299920/2019/HYDEL-II SECTION
25/78
299920/2019/HYDEL-II SECTION
1. In order to restore and maintain the wholesomeness of the River Ganga, Govt.
of India vide Gazette notification dated 09.10.2018 of National Mission for Clean
Ganga (MoWR), have notified ecological flows to be maintained in river Ganga at
different locations downstream of structures or projects meant for diversion of
river flows for purposes like irrigation, hydropower etc. (Copy enclosed) as
below:
i.) Upper Ganga River Basin Stretch starting from originating glaciers and
through respective confluences finally meeting at Devprayag up to Haridwar:
ii.) Stretch of main stem of River Ganga from Haridwar, Uttrakhand to Unnao,
Uttar Pradesh:
(In Cumecs)
Sl. Location of Minimum flow releases immediately
No. Barrage downstream of barrages (in Cumecs)
Non-Monsoon Monsoon
(Oct.- May) (Jun. - Sept.)
1 Bhimgoda
36 57
(Haridwar)
2 Bijnor 24 48
3 Narora 24 48
4 Kanpur 24 48
*****
28/78
299920/2019/HYDEL-II SECTION
Annex
Status of Under Execution Hydro Electric Projects (above 25 MW) in Uttarakhand
Name of Project State Broad Present Status / Critical Area Remarks/
Sl. Executing Agency Comm. Critical issues
No. Date of CEA clearance Sch.
/ Approval (original/
Capacity (MW) Now Ant.
Broad Features
Cost (original/latest)
In Rs. Crores.
Central Sector
1. Tapovan Vishnugad Uttara River diversion achieved on 13.04.2013 - Completion of HRT.
NTPC khand Barrage: Excavation completed and Concreting 122230 - Restoration of TBM
11.08.2004/Nov, 2006 cum out of 125575 cum completed. - Associated
4x130 = 520 MW 2012-13 HRT: 8.25 Km excavation completed out of 12.62 Km, Transmission system.
Broad Features : 2020-21 TBM struck due to cavity (5.5km completed out of
Barrage–5 bays of 12m (Dec’20) 8.8km)
HRT- 5.4m x 11.97km PH Cavern: Excavation and concreting completed.
3
P.House- underground Desilting Chamber & Intake: 5.40 lakhs m out of 6.42
3
Turbine- V.Pelton lakh m Excavation completed.
Cost: Original: 2978.48 TRT: Excavation completed.
Latest: 3846.30 Surge shaft: Excavation & Lining completed.
Contractors Penstock: Excavation completed and Lining almost
Civil : Rithwik/L&T / completed.
Patel E&M works: Pit liner erection on all 4 units completed.
HM : Om Metals Turbine housing erection of all 4 units completed.
E&M : BHEL Erection of EOT crane in BVC & service bay
completed.
Unit #1: Stator & Rotor lowered.
Unit #2: Stator winding is in progress.
Unit #3: Stator Core building is in progress.
Unit #4: Distributor Barrel Concreting completed.
Critical : HRT
2. Tehri PSS, Uttara EPC contract has been awarded on 23.06.11 with - Poor Geology in under
THDC, khand commencement date from 27.07.11. ground works of BVC,
18.7.06 Upstream (Tehri Dam) and Downstream (Koteshwar PAC, TRT, PH Cavern
Nov-11 (Revised 2010-11 Dam), intake and Head Race Tunnels (2 Nos.) already etc.
CCEA) 2021-22 completed alongwith Tehri Stage-I works. - Slow progress of works
4x250=1000 MW (May’21) Surge Shafts upstream (2nos- 140m).: After completion - Cash flow crisis with
Broad Features : (Subject to of Crown slashing, widening is in progress. Erection of M/s. HCC.
Surge Shaft: U/s – 2 re-start of Gantry completed. - Works are stalled since
nos. works) Butterfly Valve Chamber (BVC): Crown slashing with April, 2018 due to funds
D/s – 2 nos steel ribs completed. Benching work and additional constraints with
Power House: U/G stabilization work is nearing completion. Cumulative contractor.
TRT: 2, Dia 9m and Benching Excavation 7942 Cum (49.42%) completed.
Lenghth 1070m + Penstock Assembly Chamber (PAC): Crown slashing
st
1160m with steel ribs completed. Excavation of 1 bench has been
Turbine: VF reversible completed.
pump turbine Power House: Excavation completed.
Cost: Original: 1657.60 Surge Shafts downstream (2nos).: Excavation of Top
Latest: 4401.90 Chamber completed. Surge Shaft-4: Works for Collar beam
Contractors completed. Surge Shaft-3: Excavation for Collar Beam
Turnkey : Alstom, completed. Widening is under progress.
France/ HCC TRT-3(1151 RM): Excavation in Heading 862 RM,
Benching 188.5 RM. Invert Lining-126m Overt Lining -
48m completed
TRT-4 (1255 RM): Excavation in Heading-948 RM,
Benching- 422.5 RM Invert Lining-156m completed.
E&M Works: Manufacturing & supplies are in progress.
3. Lata Tapovan, Uttara Infrastructure works are almost completed. Main works to -Works of barrage &
NTPC khand re-start after clearances from Hon ‘ble Supreme Court. HRT yet to start due to
Aug-2012 2017-18 EPC contract for Civil & HM works awarded to M/s L&T on protest by villagers.
3x57= 171 MW 2022-23 17-08-2012. E&M package awarded to M/s BHEL on
Broad Features : (Subject to 07.12.12. -Construction work
29/78
299920/2019/HYDEL-II SECTION
Name of Project State Broad Present Status / Critical Area Remarks/
Sl. Executing Agency Comm. Critical issues
No. Date of CEA clearance Sch.
/ Approval (original/
Capacity (MW) Now Ant.
Broad Features
Cost (original/latest)
In Rs. Crores.
Barrage–14 bays of re-start of stopped vide Hon’ble
11m each works) Supreme Court order
HRT- 7.51 Km, 4.7m dia dated 7.5.14.
P.House- underground
Turbine- V.Francis
Cost: Original: 1527.00
Latest: 1527.00
Contractors
Civil & HM : L&T
E&M : BHEL
4. Vishnugad Pipakoti Uttara River diverted on 02.04.2018. -Frequent disruption of
THDC khand Work on construction of coffer dam is in progress. works by local people.
21.08. 2008 2013-14 Development for TBM platform excavation 95% has been - Slow progress of works
4x111= 444 MW 2021-22 completed. - Cash flow crisis with
Broad Features : (Dec’21) Main Access Tunnel (MAT) 413.5m: Excavation completed M/s. HCC.
Dam – 65m High, upto 397.50m.
89.3m long, concrete HRT (13400m): 395.80m completed by DBM.
gravity Construction of Adits and infrastructure works are under
HRT- 13.4 Km, 8.8m dia progress
Horse shoe shape Desilting Chambers (3 No. X 390m) : Crown Slashing
P. House-Underground completed. In DC #2 & DC #3 and Benching is under
127mx 20.3mx 50m progress in DC #1 and DC#3.
Turbine- Francis
SWYD- 13.8/420 kV
Cost:Original: 2491.58
Latest: 4105.30
Contractors
Civil & HM : HCC
E&M : BHEL
5. Naitwar Mori Uttara LoA for civil works has been issued to M/s. Jaiprakash -
SJVN Limited khand Associates Ltd. on 05.12.2017.
16.10.2017 2021-22 Desilting Tank : Removal of slide deposit in desilting tank
2x30=60 MW 2021-22 area is in progress. Cumulative 22,820 cum out of 48,000
Broad Features : (Dec,21) cum completed.
Barrage: 30.5m height Diversion channel : Open excavation of diversion channel
HRT: 5.6m horse shoe, is in progress. Cumulative 55,005 cum out of 77,000 cum
4330m long completed.
Pressure shaft: 4m dia, Adit 1&2 : Portal development work of Adit #2 is in
109m long progress. Excavation of Adit #1 27m out of 98m
Surge shaft: 18m dia, completed.
51.65m height HM works : LoA issued to M/s GMW Private Ltd. on
Cost : Original: 648.33 18.04.18. M/s GMW has submitted the construction
Latest : 648.33 schedule.
Contractors E&M works : Works awarded to M/s. Voith Hydro Pvt. Ltd.
Civil : JP Associates On 20.07.18.
HM : GMW
E&M : Voith
State Sector
6. Vyasi Uttarakhan Civil Works: -Dam and E&M works
UJVNL d Dam : Excavation completed. 197122 cum out of 3.6 lakh are Critical.
cum of Concreting completed. -Local issues.
25.10.2011 (TEC) Diversion Channel : Completed.
2x60= 120 MW 2014-15 Head Race Tunnel (2.7 Km): Excavation of HRT
Broad Features: 2019-20 completed. 2359.8m Overt Lining and 1325m Invert Lining
Dam: Conc. Gravity (Mar,20) out of 2655m has been done.
H- 86m L-207.2m Pressure Shaft: 3022cum out of 5000cum Excavation
30/78
299920/2019/HYDEL-II SECTION
Name of Project State Broad Present Status / Critical Area Remarks/
Sl. Executing Agency Comm. Critical issues
No. Date of CEA clearance Sch.
/ Approval (original/
Capacity (MW) Now Ant.
Broad Features
Cost (original/latest)
In Rs. Crores.
HRT- Circular, 7m dia, completed.
2.7Km long. Surge Shaft : Excavation completed. Concreting-250cum
Power House- Surface out of 6626cum completed.
Turbine- VF. Power House: 258500 cum out of 270,000cum Excavation
Switchyard: 220 Kv. completed.
Cost: Original: 936.23
Latest: 936.23
Contractors
Civil : Gammon / MPCC
E&M : BHEL
Private Sector
7. Phata Byung Uttara Dam concreting: 17800/18000 cum concreting - Works severely
M/s Lanco khand completed. affected due to flash
06.10.2008 P.H.: Excavation completed & Concreting in progress. floods in June, 2013.
2x38 MW = 76 MW 2012-13 HRT: Excavation almost completed. 1400 m Lining has Works are stalled since
Broad Features: 2021-22 been completed. July, 2017 due to funds
Dam – 26m high (Subject to Excavation and lining of Intake-I & Intake-II completed. constraints with
HRT- 3.2 m dia & re-start of Pressure shaft: Excavation completed & lining is under contractor.
9.38 km length works) progress.
Turbine – Frances TRT: Excacation 178/235m completed.
Cost: Original: 520.00 E&M Works: Pit liner erection of units completed. EOT
Latest : 1225.53 Crane installed and Commissioned.
Contractors
Civil : Lanco
HM : Cimmco
E&M : Alstom
8. Singoli Bhatwari Uttara River diversion – completed. - Works severely
M/s L&T khand Dam & Dykes/Barrage: Excavation almost completed and affected due to flash
11.07.2008 concreting 62147 / 70220 cum completed. floods in June, 2013.
3x33 MW = 99 MW 2012-13 HRT: Excavation completed - HRT Critical
Broad Features: 2019-20 Overt Concrete Lining 4940m / 11257m completed.
Barrage-FRL 1017 m, (Jun,19) Invert Lining 4950m / 11257m completed.
MDDL 1009 m, Pressure Shaft: Excavation completed.
Barrage Top 1020m PH: Excavation completed & concreting 25180/ 29959cum
HRT- 4.65m dia & completed.
11.870m length Surge Tank: Excavation completed. 4113.93cum out of
Surge Shaft-10 m dia & 5349cum concreting completed.
102.85 m length E&M Works: Erection of spiral casing of Unit#1 is in
Pressure Shaft-One, progress. Draft tube erection and EOT crane Erection &
3.80m dia & 358m Load testing completed.
length
Penstock- 3 Nos., 2.20
m dia & 34m, 42m, 48m
long.
P. House-Surface
Turbine-Vertical Francis
TRT- Open Channel,
650m length
Cost : Original : 666.47
Latest:1694.00(PL-2018)
Contractors
Civil : L&T
HM : General
Mechanical Works
E&M : Voith
*****
31/78
299920/2019/HYDEL-II SECTION
vlk/kj.k
EXTRAORDINARY
Hkkx II—[k.M 3—mi&[k.M (ii)
PART II—Section 3—Sub-section (ii)
izkf/dkj ls izdkf'kr
PUBLISHED BY AUTHORITY
la- 4009] ubZ fnYyh] cq/okj] vDrwcj 10] 2018@vkf'ou 18] 1940
No. 4009] NEW DELHI, WEDNESDAY, OCTOBER 10, 2018/ASVINA 18, 1940
आदेश
नई दली, 9 अ
तूबर, 2018
का.
का.आ. 5195(
5195(अ).—
).—गंगा नदी अ
यिधक पिव और इस देश के लोग ारा अ
यंत पूयनीय है तथा गंगा नदी बेिसन जल हण
े के िनबंधनानुसार भारत म# वृह$म नदी बेिसन है, िजसम# संपूण' देश क( छ*बीस ,ितशत भूिम सि.मिलत है तथा जो लगभग पचास
करोड़ जनसं/या के िलए पोषणीय है;
और गंगा नदी िवशेष गुण, िविश3ता4 तथा मह
व के 6प म# अीतीय है िजसका मह
वपूण' लौकक और 9थािनक ,भाव िभ;ता के साथ
जल-िव<ान, भू-आकृ ितिव<ान, ऐितहािसक, सामािजक-सां9कृ ितक और आ?थक कारण ह@;
और गंगा नदी को राAीय नदी का दजा' दया गया है तथा नदी-,णाली म# Bसचाई, घरे लू, औDोिगक और अEय ,योजन के िलए बेिसन म#
सदैव पानी क( बढ़ती मांग के साथ घरे लू अपिश3 और आDोिगक अपिश3 सिहत िविभ; Iोत से ,दूषण ,वेश कर रहा है, जो नदी के
9वा9Jय को लंबे समय से ,भािवत कर रहा है;
और भारत सरकार समुिचत पया'वरण ,वाह तथा साथ ही नदी म# ,दूषण के ,वेश के िनवारण को सुिनिKत करने के िलए नदय क(
पौि3कता क( बहाली करने और उसे बनाए रखने के िलए वचनबN है;
और यह सुिनिKत करना आवOयक है क गंगा नदी म# हर समय पानी के िनबा'ध ,वाह को पूरी तरह से बनाए रखा जाए, िजससे मौसमी
िभ;ता4 को बदले िबना नदी म# ,वाह क( िनरं तरता सुिनिKत हो सके ;
क# Pीय सरकार ने पया'वरण (संर ण) अिधिनयम, 1986 (1986 का 29) के अधीन अिधसूचना का.आ. 3187 (अ), तारीख 7 अ\ू बर,
2016 ारा गंगा नदी जल े के संर ण, संर ा और ,बंध तथा िन^िलिखत ,योजन के िलए एक ,ािधकरण अथा'त् राAीय 9व`छ गंगा
िमशन का गठन कया था, अथा'त:् -
गा नदी और उसक( सहायक नदय के जल क( गुणव$ा और पया'वरणीय वहनीय संर ण, संर ा और ,बंध को सुिनिKत करने के
(क) गं
उbेOय से सतैव िविभन् े म# िविभ; Bबदु4 पर बनाए रखने के िलए अपेि त गंगा नदी और उसक( सहायक नदय म# पाcरि9थितक
5941 GI/2018
32/78
299920/2019/HYDEL-II SECTION
2 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(ii)]
,वाह के पcरमाण को अवधाcरत करवाने तथा उसे अिधसूिचत करवाने और पया'd पाcरि9थितक ,वाह को बनाए रखने के िलए ऐसे सभी
आवOयक कदम उठाना या िनदेिशत करना;
(ख) गंगा नदी के जलीय ,े ण 9टे शन के माgयम से िविनhद3 Bबदु4 पर पानी के औसत ,वाह को िविनhद3 करना;
(ग ) गंगा नदी तथा उसक( सहायक नदय म# जल के ,वाह क( िनरं तर मानीटरी के िलए तं िवकिसत करना;
और क# Pीय सरकार ने गंगा नदी और उसक( सहायक नदय म# कितपय ,वाह को िनधा'cरत करने का िविनKय कया है ।
2. अतः क# Pीय सरकार, गंगा नदी (संर ण, सुर ा एंव ,बंधन) ,ािधकरण आदेश, 2016 के पैरा 39 के उपपैरा (3) और पैरा 41 के
उपपैरा (2) क( मद (ज) के साथ पcठत पया'वरण संर ण अिधिनयम, 1986 क( धारा 3 क( उपधारा (3) ारा ,द$ शि\य का ,योग
करते lए, Bसचाई, जल िवDुत्, घरे लू और औDोिगक ,योजन तथा अEय अपे ा4 के िलए नदी ,वाह को पcरव?तत करने के िलए
संरचना4 या पcरयोजना4 के िन^ ,वाह अव9थान पर Eयूनतम पया'वरणीय ,वाह को बनाए रखने के िलए अिधसूिचत करती है,
अथा'त:् -
I. देव,याग से हcरार तक अंत म# िमलने वाले mमवतnय सि.मलन के माgयम से और उoव वाले pलेिशयर से आरं भ होने वाला
उपरी गंगा नदी बेिसन िवतार :
II. ह"र#ार, उ$राखंड से उ'ाव, उ$र (देश तक गंगा नदी के मु*य माग+ का िवतार:
mम सं. बैराज क( बैराज के सि;कट िन^ धारा को बैराज% के सि&कट िन( धारा को
अवि9थित िनमु'\ करने वाला Eयूनतम ,वाह िनमु*
करने वाला ,यूनतम वाह
(-यूमै-स म0) (अ3ू बर से मई) (यूमैक म ) (जून से िसतंबर)
(1) भीमगौड़ा 36 57
(हcरार)
(2) िबजनौर 24 48
(3) नरौरा 24 48
(4) कानपुर 24 48
यूमैक-घनमीटर ,ितसेकंड ।
III. उपरो\ उ\ पाcरि9थितक( ,वाह िन^ के अgयधीन ह@, अथा'त्:-
(i) Eयूनतम पया'वरणीय ,वाह का अनुपालन सभी िवDमान, िनमा'णाधीन और भिव्qय क( पcरयोजना4 को लागू होता है;
(ii) िवDमान पcरयोजनाएं जो वत'मान म# इन पया'वरणीय ,वाह के मानदंड के अनु6प नहv ह@, इनका पालन कर# गी और यह सुिनिKत
कर# गी क वांिछत पया'वरणीय ,वाह मानदंड का पालन इस अिधसूचना के जारी करने क( तारीख से तीन वष' क( अविध के भीतर कया
जाए;
पcरयोजना जो सि;मा'ण क( िविभ; ,mम पर ह@, जहां जमीनी भौितक ,गित आरं भ हो चुक( है और समुिचत ,ािधकारी को cरपोट'
(iii)
क( गई है, पcरयोजना को आरं भ करने के पूव' और उसके पKात् अनुबN पया'वरणीय ,वाह को बनाए रखने के िलए भी आवOयक उपबंध
करे गी;
लघु और सूwम पcरयोजनाएं जो सारवान 6प से नदी या धारा क( ,वाही िवशेषता4 को पcरव?तत नहv करती ह@, इन पcरयावरणीय
(iv)
क# Pीय सरकार, राAीय 9व`छ गंगा िमशन के माgयम से, जब कभी अपेि त हो, गंगा नदी म# िवशेष मांग को पूरा करने के िलए
(viii)
,योजन के िलए भूजल िनकालने क( मानीटxरग और िविनयमन भी है, जैसे अ`छे और वै<ािनक zवहार को अपना कर गंगा नदी के जल
िनकालने म# कमी करने के िलए मांग प ,बंध योजना काया'िEवत कर# गे ।
3. यह आदेश इसके राजप म# ,काशन क( तारीख से ,वृ$ होगा ।
4. यह आदेश उoव वाले pलेिशयर से आरं भ होने वाले उपरी गंगा नदी बेिसन तथा देव,याग से हcरार तक और उ$र ,देश के उ;ाव
िजले तक गंगा नदी क( मु/य धारा को तथा अंत म# िमलने वाली इसक( मु/य सहायक नदय के mमवतn सि.मलन पर लागू होगा ।
[फा. सं. - Estt.01/2016-17/111/NMCG (Vol III)]
(%) Percentage of
Sl. Monthly Average Flow
Season Months
No. observed during each of
preceding 10-daily period
1 Dry November to March 20
2 Lean October, April and May 25
3 High Flow season June to September 30*#
(1) Bhimgoda 36 57
(Haridwar)
(2) Bijnor 24 48
(3) Narora 24 48
(4) Kanpur 24 48
Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064
and Published by the Controller of Publications, Delhi-110054.