Sie sind auf Seite 1von 8

BID DOCUMENTS

Prepared by: Energy Solutions, Inc


580 main Street, Suite 580
Carbondale, Co 81623

For the Project: XYZ

Located at: XYZ

BID FORM
Table of Contents

Article 1 - Bid Receipt

Article 2 - Bidders Acknowledgements

Article 3 – Bidders Representations

Article 4 – Further Representations

Article 5 – Basis of Bid

Article 6 – Time of Completion

Article 7 – Attachments to This Bid

Article 8 – Defined Terms

Article 9 – Bid Submittal

Article 1 - Bid Receipt


1.1 This bid is submitted to: ____________________________________ (Owner)
___________________________________(Address)
______________________________(City, State, Zip)
Phone: _______________ Fax: _________________

1.2 The undersigned Bidder proposes and agrees, if this bid is accepted, to enter
into an Agreement with the Owner in the form included in the bidding Document to
perform all Work as specified and indicated in the Bidding Documents for the price and
within the times indicated in this bid document and in accordance with the terms and
conditions of these bidding documents.

Article 2 - Bidders Acknowledgements

2.01 Bidder accepts all the term and conditions of the Instructions to Bidders, including
without limitations, those dealing with the disposition of Bid Security. This Bid will
remain subject to acceptance for 60 days after the submission of the Bid, or for such
longer time that the Bidder may agree in writing to extend the bid offer.

Article 3 – Bidders Representations

3.01 In submitting this Bid, Bidder represents that:


A. Bidder has examined and carefully studied the Bidding Documents, the other
related data identified in the Bidding Documents, and the following Addenda,
receipt of which is hereby acknowledged.
Addendum # Addendum Date
_______________________ __________________________
_______________________ __________________________
_______________________ __________________________
_______________________ __________________________
_______________________ __________________________

B. Bidder has visited the Site and become familiar with and is satisfied as to the
general, local and Site conditions that may affect cost and progress and
performance of the Work.

C. Bidder is familiar with and is satisfied as to the federal, state, and local Laws
and Regulations that may affect cost, progress and performance of Work.
D. Bidder has carefully studied all additional or supplememtary examinations,
investigations, tests, studies, and data concerning conditions at or contigious to
the site, all shop drawings provided by the equipment suppliers, all existing plans
provide by Owner.
E. Bidder does not consider that any further examinations, explorations, test
studies, or data are needed in order to submit a bid to perform the work for the
Bid Price and within the time allowed and in accordance with the other terms of
the Bidding Documents.

F. Bidder is aware of the general nature of the work to be performed by the


Owner and other at the Site that relates to the Work as indicated in the Bidding
Documents, or to the normal day to day operation of the site. Bidder
acknowledges their ability to perform the work in the prevailing condition and will
make reasonable efforts to maintain operations of the Site as normal as possible
during construction. Work to be provided by the Owner is:
___________________________________________________________
___________________________________________________________
___________________________________________________________

G. Bidder has correlated the information know to the Bidder, information and
observations obtained from visits to the Site, reports and drawings identified in
the Bidding Documents and all additional examinations, explorations, tests,
studies and data contained in the Bidding Documents.

H. Bidder has given Owner written notice of all conflicts, errors, ambiguities, or
discrepancies that the bidder has discovered in the bidding documents and the
written resolution thereof by Owner is acceptable to Bidder.

I. The Bidding Documents are generally sufficient to indicate and convey


understanding of all terms and conditions for the performance of the Work for
which this bid ids submitted.

K. Bidder will submit written evidence of its authority to do business in the State
of _______________.

Article 4 – Further Representations

4.04 Bidder further represents that.

A. This bid is genuine and not made in the interest of or on behalf of any
undisclosed individual or entity and is not submitted in conformity with any
agreement or rules of any group, association, organization or corporation.
B. Bidder has not directly or indirectly induced or solicited any other Bidder to
submit a false or sham Bid.

C. Bidder has not solicited or induced any individual ar entity to refrain from
bidding, and.

D. Bidder has not sought by collusion to obtain for itself any advantage over any
other Bidder.

Article 5 – Basis of Bid

5.01 Bidder will complete the Work in accordance with the Contract Documents for the
following price.

A. Lump Sum Bid

Lump Sum Bid Price: __________________________________(written amount)


$_______________________________________________________(numbers)

OR

Lump Sum for Base Bid Price: ___________________________(written amount)


________________________________________________________(numbers)

Plus (minus) the following Alternates

Alternate 1 Add (Deduct): ______________________________(written amount)


$________________________________________________________(number)

Alternate 2 Add (Deduct): ______________________________(written amount)


$_______________________________________________________(numbers)

OR

B. Cost Plus Bid


The cost of all Work other than Unit Price Work shall be determined as provided
in Appendix A of this Document plus for all unit price work the amounts indicated
below:
The Guaranteed Maximum Price to Owner of the Cost of the Work including
Contractors Fee will not exceed:
___________________________________________________(written amount)
$_______________________________________________________(numbers)

Contractors Fee will be a fixed sum of:


__________________________________________________ (written amount)
$_______________________________________________________( numbers)

(Or)

Contractors Fee will be determined by applying the following percentages to the


various portions of the Cost of Work defined in Appendix A of this Document”
Payroll Costs _______________%
Material and equipment Cost: _______________%
Amounts paid to Subcontractors: _______________%
Amount paid to Consultants: _______________%
Supplemental Costs _______________%

None of the cost indicated above will be included in Determining the Contractors
Fee

The maximum amount payable to the Contractor on account of this percentage


fee will not exceed
___________________________________________________(written amount)
$_______________________________________________________(numbers)

(Or)

C. Unit Price Bid

Item Number Description Units Estimated Bid Unit Price Total Bid
Quantity
________ _________________ ____ ________ $___________ $________
________ _________________ ____ ________ $___________ $________
________ _________________ ____ ________ $___________ $________
________ _________________ ____ ________ $___________ $________
________ _________________ ____ ________ $___________ $________
________ _________________ ____ ________ $___________ $________

Article 6 – Time of Completion


6.01 Bidder agrees that Work will be substantially completed and ready for final
payment in on or before the following date (or within the number of calander days
indicated)

Date of Substantial Completion; __________________________ 200__

OR
Number of Calander Days: _________________________ days

Article 7 – Attachments to This Bid

7.01The following documents are attached to and made a condition of this bid
A. Required Bid Security ___ yes ____no
B. List of Proposed Sub-contractors ___ yes ____no
C. List of proposed suppliers___ yes ____no
D. List of Project References___ yes ____no
E. Required Bidder Qualifications Statement ___ yes ____no
F. Affidavit of Non-Collusion___ yes ____no
G. Documents as Follows___ yes ____no
__________________________________________
__________________________________________
__________________________________________
__________________________________________
__________________________________________
__________________________________________

Article 8 – Defined Terms

8.01 The terms used in this Bid with capital letters have the meanings stated in
Appendix B of this Contract.

Article 9 – Bid Submittal

9.1 This Bid submitted by:

A. If bidder is an Individual:_______

Name (Typed or Printed): _____________________________________________


By (Individuals signature):_____________________________________________
Doing Business as:___________________________________________________

B If bidder is a Partnership:_______

Partnership Name (Typed or Printed): ____________________________________


By (Individuals Signature):____________________________________________
General Partner (Typed or printed):______________________________________

C If bidder is an Individual: ________


Corporation Name : ________________________________________________
State of Incorporation:_______________________________________________
Corporation Type: __________________________________________________
By (Individuals Signature):____________________________________________
Title:_____________________________________________________________
Attest:____________________________________________________________
Date of Qualification to do business in ________________ (State) is:
______Day ______Mo _______Year

Bidders Business Address: ________________________________________________


______________________________________________________________________
Phone ____________________________ Fax___________________________
E-mail_________________________________________________
Submitted on this Da__________________________________________ 20____
State Contractors Liscense: ___________________________________ (If applicable)

End of Document