Labor Cost) 14.99
Sub-Total for B.1 - As Submitted 14.99
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 164.91
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output per hour - As Submitted 11.80
D.2 Output per hour - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 13.98
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Gutter (0.6 mm) m 1.00 168.00 168.00
12" x 1" Plain GI Strap pc 3.00 40.00 120.00
Blind Rivets pc 16.00 1.50 24.00
Consumables (3% of Materials Cost) 9.36
Sub-Total for F.1 - As Submitted 321.36
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 335.34
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 40.24
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 26.83
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 20.12
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 422.52
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1047(2)a Structural Steel (Trusses)
Unit of Measurement : kg
Output - As Submitted : 85.00
Output - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Fabrication
Foreman 1 1.00 65.55 65.55
Skilled Laborer 2 1.00 47.62 95.24
Unskilled Laborer 2 1.00 36.75 73.50
Erection
Skilled Laborer 3 0.49 47.62 70.00
Unskilled Laborer 3 0.49 36.75 54.02
Sub-Total for A.1 - As Submitted 358.31
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Welding Machine 1 0.75 391.00 293.25
Cutting Outfit 1 0.25 45.45 11.36
Truck Mounted Crane (20-25 mt) 1 0.49 1631.00 799.19
Minor Tools (10 % of Labor Cost) 35.83
Sub-Total for B.1 - As Submitted 1,139.63
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 1,497.95
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output - As Submitted 85.00
D.2 Output - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 17.62
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Structural Steel Truss kg 1.000 52.00 52.00
Acetylene kg 0.011 65.00 0.72
Oxygen kg 0.022 45.00 0.99
Welding Rod kg 0.020 120.00 2.40
Consumables (5% of Materials Cost) 2.81
Sub-Total for F.1 - As Submitted 58.91
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 76.53
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 9.18
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 6.12
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 4.59
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 96.43
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1047(2)b Structural Steel (Purlins)
Unit of Measurement : kg
Output - As Submitted : 90.45
Output - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 1.00 65.55 65.55
Skilled Laborer 2 1.00 47.62 95.24
Unskilled Laborer 4 1.00 36.75 147.00
Sub-Total for A.1 - As Submitted 307.79
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Welding Machine 2 1 391.00 782.00
Minor Tools (10 % of Labor Cost) 30.78
Sub-Total for B.1 - As Submitted 812.78
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 1,120.57
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output - As Submitted 90.45
D.2 Output - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 12.39
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Structural Steel Purlins kg 1.050 52.00 54.60
Welding Rod kg 0.020 120.00 2.40
Consumables (5% of Materials Cost) 2.85
Sub-Total for F.1 - As Submitted 59.85
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 72.24
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 8.67
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 5.78
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 4.33
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 91.02
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1047(6) Metal Structure Accessories (Steel Plates)
Unit of Measurement : kg
Output - As Submitted : 12.995
Output - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 1.00 65.55 65.55
Skilled Laborer 1 1.00 47.62 47.62
Unskilled Laborer 1 1.00 36.75 36.75
Sub-Total for A.1 - As Submitted 149.92
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Minor Tools (10 % of Labor Cost) 14.99
Sub-Total for B.1 - As Submitted 14.99
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 164.91
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output - As Submitted 13.00
D.2 Output - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 12.69
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Steel Plate m 1.05 52.00 54.60
Consumables (3% of Materials Cost) 1.64
Sub-Total for F.1 - As Submitted 56.24
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 68.93
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 8.27
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 5.51
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 4.14
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 86.85
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1047(3)c Metal Structure Accessories (Turnbuckle)
Unit of Measurement : pc
Output - As Submitted : 1.00
Output - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 0.15 65.55 9.83
Skilled Laborer 1 0.15 47.62 7.14
Unskilled Laborer 1 0.15 36.75 5.51
Sub-Total for A.1 - As Submitted 22.49
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Minor Tools (10 % of Labor Cost) 2.25
Sub-Total for B.1 - As Submitted 2.25
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 24.74
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output - As Submitted 1.00
D.2 Output - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 24.74
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Standard Turnbuckle pc. 1.00 185.00 185.00
Sub-Total for F.1 - As Submitted 185.00
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 209.74
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 25.17
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 16.78
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 12.58
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 264.27
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1047(7)b Metal Structure Accessories (Sagrods)
Unit of Measurement : kg
Output - As Submitted : 12.995
Output - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 1.00 65.55 65.55
Skilled Laborer 1 1.00 47.62 47.62
Unskilled Laborer 1 1.00 36.75 36.75
Sub-Total for A.1 - As Submitted 149.92
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Minor Tools (10 % of Labor Cost) 14.99
Sub-Total for B.1 - As Submitted 14.99
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 164.91
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output - As Submitted 13.00
D.2 Output - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 12.69
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Sagrod with nuts and bolts kg 1.05 31.00 32.55
Sub-Total for F.1 - As Submitted 32.55
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 45.24
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 5.43
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 3.62
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 2.71
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 57.00
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1047(4) Metal Structure Accessories (Crossbracing)
Unit of Measurement : kg
Output - As Submitted : 12.995
Output - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 1.00 65.55 65.55
Skilled Laborer 1 1.00 47.62 47.62
Unskilled Laborer 1 1.00 36.75 36.75
Sub-Total for A.1 - As Submitted 149.92
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Minor Tools (10 % of Labor Cost) 14.99
Sub-Total for B.1 - As Submitted 14.99
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 164.91
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output - As Submitted 13.00
D.2 Output - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 12.69
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Cross Bracing kg 1.05 37.00 38.85
Consumables (3% of Materials Cost) 1.17
Sub-Total for F.1 - As Submitted 40.02
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 52.71
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 6.32
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 4.22
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 3.16
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 66.41
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1047(1) Structural Steel (Fire Escape)
Unit of Measurement : L.S.
Output - As Submitted : 1.00
Output - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 73.57 65.55 4,822.25
Skilled Laborer 1 73.57 47.62 3,503.21
Unskilled Laborer 1 73.57 36.75 2,703.55
Sub-Total for A.1 - As Submitted 11,029.00
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Welding Machine 1 73.57 391.00 28,764.27
Minor Tools (10 % of Labor Cost) 1,102.90
Sub-Total for B.1 - As Submitted 29,867.17
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 40,896.17
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output - As Submitted 1.00
D.2 Output - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 40,896.17
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
4" G.I. Pipe pcs. 2.13 3800.00 8,106.67
65 x 65 x 6mm Angular Bar kgs. 113.47 52.00 5,900.54
12mm Anchor Bolts with Nuts and Washer kgs. 1.64 160.00 262.40
C 8x13 (Stringer) kgs. 407.56 52.00 21,193.12
50 x 50 x 6mm Angular Bar kgs. 74.20 52.00 3,858.40
38 x 38 x 4.5mm Angular Bar kgs. 23.05 52.00 1,198.60
LC 255 x 90 x 2.5mm Stair Thread kgs. 163.98 52.00 8,526.96
Checkered Plate kgs. 136.56 52.00 7,100.91
25 x 25 x 4.5mm Angular Bar kgs. 0.68 52.00 35.10
Gusset Plate kgs. 33.08 52.00 1,720.16
16mm dia. Round Bar (Plain) kgs. 1.78 37.00 65.71
Welding Rod kgs. 19.12 120.00 2,294.40
Acetylene kgs. 10.52 65.00 683.54
Oxygen kgs. 21.03 45.00 946.44
Sub-Total for F.1 - As Submitted 61,892.95
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 102,789.13
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 12,334.70
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 8,223.13
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 6,167.35
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 129,514.30
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1001(6)a Catch Basin
Unit of Measurement : each
Output - As Submitted : 1.00
Output - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Foreman 1 1.00 65.55 65.55
Skilled Laborer 1 1.00 47.62 47.62
Unskilled Laborer 1 1.00 36.75 36.75
Sub-Total for A.1 - As Submitted 149.92
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Minor Tools (10 % of Labor Cost) 14.99
Sub-Total for B.1 - As Submitted 14.99
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 164.91
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output - As Submitted 1.00
D.2 Output - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 164.91
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
10 mm dia x 6.0 Reinforcing Steel Bars kg 8.63 35.00 302.05
concrete m³ 0.07 3740.00 261.80
masonry m² 0.80 10.00 8.00
plaster m² 1.76 84.25 148.28
Sub-Total for F.1 - As Submitted 720.13
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 885.04
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 106.21
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 70.80
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 53.10
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 1,115.15
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1001(8) Sewer Line Works
Unit of Measurement : L.S.
Output - As Submitted : 1.00
Output - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Plumber 1 28.00 65.55 1,835.40
Skilled Laborer 1 28.00 47.62 1,333.36
Unskilled Laborer 2 28.00 36.75 2,058.00
Sub-Total for A.1 - As Submitted 5,226.76
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Minor Tools (10 % of Labor Cost) 522.68
Sub-Total for B.1 - As Submitted 522.68
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 5,749.44
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output - As Submitted 1.00
D.2 Output - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 5,749.44
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
uPVC Pipe, 100mm Ø x 3m, S-1000 lgths. 9.00 583.00 5,247.00
uPVC Pipe, 75mm Ø x 3m, S-1000 VENT lgths. 2.00 434.00 868.00
uPVC Pipe, 50mm Ø x 3m, S-1000 lgths. 14.00 291.00 4,074.00
Elbow, 50mm dia. x 90 deg. Bend pc 9.00 26.00 234.00
Elbow, 100mm dia. x 90 deg. bend pc 4.00 81.00 324.00
WYE, 100mm Ø pc 6.00 126.00 756.00
WYE Reducer, 100mm Ø x 75mm Ǿ pc 1.00 120.00 120.00
WYE Reducer, 100mm Ø x 50mm Ǿ pc 9.00 100.00 900.00
uPVC Tee 100mm dia.x 100mm dia. pc 4.00 135.00 540.00
uPVC Tee 50mm dia.x50mm dia. pc 11.00 37.00 407.00
uPVC Tee Reducer, 75mm dia.x 50mm dia. pc 1.00 94.00 94.00
Clean Out w/ Cover, 100mm dia. pc 9.00 59.00 531.00
Clean out with cover, 75mm dia. pc 1.00 36.00 36.00
P-trap, 50mm dia. pc 24.00 107.00 2,568.00
PVC Solvent, 400cc cans 5.00 190.00 950.00
Sub-Total for F.1 - As Submitted 17,649.00
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 23,398.44
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 2,807.81
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 1,871.87
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 1,403.91
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 29,482.03
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1001(9) Storm Drainage and Downspout
Unit of Measurement : L.S.
Output - As Submitted : 1.00
Output - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Plumber 1 36.00 65.55 2,359.80
Skilled Laborer 4 36.00 47.62 6,857.28
Unskilled Laborer 4 36.00 36.75 5,292.00
Sub-Total for A.1 - As Submitted 14,509.08
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Minor Tools (10 % of Labor Cost) 1,450.91
Sub-Total for B.1 - As Submitted 1,450.91
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 15,959.99
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output - As Submitted 1.00
D.2 Output - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 15,959.99
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
PVC 150mm dia x 3m lgths. 15.00 921.00 13,815.00
PVC Pipe, 75mm Ø x 3m, S-1000 lgths. 26.00 434.00 11,284.00
Elbow, 75mm dia. x 45 deg. Bend pcs. 24.00 50.00 1,200.00
PVC Solvent, 400cc cans 2.00 190.00 380.00
Roof Drain (Dome-type strainer) pcs. 12.00 1500.00 18,000.00
Sub-Total for F.1 - As Submitted 44,679.00
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 60,638.99
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 7,276.68
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 4,851.12
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 3,638.34
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 76,405.12
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1002(8) Plumbing Fixtures
Unit of Measurement : L.S.
Output - As Submitted : 1.00
Output - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Plumber 1 167.56 65.55 10,983.78
Skilled Laborer 2 167.56 47.62 15,958.73
Unskilled Laborer 4 167.56 36.75 24,631.81
Sub-Total for A.1 - As Submitted 51,574.32
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Minor Tools (10 % of Labor Cost) 5,157.43
Sub-Total for B.1 - As Submitted 5,157.43
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 56,731.76
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output - As Submitted 1.00
D.2 Output - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 56,731.76
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Plumbing Fixtures
Water Closet complete w/ fittings & accs. sets 6.00 7800.00 46,800.00
Wall Hung Lavatory, complete w/ fittings & accs. sets 1.00 7000.00 7,000.00
Floor Drain pcs 24.00 280.00 6,720.00
Bronze Faucet pcs 6.00 165.00 990.00
Gate Valve 32mm sets 2.00 627.00 1,254.00
Mirror sq.ft. 12.00 5379.20 64,550.40
Urinal (trough) set 2.00 9000.00 18,000.00
Concrete Sink 3 faucet set 1.00 6028.00 6,028.00
Concrete Sink 1 faucet set 3.00 2895.00 8,685.00
Gate Valve 50mm pcs 2.00 980.00 1,960.00
Gate Valve 20mm pcs 2.00 330.00 660.00
Check Valve 50mm pcs 1.00 954.00 954.00
PWD handrail set 1.00 4500.00 4,500.00
Consumables 8,405.07
Septic Vault Type E
Reinforcing Bars Grade 40 kgs 528.98 35.00 18,514.30
Concrete m³ 5.28 3740.00 19,747.20
Plaster m² 57.56 84.25 4,849.43
Sahara bag 139.00 45.00 6,255.00
6 chb m² 5.00 12.00 60.00
4 chb m² 2.50 10.00 25.00
Sub-Total for F.1 - As Submitted 225,957.40
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 282,689.16
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 33,922.70
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 22,615.13
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 16,961.35
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 356,188.34
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1002(28) Cold Water Lines
Unit of Measurement : L.S.
Output - As Submitted : 1.00
Output - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Plumber 1 3.25 65.55 213.04
Skilled Laborer 1 3.25 47.62 154.77
Unskilled Laborer 2 3.25 36.75 238.88
Sub-Total for A.1 - As Submitted 606.68
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Minor Tools (10 % of Labor Cost) 60.67
Sub-Total for B.1 - As Submitted 60.67
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 667.35
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output - As Submitted 1.00
D.2 Output - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 667.35
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
PPRC Pipe, 20mm dia. X 4m, PN 16 lgths 5.00 187.02 935.10
PPRC Pipe, 25mm dia. X 4m, PN 16 lgths 2.00 279.63 559.26
PPRC Pipe, 32mm dia. X 4m, PN 16 lgths 4.00 456.36 1,825.44
PPRC Elbow, 20mm Ǿ pc 3.00 17.16 51.48
PPRC Elbow, 25mm Ǿ pc 1.00 27.72 27.72
PPRC Elbow, 32mm Ǿ pc 2.00 43.56 87.12
PPRC Tee, 20mm Ǿ pc 5.00 21.12 105.60
PPRC Reducer, 25mm Ǿ x 20mm Ǿ pc 2.00 29.00 58.00
PPRC Reducer, 32mm Ǿ x 25mm Ǿ pc 2.00 34.00 68.00
Sub-Total for F.1 - As Submitted 3,717.72
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 4,385.07
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 526.21
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 350.81
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 263.10
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 5,525.18
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1100(30) Conduits, Boxes and Fittings
Unit of Measurement : L.S.
Output - As Submitted : 1.00
Output - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Electrician 1 30.00 65.55 1,966.50
Skilled Laborer 1 56.80 47.62 2,704.82
Unskilled Laborer 1 56.80 36.75 2,087.40
Sub-Total for A.1 - As Submitted 6,758.72
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Minor Tools (10 % of Labor Cost) 675.87
Sub-Total for B.1 - As Submitted 675.87
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 7,434.59
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output - As Submitted 1.00
D.2 Output - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 7,434.59
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
20mmØ PVC conduit length 143.00 92.00 13,156.00
25mmØ PVC pipe length 2.00 120.00 240.00
40mmØ RSC pipe length 4.00 1143.30 4,573.20
20mmØ PVC adapter pc 265.00 8.00 2,120.00
25mmØ PVC Adapter pc 2.00 14.00 28.00
20mmØ Locknut & Bushing pc 265.00 10.00 2,650.00
40mmØ RSC Elbow pc 2.00 301.00 602.00
25mmØ Locknut & Bushing pc 2.00 12.00 24.00
20mmØ liquidtight flexible metal conduit m. 3.00 20.00 60.00
20mmØ Connector pc 2.00 10.00 20.00
Utility box, deep type pc 45.00 30.00 1,350.00
Junction box, deep type pc 60.00 31.00 1,860.00
40mmØ entrance cap pc 1.00 301.00 301.00
16mmØX2.4m ground rod w/ connector pc 2.00 1200.00 2,400.00
Sub-Total for F.1 - As Submitted 29,384.20
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 36,818.79
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 4,418.25
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 2,945.50
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 2,209.13
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 46,391.67
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1101(42) Wires and Wiring Devices
Unit of Measurement : L.S.
Output - As Submitted : 1.00
Output - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Electrician 1 25.00 65.55 1,638.75
Skilled Laborer 1 62.00 47.62 2,952.44
Unskilled Laborer 1 62.00 36.75 2,278.50
Sub-Total for A.1 - As Submitted 6,869.69
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Minor Tools (10 % of Labor Cost) 686.97
Sub-Total for B.1 - As Submitted 686.97
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 7,556.66
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output - As Submitted 1.00
D.2 Output - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 7,556.66
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
2.0mm2 TW wire,stranded m 60.00 24.00 1,440.00
3.5mm2 THWN wire,stranded m 910.00 24.00 21,840.00
3.5mm2 TW wire,stranded m 455.00 24.00 10,920.00
5.5mm2 THWN wire,stranded m 18.00 37.00 666.00
5.5mm2 TW wire,stranded m 21.00 37.00 777.00
14.0mm2 TW wire,stranded m 12.00 95.00 1,140.00
14mm2 THWN wire,stranded m 12.00 95.00 1,140.00
38mm2 THWN wire,stranded m 24.00 260.00 6,240.00
one gang switch set 9.00 90.00 810.00
two gang switch set 7.00 110.00 770.00
one gang 3 way switch set 8.00 150.00 1,200.00
-
duplex C.O. grounding type, 15A, 250V set 8.00 330.00 2,640.00
duplex C.O. grounding type, 15A, 250V, WP set 2.00 420.00 840.00
KWHR meter round with base set 1.00 2200.00 2,200.00
Tape, bolt&nut, mica tube, terminal lugs, JB
lot 1.00 4500.00 4,500.00
cover clamps, screw and anchors
Sub-Total for F.1 - As Submitted 57,123.00
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 64,679.66
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 7,761.56
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 5,174.37
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 3,880.78
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 81,496.37
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1102(27) Panel Load Center, Switch Gear and Panelboards
Unit of Measurement : L.S.
Output - As Submitted : 1.00
Output - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Electrician 1 6.50 65.55 426.08
Skilled Laborer 1 6.50 47.62 309.53
Unskilled Laborer 2 6.50 36.75 477.75
Sub-Total for A.1 - As Submitted 1,213.36
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Minor Tools (10 % of Labor Cost) 121.34
Sub-Total for B.1 - As Submitted 121.34
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 1,334.69
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output - As Submitted 1.00
D.2 Output - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 1,334.69
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
LPA - Flush Mounted, NEMA 1 Enclosure
set 1 19459.70 19,459.70
w/ Ground Terminal
Main: 100at, 100af, 2p, 240v, 18KAIC
Branches: 4 - 15at, 50af, 2p, 230v
7 - 20at, 50af, 2p, 240v
2- 30at, 50af, 2p, 240v
1- 30at, 50af, 2p, 240v

30at, 50af, 2p, 240v, in NEMA 3R enclosure set 2.00 1200.00 2,400.00
20at, 50af, 2p, 240v, in NEMA 3R enclosure set 1.00 1200.00 1,200.00
40at, 50af, 2p, 240v, in NEMA 3R enclosure set 1.00 1200.00 1,200.00
Sub-Total for F.1 - As Submitted 24,259.70
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 25,594.39
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 3,071.33
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 2,047.55
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 1,535.66
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 32,248.93
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1103(1) Lighting Fixtures
Unit of Measurement : L.S.
Output - As Submitted : 1.00
Output - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Electrician 1 36.51 65.55 2,393.08
Skilled Laborer 1 36.51 47.62 1,738.49
Unskilled Laborer 2 36.51 36.75 2,683.31
Sub-Total for A.1 - As Submitted 6,814.88
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Minor Tools (10 % of Labor Cost) 681.49
Sub-Total for B.1 - As Submitted 681.49
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 7,496.37
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output - As Submitted 1.00
D.2 Output - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 7,496.37
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
2 x 36 watts FL fixture box type w/ canopy base
and stem 1.5 ft. (450mm) length similar to amco set 16.00 1236.00 19,776.00
AP-113-1.5 or aproved equal
2 x 36 watts FL fixture set 8.00 600.00 4,800.00
1 x 36 watts FL fixture box type set 13.00 280.00 3,640.00
1 - 18 watts CFL w/ medium base keyless type
set 9.00 150.00 1,350.00
porcelain receptacle
Wall Fan with control Switch set 8.00 1200.00 9,600.00
Sub-Total for F.1 - As Submitted 39,166.00
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 46,662.37
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 5,599.48
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 3,732.99
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 2,799.74
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 58,794.59
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1202(1) Automatic Water Sprinkler System
Unit of Measurement : L.S.
Output - As Submitted : 1.00
Output - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Electrician 1 221.70 65.55 14,532.44
Skilled Laborer 2 221.70 47.62 21,114.71
Unskilled Laborer 3 221.70 36.75 24,442.43
Sub-Total for A.1 - As Submitted 60,089.57
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Minor Tools (10 % of Labor Cost) 6,008.96
Sub-Total for B.1 - As Submitted 6,008.96
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 66,098.52
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output - As Submitted 1.00
D.2 Output - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 66,098.52
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Automatic Water Sprinkler System
B.I. Pipe 65mm dia lm 20.00 708.00 14,160.00
Fittings (Elbow, Tee, Reducer, etc) l.s. 1.00 1,416.00 1,416.00
Fire Extinguisher, 10 lbs Capacity, Wall Mounted,
set 4.00 6,825.00 27,300.00
HCFC 123
Water Pumping System
Overhead Water Tank 2000 US Gal unit 1.00 167,000.00 167,000.00
20 liters Pressure Tank unit 1.00 8,500.00 8,500.00
Concrete m³ 15.45 3,740.00 57,783.00
Rebar kg 648.90 35.00 22,711.50
Plaster Finish m² 66.00 84.25 5,560.50
Cement Based Waterproofing bag 159.00 45.00 7,155.00
0.60 x 0.60 Manhole ea 2.00 21,000.00 42,000.00
End-Suction Centrifugal Water Pump, TDH 9m,
unit 2.00 23,500.00 47,000.00
0.5HP, 60GPM
Sub-Total for F.1 - As Submitted 400,586.00
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 466,684.52
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 56,002.14
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 37,334.76
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 28,001.07
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 588,022.50
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning&Design Section
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM POW-2015-01D-00
Item No./Description : 1208(1) Fire Alarm System
Unit of Measurement : L.S.
Output - As Submitted : 1.00
Output - As Evaluated :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


A.1 Labor
Skilled Laborer 1 23.00 47.62 1,095.26
Unskilled Laborer 1 23.00 36.75 845.25
Sub-Total for A.1 - As Submitted 1,940.51
A.2 Labor
-
Sub-Total for A.2 - As Evaluated -
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment
Minor Tools (10 % of Labor Cost) 194.05
Sub-Total for B.1 - As Submitted 194.05
B.2 Equipment
-
Sub-Total for B.2 - As Evaluated -
C.1 Total (A.1 + B.1) - As Submitted 2,134.56
C.2 Total (A.2 + B.2) - As Evaluated -
D.1 Output - As Submitted 1.00
D.2 Output - As Evaluated -
E.1 Direct Unit Cost (C.1 / D.1) - As Submitted 2,134.56
E.2 Direct Unit Cost (C.2 / D.2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
Fire Alarm Control Panel set 1.00 800.00 800.00
Fire Alarm Bell set 2.00 1442.00 2,884.00
Manual Pull Station Switch set 2.00 1250.00 2,500.00
Sub-Total for F.1 - As Submitted 6,184.00
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 8,318.56
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 998.23
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 665.48
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 499.11
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 10,481.39
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -

Prepared by: Checked/Reviewed by:

RAMIL S. ISIT JONATHAN B. RAMOS


Architect II Engineer II
OIC-Chief, Planning & Design Section

Das könnte Ihnen auch gefallen