University of Peshawar
Project Planning and Management.
Q1- You have been appointed as a project manager of a youth project in your constituency. Your task is
to develop a youth project based on the needs of the target group. Explain the phases/stages of the
project cycle, this particular project would go through until its completion. Use a relevant example to
illustrate. (15 marks)
Nishat Mills Ltd is the largest textile composite unit in Pakistan. Nishat Linen is a concern of
Nishat Mills, the textile and home fashion retail chain that has redefined the industry with
acute attention paid to quality, design and affordability. Nishat Linen prides itself on being the
brand of preference for discerning customers who are in search of things, unique and chic
without compromising on aesthetics or price. Unsurpassed customer service, including tailor-
made orders, ensures our clientele remains loyal to the Nishat family.
Profit maximization
Cost minimization
MUHAMMAD ADEEL
Institute Of Management Studies
University of Peshawar
Project Planning and Management.
Quality
Maximizing rate of production
Minimizing manufacturing lead time
3- Project Scheduling
Production Network of Nishat Textile Limited
MUHAMMAD ADEEL
Institute Of Management Studies
University of Peshawar
Project Planning and Management.
Activity Activity Name Immediate Time(Days)
Predecessor
A Fabric --- 9
B Inspection A 6
C Singeing and Desizing B 6
D Bleaching C 3
E Inspection D 3
F Setting(on Stenter) E 2
G Dyeing or Printing F 6
H Curing(if Printed) G 8
I Washing (On PAD steam if G 6
dyed)
J Deliver/Calender I 9
K Finish J 2
Draw a network diagram; derive its critical path, EF, ES, LF, LS.
Q3- Nishat linen Wants to open a new factory outlet in Bara Khyber Agency. Make a WBS
for their Construction Activities and Promotional Activities. Prepare a scope statement as
well as suggest how Nishat can effectively control its cost. (15 Marks)