Beruflich Dokumente
Kultur Dokumente
© DNV GL
OIL & GAS
PIPELINE UPRATING
Increasing demand for gas requires increased pipeline capacity. What are the Benefits?
Instead of an expensive new-build project, it is often possible ■■ Independent justification of safe operation to Regulator
to demonstrate a pipeline’s safety at an increased pressure, ■■ Robust documentation suitable for rigorous technical audit
via DNV GL’s uprating methodology. Uprating can achieve ■■ Allows the operator to target resources towards maintaining
increased capacity at a fraction of the capital expenditure or improving integrity through quantified risks.
incurred by new-build work.
Proven Track Record
Typically, internationally recognized pipeline design codes allow ■■ National Grid successfully uprated >1000km of pipeline
operation of high-pressure gas pipelines at levels above their utilising systems and methods developed by DNV GL
original design factors. In order to operate a pipeline at higher ■■ DNV GL worked with National Grid in developing the systems
pressures, it is necessary to demonstrate that the same level of and methods
safety to the surrounding population and environment is ■■ DNV GL has incorporated previous learning points within
maintained at the proposed uprated pressure. current methodology
■■ DNV GL, as principal contractor, has successfully uprated
DNV GL have developed a proven fitness for purpose 375km of pipeline for National Grid when DNV GL executed
methodology for demonstrating safe operation of pipelines at all works from feasibility study, through assessment and site
design factors greater than the limiting value given by remedials, to pressure-raise
design codes. ■■ DNV GL has worked via other principle contractors to provide
complete uprate safety justifications for National Grid
DNV GL are able to apply this methodology in its entirety ■■ DNV GL offer modular up-rating work packages that cover an
on behalf of the customer or, if preferred, carry out separate entire project or any discreet part thereof.
tasks alongside the customer.
The required remedial actions were then identified, based on
the results from these assessments.
from to
© DNV GL
Wooler to Bishop Auckland 70 84
“We estimate this has saved us in the region of £530m, whilst UK Distribution Pipelines Pressure
Increase (bar)
continuing to maintain safety levels.” - National Grid
from to
DNV GL’s Methodology Safety Justification
7 Distinct Phases Submission to Regulator North London Southhall - Fulham 7 9
Network Reaffirmation
Detail Design
Modification/Replacement
North West Whasset - Natland 9 16
Fitness-for-Purpose Network
Assessment
European Pipelines Pressure
Code Compliance
Assessment Increase (bar)
Stress Analysis
from to
Feasibility Study
DNV GL first of all identified the gaps in the available data, and
considered what assessments and surveys would be required.
In parallel with this, an ‘early-works’ assessment was undertaken
© DNV GL
DNV GL, Holywell Park, Ashby Road, Loughborough, LE11 3GR. Tel: +44 (0)1509 282000, www.dnvgl.com 16902_JS 14.06 2016