Sie sind auf Seite 1von 18

1)Area to be

level and
compacted.

2)
Scaffolding
material to
be cleared

3)Piping
material
near topside
to be
cleared

4)Structure
materials to
be cleared
CLEAR OF COLLER DECK

SIDE VIEW
CLASH WITH SERVICE DECK,
SPLICE BEAM TO BE
INSTALLED AFTER ROLL UP

SIDE VIEW
CLASH WITH SERVICE DECK, SPLICE BEAM TO BE
INSTALLED AFTER ROLL UP
CLASH WITH SERVICE DECK, SPLICE BEAM TO BE
INSTALLED AFTER ROLL UP
TOP HORIZAL BRACE CLASH WITH
VESSEL
TO BE INSTALLED AFTER ROLL UP)
CLASH WITH SERVICE
DECK, SPLICE BEAM
TO BE INSTALLED
AFTER ROLL UP
Ouside perimeter to be
installed afetr roll up
Stair Clash (to be
installed afer roll up)
Stair tower post need
to be splice to have
clearance (see next
page)

Vessel Clear of to X
Brace
Stair Clash

Post Clash, to be splice


to have clearance with
X Brace
Post Clash, to be
splice to have
clearance with X Brace
Scaffolding clash with
flare boom

3 nos beam clash with flare


boom

Scaffolding clash
with flare boom
Scaffolding clash with flare boom
Any installation/tie
in/structure erection
above/ surrounding
TEG CONTACTOR to
hold due to clashing
Piping
protruding
flare boom
Protruding piping to hold

Protruding piping to hold


Pipe support clash/ tight
clearance with flare boom
Pipe support
clash/ tight
clearance with
flare boom