Package Name: CP-08, Supplying,fabrication & Laying of clear water transmission main from Harohalli

DAILY PROGRESS REPORT DATE:16.10.2020


MS PIPELINE WORKS

Sl No Description Previous Day Present Day


1 Edge cutting (Nos) 30.0 3

2 Rolling (Nos) 21.0 0

3 Fit up (Meters) 30.0 0

4 SAW Welding (Meters) 0.0 15

5 Radiography test (Meters) 0.0 0

6 Hydraulic test (Meters) 0.0 0

7 Epoxy coating (Meters) 0.0 0

8 Wrapping of welded mesh (Meters) 0.0 0

9 Guniting (Meters) 0.0 0

CIVIL WORKS

NAME OF THE STRUCTURE WORK PROGRESS STATUS

MANPOWER

Name of Contractor Supervisor Fitter Welder Cutter Grinders

1
SPML 6 3 3 7 4
2

3
ransmission main from Harohalli to Vajarahalli.
DATE:16.10.2020

Present Day Cummulative Quantity


3 33

0 21

0 30

15 15

0 0

0 0

0 0

0 0

0 0

NAME OF THE CONTRACTOR REMARKS

Riggers Operators Helpers Total

5 3 6 37