Beruflich Dokumente
Kultur Dokumente
EXAMPLE: Klone Computers will design and manufacture a new computer, train staff and
sales vendors, and advertise the product. The activities and their expected completion
times are below.
A Prototype Design 90
B Purchase Materials 15
C Manufacture Prototypes 5
D Revise Design 20
E Initial Production Run 21
F Staff Training 25
G Staff Input on Design 14
H Sales Vendor Training 28
I Preproduction Advertising 30
J Post Redesign Advertising 45
To fill in the immediate predecessor column, the following describes the project:
The project begins with the prototype design (A)
Materials are purchased (B) after the prototype has been designed (A)
Prototypes are manufactured (C) after the materials have been purchased (B)
The design is revised (D) after getting staff input (G)
An initial production run is started (E) after the design has been revised (D)
Once the prototype has been designed (A), staff can be trained (F)
Staff Input on the prototype (G) occurs after BOTH the manufacture of the
prototype (C) and the staff training (F)
Sales vendor training (H) begins once the design has been revised (D)
A preproduction advertising campaign (I) can start after the prototype is designed (A)
The full-blown post-redesign advertising campaign (J) begins once the design has
been revised (D AND the preproduction advertising campaign is completed (I)
Draw the network for the project:
• A linear program can be solved to determine the completion time for the project:
Three time estimates are determined (by studies, guesses, etc.) for each activity
o a = an optimistic completion time (the chance of finishing in < a is very small)
o m = a most likely completion time (this is the mode)
o b = a pessimistic completion time (the chance of finishing in > b is very small)
Activity approximations
o An approximation for the distribution of an activity’s completion time is a
BETA distribution
o An approximation for the mean completion time for an activity is a weighted
a + 4m + b
average (1/6, 4/6, 1/6) of the three completion times; so it is
6
o An approximation for the standard deviation for the completion time for an
b −a
activity is its Range/6 or
6
o The variance of an activity’s completion time is the square of the standard
2
b −a
deviation =
6
Project assumptions
1. The distribution of the project completion time is determined by the critical path
using the mean activity completion times
2. The activity completion times are independent – just because one activity takes
longer or shorter than expected does not affect another activity’s time.
3. There are enough activities on the critical path so that the central limit can be used
to determine the distribution, mean, variance and standard deviation of the project
Project distribution
Given the above assumption this means
o The project completion time distribution is normal
o The mean (expected) completion time, µ, of the project is the sum of the
expected completion times along the critical path
o The variance of the completion time, σ2, of the project is the sum of the
variance in completion times along the critical path
o The standard deviation of the completion time, σ, of the project is the square
root of the variance of the completion time of the project
The probability of completing by a certain date t, can now be found by finding the
P(X < t) from a normal distribution with mean µ and standard deviation σ
You should know how to use the PERT/CPM template for projects
whose activity completion times are given by three time estimates.
Comparing Options Using Probability Approach to Project Scheduling
The Expected Value Approach
Example 1
Suppose there is a bonus of $8000 for completing a project within 50 days.
A – Do what you are currently doing and from the template, you find
P(Finish < 50) = .27 and thus P(Finish > 50) = 1 - .27 = .73
B – For $2000 you can alter the activity completion times. From the template you
find the revised P(Finish < 50) = .64 and thus P(Finish > 50) = 1 - .64 = .36
Example 2
Suppose there is a cost of $30,000 for not completing a project within 75 days.
A – Do what you are currently doing and from the template, you find,
P(Finish < 75) = .42 and thus P(Finish > 75) = 1 - .42 = .58
B – For $5000 you can alter the activity completion times. From the template you
find the revised P(Finish < 75) = .55 and thus P(Finish > 75) = 1 - .55 = .45