Beruflich Dokumente
Kultur Dokumente
TURA
TP-131
{NASA-CR-131200)
LANDING
Newbury
SYSTEM
Park, Calif.)
TIE
(Northrop
APOLLO
28
Ventura
p
PARACHUTE
Corp.,
__
N73-71907
Inclas !.
H
_I
U0/99 65643 ' _/
T. "_V. Knacke f
Northrop Ventura
El Centro, California
September 1968
"o
J
INTRODUCTION
suitable for water landing. In addition it provides, together with the Launch
Escape System, the means for safely landing the Apollo crew for all
mission abort cases prior to obtaining orbit. The Apollo parachute system
combined with advanced design and testing methods have created an out-
The system approach started with a design concept that defined aii
abort landings as operational cases and established the ground rule that no
was able to cope with the considerable command module weight increases
caused by normal design changes and the added safety measures dictated
NORTHROP VENTURA
All limit design cases of high dynamic pressures, large command module
oscillations and high loads are the result of abort cases, in particular,
landings are shown in Figure I and include the Apollo Command Module
(CM), the Launch Escape System (LES) with canards and pitch-over control
motors (PCM}, the boost protection cover (BTC),and the apex cover or
forward heat shield. The latter protects the parachute system located
outside the crew compartment in the upper part of the command module
LAUNCH ESCAPE
APEX COVER,
COMMAND MODULE
SERVICE MODULE
364 FT
5-|VB
2
_ORTHROPVI_'_TURA
details.
RECOVERY CONCEPT
The parachute landing system must assure safe landing for two
primary landing modes: (a) landing after completed mission; and (b) landings
by means of the launch escape system (LES) from the time the Apollo crew
second stage booster ignition. Above 300, 000 feet normal landings can
upon the altitude at which abort takes place: (a) Pad-Abort causes extensive
sequencing modes; and (c) high altitude abort results in maximum dynamic
system (LES) that provides the command module with safe vertical and
bility requirements for normal and abort mission landings. This creates
3
NORTHROP VENTURA
the need of sufficient time for failure sensing and for obtaining adequate
one considers the necessary thrust and time required to cope with a
systems exist which use the parachute as the primary means of transpor-
tation. These are, besides the Apollo spacecraft, the parachute systems
for the Mercury and Gemini spacecrafts and the paratrooper parachute.
All of these systems use the primary and back-up parachute concept.
PARACHUTE SYSTEM
The final parachute system selected for the Apollo command module
deceleration and stabilization, with only one parachute being required and
the second parachute providing the back-up mode. Deploying both para-
parachutes; two of which will provide the rate of descent necessary for
main parachute failures eliminated the necessity for a fourth main para-
chute. Again deploying all three parachutes precludes the need for a
failure sensor, saves time and altitude and establishes more favorable
landing conditions.
chute types for the Gemini and Mercury parachute landing systems.
4
NORTHROP V1Er|llJRA
Back -up
I I PiIot Chul*
Chute l
16.5-gt-Dia. Conical
Texlile Rtser
Ribbon Parachute
One-Step Re_fi_g
t
l_oEue
_ _
_.IP.-- IZZ '
t
1-} _Deploymenl _
" g
Z-Step Reefing
\ L
\l
Textile
Riser
" 1494
4-PLy
Sleel Cabte
Zqo _ \ ]TO
_I_
mission is shown in Figure 3. The recovery sequence starts with the turning
off of the reaction control system and with the ejection of the apex cover at
to support apex cover removal and to prevent recontact between cover and
command module. The two drogue parachutes are mortar ejected, the
individual attach points provide for a command module hang angle of Z9.5
ordnance cutters and three pilot parachutes are mortar deployed simulta-
Chutes in turn extract the three main parachutes. The deployment sequence
5
NORTHROP VENTURA
, f
' "I"" / I
\ , J
/ I
! i l
Three Main Plr_chutes DroEue Chule s T_o DroKue ChuZes Apex Co, er Eiected 5tart Of
Extrlcted by Mortar Disconnected
Mortar Deployed At by l:Z'yro÷Thr_er _eco_ery
Dep|ol'ed Piloz Chatel T ÷ }.6Sec and 7.2-ff-dfa.
Three Pilot
Rin_ ._loz ParJchute Allitude: 25. 000 r_
Rate of Delcent Chules Mor_]r
Time, 0 .e¢ Velocity: 0.7 Mach
Vv -- 29 ft/.ec Deployed
approximately 300, 000 feet. Upon abort command the launch escape motor
fires and lifts ;:he CM off the Saturn booster. The pitch over motor and
boost protection cover, and docking probe separate followed by the time
abort, can select to override the drogue parachutes and to deploy the main
6
HORTHROPVENTURA
Clnardl
Abort |1 Sec
_'ct Tower
Probe
T_me
BPC + • Dockln|
]4 Sec
Dllconn_-ct _ '
25,000 feet and below 124 psf an automatic sequencing system deploys the
two drogue parachutes (normal reentry region in Figure 5). The astronaut
may deploy the drogue parachutes up to 40, 000 feet altitude if flight con-
of the drogue parachutes above 25,000 feet. Pad abort and low or medium
q = _I PSF
AR_RT R IF'C;T(3N
A LTTTUD'_
(1000 FT)
Z0
Z /zz.,',, .. a
I I | [ I i J
M ACH ,_0.
deployment by automatic control may occur in abort cases between 10, 000
to 18,000 feet dje to aneroid sensor lag and ascent and descent hysteresis.
during abort causes command module motions in pitch, roll and yaw.
8
t"lORTltROP V1EI_URA
SYSTEM APPROACH
reserve that permitted failure of one drogue and/or one main parachute
extent. A minimum factor of safety of 1.35 was defined for all components
Its complexity ?
k_fa i. Parachute
_O SM > zl.oonl>_.onn
marginal
(]] Flli_h! Mode h HiKh allit,lde ab:,rl, mlx|mul'_ _vnarfl_¢ _r_l_l?_ g, rlrnQlle discnnnec! and main par_rh,,r*
l0
NORTHROP VEHTURA
._v[N i rret_ w
_r tlewP¢_E_T e.e_uw
J_' %, 'c
L._ 11
ii ,_l. ,fT.._
• T
DESIGN CRITERIA
ground rules and design criteria with each case jointly agreed upon with
ll
NORTHF_OP VE_TURA
DESIGN LOADS
criteria indicates that the maximum drogue parachute and main parachute
design loads do not occur at normal reentry but at abort conditions com-
12
NORT_fROP VENTUFLA
following combinations :
These combinations not only affect the reefed parachute load but
all subsequent load stages as well. The maximum loads of the reefed
drogue and main parachutes are not caused by the same combination of
proving in tests that all parachute stages will withstand the ultimate load
13
F.'GRTHROPVENTI_RA
/ o
\
,01_ ° /r% "" _ ._o
h ."/ °. "R /_,
/J " _"/ \ 0 o
/ _- -_ R
i' / , ,,- /\o,,
/I _ / / -%, .---UL"_rMATE t.n,DS
2OTi • / /
h . _ / ro / % H,C,H*L''TUOEAeORT
'Tokg_:0":i_TE li_ / / / .oc,,MP,
I%
t_
//
/. /
/
r
'o Ill o
loads for both the drogue parachute and the main parachute are calculated
vehicles (ICTV) and a parachute test vehicle (PTV) that duplicated the
Apollo CM parachute deck but had a much smaller vehicle diameter were
to be duplicated in tests.
14
NORi'HROlI VI[NTURA
conditions.
ICTV's and PTV's were dropped from B-52 and B-66 aircraft, a
modified C-133 aircraft was used for dropping the boilerplate test vehicles.
tests of drogue and main parachutes at the same test mission. An Apollo
Figures 8 and 9.
15
NORTItRCP VE_ITU RA
Design load and ultimate load tests were conducted with single
and multiple drogue parachutes and main parachutes using ICTV's and PTV
test vehicles. Ultimate loads of the first reefed parachute stage can be
the dynamic pressure at the end of the first reefing stage always approaches
the same value independent of the starting point. This problem was solved
• It was found during these tests that the wake of the test vehicle
had a pronounced effect not only on the drag area of the drogue parachute
in the wake of the forebody but surprisingly also on the dynamic load
16
N_RH_ROP VEI_IJRA
various test vehicles the drogue parachute drag areas, the dynamic load
factor C K and typical parachute force traces. The turbulent wake not only
decreases the drag area but increases notably the load fluctuations and
thus the dynamic load factor. These data have to be taken into account in
order to predict what loads obtained behind an ICTV or PTV are equivalent
It was impossible to predict parachute test loads with the desired accuracy
of 5 percent. This requires not only proper load prediction methods but
cent.
]. 4
r_
r.., nar_t¢
L_cl
Factor
I.Z
t D []
].
CZ<
Drag
14
I
1
'
l-
°
Area
0 I
CD$ IZO
i i
(FT 2)
_00
"rime
I I
Diameter
II.q S.8
LO
(FT1
------_-- _ i
17
NORTHROP VENTURA
FAILURE TEST
and series drogue parachute and main parachute failures, main parachute
failure.
ENVIRONMENTAL TEST
and main parachutes for spaceflight as well as for reentry with follow-on
nor_nal landings. It was found that the main parachute temperature increased
to 140F ° after apex cover ejection from the hot air flowing around the heat
shield and streaming along the packed main parachutes. The resultant
ultimate load tests in the form of an equivalent higher test load. The results
test reports.
18
NORTHROP VENTURA
QUALIFICATION TESTS
boilerplate test vehicle and the spacecraft end item parachute system.
This included three normal reentry tests with variation in drogue parachute
deployment altitude and use of either two or one drogue parachute, the
deployment. Only one drogue Parachute was used in these tests in order
low altitude aborts using in one test, two drogue p_rachutes with minimum
time sequence for drogue parachute and main parachute deployment. The
than limit case dynamic pressure at main parachute opening. The two low
tests without introducing non-spacecraft type load links was not entirely
and the hot rear heat shield, and last but not least, the increase in CM
19
NORTHROP VE_;TURA
parachute and main parachute risers end in steel cables which are attached
steel cables were selected to avoid riser damage due to contact with the
hot heat shield in case of command module oscillations. The need for
small steel cable bending radii was solved by using four ply steel cables
swagged into common fittings for both the drogue and the main parachute
strain gages attached to the risers and are not part of spacecraft equipment.
%.
. +. ......
+:++:.:.:.].
j,-;-+._C
+_;.-- <: .,.].#+_+._,.
2O
NORTHROP VENTURA
kinking both riser ends are secured and the risers are coiled under tension
without twisting the ends; the risers are then cast in urethane foam. Upon
deployment the light foam disintegrates and the risers stretch without
the steel risers to bend and roll over the flower pot resulting in abrasion
bet_veen the Titanium flower pot collar and the steel cables. Surrounding
each individual steel cable with lead tubing helped to minimize this problem;
see Figure 13. All mortars are hermetically sealed and dual cartridges
CARTRIDGE
R F.STR [CTOR
OFFSET
ORIFICE
"0" RING
COVER NIGER
A_E_(BL¥
Zl
NORTHROP VENI[UFIA
parachute size and weight produced reaction forces upon mortar firing that
developed that maintained the required muzzle velocity for the heavier
drogue parachutes without increasing the reaction loads of the more power-
shown in the upper left hand corner of Figure 14 produce the typical
orifice has brass and aluminum inserts which burn away progressively and
allow more gas to enter the mortar tube. The aluminum insert keeps the
reasonably constant mortar tube pressure and maintains the mortar reac-
22
rtORTHFIOP VE_TURA
STAN_D _D ( FIXED}
Ol_ IFICE
_ P_ESgU_ E CURVE
/ \
STA_/t_Ai_D ¢)PTF_CE HYI!_ID ORIY|CE
reef, a reliability requirement introduced for the first time on the Apollo
design of the main parachute reefing system are shown in Figure 15, Two
reefing lines are used for the first stage, with each line having its individual
will not disreef the parachute; separation of both lines is required to dis-
reef the parachute to the second stage. The second stage has only one
reefing line with two cutters. Analysis and tests have proven that premature
rupture of the second stage reefing line will not result in destruction of the
parachute.
23 _
NORTHROP
VEI'_TLIRA.
"N Y'-,
RACH
were developed with both first stage lines passing through the same ring
opening. The slack part of the second stage reefing line is gathered with
a draw string of the same length as the first stage line; this draw string
approach avoids the problems of stowing and securing the second stage lipe.
segment and must maintain their highly compressed form throughout storage
and mission in order to assure a specific gap between the apex cover and
the packed parachute necessary for heat protection during and after reentry.
During the development cycle the hard packed main parachutes experienced
24
NORTHROP.VE_TURA
truncated cone form is maintained for a period of one year without growth
bays are restrained with daisy chain retainers on three sides, see Figure 16.
into the conical shaped bags are shown in Figure 17. The parachute, in
vacuum storage in the wooden former sealed with plastic film, ready for
25
_ORTXROP VE_TURA
:il
26
NORTHROP VENTURA
GONC LUSIONS
The ability to cope with all conceivable emergencies, full system redun-
development required the joint engineering efforts and skills of NASA MSC,
spacecraft landing system, the broad engineering spectrum and the out-
27