Sie sind auf Seite 1von 11

Chapter 18

THE GOLDSTRIKE AUTOCLAVE PLANT


DESIGN, COMMISSIONING AND OPERATION

K.G. Thomas
Senior Vlce President, American Barrick Resources Corp., Toronto, ON

H. Pieterse
Assist. Vlce President-Engineering, American Barrlck Resources Corp., Elko, NV

R. Williams
Autoclave General Foreman, Barrlck Goldstrlke Mines, Inc., Elko, NV

K.S. Fraser
Senior M e t a l l u r g i s t , Kilborn Limited, Toronto, ON

J .R. Goode
Manager o f Metallurgy, Kllborn Limited, Toronto, ON

ABSTRACT i s about 40 km (25 miles) northwest of


the town o f C a r l l n which I s situated on
The Goldstrike autoclave p l a n t i s I n t e r s t a t e Highway 80. The s i t e I s
designed f o r the pressure oxidation o f about 1700 m (5576 f t ) above sea l e v e l
1363 t / d (1500 stpd) o f r e f r a c t o r y gold I n the Tuscarora Mountains.
ore. The p l a n t was commissioned i n
e a r l y February 1990 over a one week I n i t i a l Goldstrike Operations
period - an unusually short period f o r a
p l a n t o f t h i s complexity. The rapid Shallow, low-grade mineralization was
p l a n t start-up i s a t t r i b u t e d t o c e r t a i n discovered by diamond d r l l l i n g I n the
d e t a i l e d design and c o n t r o l aspects o f Goldstrlke area I n the 1960's. A heap
the plant. leach operation was established I n the
mid-1970's by the previous owners.
This paper discusses key features o f
the autoclave p l a n t w i t h emphasis on the The Post deposit was discovered I n
design o f the splash/flash system o f 1982. Gold production by mining and
heat recovery and the control systems. heap leaching reached 1 t / a (40,000
Commissioni ng and p l a n t operations over
the f 1r s t three months are reviewed.
oz/a) .
American Barrick purchased t h e
property I n 1987 and s t a r t e d an
BACKGROUND aggressive program of deep d r i l l i n g .
This l e d t o the discovery o f the Deep
Locatl on Post/Betze deposit and establ ished
s u f f i c i e n t reserves t o j u s t i f y an
The Goldstrlke property i s located I n i n i t i a l 4100 t / d (4500 stpd) m i 11 and a
Eureka County i n north-central Nevada on 5 500 000 t / a ( 6 m i l l i o n tons/a) heap
the C a r l i n geological trend. The mine leach operation.
181
182 ADVANCES IN GOLD AND SILVER PROCESSING

Geology and Reserves Oxlde M i l l

The deeper deposits occur i n s i l t y The Goldstrike oxide m l l l was


limestones which have been s i l i c i f i e d commissioned on August 5, 1988 w i t h a
and a r g i l l i z e d . Gold i n t h e sulphide capacity o f 4100 t / d (4500 stpd). The
ore occurs mainly as inclusions i n f i n e - p l a n t incorporates a jaw crusher, a 1865
grained p y r i t e and marcaslte. Oxidized kW (2500 hp) semi-autogenous (SAG) m i 11
ore l i e s i n t h e upper p a r t s o f t h e and two b a l l m i l l s w i t h a t o t a l o f 2275
deposit. kW (3050 hp). Ground ore i s c l a s s i f i e d
i n cyclones and cyclone overflow t r e a t e d
Total ore reserves have increased f o r gold recovery i n a conventional
dramatically as more d r i l l i n g has been carbon-in-leach (CIL) c i r c u i t .
performed. Reserves which stood a t 18 t
(0.6 m i l l i o n ounces) o f gold a t Loaded carbon i s s t r i p p e d using the
a c q u i s i t i o n increased t o over 620 t (20 h i g h temperature Zadra process. Gold i s
m i l l i o n ounces) a t t h e end o f 1989. recovered from the s t r i p s o l u t i o n by
Almost 90% o f the gold i s i n r e f r a c t o r y electrowinning. Cathodes are t r e a t e d i n
sulphide ore. This makes autoclavlng a r e t o r t f o r mercury recovery before t h e
p a r t i c u l a r 1y important t o Barrick. gold i s r e f i n e d I n an induction furnace.

Betze Development Plan Overview I n 1989/1990, t h e oxide m l l l capaclty


was increased t o 5500 t / d (6000 stpd)
The $400-mi 11i o n Betze Development through t h e a d d i t i o n o f a cone crusher
Plan was announced on January 9, 1989. i n t h e SAG c l r c u l t , increasing the m l l l
The Plan involves the staged expansion speeds, modifying t h e m l l l l i n e r s and
o f f a c i l i t i e s a t Goldstrike t o permit grates and changing t h e CIL c i r c u i t .
t h e annual production o f up t o 30 t (1 The c i r c u i t I s shown i n Figure 1.
m i l l i o n ounces) o f gold.

D e t a i l s o f the Plan have changed as


JAW SAG

-
the deposit has become b e t t e r defined. CRUSmR WL
The sequence i s summarized i n Table 1. I

I CYCLONE I
1990 Oxide 4 100 I '1 .-e LUTOCLAVE RESDUE I
Sulphlde 1360
5460 6.2

1991 Oxide 4 100


Sulphlde 1 360
5 460 12.2
I I
1992 Oxide 6 100 Figure 1 Goldstrike Oxide C i r c u i t
Sulphlde 5 500
11 600 11.5 DEVELOPMENT PROGRAM
1993 Oxide 0 I n i t i a l Testwork and Studies
Sulphlde 11 600
11 600 31.0 B a r r i c k and K i l b o r n s t a r t e d an
i n t e n s i v e program o f testwork when t h e
importance of Goldstrike's r e f r a c t o r y
Table 1 Betze Developlent Plan ore became apparent. E a r l i e r testwork
GOLDSTRIKE AUTOCLAVE PLANT DESIGN 183

produced the data o f Table 2. Flotatlon


t e s t s showed only 75% gold recovery t o a
bulk, 20% mass p u l l , concentrate. 7 g/t (0.2 oz/st)
Silver 1 g/t ( .02 oz/st)

I PROCESS RECOVERY -%
I Copper
Lead
Zinc
Cyanidation 10 t o 20 Iron
Chlorlnatlon 15 t o 40
-

'
Flotatlon,Roast
with T a l l s Leach
Whole Ore Roast 75
Pressure O X I ~ .
50

88
t o 60
t o 85
t o 95
I Sulphur
Sulphur

Carbon - Total
Total
- Sulphlde
2.5 %
2.1 %

1.36 %
I
Carbon - as C 4 3.5 %
I Carbon - Organlc 0.75 %
fable 2 Recovery frm Goldstrike O r e -
I n i t i a l Test Data

Prellmlnary economlc analyses clearly


I
I
Mercury
Arsenic
Table 3 Goldstrike Ore Analysis
26 PPm
0.15 %
I

showed t h a t pressure oxidation was the


preferred process. I n t h i s operation
the gold-bearing sulphldes are oxidized oz/st). Fine sulphides (20 micrometres)
using oxygen gas under elevated pressure assay as high as 170 g/t (5 oz/st).
and temperature. Oxidation destroys the
sulphide structure and exposes the gold Thickening. Tests and prel lminary
thereby maklng It more amenable t o studies showed that an autoclave feed
cyanldation. Detailed study o f the containing a t least 40% solids was
process was in l t l ated. desirable. This would require 50%
sollds i n the feed t o the pre-heat
D e f i n i t i v e Tests and Studies system. A thickener would therefore be
required t o partially dewater the
D r l l l data and orebody model l i n g grinding cyclone overflow. Tests showed
established the t y p i c a l ore compositlon that a hlgh r t e type t h i c ener sized
sunmarlzed i n Table 3. f o r 8.8 t/d.
suitable.
-3 5
(0.9 stpd/ft ) would be

The metallurgical team designed a


detailed program o f testwork. An Carbonate Reduction, Tests Indicated
i n i t l a l serles o f bench scale tests was that the Goldstrlke ore was preferably
undertaken by Lakefield Research, oxidized i n the presence o f 10 t o 15 g/L
Ontario, Canada. A program o f p i l o t o f free sulphuric acld. Oxidation o f
plant t e s t s was then designed and the sulphides produces acid but
several laboratories Invited t o make carbonates i n the ore consume acld. To
proposals. The work was awarded t o ensure that oxidation takes place under
Hazen Research, Golden, W. acid conditions, excess carbonate must
be destroyed before the ore enters the
Principal flndlngs o f the definitive autoclave.
bench and p i l o t scale t e s t s were:
Pr The batch tests
Mlneraloav. Pyrite and marcaslte are established that the rate o f oxldatlon
the maln sulphldes with minor quantities Increased with free acid content o f the
of arsenopyrite, pyrrhotite and slurry. Tem rature variations i n the
chalcopyrite. Most o f the gold occurs
as 0.5 micrometre grains i n p y r i t e and
IY
range o f 185 c (365OF) t o 225'~ ( 4 3 7 ' ~ )
had only minor impact on the overall
marcasite. Coarse sulphides (200 rate o f oxidation, other factors being
micrometres) contain up t o 16 g / t (0.5 constant. Design resldence times o f
184 ADVANCES IN GOLD AND SILVER PROCESSING

75 minutes were required f o r 95%


sulphlde oxidation a t an oxygen p a r t i a l I PLANT CONFIGURATION COST 1
pressure o f 345 kPa (50 p s i ) .

Neutrallzatlon Several 3 lines, 6 compartment 71


autoclave plants separate the oxidized horizontal, splash/f lash
s l u r r y i n t o l i q u i d and s o l i d f r a c t i o n s heat exchanger (HX)
by thickening. Acidic solutions are
neutralized and p r e c i p i t a t e d s o l i d s
discarded. Oxidized s o l i d s are washed
f r e e o f solute and neutralized before
I 3 lines, 6 compartment
horizontal, double pipe HX 69 I
CIL treatment. On some ores t h i s 4 11nes , 5 compartment 74
treatment y i e l d s improved gold recovery. horizontal, splash/flash HX
I t i s also a means o f cooling the
autoclave product p r i o r t o CIL
processing. 1 2 lines, 7 v e r t i c a l pots
per 1lne, splash/flash HX 68 1
The separate treatment route requi res 2 lines, 6 v e r t i c a l pots 69
expensive, acid-proof thickeners and two per l i n e , splash/flash HX
separate n e u t r a l i z a t i o n c i r c u i t s . Tests
on Goldstrike ore showed t h a t a bulk
n e u t r a l i z a t i o n step would work well.
Design requirements were established. 1
1
2 lines, 8 v e r t i c a l pots
per l i n e , double pipe HX

Comparing Type o f Vessel and Heat


65 1
I

P i l o t Plant. The basic autoclave p l a n t


flowsheet was established from the bench Exchanger. 1988 data, 4500 t / d plant.
t e s t data and preliminary economic
analyses. Major elements o f the
proposed p l a n t were then tested i n a Final Design C r i t e r i a
continuous p i l o t operation.
The various t e s t programs and
During t h e p i l o t plant operation, a comparat ive studies were used t o develop
t o t a l o f 3 t o f Goldstrike ore were the general flowsheet o f Figure 2. The
processed through a 24 L capacity f i n a l process design c r i t e r i a are
autoclave. Six t e s t campaigns were sumnarized i n Table 5 .
completed processing up t o 10 kg/h
during runs o f about 60 h duration each.

- 0 Throughout the
development period various mini-studies
were conducted t o guide the testwork and
permit selectlon o f the f i n a l design.
The economic r e s u l t s o f a t y p i c a l study
are presented i n Table 4 . Plant
o p e r a b i l i t y , a v a i l a b i l i t y , c a p i t a l and
operating costs featured i n the
selectlon process as well as economic
factors.

A spreadsheet template was developed


t o solve the complex material and
thermal balances around the autoclave.
This proved essential t o the rapid
assessment o f a l t e r n a t i v e p l a n t I
k i g u r e 2 Ooldstrike Autoclave C i r c u i t
configurations.
GOLDSTRIKE AUTOCLAVE PLANT DESIGN

I UNITS DATA 1 the f i r s t o f two 12 m dia. x 13 m (40'


dia. x 42') acidulatlon/surge tanks.
Sulphuric acid i s added t o destroy
Genersl s u f f i c i e n t carbonate t o give a minimum
Average Feed Rate t/d 1360 required f r e e a c i d i t y l e v e l i n the
stpd 1500 autoclave discharge. A i r i s injected
Plant Avai lab11l t y X 85 i n t o the acidulation tanks t o s t r i p
Thickener carbon dioxide. The second tank also
Cyclone O/F Solids X 38 acts as a surge tank providing enough
Thickener Type High Rate feed t o keep the autoclave plant
Feed Sol ids X 12 operational when the grinding c i r c u i t i s
U/F Solids X 50.0 processing oxide ore.
U n i t Rate t/d. m1 8.8
Pressure Oxldatlon Splash/Fl ash Heat Exchange
Reaction Temp. OC 225
"F 437 Ore s l u r r y i s pre-heated t o 177'~
Oxygen Pressure Kpa 345 (350"~) i n a series o f three splash
PSI 50 condensers. The heat source I s l i v e
Design React. Time min 75 steam released from the autoclave
Sulphlde Oxldatlon X 95 discharge i n f l a s h vessels.
Oxygen Consumed kg/kg S 3.1
Oxygen U t i l i z a t i o n X 60
Vessel Canpartments 5 A l l three condensers are 2.3 m
-
Heat Recoverv Tmceratures i n t e r n a l diameter (1.d.) by 9.1 m side
System Feed OC 32 wall height (7.6'i.d. x 30'). The
Vessel Feed OC 177 carbon steel vessels are l i n e d w i t h acid
Approach Temp. OC 3 b r i c k and provided w i t h splash t r a y s t o
Peak CIL Feed OC 27

Main System
-
Heat Recovery Svstenog
Splash/Flash
maximize contact between steam and feed
slurry.
Number o f Stages 3 The bottan o f each vessel acts as a
Final Cooling Shell and Tube pumpbox f o r the inter-stage f w d pumps.
I I These consist o f a s i n g l e operating pump
Table 5 Simplified Design C r i t e r i a f o r
Goldstrlke Phase 1 Autoclave Plant. between the f i r s t and second splash
tower and a two-stage system between the
second and t h i r d tower. A1 1 inter-stage
pumps are 6" x 4" Denver Orion units.
PLANT DESIGN The high pressure ( t h i r d ) condenser
product i s pumped by two Geho ZPM 600
Feed Source and Preparation s l u r r y pumps i n t o the autoclave. Each
pump can d e l i ver approx imatel y 60% o f
Sulphide ore i s campaigned through the required feed r a t e t o the autoclave.
the crushing plant and stockpiled When one pump i s shut down f o r valve
separately. The Goldstrlke grinding maintenance o r other work, the second
plant i s operated on oxide ore f o r about pump i s operated a t maximum speed.
18 h/d and sulphide ore f o r 6 h/d. The Therefore planned shutdowns do not
grinding m i 11s are flushed out between seriously affect plant avai lab1l i t y .
ore changes. Cyclone overflow i s pumped
t o the 30 m (100 ft) diameter pre- Autoc 1eve
oxidation thickener when sulphides are
being processed. The autoclave vessel i s 4.12 m 1.d.
by 18.5 m tangent t o tangent (13.5' 1.d.
During about 18 h every day the x 60.9'). I t has a proprietary
thickener underflow i s recirculated. membrane/brick l i n i n g suitable f o r acid
When new feed i s entering the system, service. The vessel i s i l l u s t r a t e d I n
the thickener underflow i s advanced t o Figure 3.
ADVANCES IN GOLD AND SILVER PROCESSING

I pressure from the s l u r r y . As the


pressure I s lowered, p a r t o f the water
i n the s l u r r y i s evaporated thereby
cooling the s l u r r y .

Control led pressure reduct ion takes


place i n a series o f three f l a s h tanks.
SLURRY-/ LAGITATOR
&SLURRY Each i s provided w l t h a r e s t r i c t i o n
INLET MANHOLE OUTLET o r i f i c e (choke) through which the s l u r r y
-
PLAN (TYP)
passes. Each choke i s sized f o r a
'OR predetermined pressure drop selected t o
give the required thermal balance. As
an example, the f i r s t (high pressure)
f l a s h tank I s equipped w l t h a 71 mm
(2.8") choke designed t o create a
pressure drop o f 2.2 HPa (320 p s i ) a t
the design flow rate. I n contrast the
l a s t stage u n i t has a 89 mm (3.5") choke
ELEVATION
and a pressure drop o f only 275 kPa (40
psig).
Figure 3 General Arrangement of Autoclave
A l l three f l a s h tanks are 3 m 1.d. by
3.7 m tangent t o tangent (10' 1.d. x
Each o f the f i v e compartments i s 12') and have a side o u t l e t f o r s l u r r y
provided w l t h a 93 kW (125 hp) mixer discharge. Thls ensures t h a t there i s a
mechanism. Shafts are equipped w l t h a pool o f s l u r r y I n the vessel a t a l l
double mechanical seal. A sophisticated times t o protect the b r i c k l i n i n g o f the
seal water cooling/flushing system I s flash tank from d i r e c t s l u r r y
provided. Each mixer i s mounted on a impingement. Thls feature has been
flange sized t o permit removal o f the missed from other desi gns and resulted
mechanism, shaft and impeller without i n rapid f a i l u r e o f the l i n i n g due t o
dismantling the assembly. abrasion effects.

Oxygen i s introduced t o each The steam from each f l a s h tank i s


compartment through a d i p tube extending ducted t o the corresponding splash
t o beneath the impeller. condenser t o preheat the feed t o the
autoclave. A t one p o i n t i n the design,
Steam can be admitted through a the team considered the use o f cyclones
second plpe t o pre-heat the vessel o r t o prevent the carry-over o f s l u r r y
provide supplementary heat i f sul phide droplets i n the steam. However t h i s
levels are low. Cooling water can be concept was rejected i n favour of larger
added through the same plpe t o l i m i t the f l a s h tanks and steam ducts.
temperature i f necessary. Thls may be
required I n t h e l a s t few compartments - The larger f l a s h tanks also provide
especially i f sulphur l e v e l s are very greater inter-stage surge capacity and
high. improve c i r c u i t control.

Slurry Cooling The configuration o f a flash/splash


u n i t i s i l l u s t r a t e d i n Figure 4.
Slurry e x i t s the autoclave a t about
225'~ (437'~). A target temperature o f Flash evaporation i s not e f f e c t i v e
2 7 ' ~ ( 8 0 ' ~ ) was set f o r the CIL feed t o below the b o i l i n g p o i n t o f water.
minimize carbon loading problems and Therefore shell-and-tube heat exchangers
cyanide consumption. are used t o reduce the s l u r r y
temperature t o t h e desired CIL feed
An i n i t i a l s l u r r y cooling stage temperature. A cooling tower i s used t o
involves the controlled release o f dispose o f low grade heat.
GOLDSTRIKE AUTOCLAVE PLANT DESIGN 187

t / d (175 stpd) cryogenic plant located


FROM FEED adjacent t o the autoclave plant.

SPLASH
"3r The oxygen plant Includes 530 t (580
s t ) o f l l q u l d oxygen storage capaclty as
a precautlon.agalnst oxygen production
problems. Up t o 8 t / d (9 stpd) o f
l l q u l d oxygen can be produced f o r
CONDEN
storage.

Hlgh pressure oxygen I s dellvered t o


the autoclave through a blow-out tank
and other safety devlces t o ellmlnate
the p o s s l b l l l t y o f s l u r r y belng blown
back t o the oxygen plant.
TO HIGH PRESSURE
SPLASH CONDENSER
FEED PUMPS Clme. Lime I s stored I n a 230 t (250
s t ) capaclty s l l o before slaklng I n a
I ~ l g u r e4 Arrangmmt o f ~ n t e m i a t ; detention type u n l t . Slurry contalnlng
Pressure Splash/Flash Cool ing/Heating 15% s o l i d s I s held I n a 7.6 dla. x 7.6 m
Systen (25' x 25') storage tank and d l s t r l b u t e d
through a loop l l n e .

Steam. Steam I s provlded from an 18 t / h


(40,000 lb/h) capaclty, 4.1 MPa (600
p s l ) bol l e r . The water q u a l l t y a t the
Neutrallzatlon and CIL Goldstrlke s l t e i s poor. An elaborate
water treatmant plant I s provlded
Cooled s l u r r y I s pumped t o the f l r s t Including c l a r l f l e r s , polymer traps,
o f three n e u t r a l l z a t l o n tanks connected reverse osmosl s and demlneral lzers.
I n series. The acld I n the s l u r r y I s
neutralized w l t h llme s l u r r y . I t was A blow-out tank and other safety
Intended t o pump neutral s l u r r y t o the devlces are provlded t o prevent back-
CIL c l r c u l t when the grinding c l r c u l t I s flow of s l u r r y t o the b o i l e r .
handllng sulphldes. As noted below,
t h l s strategy has been revised. Alr. The autoclave plant I s provlded
w l t h hlgh pressure Instrument and plant
Reagents and U t l l l t l e s a l r compressors and a low pressure
process a1r compressor.
Flocculant. A packaged flocculant
system i s used f o r the preparation and Plant Layout
dlspenslng of reagent used f o r the
thickener. Deslgn capaclty I s 250 kg/d 'The arrangement o f the autoclave
(530 lb/d). p l a n t was developed by a team t h a t
Included several operators w i t h e a r l i e r
Concentrated acid I s autoclave plant experlence. The team
displaced from road tankers by dry a l r had a c l e a r understanding o f the
i n t o a 330 t capaclty storage tank. I t operating and malntenance problems
I s dispensed from a loop l l n e t o the created by unsatisfactory layout a t
acldulatlon tanks. Acid consumptlon other autoclave plants.
varies w l t h ore carbonate content.
Design acld handllng capaclty I s 39 t / d The team ensured t h a t good crane
(43 stpd). access was provlded t o a l l pumps,
agltators, large s l u r r y valves and other
Oxvnen. Big Three I n d u s t r i a l Gas, I n c hlgh maintenance Items.
o f Houston, TX own and operate the 160
188 ADVANCES IN GOLD AND SILVER PROCESSING

An important f a c t o r i n the design was Materials o f Construction


the f a c t t h a t the p l a n t w i l l be expanded
i n l a t e r phases o f the Development Plan. Acidic pressure oxidation presents
special, and p o t e n t i a l 1y severe,
It should also be noted t h a t the corrosion and abrasion problems.
Goldstrike s i t e i s extremely r e s t r i c t e d . Materials s e h c t e d f o r the Goldstrike
This required a compromise between good p l a n t are presented i n Table 6.
access t o equipment and a compact plant.
The r e s u l t i n g layout i s shown i n Figures
5 and 6. ITEM WETTED SURFACE
Thickener Painted Steel
Acidulation Tk. Chlorobutyl Rubber
Acidulation Agit. Chlorobutyl Rubber
SPLASH Splash Tks. Acid-proof Brick
CONDENSERS Inter-stage Pumps High C r I r o n
Geho - Housing CD4MCu
~ e h o- valves CD4MCu
Geho - Diaphragm EDPM
Autoclave Shell Acid-proof Brick
I n j e c t i o n Tubes Hastelloy C276
Auto. Aglt. Shaft T i Grade 12
Auto. Aglt. Imp. T i Grade 5
Flash Tank Walls Acid-proof Brick
Flash Valve Body T i Grade 2
Flash Choke Ceramic

Flash-Splash Steam Ducts


High Pressure Ti
Medium Pressure 20Cb-3
LOW pressure 316 Stainless Steel

Cooler Feed Pumps Chlorobutyl Rubber


Cooler Shell Carbon Steel
Cooler Tubes 316 Stainless Steel
Neut. Tank Chlorobutyl Rubber

r:z /
Neut. Tank Agit. Chlorobutyl Rubber

/ AGITATOR
REM~V-
AUTOCLAVET
J pONDENSEf?
SPLASH Table 6 Materials o f Construction

CONTROL SYSTEMS

D i s t r i b u t e d Control System

The autoclave p l a n t i s provided w i t h


a Bailey Network 90 d i s t r i b u t e d control
system (DCS). The DCS i s provided w i t h
two operator s t a t i o n s providing 15
screens o f process graphics, alarms,
trends and remote s t a r t / s t o p f unct ions.
An engineering workstation i s provided
f o r system configuration.

I I Two process control u n i t s are


Figure 6 Plant Section a t High Pressure provided, one f o r the autoclave and one
Flash Tanks f o r the a n c i l l a r y c i r c u i t s . A t o t a l of
GOLDSTRIKE AUTOCLAVE PLANT DESIGN

about 300 discrete and 100 analogue The rather complex control system
loops are handled by the system. described above worked flawlessly. It
allowed an extremely rapid and trouble-
Thickening and A c i d i f i c a t i o n free cmlssioning.

Thickener underflow pumping r a t e I s Control o f the pre-heat system i s


governed by t h e underflow density. considerably eased through careful
Flocculant i s added a t a pre-set rate. design o f the system geometry. The
vessels are elevated t o ensure a high
Acid i s added t o the acidulation head over suction o f each pump. 'This
tanks a t a pre-set r a t e determined by provides a measure o f passive flow
the l e v e l o f carbonate i n the feed and control and ensures t h a t the pump
the ore flow rate. suction requirements are s a t i s f i e d .
R e s t r i c t i o n o r i f i c e s i n the inter-stage
Splash/Flash System pipe 1ines steepen the system curves and
f u r t h e r improve control. The surge
E f f e c t i v e control o f the splash/flash capacity provided i n the bottom o f the
system I s c r u c l a l t o t h e operation o f vessels also improves c i r c u i t s t a b i l i t y .
the c i r c u i t .
Autoclave
The dynamics o f t h e system are q u i t e
complex making control p o t e n t i a l l y Oxygen i s admitted t o the autoclave
d l f f l c u l t . For example, an increase i n a t a pre-set, control led rate. The
the flow o f cold s l u r r y t o a splash requl red feed r a t e I s calculated from
condenser w i l l cause more s t e m t o the sulphlde sulphur level i n the
condense and reduce the pressure i n the autoclave feed assuming 60% u t i l i z a t i o n
condenser. This reduces the head across and a consumption o f 3.125 kg o f oxygen
the condenser feed pump which causes the per kg o f sulphide sulphur. An
flow t o increase even f u r t h e r . additional, f i x e d amount o f oxygen I s
added t o compensate f o r vent losses.
The primary controlled variable i n
the system I s t h e flow r a t e between the As i n e r t gases, such as nitrogen and
intermediate and high pressure splash carbon dioxide, accumulate i n the
condenser. Flow r a t e i s sensed w l t h a autoclave atmosphere, the pressure tends
magnetic flowmeter and controlled by a t o Increase. A vent valve I s used t o
variable speed pump. The level i n the remove i n e r t s and control autoclave
high pressure splash condenser i s used pressure. Attempts t o use an on-line
t o control the speed o f the autoclave oxygen analyzer have so f a r met w l t h
feed pump. only l i m i t e d success.
A cascade l e v e l / f low system i s used Steam i s added t o the f i r s t and
t o control the r a t e a t which s l u r r y i s second autoclave compartments t o control
pumped from the low pressure t o the the temperature t o pre-set levels.
intermediate pressure condenser. The Water i s automatically added t o the l a s t
level i n the intermediate condenser i s three compartments t o control
used t o modify the set p o i n t on a flow temperatures.
control loop on the lntermedlate
condenser feed pump. A nuclear source and detector array
determine the level i n t h e l a s t
The feed t o the low pressure compartment. The choke valve on the
condenser I s governed by t h e s l u r r y f i r s t flash tank i s modulated t o hold
level I n t h a t vessel. the desired level.
The low pressure condenser I s Sampl 1ng
operated a t atmospheric pressure. The
other two splash condensers are provided The autoclave plant i s provided wlth
w l t h pressure controlled vent valves. sampling systems t o allow proper
ADVANCES IN GOLD AND SILVER PROCESSING

assessment o f operating performance. operating torque requirements a f t e r a


Sampling systems generally consist o f a few valve cycles. These problems were
primary t h i e f sampler followed by a accomnodated during t h e start-up. The
secondary moving pipe type sampler. valves have since been modified by t h e
Energy d i s s i p a t i n g tanks have been a d d i t i o n o f hard surfacing on the
provided between the two samplers. trunnions and bearing surfaces and the
addition o f l u b r i c a n t t o the trunnion.

CONSTRUCTION AND COMMISSIONING TrWD Oversize. E a r l i e r operation o f


the p l a n t was made d i f f i c u l t by the
General Schedule presence o f coarse ore p a r t i c l e s .
Construction debris was also a minor
Authorization f o r t h e autoclave annoyance. Problems were eliminated by
p r o j e c t was given i n mid-September, the re-routing o f sump l i n e s and the
1988. The order f o r t h e longest addition o f second stage t r a s h screens
d e l i v e r y item, the autoclave was awarded on the p l a n t feed .
immediately. The autoclave was received
on s i t e i n mid-June, 1989. I n s t a l l a t i o n Feed D i l u t i o n . Feed t o the autoclave
o f the l i n i n g system and acid curing was pre-heat c i r c u i t was o f lower than
completed a t the end o f September 1989. desired s l u r r y density during the f l r s t
few days o f operation. D i l u t i o n was
The i n s t a l l a t i o n o f process and reduced by re-routing o f sump lines.
service piping and the inspection and
cleaning o f the oxygen systems were Strainer Blockage. Perforated basket
completed i n mid-January 1990. s t r a l n e r s are provided on the suction
l i n e s o f the autoclave feed pumps.
Slurry was f l r s t admitted t o the These are intended t o protect the
autoclave i n l a t e January and continuous p o s i t l v e displacement pumps from damage
operation achieved on February 2, 1990. by coarse debris. During startup, the
Production data from t h a t date are s t r a l n e r s required frequent cleaning
discussed below. because o f tramp oversize.

Check-out and Comissionlng Problems More recently the s t r a i n e r s have


agai n requi red frequent clean1 ng .
The
There were remarkably few problems entrapped material i s scale. This
during the check-out and comnissioning originates i n the high pressure splash
period. The main problems were as condenser, becomes detached from the
follows: walls and entrapped by t h e strainer.
Under some c i rcumstances, p a r t la11y
Agitator Seals. The double mechanical blocked s t r a i n e r baskets have resulted
seals supplied w i t h the autoclave i n erosion perforation o f the s t r a i n e r .
a g i t a t o r s were of a modified design.
Retaining pins were inadequate f o r the
torque and sheared. The problem was OPERATING RESULTS
eliminated by increasing the strength
and the number o f pins. The addition o f Plant Throughput
glycol t o the closed-loop cooling f l u i d
system also helped by acting as a The p l a n t throughput has increased as
l u b r i c a n t a t the seal face. r e s t r i c t i o n s have been I d e n t i f i e d and
eliminated. Daily tonnages i n excess o f
1820 t / d (2000 stpd) have been comnon.
B a l l Valves. Trunnion mounted b a l l
valves are i n s t a l l e d as block valves Plant a v a i l a b i l i t y has also shown a
around the autoclave and t o prevent steady improvement. Seven-day running
back-flow from the high-pressure splash averages i n excess o f 96% have been
condenser. I n i t i a l operations w i t h achieved. The average a v a i l a b i l i t y over
these valves indicated very high the f i r s t three months was 77%.

Das könnte Ihnen auch gefallen