Beruflich Dokumente
Kultur Dokumente
BUREAU OF CONSTRUCTION
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 0.71% 156,000.00
Part II Other General Requirements 1.40% 308,835.57
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 1.48% 326,826.85
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 27.32% 6,036,544.79
PART C FINISHING WORKS 57.75% 12,756,850.44
PART D PLUMBING/SANITARY WORKS 8.05% 1,777,293.27
PART E ELECTRICAL WORKS 3.30% 729,308.27
Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:
Name & Signature Name & Signature Name & Signature Name & Signature Name & Signature
Position Title Position Title Position Title Position Title Position Title
Planning. Section/Division Planning Section/Division Planning Division
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST
TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
II.5 Project Billboard/ Sign Board 1.00 ea 4,274.69 4,274.69 5,386.11 0.02
II.7 Occupational Safety and Health 1.00 lot 142,359.70 142,359.70 161,435.90 0.64
Project ID
PART A EARTHWORKS
804(1)a Embankment from Structure Excavation 257.76 m3 38,528.28 149.47 188.34 0.17
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days) 384.71 m3 1,497,023.88 3,891.30 4,903.04 6.78
PART C FINISHING
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel) 961.80 m2 807,526.19 839.60 1,057.89 3.66
1003(9) Carpentry and Joinery Works (Blackboard) 1.00 l.s. 45,425.71 45,425.71 57,236.39 0.21
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST
TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1027(1) Plain Cement Plaster Finish 4,355.83 m2 658,571.39 151.19 190.50 2.98
1053(2)a1 38 mm dia. G.I. Pipe Railings 66.00 m 30,108.42 456.19 574.80 0.14
1053(2)a2 50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar stiffener 144.00 m 281,249.81 1,953.12 2,460.94 1.27
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame 661.00 m2 484,837.39 733.49 924.20 2.19
1018(1) Glazed Tiles and Trims 115.51 m2 161,776.15 1,400.59 1,764.74 0.73
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk) 64.20 m 13,528.18 210.72 265.51 0.06
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk) 26.21 m 5,522.29 210.72 265.51 0.02
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk) 128.40 m 41,240.42 321.19 404.70 0.19
1047(6) Metal Structure Accessories, Steel Plates 277.47 kg 19,713.10 71.05 89.52 0.09
1047(7)b Metal Structure Accessories, Sag Rods 293.65 kg 15,756.51 53.66 67.61 0.07
1047(4) Metal Structure Accessories, Cross Bracing 628.56 kg 34,459.52 54.82 69.08 0.16
1047(3)c Metal Structure Accessories, Turn Buckle 52.00 pc 10,985.82 211.27 266.19 0.05
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST
TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1001(8) Sewer Line Works 1.00 l.s. 51,700.29 51,700.29 65,142.37 0.23
1002(6) Cold Water Line Works 1.00 l.s. 43,480.13 43,480.13 54,784.97 0.20
SPL-3 Septic Vault "Type E" 1.00 l.s. 102,273.42 102,273.42 128,864.51 0.46
PART E ELECTRICAL
1100(19) Conduits, Boxes, and Fittings 1.00 l.s. 120,931.64 120,931.64 152,373.87 0.55
1101(18) Wires and Wiring Devices 1.00 l.s. 209,234.39 209,234.39 263,635.33 0.95
1208(1) Fire Alarm System 1.00 l.s. 14,922.42 14,922.42 18,802.25 0.07
FORM POW-2015-01B-00
MINIMUM EQUIPMENT REQUIREMENT
Number of Number of
No. Equipment Description Capacity No. Equipment Description Capacity
Equipment Equipment
1 Backhoe 0.80 m3 1 31
2 Dump Truck 12 yd 3
2 32
3 Plate Compactor 5 hp 1 33
4 Concrete Vibrator 5 amp 1 34
5 Pumpcrete 1 35
6 One Bagger Mixer 4 - 6 ft /min
3
1 36
7 Bar Cutter 1 37
8 Bar Bender 1 38
9 Welding Machine 500 amp 2 39
10 Cutting Outfit 1 40
11 Truck Mounted Crane 20 - 25 mt 1 41
12 Drill Rig, Mechanical Rotary 300 hp 1 42
13 Bentonite Mixer 1 43
14 Bentonite Bin 1 44
15 Water Pump 1,800 lpm, 7.5 hp 1 45
16 Water Truck 16,000 L, 360 hp 1 46
17 Tremie Pipe Set 1 47
18 SPT & Desanding Machine 1 48
19 Tower Lights 2 49
20 50
21 51
22 52
23 53
24 54
25 55
26 56
27 57
28 58
29 59
30 60
SUB-TOTAL SUB-TOTAL
TOTAL
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted 0.71 6.00 mo - - 156,000.00 156,000.00 8% 12,480.00 8,424.00 176,904.00
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 156,000.00 156,000.00 12,480.00 8,424.00 176,904.00
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted 0.02 1.00 ea 3,505.00 699.72 69.97 4,274.69 20% 854.94 256.48 5,386.11
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted 0.64 1.00 lot 137,035.54 5,324.16 - 142,359.70 8% 11,388.78 7,687.42 161,435.90
II.7 Occupational Safety and Health
As Evaluated
As Submitted 0.73 1.00 l.s. - - 162,201.18 162,201.18 8% 12,976.09 8,758.86 183,936.13
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 140,540.54 6,023.88 162,271.15 308,835.57 25,219.81 16,702.76 350,758.14
TOTAL OF PART II
As Evaluated
(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted 0.43 413.71 m3 - 4,246.53 90,965.09 95,211.61 20% 19,042.32 5,712.70 119,966.63
803(1)a Structure Excavation
As Evaluated
As Submitted 0.17 257.76 m3 - 5,377.60 33,150.69 38,528.28 20% 7,705.66 2,311.70 48,545.64
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted 0.53 335.90 m3 67,180.00 7,007.82 43,200.32 117,388.14 20% 23,477.63 7,043.29 147,909.06
804(1)b Embankment from Borrow
As Evaluated
As Submitted 0.34 90.34 m3 54,068.49 15,454.92 6,175.42 75,698.82 20% 15,139.76 4,541.93 95,380.51
804(4) Gravel Fill
As Evaluated
As Submitted 121,248.49 32,086.85 173,491.51 326,826.85 65,365.37 19,609.62 411,801.84
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted 6.78 384.71 m3 1,369,567.60 46,014.21 81,442.07 1,497,023.88 20% 299,404.78 89,821.43 1,886,250.09
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted 15.13 68,853.89 kg 2,745,462.80 404,214.05 192,763.05 3,342,439.90 20% 668,487.98 200,546.39 4,211,474.27
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted 5.42 2,577.60 m2 532,344.32 425,539.54 239,197.16 1,197,081.01 20% 239,416.20 71,824.86 1,508,322.07
903(2) Forms and Falseworks
As Evaluated
As Submitted 4,647,374.71 875,767.80 513,402.28 6,036,544.79 1,207,308.96 362,192.68 7,606,046.43
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted 0.51 300.27 L 99,089.10 12,113.11 1,211.31 112,413.53 20% 22,482.71 6,744.81 141,641.05
1000(1) Soil Poisoning
As Evaluated
As Submitted 99,089.10 12,113.11 1,211.31 112,413.53 22,482.71 6,744.81 141,641.05
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted 0.70 285.37 m2 115,968.66 23,591.33 15,191.46 154,751.45 20% 30,950.29 9,285.09 194,986.83
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted 3.66 961.80 m2 650,301.83 95,638.61 61,585.75 807,526.19 20% 161,505.24 48,451.57 1,017,483.00
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 766,270.49 119,229.94 76,777.21 962,277.64 192,455.53 57,736.66 1,212,469.83
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted 1.44 1.00 l.s 267,447.00 50,729.70 34.99 318,211.69 20% 63,642.34 19,092.70 400,946.73
1010(4) Wooden Doors
As Evaluated
As Submitted 0.51 70.87 m2 62,046.69 45,915.89 4,591.59 112,554.16 20% 22,510.83 6,753.25 141,818.24
1009(1)a Jalousie Window
As Evaluated
As Submitted 2.36 146.88 m2 285,314.40 142,742.88 94,038.29 522,095.57 20% 104,419.11 31,325.73 657,840.41
1005(1) Steel Casement Window
As Evaluated
As Submitted 18.78 65.28 m2 3,353,737.09 479,616.08 315,968.65 4,149,321.81 20% 829,864.36 248,959.31 5,228,145.48
1005(5) Window Grilles
As Evaluated
As Submitted 4.93 43.00 set 1,089,620.00 - - 1,089,620.00 20% 217,924.00 65,377.20 1,372,921.20
1004(2)a Locksets
As Evaluated
As Submitted 0.05 172.00 pc 11,180.00 - - 11,180.00 20% 2,236.00 670.80 14,086.80
1004(2)g Hinges
As Evaluated
As Submitted 0.21 1.00 l.s. 37,200.00 7,477.92 747.79 45,425.71 20% 9,085.14 2,725.54 57,236.39
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 5,106,545.17 726,482.46 415,381.30 6,248,408.94 1,249,681.78 374,904.53 7,872,995.25
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted 1.42 1,161.01 m2 257,163.72 50,879.56 5,087.96 313,131.23 20% 62,626.25 18,787.87 394,545.35
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted 2.98 4,355.83 m2 417,070.72 219,546.06 21,954.61 658,571.39 20% 131,714.28 39,514.28 829,799.95
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted 0.14 66.00 m 24,365.88 2,298.55 3,443.99 30,108.42 20% 6,021.68 1,806.51 37,936.61
1053(2)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar As Submitted 1.27 144.00 m 268,720.62 5,015.02 7,514.16 281,249.81 20% 56,249.96 16,874.99 354,374.76
1053(2)a2
stiffener As Evaluated
As Submitted 2.19 661.00 m 2
357,410.63 115,842.51 11,584.25 484,837.39 20% 96,967.48 29,090.24 610,895.11
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted 0.70 841.24 m 2
119,245.77 32,959.66 3,295.97 155,501.40 20% 31,100.28 9,330.08 195,931.76
1038(1) Reflective Insulation
As Evaluated
As Submitted 0.73 115.51 m2 108,867.55 48,098.73 4,809.87 161,776.15 20% 32,355.23 9,706.57 203,837.95
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted 0.32 50.68 m2 53,538.04 14,772.83 1,477.28 69,788.15 20% 13,957.63 4,187.29 87,933.07
1018(2) Unglazed Tiles
As Evaluated
As Submitted 1,606,382.93 489,412.92 59,168.09 2,154,963.94 430,992.79 129,297.83 2,715,254.56
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted 5.41 4,943.76 m2 599,346.86 542,377.56 54,237.76 1,195,962.17 20% 239,192.43 71,757.73 1,506,912.33
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted 0.23 247.39 m 2
17,754.56 30,156.71 3,015.67 50,926.94 20% 10,185.39 3,055.62 64,167.95
1032(1)b Wood Painting
As Evaluated
As Submitted 0.14 125.09 m 2
15,342.61 14,409.74 1,440.97 31,193.33 20% 6,238.67 1,871.60 39,303.60
1032(1)c Metal Painting
As Evaluated
As Submitted 632,444.03 586,944.01 58,694.40 1,278,082.44 255,616.49 76,684.95 1,610,383.88
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted 2.24 841.24 m2 397,280.03 88,273.52 8,827.35 494,380.91 20% 98,876.18 29,662.85 622,919.94
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted 0.06 64.20 m 12,292.82 1,123.05 112.31 13,528.18 20% 2,705.64 811.69 17,045.51
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted 0.02 26.21 m 5,018.01 458.44 45.84 5,522.29 20% 1,104.46 331.34 6,958.09
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 0.19 128.40 m 39,146.59 1,903.48 190.35 41,240.42 20% 8,248.08 2,474.43 51,962.93
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted 2.73 7,703.59 kg 463,688.71 37,874.83 102,466.17 604,029.70 20% 120,805.94 36,241.78 761,077.42
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted 3.34 10,028.53 kg 611,263.97 39,816.98 86,250.01 737,330.97 20% 147,466.19 44,239.86 929,037.02
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted 0.11 128.40 m 21,166.74 2,354.36 235.44 23,756.53 20% 4,751.31 1,425.39 29,933.23
1003(5)a1 Fascia Board
As Evaluated
As Submitted 0.09 277.47 kg 15,604.45 3,735.14 373.51 19,713.10 20% 3,942.62 1,182.79 24,838.51
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted 0.07 293.65 kg 11,408.30 3,952.92 395.29 15,756.51 20% 3,151.30 945.39 19,853.20
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted 0.16 628.56 kg 25,152.14 8,461.25 846.13 34,459.52 20% 6,891.90 2,067.57 43,418.99
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted 0.05 52.00 pc 9,620.00 1,364.45 1.36 10,985.82 20% 2,197.16 659.15 13,842.13
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted 1,611,641.78 189,318.41 199,743.76 2,000,703.95 400,140.78 120,042.24 2,520,886.97
Sub-Total C.6
As Evaluated
As Submitted 9,822,373.51 2,123,500.86 810,976.07 12,756,850.44 2,551,370.08 765,411.02 16,073,631.54
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted 0.23 1.00 l.s. 42,834.20 8,060.08 806.01 51,700.29 20% 10,340.06 3,102.02 65,142.37
1001(8) Sewer Line Works
As Evaluated
As Submitted 0.20 1.00 l.s. 37,309.81 5,609.38 560.94 43,480.13 20% 8,696.03 2,608.81 54,784.97
1002(6) Cold Water Line Works
As Evaluated
As Submitted 1.05 1.00 l.s. 195,447.14 33,936.84 3,393.68 232,777.66 20% 46,555.53 13,966.66 293,299.85
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted 1.65 1.00 l.s. 333,664.59 28,819.72 2,881.97 365,366.28 20% 73,073.26 21,921.98 460,361.52
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted 0.46 1.00 l.s. 84,694.50 15,980.84 1,598.08 102,273.42 20% 20,454.68 6,136.41 128,864.51
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted 0.15 30.00 units 18,768.24 5,247.90 9,148.41 33,164.55 20% 6,632.91 1,989.87 41,787.33
1001(6)b1 Catch basin
As Evaluated
As Submitted 4.29 1.00 lot 875,153.75 66,706.54 6,670.65 948,530.94 20% 189,706.19 56,911.86 1,195,148.99
SPL-2 Fire Protection System
As Evaluated
As Submitted 1,587,872.23 164,361.30 25,059.75 1,777,293.27 355,458.66 106,637.61 2,239,389.54
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted 0.55 1.00 l.s. 106,537.14 13,085.91 1,308.59 120,931.64 20% 24,186.33 7,255.90 152,373.87
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted 0.95 1.00 l.s. 192,446.10 15,262.08 1,526.21 209,234.39 20% 41,846.88 12,554.06 263,635.33
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted 1.16 1.00 l.s. 251,941.00 3,267.60 326.76 255,535.36 20% 51,107.07 15,332.12 321,974.55
1102(21) Panel Board
As Evaluated
As Submitted 0.58 1.00 l.s. 120,058.00 7,842.24 784.22 128,684.46 20% 25,736.89 7,721.07 162,142.42
1003(1) Lighting Fixtures
As Evaluated
As Submitted 0.07 1.00 l.s. 11,568.00 3,049.47 304.95 14,922.42 20% 2,984.48 895.35 18,802.25
1208(1) Fire Alarm System
As Evaluated
As Submitted 682,550.24 42,507.30 4,250.73 729,308.270 145,861.650 43,758.500 918,928.420
TOTAL OF PART E
As Evaluated
As Submitted 16,861,419.18 3,238,224.11 1,527,180.34 21,626,823.620 4,325,364.720 1,297,609.430 27,249,797.770
TOTAL OF PART III
As Evaluated
As Submitted 17,001,959.72 3,244,247.99 1,845,451.49 22,091,659.190 4,363,064.530 1,322,736.190 27,777,459.910
GRAND TOTAL
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
GRAND TOTAL
As Evaluated
BUREAU OF CONSTRUCTION
FORM ABC-2015-02-00
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING
(Project ID)
(Project Component ID - Description)
CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING
PART II
WORKS
AS SUBMITTED 326,826.85 20.00% 65,365.37 19,609.62 84,974.99 411,801.84
PART A EARTHWORKS
AS EVALUATED
Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:
Name & Signature Name & Signature Name & Signature Name & Signature Name & Signature
Position Title Position Title Position Title Position Title Position Title
Planning. Section/Division Planning Section/Division Planning Division
BUREAU OF CONSTRUCTION
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING
(Project ID)
(Project Component ID - Description)
PART A EARTHWORKS
AS SUBMITTED 413.71 m3 95,211.61 20% 19,042.32 5,712.70 24,755.02 119,966.63 289.98
803(1)a Structure Excavation
AS EVALUATED
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING
100 mm CHB Non Load Bearing Wall (including Reinforcing AS SUBMITTED 285.37 m2 154,751.45 20% 30,950.29 9,285.09 40,235.38 194,986.83 683.28
1046(2)a1
Steel) AS EVALUATED
150 mm CHB Non Load Bearing Wall (including Reinforcing AS SUBMITTED 961.80 m2 807,526.19 20% 161,505.24 48,451.57 209,956.81 1,017,483.00 1,057.89
1046(2)a2
Steel) AS EVALUATED
AS SUBMITTED 1.00 l.s 318,211.69 20% 63,642.34 19,092.70 82,735.04 400,946.73 400,946.73
1010(4) Wooden Doors
AS EVALUATED
AS SUBMITTED 43.00 set 1,089,620.00 20% 217,924.00 65,377.20 283,301.20 1,372,921.20 31,928.40
1004(2)a Locksets
AS EVALUATED
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING
50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing AS SUBMITTED 144.00 m 281,249.81 20% 56,249.96 16,874.99 73,124.95 354,374.76 2,460.94
1053(2)a2
on 19 mm bar stiffener AS EVALUATED
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING
AS SUBMITTED 1.00 l.s. 43,480.13 20% 8,696.03 2,608.81 11,304.84 54,784.97 54,784.97
1002(6) Cold Water Line Works
AS EVALUATED
AS SUBMITTED 1.00 l.s. 232,777.66 20% 46,555.53 13,966.66 60,522.19 293,299.85 293,299.85
1001(9) Downspout/Storm Drain
AS EVALUATED
AS SUBMITTED 1.00 l.s. 365,366.28 20% 73,073.26 21,921.98 94,995.24 460,361.52 460,361.52
1002(5) Sanitary/Plumbing Fixtures
AS EVALUATED
AS SUBMITTED 1.00 l.s. 102,273.42 20% 20,454.68 6,136.41 26,591.09 128,864.51 128,864.51
SPL-1 Septic Vault "Type E"
AS EVALUATED
AS SUBMITTED 30.00 units 33,164.55 20% 6,632.91 1,989.87 8,622.78 41,787.33 1,392.91
1001(6)b1 Catch basin
AS EVALUATED
AS SUBMITTED 1.00 lot 948,530.94 20% 189,706.19 56,911.86 246,618.05 1,195,148.99 1,195,148.99
Fire Protection System
AS EVALUATED
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING
AS SUBMITTED 1.00 l.s. 209,234.39 20% 41,846.88 12,554.06 54,400.94 263,635.33 263,635.33
1101(18) Wires and Wiring Devices
AS EVALUATED
AS SUBMITTED 1.00 l.s. 255,535.36 20% 51,107.07 15,332.12 66,439.19 321,974.55 321,974.55
1102(21) Panel Board
AS EVALUATED
AS SUBMITTED 1.00 l.s. 128,684.46 20% 25,736.89 7,721.07 33,457.96 162,142.42 162,142.42
1003(1) Lighting Fixtures
AS EVALUATED
AS SUBMITTED 1.00 l.s. 14,922.42 20% 2,984.48 895.35 3,879.83 18,802.25 18,802.25
1208(1) Fire Alarm System
AS EVALUATED
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 0.79% 151,666.67
Part II Other General Requirements 1.43% 275,454.79
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 1.47% 283,708.00
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 27.18% 5,248,765.45
PART C FINISHING WORKS 56.88% 10,984,919.46
PART D PLUMBING/SANITARY WORKS 8.75% 1,689,839.15
PART E ELECTRICAL WORKS 3.51% 678,607.54
`
Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:
Name & Signature Name & Signature Name & Signature Name & Signature Name & Signature
Position Title Position Title Position Title Position Title Position Title
Planning. Section/Division Planning Section/Division Planning Division
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)
AS SUBMITTED ASC EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALAUTED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
II.5 Project Billboard/ Sign Board 1.00 ea 4,274.69 4,274.69 5,386.11 0.02
II.7 Occupational Safety and Health 1.00 lot 129,536.30 129,536.30 146,894.16 0.67
Project ID
PART A EARTHWORKS
804(1)a Embankment from Structure Excavation 223.43 m3 33,396.86 149.47 188.34 0.17
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days) 335.41 m3 1,305,182.56 3,891.30 4,903.04 6.76
PART C FINISHING
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel) 838.99 m2 704,415.05 839.60 1,057.89 3.65
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)
AS SUBMITTED ASC EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALAUTED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1003(9) Carpentry and Joinery Works (Blackboard) 1.00 l.s. 37,854.76 37,854.76 47,697.00 0.20
1027(1) Plain Cement Plaster Finish 3,825.21 m2 578,345.31 151.19 190.50 2.99
1053(2)a1 38 mm dia. G.I. Pipe Railings 66.00 m 30,108.42 456.19 574.80 0.16
1053(2)a2 50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar stiffener 127.60 m 249,218.58 1,953.12 2,460.94 1.29
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame 565.91 m2 415,089.76 733.49 924.20 2.15
1018(1) Glazed Tiles and Trims 115.51 m2 161,776.15 1,400.59 1,764.74 0.84
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk) 55.20 m 11,631.71 210.72 265.51 0.06
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk) 26.21 m 5,522.29 210.72 265.51 0.03
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk) 110.40 m 35,459.05 321.19 404.70 0.18
1047(6) Metal Structure Accessories, Steel Plates 277.47 kg 19,713.10 71.05 89.52 0.10
1047(7)b Metal Structure Accessories, Sag Rods 248.16 kg 13,315.64 53.66 67.61 0.07
1047(4) Metal Structure Accessories, Cross Bracing 528.07 kg 28,950.36 54.82 69.08 0.15
1047(3)c Metal Structure Accessories, Turn Buckle 44.00 pc 9,295.69 211.27 266.19 0.05
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)
AS SUBMITTED ASC EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALAUTED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1001(8) Sewer Line Works 1.00 l.s. 48,956.59 48,956.59 61,685.31 0.25
1002(6) Cold Water Line Works 1.00 l.s. 40,653.40 40,653.40 51,223.28 0.21
SPL-3 Septic Vault "Type E" 1.00 l.s. 87,093.88 87,093.88 109,738.29 0.45
PART E ELECTRICAL
1100(19) Conduits, Boxes, and Fittings 1.00 l.s. 105,286.38 105,286.38 132,660.84 0.55
1101(18) Wires and Wiring Devices 1.00 l.s. 199,606.12 199,606.12 251,503.71 1.03
1208(1) Fire Alarm System 1.00 l.s. 14,922.42 14,922.42 18,802.25 0.08
FORM POW-2015-01B-00
MINIMUM EQUIPMENT REQUIREMENT
Number of Number of
No. Equipment Description Capacity No. Equipment Description Capacity
Equipment Equipment
1 Backhoe 0.80 m3 1 31
2 Dump Truck 12 yd 3
2 32
3 Plate Compactor 5 hp 1 33
4 Concrete Vibrator 5 amp 1 34
5 Pumpcrete 1 35
6 One Bagger Mixer 4 - 6 ft /min
3
1 36
7 Bar Cutter 1 37
8 Bar Bender 1 38
9 Welding Machine 500 amp 2 39
10 Cutting Outfit 1 40
11 Truck Mounted Crane 20 - 25 mt 1 41
12 Drill Rig, Mechanical Rotary 300 hp 1 42
13 Bentonite Mixer 1 43
14 Bentonite Bin 1 44
15 Water Pump 1,800 lpm, 7.5 hp 1 45
16 Water Truck 16,000 L, 360 hp 1 46
17 Tremie Pipe Set 1 47
18 SPT & Desanding Machine 1 48
19 Tower Lights 2 49
20 50
21 51
22 52
23 53
24 54
25 55
26 56
27 57
28 58
29 59
30 60
SUB-TOTAL SUB-TOTAL
TOTAL
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted 0.79 5.83 mo - - 151,666.67 151,666.67 8% 12,133.33 8,190.00 171,990.00
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 151,666.67 151,666.67 12,133.33 8,190.00 171,990.00
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted 0.02 1.00 ea 3,505.00 699.72 69.97 4,274.69 20% 854.94 256.48 5,386.11
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted 0.67 1.00 L.S. 124,212.14 5,324.16 - 129,536.30 8% 10,362.90 6,994.96 146,894.16
II.7 Occupational Safety and Health
As Evaluated
As Submitted 0.73 1.00 l.s. - - 141,643.80 141,643.80 8% 11,331.50 7,648.77 160,624.07
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 127,717.14 6,023.88 141,713.77 275,454.79 22,549.34 14,900.21 312,904.34
TOTAL OF PART II
As Evaluated
(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted 0.44 365.45 m3 - 3,751.16 80,353.85 84,105.01 20% 16,821.00 5,046.30 105,972.31
803(1)a Structure Excavation
As Evaluated
804(1)a As Submitted 0.17 223.43 m3 - 4,661.38 28,735.48 33,396.86 20% 6,679.37 2,003.81 42,080.04
Embankment from Structure Excavation
As Evaluated
As Submitted 0.52 288.09 m3 57,618.00 6,010.37 37,051.45 100,679.81 20% 20,135.96 6,040.79 126,856.56
804(1)b Embankment from Borrow
As Evaluated
As Submitted 0.34 78.20 m3 46,802.70 13,378.07 5,345.56 65,526.32 20% 13,105.26 3,931.58 82,563.16
804(4) Gravel Fill
As Evaluated
As Submitted 104,420.70 27,800.97 151,486.34 283,708.00 56,741.59 17,022.48 357,472.07
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted 6.76 335.41 m3 1,194,059.60 40,117.56 71,005.40 1,305,182.56 20% 261,036.51 78,310.95 1,644,530.02
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted 15.07 59,947.73 kg 2,390,340.80 351,929.50 167,829.40 2,910,099.70 20% 582,019.94 174,605.98 3,666,725.62
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted 5.35 2,225.34 m2 459,592.04 367,383.62 206,507.53 1,033,483.19 20% 206,696.64 62,008.99 1,302,188.82
903(2) Forms and Falseworks
As Evaluated
As Submitted 4,043,992.44 759,430.68 445,342.33 5,248,765.45 1,049,753.09 314,925.92 6,613,444.46
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted 0.50 259.98 L 85,793.40 10,487.79 1,048.78 97,329.96 20% 19,465.99 5,839.80 122,635.75
1000(1) Soil Poisoning
As Evaluated
As Submitted 85,793.40 10,487.79 1,048.78 97,329.96 19,465.99 5,839.80 122,635.75
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted 0.75 267.94 m2 108,885.46 22,150.41 14,263.58 145,299.45 20% 29,059.89 8,717.97 183,077.31
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted 3.65 838.99 m2 567,266.31 83,426.74 53,722.01 704,415.05 20% 140,883.01 42,264.90 887,562.96
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 676,151.77 105,577.15 67,985.59 849,714.50 169,942.90 50,982.87 1,070,640.27
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted 1.47 1.00 l.s. 233,127.00 45,481.80 4,548.18 283,156.98 20% 56,631.40 16,989.42 356,777.80
1010(4) Wooden Doors
As Evaluated
As Submitted 0.49 59.98 m2 52,512.49 38,860.38 3,886.04 95,258.90 20% 19,051.78 5,715.53 120,026.21
1009(1)a Jalousie Window
As Evaluated
As Submitted 2.25 122.40 m2 237,762.00 118,952.40 78,365.24 435,079.64 20% 87,015.93 26,104.78 548,200.35
1005(1) Steel Casement Window
As Evaluated
As Submitted 17.90 54.40 m2 2,794,780.91 399,680.06 263,307.21 3,457,768.18 20% 691,553.64 207,466.09 4,356,787.91
1005(5) Window Grills
As Evaluated
As Submitted 5.12 39.00 set 988,260.00 - - 988,260.00 20% 197,652.00 59,295.60 1,245,207.60
1004(2)a Locksets
As Evaluated
As Submitted 0.05 156.00 pc 10,140.00 - - 10,140.00 20% 2,028.00 608.40 12,776.40
1004(2)g Hinges
As Evaluated
As Submitted 0.20 1.00 l.s. 31,000.00 6,231.60 623.16 37,854.76 20% 7,570.95 2,271.29 47,697.00
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 4,347,582.40 609,206.24 350,729.82 5,307,518.46 1,061,503.70 318,451.11 6,687,473.27
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted 1.40 1,000.20 m2 221,544.30 43,832.29 4,383.23 269,759.82 20% 53,951.96 16,185.59 339,897.37
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted 2.99 3,825.21 m2 366,263.86 192,801.32 19,280.13 578,345.31 20% 115,669.06 34,700.72 728,715.09
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted 0.16 66.00 m 24,365.88 2,298.55 3,443.99 30,108.42 20% 6,021.68 1,806.51 37,936.61
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar As Submitted 1.29 127.60 m 238,116.33 4,443.87 6,658.38 249,218.58 20% 49,843.72 14,953.12 314,015.42
1053(3)a2
stiffener As Evaluated
As Submitted 2.15 565.91 m 2
305,994.33 99,177.66 9,917.77 415,089.76 20% 83,017.95 24,905.39 523,013.10
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted 0.69 723.31 m 2
102,529.19 28,339.18 2,833.92 133,702.29 20% 26,740.46 8,022.14 168,464.89
1038(1) Reflective Insulation
As Evaluated
As Submitted 0.84 115.51 m2 108,867.55 48,098.73 4,809.87 161,776.15 20% 32,355.23 9,706.57 203,837.95
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted 0.36 50.68 m2 53,538.04 14,772.83 1,477.28 69,788.15 20% 13,957.63 4,187.29 87,933.07
1018(2) Unglazed Tiles
As Evaluated
As Submitted 1,421,219.47 433,764.44 52,804.58 1,907,788.48 381,557.69 114,467.33 2,403,813.50
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted 5.43 4,336.71 m2 525,752.36 475,778.39 47,577.84 1,049,108.59 20% 209,821.72 62,946.52 1,321,876.83
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted 0.23 218.61 m 2
15,689.09 26,648.44 2,664.84 45,002.38 20% 9,000.48 2,700.14 56,703.00
1032(1)b Wood Painting
As Evaluated
As Submitted 0.15 112.50 m 2
13,798.42 12,959.44 1,295.94 28,053.80 20% 5,610.76 1,683.23 35,347.79
1032(1)c Metal Painting
As Evaluated
As Submitted 555,239.87 515,386.27 51,538.63 1,122,164.77 224,432.96 67,329.89 1,413,927.62
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted 2.20 723.31 m2 341,586.57 75,898.73 7,589.87 425,075.17 20% 85,015.03 25,504.51 535,594.71
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted 0.06 55.20 m 10,569.53 965.61 96.56 11,631.71 20% 2,326.34 697.90 14,655.95
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted 0.03 26.21 m 5,018.01 458.44 45.84 5,522.29 20% 1,104.46 331.34 6,958.09
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 0.18 110.40 m 33,658.75 1,636.63 163.66 35,459.05 20% 7,091.81 2,127.54 44,678.40
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted 2.61 6,440.06 kg 387,635.26 31,662.66 85,659.84 504,957.76 20% 100,991.55 30,297.47 636,246.78
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted 3.24 8,515.07 kg 519,014.80 33,807.98 73,233.56 626,056.34 20% 125,211.27 37,563.38 788,830.99
1047(2)b Structural Steel, Purlins
As Evaluated
1003(11) As Submitted 0.11 110.40 m 18,199.44 2,024.31 202.43 20,426.18 20% 4,085.24 1,225.57 25,736.99
Fascia Board
As Evaluated
1047(6) As Submitted 0.10 277.47 kg 15,604.45 3,735.14 373.51 19,713.10 20% 3,942.62 1,182.79 24,838.51
Metal Structure Accessories, Steel Plates
As Evaluated
1047(7)b As Submitted 0.07 248.16 kg 9,641.02 3,340.56 334.06 13,315.64 20% 2,663.13 798.94 16,777.71
Metal Structure Accessories, Sag Rods
As Evaluated
1047(4) As Submitted 0.15 528.07 kg 21,130.99 7,108.53 710.85 28,950.36 20% 5,790.07 1,737.02 36,477.45
Metal Structure Accessories, Cross Bracing
As Evaluated
1047(3)c As Submitted 0.05 44.00 pc 8,140.00 1,154.54 1.15 9,295.69 20% 1,859.14 557.74 11,712.57
Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted 1,370,198.82 161,793.13 168,411.34 1,700,403.29 340,080.66 102,024.20 2,142,508.15
Sub-Total C.6
As Evaluated
As Submitted 8,456,185.73 1,836,215.00 692,518.74 10,984,919.46 2,196,983.90 659,095.20 13,840,998.56
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted 0.25 1.00 l.s. 40,569.75 7,624.40 762.44 48,956.59 20% 9,791.32 2,937.40 61,685.31
1001(8) Sewer Line Works
As Evaluated
As Submitted 0.21 1.00 l.s. 34,962.33 5,173.70 517.37 40,653.40 20% 8,130.68 2,439.20 51,223.28
1002(6) Cold Water Line Works
As Evaluated
As Submitted 1.08 1.00 l.s. 175,017.11 30,435.42 3,043.54 208,496.07 20% 41,699.21 12,509.76 262,705.04
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted 1.88 1.00 l.s. 332,488.59 28,688.52 2,868.85 364,045.96 20% 72,809.19 21,842.76 458,697.91
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted 0.45 1.00 l.s. 71,983.91 13,736.34 1,373.63 87,093.88 20% 17,418.78 5,225.63 109,738.29
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted 0.11 26.00 units 16,265.81 4,548.18 454.82 21,268.81 20% 4,253.76 1,276.13 26,798.70
1001(6)b1 Catch basin
As Evaluated
As Submitted 4.76 1.00 lot 848,514.95 64,372.26 6,437.23 919,324.44 20% 183,864.89 55,159.47 1,158,348.80
SPL-2 Fire Protection System
As Evaluated
As Submitted 1,519,802.45 154,578.82 15,457.88 1,689,839.15 337,967.83 101,390.35 2,129,197.33
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted 0.55 1.00 l.s. 93,357.14 10,844.76 1,084.48 105,286.38 20% 21,057.28 6,317.18 132,660.84
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted 1.03 1.00 l.s. 185,259.10 13,042.74 1,304.27 199,606.12 20% 39,921.22 11,976.37 251,503.71
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted 1.29 1.00 l.s. 244,155.30 5,228.16 522.82 249,906.28 20% 49,981.26 14,994.38 314,881.92
1102(21) Panel Board
As Evaluated
As Submitted 0.56 1.00 l.s. 101,458.00 6,753.04 675.30 108,886.34 20% 21,777.27 6,533.18 137,196.79
1003(1) Lighting Fixtures
As Evaluated
As Submitted 0.08 1.00 l.s. 11,568.00 3,049.47 304.95 14,922.42 20% 2,984.48 895.35 18,802.25
1208(1) Fire Alarm System
As Evaluated
As Submitted 635,797.54 38,918.17 3,891.82 678,607.540 135,721.510 40,716.460 855,045.510
TOTAL OF PART E
As Evaluated
As Submitted 14,760,198.86 2,816,943.64 1,308,697.10 18,885,839.600 3,777,167.920 1,133,150.410 23,796,157.930
TOTAL OF PART III
As Evaluated
As Submitted 14,887,916.00 2,822,967.52 1,602,077.54 19,312,961.060 3,811,850.590 1,156,240.620 24,281,052.270
GRAND TOTAL
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
GRAND TOTAL
As Evaluated
BUREAU OF CONSTRUCTION
FORM ABC-2015-02-00
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING
(Project ID)
(Project Component ID - Description)
CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING
PART III
WORKS
AS SUBMITTED 283,708.00 20.00% 56,741.59 17,022.48 73,764.07 357,472.07
PART A EARTHWORKS
AS EVALUATED
Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:
Name & Signature Name & Signature Name & Signature Name & Signature Name & Signature
Position Title Position Title Position Title Position Title Position Title
Planning. Section/Division Planning Section/Division Planning Division
BUREAU OF CONSTRUCTION
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING
(Project ID)
(Project Component ID - Description)
PART A EARTHWORKS
AS SUBMITTED 365.45 m3 84,105.01 20% 16,821.00 5,046.30 21,867.30 105,972.31 289.98
803(1)a Structure Excavation
AS EVALUATED
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING
100 mm CHB Non Load Bearing Wall (including Reinforcing AS SUBMITTED 267.94 m2 145,299.45 20% 29,059.89 8,717.97 37,777.86 183,077.31 683.28
1046(2)a1
Steel) AS EVALUATED
150 mm CHB Non Load Bearing Wall (including Reinforcing AS SUBMITTED 838.99 m2 704,415.05 20% 140,883.01 42,264.90 183,147.91 887,562.96 1,057.89
1046(2)a2
Steel) AS EVALUATED
AS SUBMITTED 1.00 l.s. 283,156.98 20% 56,631.40 16,989.42 73,620.82 356,777.80 356,777.80
1010(4) Wooden Doors
AS EVALUATED
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING
AS SUBMITTED 1.00 l.s. 37,854.76 20% 7,570.95 2,271.29 9,842.24 47,697.00 47,697.00
1003(9) Carpentry and Joinery Works (Blackboard)
AS EVALUATED
50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing AS SUBMITTED 127.60 m 249,218.58 20% 49,843.72 14,953.12 64,796.84 314,015.42 2,460.94
1053(3)a2
on 19 mm bar stiffener AS EVALUATED
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING
AS SUBMITTED 1.00 l.s. 208,496.07 20% 41,699.21 12,509.76 54,208.97 262,705.04 262,705.04
1001(9) Downspout/Storm Drain
AS EVALUATED
AS SUBMITTED 1.00 l.s. 364,045.96 20% 72,809.19 21,842.76 94,651.95 458,697.91 458,697.91
1002(5) Sanitary/Plumbing Fixtures
AS EVALUATED
AS SUBMITTED 1.00 l.s. 87,093.88 20% 17,418.78 5,225.63 22,644.41 109,738.29 109,738.29
SPL-1 Septic Vault "Type E"
AS EVALUATED
AS SUBMITTED 26.00 units 21,268.81 20% 4,253.76 1,276.13 5,529.89 26,798.70 1,030.72
1001(6)b1 Catch basin
AS EVALUATED
AS SUBMITTED 1.00 lot 919,324.44 20% 183,864.89 55,159.47 239,024.36 1,158,348.80 1,158,348.80
Dry Standpipe
AS EVALUATED
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 0.79% 130,000.00
Part II Other General Requirements 1.47% 241,562.03
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 1.46% 239,317.45
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 27.13% 4,460,986.10
PART C FINISHING WORKS 56.01% 9,207,970.82
PART D PLUMBING/SANITARY WORKS 9.58% 1,574,675.92
PART E ELECTRICAL WORKS 3.57% 586,526.49
Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:
Name & Signature Name & Signature Name & Signature Name & Signature Name & Signature
Position Title Position Title Position Title Position Title Position Title
Planning. Section/Division Planning Section/Division Planning Division
ANNEX A
BUREAU OF CONSTRUCTION
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 130,000.00
Part II Other General Requirements 241,562.03
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 239,317.45
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 4,460,986.10
PART C FINISHING WORKS 9,207,970.82
PART D PLUMBING/SANITARY WORKS 1,574,675.92
PART E ELECTRICAL WORKS 586,526.49
Total
Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:
Name & Signature Name & Signature Name & Signature Name & Signature Name & Signature
Position Title Position Title Position Title Position Title Position Title
Planning/Const. Section/Division/Consultant Planning/Const. Section/Division/UPMO Planning/Construction Division/BOC
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
II.5 Project Billboard/ Sign Board 1.00 ea 4,274.69 4,274.69 5,386.11 0.03
II.7 Occupational Safety and Health 1.00 lot 116,766.26 116,766.26 132,412.94 0.71
Project ID
PART A EARTHWORKS
804(1)a Embankment from Structure Excavation 185.75 m3 27,764.70 149.47 188.34 0.17
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days) 286.11 m3 1,113,341.23 3,891.30 4,903.04 6.77
PART C FINISHING
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel) 716.18 m2 601,303.92 839.60 1,057.89 3.66
1005 (1) Steel Casement Window 97.92 m2 348,063.71 3,554.57 4,478.76 2.12
1003(9) Carpentry and Joinery Works (Blackboard) 1.00 l.s. 30,283.81 30,283.81 38,157.60 0.18
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1027(1) Plain Cement Plaster Finish 3,294.60 m2 498,120.75 151.19 190.50 3.03
1053(3)a1 38 mm dia. G.I. Pipe Railings 66.00 m 30,108.42 456.19 574.80 0.18
1053(3)a2 50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar stiffener 111.20 m 217,187.35 1,953.12 2,460.94 1.32
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame 470.83 m2 345,349.46 733.49 924.20 2.10
1018(1) Glazed Tiles and Trims 115.51 m2 161,776.15 1,400.59 1,764.74 0.98
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk) 46.20 m 9,735.23 210.72 265.51 0.06
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk) 26.21 m 5,522.29 210.72 265.51 0.03
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk) 92.40 m 29,677.68 321.19 404.70 0.18
1047(6) Metal Structure Accessories, Steel Plates 277.47 kg 19,713.10 71.05 89.52 0.12
1047(7)b Metal Structure Accessories, Sag Rods 202.67 kg 10,874.76 53.66 67.61 0.07
1047(4) Metal Structure Accessories, Cross Bracing 427.58 kg 23,441.20 54.82 69.08 0.14
1047(3)c Metal Structure Accessories, Turn Buckle 36.00 pc 7,605.57 211.27 266.19 0.05
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1001(8) Sewer Line Works 1.00 l.s. 45,147.12 45,147.12 56,885.37 0.27
1002(6) Cold Water Line Works 1.00 l.s. 36,473.20 36,473.20 45,956.23 0.22
SPL-3 Septic Vault "Type E" 1.00 l.s. 79,803.17 79,803.17 100,551.99 0.49
PART E ELECTRICAL
1100(19) Conduits, Boxes, and Fittings 1.00 l.s. 94,926.36 94,926.36 119,607.21 0.58
1101(18) Wires and Wiring Devices 1.00 l.s. 139,839.83 139,839.83 176,198.19 0.85
1208(1) Fire Alarm System 1.00 l.s. 14,922.42 14,922.42 18,802.25 0.09
FORM POW-2015-01B-00
MINIMUM EQUIPMENT REQUIREMENT
Number of Number of
No. Equipment Description Capacity No. Equipment Description Capacity
Equipment Equipment
1 Backhoe 0.80 m3 1 31
2 Dump Truck 12 yd 3
2 32
3 Plate Compactor 5 hp 1 33
4 Concrete Vibrator 5 amp 1 34
5 Pumpcrete 1 35
6 One Bagger Mixer 4 - 6 ft /min
3
1 36
7 Bar Cutter 1 37
8 Bar Bender 1 38
9 Welding Machine 500 amp 2 39
10 Cutting Outfit 1 40
11 Truck Mounted Crane 20 - 25 mt 1 41
12 Drill Rig, Mechanical Rotary 300 hp 1 42
13 Bentonite Mixer 1 43
14 Bentonite Bin 1 44
15 Water Pump 1,800 lpm, 7.5 hp 1 45
16 Water Truck 16,000 L, 360 hp 1 46
17 Tremie Pipe Set 1 47
18 SPT & Desanding Machine 1 48
19 Tower Lights 2 49
20 50
21 51
22 52
23 53
24 54
25 55
26 56
27 57
28 58
29 59
30 60
SUB-TOTAL SUB-TOTAL
TOTAL
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted 0.79 5.00 mo - - 130,000.00 130,000.00 8% 10,400.00 7,020.00 147,420.00
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 130,000.00 130,000.00 10,400.00 7,020.00 147,420.00
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted 0.03 1.00 ea 3,505.00 699.72 69.97 4,274.69 20% 854.94 256.48 5,386.11
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted 0.71 1.00 l.s. 112,329.46 4,436.80 - 116,766.26 8% 9,341.30 6,305.38 132,412.94
II.7 Occupational Safety and Health
As Evaluated
As Submitted 0.73 1.00 l.s. - - 120,521.08 120,521.08 8% 9,641.69 6,508.14 136,670.91
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 115,834.46 5,136.52 120,591.05 241,562.03 19,837.93 13,070.00 274,469.96
TOTAL OF PART II
As Evaluated
(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted 0.44 313.84 m3 - 3,221.41 69,006.03 72,227.44 20% 14,445.49 4,333.65 91,006.58
803(1)a Structure Excavation
As Evaluated
As Submitted 0.17 185.75 m3 - 3,875.27 23,889.43 27,764.70 20% 5,552.94 1,665.88 34,983.52
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted 0.51 240.28 m3 48,056.00 5,012.91 30,902.57 83,971.49 20% 16,794.30 5,038.29 105,804.08
804(1)b Embankment from Borrow
As Evaluated
As Submitted 0.34 66.06 m3 39,536.91 11,301.21 4,515.70 55,353.82 20% 11,070.76 3,321.23 69,745.81
804(4) Gravel Fill
As Evaluated
As Submitted 87,592.91 23,410.81 128,313.73 239,317.45 47,863.49 14,359.05 301,539.99
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted 6.77 286.11 m3 1,018,551.60 34,220.91 60,568.72 1,113,341.23 20% 222,668.25 66,800.47 1,402,809.95
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted 15.07 51,041.57 kg 2,035,218.80 299,644.94 142,895.76 2,477,759.50 20% 495,551.90 148,665.57 3,121,976.97
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted 5.29 1,873.07 m2 386,839.76 309,227.71 173,817.90 869,885.37 20% 173,977.07 52,193.12 1,096,055.56
903(2) Forms and Falseworks
As Evaluated
As Submitted 3,440,610.16 643,093.56 377,282.37 4,460,986.10 892,197.22 267,659.16 5,620,842.48
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted 0.50 219.68 L 72,494.40 8,862.05 886.21 82,242.66 20% 16,448.53 4,934.56 103,625.75
1000(1) Soil Poisoning
As Evaluated
As Submitted 72,494.40 8,862.05 886.21 82,242.66 16,448.53 4,934.56 103,625.75
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted 0.83 250.52 m2 101,806.32 20,710.31 13,336.24 135,852.87 20% 27,170.57 8,151.17 171,174.61
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted 3.66 716.18 m2 484,230.78 71,214.87 45,858.27 601,303.92 20% 120,260.78 36,078.24 757,642.94
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 586,037.10 91,925.18 59,194.51 737,156.79 147,431.35 44,229.41 928,817.55
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted 1.48 1.00 l.s. 198,807.00 40,233.90 4,023.39 243,064.29 20% 48,612.86 14,583.86 306,261.01
1010(4) Wooden Doors
As Evaluated
As Submitted 0.47 49.10 m2 42,987.05 31,811.34 3,181.13 77,979.53 20% 15,595.91 4,678.77 98,254.21
1009(1)a Jalousie Window
As Evaluated
As Submitted 2.12 97.92 m2 190,209.60 95,161.92 62,692.19 348,063.71 20% 69,612.74 20,883.82 438,560.27
1005 (1) Steel Casement Window
As Evaluated
As Submitted 16.83 43.52 m2 2,235,824.72 319,744.05 210,645.77 2,766,214.54 20% 553,242.91 165,972.87 3,485,430.32
1005 (5) Window Grills
As Evaluated
As Submitted 5.39 35.00 set 886,900.00 - - 886,900.00 20% 177,380.00 53,214.00 1,117,494.00
1004(2)a Locksets
As Evaluated
As Submitted 0.06 140.00 pc 9,100.00 - - 9,100.00 20% 1,820.00 546.00 11,466.00
1004(2)g Hinges
As Evaluated
As Submitted 0.18 1.00 l.s. 24,800.00 4,985.28 498.53 30,283.81 20% 6,056.76 1,817.03 38,157.60
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 3,588,628.37 491,936.50 281,041.01 4,361,605.88 872,321.18 261,696.35 5,495,623.41
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted 1.38 839.37 m2 185,920.46 36,784.16 3,678.42 226,383.03 20% 45,276.61 13,582.98 285,242.62
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted 3.03 3,294.60 m2 315,457.95 166,057.09 16,605.71 498,120.75 20% 99,624.15 29,887.25 627,632.15
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted 0.18 66.00 m 24,365.88 2,298.55 3,443.99 30,108.42 20% 6,021.68 1,806.51 37,936.61
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
As Submitted 1.32 111.20 m 207,512.03 3,872.71 5,802.60 217,187.35 20% 43,437.47 13,031.24 273,656.06
1053(3)a2 50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar stiffener
As Evaluated
As Submitted 2.10 470.83 m 2
254,583.43 82,514.57 8,251.46 345,349.46 20% 69,069.89 20,720.97 435,140.32
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted 0.68 605.38 m 2
85,812.62 23,718.70 2,371.87 111,903.19 20% 22,380.64 6,714.19 140,998.02
1038(1) Reflective Insulation
As Evaluated
As Submitted 0.98 115.51 m2 108,867.55 48,098.73 4,809.87 161,776.15 20% 32,355.23 9,706.57 203,837.95
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted 0.42 50.68 m2 53,538.04 14,772.83 1,477.28 69,788.15 20% 13,957.63 4,187.29 87,933.07
1018(2) Unglazed Tiles
As Evaluated
As Submitted 1,236,057.95 378,117.33 46,441.20 1,660,616.50 332,123.30 99,637.00 2,092,376.80
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted 5.49 3,729.66 m2 452,157.87 409,179.22 40,917.92 902,255.02 20% 180,451.00 54,135.30 1,136,841.32
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted 0.24 189.83 m 2
13,623.62 23,140.18 2,314.02 39,077.82 20% 7,815.56 2,344.67 49,238.05
1032(1)b Wood Painting
As Evaluated
As Submitted 0.15 99.91 m 2
12,254.22 11,509.13 1,150.91 24,914.27 20% 4,982.85 1,494.86 31,391.98
1032(1)c Metal Painting
As Evaluated
As Submitted 478,035.72 443,828.53 44,382.85 966,247.11 193,249.41 57,974.83 1,217,471.35
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted 2.16 605.38 m2 285,893.11 63,523.94 6,352.39 355,769.44 20% 71,153.89 21,346.17 448,269.50
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted 0.06 46.20 m 8,846.24 808.18 80.82 9,735.23 20% 1,947.05 584.11 12,266.39
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted 0.03 26.21 m 5,018.01 458.44 45.84 5,522.29 20% 1,104.46 331.34 6,958.09
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 0.18 92.40 m 28,170.91 1,369.79 136.98 29,677.68 20% 5,935.54 1,780.66 37,393.88
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted 2.47 5,176.53 kg 311,581.81 25,450.50 68,853.51 405,885.81 20% 81,177.16 24,353.15 511,416.12
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted 3.13 7,001.60 kg 426,765.02 27,798.95 60,217.01 514,780.98 20% 102,956.20 30,886.86 648,624.04
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted 0.10 92.40 m 15,232.14 1,694.26 169.43 17,095.82 20% 3,419.16 1,025.75 21,540.73
1003(11) Fascia Board
As Evaluated
As Submitted 0.12 277.47 kg 15,604.45 3,735.14 373.51 19,713.10 20% 3,942.62 1,182.79 24,838.51
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted 0.07 202.67 kg 7,873.73 2,728.21 272.82 10,874.76 20% 2,174.95 652.49 13,702.20
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted 0.14 427.58 kg 17,109.83 5,755.80 575.58 23,441.20 20% 4,688.24 1,406.47 29,535.91
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted 0.05 36.00 pc 6,660.00 944.62 0.94 7,605.57 20% 1,521.11 456.33 9,583.01
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted 1,128,755.25 134,267.80 137,078.84 1,400,101.88 280,020.38 84,006.12 1,764,128.38
Sub-Total C.6
As Evaluated
As Submitted 7,090,008.80 1,548,937.39 569,024.62 9,207,970.82 1,841,594.15 552,478.27 11,602,043.24
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted 0.27 1.00 l.s. 37,479.15 6,970.88 697.09 45,147.12 20% 9,029.42 2,708.83 56,885.37
1001(8) Sewer Line Works
As Evaluated
As Submitted 0.22 1.00 l.s. 31,441.10 4,574.64 457.46 36,473.20 20% 7,294.64 2,188.39 45,956.23
1002(6) Cold Water Line Works
As Evaluated
As Submitted 1.08 1.00 l.s. 149,178.38 25,946.42 2,594.64 177,719.45 20% 35,543.89 10,663.17 223,926.51
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted 2.20 1.00 l.s. 330,724.59 28,557.32 2,855.73 362,137.64 20% 72,427.53 21,728.26 456,293.43
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted 0.49 1.00 l.s. 66,075.81 12,479.42 1,247.94 79,803.17 20% 15,960.63 4,788.19 100,551.99
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted 0.10 20.00 units 12,512.16 3,498.60 349.86 16,360.62 20% 3,272.12 981.64 20,614.38
1001(6)b1 Catch basin
As Evaluated
As Submitted 5.21 1.00 lot 792,545.75 58,626.34 5,862.63 857,034.72 20% 171,406.94 51,422.08 1,079,863.74
SPL-2 Fire Protection System
As Evaluated
As Submitted 1,419,956.94 140,653.62 14,065.36 1,574,675.92 314,935.17 94,480.56 1,984,091.65
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted 0.58 1.00 l.s. 84,199.64 9,751.56 975.16 94,926.36 20% 18,985.27 5,695.58 119,607.21
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted 0.85 1.00 l.s. 129,016.65 9,839.25 983.93 139,839.83 20% 27,967.97 8,390.39 176,198.19
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted 1.51 1.00 l.s. 244,155.30 3,267.60 326.76 247,749.66 20% 49,549.93 14,864.98 312,164.57
1102(21) Panel Board
As Evaluated
As Submitted 0.54 1.00 l.s. 82,858.00 5,663.84 566.38 89,088.22 20% 17,817.64 5,345.29 112,251.15
1003(1) Lighting Fixtures
As Evaluated
As Submitted 0.09 1.00 l.s. 11,568.00 3,049.47 304.95 14,922.42 20% 2,984.48 895.35 18,802.25
1208(1) Fire Alarm System
As Evaluated
As Submitted 551,797.59 31,571.72 3,157.17 586,526.490 117,305.290 35,191.590 739,023.370
TOTAL OF PART E
As Evaluated
As Submitted 12,589,966.40 2,387,667.10 1,091,843.25 16,069,476.780 3,213,895.320 964,168.630 20,247,540.730
TOTAL OF PART III
As Evaluated
As Submitted 12,705,800.86 2,392,803.62 1,342,434.30 16,441,038.810 3,244,133.250 984,258.630 20,669,430.690
GRAND TOTAL
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
GRAND TOTAL
As Evaluated
BUREAU OF CONSTRUCTION
FORM ABC-2015-02-00
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
(Project ID)
(Project Component ID - Description)
CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING
PART III
WORKS
AS SUBMITTED 239,317.45 20.00% 47,863.49 14,359.05 62,222.54 301,539.99
PART A EARTHWORKS
AS EVALUATED
Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:
Name & Signature Name & Signature Name & Signature Name & Signature Name & Signature
Position Title Position Title Position Title Position Title Position Title
Planning. Section/Division Planning Section/Division Planning Division
BUREAU OF CONSTRUCTION
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
(Project ID)
(Project Component ID - Description)
PART A EARTHWORKS
AS SUBMITTED 313.84 m3 72,227.44 20% 14,445.49 4,333.65 18,779.14 91,006.58 289.98
803(1)a Structure Excavation
AS EVALUATED
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
100 mm CHB Non Load Bearing Wall (including Reinforcing AS SUBMITTED 250.52 m2 135,852.87 20% 27,170.57 8,151.17 35,321.74 171,174.61 683.28
1046(2)a1
Steel) AS EVALUATED
150 mm CHB Non Load Bearing Wall (including Reinforcing AS SUBMITTED 716.18 m2 601,303.92 20% 120,260.78 36,078.24 156,339.02 757,642.94 1,057.89
1046(2)a2
Steel) AS EVALUATED
AS SUBMITTED 1.00 l.s. 243,064.29 20% 48,612.86 14,583.86 63,196.72 306,261.01 306,261.01
1010(4) Wooden Doors
AS EVALUATED
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
AS SUBMITTED 1.00 l.s. 30,283.81 20% 6,056.76 1,817.03 7,873.79 38,157.60 38,157.60
1003(9) Carpentry and Joinery Works (Blackboard)
AS EVALUATED
50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing AS SUBMITTED 111.20 m 217,187.35 20% 43,437.47 13,031.24 56,468.71 273,656.06 2,460.94
1053(3)a2
on 19 mm bar stiffener AS EVALUATED
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
AS SUBMITTED 1.00 l.s. 177,719.45 20% 35,543.89 10,663.17 46,207.06 223,926.51 223,926.51
1001(9) Downspout/Storm Drain
AS EVALUATED
AS SUBMITTED 1.00 l.s. 362,137.64 20% 72,427.53 21,728.26 94,155.79 456,293.43 456,293.43
1002(5) Sanitary/Plumbing Fixtures
AS EVALUATED
AS SUBMITTED 1.00 l.s. 79,803.17 20% 15,960.63 4,788.19 20,748.82 100,551.99 100,551.99
SPL-1 Septic Vault "Type E"
AS EVALUATED
AS SUBMITTED 20.00 units 16,360.62 20% 3,272.12 981.64 4,253.76 20,614.38 1,030.72
1001(6)b1 Catch basin
AS EVALUATED
AS SUBMITTED 1.00 lot 857,034.72 20% 171,406.94 51,422.08 222,829.02 1,079,863.74 1,079,863.74
Fire Protection System
AS EVALUATED
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 1.06% 121,333.33
Part II Other General Requirements 1.59% 182,158.82
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 1.50% 171,470.97
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 27.48% 3,147,815.32
PART C FINISHING WORKS 58.54% 6,705,462.58
PART D PLUMBING/SANITARY WORKS 7.91% 905,548.48
PART E ELECTRICAL WORKS 1.93% 221,298.13
Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:
Name & Signature Name & Signature Name & Signature Name & Signature Name & Signature
Position Title Position Title Position Title Position Title Position Title
Planning. Section/Division Planning Section/Division Planning Division
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS SUBMITTED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
II.5 Project Billboard/ Sign Board 1.00 ea 4,274.69 4,274.69 5,386.11 0.04
II.7 Occupational Safety and Health 1.00 lot 94,247.16 94,247.16 106,876.28 0.82
Project ID
PART A EARTHWORKS
804(1)a Embankment from Structure Excavation 139.08 m3 20,788.77 149.47 188.34 0.18
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days) 201.23 m3 783,047.27 3,891.30 4,903.04 6.84
PART C FINISHING
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel) 522.79 m2 438,933.89 839.60 1,057.89 3.83
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS SUBMITTED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1005 (1) Steel Casement Window 73.44 m2 261,047.78 3,554.57 4,478.76 2.28
1003(9) Carpentry and Joinery Works (Blackboard) 1.00 l.s. 22,712.86 22,712.86 28,618.20 0.20
1027(1) Plain Cement Plaster Finish 2,313.83 m2 349,835.10 151.19 190.50 3.05
1053(3)a1 38 mm dia. G.I. Pipe Railings 33.00 m 15,054.21 456.19 574.80 0.13
1053(3)a2 50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar stiffener 92.12 m 179,921.75 1,953.12 2,460.94 1.57
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame 332.94 m2 244,208.41 733.49 924.20 2.13
1018(1) Glazed Tiles and Trims 71.55 m2 100,211.97 1,400.59 1,764.74 0.87
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk) 32.90 m 6,932.66 210.72 265.51 0.06
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk) 26.21 m 5,522.95 210.72 265.51 0.05
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk) 65.80 m 21,134.11 321.19 404.70 0.18
1047(6) Metal Structure Accessories, Steel Plates 277.47 kg 19,712.99 71.05 89.52 0.17
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS SUBMITTED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1047(7)b Metal Structure Accessories, Sag Rods 146.82 kg 7,877.99 53.66 67.61 0.07
1047(4) Metal Structure Accessories, Cross Bracing 314.91 kg 17,264.30 54.82 69.08 0.15
1047(3)c Metal Structure Accessories, Turn Buckle 26.00 pc 5,492.91 211.27 266.19 0.05
1047(6)-1 Metal Structure Accessories, Fire Escape 1.00 l.s. 103,115.53 103,115.53 129,925.57 0.90
1001(8) Sewer Line Works 1.00 l.s. 21,924.81 21,924.81 27,625.26 0.19
1002(6) Cold Water Line Works 1.00 l.s. 10,994.96 10,994.96 13,853.65 0.10
SPL-3 Septic Vault "Type E" 1.00 l.s. 68,102.96 68,102.96 85,809.73 0.59
PART E ELECTRICAL
1100(19) Conduits, Boxes, and Fittings 1.00 l.s. 45,607.72 45,607.72 57,465.72 0.40
1101(18) Wires and Wiring Devices 1.00 l.s. 62,680.72 62,680.72 78,977.70 0.55
1208(1) Fire Alarm System 1.00 l.s. 8,780.97 8,780.97 11,064.02 0.08
FORM POW-2015-01B-00
MINIMUM EQUIPMENT REQUIREMENT
Number of Number of
No. Equipment Description Capacity No. Equipment Description Capacity
Equipment Equipment
1 Backhoe 0.80 m3 1 31
2 Dump Truck 12 yd 3
2 32
3 Plate Compactor 5 hp 1 33
4 Concrete Vibrator 5 amp 1 34
5 Pumpcrete 1 35
6 One Bagger Mixer 4 - 6 ft /min
3
1 36
7 Bar Cutter 1 37
8 Bar Bender 1 38
9 Welding Machine 500 amp 2 39
10 Cutting Outfit 1 40
11 Truck Mounted Crane 20 - 25 mt 1 41
12 Drill Rig, Mechanical Rotary 300 hp 1 42
13 Bentonite Mixer 1 43
14 Bentonite Bin 1 44
15 Water Pump 1,800 lpm, 7.5 hp 1 45
16 Water Truck 16,000 L, 360 hp 1 46
17 Tremie Pipe Set 1 47
18 SPT & Desanding Machine 1 48
19 Tower Lights 2 49
20 50
21 51
22 52
23 53
24 54
25 55
26 56
27 57
28 58
29 59
30 60
SUB-TOTAL SUB-TOTAL
TOTAL
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted 1.06 4.67 mo - - 121,333.33 121,333.33 8% 9,706.67 6,552.00 137,592.00
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 121,333.33 121,333.33 9,706.67 6,552.00 137,592.00
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted 0.04 1.00 ea 3,505.00 699.72 69.97 4,274.69 20% 854.94 256.48 5,386.11
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted 0.82 1.00 l.s. 89,810.36 4,436.80 - 94,247.16 8% 7,539.77 5,089.35 106,876.28
II.7 Occupational Safety and Health
As Evaluated
As Submitted 0.73 1.00 l.s. - - 83,636.97 83,636.97 8% 6,690.96 4,516.40 94,844.33
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 93,315.36 5,136.52 83,706.94 182,158.82 15,085.67 9,862.23 207,106.72
TOTAL OF PART II
As Evaluated
(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted 0.49 244.62 m3 - 2,510.90 53,786.18 56,297.08 20% 11,259.42 3,377.83 70,934.33
803(1)a Structure Excavation
As Evaluated
As Submitted 0.18 139.08 m3 - 2,901.60 17,887.17 20,788.77 20% 4,157.75 1,247.33 26,193.85
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted 0.49 159.64 m3 31,928.00 3,330.54 20,531.41 55,789.95 20% 11,157.99 3,347.40 70,295.34
804(1)b Embankment from Borrow
As Evaluated
As Submitted 0.34 46.06 m3 27,566.91 7,879.71 3,148.55 38,595.17 20% 7,719.03 2,315.71 48,629.91
804(4) Gravel Fill
As Evaluated
As Submitted 59,494.91 16,622.75 95,353.30 171,470.97 34,294.19 10,288.27 216,053.43
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted 6.84 201.23 m3 716,378.80 24,068.62 42,599.85 783,047.27 20% 156,609.45 46,982.84 986,639.56
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted 15.32 36,154.58 kg 1,441,618.68 212,249.29 101,218.20 1,755,086.18 20% 351,017.24 105,305.17 2,211,408.59
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted 5.32 1,312.79 m2 271,126.74 216,730.31 121,824.81 609,681.87 20% 121,936.37 36,580.91 768,199.15
903(2) Forms and Falseworks
As Evaluated
As Submitted 2,429,124.23 453,048.22 265,642.87 3,147,815.32 629,563.06 188,868.92 3,966,247.30
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted 0.52 159.89 L 52,763.70 6,450.08 645.01 59,858.79 20% 11,971.76 3,591.53 75,422.08
1000(1) Soil Poisoning
As Evaluated
As Submitted 52,763.70 6,450.08 645.01 59,858.79 11,971.76 3,591.53 75,422.08
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted 0.70 147.30 m2 59,859.77 12,177.19 7,841.40 79,878.36 20% 15,975.67 4,792.70 100,646.73
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted 3.83 522.79 m2 353,474.00 51,984.73 33,475.16 438,933.89 20% 87,786.78 26,336.03 553,056.70
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 413,333.78 64,161.91 41,316.57 518,812.25 103,762.45 31,128.73 653,703.43
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted 1.49 1.00 l.s. 141,984.00 26,239.50 2,623.95 170,847.45 20% 34,169.49 10,250.85 215,267.79
1010(4) Wooden Dooor
As Evaluated
As Submitted 0.48 34.93 m2 30,581.22 22,630.76 2,263.08 55,475.05 20% 11,095.01 3,328.50 69,898.56
1009(1)a Jalousie Window
As Evaluated
As Submitted 2.28 73.44 m2 142,657.20 71,371.44 47,019.14 261,047.78 20% 52,209.56 15,662.87 328,920.21
1005 (1) Steel Casement Window
As Evaluated
As Submitted 18.11 32.64 m2 1,676,868.54 239,808.04 157,984.32 2,074,660.91 20% 414,932.18 124,479.65 2,614,072.74
1005(5) Window Grill
As Evaluated
As Submitted 5.31 24.00 set 608,160.00 - - 608,160.00 20% 121,632.00 36,489.60 766,281.60
1004(2)a Locksets
As Evaluated
As Submitted 0.05 96.00 pc 6,240.00 - - 6,240.00 20% 1,248.00 374.40 7,862.40
1004(2)g Hinges
As Evaluated
As Submitted 0.20 1.00 l.s. 18,600.00 3,738.96 373.90 22,712.86 20% 4,542.57 1,362.77 28,618.20
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 2,625,090.96 363,788.70 210,264.39 3,199,144.05 639,828.81 191,948.64 4,030,921.50
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted 1.38 584.99 m2 129,575.29 25,636.33 2,563.63 157,775.24 20% 31,555.05 9,466.51 198,796.80
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted 3.05 2,313.83 m2 221,549.22 116,623.53 11,662.35 349,835.10 20% 69,967.02 20,990.11 440,792.23
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted 0.13 33.00 m 12,182.94 1,149.28 1,722.00 15,054.21 20% 3,010.84 903.25 18,968.30
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar As Submitted 1.57 92.12 m 171,906.55 3,208.22 4,806.98 179,921.75 20% 35,984.35 10,795.31 226,701.41
1053(3)a2
stiffener As Evaluated
As Submitted 2.13 332.94 m 2
180,024.65 58,348.87 5,834.89 244,208.41 20% 48,841.68 14,652.50 307,702.59
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted 0.70 434.28 m 2
61,559.19 17,015.03 1,701.50 80,275.72 20% 16,055.14 4,816.54 101,147.40
1038(1) Reflective Insulation
As Evaluated
As Submitted 0.87 71.55 m2 67,437.82 29,794.68 2,979.47 100,211.97 20% 20,042.39 6,012.72 126,267.08
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted 0.24 20.05 m2 21,180.69 5,844.42 584.44 27,609.56 20% 5,521.91 1,656.57 34,788.04
1018(2) Unglazed Tiles
As Evaluated
As Submitted 865,416.36 257,620.35 31,855.26 1,154,891.96 230,978.38 69,293.51 1,455,163.85
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted 5.39 2,553.91 m2 309,618.17 280,188.25 28,018.82 617,825.25 20% 123,565.05 37,069.52 778,459.82
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted 0.24 133.27 m 2
9,564.45 16,245.54 1,624.55 27,434.55 20% 5,486.91 1,646.07 34,567.53
1032(1)b Wood Painting
As Evaluated
As Submitted 0.14 62.73 m 2
7,694.00 7,226.18 722.62 15,642.80 20% 3,128.56 938.57 19,709.93
1032(1)c Metal Painting
As Evaluated
As Submitted 326,876.62 303,659.97 30,366.00 660,902.60 132,180.52 39,654.16 832,737.28
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted 2.23 434.28 m2 205,090.90 45,570.11 4,557.01 255,218.03 20% 51,043.61 15,313.08 321,574.72
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted 0.06 32.90 m 6,299.59 575.52 57.55 6,932.66 20% 1,386.53 415.96 8,735.15
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted 0.05 26.21 m 5,018.61 458.49 45.85 5,522.95 20% 1,104.59 331.38 6,958.92
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 0.18 65.80 m 20,061.10 975.46 97.55 21,134.11 20% 4,226.82 1,268.05 26,628.98
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted 2.42 3,535.91 kg 212,830.84 17,384.36 47,031.47 277,246.67 20% 55,449.33 16,634.80 349,330.80
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted 3.32 5,170.61 kg 315,161.61 20,529.24 44,469.65 380,160.49 20% 76,032.10 22,809.63 479,002.22
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted 0.11 65.80 m 10,847.13 1,206.52 120.65 12,174.30 20% 2,434.86 730.46 15,339.62
1003(11) Fascia Board
As Evaluated
As Submitted 0.17 277.47 kg 15,604.36 3,735.12 373.51 19,712.99 20% 3,942.60 1,182.78 24,838.37
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted 0.07 146.82 kg 5,703.96 1,976.39 197.64 7,877.99 20% 1,575.60 472.68 9,926.27
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted 0.15 314.91 kg 12,601.28 4,239.11 423.91 17,264.30 20% 3,452.86 1,035.86 21,753.02
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted 0.05 26.00 pc 4,810.00 682.23 0.68 5,492.91 20% 1,098.58 329.57 6,921.06
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted 0.90 1.00 l.s. 62,940.83 12,868.88 27,305.82 103,115.53 20% 20,623.11 6,186.93 129,925.57
1047(6)-1 Metal Structure Accessories, Fire Escape
As Evaluated
As Submitted 876,970.21 110,201.42 124,681.29 1,111,852.93 222,370.59 66,711.18 1,400,934.70
Sub-Total C.6
As Evaluated
As Submitted 5,160,451.63 1,105,882.44 439,128.51 6,705,462.58 1,341,092.51 402,327.75 8,448,882.84
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted 0.19 1.00 l.s. 18,330.45 3,267.60 326.76 21,924.81 20% 4,384.96 1,315.49 27,625.26
1001(8) Sewer Line Works
As Evaluated
As Submitted 0.10 1.00 l.s. 9,856.75 1,034.74 103.47 10,994.96 20% 2,198.99 659.70 13,853.65
1002(6) Cold Water Line Works
As Evaluated
As Submitted 0.74 1.00 l.s. 71,668.92 12,389.64 1,238.96 85,297.52 20% 17,059.50 5,117.85 107,474.87
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted 1.62 1.00 l.s. 169,754.97 14,344.26 1,434.43 185,533.66 20% 37,106.73 11,132.02 233,772.41
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted 0.59 1.00 l.s. 56,252.00 10,773.60 1,077.36 68,102.96 20% 13,620.59 4,086.18 85,809.73
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted 0.11 16.00 units 10,009.73 2,798.88 279.89 13,088.50 20% 2,617.70 785.31 16,491.51
1001(6)b1 Catch basin
As Evaluated
As Submitted 4.54 1.00 lot 479,028.95 37,797.38 3,779.74 520,606.07 20% 104,121.21 31,236.36 655,963.64
SPL-2 Fire Protection System
As Evaluated
As Submitted 814,901.76 82,406.10 8,240.61 905,548.48 181,109.68 54,332.91 1,140,991.07
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted 0.40 1.00 l.s. 37,515.20 7,356.84 735.68 45,607.72 20% 9,121.54 2,736.46 57,465.72
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted 0.55 1.00 l.s. 56,162.82 5,925.36 592.54 62,680.72 20% 12,536.14 3,760.84 78,977.70
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted 0.34 1.00 l.s. 36,455.00 2,396.24 239.62 39,090.86 20% 7,818.17 2,345.45 49,254.48
1102(21) Panel Board
As Evaluated
As Submitted 0.57 1.00 l.s. 60,585.00 4,138.96 413.90 65,137.86 20% 13,027.57 3,908.27 82,073.70
1003(1) Lighting Fixtures
As Evaluated
As Submitted 0.08 1.00 l.s. 6,184.00 2,360.88 236.09 8,780.97 20% 1,756.19 526.86 11,064.02
1208(1) Fire Alarm System
As Evaluated
As Submitted 196,902.02 22,178.28 2,217.83 221,298.130 44,259.610 13,277.880 278,835.620
TOTAL OF PART E
As Evaluated
As Submitted 8,660,874.55 1,680,137.79 810,583.12 11,151,595.480 2,230,319.050 669,095.730 14,051,010.260
TOTAL OF PART III
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
TOTAL OF PART III
As Evaluated
As Submitted 8,754,189.91 1,685,274.31 1,015,623.39 11,455,087.630 2,255,111.390 685,509.960 14,395,708.980
GRAND TOTAL
As Evaluated
BUREAU OF CONSTRUCTION
FORM ABC-2015-02-00
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING
(Project ID)
(Project Component ID - Description)
CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING
PART III
WORKS
AS SUBMITTED 171,470.97 20.00% 34,294.19 10,288.27 44,582.46 216,053.43
PART A EARTHWORKS
AS EVALUATED
Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:
Name & Signature Name & Signature Name & Signature Name & Signature Name & Signature
Position Title Position Title Position Title Position Title Position Title
Planning. Section/Division Planning Section/Division Planning Division
BUREAU OF CONSTRUCTION
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING
(Project ID)
(Project Component ID - Description)
PART A EARTHWORKS
AS SUBMITTED 244.62 m3 56,297.08 20% 11,259.42 3,377.83 14,637.25 70,934.33 289.98
803(1)a Structure Excavation
AS EVALUATED
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING
100 mm CHB Non Load Bearing Wall (including Reinforcing AS SUBMITTED 147.30 m2 79,878.36 20% 15,975.67 4,792.70 20,768.37 100,646.73 683.28
1046(2)a1
Steel) AS EVALUATED
150 mm CHB Non Load Bearing Wall (including Reinforcing AS SUBMITTED 522.79 m2 438,933.89 20% 87,786.78 26,336.03 114,122.81 553,056.70 1,057.89
1046(2)a2
Steel) AS EVALUATED
AS SUBMITTED 1.00 l.s. 170,847.45 20% 34,169.49 10,250.85 44,420.34 215,267.79 215,267.79
1010(4) Wooden Dooor
AS EVALUATED
AS SUBMITTED 24.00 set 608,160.00 20% 121,632.00 36,489.60 158,121.60 766,281.60 31,928.40
1004(2)a Locksets
AS EVALUATED
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING
50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing AS SUBMITTED 92.12 m 179,921.75 20% 35,984.35 10,795.31 46,779.66 226,701.41 2,460.94
1053(3)a2
on 19 mm bar stiffener AS EVALUATED
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING
AS SUBMITTED 1.00 l.s. 103,115.53 20% 20,623.11 6,186.93 26,810.04 129,925.57 129,925.57
1047(6)-1 Metal Structure Accessories, Fire Escape
AS EVALUATED
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING
AS SUBMITTED 1.00 l.s. 85,297.52 20% 17,059.50 5,117.85 22,177.35 107,474.87 107,474.87
1001(9) Downspout/Storm Drain
AS EVALUATED
AS SUBMITTED 1.00 l.s. 185,533.66 20% 37,106.73 11,132.02 48,238.75 233,772.41 233,772.41
1002(5) Sanitary/Plumbing Fixtures
AS EVALUATED
AS SUBMITTED 1.00 l.s. 68,102.96 20% 13,620.59 4,086.18 17,706.77 85,809.73 85,809.73
SPL-1 Septic Vault "Type E"
AS EVALUATED
AS SUBMITTED 16.00 units 13,088.50 20% 2,617.70 785.31 3,403.01 16,491.51 1,030.72
1001(6)b1 Catch basin
AS EVALUATED
AS SUBMITTED 1.00 lot 520,606.07 20% 104,121.21 31,236.36 135,357.57 655,963.64 655,963.64
Dry Stand Pipe
AS EVALUATED
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part II Other General Requirements 1.89% 138,699.58
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 2.32% 170,885.93
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 33.67% 2,477,374.16
PART C FINISHING WORKS 49.24% 3,622,739.19
PART D PLUMBING/SANITARY WORKS 10.58% 778,326.84
PART E ELECTRICAL WORKS 2.30% 169,464.38
Prepared by: Checked by: Submitted by: Recommending Approval: Approved by: Concurred by:
DOMINADOR R. PASTOR EVELYN P. TAMAYO URBANO R. PALACPAC RAYNALDO R. ABLOG,MAPA REYNALDO S. ORGANO, MBA GEMMA Q. TACUYCUY
Engineer II Engineer II Chief, Planning and Design Section OIC-Assistant District Engineer District Engineer School Division Superintendent
Bantay, Ilocos Sur
STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
(DIRECT+INDIRECT)
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALAUTED AS SUBMITTED AS EVALAUTED
B.5 Project Billboard/ Sign Board 1.00 ea 4,274.69 4,274.69 5,386.11 0.06
B.7(2) Occupational Safety and Health 1.00 lot 80,283.96 80,283.96 91,042.01 1.09
Project ID
PART A EARTHWORKS
801(1) Removal of Structures and Obstruction 1.00 l.s. 15,016.10 15,016.10 18,920.29 0.20
804(1)a Embankment (from Roadway/Structure Excavation) 89.16 m3 13,327.06 149.47 188.34 0.18
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days) 240.91 m3 937,454.25 3,891.30 4,903.04 12.74
902(1)a Reinforcing Steel (Deformed) , Grade 40 25,503.67 kg 1,238,048.92 48.54 61.17 16.83
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
(DIRECT+INDIRECT)
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALAUTED AS SUBMITTED AS EVALAUTED
PART C FINISHING
1046(2)a2 CHB Non Load Bearing Wall (including Reinforcing Steel) 150 mm 566.12 m2 475,313.71 839.60 1,057.89 6.46
1005 (1) Residential Casement (Steel) 48.96 m2 174,031.86 3,554.57 4,478.76 2.37
1005 (5) Window Accessory (Grill) 1.00 l.s. 63,561.92 63,561.92 80,088.02 0.86
1003(9) Carpentry and Joinery Works (Blackboard) 1.00 l.s. 15,141.90 15,141.90 19,078.79 0.21
1051(1) Railing (38 mm dia. G.I. Pipe Railings) 36.00 m 16,422.78 456.19 574.80 0.22
Metal Railing (50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar
1051(5) 96.00 m 187,499.87 1,953.12 2,460.94 2.55
stiffener)
1003(1)a1 Ceiling (Fiber Cement Board on Metal Frame) 281.66 m2 206,595.01 733.49 924.20 2.81
1018(1) Glazed Tiles and Trims 36.69 m2 51,387.52 1,400.59 1,764.74 0.70
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
(DIRECT+INDIRECT)
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALAUTED AS SUBMITTED AS EVALAUTED
1013(2)a1 Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk) 26.20 m 5,520.85 210.72 265.51 0.08
1013(2)a2 Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk) 29.48 m 6,212.00 210.72 265.51 0.08
1013(2)b1 Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk) 47.00 m 15,095.80 321.19 404.70 0.21
1003(11)a1Fascia Board (Fiber Cement Board) 70.20 m 12,988.39 185.02 233.12 0.18
1047(6) Metal Structure Accessories, Steel Plates 920.30 kg 65,383.14 71.05 89.52 0.89
1047(7)a Metal Structure Accessories, Bolts 170.06 kg 8,948.36 52.62 66.30 0.12
1047(7)b Metal Structure Accessories, Sag Rods 195.00 kg 10,253.01 52.58 66.25 0.14
1047(4) Metal Structure Accessories, Cross Bracing 75.76 kg 4,153.38 54.82 69.08 0.06
1047(3)c Metal Structure Accessories, Turn Buckle 28.00 pc 5,915.44 211.27 266.20 0.08
1047(10) Metal Structure Accessories, Fire Escape 1.00 l.s. 103,115.53 103,115.53 129,925.57 1.40
1001(8) Sewer Line Works 1.00 l.s. 21,436.90 21,436.90 27,010.49 0.29
1002(24) Cold Water Lines 1.00 l.s. 10,994.96 10,994.96 13,853.65 0.15
1001(9) Storm Drainage and Downspout 1.00 l.s. 75,264.10 75,264.10 94,832.77 1.02
1001(11) Septic Vault (Concrete/CHB) 1.00 l.s. 56,986.63 56,986.63 71,803.16 0.77
1001(5)b Catch basin (CHB) 12.00 units 9,816.38 818.03 1,030.72 0.13
1202(1) Automatic Fire Sprinkler System (AFSS) 1.00 lot 419,566.42 419,566.42 528,653.69 5.70
PART E ELECTRICAL
1100(10) Conduits, Boxes, and Fittings 1.00 l.s. 37,420.23 37,420.23 47,149.49 0.51
1101(33) Wires and Wiring Devices 1.00 l.s. 51,507.12 51,507.12 64,898.97 0.70
1102(1) Panel Board with Main & Branch Breakers 1.00 l.s. 26,416.32 26,416.32 33,284.56 0.36
1003(1) Lighting Fixtures and Lamps 1.00 l.s. 45,339.74 45,339.74 57,128.07 0.62
1208(1) Fire Alarm System 1.00 l.s. 8,780.97 8,780.97 11,064.02 0.12
FORM POW-2015-01B-00
MINIMUM EQUIPMENT REQUIREMENT
Number of Number of
No. Equipment Description Capacity No. Equipment Description Capacity
Equipment Equipment
1 Backhoe 0.80 m3 1 31
2 Dump Truck 12 yd 3
2 32
3 Plate Compactor 5 hp 1 33
4 Concrete Vibrator 5 amp 1 34
5 Pumpcrete 1 35
6 One Bagger Mixer 4 - 6 ft /min
3
1 36
7 Bar Cutter 1 37
8 Bar Bender 1 38
9 Welding Machine 500 amp 2 39
10 Cutting Outfit 1 40
11 Truck Mounted Crane 20 - 25 mt 1 41
12 Drill Rig, Mechanical Rotary 300 hp 1 42
13 Bentonite Mixer 1 43
14 Bentonite Bin 1 44
15 Water Pump 1,800 lpm, 7.5 hp 1 45
16 Water Truck 16,000 L, 360 hp 1 46
17 Tremie Pipe Set 1 47
18 SPT & Desanding Machine 1 48
19 Tower Lights 2 49
20 50
21 51
22 52
23 53
24 54
25 55
26 56
27 57
28 58
29 59
30 60
SUB-TOTAL SUB-TOTAL
TOTAL
STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE
PART II OTHER GENERAL REQUIREMENTS
As Submitted 0.06 1.00 ea 3,505.00 699.72 69.97 4,274.69 4,274.69 20% 854.94 256.48 5,386.11
B.5 Project Billboard/ Sign Board
As Evaluated
As Submitted 1.09 1.00 l.s. 76,734.52 3,549.44 - 80,283.96 80,283.96 8% 6,422.72 4,335.33 91,042.01
B.7(2) Occupational Safety and Health
As Evaluated
As Submitted 0.74 1.00 l.s. - - 54,140.93 54,140.93 54,140.93 8% 4,331.27 2,923.61 61,395.81
B.9 Mobilization/ Demobilization
As Evaluated
As Submitted 80,239.52 4,249.16 54,210.90 138,699.58 11,608.93 7,515.42 157,823.93
TOTAL OF PART II
As Evaluated
(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted 0.20 1.00 l.s. - 13,651.00 1,365.10 15,016.10 15,016.10 20% 3,003.22 900.97 18,920.29
801(1) Removal of Structures and Obstruction
As Evaluated
As Submitted 0.39 124.00 m3 - 1,272.80 27,264.68 230.14 28,537.48 20% 5,707.50 1,712.25 35,957.23
803(1)a Structure Excavation
As Evaluated
As Submitted 0.18 89.16 m 3
- 1,860.13 11,466.93 149.47 13,327.06 20% 2,665.41 799.62 16,792.09
804(1)a Embankment (from Roadway/Structure Excavation)
As Evaluated
As Submitted 1.17 247.10 m3 49,419.20 5,155.12 31,779.19 349.47 86,353.51 20% 17,270.70 5,181.21 108,805.42
804(1)b Embankment (from Borrow)
As Evaluated
As Submitted 0.38 33.00 m3 19,750.50 5,645.48 2,255.80 837.93 27,651.78 20% 5,530.36 1,659.11 34,841.25
804(4) Gravel Fill
As Evaluated
As Submitted 69,169.70 27,584.53 74,131.70 170,885.93 34,177.19 10,253.16 215,316.28
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted 12.74 240.91 m3 857,639.60 28,814.65 51,000.00 3,891.30 937,454.25 20% 187,490.85 56,247.26 1,181,192.36
900(1)c1 Structural Concrete ( Class A, 28 days)
As Evaluated
As Submitted 16.83 25,503.67 kg 1,016,926.96 149,722.00 71,399.96 48.54 1,238,048.92 20% 247,609.78 74,282.94 1,559,941.64
902(1)a Reinforcing Steel (Deformed) , Grade 40
As Evaluated
As Submitted 4.10 650.00 m2 134,242.63 107,309.40 60,318.96 464.42 301,870.99 20% 60,374.20 18,112.26 380,357.45
903(2) Forms and Falseworks
As Evaluated
As Submitted 2,008,809.19 285,846.05 182,718.92 2,477,374.16 495,474.83 148,642.46 3,121,491.45
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted 0.17 34.00 L 11,220.00 1,371.59 137.16 374.38 12,728.75 20% 2,545.75 763.73 16,038.23
1000(1) Soil Poisoning
As Evaluated
As Submitted 11,220.00 1,371.59 137.16 12,728.75 2,545.75 763.73 16,038.23
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted 0.40 53.62 m2 21,790.10 4,432.73 2,854.42 542.28 29,077.25 20% 5,815.45 1,744.64 36,637.34
1046(2)a1 CHB Non Load Bearing Wall (including Reinforcing Steel) 100 mm
As Evaluated
As Submitted 6.46 566.12 m2 382,770.72 56,293.33 36,249.66 839.60 475,313.71 20% 95,062.74 28,518.82 598,895.27
1046(2)a2 CHB Non Load Bearing Wall (including Reinforcing Steel) 150 mm
As Evaluated
As Submitted 404,560.82 60,726.06 39,104.08 504,390.96 100,878.19 30,263.46 635,532.61
Sub - Total C.2
As Evaluated
STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE
C.3 Fabricated Materials
As Submitted 1.76 1.00 l.s. 107,664.00 20,116.95 2,011.70 129,792.65 129,792.65 20% 25,958.53 7,787.56 163,538.74
1010(4) Wooden Doors and Windows
As Evaluated
As Submitted 0.52 24.05 m2 21,055.78 15,581.73 1,558.17 1,588.18 38,195.68 20% 7,639.14 2,291.74 48,126.56
1009(1)a Jalousie Window (Glass)
As Evaluated
As Submitted 2.37 48.96 m 2
95,104.80 47,580.96 31,346.10 3,554.57 174,031.86 20% 34,806.37 10,441.91 219,280.14
1005 (1) Residential Casement (Steel)
As Evaluated
As Submitted 0.86 1.00 l.s. 51,374.65 7,347.06 4,840.21 63,561.92 63,561.92 20% 12,712.38 3,813.72 80,088.02
1005(6) Window Accessory (Window Grill)
As Evaluated
As Submitted 0.34 1.00 l.s. 25,340.00 - - 25,340.00 25,340.00 20% 5,068.00 1,520.40 31,928.40
1004(2) Finishing Hardware
As Evaluated
As Submitted 0.21 1.00 l.s. 12,400.00 2,492.64 249.26 15,141.90 15,141.90 20% 3,028.38 908.51 19,078.79
1003(17) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 312,939.23 93,119.34 40,005.44 446,064.01 89,212.80 26,763.84 562,040.65
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted 0.82 224.90 m2 49,815.35 9,855.91 985.59 269.71 60,656.85 20% 12,131.37 3,639.41 76,427.63
1021(1)c Cement Floor Finish (with floor hardener)
As Evaluated
As Submitted 1.87 910.31 m2 87,162.18 45,882.18 4,588.22 151.19 137,632.58 20% 27,526.52 8,257.96 173,417.06
1027(1) Cement Plaster Finish
As Evaluated
As Submitted 0.22 36.00 m 13,290.48 1,253.76 1,878.54 456.19 16,422.78 20% 3,284.56 985.37 20,692.71
1051(1) Railing (38 mm dia. G.I. Pipe Railings)
As Evaluated
Metal Railing (50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 As Submitted 2.55 96.00 m 179,147.08 3,343.35 5,009.44 1,953.12 187,499.87 20% 37,499.97 11,249.99 236,249.83
1051(5)
mm bar stiffener) As Evaluated
As Submitted 2.81 281.66 m 2
152,296.94 49,361.88 4,936.19 733.49 206,595.01 20% 41,319.00 12,395.70 260,309.71
1003(1)a1 Ceiling (Fiber Cement Board on Metal Frame)
As Evaluated
As Submitted 0.71 282.97 m2 40,111.00 11,086.72 1,108.67 184.85 52,306.39 20% 10,461.28 3,138.38 65,906.05
1038(1) Reflective Insulation
As Evaluated
As Submitted 0.70 36.69 m2 34,581.32 15,278.36 1,527.84 1,400.59 51,387.52 20% 10,277.50 3,083.25 64,748.27
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted 3.93 210.21 m2 222,064.53 61,274.60 6,127.46 1,377.04 289,466.59 20% 57,893.32 17,368.00 364,727.91
1018(2) Unglazed Tiles
As Evaluated
As Submitted 778,468.88 197,336.76 26,161.95 1,001,967.59 200,393.52 60,118.06 1,262,479.17
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted 3.71 1,128.81 m2 136,849.02 123,841.21 12,384.12 241.91 273,074.35 20% 54,614.87 16,384.46 344,073.68
1032(1)a Painting Works (Masonry/Concrete)
As Evaluated
As Submitted 0.93 332.22 m 2
23,842.60 40,497.44 4,049.74 205.86 68,389.78 20% 13,677.96 4,103.39 86,171.13
1032(1)b Painting Works (Wood)
As Evaluated
As Submitted 2.53 747.15 m 2
91,639.89 86,067.94 8,606.79 249.37 186,314.62 20% 37,262.92 11,178.88 234,756.42
1032(1)c Painting Works (Steel)
As Evaluated
As Submitted 252,331.51 250,406.59 25,040.65 527,778.75 105,555.75 31,666.73 665,001.23
Sub-Total C.5
As Evaluated
STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE
C.6 Roof Framing and Roofing Works
As Submitted 2.26 282.97 m2 133,634.00 29,692.77 2,969.28 587.68 166,296.05 20% 33,259.21 9,977.76 209,533.02
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted 0.08 26.20 m 5,016.70 458.32 45.83 210.72 5,520.85 20% 1,104.17 331.25 6,956.27
1013(2)a1 Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted 0.08 29.48 m 5,644.74 515.69 51.57 210.72 6,212.00 20% 1,242.40 372.72 7,827.12
1013(2)a2 Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
As Submitted 0.21 47.00 m 14,329.36 696.76 69.68 321.19 15,095.80 20% 3,019.16 905.75 19,020.71
1013(2)b1 Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted 6.49 6,092.46 kg 366,712.78 29,953.68 81,036.38 78.41 477,702.84 20% 95,540.57 28,662.17 601,905.58
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted 3.37 3,376.13 kg 205,783.56 13,404.49 29,036.29 73.52 248,224.34 20% 49,644.87 14,893.46 312,762.67
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted 0.18 70.20 m 11,572.47 1,287.20 128.72 185.02 12,988.39 20% 2,597.68 779.30 16,365.37
1003(11)a1 Fascia Board (Fiber Cement Board)
As Evaluated
As Submitted 0.89 920.30 kg 51,755.83 12,388.46 1,238.85 71.05 65,383.14 20% 13,076.63 3,922.99 82,382.76
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted 0.12 170.06 kg 6,606.83 2,289.23 52.30 52.62 8,948.36 20% 1,789.67 536.90 11,274.93
1047(7)a Metal Structure Accessories, Bolts
As Evaluated
As Submitted 0.14 195.00 kg 7,575.75 2,624.96 52.30 52.58 10,253.01 20% 2,050.60 615.18 12,918.79
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted 0.06 75.76 kg 3,031.57 1,019.83 101.98 54.82 4,153.38 20% 830.68 249.20 5,233.26
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted 0.08 28.00 pc 5,180.00 734.71 0.73 211.27 5,915.44 20% 1,183.09 354.93 7,453.46
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted 1.40 1.00 l.s. 62,940.83 12,868.88 27,305.82 103,115.53 103,115.53 20% 20,623.11 6,186.93 129,925.57
1047(10) Metal Structure Accessories, Fire Escape
As Evaluated
As Submitted 879,784.42 107,934.98 142,089.73 1,129,809.13 225,961.84 67,788.54 1,423,559.51
Sub-Total C.6
As Evaluated
As Submitted 2,639,304.86 710,895.32 272,539.01 3,622,739.19 724,547.85 217,364.36 4,564,651.40
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted 0.29 1.00 l.s. 17,902.45 3,213.14 321.31 21,436.90 21,436.90 20% 4,287.38 1,286.21 27,010.49
1001(8) Sewer Line Works
As Evaluated
As Submitted 0.15 1.00 l.s. 9,856.75 1,034.74 103.47 10,994.96 10,994.96 20% 2,198.99 659.70 13,853.65
1002(24) Cold Water Lines
As Evaluated
As Submitted 1.02 1.00 l.s. 63,215.62 10,953.16 1,095.32 75,264.10 75,264.10 20% 15,052.82 4,515.85 94,832.77
1001(9) Storm Drainage and Downspout
As Evaluated
As Submitted 2.50 1.00 l.s. 168,578.97 14,256.80 1,425.68 184,261.45 184,261.45 20% 36,852.29 11,055.69 232,169.43
1002(4) Plumbing Fixtures
As Evaluated
As Submitted 0.77 1.00 l.s. 46,913.31 9,157.56 915.76 56,986.63 56,986.63 20% 11,397.33 3,419.20 71,803.16
1001(11) Septic Vault (Concrete/CHB)
As Evaluated
As Submitted 0.13 12.00 units 7,507.30 2,099.16 209.92 818.03 9,816.38 20% 1,963.28 588.98 12,368.64
1001(5)b Catch basin (CHB)
As Evaluated
As Submitted 5.70 1.00 lot 385,396.15 31,063.88 3,106.39 419,566.42 419,566.42 20% 83,913.28 25,173.99 528,653.69
1202(1) Automatic Fire Sprinkler System (AFSS)
As Evaluated
As Submitted 699,370.55 71,778.44 7,177.85 778,326.84 155,665.37 46,699.62 980,691.83
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted 0.51 1.00 l.s. 30,337.80 6,438.57 643.86 37,420.23 37,420.23 20% 7,484.05 2,245.21 47,149.49
1100(10) Conduits, Boxes, and Fittings
As Evaluated
As Submitted 0.70 1.00 l.s. 46,384.17 4,657.23 465.72 51,507.12 51,507.12 20% 10,301.42 3,090.43 64,898.97
1101(33) Wires and Wiring Devices
As Evaluated
As Submitted 0.36 1.00 l.s. 24,259.70 1,960.56 196.06 26,416.32 26,416.32 20% 5,283.26 1,584.98 33,284.56
1102(1) Panel Board with Main & Branch Breakers
As Evaluated
As Submitted 0.62 1.00 l.s. 41,985.00 3,049.76 304.98 45,339.74 45,339.74 20% 9,067.95 2,720.38 57,128.07
1103(1) Lighting Fixtures and Lamps
As Evaluated
As Submitted 0.12 1.00 l.s. 6,184.00 2,360.88 236.09 8,780.97 8,780.97 20% 1,756.19 526.86 11,064.02
1208(1) Fire Alarm System
As Evaluated
As Submitted 149,150.67 18,467.00 1,846.71 169,464.380 33,892.870 10,167.860 213,525.110
TOTAL OF PART E
As Evaluated
STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE
As Submitted 5,565,804.97 1,114,571.34 538,414.19 7,218,790.50 1,443,758.110 433,127.460 9,095,676.070
TOTAL OF PART III
As Evaluated
As Submitted 5,646,044.49 1,118,820.50 592,625.09 7,357,490.08 1,455,367.040 440,642.880 9,253,500.000
GRAND TOTAL
As Evaluated
Republic of the Philippines
Department of Public Works and Highways
Ilocos Sur 1st
District Engineering Office
Regional Office I
Zone VI, Bantay, Ilocos Sur
FORM ABC-2015-02-00
STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING
(Project ID)
(Project Component ID - Description)
CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING
PART III
WORKS
AS SUBMITTED 170,885.93 20.00% 34,177.19 10,253.16 44,430.35 215,316.28
PART A EARTHWORKS
AS EVALUATED
EVELYN P. TAMAYO MARY JANE A. ETRATA RAYNALDO R. ABLOG,MAPA REYNALDO S. ORGANO, MBA
Engineer II OIC-Chief (Construction Section) OIC-Assistant District Engineer District Engineer
(Member) (Member)
Republic of the Philippines
Department of Public Works and Highways
Ilocos Sur 1st
District Engineering Office
Regional Office I
Zone VI, Bantay, Ilocos Sur FORM ABC-2015-02A-00
(Project ID)
(Project Component ID - Description)
PART A EARTHWORKS
AS SUBMITTED 1.00 l.s. 15,016.10 20% 3,003.22 900.97 3,904.19 18,920.29 18,920.29
801(1) Removal of Structures and Obstruction
AS EVALUATED
EVELYN P. TAMAYO MARY JANE A. ETRATA RAYNALDO R. ABLOG,MAPA REYNALDO S. ORGANO, MBA
Engineer II OIC-Chief (Construction Section) OIC-Assistant District Engineer District Engineer
Republic of the Philippines
Department of Public Works and Highways
Ilocos Sur 1st
District Engineering Office
Regional Office I
Zone VI, Bantay, Ilocos Sur FORM ABC-2015-02A-00
CHB Non Load Bearing Wall (including Reinforcing Steel) 100 AS SUBMITTED 53.62 m2 29,077.25 20% 5,815.45 1,744.64 7,560.09 36,637.34 683.28
1046(2)a1
mm AS EVALUATED
CHB Non Load Bearing Wall (including Reinforcing Steel) 150 AS SUBMITTED 566.12 m2 475,313.71 20% 95,062.74 28,518.82 123,581.56 598,895.27 1,057.89
1046(2)a2
mm AS EVALUATED
AS SUBMITTED 1.00 l.s. 129,792.65 20% 25,958.53 7,787.56 33,746.09 163,538.74 163,538.74
1010(4) Wooden Doors and Windows
AS EVALUATED
AS SUBMITTED 1.00 l.s. 63,561.92 20% 12,712.38 3,813.72 16,526.10 80,088.02 80,088.02
1005(6) Window Accessory (Window Grill)
AS EVALUATED
AS SUBMITTED 1.00 l.s. 25,340.00 20% 5,068.00 1,520.40 6,588.40 31,928.40 31,928.40
1004(2) Finishing Hardware
AS EVALUATED
EVELYN P. TAMAYO MARY JANE A. ETRATA RAYNALDO R. ABLOG,MAPA REYNALDO S. ORGANO, MBA
Engineer II OIC-Chief (Construction Section) OIC-Assistant District Engineer District Engineer
(Member) (Member)
Republic of the Philippines
Department of Public Works and Highways
Ilocos Sur 1st
District Engineering Office
Regional Office I
Zone VI, Bantay, Ilocos Sur FORM ABC-2015-02A-00
Metal Railing (50 mm Ø G.I. Pipe Handrail Fully Welded on AS SUBMITTED 96.00 m 187,499.87 20% 37,499.97 11,249.99 48,749.96 236,249.83 2,460.94
1051(5)
vertical Railing on 19 mm bar stiffener) AS EVALUATED
AS SUBMITTED 1.00 l.s. 103,115.53 20% 20,623.11 6,186.93 26,810.04 129,925.57 129,925.57
1047(10) Metal Structure Accessories, Fire Escape
AS EVALUATED
AS SUBMITTED 1.00 l.s. 75,264.10 20% 15,052.82 4,515.85 19,568.67 94,832.77 94,832.77
1001(9) Storm Drainage and Downspout
AS EVALUATED
AS SUBMITTED 1.00 l.s. 184,261.45 20% 36,852.29 11,055.69 47,907.98 232,169.43 232,169.43
1002(4) Plumbing Fixtures
AS EVALUATED
AS SUBMITTED 1.00 l.s. 56,986.63 20% 11,397.33 3,419.20 14,816.53 71,803.16 71,803.16
1001(11) Septic Vault (Concrete/CHB)
AS EVALUATED
AS SUBMITTED 12.00 units 9,816.38 20% 1,963.28 588.98 2,552.26 12,368.64 1,030.72
1001(5)b Catch basin (CHB)
AS EVALUATED
AS SUBMITTED 1.00 lot 419,566.42 20% 83,913.28 25,173.99 109,087.27 528,653.69 528,653.69
1202(1) Automatic Fire Sprinkler System (AFSS)
AS EVALUATED
EVELYN P. TAMAYO MARY JANE A. ETRATA RAYNALDO R. ABLOG,MAPA REYNALDO S. ORGANO, MBA
Engineer II OIC-Chief (Construction Section) OIC-Assistant District Engineer District Engineer
(Member) (Member)
Republic of the Philippines
Department of Public Works and Highways
Ilocos Sur 1st
District Engineering Office
Regional Office I
Zone VI, Bantay, Ilocos Sur FORM ABC-2015-02A-00
EVELYN P. TAMAYO MARY JANE A. ETRATA RAYNALDO R. ABLOG,MAPA REYNALDO S. ORGANO, MBA
Engineer II OIC-Chief (Construction Section) OIC-Assistant District Engineer District Engineer
(Member) (Member)
ANNEX A
BUREAU OF CONSTRUCTION
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 1.71% 99,666.67
Part II Other General Requirements 1.95% 113,214.26
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 1.44% 83,682.13
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 27.04% 1,572,255.66
PART C FINISHING WORKS 53.32% 3,099,822.64
PART D PLUMBING/SANITARY WORKS 12.55% 729,557.62
PART E ELECTRICAL WORKS 1.98% 115,373.83
Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:
Name & Signature Name & Signature Name & Signature Name & Signature Name & Signature
Position Title Position Title Position Title Position Title Position Title
Planning. Section/Division Planning Section/Division Planning Division
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED
II.5 Project Billboard/ Sign Board 1.00 ea 4,274.69 4,274.69 5,386.11 0.07
II.7 Occupational Safety and Health 1.00 l.s. 66,934.38 66,934.38 75,903.59 1.15
Project ID
PART A EARTHWORKS
804(1)a Embankment from Structure Excavation 66.34 m3 9,916.07 149.47 188.34 0.17
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days) 102.63 m3 399,364.62 3,891.30 4,903.04 6.87
PART C FINISHING
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel) 227.17 m2 190,731.67 839.60 1,057.89 3.28
1005 (1) Steel Casement Window 24.48 m2 87,015.93 3,554.57 4,478.76 1.50
1003(9) Carpentry and Joinery Works (Blackboard) 1.00 l.s. 7,570.95 7,570.95 9,539.40 0.13
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED
1021(1)c Plain Cement Finish with floor hardener 263.35 m2 71,027.04 269.71 339.83 1.22
1027(1) Plain Cement Plaster Finish 1,252.61 m2 189,385.97 151.19 190.50 3.26
1053(3)a1 38 mm dia. G.I. Pipe Railings 33.00 m 15,054.21 456.19 574.80 0.26
1053(3)a2 50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar stiffener 55.82 m 109,023.36 1,953.12 2,460.94 1.88
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame 142.77 m2 104,720.48 733.49 924.20 1.80
1018(1) Glazed Tiles and Trims 71.55 m2 100,211.97 1,400.59 1,764.74 1.72
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk) 14.90 m 3,139.72 210.72 265.51 0.05
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk) 26.21 m 5,522.95 210.72 265.51 0.10
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk) 29.80 m 9,571.37 321.19 404.70 0.16
1047(6) Metal Structure Accessories, Steel Plates 277.47 kg 19,712.99 71.05 89.52 0.34
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED
1047(7)b Metal Structure Accessories, Sag Rods 55.85 kg 2,996.77 53.66 67.61 0.05
1047(4) Metal Structure Accessories, Cross Bracing 113.93 kg 6,245.98 54.82 69.08 0.11
1047(3)c Metal Structure Accessories, Turn Buckle 10.00 pc 2,112.66 211.27 266.20 0.04
1047(6)-1 Metal Structure Accessories, Fire Escape 1.00 l.s. 103,115.53 103,115.53 129,925.57 1.77
1001(8) Sewer Line Works 1.00 l.s. 20,649.47 20,649.47 26,018.33 0.36
1002(6) Cold Water Line Works 1.00 l.s. 10,994.96 10,994.96 13,853.65 0.19
SPL-3 Septic Vault "Type E" 1.00 l.s. 39,187.36 39,187.36 49,376.07 0.67
PART E ELECTRICAL
1100(19) Conduits, Boxes, and Fittings 1.00 l.s. 24,542.42 24,542.42 30,923.45 0.42
1101(18) Wires and Wiring Devices 1.00 l.s. 36,441.35 36,441.35 45,916.10 0.63
1208(1) Fire Alarm System 1.00 l.s. 8,780.97 8,780.97 11,064.02 0.15
FORM POW-2015-01B-00
MINIMUM EQUIPMENT REQUIREMENT
Number of Number of
No. Equipment Description Capacity No. Equipment Description Capacity
Equipment Equipment
1 Backhoe 0.80 m3 1 31
2 Dump Truck 12 yd 3
2 32
3 Plate Compactor 5 hp 1 33
4 Concrete Vibrator 5 amp 1 34
5 Pumpcrete 1 35
6 One Bagger Mixer 4 - 6 ft /min
3
1 36
7 Bar Cutter 1 37
8 Bar Bender 1 38
9 Welding Machine 500 amp 2 39
10 Cutting Outfit 1 40
11 Truck Mounted Crane 20 - 25 mt 1 41
12 Drill Rig, Mechanical Rotary 300 hp 1 42
13 Bentonite Mixer 1 43
14 Bentonite Bin 1 44
15 Water Pump 1,800 lpm, 7.5 hp 1 45
16 Water Truck 16,000 L, 360 hp 1 46
17 Tremie Pipe Set 1 47
18 SPT & Desanding Machine 1 48
19 Tower Lights 2 49
20 50
21 51
22 52
23 53
24 54
25 55
26 56
27 57
28 58
29 59
30 60
SUB-TOTAL SUB-TOTAL
TOTAL
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted 1.71 3.83 mo - - 99,666.67 99,666.67 8% 7,973.33 5,382.00 113,022.00
I.1.1 (1) 0
As Evaluated
As Submitted - - 99,666.67 99,666.67 7,973.33 5,382.00 113,022.00
TOTAL OF PART I
As Evalauted
PART II OTHER GENERAL REQUIREMENTS
As Submitted 0.07 1.00 ea 3,505.00 699.72 69.97 4,274.69 20% 854.94 256.48 5,386.11
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted 1.15 1.00 l.s. 63,384.94 3,549.44 - 66,934.38 8% 5,354.75 3,614.46 75,903.59
II.7 Occupational Safety and Health
As Evaluated
As Submitted 0.72 1.00 l.s. - - 42,005.19 42,005.19 8% 3,360.42 2,268.28 47,633.89
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 66,889.94 4,249.16 42,075.16 113,214.26 9,570.11 6,139.22 128,923.59
TOTAL OF PART II
As Evaluated
(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted 0.57 144.01 m3 - 1,478.19 31,664.41 33,142.60 20% 6,628.52 1,988.56 41,759.68
803(1)a Structure Excavation
As Evaluated
As Submitted 0.17 66.34 m3 - 1,384.04 8,532.03 9,916.07 20% 1,983.21 594.96 12,494.24
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted 0.38 64.02 m3 12,804.00 1,335.64 8,233.66 22,373.29 20% 4,474.66 1,342.40 28,190.35
804(1)b Embankment from Borrow
As Evaluated
As Submitted 0.31 21.78 m3 13,035.33 3,726.01 1,488.83 18,250.17 20% 3,650.03 1,095.01 22,995.21
804(4) Gravel Fill
As Evaluated
As Submitted 25,839.33 7,923.88 49,918.92 83,682.13 16,736.42 5,020.93 105,439.48
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted 6.87 102.63 m3 365,362.80 12,275.32 21,726.50 399,364.62 20% 79,872.92 23,961.88 503,199.42
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted 15.32 18,342.24 kg 731,373.89 107,680.06 51,350.86 890,404.81 20% 178,080.96 53,424.29 1,121,910.06
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted 4.86 608.26 m2 125,622.19 100,418.48 56,445.55 282,486.23 20% 56,497.25 16,949.17 355,932.65
903(2) Forms and Falseworks
As Evaluated
As Submitted 1,222,358.88 220,373.86 129,522.91 1,572,255.66 314,451.13 94,335.34 1,981,042.13
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted 0.48 75.31 L 24,852.30 3,038.06 303.81 28,194.17 20% 5,638.83 1,691.65 35,524.65
1000(1) Soil Poisoning
As Evaluated
As Submitted 24,852.30 3,038.06 303.81 28,194.17 5,638.83 1,691.65 35,524.65
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted 1.05 112.48 m2 45,709.62 9,298.64 5,987.79 60,996.05 20% 12,199.21 3,659.76 76,855.02
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted 3.28 227.17 m2 153,596.45 22,589.13 14,546.10 190,731.67 20% 38,146.33 11,443.90 240,321.90
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 199,306.07 31,887.77 20,533.88 251,727.72 50,345.54 15,103.66 317,176.92
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted 1.54 1.00 l.s. 73,344.00 14,869.05 1,486.91 89,699.96 20% 17,939.99 5,382.00 113,021.95
1010(4) Wooden Doors
As Evaluated
As Submitted 0.37 13.71 m2 12,003.11 8,882.56 888.26 21,773.92 20% 4,354.78 1,306.44 27,435.14
1009(1)a Jalousie Window
As Evaluated
As Submitted 1.50 24.48 m2 47,552.40 23,790.48 15,673.05 87,015.93 20% 17,403.19 5,220.96 109,640.08
1005 (1) Steel Casement Window
As Evaluated
As Submitted 11.90 10.88 m 2
558,956.18 79,936.01 52,661.44 691,553.64 20% 138,310.73 41,493.22 871,357.59
1005 (5) Window Grill
As Evaluated
As Submitted 6.97 16.00 set 405,440.00 - - 405,440.00 20% 81,088.00 24,326.40 510,854.40
1004(2)a Locksets
As Evaluated
As Submitted 0.07 64.00 pc 4,160.00 - - 4,160.00 20% 832.00 249.60 5,241.60
1004(2)g Hinges
As Evaluated
As Submitted 0.13 1.00 l.s. 6,200.00 1,246.32 124.63 7,570.95 20% 1,514.19 454.26 9,539.40
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 1,107,655.69 128,724.42 70,834.28 1,307,214.40 261,442.88 78,432.88 1,647,090.16
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted 1.22 263.35 m2 58,332.03 11,540.93 1,154.09 71,027.04 20% 14,205.41 4,261.62 89,494.07
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted 3.26 1,252.61 m2 119,937.41 63,135.06 6,313.51 189,385.97 20% 37,877.19 11,363.16 238,626.32
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted 0.26 33.00 m 12,182.94 1,149.28 1,722.00 15,054.21 20% 3,010.84 903.25 18,968.30
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
As Submitted 1.88 55.82 m 104,166.56 1,944.02 2,912.78 109,023.36 20% 21,804.67 6,541.40 137,369.43
1053(3)a2 50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar stiffener
As Evaluated
As Submitted 1.80 142.77 m2 77,197.45 25,020.93 2,502.09 104,720.48 20% 20,944.10 6,283.23 131,947.81
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted 0.63 196.68 m2 27,879.39 7,705.89 770.59 36,355.87 20% 7,271.17 2,181.35 45,808.39
1038(1) Reflective Insulation
As Evaluated
As Submitted 1.72 71.55 m2 67,437.82 29,794.68 2,979.47 100,211.97 20% 20,042.39 6,012.72 126,267.08
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted 0.47 20.05 m2 21,180.69 5,844.42 584.44 27,609.56 20% 5,521.91 1,656.57 34,788.04
1018(2) Unglazed Tiles
As Evaluated
As Submitted 488,314.30 146,135.20 18,938.97 653,388.46 130,677.68 39,203.30 823,269.44
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted 5.58 1,339.81 m2 162,429.19 146,989.92 14,698.99 324,118.09 20% 64,823.62 19,447.09 408,388.80
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted 0.27 75.71 m2 5,433.52 9,229.01 922.90 15,585.43 20% 3,117.09 935.13 19,637.65
1032(1)b Wood Painting
As Evaluated
As Submitted 0.16 37.55 m2 4,605.61 4,325.57 432.56 9,363.73 20% 1,872.75 561.82 11,798.30
1032(1)c Metal Painting
As Evaluated
As Submitted 172,468.31 160,544.50 16,054.45 349,067.25 69,813.46 20,944.04 439,824.75
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted 1.99 196.68 m2 92,883.11 20,638.14 2,063.81 115,585.06 20% 23,117.01 6,935.10 145,637.17
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted 0.05 14.90 m 2,853.01 260.65 26.06 3,139.72 20% 627.94 188.38 3,956.04
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted 0.10 26.21 m 5,018.61 458.49 45.85 5,522.95 20% 1,104.59 331.38 6,958.92
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 0.16 29.80 m 9,085.42 441.77 44.18 9,571.37 20% 1,914.27 574.28 12,059.92
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted 1.36 1,008.85 kg 60,723.94 4,960.03 13,418.81 79,102.78 20% 15,820.56 4,746.17 99,669.51
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted 2.71 2,143.69 kg 130,663.26 8,511.24 18,436.73 157,611.24 20% 31,522.25 9,456.67 198,590.16
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted 0.09 29.80 m 4,912.53 546.42 54.64 5,513.59 20% 1,102.72 330.82 6,947.13
1003(11) Fascia Board
As Evaluated
As Submitted 0.34 277.47 kg 15,604.36 3,735.12 373.51 19,712.99 20% 3,942.60 1,182.78 24,838.37
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted 0.05 55.85 kg 2,169.77 751.82 75.18 2,996.77 20% 599.35 179.81 3,775.93
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted 0.11 113.93 kg 4,558.97 1,533.65 153.36 6,245.98 20% 1,249.20 374.76 7,869.94
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted 0.04 10.00 pc 1,850.00 262.40 0.26 2,112.66 20% 422.53 126.76 2,661.95
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted 1.77 1.00 l.s. 62,940.83 12,868.88 27,305.82 103,115.53 20% 20,623.11 6,186.93 129,925.57
1047(6)-1 Metal Structure Accessories, Fire Escape
As Evaluated
As Submitted 393,263.82 54,968.59 61,998.23 510,230.64 102,046.13 30,613.84 642,890.61
Sub-Total C.6
As Evaluated
As Submitted 2,385,860.48 525,298.54 188,663.62 3,099,822.64 619,964.52 185,989.37 3,905,776.53
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted 0.36 1.00 l.s. 17,474.45 2,886.38 288.64 20,649.47 20% 4,129.89 1,238.97 26,018.33
1001(8) Sewer Line Works
As Evaluated
As Submitted 0.19 1.00 l.s. 9,856.75 1,034.74 103.47 10,994.96 20% 2,198.99 659.70 13,853.65
1002(6) Cold Water Line Works
As Evaluated
As Submitted 1.10 1.00 l.s. 53,942.02 9,337.12 933.71 64,212.85 20% 12,842.57 3,852.77 80,908.19
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted 3.15 1.00 l.s. 167,402.97 14,125.60 1,412.56 182,941.13 20% 36,588.23 10,976.47 230,505.83
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted 0.67 1.00 l.s. 32,175.55 6,374.38 637.44 39,187.36 20% 7,837.47 2,351.24 49,376.07
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted 0.11 8.00 units 5,004.86 1,399.44 139.94 6,544.25 20% 1,308.85 392.66 8,245.76
1001(6)b1 Catch basin
As Evaluated
As Submitted 6.97 1.00 lot 371,746.15 30,255.86 3,025.59 405,027.60 20% 81,005.52 24,301.66 510,334.78
SPL-2 Fire Protection System
As Evaluated
As Submitted 657,602.75 65,413.52 6,541.35 729,557.62 145,911.52 43,773.47 919,242.61
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted 0.42 1.00 l.s. 22,594.20 1,771.11 177.11 24,542.42 20% 4,908.48 1,472.55 30,923.45
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted 0.63 1.00 l.s. 33,302.85 2,853.18 285.32 36,441.35 20% 7,288.27 2,186.48 45,916.10
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted 0.35 1.00 l.s. 18,390.10 1,524.88 152.49 20,067.47 20% 4,013.49 1,204.05 25,285.01
1102(21) Panel Board
As Evaluated
As Submitted 0.44 1.00 l.s. 23,385.00 1,960.56 196.06 25,541.62 20% 5,108.32 1,532.50 32,182.44
1003(1) Lighting Fixtures
As Evaluated
As Submitted 0.15 1.00 l.s. 6,184.00 2,360.88 236.09 8,780.97 20% 1,756.19 526.86 11,064.02
1208(1) Fire Alarm System
As Evaluated
As Submitted 103,856.15 10,470.61 1,047.06 115,373.830 23,074.750 6,922.440 145,371.020
TOTAL OF PART E
As Evaluated
As Submitted 4,395,517.59 829,480.42 375,693.85 5,600,691.880 1,120,138.340 336,041.550 7,056,871.770
TOTAL OF PART III
As Evaluated
As Submitted 4,395,517.59 829,480.42 375,693.85 5,600,691.880 1,120,138.340 336,041.550 7,056,871.770
TOTAL OF (Project ID)
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
TOTAL OF (Project ID)
As Evaluated
As Submitted 4,462,407.53 833,729.58 517,435.68 5,813,572.810 1,137,681.780 347,562.770 7,298,817.360
GRAND TOTAL
As Evaluated
BUREAU OF CONSTRUCTION
FORM ABC-2015-02-00
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING
(Project ID)
(Project Component ID - Description)
CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING
PART III
WORKS
AS SUBMITTED 83,682.13 20.00% 16,736.42 5,020.93 21,757.35 105,439.48
PART A EARTHWORKS
AS EVALUATED
Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:
Name & Signature Name & Signature Name & Signature Name & Signature Name & Signature
Position Title Position Title Position Title Position Title Position Title
Planning. Section/Division Planning Section/Division Planning Division
BUREAU OF CONSTRUCTION
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING
(Project ID)
(Project Component ID - Description)
PART A EARTHWORKS
AS SUBMITTED 144.01 m3 33,142.60 20% 6,628.52 1,988.56 8,617.08 41,759.68 289.98
803(1)a Structure Excavation
AS EVALUATED
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING
100 mm CHB Non Load Bearing Wall (including Reinforcing AS SUBMITTED 112.48 m2 60,996.05 20% 12,199.21 3,659.76 15,858.97 76,855.02 683.28
1046(2)a1
Steel) AS EVALUATED
150 mm CHB Non Load Bearing Wall (including Reinforcing AS SUBMITTED 227.17 m2 190,731.67 20% 38,146.33 11,443.90 49,590.23 240,321.90 1,057.89
1046(2)a2
Steel) AS EVALUATED
AS SUBMITTED 1.00 l.s. 89,699.96 20% 17,939.99 5,382.00 23,321.99 113,021.95 113,021.95
1010(4) Wooden Doors
AS EVALUATED
AS SUBMITTED 16.00 set 405,440.00 20% 81,088.00 24,326.40 105,414.40 510,854.40 31,928.40
1004(2)a Locksets
AS EVALUATED
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING
50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing AS SUBMITTED 55.82 m 109,023.36 20% 21,804.67 6,541.40 28,346.07 137,369.43 2,460.94
1053(3)a2
on 19 mm bar stiffener AS EVALUATED
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING
AS SUBMITTED 1.00 l.s. 103,115.53 20% 20,623.11 6,186.93 26,810.04 129,925.57 129,925.57
1047(6)-1 Metal Structure Accessories, Fire Escape
AS EVALUATED
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING
AS SUBMITTED 1.00 l.s. 64,212.85 20% 12,842.57 3,852.77 16,695.34 80,908.19 80,908.19
1001(9) Downspout/Storm Drain
AS EVALUATED
AS SUBMITTED 1.00 l.s. 182,941.13 20% 36,588.23 10,976.47 47,564.70 230,505.83 230,505.83
1002(5) Sanitary/Plumbing Fixtures
AS EVALUATED
AS SUBMITTED 1.00 l.s. 39,187.36 20% 7,837.47 2,351.24 10,188.71 49,376.07 49,376.07
SPL-1 Septic Vault "Type E"
AS EVALUATED
AS SUBMITTED 8.00 units 6,544.25 20% 1,308.85 392.66 1,701.51 8,245.76 1,030.72
1001(6)b1 Catch basin
AS EVALUATED
AS SUBMITTED 1.00 lot 405,027.60 20% 81,005.52 24,301.66 105,307.18 510,334.78 510,334.78
Dry Stand Pipe
AS EVALUATED
FORM ABC-2015-02A-00
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 0.71% 156,000.00
Part II Other General Requirements 1.40% 308,835.57
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 1.48% 326,826.85
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 27.32% 6,036,544.79
PART C FINISHING WORKS 57.75% 12,756,850.44
PART D PLUMBING/SANITARY WORKS 8.05% 1,777,293.27
PART E ELECTRICAL WORKS 3.30% 729,308.27
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted 0.71 6.00 mo - - 156,000.00 156,000.00 8% 12,480.00 20,217.60 188,697.60
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 156,000.00 156,000.00 12,480.00 20,217.60 188,697.60
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted 0.02 1.00 ea 3,505.00 699.72 69.97 4,274.69 20% 854.94 615.56 5,745.19
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted 0.64 1.00 lot 137,035.54 5,324.16 - 142,359.70 8% 11,388.78 18,449.82 172,198.30
II.7 Occupational Safety and Health
As Evaluated
As Submitted 0.73 1.00 l.s. - - 162,201.18 162,201.18 8% 12,976.09 21,021.27 196,198.54
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 140,540.54 6,023.88 162,271.15 308,835.57 25,219.81 40,086.65 374,142.03
TOTAL OF PART II
As Evaluated
(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted 0.43 413.71 m3 - 4,246.53 90,965.09 95,211.61 20% 19,042.32 13,710.47 127,964.40
803(1)a Structure Excavation
As Evaluated
As Submitted 0.17 257.76 m3 - 5,377.60 33,150.69 38,528.28 20% 7,705.66 5,548.07 51,782.01
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted 0.53 335.90 m3 67,180.00 7,007.82 43,200.32 117,388.14 20% 23,477.63 16,903.89 157,769.66
804(1)b Embankment from Borrow
As Evaluated
As Submitted 0.34 90.34 m3 54,068.49 15,454.92 6,175.42 75,698.82 20% 15,139.76 10,900.63 101,739.21
804(4) Gravel Fill
As Evaluated
As Submitted 121,248.49 32,086.85 173,491.51 326,826.85 65,365.37 47,063.06 439,255.28
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted 6.78 384.71 m3 1,369,567.60 46,014.21 81,442.07 1,497,023.88 20% 299,404.78 215,571.44 2,012,000.10
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted 15.13 68,853.89 kg 2,745,462.80 404,214.05 192,763.05 3,342,439.90 20% 668,487.98 481,311.35 4,492,239.23
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted 5.42 2,577.60 m2 532,344.32 425,539.54 239,197.16 1,197,081.01 20% 239,416.20 172,379.67 1,608,876.88
903(2) Forms and Falseworks
As Evaluated
As Submitted 4,647,374.71 875,767.80 513,402.28 6,036,544.79 1,207,308.96 869,262.46 8,113,116.21
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted 0.51 300.27 L 99,089.10 12,113.11 1,211.31 112,413.53 20% 22,482.71 16,187.55 151,083.79
1000(1) Soil Poisoning
As Evaluated
As Submitted 99,089.10 12,113.11 1,211.31 112,413.53 22,482.71 16,187.55 151,083.79
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted 0.70 285.37 m2 115,968.66 23,591.33 15,191.46 154,751.45 20% 30,950.29 22,284.21 207,985.95
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted 3.66 961.80 m2 650,301.83 95,638.61 61,585.75 807,526.19 20% 161,505.24 116,283.77 1,085,315.20
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 766,270.49 119,229.94 76,777.21 962,277.64 192,455.53 138,567.98 1,293,301.15
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted 1.44 1.00 l.s 267,447.00 50,729.70 34.99 318,211.69 20% 63,642.34 45,822.48 427,676.51
1010(4) Wooden Doors
As Evaluated
As Submitted 0.51 70.87 m2 62,046.69 45,915.89 4,591.59 112,554.16 20% 22,510.83 16,207.80 151,272.79
1009(1)a Jalousie Window
As Evaluated
As Submitted 2.36 146.88 m2 285,314.40 142,742.88 94,038.29 522,095.57 20% 104,419.11 75,181.76 701,696.44
1005(1) Steel Casement Window
As Evaluated
As Submitted 18.78 65.28 m 2
3,353,737.09 479,616.08 315,968.65 4,149,321.81 20% 829,864.36 597,502.34 5,576,688.51
1005(5) Window Grilles
As Evaluated
As Submitted 4.93 43.00 set 1,089,620.00 - - 1,089,620.00 20% 217,924.00 156,905.28 1,464,449.28
1004(2)a Locksets
As Evaluated
As Submitted 0.05 172.00 pc 11,180.00 - - 11,180.00 20% 2,236.00 1,609.92 15,025.92
1004(2)g Hinges
As Evaluated
As Submitted 0.21 1.00 l.s. 37,200.00 7,477.92 747.79 45,425.71 20% 9,085.14 6,541.30 61,052.15
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 5,106,545.17 726,482.46 415,381.30 6,248,408.94 1,249,681.78 899,770.88 8,397,861.60
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted 1.42 1,161.01 m2 257,163.72 50,879.56 5,087.96 313,131.23 20% 62,626.25 45,090.90 420,848.38
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted 2.98 4,355.83 m2 417,070.72 219,546.06 21,954.61 658,571.39 20% 131,714.28 94,834.28 885,119.95
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted 0.14 66.00 m 24,365.88 2,298.55 3,443.99 30,108.42 20% 6,021.68 4,335.61 40,465.71
1053(2)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
As Submitted 1.27 144.00 m 268,720.62 5,015.02 7,514.16 281,249.81 20% 56,249.96 40,499.97 377,999.74
1053(2)a2 50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar stiffener
As Evaluated
As Submitted 2.19 661.00 m2 357,410.63 115,842.51 11,584.25 484,837.39 20% 96,967.48 69,816.58 651,621.45
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted 0.70 841.24 m2 119,245.77 32,959.66 3,295.97 155,501.40 20% 31,100.28 22,392.20 208,993.88
1038(1) Reflective Insulation
As Evaluated
As Submitted 0.73 115.51 m2 108,867.55 48,098.73 4,809.87 161,776.15 20% 32,355.23 23,295.77 217,427.15
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted 0.32 50.68 m2 53,538.04 14,772.83 1,477.28 69,788.15 20% 13,957.63 10,049.49 93,795.27
1018(2) Unglazed Tiles
As Evaluated
As Submitted 1,606,382.93 489,412.92 59,168.09 2,154,963.94 430,992.79 310,314.80 2,896,271.53
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted 5.41 4,943.76 m2 599,346.86 542,377.56 54,237.76 1,195,962.17 20% 239,192.43 172,218.55 1,607,373.15
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted 0.23 247.39 m2 17,754.56 30,156.71 3,015.67 50,926.94 20% 10,185.39 7,333.48 68,445.81
1032(1)b Wood Painting
As Evaluated
As Submitted 0.14 125.09 m2 15,342.61 14,409.74 1,440.97 31,193.33 20% 6,238.67 4,491.84 41,923.84
1032(1)c Metal Painting
As Evaluated
As Submitted 632,444.03 586,944.01 58,694.40 1,278,082.44 255,616.49 184,043.87 1,717,742.80
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted 2.24 841.24 m2 397,280.03 88,273.52 8,827.35 494,380.91 20% 98,876.18 71,190.85 664,447.94
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted 0.06 64.20 m 12,292.82 1,123.05 112.31 13,528.18 20% 2,705.64 1,948.06 18,181.88
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted 0.02 26.21 m 5,018.01 458.44 45.84 5,522.29 20% 1,104.46 795.21 7,421.96
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
As Submitted 0.19 128.40 m 39,146.59 1,903.48 190.35 41,240.42 20% 8,248.08 5,938.62 55,427.12
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 2.73 7,703.59 kg 463,688.71 37,874.83 102,466.17 604,029.70 20% 120,805.94 86,980.28 811,815.92
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted 3.34 10,028.53 kg 611,263.97 39,816.98 86,250.01 737,330.97 20% 147,466.19 106,175.66 990,972.82
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted 0.11 128.40 m 21,166.74 2,354.36 235.44 23,756.53 20% 4,751.31 3,420.94 31,928.78
1003(5)a1 Fascia Board
As Evaluated
As Submitted 0.09 277.47 kg 15,604.45 3,735.14 373.51 19,713.10 20% 3,942.62 2,838.69 26,494.41
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted 0.07 293.65 kg 11,408.30 3,952.92 395.29 15,756.51 20% 3,151.30 2,268.94 21,176.75
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted 0.16 628.56 kg 25,152.14 8,461.25 846.13 34,459.52 20% 6,891.90 4,962.17 46,313.59
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted 0.05 52.00 pc 9,620.00 1,364.45 1.36 10,985.82 20% 2,197.16 1,581.96 14,764.94
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted 1,611,641.78 189,318.41 199,743.76 2,000,703.95 400,140.78 288,101.38 2,688,946.11
Sub-Total C.6
As Evaluated
As Submitted 9,822,373.51 2,123,500.86 810,976.07 12,756,850.44 2,551,370.08 1,836,986.46 17,145,206.98
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted 0.23 1.00 l.s. 42,834.20 8,060.08 806.01 51,700.29 20% 10,340.06 7,444.84 69,485.19
1001(8) Sewer Line Works
As Evaluated
As Submitted 0.20 1.00 l.s. 37,309.81 5,609.38 560.94 43,480.13 20% 8,696.03 6,261.14 58,437.30
1002(6) Cold Water Line Works
As Evaluated
As Submitted 1.05 1.00 l.s. 195,447.14 33,936.84 3,393.68 232,777.66 20% 46,555.53 33,519.98 312,853.17
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted 1.65 1.00 l.s. 333,664.59 28,819.72 2,881.97 365,366.28 20% 73,073.26 52,612.74 491,052.28
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted 0.46 1.00 l.s. 84,694.50 15,980.84 1,598.08 102,273.42 20% 20,454.68 14,727.37 137,455.47
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted 0.15 30.00 units 18,768.24 5,247.90 9,148.41 33,164.55 20% 6,632.91 4,775.70 44,573.16
1001(6)b1 Catch basin
As Evaluated
As Submitted 4.29 1.00 lot 875,153.75 66,706.54 6,670.65 948,530.94 20% 189,706.19 136,588.46 1,274,825.59
SPL-2 Fire Protection System
As Evaluated
As Submitted 1,587,872.23 164,361.30 25,059.75 1,777,293.27 355,458.66 255,930.23 2,388,682.16
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted 0.55 1.00 l.s. 106,537.14 13,085.91 1,308.59 120,931.64 20% 24,186.33 17,414.16 162,532.13
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted 0.95 1.00 l.s. 192,446.10 15,262.08 1,526.21 209,234.39 20% 41,846.88 30,129.75 281,211.02
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted 1.16 1.00 l.s. 251,941.00 3,267.60 326.76 255,535.36 20% 51,107.07 36,797.09 343,439.52
1102(21) Panel Board
As Evaluated
As Submitted 0.58 1.00 l.s. 120,058.00 7,842.24 784.22 128,684.46 20% 25,736.89 18,530.56 172,951.91
1003(1) Lighting Fixtures
As Evaluated
As Submitted 0.07 1.00 l.s. 11,568.00 3,049.47 304.95 14,922.42 20% 2,984.48 2,148.83 20,055.73
1208(1) Fire Alarm System
As Evaluated
As Submitted 682,550.24 42,507.30 4,250.73 729,308.270 145,861.650 105,020.390 980,190.310
TOTAL OF PART E
As Evaluated
As Submitted 16,861,419.18 3,238,224.11 1,527,180.34 21,626,823.620 4,325,364.720 3,114,262.600 29,066,450.940
TOTAL OF PART III
As Evaluated
As Submitted 17,001,959.72 3,244,247.99 1,845,451.49 22,091,659.190 4,363,064.530 3,174,566.850 29,629,290.570
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 0.79% 151,666.67
Part II Other General Requirements 1.43% 275,454.79
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 1.47% 283,708.00
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 27.18% 5,248,765.45
PART C FINISHING WORKS 56.88% 10,984,919.46
PART D PLUMBING/SANITARY WORKS 8.75% 1,689,839.15
PART E ELECTRICAL WORKS 3.51% 678,607.54
`
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted 0.79 5.83 mo - - 151,666.67 151,666.67 8% 12,133.33 19,656.00 183,456.00
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 151,666.67 151,666.67 12,133.33 19,656.00 183,456.00
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted 0.02 1.00 ea 3,505.00 699.72 69.97 4,274.69 20% 854.94 615.56 5,745.19
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted 0.67 1.00 L.S. 124,212.14 5,324.16 - 129,536.30 8% 10,362.90 16,787.90 156,687.10
II.7 Occupational Safety and Health
As Evaluated
As Submitted 0.73 1.00 l.s. - - 141,643.80 141,643.80 8% 11,331.50 18,357.04 171,332.34
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 127,717.14 6,023.88 141,713.77 275,454.79 22,549.34 35,760.50 333,764.63
TOTAL OF PART II
As Evaluated
(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted 0.44 365.45 m3 - 3,751.16 80,353.85 84,105.01 20% 16,821.00 12,111.12 113,037.13
803(1)a Structure Excavation
As Evaluated
804(1)a As Submitted 0.17 223.43 m3 - 4,661.38 28,735.48 33,396.86 20% 6,679.37 4,809.15 44,885.38
Embankment from Structure Excavation
As Evaluated
As Submitted 0.52 288.09 m3 57,618.00 6,010.37 37,051.45 100,679.81 20% 20,135.96 14,497.89 135,313.66
804(1)b Embankment from Borrow
As Evaluated
As Submitted 0.34 78.20 m3 46,802.70 13,378.07 5,345.56 65,526.32 20% 13,105.26 9,435.79 88,067.37
804(4) Gravel Fill
As Evaluated
As Submitted 104,420.70 27,800.97 151,486.34 283,708.00 56,741.59 40,853.95 381,303.54
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted 6.76 335.41 m3 1,194,059.60 40,117.56 71,005.40 1,305,182.56 20% 261,036.51 187,946.29 1,754,165.36
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted 15.07 59,947.73 kg 2,390,340.80 351,929.50 167,829.40 2,910,099.70 20% 582,019.94 419,054.36 3,911,174.00
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted 5.35 2,225.34 m2 459,592.04 367,383.62 206,507.53 1,033,483.19 20% 206,696.64 148,821.58 1,389,001.41
903(2) Forms and Falseworks
As Evaluated
As Submitted 4,043,992.44 759,430.68 445,342.33 5,248,765.45 1,049,753.09 755,822.23 7,054,340.77
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted 0.50 259.98 L 85,793.40 10,487.79 1,048.78 97,329.96 20% 19,465.99 14,015.51 130,811.46
1000(1) Soil Poisoning
As Evaluated
As Submitted 85,793.40 10,487.79 1,048.78 97,329.96 19,465.99 14,015.51 130,811.46
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted 0.75 267.94 m2 108,885.46 22,150.41 14,263.58 145,299.45 20% 29,059.89 20,923.12 195,282.46
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted 3.65 838.99 m2 567,266.31 83,426.74 53,722.01 704,415.05 20% 140,883.01 101,435.77 946,733.83
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted 676,151.77 105,577.15 67,985.59 849,714.50 169,942.90 122,358.89 1,142,016.29
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted 1.47 1.00 l.s. 233,127.00 45,481.80 4,548.18 283,156.98 20% 56,631.40 40,774.61 380,562.99
1010(4) Wooden Doors
As Evaluated
As Submitted 0.49 59.98 m2 52,512.49 38,860.38 3,886.04 95,258.90 20% 19,051.78 13,717.28 128,027.96
1009(1)a Jalousie Window
As Evaluated
As Submitted 2.25 122.40 m 2
237,762.00 118,952.40 78,365.24 435,079.64 20% 87,015.93 62,651.47 584,747.04
1005(1) Steel Casement Window
As Evaluated
As Submitted 17.90 54.40 m2 2,794,780.91 399,680.06 263,307.21 3,457,768.18 20% 691,553.64 497,918.62 4,647,240.44
1005(5) Window Grills
As Evaluated
As Submitted 5.12 39.00 set 988,260.00 - - 988,260.00 20% 197,652.00 142,309.44 1,328,221.44
1004(2)a Locksets
As Evaluated
As Submitted 0.05 156.00 pc 10,140.00 - - 10,140.00 20% 2,028.00 1,460.16 13,628.16
1004(2)g Hinges
As Evaluated
As Submitted 0.20 1.00 l.s. 31,000.00 6,231.60 623.16 37,854.76 20% 7,570.95 5,451.09 50,876.80
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 4,347,582.40 609,206.24 350,729.82 5,307,518.46 1,061,503.70 764,282.67 7,133,304.83
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted 1.40 1,000.20 m2 221,544.30 43,832.29 4,383.23 269,759.82 20% 53,951.96 38,845.41 362,557.19
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted 2.99 3,825.21 m2 366,263.86 192,801.32 19,280.13 578,345.31 20% 115,669.06 83,281.72 777,296.09
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted 0.16 66.00 m 24,365.88 2,298.55 3,443.99 30,108.42 20% 6,021.68 4,335.61 40,465.71
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar As Submitted 1.29 127.60 m 238,116.33 4,443.87 6,658.38 249,218.58 20% 49,843.72 35,887.48 334,949.78
1053(3)a2
stiffener As Evaluated
As Submitted 2.15 565.91 m2 305,994.33 99,177.66 9,917.77 415,089.76 20% 83,017.95 59,772.93 557,880.64
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted 0.69 723.31 m2 102,529.19 28,339.18 2,833.92 133,702.29 20% 26,740.46 19,253.13 179,695.88
1038(1) Reflective Insulation
As Evaluated
As Submitted 0.84 115.51 m 2
108,867.55 48,098.73 4,809.87 161,776.15 20% 32,355.23 23,295.77 217,427.15
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted 0.36 50.68 m2 53,538.04 14,772.83 1,477.28 69,788.15 20% 13,957.63 10,049.49 93,795.27
1018(2) Unglazed Tiles
As Evaluated
As Submitted 1,421,219.47 433,764.44 52,804.58 1,907,788.48 381,557.69 274,721.54 2,564,067.71
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted 5.43 4,336.71 m2 525,752.36 475,778.39 47,577.84 1,049,108.59 20% 209,821.72 151,071.64 1,410,001.95
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted 0.23 218.61 m2 15,689.09 26,648.44 2,664.84 45,002.38 20% 9,000.48 6,480.34 60,483.20
1032(1)b Wood Painting
As Evaluated
As Submitted 0.15 112.50 m2 13,798.42 12,959.44 1,295.94 28,053.80 20% 5,610.76 4,039.75 37,704.31
1032(1)c Metal Painting
As Evaluated
As Submitted 555,239.87 515,386.27 51,538.63 1,122,164.77 224,432.96 161,591.73 1,508,189.46
Sub-Total C.5
As Evaluated
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
C.6 Roof Framing and Roofing Works
As Submitted 2.20 723.31 m2 341,586.57 75,898.73 7,589.87 425,075.17 20% 85,015.03 61,210.82 571,301.02
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted 0.06 55.20 m 10,569.53 965.61 96.56 11,631.71 20% 2,326.34 1,674.97 15,633.02
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted 0.03 26.21 m 5,018.01 458.44 45.84 5,522.29 20% 1,104.46 795.21 7,421.96
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
As Submitted 0.18 110.40 m 33,658.75 1,636.63 163.66 35,459.05 20% 7,091.81 5,106.10 47,656.96
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted 2.61 6,440.06 kg 387,635.26 31,662.66 85,659.84 504,957.76 20% 100,991.55 72,713.92 678,663.23
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted 3.24 8,515.07 kg 519,014.80 33,807.98 73,233.56 626,056.34 20% 125,211.27 90,152.11 841,419.72
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted 0.11 110.40 m 18,199.44 2,024.31 202.43 20,426.18 20% 4,085.24 2,941.37 27,452.79
1003(11) Fascia Board
As Evaluated
As Submitted 0.10 277.47 kg 15,604.45 3,735.14 373.51 19,713.10 20% 3,942.62 2,838.69 26,494.41
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted 0.07 248.16 kg 9,641.02 3,340.56 334.06 13,315.64 20% 2,663.13 1,917.45 17,896.22
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted 0.15 528.07 kg 21,130.99 7,108.53 710.85 28,950.36 20% 5,790.07 4,168.85 38,909.28
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted 0.05 44.00 pc 8,140.00 1,154.54 1.15 9,295.69 20% 1,859.14 1,338.58 12,493.41
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted 1,370,198.82 161,793.13 168,411.34 1,700,403.29 340,080.66 244,858.07 2,285,342.02
Sub-Total C.6
As Evaluated
As Submitted 8,456,185.73 1,836,215.00 692,518.74 10,984,919.46 2,196,983.90 1,581,828.41 14,763,731.77
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted 0.25 1.00 l.s. 40,569.75 7,624.40 762.44 48,956.59 20% 9,791.32 7,049.75 65,797.66
1001(8) Sewer Line Works
As Evaluated
As Submitted 0.21 1.00 l.s. 34,962.33 5,173.70 517.37 40,653.40 20% 8,130.68 5,854.09 54,638.17
1002(6) Cold Water Line Works
As Evaluated
As Submitted 1.08 1.00 l.s. 175,017.11 30,435.42 3,043.54 208,496.07 20% 41,699.21 30,023.43 280,218.71
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted 1.88 1.00 l.s. 332,488.59 28,688.52 2,868.85 364,045.96 20% 72,809.19 52,422.62 489,277.77
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted 0.45 1.00 l.s. 71,983.91 13,736.34 1,373.63 87,093.88 20% 17,418.78 12,541.52 117,054.18
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted 0.11 26.00 units 16,265.81 4,548.18 454.82 21,268.81 20% 4,253.76 3,062.71 28,585.28
1001(6)b1 Catch basin
As Evaluated
As Submitted 4.76 1.00 lot 848,514.95 64,372.26 6,437.23 919,324.44 20% 183,864.89 132,382.72 1,235,572.05
SPL-2 Fire Protection System
As Evaluated
As Submitted 1,519,802.45 154,578.82 15,457.88 1,689,839.15 337,967.83 243,336.84 2,271,143.82
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted 0.55 1.00 l.s. 93,357.14 10,844.76 1,084.48 105,286.38 20% 21,057.28 15,161.24 141,504.90
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted 1.03 1.00 l.s. 185,259.10 13,042.74 1,304.27 199,606.12 20% 39,921.22 28,743.28 268,270.62
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted 1.29 1.00 l.s. 244,155.30 5,228.16 522.82 249,906.28 20% 49,981.26 35,986.50 335,874.04
1102(21) Panel Board
As Evaluated
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 0.56 1.00 l.s. 101,458.00 6,753.04 675.30 108,886.34 20% 21,777.27 15,679.63 146,343.24
1003(1) Lighting Fixtures
As Evaluated
As Submitted 0.08 1.00 l.s. 11,568.00 3,049.47 304.95 14,922.42 20% 2,984.48 2,148.83 20,055.73
1208(1) Fire Alarm System
As Evaluated
As Submitted 635,797.54 38,918.17 3,891.82 678,607.540 135,721.510 97,719.480 912,048.530
TOTAL OF PART E
As Evaluated
As Submitted 14,760,198.86 2,816,943.64 1,308,697.10 18,885,839.600 3,777,167.920 2,719,560.910 25,382,568.430
TOTAL OF PART III
As Evaluated
As Submitted 14,887,916.00 2,822,967.52 1,602,077.54 19,312,961.060 3,811,850.590 2,774,977.410 25,899,789.060
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 0.79% 130,000.00
Part II Other General Requirements 1.47% 241,562.03
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 1.46% 239,317.45
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 27.13% 4,460,986.10
PART C FINISHING WORKS 56.01% 9,207,970.82
PART D PLUMBING/SANITARY WORKS 9.58% 1,574,675.92
PART E ELECTRICAL WORKS 3.57% 586,526.49
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted 0.79 5.00 mo - - 130,000.00 130,000.00 8% 10,400.00 16,848.00 157,248.00
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 130,000.00 130,000.00 10,400.00 16,848.00 157,248.00
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted 0.03 1.00 ea 3,505.00 699.72 69.97 4,274.69 20% 854.94 615.56 5,745.19
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted 0.71 1.00 l.s. 112,329.46 4,436.80 - 116,766.26 8% 9,341.30 15,132.91 141,240.47
II.7 Occupational Safety and Health
As Evaluated
As Submitted 0.73 1.00 l.s. - - 120,521.08 120,521.08 8% 9,641.69 15,619.53 145,782.30
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 115,834.46 5,136.52 120,591.05 241,562.03 19,837.93 31,368.00 292,767.96
TOTAL OF PART II
As Evaluated
(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted 0.44 313.84 m3 - 3,221.41 69,006.03 72,227.44 20% 14,445.49 10,400.75 97,073.68
803(1)a Structure Excavation
As Evaluated
As Submitted 0.17 185.75 m3 - 3,875.27 23,889.43 27,764.70 20% 5,552.94 3,998.12 37,315.76
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted 0.51 240.28 m3 48,056.00 5,012.91 30,902.57 83,971.49 20% 16,794.30 12,091.89 112,857.68
804(1)b Embankment from Borrow
As Evaluated
As Submitted 0.34 66.06 m3 39,536.91 11,301.21 4,515.70 55,353.82 20% 11,070.76 7,970.95 74,395.53
804(4) Gravel Fill
As Evaluated
As Submitted 87,592.91 23,410.81 128,313.73 239,317.45 47,863.49 34,461.71 321,642.65
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted 6.77 286.11 m3 1,018,551.60 34,220.91 60,568.72 1,113,341.23 20% 222,668.25 160,321.14 1,496,330.62
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted 15.07 51,041.57 kg 2,035,218.80 299,644.94 142,895.76 2,477,759.50 20% 495,551.90 356,797.37 3,330,108.77
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted 5.29 1,873.07 m2 386,839.76 309,227.71 173,817.90 869,885.37 20% 173,977.07 125,263.49 1,169,125.93
903(2) Forms and Falseworks
As Evaluated
As Submitted 3,440,610.16 643,093.56 377,282.37 4,460,986.10 892,197.22 642,382.00 5,995,565.32
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted 0.50 219.68 L 72,494.40 8,862.05 886.21 82,242.66 20% 16,448.53 11,842.94 110,534.13
1000(1) Soil Poisoning
As Evaluated
As Submitted 72,494.40 8,862.05 886.21 82,242.66 16,448.53 11,842.94 110,534.13
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted 0.83 250.52 m2 101,806.32 20,710.31 13,336.24 135,852.87 20% 27,170.57 19,562.81 182,586.25
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 3.66 716.18 m2 484,230.78 71,214.87 45,858.27 601,303.92 20% 120,260.78 86,587.76 808,152.46
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 586,037.10 91,925.18 59,194.51 737,156.79 147,431.35 106,150.57 990,738.71
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted 1.48 1.00 l.s. 198,807.00 40,233.90 4,023.39 243,064.29 20% 48,612.86 35,001.26 326,678.41
1010(4) Wooden Doors
As Evaluated
As Submitted 0.47 49.10 m 2
42,987.05 31,811.34 3,181.13 77,979.53 20% 15,595.91 11,229.05 104,804.49
1009(1)a Jalousie Window
As Evaluated
As Submitted 2.12 97.92 m2 190,209.60 95,161.92 62,692.19 348,063.71 20% 69,612.74 50,121.17 467,797.62
1005 (1) Steel Casement Window
As Evaluated
As Submitted 16.83 43.52 m2 2,235,824.72 319,744.05 210,645.77 2,766,214.54 20% 553,242.91 398,334.89 3,717,792.34
1005 (5) Window Grills
As Evaluated
As Submitted 5.39 35.00 set 886,900.00 - - 886,900.00 20% 177,380.00 127,713.60 1,191,993.60
1004(2)a Locksets
As Evaluated
As Submitted 0.06 140.00 pc 9,100.00 - - 9,100.00 20% 1,820.00 1,310.40 12,230.40
1004(2)g Hinges
As Evaluated
As Submitted 0.18 1.00 l.s. 24,800.00 4,985.28 498.53 30,283.81 20% 6,056.76 4,360.87 40,701.44
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 3,588,628.37 491,936.50 281,041.01 4,361,605.88 872,321.18 628,071.24 5,861,998.30
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted 1.38 839.37 m2 185,920.46 36,784.16 3,678.42 226,383.03 20% 45,276.61 32,599.16 304,258.80
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted 3.03 3,294.60 m 2
315,457.95 166,057.09 16,605.71 498,120.75 20% 99,624.15 71,729.39 669,474.29
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted 0.18 66.00 m 24,365.88 2,298.55 3,443.99 30,108.42 20% 6,021.68 4,335.61 40,465.71
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar As Submitted 1.32 111.20 m 207,512.03 3,872.71 5,802.60 217,187.35 20% 43,437.47 31,274.98 291,899.80
1053(3)a2
stiffener As Evaluated
As Submitted 2.10 470.83 m2 254,583.43 82,514.57 8,251.46 345,349.46 20% 69,069.89 49,730.32 464,149.67
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted 0.68 605.38 m2 85,812.62 23,718.70 2,371.87 111,903.19 20% 22,380.64 16,114.06 150,397.89
1038(1) Reflective Insulation
As Evaluated
As Submitted 0.98 115.51 m2 108,867.55 48,098.73 4,809.87 161,776.15 20% 32,355.23 23,295.77 217,427.15
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted 0.42 50.68 m2 53,538.04 14,772.83 1,477.28 69,788.15 20% 13,957.63 10,049.49 93,795.27
1018(2) Unglazed Tiles
As Evaluated
As Submitted 1,236,057.95 378,117.33 46,441.20 1,660,616.50 332,123.30 239,128.78 2,231,868.58
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted 5.49 3,729.66 m2 452,157.87 409,179.22 40,917.92 902,255.02 20% 180,451.00 129,924.72 1,212,630.74
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted 0.24 189.83 m2 13,623.62 23,140.18 2,314.02 39,077.82 20% 7,815.56 5,627.21 52,520.59
1032(1)b Wood Painting
As Evaluated
As Submitted 0.15 99.91 m2 12,254.22 11,509.13 1,150.91 24,914.27 20% 4,982.85 3,587.65 33,484.77
1032(1)c Metal Painting
As Evaluated
As Submitted 478,035.72 443,828.53 44,382.85 966,247.11 193,249.41 139,139.58 1,298,636.10
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted 2.16 605.38 m2 285,893.11 63,523.94 6,352.39 355,769.44 20% 71,153.89 51,230.80 478,154.13
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted 0.06 46.20 m 8,846.24 808.18 80.82 9,735.23 20% 1,947.05 1,401.87 13,084.15
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 0.03 26.21 m 5,018.01 458.44 45.84 5,522.29 20% 1,104.46 795.21 7,421.96
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 0.18 92.40 m 28,170.91 1,369.79 136.98 29,677.68 20% 5,935.54 4,273.59 39,886.81
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted 2.47 5,176.53 kg 311,581.81 25,450.50 68,853.51 405,885.81 20% 81,177.16 58,447.56 545,510.53
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted 3.13 7,001.60 kg 426,765.02 27,798.95 60,217.01 514,780.98 20% 102,956.20 74,128.46 691,865.64
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted 0.10 92.40 m 15,232.14 1,694.26 169.43 17,095.82 20% 3,419.16 2,461.80 22,976.78
1003(11) Fascia Board
As Evaluated
As Submitted 0.12 277.47 kg 15,604.45 3,735.14 373.51 19,713.10 20% 3,942.62 2,838.69 26,494.41
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted 0.07 202.67 kg 7,873.73 2,728.21 272.82 10,874.76 20% 2,174.95 1,565.97 14,615.68
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted 0.14 427.58 kg 17,109.83 5,755.80 575.58 23,441.20 20% 4,688.24 3,375.53 31,504.97
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted 0.05 36.00 pc 6,660.00 944.62 0.94 7,605.57 20% 1,521.11 1,095.20 10,221.88
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted 1,128,755.25 134,267.80 137,078.84 1,400,101.88 280,020.38 201,614.68 1,881,736.94
Sub-Total C.6
As Evaluated
As Submitted 7,090,008.80 1,548,937.39 569,024.62 9,207,970.82 1,841,594.15 1,325,947.79 12,375,512.76
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted 0.27 1.00 l.s. 37,479.15 6,970.88 697.09 45,147.12 20% 9,029.42 6,501.18 60,677.72
1001(8) Sewer Line Works
As Evaluated
As Submitted 0.22 1.00 l.s. 31,441.10 4,574.64 457.46 36,473.20 20% 7,294.64 5,252.14 49,019.98
1002(6) Cold Water Line Works
As Evaluated
As Submitted 1.08 1.00 l.s. 149,178.38 25,946.42 2,594.64 177,719.45 20% 35,543.89 25,591.60 238,854.94
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted 2.20 1.00 l.s. 330,724.59 28,557.32 2,855.73 362,137.64 20% 72,427.53 52,147.82 486,712.99
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted 0.49 1.00 l.s. 66,075.81 12,479.42 1,247.94 79,803.17 20% 15,960.63 11,491.66 107,255.46
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted 0.10 20.00 units 12,512.16 3,498.60 349.86 16,360.62 20% 3,272.12 2,355.93 21,988.67
1001(6)b1 Catch basin
As Evaluated
As Submitted 5.21 1.00 lot 792,545.75 58,626.34 5,862.63 857,034.72 20% 171,406.94 123,413.00 1,151,854.66
SPL-2 Fire Protection System
As Evaluated
As Submitted 1,419,956.94 140,653.62 14,065.36 1,574,675.92 314,935.17 226,753.33 2,116,364.42
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted 0.58 1.00 l.s. 84,199.64 9,751.56 975.16 94,926.36 20% 18,985.27 13,669.40 127,581.03
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted 0.85 1.00 l.s. 129,016.65 9,839.25 983.93 139,839.83 20% 27,967.97 20,136.94 187,944.74
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted 1.51 1.00 l.s. 244,155.30 3,267.60 326.76 247,749.66 20% 49,549.93 35,675.95 332,975.54
1102(21) Panel Board
As Evaluated
As Submitted 0.54 1.00 l.s. 82,858.00 5,663.84 566.38 89,088.22 20% 17,817.64 12,828.70 119,734.56
1003(1) Lighting Fixtures
As Evaluated
As Submitted 0.09 1.00 l.s. 11,568.00 3,049.47 304.95 14,922.42 20% 2,984.48 2,148.83 20,055.73
1208(1) Fire Alarm System
As Evaluated
As Submitted 551,797.59 31,571.72 3,157.17 586,526.490 117,305.290 84,459.820 788,291.600
TOTAL OF PART E
As Evaluated
As Submitted 12,589,966.40 2,387,667.10 1,091,843.25 16,069,476.780 3,213,895.320 2,314,004.650 21,597,376.750
TOTAL OF PART III
As Evaluated
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 12,705,800.86 2,392,803.62 1,342,434.30 16,441,038.810 3,244,133.250 2,362,220.650 22,047,392.710
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 1.06% 121,333.33
Part II Other General Requirements 1.59% 182,158.82
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 1.50% 171,470.97
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 27.48% 3,147,815.32
PART C FINISHING WORKS 58.54% 6,705,462.58
PART D PLUMBING/SANITARY WORKS 7.91% 905,548.48
PART E ELECTRICAL WORKS 1.93% 221,298.13
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted 1.06 4.67 mo - - 121,333.33 121,333.33 8% 9,706.67 15,724.80 146,764.80
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 121,333.33 121,333.33 9,706.67 15,724.80 146,764.80
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted 0.04 1.00 ea 3,505.00 699.72 69.97 4,274.69 20% 854.94 615.56 5,745.19
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted 0.82 1.00 l.s. 89,810.36 4,436.80 - 94,247.16 8% 7,539.77 12,214.43 114,001.36
II.7 Occupational Safety and Health
As Evaluated
As Submitted 0.73 1.00 l.s. - - 83,636.97 83,636.97 8% 6,690.96 10,839.35 101,167.28
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 93,315.36 5,136.52 83,706.94 182,158.82 15,085.67 23,669.34 220,913.83
TOTAL OF PART II
As Evaluated
(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted 0.49 244.62 m3 - 2,510.90 53,786.18 56,297.08 20% 11,259.42 8,106.78 75,663.28
803(1)a Structure Excavation
As Evaluated
As Submitted 0.18 139.08 m3 - 2,901.60 17,887.17 20,788.77 20% 4,157.75 2,993.58 27,940.10
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted 0.49 159.64 m3 31,928.00 3,330.54 20,531.41 55,789.95 20% 11,157.99 8,033.75 74,981.69
804(1)b Embankment from Borrow
As Evaluated
As Submitted 0.34 46.06 m3 27,566.91 7,879.71 3,148.55 38,595.17 20% 7,719.03 5,557.70 51,871.90
804(4) Gravel Fill
As Evaluated
As Submitted 59,494.91 16,622.75 95,353.30 171,470.97 34,294.19 24,691.81 230,456.97
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted 6.84 201.23 m3 716,378.80 24,068.62 42,599.85 783,047.27 20% 156,609.45 112,758.81 1,052,415.53
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted 15.32 36,154.58 kg 1,441,618.68 212,249.29 101,218.20 1,755,086.18 20% 351,017.24 252,732.41 2,358,835.83
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted 5.32 1,312.79 m2 271,126.74 216,730.31 121,824.81 609,681.87 20% 121,936.37 87,794.19 819,412.43
903(2) Forms and Falseworks
As Evaluated
As Submitted 2,429,124.23 453,048.22 265,642.87 3,147,815.32 629,563.06 453,285.41 4,230,663.79
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted 0.52 159.89 L 52,763.70 6,450.08 645.01 59,858.79 20% 11,971.76 8,619.67 80,450.22
1000(1) Soil Poisoning
As Evaluated
As Submitted 52,763.70 6,450.08 645.01 59,858.79 11,971.76 8,619.67 80,450.22
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted 0.70 147.30 m2 59,859.77 12,177.19 7,841.40 79,878.36 20% 15,975.67 11,502.48 107,356.51
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted 3.83 522.79 m2 353,474.00 51,984.73 33,475.16 438,933.89 20% 87,786.78 63,206.48 589,927.15
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 413,333.78 64,161.91 41,316.57 518,812.25 103,762.45 74,708.96 697,283.66
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted 1.49 1.00 l.s. 141,984.00 26,239.50 2,623.95 170,847.45 20% 34,169.49 24,602.03 229,618.97
1010(4) Wooden Dooor
As Evaluated
As Submitted 0.48 34.93 m2 30,581.22 22,630.76 2,263.08 55,475.05 20% 11,095.01 7,988.41 74,558.47
1009(1)a Jalousie Window
As Evaluated
As Submitted 2.28 73.44 m2 142,657.20 71,371.44 47,019.14 261,047.78 20% 52,209.56 37,590.88 350,848.22
1005 (1) Steel Casement Window
As Evaluated
As Submitted 18.11 32.64 m2 1,676,868.54 239,808.04 157,984.32 2,074,660.91 20% 414,932.18 298,751.17 2,788,344.26
1005(5) Window Grill
As Evaluated
As Submitted 5.31 24.00 set 608,160.00 - - 608,160.00 20% 121,632.00 87,575.04 817,367.04
1004(2)a Locksets
As Evaluated
As Submitted 0.05 96.00 pc 6,240.00 - - 6,240.00 20% 1,248.00 898.56 8,386.56
1004(2)g Hinges
As Evaluated
As Submitted 0.20 1.00 l.s. 18,600.00 3,738.96 373.90 22,712.86 20% 4,542.57 3,270.65 30,526.08
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 2,625,090.96 363,788.70 210,264.39 3,199,144.05 639,828.81 460,676.74 4,299,649.60
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted 1.38 584.99 m2 129,575.29 25,636.33 2,563.63 157,775.24 20% 31,555.05 22,719.63 212,049.92
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted 3.05 2,313.83 m2 221,549.22 116,623.53 11,662.35 349,835.10 20% 69,967.02 50,376.25 470,178.37
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted 0.13 33.00 m 12,182.94 1,149.28 1,722.00 15,054.21 20% 3,010.84 2,167.81 20,232.86
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
As Submitted 1.57 92.12 m 171,906.55 3,208.22 4,806.98 179,921.75 20% 35,984.35 25,908.73 241,814.83
1053(3)a2 50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar stiffener
As Evaluated
As Submitted 2.13 332.94 m 2
180,024.65 58,348.87 5,834.89 244,208.41 20% 48,841.68 35,166.01 328,216.10
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted 0.70 434.28 m 2
61,559.19 17,015.03 1,701.50 80,275.72 20% 16,055.14 11,559.70 107,890.56
1038(1) Reflective Insulation
As Evaluated
As Submitted 0.87 71.55 m2 67,437.82 29,794.68 2,979.47 100,211.97 20% 20,042.39 14,430.52 134,684.88
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted 0.24 20.05 m2 21,180.69 5,844.42 584.44 27,609.56 20% 5,521.91 3,975.78 37,107.25
1018(2) Unglazed Tiles
As Evaluated
As Submitted 865,416.36 257,620.35 31,855.26 1,154,891.96 230,978.38 166,304.43 1,552,174.77
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted 5.39 2,553.91 m2 309,618.17 280,188.25 28,018.82 617,825.25 20% 123,565.05 88,966.84 830,357.14
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted 0.24 133.27 m 2
9,564.45 16,245.54 1,624.55 27,434.55 20% 5,486.91 3,950.58 36,872.04
1032(1)b Wood Painting
As Evaluated
As Submitted 0.14 62.73 m 2
7,694.00 7,226.18 722.62 15,642.80 20% 3,128.56 2,252.56 21,023.92
1032(1)c Metal Painting
As Evaluated
As Submitted 326,876.62 303,659.97 30,366.00 660,902.60 132,180.52 95,169.98 888,253.10
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted 2.23 434.28 m2 205,090.90 45,570.11 4,557.01 255,218.03 20% 51,043.61 36,751.40 343,013.04
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted 0.06 32.90 m 6,299.59 575.52 57.55 6,932.66 20% 1,386.53 998.30 9,317.49
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted 0.05 26.21 m 5,018.61 458.49 45.85 5,522.95 20% 1,104.59 795.30 7,422.84
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 0.18 65.80 m 20,061.10 975.46 97.55 21,134.11 20% 4,226.82 3,043.31 28,404.24
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted 2.42 3,535.91 kg 212,830.84 17,384.36 47,031.47 277,246.67 20% 55,449.33 39,923.52 372,619.52
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted 3.32 5,170.61 kg 315,161.61 20,529.24 44,469.65 380,160.49 20% 76,032.10 54,743.11 510,935.70
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted 0.11 65.80 m 10,847.13 1,206.52 120.65 12,174.30 20% 2,434.86 1,753.10 16,362.26
1003(11) Fascia Board
As Evaluated
As Submitted 0.17 277.47 kg 15,604.36 3,735.12 373.51 19,712.99 20% 3,942.60 2,838.67 26,494.26
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted 0.07 146.82 kg 5,703.96 1,976.39 197.64 7,877.99 20% 1,575.60 1,134.43 10,588.02
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted 0.15 314.91 kg 12,601.28 4,239.11 423.91 17,264.30 20% 3,452.86 2,486.06 23,203.22
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted 0.05 26.00 pc 4,810.00 682.23 0.68 5,492.91 20% 1,098.58 790.98 7,382.47
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted 0.90 1.00 l.s. 62,940.83 12,868.88 27,305.82 103,115.53 20% 20,623.11 14,848.64 138,587.28
1047(6)-1 Metal Structure Accessories, Fire Escape
As Evaluated
As Submitted 876,970.21 110,201.42 124,681.29 1,111,852.93 222,370.59 160,106.82 1,494,330.34
Sub-Total C.6
As Evaluated
As Submitted 5,160,451.63 1,105,882.44 439,128.51 6,705,462.58 1,341,092.51 965,586.60 9,012,141.69
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted 0.19 1.00 l.s. 18,330.45 3,267.60 326.76 21,924.81 20% 4,384.96 3,157.17 29,466.94
1001(8) Sewer Line Works
As Evaluated
As Submitted 0.10 1.00 l.s. 9,856.75 1,034.74 103.47 10,994.96 20% 2,198.99 1,583.27 14,777.22
1002(6) Cold Water Line Works
As Evaluated
As Submitted 0.74 1.00 l.s. 71,668.92 12,389.64 1,238.96 85,297.52 20% 17,059.50 12,282.84 114,639.86
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted 1.62 1.00 l.s. 169,754.97 14,344.26 1,434.43 185,533.66 20% 37,106.73 26,716.85 249,357.24
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted 0.59 1.00 l.s. 56,252.00 10,773.60 1,077.36 68,102.96 20% 13,620.59 9,806.83 91,530.38
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted 0.11 16.00 units 10,009.73 2,798.88 279.89 13,088.50 20% 2,617.70 1,884.74 17,590.94
1001(6)b1 Catch basin
As Evaluated
As Submitted 4.54 1.00 lot 479,028.95 37,797.38 3,779.74 520,606.07 20% 104,121.21 74,967.27 699,694.55
SPL-2 Fire Protection System
As Evaluated
As Submitted 814,901.76 82,406.10 8,240.61 905,548.48 181,109.68 130,398.97 1,217,057.13
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted 0.40 1.00 l.s. 37,515.20 7,356.84 735.68 45,607.72 20% 9,121.54 6,567.51 61,296.77
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted 0.55 1.00 l.s. 56,162.82 5,925.36 592.54 62,680.72 20% 12,536.14 9,026.02 84,242.88
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted 0.34 1.00 l.s. 36,455.00 2,396.24 239.62 39,090.86 20% 7,818.17 5,629.08 52,538.11
1102(21) Panel Board
As Evaluated
As Submitted 0.57 1.00 l.s. 60,585.00 4,138.96 413.90 65,137.86 20% 13,027.57 9,379.85 87,545.28
1003(1) Lighting Fixtures
As Evaluated
As Submitted 0.08 1.00 l.s. 6,184.00 2,360.88 236.09 8,780.97 20% 1,756.19 1,264.46 11,801.62
1208(1) Fire Alarm System
As Evaluated
As Submitted 196,902.02 22,178.28 2,217.83 221,298.130 44,259.610 31,866.920 297,424.660
TOTAL OF PART E
As Evaluated
As Submitted 8,660,874.55 1,680,137.79 810,583.12 11,151,595.480 2,230,319.050 1,605,829.710 14,987,744.240
TOTAL OF PART III
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
TOTAL OF PART III
As Evaluated
As Submitted 8,754,189.91 1,685,274.31 1,015,623.39 11,455,087.630 2,255,111.390 1,645,223.850 15,355,422.870
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 1.21% 104,000.00
Part II Other General Requirements 1.61% 138,699.58
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 1.49% 128,587.47
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 27.44% 2,360,033.64
PART C FINISHING WORKS 57.23% 4,923,041.82
PART D PLUMBING/SANITARY WORKS 9.05% 778,326.81
PART E ELECTRICAL WORKS 1.97% 169,464.38
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted - 4.00 mo - - 104,000.00 104,000.00 8% 8,320.00 13,478.40 125,798.40
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 104,000.00 104,000.00 8,320.00 13,478.40 125,798.40
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted 0.06 1.00 ea 3,505.00 699.72 69.97 4,274.69 20% 854.94 615.56 5,745.19
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted 1.09 1.00 l.s. 76,734.52 3,549.44 - 80,283.96 8% 6,422.72 10,404.80 97,111.48
II.7 Occupational Safety and Health
As Evaluated
As Submitted 0.74 1.00 l.s. - - 54,140.93 54,140.93 8% 4,331.27 7,016.66 65,488.86
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 80,239.52 4,249.16 54,210.90 138,699.58 11,608.93 18,037.02 168,345.53
TOTAL OF PART II
As Evaluated
(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted 0.39 196.98 m3 - 2,021.90 43,311.26 45,333.16 20% 9,066.63 6,527.97 60,927.76
803(1)a Structure Excavation
As Evaluated
As Submitted 0.18 105.37 m3 - 2,198.31 13,551.71 15,750.02 20% 3,150.00 2,268.00 21,168.02
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted 1.17 111.83 m3 22,366.00 2,333.09 14,382.53 39,081.62 20% 7,816.32 5,627.75 52,525.69
804(1)b Embankment from Borrow
As Evaluated
As Submitted 0.38 33.92 m3 20,301.12 5,802.86 2,318.69 28,422.67 20% 5,684.53 4,092.86 38,200.06
804(4) Gravel Fill
As Evaluated
As Submitted 42,667.12 12,356.17 73,564.19 128,587.47 25,717.48 18,516.58 172,821.53
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted 12.74 151.93 m3 540,870.80 18,171.97 32,163.17 591,205.94 20% 118,241.19 85,133.66 794,580.79
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted 16.83 27,248.42 kg 1,086,496.69 159,964.74 76,284.56 1,322,745.98 20% 264,549.20 190,475.42 1,777,770.60
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted 4.10 960.52 m2 198,373.43 158,573.57 89,134.72 446,081.72 20% 89,216.34 64,235.77 599,533.83
903(2) Forms and Falseworks
As Evaluated
As Submitted 1,825,740.92 336,710.28 197,582.45 2,360,033.64 472,006.73 339,844.85 3,171,885.22
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted 0.17 115.60 L 38,148.00 4,663.39 466.34 43,277.73 20% 8,655.55 6,231.99 58,165.27
1000(1) Soil Poisoning
As Evaluated
As Submitted 38,148.00 4,663.39 466.34 43,277.73 8,655.55 6,231.99 58,165.27
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted 0.40 129.91 m2 52,792.83 10,739.57 6,915.66 70,448.05 20% 14,089.61 10,144.52 94,682.18
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted 6.46 399.98 m2 270,438.48 39,772.85 25,611.42 335,822.76 20% 67,164.55 48,358.48 451,345.79
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 323,231.30 50,512.42 32,527.08 406,270.81 81,254.16 58,503.00 546,027.97
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted 1.76 1.00 l.s. 107,664.00 20,116.95 2,011.70 129,792.65 20% 25,958.53 18,690.14 174,441.32
1010(4) Wooden Doors
As Evaluated
As Submitted 0.52 24.05 m2 21,055.78 15,581.73 1,558.17 38,195.68 20% 7,639.14 5,500.18 51,335.00
1009(1)a Jalousie Window
As Evaluated
As Submitted 2.37 48.96 m2 95,104.80 47,580.96 31,346.10 174,031.86 20% 34,806.37 25,060.59 233,898.82
1005 (1) Steel Casement Window
As Evaluated
As Submitted 0.86 21.76 m2 1,117,912.36 159,872.03 105,322.88 1,383,107.27 20% 276,621.45 199,167.45 1,858,896.17
1005(5) Window Grill
As Evaluated
As Submitted 0.34 20.00 set 506,800.00 - - 506,800.00 20% 101,360.00 72,979.20 681,139.20
1004(2)a Locksets
As Evaluated
As Submitted - 80.00 pc 5,200.00 - - 5,200.00 20% 1,040.00 748.80 6,988.80
1004(2)g Hinges
As Evaluated
As Submitted 0.21 1.00 l.s. 12,400.00 2,492.64 249.26 15,141.90 20% 3,028.38 2,180.43 20,350.71
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 1,866,136.94 245,644.30 140,488.11 2,252,269.36 450,453.87 324,326.79 3,027,050.02
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted 0.82 424.17 m2 93,953.66 18,588.63 1,858.86 114,401.14 20% 22,880.23 16,473.76 153,755.13
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted 1.87 1,783.22 m2 170,743.32 89,879.29 8,987.93 269,610.54 20% 53,922.11 38,823.92 362,356.57
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted 0.22 33.00 m 12,182.94 1,149.28 1,722.00 15,054.21 20% 3,010.84 2,167.81 20,232.86
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar As Submitted 2.55 73.42 m 137,010.19 2,556.96 3,831.18 143,398.34 20% 28,679.67 20,649.36 192,727.37
1053(3)a2
stiffener As Evaluated
As Submitted 2.81 237.86 m 2
128,613.76 41,685.78 4,168.58 174,468.11 20% 34,893.62 25,123.41 234,485.14
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted 0.71 315.48 m 2
44,719.29 12,360.46 1,236.05 58,315.80 20% 11,663.16 8,397.48 78,376.44
1038(1) Reflective Insulation
As Evaluated
As Submitted 0.70 71.55 m2 67,437.82 29,794.68 2,979.47 100,211.97 20% 20,042.39 14,430.52 134,684.88
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted 3.93 20.05 m2 21,180.69 5,844.42 584.44 27,609.56 20% 5,521.91 3,975.78 37,107.25
1018(2) Unglazed Tiles
As Evaluated
As Submitted 675,841.67 201,859.50 25,368.50 903,069.67 180,613.93 130,042.04 1,213,725.64
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted 3.71 1,946.86 m2 236,023.68 213,589.08 21,358.91 470,971.67 20% 94,194.33 67,819.92 632,985.92
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted 0.93 104.49 m 2
7,498.99 12,737.28 1,273.73 21,509.99 20% 4,302.00 3,097.44 28,909.43
1032(1)b Wood Painting
As Evaluated
As Submitted 2.53 50.14 m 2
6,149.80 5,775.88 577.59 12,503.27 20% 2,500.65 1,800.47 16,804.39
1032(1)c Metal Painting
As Evaluated
As Submitted 249,672.47 232,102.24 23,210.22 504,984.93 100,996.98 72,717.83 678,699.74
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted 2.26 315.48 m2 148,987.01 33,104.12 3,310.41 185,401.54 20% 37,080.31 26,697.82 249,179.67
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted 0.08 23.90 m 4,576.30 418.08 41.81 5,036.19 20% 1,007.24 725.21 6,768.64
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted 0.08 26.21 m 5,018.61 458.49 45.85 5,522.95 20% 1,104.59 795.30 7,422.84
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
As Submitted 0.21 47.80 m 14,573.26 708.61 70.86 15,352.74 20% 3,070.55 2,210.79 20,634.08
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted 6.49 2,271.38 kg 136,717.20 11,167.28 30,211.84 178,096.31 20% 35,619.26 25,645.87 239,361.44
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted 3.37 3,687.15 kg 224,741.01 14,639.35 31,711.20 271,091.56 20% 54,218.31 39,037.18 364,347.05
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted 0.18 47.80 m 7,879.83 876.47 87.65 8,843.94 20% 1,768.79 1,273.53 11,886.26
1003(11) Fascia Board
As Evaluated
As Submitted 0.89 277.47 kg 15,604.36 3,735.12 373.51 19,712.99 20% 3,942.60 2,838.67 26,494.26
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted 0.14 101.34 kg 3,937.06 1,364.17 136.42 5,437.65 20% 1,087.53 783.02 7,308.20
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted 0.06 214.42 kg 8,580.12 2,886.38 288.64 11,755.14 20% 2,351.03 1,692.74 15,798.91
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted 0.08 18.00 pc 3,330.00 472.31 0.47 3,802.78 20% 760.56 547.60 5,110.94
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted 1.40 1.00 l.s. 62,940.83 12,868.88 27,305.82 103,115.53 20% 20,623.11 14,848.64 138,587.28
1047(6)-1 Metal Structure Accessories, Fire Escape
As Evaluated
As Submitted 636,885.59 82,699.27 93,584.48 813,169.32 162,633.88 117,096.37 1,092,899.57
Sub-Total C.6
As Evaluated s
As Submitted 3,789,915.97 817,481.12 315,644.74 4,923,041.82 984,608.37 708,918.02 6,616,568.21
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted 0.29 1.00 l.s. 17,902.45 3,213.14 321.31 21,436.90 20% 4,287.38 3,086.91 28,811.19
1001(8) Sewer Line Works
As Evaluated
As Submitted 0.15 1.00 l.s. 9,856.75 1,034.74 103.47 10,994.96 20% 2,198.99 1,583.27 14,777.22
1002(6) Cold Water Line Works
As Evaluated
As Submitted 1.02 1.00 l.s. 63,215.62 10,953.16 1,095.32 75,264.09 20% 15,052.82 10,838.03 101,154.94
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted 2.50 1.00 l.s. 168,578.97 14,256.80 1,425.68 184,261.44 20% 36,852.29 26,533.65 247,647.38
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted 0.77 1.00 l.s. 46,913.31 9,157.56 915.76 56,986.63 20% 11,397.33 8,206.08 76,590.04
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted 0.13 12.00 units 7,507.30 2,099.16 209.92 9,816.37 20% 1,963.27 1,413.56 13,193.20
1001(6)b1 Catch basin
As Evaluated
As Submitted 5.70 1.00 lot 385,396.15 31,063.88 3,106.39 419,566.42 20% 83,913.28 60,417.56 563,897.26
SPL-2 Fire Protection System
As Evaluated
As Submitted 699,370.54 71,778.44 7,177.84 778,326.81 155,665.36 112,079.06 1,046,071.23
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted 0.51 1.00 l.s. 30,337.80 6,438.57 643.86 37,420.23 20% 7,484.05 5,388.51 50,292.79
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted 0.70 1.00 l.s. 46,384.17 4,657.23 465.72 51,507.12 20% 10,301.42 7,417.02 69,225.56
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted 0.36 1.00 l.s. 24,259.70 1,960.56 196.06 26,416.32 20% 5,283.26 3,803.95 35,503.53
1102(21) Panel Board
As Evaluated
As Submitted 0.62 1.00 l.s. 41,985.00 3,049.76 304.98 45,339.74 20% 9,067.95 6,528.92 60,936.61
1003(1) Lighting Fixtures
As Evaluated
As Submitted 0.12 1.00 l.s. 6,184.00 2,360.88 236.09 8,780.97 20% 1,756.19 1,264.46 11,801.62
1208(1) Fire Alarm System
As Evaluated
As Submitted 149,150.67 18,467.00 1,846.70 169,464.380 33,892.870 24,402.860 227,760.110
TOTAL OF PART E
As Evaluated
STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 6,506,845.22 1,256,793.00 595,815.92 8,359,454.120 1,671,890.810 1,203,761.370 11,235,106.300
TOTAL OF PART III
As Evaluated
As Submitted 6,587,084.74 1,261,042.16 754,026.82 8,602,153.700 1,691,819.740 1,235,276.790 11,529,250.230
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 1.71% 99,666.67
Part II Other General Requirements 1.95% 113,214.26
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 1.44% 83,682.13
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 27.04% 1,572,255.66
PART C FINISHING WORKS 53.32% 3,099,822.64
PART D PLUMBING/SANITARY WORKS 12.55% 729,557.62
PART E ELECTRICAL WORKS 1.98% 115,373.83
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted 1.71 3.83 mo - - 99,666.67 99,666.67 8% 7,973.33 12,916.80 120,556.80
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 99,666.67 99,666.67 7,973.33 12,916.80 120,556.80
TOTAL OF PART I
As Evalauted
PART II OTHER GENERAL REQUIREMENTS
As Submitted 0.07 1.00 ea 3,505.00 699.72 69.97 4,274.69 20% 854.94 615.56 5,745.19
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted 1.15 1.00 l.s. 63,384.94 3,549.44 - 66,934.38 8% 5,354.75 8,674.70 80,963.83
II.7 Occupational Safety and Health
As Evaluated
As Submitted 0.72 1.00 l.s. - - 42,005.19 42,005.19 8% 3,360.42 5,443.87 50,809.48
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 66,889.94 4,249.16 42,075.16 113,214.26 9,570.11 14,734.13 137,518.50
TOTAL OF PART II
As Evaluated
(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted 0.57 144.01 m3 - 1,478.19 31,664.41 33,142.60 20% 6,628.52 4,772.53 44,543.65
803(1)a Structure Excavation
As Evaluated
As Submitted 0.17 66.34 m3 - 1,384.04 8,532.03 9,916.07 20% 1,983.21 1,427.91 13,327.19
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted 0.38 64.02 m3 12,804.00 1,335.64 8,233.66 22,373.29 20% 4,474.66 3,221.75 30,069.70
804(1)b Embankment from Borrow
As Evaluated
As Submitted 0.31 21.78 m3 13,035.33 3,726.01 1,488.83 18,250.17 20% 3,650.03 2,628.02 24,528.22
804(4) Gravel Fill
As Evaluated
As Submitted 25,839.33 7,923.88 49,918.92 83,682.13 16,736.42 12,050.21 112,468.76
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted 6.87 102.63 m3 365,362.80 12,275.32 21,726.50 399,364.62 20% 79,872.92 57,508.50 536,746.04
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted 15.32 18,342.24 kg 731,373.89 107,680.06 51,350.86 890,404.81 20% 178,080.96 128,218.29 1,196,704.06
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted 4.86 608.26 m2 125,622.19 100,418.48 56,445.55 282,486.23 20% 56,497.25 40,678.02 379,661.50
903(2) Forms and Falseworks
As Evaluated
As Submitted 1,222,358.88 220,373.86 129,522.91 1,572,255.66 314,451.13 226,404.81 2,113,111.60
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted 0.48 75.31 L 24,852.30 3,038.06 303.81 28,194.17 20% 5,638.83 4,059.96 37,892.96
1000(1) Soil Poisoning
As Evaluated
As Submitted 24,852.30 3,038.06 303.81 28,194.17 5,638.83 4,059.96 37,892.96
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted 1.05 112.48 m2 45,709.62 9,298.64 5,987.79 60,996.05 20% 12,199.21 8,783.43 81,978.69
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted 3.28 227.17 m2 153,596.45 22,589.13 14,546.10 190,731.67 20% 38,146.33 27,465.36 256,343.36
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 199,306.07 31,887.77 20,533.88 251,727.72 50,345.54 36,248.79 338,322.05
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted 1.54 1.00 l.s. 73,344.00 14,869.05 1,486.91 89,699.96 20% 17,939.99 12,916.79 120,556.74
1010(4) Wooden Doors
As Evaluated
As Submitted 0.37 13.71 m2 12,003.11 8,882.56 888.26 21,773.92 20% 4,354.78 3,135.44 29,264.14
1009(1)a Jalousie Window
As Evaluated
As Submitted 1.50 24.48 m2 47,552.40 23,790.48 15,673.05 87,015.93 20% 17,403.19 12,530.29 116,949.41
1005 (1) Steel Casement Window
As Evaluated
As Submitted 11.90 10.88 m 2
558,956.18 79,936.01 52,661.44 691,553.64 20% 138,310.73 99,583.72 929,448.09
1005 (5) Window Grill
As Evaluated
As Submitted 6.97 16.00 set 405,440.00 - - 405,440.00 20% 81,088.00 58,383.36 544,911.36
1004(2)a Locksets
As Evaluated
As Submitted 0.07 64.00 pc 4,160.00 - - 4,160.00 20% 832.00 599.04 5,591.04
1004(2)g Hinges
As Evaluated
As Submitted 0.13 1.00 l.s. 6,200.00 1,246.32 124.63 7,570.95 20% 1,514.19 1,090.22 10,175.36
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 1,107,655.69 128,724.42 70,834.28 1,307,214.40 261,442.88 188,238.86 1,756,896.14
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted 1.22 263.35 m2 58,332.03 11,540.93 1,154.09 71,027.04 20% 14,205.41 10,227.89 95,460.34
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted 3.26 1,252.61 m2 119,937.41 63,135.06 6,313.51 189,385.97 20% 37,877.19 27,271.58 254,534.74
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted 0.26 33.00 m 12,182.94 1,149.28 1,722.00 15,054.21 20% 3,010.84 2,167.81 20,232.86
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
As Submitted 1.88 55.82 m 104,166.56 1,944.02 2,912.78 109,023.36 20% 21,804.67 15,699.36 146,527.39
1053(3)a2 50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar stiffener
As Evaluated
As Submitted 1.80 142.77 m2 77,197.45 25,020.93 2,502.09 104,720.48 20% 20,944.10 15,079.75 140,744.33
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted 0.63 196.68 m2 27,879.39 7,705.89 770.59 36,355.87 20% 7,271.17 5,235.24 48,862.28
1038(1) Reflective Insulation
As Evaluated
As Submitted 1.72 71.55 m2 67,437.82 29,794.68 2,979.47 100,211.97 20% 20,042.39 14,430.52 134,684.88
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted 0.47 20.05 m2 21,180.69 5,844.42 584.44 27,609.56 20% 5,521.91 3,975.78 37,107.25
1018(2) Unglazed Tiles
As Evaluated
As Submitted 488,314.30 146,135.20 18,938.97 653,388.46 130,677.68 94,087.93 878,154.07
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted 5.58 1,339.81 m2 162,429.19 146,989.92 14,698.99 324,118.09 20% 64,823.62 46,673.01 435,614.72
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted 0.27 75.71 m2 5,433.52 9,229.01 922.90 15,585.43 20% 3,117.09 2,244.30 20,946.82
1032(1)b Wood Painting
As Evaluated
As Submitted 0.16 37.55 m2 4,605.61 4,325.57 432.56 9,363.73 20% 1,872.75 1,348.38 12,584.86
1032(1)c Metal Painting
As Evaluated
As Submitted 172,468.31 160,544.50 16,054.45 349,067.25 69,813.46 50,265.69 469,146.40
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted 1.99 196.68 m2 92,883.11 20,638.14 2,063.81 115,585.06 20% 23,117.01 16,644.25 155,346.32
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted 0.05 14.90 m 2,853.01 260.65 26.06 3,139.72 20% 627.94 452.12 4,219.78
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted 0.10 26.21 m 5,018.61 458.49 45.85 5,522.95 20% 1,104.59 795.30 7,422.84
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 0.16 29.80 m 9,085.42 441.77 44.18 9,571.37 20% 1,914.27 1,378.28 12,863.92
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted 1.36 1,008.85 kg 60,723.94 4,960.03 13,418.81 79,102.78 20% 15,820.56 11,390.80 106,314.14
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted 2.71 2,143.69 kg 130,663.26 8,511.24 18,436.73 157,611.24 20% 31,522.25 22,696.02 211,829.51
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted 0.09 29.80 m 4,912.53 546.42 54.64 5,513.59 20% 1,102.72 793.96 7,410.27
1003(11) Fascia Board
As Evaluated
As Submitted 0.34 277.47 kg 15,604.36 3,735.12 373.51 19,712.99 20% 3,942.60 2,838.67 26,494.26
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted 0.05 55.85 kg 2,169.77 751.82 75.18 2,996.77 20% 599.35 431.53 4,027.65
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted 0.11 113.93 kg 4,558.97 1,533.65 153.36 6,245.98 20% 1,249.20 899.42 8,394.60
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted 0.04 10.00 pc 1,850.00 262.40 0.26 2,112.66 20% 422.53 304.22 2,839.41
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted 1.77 1.00 l.s. 62,940.83 12,868.88 27,305.82 103,115.53 20% 20,623.11 14,848.64 138,587.28
1047(6)-1 Metal Structure Accessories, Fire Escape
As Evaluated
As Submitted 393,263.82 54,968.59 61,998.23 510,230.64 102,046.13 73,473.21 685,749.98
Sub-Total C.6
As Evaluated
As Submitted 2,385,860.48 525,298.54 188,663.62 3,099,822.64 619,964.52 446,374.44 4,166,161.60
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted 0.36 1.00 l.s. 17,474.45 2,886.38 288.64 20,649.47 20% 4,129.89 2,973.52 27,752.88
1001(8) Sewer Line Works
As Evaluated
As Submitted 0.19 1.00 l.s. 9,856.75 1,034.74 103.47 10,994.96 20% 2,198.99 1,583.27 14,777.22
1002(6) Cold Water Line Works
As Evaluated
As Submitted 1.10 1.00 l.s. 53,942.02 9,337.12 933.71 64,212.85 20% 12,842.57 9,246.65 86,302.07
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted 3.15 1.00 l.s. 167,402.97 14,125.60 1,412.56 182,941.13 20% 36,588.23 26,343.52 245,872.88
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted 0.67 1.00 l.s. 32,175.55 6,374.38 637.44 39,187.36 20% 7,837.47 5,642.98 52,667.81
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted 0.11 8.00 units 5,004.86 1,399.44 139.94 6,544.25 20% 1,308.85 942.37 8,795.47
1001(6)b1 Catch basin
As Evaluated
As Submitted 6.97 1.00 lot 371,746.15 30,255.86 3,025.59 405,027.60 20% 81,005.52 58,323.97 544,357.09
SPL-2 Fire Protection System
As Evaluated
As Submitted 657,602.75 65,413.52 6,541.35 729,557.62 145,911.52 105,056.28 980,525.42
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted 0.42 1.00 l.s. 22,594.20 1,771.11 177.11 24,542.42 20% 4,908.48 3,534.11 32,985.01
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted 0.63 1.00 l.s. 33,302.85 2,853.18 285.32 36,441.35 20% 7,288.27 5,247.55 48,977.17
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted 0.35 1.00 l.s. 18,390.10 1,524.88 152.49 20,067.47 20% 4,013.49 2,889.72 26,970.68
1102(21) Panel Board
As Evaluated
As Submitted 0.44 1.00 l.s. 23,385.00 1,960.56 196.06 25,541.62 20% 5,108.32 3,677.99 34,327.93
1003(1) Lighting Fixtures
As Evaluated
As Submitted 0.15 1.00 l.s. 6,184.00 2,360.88 236.09 8,780.97 20% 1,756.19 1,264.46 11,801.62
1208(1) Fire Alarm System
As Evaluated
As Submitted 103,856.15 10,470.61 1,047.06 115,373.830 23,074.750 16,613.830 155,062.410
TOTAL OF PART E
As Evaluated
As Submitted 4,395,517.59 829,480.42 375,693.85 5,600,691.880 1,120,138.340 806,499.570 7,527,329.790
TOTAL OF PART III
As Evaluated
As Submitted 4,395,517.59 829,480.42 375,693.85 5,600,691.880 1,120,138.340 806,499.570 7,527,329.790
TOTAL OF (Project ID)
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
TOTAL OF (Project ID)
As Evaluated
As Submitted 4,462,407.53 833,729.58 517,435.68 5,813,572.810 1,137,681.780 834,150.500 7,785,405.090
GRAND TOTAL
As Evaluated