Beruflich Dokumente
Kultur Dokumente
0 THE EMPLOYER
14
2.0 The Employer
Sub-
If the Employer intends to make any material change to these
financial arrangements, or changes in the financial
situation, the Employer shall give a Notice to the Contractor with
supporting particulars.
If the Contractor:
(a) receives an instruction for Variation more than 10%, or accumulated
total of Variations exceeds 30% of the Accepted Contract Amount;
(b) does not receive payment in accordance with Sub-Clause 14.7
[Payment]; or
(c) becomes
arrangements of which the Contractor has not received a Notice
under this Sub-Clause,
the Contractor may request Employer to provide reasonable evidence
about the financial arrangements. 15
3.0 The Engineer
16
3.0 Engineer
New Sub-Clauses
FIDIC - 2017
17
3 Engineer
3.5 - Determination (FIDIC 1999)
18
3 Engineer
3.7 - Agreement or Determination (2017)
3.2- Determination (1999)
The Engineer
Agree or Determine 3.7 Agreement or Determination
20
3.7 Agreement or Determination (Cont.)
21
3.7 Agreement or Determination (Cont.)
3.7. 2 Determination
Within the time limit under Sub-Clause 3.7.3 [Time limits],
the Engineer shall give a Notice that it is a of the
, and shall describe the
determination in detail with reasons and detailed supporting
particulars.
FIDIC -
22
3.7 Agreement or Determination (Cont)
26
The Contractor
FIDIC 2017
FIDIC 1999
27
The Contractor
4.2 Performance Security
4.2.1 Bond shall be valid till Performance Bond
obligations issued and till clearing of the Site (11.11)
4.2.2 Claim under the - Four situations in FIDIC 99
Performance Security - Five situations in FIDIC 2017 - Failure
comply with the remedying defective
works off Site
4.2.3 Return of - One situations in FIDIC 99 [upon release
Performance Security of Performance Certificate)
- Two situations in FIDIC 2017
Upon termination of the Contract;
Sub-Clause 15.5 -
Convenience],
Sub-Clause 16.2 - Termination by Contractor,
Sub-Clause 18.5 - Optional Termination]
Sub-Clause 18.6 - Release from Performance
under the Law].
28
The Contractor
(new)
(e)
General Obligations
29
The Contractor
4.5 Training (new)
30
The Contractor
4.5 Co-operation
1999
Any such instruction shall constitute a Variation if and to
the extent that it causes the Contractor to incur
Unforeseeable Cost.
2017
If the Contractor suffers delay and/or incurs Cost as a result
of an instruction under this Sub-Clause, to the extent that
co-operation was Unforeseeable, the Contractor shall be
entitled subject to EOT and/or payment of such Cost Plus
Profit under Sub-Clause 20.2 [Claims For Payment and/or
EOT].
31
The Contractor
4.7 Setting Out
4.7.2 Errors
32
The Contractor
1999
4.9 Quality Assurance
2017
4.9 Quality Management and Compliance
Verification Systems
33
The Contractor
1999
4.12 Unforeseeable Physical Conditions
2017
4.12 Unforeseeable Physical Conditions
In this Sub-
and physical obstructions (natural or man-made
4.12.1
4.12.2
investigation
4.12.3
35