Sie sind auf Seite 1von 2

UNIVERSAL INTERNATIONAL ISSUE: WON UNIVERSAL IS ENTITLED TO:

INVESTMENT v RAY BURTON DEV’T CORP


1. Liquidated damages under Section 6 of the
RBDC/ BURTON– Elizabeth Place developer Contract to Sell
2. Claims for losses
UNIVERSAL INT’L – Purchaser/Buyer 3. Damages from contractual breach

Facts: UNIVERSAL purchased 10 condo units and RULING:


10 parking slots from BURTON for P52.8M.
BURTON failed to deliver properties even upon 1. No. Section 6 of the Contract of Sell
demand, and it was later discovered that the mother provides that the agreement shall be deemed
title of ELIZABETH PLACE was mortgaged to cancelled at the option of the buyer in case
CHINA BANK. of force majeure and substantial delay in
the condo project- Elizabeth Place.
BEFORE HLURB Substantial delay is SIX months from the
date of estimated completion.
UNIVERSAL filed for specific performance or
rescission of contract and damages before ITC, Universal merely alleged the failure of RBDC to
EXPANDED NATIONAL CAPITAL REGION deliver the condo, parking slots, and CCT and failed
FIELD OFFICE of HLURB imputing fraud for to assert either of the two circumstances provided in
concealing the mortgage. It also sought the delivery the agreement. The cause of action was not grounded
of 1 CONDO unit and its two CCT otherwise; the on force majeure nor substantial delay.
contract shall be rescinded with a refund of purchase
price plus penalty interest, 1.5% monthly interest on 2. No. Article 2200 applies to indemnify the
the total PP computed from the date of cancellation claimant for lost profits obtained other than
of the sale until full refund. It further moved to injury caused.
attached Lapu-lapu property of RBDC as claim
security. DAMAGES is the sum of money imposed as
pecuniary compensation, recompense or satisfaction
BURTON argued that UNIVERSAL should direct its for an injury done or wrong sustained from
claim for delivery of titles to China Bank based on a contractual breach or torts. The claimant must
compromise agreement between BURTON and therefore prove:
CHINA BANK where the latter has to release titles
of units fully paid to respective buyers. 1. Injury or wrong
2. Breach of contract or tort
ENCRFO ruled in favor of Universal. Appeal by 3. Caused by the party charge
RBDC to BOC of HLURB and moved to release lot
in Lapu-lapu which eventually allowed the UNIVERSAL invoked ARTICLE 2200 to recover
discharged. depreciation and other cost. However it failed to
allege that the properties are for lease or sale (for
UNIVERSAL assailed the discharge of Lapu-lapu lot profit). Therefore, ARTICLE 2200 is inapplicable.
with the CA. While the case was pending, China
Bank released the properties and CCT. However, National Power Corp. v. Philipp Brothers Oceanic,
IT STILL claimed for damages under SECTION 6 of Inc. in order to recover actual damages, the alleged
Contract of Sale for the delay in delivery of the unearned profits must not be conjectural or based on
properties and compensation for property loss contingent transactions. Speculative damages are too
amounting to P19.6M as depreciation costs of the remote to be included in an accurate estimate of
properties. damages.

RBDC countered that it cannot deliver the same for 3. In contract to sell, the obligation of the seller
Universal did not pay the transfer charges. becomes demandable only upon full
payment of the purchase price, such that the 3. EXEMPLARY DAMAGES
full payment gives the buyer the right to
demand the execution of contract of sale. RULING: The grant of exemplary damages is to curb
socially deleterious actions. ITC, refusal of RBDC to
In contract of sale, the seller is required to transfer execute DEEDS warrants and nondisclosure of
ownership of the thing sold through delivery. In sale mortgage to China Bank warrant exemplary damages.
of real property, the seller is OBLIGE TO
TRANSFER THE OWNERSHIP not the transfer NB: Since RBDC’s contention that nonpayment of
the name of the new buyer in the certificate of transfer charges is unmeritorious, it is not impeded to
title. issue the deeds of sale. That is why EXEMPLARY
DAMAGES ARE AWARDED. Universal was
Section 3 of Contract to Sell, RBCD has to deliver purchaser in good faith.
the DEEDS of absolute sale and to deliver the
corresponding CCTs.

ITC, the ground damages was RBDC’s failure to


transfer CCT and possession of the properties and not
that of CONTRACT TO SELL. RBDC has no
contractual obligation to neither surrender the
possession of the properties nor cause the transfer of
CCT to UNIVERSAL.

IN SUM, Universal is not entitled to damages. It did


not specify the non-delivery of properties resulted to
depreciation and had the properties been delivered,
IT could have avoided the losses.

INCIDENTAL ISSUES:

1. RBDC argument that Universal defaulted on


paying TRANSFER CHARGES

RULING: Universal doesn’t have to pay transfer


charges. Their agreement provided that the buyer
shall pay the charges only upon election that the
BUYER handles the titling of properties. The charges
are therefore lodged specifically to the SELLER.

2. UNIVERSAL is entitled to TEMPERATE


OR MODERATE DAMAGES.

RULING: Temperate damages are awarded when


some pecuniary loss has been suffered but the
amount cannot be proven with certainty. ITC,
UNIVERSAL sustained pecuniary loss from non-
delivery of CCTs and non-execution of DEED of
absolute sale.

Das könnte Ihnen auch gefallen