Beruflich Dokumente
Kultur Dokumente
Bo Eriksson-Vanke
Civil Eng.. National Rail Admin.. Stockholm. Sweden
Introduction
The 2070 m long Igelsta Bridge. now
under construction, will be one of the
largest railway bridges in Europe. It
will be a part of the Grodinge railway
line, a new 30 km long double-track
line south of Stockholm. The new line
will he used for mixed traffic: both
heavy freight trains and new light high-
speed passenger trains. At the south
end of the bridge a new station will he
incorporated.
General Description
The Igelsta Bridge (Fig. 1) crosses a
large navigable channel. a harbour Fig. I. I/ic IgeLsia Bridge. .%Ia' /993
area and a highway. The channel is
used h' ships of up to 70000 dwt. The
bridge deck is about 49 m above the tender. The tender documents present- Foundations
water level of the channel. The design ed two alternatives: proposal A. with The bridges over land are founded
is a double-track bridge branching out outline drawings and preliminary de- directly on rock or on concrete piles
at the station into two single-track sign set up by the owner, and proposal 270 x 270 mm with a bearing capacity
bridges. Two platforms. each 35 m B. giving only basic restrictions.
of 1.1 NIX. For the bridge construction
above ground level and 375 m long, are In April 1990, five contractors or joint above water, there are three footings
located between the single-track and ventures representing Sweden. Nor- founded on about 60 m long steel pipe
double-track bridges. The platforms way, France, Italy and Turkey present- piles with a diameter of 800 mm and
are connected to the new station build- ed their tenders. Totally 15 proposals a thickness of material of 14 mm filled
ing below the bridge by means of ele- were presented. 10 of which were pro- with reinforced concrete. The piles are
vators and escalators. posal B. The basic proposal A given in skin friction-bearing or end-hearing.
The part of the bridge above the chan- the tender documents was the niost The concrete and reinforcement are
nel has been constructed of postten- competitive, however, with an estimat- designed to be capable of carrying the
sioned concrete using the balanced ed total cost of approximately 778 mil- whole pile force. should the steel pipe
cantilevered method with three spans, lion Swedish Crowns. After a period he damaged by corrosion. The niaxi-
90+158+90 m. and a vertical clear- of negotiation and hard competition. a mum force of the pile is 5.6 NIX. The
ance of 41.6 m. The design height of Swedish-Norwegian joint venture was groups of piles below the piers on the
the cross section of the box beam at awarded the contract. channel carry a maximum of about
the piers is 15.4 m and at the mid-span 200 NIX vertical loads. There the foun-
6.5 m. Over land, the bridge also con- dations are protected by rock filling.
sists of posttensioned concrete with Design Considerations The corners of the piers are chamfered
spans of about 62 m cast with launch- and the walls taper to the tops in the
able formwork structures with a design Loads cross direction of the bridge.
height of 5 m. The double-track bridge Besides the standard specification
has a total of 33 spans divided into 6 loads, the bridge is designed to with-
units: 548+338+420÷331÷375+28 m. Superstructures
stand ship collisions. The piers located
close to the channel are dcsiiicd to The superstructures both on land and
withstand the impact of So NIX of a above water are box girders. The free
Tendering ship collision in the direction of the cantilever bridge is tensioned with
channel. The structure is designed to about 100 cables: the double-track
The owner issued tender documents absorb a 25 NIX impact from 0 to 3 m bridges with about 50. and the single-
for a negotiable turn-key contract with above water level at right angles to the track bridges with about 30 cables with
quality assurance in accordance with channel. In the direction of the chan- an ultimate load of 3.2 NIX. The free
ISO 9000. After a prequalification in nel, the superstructure should be capa- cantilever bridge is also tensioned with
1989. 12 contractors were invited to ble of absorbing an impact of I NIX. vertical tendons in the webs of the box
0' Superstructure
On each pier a yoke is fixed on which
-
the framework is launched. ®
The rear edge of the framework is sus-
pended on the cantilever of the previ-
ously cast section. ®
5,5 1
Railway