CAMP CONTRACT #
JO/HC098/MP09 MP#785, MP#786, MP#784
98 12 JIB Crane Anchor Bolt Details Sketch Civil A 20/Feb/11 3944 For Review & Approval
Foundation Layout Plan showing Existing A 29/Aug/10 4119 For Review & Approval
102 15 JO-HC098-SK-001 Sketch Electrical
Under Ground Cables B 10/Oct/10 4077 For Review & Approval
A.2 STRUCTURAL
A.2.1 STRUCTURAL GENERAL NOTE FKS-785-ST-001 B T/114 12.10.2010 MP784-5-6/124 14.10.2010 REVIEWED
FOOTING, GROUND BEAM LAYOUT AND DETAILS FKS-785-ST-002 B T/114 12.10.2010 MP784-5-6/124 14.10.2010 REVIEWED
ANCHOR BOLT PLAN & DETAILS FKS-785-ST-003 B T/114 12.10.2010 MP784-5-6/124 14.10.2010 REVIEWED
12/08/2021 Page 3 of 2
F & K IBRAHIM AL SHUWAYER & PARTNERS NEW WORKSHOP FACILITIES AT ADMIN. CAMP CONTRACT #
JO/HC098/MP09 MP#785, MP#786, MP#784
98 12 JIB Crane Anchor Bolt Details Sketch Civil A 20/Feb/11 3944 For Review & Approval
Foundation Layout Plan showing Existing A 29/Aug/10 4119 For Review & Approval
102 15 JO-HC098-SK-001 Sketch Electrical
Under Ground Cables B 10/Oct/10 4077 For Review & Approval
12/08/2021 5 of 8
F & K IBRAHIM AL SHUWAYER & PARTNERS PROJECT: NEW WORKSHOP FACILITIES AT ADMIN. CAMP CONTRACT #
JO/HC098/MP09 MP#785, MP#786, MP#784
15 Stair - 2 FKS-784-ST-E-11 B
C.6 ELECTRICAL
C.6.1 LIGHTING LAYOUT - GROUND FLOOR FKS-784-EE-001 A
C.6.2 LIGHTING LAYOUT - MEZZ FLOOR FKS-784-EE-002 A
C.6.3 POWER LAYOUT - GROUND LAYOUT FKS-784-EE-003 A
C.6.4 POWER LAYOUT - MEZZ LAYOUT FKS-784-EE-004 A
C.6.5 EARTHING SYSTEM - GROUND LAYOUT FKS-784-EE-005 A
T/48 25.07.2010 MP784-5-6/073 12.08.2010 Reviewed As Noted
C.6.6 MAIN LIGHTING PANEL SINGLE LINE DIAGRAM FKS-784-EE-006 A
C.6.7 SINGLE LINE DIAGRAM MSB FKS-784-EE-007 A
C.6.8 LOAD SCHEDULE - MSB, MLP & DB - 1 FKS-784-EE-008 A
C.6.9 LOAD SCHEDULE - DB-2, MPP AND EXHAUST FAN PANEL FKS-784-EE-009 A
A
C.6.10 POWER CABLE ROUTE LAYOUT FKS-784-EE-010
B T/84 16.09.2010 MP784-5-6/095 21/9/2010 REVIEWED AS NOTED
C.7 TELEPHONE SYSTEM
C.7.1 TELEPHONE LAYOUT - GROUND FLOOR FKS-784-TT-001 A
C.7.2 TELEPHONE LAYOUT - MEZZ FLOOR FKS-784-TT-002 A
C.7.3 TELEPHONE RISER DIAGRAM FKS-784-TT-003 A
12/08/2021 T/48 25.07.2010 MP784-5-6/073 12.08.2010 Reviewed6As
of Noted
8
F & K IBRAHIM AL SHUWAYER & PARTNERS PROJECT: NEW WORKSHOP FACILITIES AT ADMIN. CAMP CONTRACT #
JO/HC098/MP09 MP#785, MP#786, MP#784
12/08/2021 7 of 8
NEW INSTRUMENT WORKSHOP ### ###