CLIENT : ASHGHAL
REVISION : 01
PETROSERV LTD
P.O.BOX: 7098
DOHA-QATAR
METHOD STATEMENT FOR 729/2-GEN-DOC-0113
PETROSERV LTD INSTALLATION OF GATE Revision 0
DOHA - QATAR VALVES AND CHECK VALVES Date 10.10.2012
(PS-17,PS40 & PSW1) Page 2 of 38
INDEX
1. PURPOSE:
The Purpose of this Method Statement is to installation of valves in pumping stations PS-
17, PS40 & PSW1 and describes the sequence of activities involved in.
2. SCOPE OF WORK
METHOD STATEMENT FOR 729/2-GEN-DOC-0113
PETROSERV LTD INSTALLATION OF GATE Revision 0
DOHA - QATAR VALVES AND CHECK VALVES Date 10.10.2012
(PS-17,PS40 & PSW1) Page 4 of 38
This document applies to manage efficiently and control the supply and install of valves and
accessories s in the pumping station on going to attain the zero tolerance accident.
1. Jack hammer
2. Hand tools (sprit level, torque wrench, spanner and screw driver sets).
3. Crane capacity 20-50 ton.
4. Chain Block (2 ton)
5. Grinding and drilling machine.
6. Wire rope /nylon slings.
7. Ladders.
8. Fork lift.
5. RESPONSIBILITY
5.5 SAFETY OFFICER: -(these responsibilities are included but not limited to):
5.5.5 Ensures first aid and emergency procedures for the site are established and
maintained.
5.5.6 Coordinates with the client for any safety related requirements at site.
5.5.7 Arranges safety induction program for the site personnel as required. He ensures
that daily toolbox meetings are conducted by Site foremen/Supervisor.
1. QA/QC Engineer along with project engineer will monitor that all components are
installed as per contract specifications and approved submittals.
All work shall be carried out in accordance with approved PETROSERV’s project
safety plan. All personnel shall be provided with necessary personnel protection
equipment (PPE) and given required training to ensure that all personnel involved in
the work are aware of importance of safety precautions, equipments and consequences
of abusing them. Excavation permits will be prepared to ensure that all necessary
precautionary measures have been taken and other requirements are fulfilled.
METHOD STATEMENT FOR 729/2-GEN-DOC-0113
PETROSERV LTD INSTALLATION OF GATE Revision 0
DOHA - QATAR VALVES AND CHECK VALVES Date 10.10.2012
(PS-17,PS40 & PSW1) Page 7 of 38
c) Whenever possible covers shall be lifted using lifting keys and proper lifting
and handling techniques or by the use of hydraulic or other approved manhole
lifting device.
d) Before entering the manhole ensure that the cover has been removed to give
natural ventilation for minimum of 5 minutes.
e) Before enter the drywell and wet well proper ventilation will be used.
f) Test for toxic and flammable gases, and oxygen deficiency, using approved
detector. If toxic and flammable gases or oxygen deficiency is detected do not
enter the manhole.
g) Before the any lifting activity the area is cordon off with safety ribbons/tape.
h) All machine, vehicles & equipments operator shall have valid licences or
certificate or approval.
i) Proper and safe support temporary supports, scaffolding, platform and access
ladders will be provided. Erect and inspect the temporary works by authorized
specialist.
j) The approved electrical lockout/tag out safety procedure (doc no. 729/2-gen-
doc-0055) will be fallowed strictly followed & also approved HSE PLAN.
k) Refer H.S.E plan clause and there sub classes 16, 17, 18, 19, 20, 21, 22, 23, 25,
26, 27, 33, 34, 36, 39, 40. Document No.729/2- GEN-
DOC-0019)
7. PREPARATIONS:
METHOD STATEMENT FOR 729/2-GEN-DOC-0113
PETROSERV LTD INSTALLATION OF GATE Revision 0
DOHA - QATAR VALVES AND CHECK VALVES Date 10.10.2012
(PS-17,PS40 & PSW1) Page 8 of 38
A. DOCUMENTS
a. Entry permits from Ashghal to enter pumping station.
B. Confined space permit.
C. Lock out/tag out (LOTO).
D. Permit of work.
1. Mechanical Screen.
2. Penstock.
3. EOT Cranes.
4. Ductile Iron Pipes & Fitting.
5. Valves and actuators
6. Dry Submersible Main Pumps.
7. Sump and Transfer Pump
8. Odour Control Unit.
9. High Pressure and Potable Pump
10. Air conditioning & Ventilation.
11. Instrumentation & control system.
12. Electrical items.
13. Civil work.
9. (A) PRE-REQUIRMENTS:
1. Ensure that approved materials are available to carry out the work.
METHOD STATEMENT FOR 729/2-GEN-DOC-0113
PETROSERV LTD INSTALLATION OF GATE Revision 0
DOHA - QATAR VALVES AND CHECK VALVES Date 10.10.2012
(PS-17,PS40 & PSW1) Page 9 of 38
2. Valves are transported from stores according to good engineering practice and physical
verification.
3. Prior to commencement of work, areas and access will be inspected to Confirm that safety
precautions ensured.
4. All relative documents (approved shop drawing and approved method statement) will be
checked by site engineer prior to commencement of work.
5. Arrangements of suitable access / scaffolding for erection.
6. Tool box talk will be conducted with all the people involved in the operation and discuss
about the past lifts observations, assign individual responsibilities before starting the job.
recommended equipment.
3. Storage area for valves has to be arranged with leveled wooden platform, the area
Ensure that the vehicle parked in a safe area and parking brake is applied.
6. The valves should not come into contact with any contaminative substances prior to
installation.
9. Hand wheels, actuators and gearboxes should not be used as lifting or rigging
points for valves.
METHOD STATEMENT FOR 729/2-GEN-DOC-0113
PETROSERV LTD INSTALLATION OF GATE Revision 0
DOHA - QATAR VALVES AND CHECK VALVES Date 10.10.2012
(PS-17,PS40 & PSW1) Page 10 of 38
10. ITP will be checked for storage and handling, refer the attached ITP
10 INSTALLATIONS OF VALVES:
We have different models of gate valves and non return valves (check valves).
1. Series 54 Gate Valves (size 700 mm to 450 mm)
2. Series 37 Gate Valves (Size 300 mm to 100 mm)
3. Check valves 41/36 (Size 600 mm to 500 mm)
4. Check valves V2-08 (size less than 300 mm)
4. The valves inside the chamber a crane is used for lowering the valve to position.
4.1 Inside the pump station fork lift will be used for transportation and
5. Place the valve between pipe flanges, and insert the bolts.
9. Tighten the bolts in a diagonal sequence to ensure flanges are pulled parallel.
13. Once the valves will be installed, check that the valve still functions correctly by
14. Inside the chamber extension spindle and stem cap will be installed as per approved
drawing.
16. Proper Hand wheel will be installed for hand wheel operated gate valves.
17. For actuators valves connection will be provided as per electrical method statement.
18. All the external debris will be cleaned off from the external surfaces of the valve.
3. Ensure the valve interior through the end ports to determine whether it is reasonably clean and
4. Ensure the mating flanges facings for correct gasket contact face, surface finish and condition.
5. For external chamber the crane is used for lowering the valves to position.
5.1 For inside the pump station use fork lift to transport the valve and chain block to position
the valve.
6. Wooden block will be provided below the flanges for temporary support.
7. Care will be taken that the lever and weight will be free of obstruction in its path of
movement.
8. The weight will be installed at the end of lever and the bolts of weight will be tightened.
10. Insert the gasket between flanges and insert the bolts in the all holes of flange.
METHOD STATEMENT FOR 729/2-GEN-DOC-0113
PETROSERV LTD INSTALLATION OF GATE Revision 0
DOHA - QATAR VALVES AND CHECK VALVES Date 10.10.2012
(PS-17,PS40 & PSW1) Page 13 of 38
11. Bolts will be tightened in a systematic manner to avoid undue stress in the body valve.
This time our well trained working team will be involved with the proper safety equipments (PPE).
Actuators
6 Gate Valves Rising stem, with Spur 450 520
gear box
7 Gate valves Rising stem, with 450 540
Actuators
8 Gate Valves Rising stem, Hand wheel 300 270
9 Gate Valves Rising stem ,with Spur 200 150
gearbox
10 Gate valves Rising stem ,Hand wheel 150 80
11 Gate valves Rising stem ,with spur 150 100
gear box
12 Gate valves Rising stem ,with Bevel 150 100
gear box
13 Gate valves Rising stem ,with 150 100
PS-17 ,PS-40 Actuators
14 and PS-W1 Gate valves Rising stem ,Hand wheel 100 60
15 Swing Check valve with lever, 600 1070
weight, guard and proximity switch
16 Swing Check valve with lever, 500 880
weight, guard and proximity switch
17 Swing Check valve with lever, 300 260
weight, guard and proximity switch
18 Swing Check valve with lever, 100 70
weight, guard and proximity switch
Emergency plan (Section 40) covers all the potential emergencies as per Do. No. : 729/2-
GEN-DOC-0019
14. ATTACHMENTS:
a) Risk Assessments (Page No.19 to 22)