Collateral Documents of Escalator

Installation Instruction

Product Type: ESP- W300


Traveling Height: 3000 6000
Step Width: 600 800 1000
Nominal Speed: 0.5

SHENYANG BRILLIANT ELEVATOR CO. LTD.


SHENYANG BRILLIANT ELEVATOR CO. LTD.
Dec. 2011

Content
1. Preface ​2
2. Installing preparation ​2
2.1 How to establish team to install escalator ​2
2.2 How to apply the construction procedure ​3
2.3 Quality inspection and installation change ​3
2.4 Identification methods for escalator ​3
2.5 Tightening torque ​6
3. Safety requirement ​7
3.1. Safety rules for operation ​7
3.2. Requirements on fire proofing ​8
3.3 Other instruction ​8
4. Installation tools ​9
5. Installing procedure ​11
5.1 Installing flow chart ​11
5.2 Preparation ​12
5.3 Civil work measurement and structure confirmation ​13
5.4 Transport ​16
5.5 Setting centerline of placement ​27
5.6 Guide rail joint at partition place ​28
5.7 Middle step chain joint ​31
5.8 Electric installation ​31
5.9. Step installation ​34
5.10 Handrail system installation ​37
5.11 Outer cover plate installation ​52
5.12 Installation of skirt plate dismantled from sectional escalator ​54
5.13 Safety device check ​57
5.14 Run escalator and check it repeatly ​59
5.15 Inner cover plate installation ​63
5.16 Stick safety signs for running ​67
5.17Running of escalator ​67
1. Preface

a. Please read the instruction in detail before getting the escalator installed and
adjusted to ensure installing work to be well-finished and installing quality. Save this

instruction for future reference.


b. The installing instruction is only suited for installation and adjustment of
commercial escalators with ESP series
c. The installing instruction shows the installing process and method of each part, and
safety requirements for installation.

2. Installing preparation

2.1 How to establish team to install escalator

In general, the team is made up of 4-5 people to install an escalator. The persons
concerned in the team shall be experienced mechanics and electricians familiar with
escalator products (at least one mechanic and one electrical per escalator). The team
leader is in charge of managing installing personnel on site, of installing quality,
construction safety and the close coordination among on-site construction unit,
customer and supervisor parties, of writing down the record and relative documents
as required, and of supervising and inspecting the personnel who shall operate and
construct in accordance with the relative norm.

2.2 How to apply the construction procedure


According to national and local codes and regulations regarding the installation of the
escalator, after preparing relative data and information, you are kindly requested to
apply the construction procedure to local authority by which installation qualification
can be issued. The installation cannot be started until it is approved to do so. The user
concerned shall be contacted in advance to work out the best route and time to get the
installation started.

2.3 Quality inspection and installation change


a. Each installing procedure should be done through self inspection, mutual
inspection and quality control system confirmed by group leader and project manager.
The group leader is responsible for filling in quality record sheet of each procedure
timely. Submit it to quality management department for confirmation after the
working procedure is qualified. The customer representative/supervising engineer
must be invited to confirm and sign at relative quality record sheet before starting
building projects.
b. If there is technical change during installing, it should be done after getting
signature of company and customer for confirmation. If the change project involves
economic issues, go through the change procedure after the change project is finished.

2.4 Identification methods for escalator

2.4.1 Principle of identification


2.4.1.1 One-one correspondence: Every component has its exclusive position to be
installed in and subsequently get each of them fixed tightly.
2.4.1.2 The surface of the component and the packaging material for each component
shall be explicitly labeled respectively as exclusive identification which means two
labels on both internal and external surfaces shall be consistent with one another.
2.4.1.3 Differentiation of left from right structural components: standing at the
downside of the escalator and then look upwards, it shall be differentiated by the
center line of escalator.
2.4.2 Method of identification
2.4.2.1 The whole escalator
N = (1, 2, 3….) Getting each of them numbered by Contract Numbers
1#, 2#, 3#….. The whole escalator
2.4.2.2 The split escalator can be classified from upside to downside: N# (Upside),
N# (Middle) (the middle section is unavailable for the whole escalator which is split
into two sections.), N# (Downside). “Upside”, “Middle”, “Downside” separately
stand for the position of each of the split sections of the whole escalator; the non-split
escalator can not be classified like that.
NB the middle section in the escalator split into 3 sections is not only labeled with
N# (middle), but also the other two sections are labeled with N#(upside) N#
(downside) respectively, which indicates these two labeled sections shall be
connected with the middle section, to protect the middle section of the whole
escalator from reverse connection to the upside and downside sections of the whole.
The installation of the whole escalator shall be started only when the label on upside
and downside sections are carefully checked.
2.4.2.3 Junction plate at the split section shall also be labeled according to the rules of
2.4.2.3 Junction plate at the split section shall also be labeled according to the rules of
N# n. In addition, the same label shall be applied to the split truss which is
connected with the junction plate. Only after these labels on the junction plate have
been the same as the one on the truss can the installation be carried out.
2.4.2.4 There is no need to figure out which side is left, right, upside or downside for
the components concerned and instead of getting them identified straightforward with
the whole escalator label, e.g. (1#) GPPS0040D001 stands for pulley group of 1#
whole elevator which can not be classified into left and right or upside and downside.
2.4.2.5 The components required to be differentiated from one another with left and
right or upside and downside, shall be labeled with the escalator number plus left and
right (or upside and downside), e.g. ‘(1# left) DRPS0039D001 upper R handrail
bracket’ which indicates that this component is for upper left of 1# whole escalator,
and so on. The details of these components and parts can be seen in the packing list
provided.
2.4.2.6 Standard components and small parts for single unit shall be placed into self-
sealed plastic bag for the purpose of installing an escalator later on; after that, getting
the bag labeled with the code name of the components and parts, along with the
details of which components or parts shall be employed for which parts of the
escalator on site, and the components shall be put at the place of standard parts of the
whole escalator. e.g. the self-sealed plastic bag is labeled with (1#) EWPS0009D001
standard components (inner cover plate for standard section), as well as, GB/T819.1-
2000 bolt M4×8 stainless steel , which indicates the standard components in the
bag are employed for (1#) EWPS0009D001 (internal cover plate for standard
section), and so on.
2.4.2.7 Identification for glass interior panelling
The glass balustrade shall be classified into left and right and numbered with
-01 -02 -03…etc. and the form of numbering is as follows:
N# left-n
N# right-n
N stands for the whole escalator number, and n means glass (balustrade) number.
From lower of escalator to its upper, and the number is -01 -02 -03… respectively.
NB: this label is regarded as an additional label which is used for auxiliary purpose of
installing the glass balustrade. The glass itself has a label that has already been serial
numbered previously and pasted up in front of the additional label.

2.5 Tightening torque

According to this instruction, the bolts should be tightened in accordance with


following tightening torque.

Bolt strength
Bolt nominal diameter mm
grade
2 2.5 3 4 5 6810121416182022 24 27 30
Tightening torque N·m

4120
0355488118
167225294441529
0.15~
0.31~
0.54~
1.25~
2.46~
0.15~
0.31~
0.54~
1.25~
2.46~
4.6 ~~~~ ~ ~ ~ ~ ~ ~ ~ ~
0.190.380.601.533.02
512
254469108
147
206284370519666

0.190.390.681.563.08512
254469108
147
206284370539666
5.6 ~ ~ ~ ~ ~ ~~~~ ~ ~ ~ ~ ~ ~ ~ ~
0.230.480.831.913.78715
315488137
186
265343441686833

0.230.470.821.883.70614
294983127
176
245343441637784
6.6 ~ ~ ~ ~ ~ ~~~~ ~ ~ ~ ~ ~ ~ ~ ~
0.280.581.002.294.53818
396498157
216
314431539784980

0.310.631.092.504.93922
4476121
189
260
3695026389331267
8.8 ~ ~ ~ ~ ~ ~~~~ ~ ~ ~ ~ ~ ~ ~ ~
0.370.771.343.066.0412
29
58
102162
252
347
4926698501244
1689

0.430.881.533.526.9313
29
64
108
176
274
372
5297259211372
1566
10.9 ~ ~ ~ ~ ~ ~~~~ ~ ~ ~ ~ ~ ~ ~ ~
0.521.081.884.308.5014
35
76
127
206
323
441
6378621098
1617
1960

0.521.061.844.228.3215
37
74
128
204
319
489
6228471096
1574
2138
12.9 ~ ~ ~ ~ ~ ~~~~ ~ ~ ~ ~ ~ ~ ~ ~
0.631.302.265.1610.20
20
50
88
171
273
425
565
830
11291435
2099
2850

3. Safety requirement

3.1. Safety rules for operation


Follow the safety rules at local site. Familiar with safety signs, for example:

Take care of
Attention High voltage Caution: slippery Put on helmet
machine

3.1.1 The personnel working for the installing team shall be qualified with safety
operation permit approved and issued by relative governmental institution.
3.1.2 If there are scaffolds, safety nets must be set and falling protection devices
(safety belt) should be used.
(safety belt) should be used.
3.1.3 If there is no safety guard, falling protection devices (safety belt) should be used
in order to prevent falling accidents from occurring.
3.1.4 The people concerned working on site shall be strictly required to wear safety
helmet and tool kit; Protective masks and special gloves must be worn when
electro gas welding works are carried out; Safety spectacles and protective gloves
shall be worn precisely when cutting and drilling works are carried out.
3.1.5 Do not use the tools which may be easy to wind or collide with other objects.
The tools should be put in tool kit.
3.1.6 The finger ring, bracelet, necklace, watch and others must not be worn in the
position where the machine rotates.
3.1.7 Operation in hoist way shall not be carried out simultaneously at upper and
lower position. As soon as electrical operation is required, there are at least two
persons working together to be on the safe side.

3.2. Requirements on fire proofing

3.2.1 The equipment concerned shall run in normal condition when portable cutting,
welding or gas cutting devices are employed, in order to prevent from fire risk.
3.2.2 The flammable articles shall be kept in safe place and also equipped with
extinguisher where appropriate.
3.2.3 Devices to put out a fire shall be provided on site where welding and cutting
operations are carried out in hoistway (shaft).
3.2.4 Dangerous gases e.g. oxygen and acetylene shall be managed by exclusive
person, and shall be kept in a ventilated place, and had better be kept apart from high
temperature and direct sunlight.

3.3 Other instruction

2.2.1 Usage of inspection switch box


➢ Usage and notice of inspection switch
➢ Make sure there are no passengers and other unsafe factors
around before using inspection switch
➢ There are sockets of inspection switch box in upper and lower
machine room.
2.2.2 Usage of turning gear, this operation should be done by two persons.
➢ Make sure the escalator can not be started when using turning
gear.
➢ Remove the guard at the axles end of traction machine top
➢ Install the hand wheel on traction machine.
➢ Turn the release rod to hidden line
➢ Turn the wheel at the same time, the escalator will run down as
turning clockwise, the escalator will run up as turning anticlockwise
➢ Loose the release rod after turning, remove turning hand wheel
➢ Reinstall the guard at the axles end
4. Installation tools

Generic tools necessary to install the escalator on site are shown below:
1) Hoisting tools

Steel wire rope above


Chain block Electric block Rolling bar Shackle
Φ16

2) Measuring tools
Calipers Plumb Tape Laser level Feeler gauge Multi meter
3) Assembling and commissioning tools

Wrench Installing tool Screwdriver


Hand drill Hand file Angle grinder
7-30 for handrail (straight, cross)

Pliers for peeling Socket wrench


Snap ring pliers Hand saw Hammer
wire (set)

5. Installing procedure

5.1 Installing flow chart

Civil work
measurement Centerline of
Preparation ―→ ―→ Transport ―→
and structure placement
confirmation

Guide rail joint


Middle step Electric Step
―→ at partition ―→ ―→ ―→
chain joint installation installation
place

Handrail Outer cover


Skirt panel Safety
―→ system ―→ plate ―→ ―→
installation device check
installation installation
Run escalator Inner cover
Run
―→ and check it ―→ plate ―→ Stick signs ―→
escalator
repeatedly installation

5.2 Preparation

5.2.1 Process
Data ―→ Investigation ―→ Check ―→ Determine
preparation at site equipment as transport and
arriving hoisting
program

4.1.2 Data preparation: the installation personnel should be familiar with the
installation technical data and relative documents (such as: scheme
drawing, installation instruction, safety code and so on.) before starting
work.
4.1.3 Investigation at site:
4.1.3.1 Start to work after confirming that shaft guard and warning sign are in
place.
The height of guard is no less than 1.2m, see the following picture
5.2.3.2 There shall be enough lighting at site.
5.2.3.3 The lifting eye should be confirmed with customer, or choose the designated
position in scheme drawing. The position which connects to escalator is the
designated position; otherwise it should be confirmed by designer.
5.2.3.4 The base structure at escalator installation place should pass acceptance and
meet the requirements of scheme drawing.
5.2.3.5 Check the power for construction at site, and make sure supply the power
continuously as working.
5.2.4 The escalator equipment inspection as arriving
※ Inspect and check immediately after open box※
5.2.4.1 After opening the equipment components box, the components should be
classified and put in orderly rows in enclosed storehouse and stuck with nameplate.
5.2.4.2 Check the components carefully and check whether the package of each
component is well and the mark is in accordance with that of whole machine.
5.2.4.3 Check the collateral documents according to packing list: packing list, scheme
drawing, certificate, safety sign and so on.
5.2.4.4 Record the loss parts, damaged parts and unqualified parts and notify the
company to replenish in the process of inspection and construction.
5.2.5 Determine the horizontal transport and hoisting program: choose proper hoisting
program according to specific circumstances at site in order to guarantee the
equipment is in good condition and constructors are safe. Generally, it uses semi-
mechanized horizontal transport and hoisting program. It can also use crane totally, it
is convenient and efficient, but it needs large investment and site
5.3 Civil work measurement and structure confirmation
→ Pit and intermediate → Fill in
support measurement summary
sheet
Determine → Measure → Measure
datum line height support
distance
5.3.1 Process
4.2.2 Determine the elevation line and escalator position line
Generally, there are uprights and walls of building around escalator, and there are
elevation lines and position lines on them 500mm above 0 line is datum elevation.
According to datum elevation line to determine escalator center line, ground line of
each floor, and position line s of machine head and tail. Use clear lines to mark on
the building. If there is no datum elevation line or datum elevation line is not clear,
determine temporary datum elevation line according to the ground line agreed with
customer. (Adopt the principle of connecting vessel)
4.2.3 Height measurement
Measure the distance between ground lines on each floor, and compare them to the
dimension in scheme drawing. Confirm that they are within the allowable range.
Measure each intermediate support height H1……Hn
※ Floor height=H±15 mm
※ Intermediate support height=Hn
±10 mm
4.2.4 Measuresupport distance
Use plumb line to measure the horizontal distance between two support beams.
Measure the horizontal distance between end support and intermediate support.
※ Take the lower support as datum to measure in order to avoid cumulative error. ※
※ Support distance = L Ln mm
4.2.5 Pit and intermediate support measurement [±20 mm ]
The width of support plate is
200mm; thickness is 25mm.
Supply by others, as per scheme
drawing.

4.2.6 Simultaneous installation of more than one escalator


When there are more than one escalator, put the line on the topmost floor to measure
shaft size in order to make center lines of escalators be in the vertical plane, thus the
positions of entry are the same. Mark on the ground, posts and walls until the
installation is finished in order to avoid repeated measuring.
4.2.7 Fill in the summary sheet of civil dimension. Several measurements will
ensure veracity.

Item Building height Support Intermediate support Intermediate support Pit


H distance L1 L2 length×width×depth
L
Required
dimension
Measured
dimension
Item Intermediate Intermediate Support 1 Support 2
support support length×width×thickness length×width×thickness
H1 H2
Required
dimension
Measured
dimension

※ If there are problems, please report to interested parties timely, and deal with according to
civil requirements in order to avoid delaying time limit for a project. Prohibit working with
hidden danger. ※
5.4 Transport

5.4.1 Nitty-gritty of how to be on the safe side


5.4.1.1 The personnel who install the escalator with crane and hoisting device shall be
qualified with safety operation permit issued and approved by relative governmental
authorities, and the operation of hoisting and moving with a crane shall conform to
the relative codes and regulations.
5.4.1.2 If something has come up unexpectedly during hoisting and moving, careful
analysis and appropriate solution to the problem are needed, and subsequently, the
operation can be carried out again.
5.4.1.3 The truss is regarded as main load bearing component of the escalator, and the
position on which the force is exerted while moving horizontally or vertically shall be
strictly defined. It is disallowed to get any force exerted on any positions beyond the
defined position in order to protect the escalator from deformation.
5.4.1.4 The surface shall be flat enough to move the truss horizontally; while hoisting
vertically, the length of the steel ropes at two hoisting positions as shown down below
shall be the same as one another in order to get the escalator hoisted gently and
smoothly.
5.4.1.5 The order of hoisting and transporting need to be paid great attention if
several escalators are installed in the same shaft and the installation shall be started
from the top floor.
5.4.1.6 Before the escalator is moved and hoisted, dismantle all of the components
installed on the truss which are packed and delivered by supplier, so that the
components will not be damaged during movement.
4.3.2 Process
Determine ―→ Determine ―→ Horizontal ―→ Lift truss
transport route lifting eye transport
5.4.3 Determine transport route
5.4.3.1 The escalator equipments are usually put in the simple storehouse at site.
Check whether the passageways are free from obstacles before equipment being
transported to site. Confirm clear height and width of building entrance the
equipments pass. The width should be no less than 2m, height should be no less than
3m.
5.4.3.2 Ensure there are no obstacles on transport route, the load capacity of ground
and temporary bearing plate meets the requirements. Reinforce them if necessary.
5.4.4 Determine the lifting eye: find out a fixed point near the installation position for
fixing hinge hoist. This lifting eye should have enough strength to endure horizontal
tensile forces. If there is no proper position, embed a temporary bracket near the
installation position as lifting eye.
5.4.5 Horizontal transport
Connect the escalator to lifting eye through more than one chain blocks in serial
outdoors.
Put crossties under escalator 100mm×100mm square timber, 4 pieces , put rollers
of diameter 80mm under the crossties. It can also use sets of rolling bars.
The lifting is operated by several persons smoothly.
The method indoors is similar to this, but the lifting eye cab be set in bearing beam..
5.4.5.1 Horizontal transport of the integral type escalator
5.4.5.2 The horizontal transport of upper and lower parts of the split type escalator
While getting the rear half part of the escalator truss moved as required, since the
centre of the gravity has been moved close to the lower end of the truss as shown
below in the picture at left hand side, therefore, according to on-site situation, the
split section can be fixed to the transporting board or put some weight blocks onto the
flat section of rear half part of the truss.

While getting the front half part of the escalator truss (including traction machine
installed inside) moved as required, crosstie shall be carefully put into the bottom of
the split truss exactly as shown below in the picture at right hand side to prevent the
joint pieces from deformation caused by external force.
※Where conditions are ripe, use forklift, crane and other machine tools.※
5.4.6 Truss hoisting
5.4.6.1 Process
Truss assembling ―→ Truss hoisting ―→ In position and
adjustment
4.3.5.2 Truss assembling
1 It can be done on the ground
or in the mid-air, which depends on operating
condition at site. If it does in the mid-air, confirm
whether there is an impact phenomenon after
being hoisted.
2 Clear up joint faces of upper,
middle and lower parts of truss and make sure
there is no uneven phenomenon.
3 The joint of lower truss and
middle truss.
1 Install hoisting bracket (for end of escalator, 4 pieces for each
escalator) and hoisting beam. Steel wire rope penetrating diagram is as
follows:
2 Confirm the signs of interface, and attach the steel wire rope to
the hoisting bracket and hoisting beam of lower truss and suspend it
from the lifting hook of hoisting device.
3 Confirm the signs of interface, and attach the steel wire rope to
the hoisting beams at two ends of middle truss and suspend it from the
lifting hook of hoisting device.
lifting hook of hoisting device.
4 Hoist the lower truss and install zip fastener hinged joint
between lower truss and middle truss, and use this hinged joint to make
joint faces of two trusses draw close slowly until they contact with each
other.

5 Use the hoisting device and zip fastener hinged joint to align
the hole of fastening bolt in truss joint face. Reinstall the joint plates
and high strength connecting bolts (16 joints for each) which have been
dismantled as segmented transporting, and make sure the signs on the
joint plates are the same with that of truss; insert after the alignment of
holes and install the bolts in turn in order to joint the truss, hammer the
head of bolt before lock-in, then tighten it up. It must use the bolts
attached to the equipment at this place, smaller bolts should not be
used.
6 Install the middle connecting plate and inclined bracer, pay
attention to installing position.

(4)Joint for middle truss and upper truss


Confirm the middle truss after connecting with lower truss and the mark of the
joint with upper truss.
Fasten the steel wire rope at the lifting place of middle and upper truss, and hang
to the lifting hook of winding equipment.
3 For the upper lifting of winding equipment, see the following picture. Install the
zipper pin joint on the middle and upper truss, and make the jointing face of the
two trusses close up slowly until they touch by the zipper pin joint
4 Repeat the , of item No.(3)
For the escalator without middle truss, refer to (4).
(5)Connect in the air after lifting
If the lifting condition is not fulfilled on site after finishing assembling completely,
lift the upper, middle and lower truss to the preset position. In that state, connect the
upper, middle and lower truss, and after connection put the truss at the supporting part
of the building.

5.4.6.3.Truss hoisting
1 Precautions
for hoisting
1. Before escalator hoisting, confirm the temporary arrangement space and do the
reinforcing treatment for the vulnerable position.
reinforcing treatment for the vulnerable position.
2. People are strictly prohibited to stand in hoisting work space.
3. Confirm the specification of suspension hook used by hoisting and the position and
weight capacity of spandrel girder. And make sure that the lifting weight of each
suspension centre is more than 5t.
4. Penetrate two pieces of flitch of 100mm×100mm×500mm into the lifting cable
sleeve on the floor plate to avoid the wearing of lifting rope during the hoisting.
2 The following two pictures is
the universal installation method under the
circumstance of floor cover plate and fixed
suspension point. It is permitted to hoist the
escalator by other methods such as self-made
gallows frame, tower crane and auto crane etc.
1 Top-down hoisting

2 Down-top hoisting

4.3.5.4 Putting
in position and adjustment
1 Align the upper and lower heads of truss to the above-
mentioned central line of escalator position, and ensure that the deviation
is within 1mm. When there are several units of escalator on upper and
lower parts, the central line should be adjusted to a vertical plane, the
deviation <5mm.
deviation <5mm.
2 The maximum distance between nosing used for placing
equipment and elevation of truss supporting angle steel is 50mm the
total gap between the upper and lower parts <100mm.
3 Put the upper and lower heads of truss on the embedded
supporting steel plate of spandrel girder.

4 Adjust the upper surface position of truss supporting angle


steel by the supporting bolt of each end, and make sure that subsequent
entrance floor levels horizon line
5 Lay the level instrument on the truss supporting angle steel
and step, adjust it by supporting bolt and make sure that the horizontal
degree of step width direction is 1/1000.
6 There are two or several units of elevator in parallel, the front
section of entrance floor supporting angle steel is required to be on the
same straight line(measure by rectangle ruler), and the unevenness degree
should be less than 2mm the gap of width direction should be even and
the width evenness of several gaps should also be considered.
7 The position of lengthwise shall be kept consistent one
another while 2 or more escalators are required to be installed on site, the
top escalators should be regarded as a reference, after the plummet has
been drawn out from the center point of supporting angle steel (see the
following picture), getting the rest of the escalators measured in order to
get the entrance-exit position be consistent with one escalator to another.
8 In the case of several escalators are installed on the same
floor, and the surface of front edge pedals shall be kept in the same plane.
The surface of the front edge pedals installed at different escalators shall
be measured correctly by taking the ground elevation as the uniform
standard height.
9 Horizontal adjustment (as shown in the following picture):
based upon ensuring the whole escalator is the same as the height of the
ground that has already been decorated, lay the level instrument on the
step, and make the horizontal error be no more than 1/1000 by adjusting
the supporting bolt.
5.5 Setting centerline of placement

Central line of work is the central benchmark for the installation of the whole
escalator, and it is the installation reference for the step guide rail, handrail glass and
skirt panel and so on. We can make the installation bracket of central line by
ourselves, one at the upper and lower terminal respectively. The central line should be
based upon the main drive center and lower tension frame.

5.6 Guide rail joint at partition place

Note Make sure that the guide rail at the split section has been connected, and
then do the following operations. Please see the item No. 8 for detail.
4.5.1 Nitty-gritty of how to be on the safe side
1 Safety spectacles shall be
worn properly to carry out polishing work.
2 Protection device shall be
employed when getting the joints of the guide
rails welded to protect from getting an electrical
shock.
3 Safety spectacles shall be
worn properly when getting the welding slag
removed from the welding seams.
Protective cover shall be
4
applied to other components nearby when the
welding work is carried out (asbestos cloth can
be possibly applied to the site where
appropriate). In addition, extinguisher shall be
provided on site to protect the components
nearby from burn damage and fire risk.
4.5.2 Installing tools: open-end spanner, ratchet spanner, angle polisher, file,
electrical welder, painting brush, safety spectacles, asbestos cloth,
extinguisher, and so on.
4.5.3 Process

Confirmation of → Installation → Connection of → Connection of


the guide rail requirements return guide return guide rail of
position rail of main sub wheel
wheel

→ Connection of → Connection of
main and sub emergency guide
wheel guide rail rail
4.5.4 Confirmation of guide rail position

4.5.5 Installation requirements


1 Connect the guide rail
according to the following pictures
2 Weld the non-working
surface of the guide rail (excluding the bottom),
and clean up the welding seam.
3 Getting the connected guide
rail adjusted to ensure both vertical and
horizontal working surfaces to be parallel to the
relative position of two guide rails respectively at
upside and downside, and the parallel degree
shall be no more than 0.2mm/200mm.
4 For the width, direction,
position and size, please refer to the following
pictures. (It is the corresponding size of escalator
width of 800 and 600 in bracket)
4.5.6 Installation of return guide rail of main wheel

4.5.7 Connection of return guide rail of sub wheel

4.5.8 Installation of the guide rail of main and sub wheel

4.5.9 Installation of emergency guide rail


※After all the guide rails have been installed, do the anticorrosive treatment by brushing the
silver powder on joint seams (especially on the welding seams) ※

5.7 Middle step chain joint

5.7.1 Installing tools spring spanner hammer.


5.7.2 Installing procedure
1 The spring spanner is used to
get retaining collar disconnected at buckle chain,
chain axes is peened by the hammer gently
enough to get the whole immobilized chain node
disconnected.
2 The chains at two sides of the
split section shall be aligned to one another, and
then getting them together by buckle chain that
has been disconnected previously.
3 Get the external chain plate
and retaining collar installed.

5.8 Electric installation

5.8.1 Electric wiring


5.8.1.1 Inspection of electric wiring
Before all the wiring work, check the electric wiring according to electric drawing to
see whether there is short circuit, broken circuit, grounding etc at the electric circuit
to avoid overlap joint and breakage of electric wiring resulted from the transportation
and installation process, and then avoid serious problem while power-on. When there
is no abnormality for the wiring, conduct the next wiring and power-on.
5.8.1.2 Connection of drive line inlet wire
First of all, measure the voltage of three phase five lines provided for the escalator on
site by universal meter to see whether it complies with the requirements of service
voltage of escalator (Domestic power supply is 380V, voltage variation does not
exceed ±7%, while those in foreign areas are based on the local standard.), and inspect
the electrical supply equipment to see whether it can meet the requirements of
escalator power (for example, whether the circuit breaker meets the motor starting
characteristic and maximum current complies with the maximum current of
escalator). If they all can meet the requirements, connect the drive three phase five
lines with drive wiring terminal in control cabinet. The soft cable with suitable
sectional area of conductor should be selected as drive cable according to escalator
power. And they shall connect with five terminals of A, B, C, N, PE in control cabinet
after connecting O shape cold-pressing terminal. The three phase power supply on
site should connect with three terminals of A, B, C, and the neutral line on site shall
connect with terminal N, the grounding line should connect with PE terminal. After
connecting firmly and no short circuit, make the power on and see whether the wrong
state appears on the phase sequence relay. If the wrong state appears, cut off the
power supply and then exchange two pieces of drive line on A and B. and make the
power on once again to see the wrong state will not appear on the phase sequence
relay. Ensure that they should be connected firmly, no virtual connection and short
circuit after wiring. Check whether the three phase power supply complies with the
requirements of service voltage of escalator by universal meter.
The water proof clamping head should be adopted on the place that the drive line of
outdoor type escalator goes into the control cabinet. Tighten the water proof clamping
head and seal after finishing wiring.
5.8.1.3 Connection of control cable at the split section
Connect cable at the split section of escalator by inserter according to wire No. and
core number of cable. After the connection, inspect whether connection is firm and
reliable, wire No. corresponds one by one, and then put the cable into the wire duct.
After the connection of outdoor type cable and normal running, it needs to cut off the
power and do waterproof treatment. The waterproof treatment uses the self-adhesive
waterproof tape and black insulated tape. First of all, use the self-adhesive waterproof
tape, prolong the tape to 1.2-1.4 times that of original and wrap the wiring place until
it covers 10mm of cable outer layer, wrap 2-3layers overall to ensure the tightness.
And then use the black insulated tape to wrap 2-3layers of outer layer again to ensure
the insulativity.
5.8.1.4 Connection of heating cable at the split section
Connect the heating cable at the split section by CEE connection inserter, and then
tighten the inserter to ensure firm sealing. After that, check whether the wiring is
reliable by universal meter and inspect whether the heating tube works normally after
power-on. Control the starting of heating tube by adjusting the temperature controller.
For the adjustment of temperature controller, please see Usage and maintenance
instruction.
Note Recover to the previous setting of temperature controller after inspection.
5.8.1.5 Connection of other parts’ inserter
Connect the switch at the entrance and exit by inserter. After installing at the entrance
and exit, connect the inserter and inspect whether the wiring is reliable by universal
meter.
After connecting the handrail heating cable according to the wiring No., and then
wrap them by self-adhesive waterproof tape and black insulated tape. The method is
the same to that of 8.1.3-wrapping method for outdoor type cable.
5.8.1.6 Connection of fire fighting alarm
Fire signal shall be provided by party A, it shall be the two nodal points signal
without voltage. The fire signal provided by party A connects with corresponding
terminals in control cabinet by cable. (For the detailed wiring No., see the schematic
diagram).
5.8.2 Installation of photo-electric switch
5.8.2.1 Installation and adjustment of diffuse reflection photo-electric switch
If the photo-electric switch and front interior panelling are delivered to the site as a
whole, connect the separated photo-electric line firmly at site according to the line
number.
If the photo-electric switch and front interior panelling are delivered to the site
separately, install the photo-electric switch back to the mounting base of front interior
panelling at site. Place the transmission unit (TXTP5) on upper side and the receiving
unit (RXTP5) on lower side. Front terminals of both the transmitter and receiver
should be flush with the exterior surface of interior panelling to guarantee the light
would not be sheltered by interior panelling.
5.8.2.2 Correlation switch
If the wire of correlation photo-electric switch is cut off, connect the wire at site
according to the wire number.
The transmitter and receiver of correlation photo-electric switch respectively adopt
two-core and three-core wires.
5.8.3 Installation of wire duct
The wire duct should be installed at the middle section of escalator. Some wire ducts
has been already fixed, but some need to be installed on site. Fix the wire ducts on the
installation frame by self-tapping bolts attached with escalator. Please ensure firm
installation and no seam at the joint place.

5.9. Step installation

4.8.1 Nitty-gritty
of how to be on the safe side
In the process of the installation of the escalator, operate the escalator by using the
inspection method to make the step run downward, and then install the step from top
to down.
In the process of putting together the step, it is disallowed to run the escalator with
different modes of running to prevent accident from happening.
4.8.2 Installing tools: hexagon-socket spanner, hammer, and
screwdriver.
4.8.3 Installing procedure:
1 The vacant step place shall be
winded to the downside of the step running track
as exactly shown in the following picture, and
remove the lower guard plate.

2 Getting two sub wheels of the


step installed into the opening section where the
direction of the step has changed downwards as
circled.

3 Make the step connect with


step axis
4 Plastic retaining cover is
installed between the step axis and the opening of
the step, and then getting the joints pushed
against one another properly using the hammer. It
is exactly as shown in the Diagram down below
(the one in the left indicates what it looks like
before the relative assembly happens, and the one
in the right indicates what it looks like after the
assembly happens.)

5 After the step at left and right


sides have been well installed, measure the
distance between the side of step and the side of
main wheel on traction chain. The position of the
step shall be adjusted to make it be symmetrical
to central line with the front and rear steps. The
symmetrical degree is no more than 0.5mm.
6 After the position is well
adjusted, retaining clamp used to lock the step
shall be pushed against the retaining cover, and
the hexagon-socket spanner shall be applied for
getting the bolt screwed tightly to prevent from
looseness.
7 After all the steps have been
installed initially, inching button is pushed to
start the escalator with the step just installed, at
the same time, get the space between the step and
comb carefully inspected to prevent any
scratches or collisions from happening. If happen
unexpectedly, the retaining clamp shall be
loosened firstly, and then re-adjusting the
position of the step until the state of being
scratched cannot be seen virtually. After that, it is
kindly requested to repeat the operation as
described in the Section (5)-(7).
8 Reset the step guard plate that
has been removed.

5.10 Handrail system installation

5.10.1 Safety items:


5.10.1.1 Clear away the obstacles on the road to keep the glasses from being broken
when carrying the glasses.
4.9.1.2 The glasses should be carried by two persons
with the protective gloves.
4.9.1.3 The glasses shall avoid being broken in the
process of installation.
4.9.1.4 The handrail bracket and guide rail shall avoid
being collided with other parts of the escalator while being moved.
5.10.1.5 The protective spectacles are also needed in the process of polishing in order
to prevent hands from being scratched.
4.9.1.6 The insertion strip should be kept away from
sharp objects to avoid fracturing.
4.9.1.7 The tools shall be prevented from falling and
injuring others when undertaking the connection.
4.9.1.8 The protection of the handrail should be
carefully concerned to avoid being scrapped.
4.9.2 Tools for installation: open-end spanner, ratchet
spanner, weight, gradienter, tape line, hammer, screwdriver, scissors,
hand saw, angle grinder, protective spectacles, rubber hammer and
crocus paper.

4.9.3 Procedure
installation of ―→ Installation ― Installation of ―→ Installation of
glass gripping of glass → handrail bracket pulley group and
element guide rail

Installation of ―→ Installation ―→ Adjust press ―→ Running


heating cable of handrail strap inspection
of handrail components
4.9.4 Installation of gripping element (only for split
escalator)
5.10.4.1 The installation of glass gripping element should be done according to label;
each of the elements shall have its fixed place, and not change it casually.

5.10.4.2 Installation of quickset of cover plate


Generally, the quickset of cover plate which shares the same length of glass shall be
fixed on the corresponding cover plate and inspect the correctness of its position.
4.9.5 Installation of glasses
5.10.5.1 Before installation, the marks on gripping element of upper and lower R
section and the relative position of glass bracket on two ends shall be checked to look
for if there is some change. It shall be adjusted in time if there is any difference in the
relative position of gripping element to the marks.
As shown in the following figure

5.10.5.2 Installation procedure of glasses: the glasses shall be installed after


confirming the correct positions. The installation procedure is as follows: glass plate
of lower R section, glass plate of standard section, glass plate of non-standard section
and glass plate of upper R section.(as the drawing down below)

5.10.5.3 Confirmation of position: the edge of glass shall be located at what has been
marked on gripping element and quickset of cover plate.

4.9.4.4 The plastic glass pad shall be placed in glass


gripping element.

In order to keep the glass of horizontal section


4.9.4.5
level, the connection between glass plate at lower R section and
glass plate at inclined section shall be at where has been marked
on gripping element. The installation of glass plate at upper R
section is the same as that of glass plate at lower R section. Then
the rest glasses shall be installed one after another. The U shape
adhesive strip shall be placed between glasses, of which distance
is limited to 2mm. The roughness between upper surfaces of
adjacent glasses shall keep same.
4.9.4.6 Theverticality of glass is no more than 2mm. It
should be checked that the distance between glass on the left and
right sides shall meet the dimension in the following drawing.
(The three sizes respectively represent the installation size for the
escalator with the step width of 1000mm, 800mm, 600mm)

4.9.4.7 The
bolts of gripping element shall be tightened
firmly after adjusting the glass properly. The tightening force
moment is 35N.m.(Add the pad plate at R sect. terminal of upper
& lower R glass )

4.9.4.8 Notice: if the parallel degree of two adjacent


glasses or the vertical degree of a single glass does not meet the
standard too much, an adjustment of gripping element shall be
necessary. (Because gripping elements have been set before
leaving the factory, usually it is not necessary to adjust on-site, but
it is possible the elements become loose due to being impacted
during transporting.) The tight bolt shall be loosen a little (it
should not be too loose in order to keep its pretightening force)
Then the crow bar shall be used to do the adjustment as the
drawings down below. Finally, the bolt shall be tightened firmly
after the two glasses are flattened.

4.9.5 Installationof handrail bracket


4.9.5.1 Installation of saddle bar. The edge of glass
shall be covered by saddle bar. One end of saddle bar shall be
fixed on the end of gripping element at the entrance. Then the
saddle bar shall be stretched along the edge of glass, meanwhile
saddle bar shall be pasted onto the two sides of glass by adhesive
tape. The stretching value of saddle bar is 100mm/1m. The space
between sticking points is from 400mm to 500mm.

The procedure of installing handrail bracket (as


4.9.5.2
the drawing down below): handrail bracket of lower turning
part → handrail bracket of lower arc section → handrail
bracket of standard section → handrail bracket of upper turning
part → handrail bracket of upper arc section → handrail
bracket of non-standard section.
4.9.5.3 Installation of handrail bracket of lower turning
part (for general escalator)
1 The glasses with saddle bar shall be covered by the handrail bracket
of turning part. The handrail bracket (Take cautions to avoid distortion and
breakage)is hit slightly by rubber hammer in order to push against the
glass(See the following figure). Take care of the dimension in the following
figure to avoid setting inversely.

2 If there is some difficulty in placing the handrail bracket onto glass,


the saddle bar should be pulled properly to increase the distance between
saddle bar and handrail bracket. The saddle bar should not be pulled too long,
or else it would result in shake of handrail bracket and even breakage of saddle
bar.
3 If the installed handrail bracket is shaking, the pulling length shall be
reduced until the handrail bracket is installed well enough.
4.9.5.4 The way of installing other handrail brackets
can be seen in item 10.6.3. The installation of handrail bracket of
non-standard section shall be done according to the condition of
on-site operation.
4.9.5.5 After installation of handrail bracket meets the
requirement, the jointing of handrail brackets shall be undertaken.
The clearance between the handrail brackets is no greater than
0.3mm, and the roughness of handrail brackets’ seam is no more
than 0.2mm. The drawings of jointing handrail brackets are shown
below.
1 Jointing drawing of
terminal handrail bracket for general escalator:

2 Jointing drawing of inclined


section handrail bracket for general escalator:
3 Jointing drawing of terminal
handrail bracket of slim escalator:

4 Jointing drawing of inclined


section handrail bracket of slim escalator:
(including pulley group)

4.9.6 Installation of pulley group and handrail guide (Not


4.9.6Installation of pulley group and handrail guide (Not
for slim escalator)
5.10.7.1The pulley group shall be installed in handrail brackets of upper and lower
part. The handrail guide shall be installed in other kinds of handrail brackets.
4.9.6.2 The procedure of installing pulley group and
handrail guide: pulley group inside lower handrail bracket →
handrail guide of lower R → handrail guide of standard section →
pulley group in upper handrail bracket → handrail guide of upper
R→ handrail guide of non-standard section.
4.9.6.3 Drawing of installation of pulley group is
shown below:

5.10.7.4 Fixing and tension of pulley group

5.10.7.5 Installation of handrail guide rail in arc section


Normal wires point of handrail guide rail and of handrail bracket should be in
alignment. Put guide rail into it. Use rubber hammer to knock guide rail slightly in order
to install properly and well. Handrail guide rail and handrail bracket should be
to install properly and well. Handrail guide rail and handrail bracket should be
connected by gripping parts of handrail guide rail with rhombus blocks. The distance of
gripping parts is about 280mm.

5.10.7.6 Installation of other handrail guide rail is similar to that of arc section guide
rail, and the handrail guide rail at non-standard section can be installed according to
actual situation on the job site. The clearance at the joint between adjacent handrail
guides is no greater than 0.3mm, and the joints shall be flattened by file and polished
by crocus paper.
5.10.7.7 Installation of guide slider
5.10.8 Installation of heating cable of handrail (only for outdoor escalator at the
surrounding temperature of below 0℃)
(1)Pay attention that the outermost layer of cable should not be in disrepair, and the
joint shall be protected by insulated materials.
(2)Connecting of heating cable:
The wire (gray) shall be connected according to the wire number from the cable set
beforehand at the entrance of handrail of upper machine-room. The wire of lead shall
be bound well by high-voltage insulating tape. Then the wire shall be placed into the
cavity of upper turning part, and finally shall be taken out from the opening.
(Drawing A)
The wire and the heating cable shall be jointed and then cable shall be placed in
handrail guide down to the lower part of escalator, and finally the heating cable shall
be fixed by strip going through the two neighboring vents of handrail guide. The
fixed distance shall be 1m. (Drawing B)
At the turning part of lower handrail, if the heating cable is too long, the unnecessary
part shall be bended back slowly at the degree of 180 so that the core line of cable
would not be broken (Drawing C). The bended part shall be placed at handrail guide
and fixed by strip.
5.10.9 Installation of handrail
Before the installation of handrail, tension pulley and pressing element on the upper
step running track shall be loosened to make the installation of handrail convenient.
(As drawing and its enlarged drawing below)
(1) The following items are for installation of subsection escalator, and the
installation of complete escalator starts from item (3).The handrail shall be pulled
from upper step running track down to lower step running track at the glass of lower
R. (The handrail shall be unscratched in this process )
(2) The carrier roller and bearing assembly of lower section of escalator shall be
checked and the bearing assembly should be loosened in order to make handrail belts
get back to position, carrier roller should be in the state of tightness.

(3) Installation of handrail shall be from subsection part of escalator to the entrance of
handrail on the side of lower step running track. The handrail shall be placed on the
carrier roller in turn, and the bearing assembly shall be placed at the opening of
handrail.
(4) The procedure of installing handrail: the handrail bracket of upper turning part
shall be covered by the handrail → the handrail bracket of lower turning part shall be
covered by the handrail → handrail bracket of middle part shall be covered by the
handrail → the end of installation. The special tools shall be used to finish the
installation. (As the drawing shown below)
(5) The bearing assembly on carrier roller shall be adjusted to the center of opening of
handrail, and then the bolt shall be fastened. Notice: the bearing assembly shall also
be checked while the test running is undertaking to prevent it from running slantingly.
An immediate adjustment shall be done if that happens.
(6) Loosen the nuts of A, B, D, and nut C shall be tightened to produce tension to
ensure the natural sag of handrail belts between two carrier rollers shall be at 5-
10mm. Then fasten the nuts of A, B, and D again.

5.10.10 Adjustment on pressing element (As the drawing shown below)

The position of pressing components shall be adjusted by nut A and B in order that all
rollers of pressing components and handrail belts attach firmly. The end distance
shows as follow. Spring compression value shall be changed by nut C so that the
tensile force caused by press belts shall be adjusted. If the escalator hoisting height is
less than 4500mm, x=118mm. When the hoisting height is between 4500mm and
6000mm, x=108mm.
5.10.11 Run the escalator upwards and downwards to see if the handrail system is in a
good condition. If there is something abnormal, the running of escalator shall be
stopped immediately, and the carrier roller and tension device shall be checked and
readjusted in time until it runs normally.

5.11 Outer cover plate installation

5.11.1 Safety requirements on installation


5.11.1.1 To prevent the conveyed cover plate from being collided with other members
of escalator, installers shall comply with safety requirement on installation.
5.11.1.2 When connecting operation is carried out, the tools concerned shall be kept
in safe place to prevent persons from being hurt on job site.
5.11.1.3 When connecting section needs to be polished, it shall be careful to prevent
the hands from being hurt by angle portion at two sides of cover plate (required to
wear safety gloves during operation on site), and safety spectacles are also required to
be used.
5.11.2 Installing tools: open-end spanner, ratchet spanner, rubber hammer, tape rule,
weight, angle polisher, flat file, rectangle ruler, hand saw, safety spectacles.
5.11.3 Procedure

5.11.4 Outer cover plate shall be installed in conformance with the drawings to
as shown below.

Where
Outer cover plate at lower R section
Outer cover plate at standard section
Outer cover plate at upper R section
Outer cover plate at non-standard section

5.11.5 Installation of outer cover plate


5.11.5.1 While adjusting the support of the outer cover plate, the space between the
upper surface of outer cover plate and truss shall be ensured, and the space between
the outer vertical surface of outer cover plate and the outer side of truss shall be up to
20mm. Other sizes see the following drawing.
5.11.5.2 Outer cover plate shall be put in its place before installing bracket and
rhombus blocks.

5.11.6 The joint section between outer cover plates that are adjacent to one another is
shown as in the following scheme; the clearance and drop height is no more than
0.3mm.

5.12 Installation of skirt plate dismantled from sectional escalator

5.12.1 Precaution on installation


5.12.1.1 The skirt panel should avoid scratching with other parts of escalator when
carrying. The work will be carried out on the premise that the installation personnel
are safe.
5.12.1.2When connecting operation is carried out; the tools shall be kept in safe place
to prevent persons from being hurt on job site.
5.12.1.3 When connecting section needs to be polished, it shall be careful not to be
hurt by angle portion at two sides of skirt panel (required to wear safety gloves during
operation on site), and safety spectacles are also required to be used.
5.12.2 Installing tools: open-spanner, ratchet spanner, tape, feeler gauge, angular
grinder, hand file, square, protective spectacles.
5.12.3 Installing procedure
5.12.3.1 The assembled attachment bolts are connected to C type panel of skirt panel,
and then screw the bolt to make the rhombus push against the inner surface of the C
type panel so that they can be hardly disconnected from one another.

5.12.3.2 Skirt panel is installed to make attachment bolt close to the opening of
connecting board.
Central symmetry and plane degree of skirt panels both at the same side are adjusted
according to the dimensions as shown in the scheme down below. The space for one
side between the skirt panel and step is required to be no greater than 4mm, and the
sum of two sides is no more than 7mm.The attachment bolts are screwed up precisely
as soon as the relative requirement is well met. (The size in the drawing of 1008,808
and 608 is respectively for installation size of escalators with the step width of
1000mm, 800mm and 600mm)

5.12.3.3 Attachment rhombus block bolts and square plate are both used to get the
adjacent skirt panel connected rightly, and then the position of skirt panel is well
adjusted to ensure the drop height of the adjacent skirt panels to be no greater than
0.3mm. While installing assembled connecting plate and rhombus block bolts to C
type panel, the bolts are screwed subsequently in order to make the rhombus block be
pushed against the C type panel. Nuts are required to be fixed firmly.

5.13 Safety device check

5.13.1 The following devices shall be inspected in turn including protective device of
drive chain, protective device of handrail entry, safety device of skirt panel, safety
device to prevent step sagging, protective device of main drive chain, protective
device of over-speed, unintentional reversal safety device, electrical protection, and
so on. The focus of the inspection is on the reliability and sensitivity of the function
elements when they are actuated on the job site. Check whether each switch and
components are loose. The concrete position shows as following.
Main drive chain protection device

5.13.2 Inspection of safety device of comb plate: as detailed in the drawing below
When a horizontal force of 600N is applied to the direction as shown by the arrow in
the scheme, front tread shall be moved flexibly to trigger the switch concerned. If it is
unavailable to meet the above-mentioned requirement, there will be some adjustment
to the tread and clean sundries between the motion surfaces until the required demand
can be fully satisfied in a technical manner.
5.14 Run escalator and check it repeatedly

5.14.1 The guideway of step shall be cleaned up to get rid of any dirty stuff on the
step and interior of escalator. Connect the power, and do well in the preparation work
ahead of operation.
5.14.2 Gap between step roller and compress guide (small C type material) in
working section shall be strictly inspected, and its gap value shall be kept within 1-1.5
mm(as shown in the scheme below). Due to the vibration in the process of
transportation, the value shall be changed accordingly. When the gap is too narrow or
none existent, the whole body concerned will be vibrant rigorously with high noise
levels; if the gap is so wide that the tread will sway along the axis of sub-wheel;
therefore, the gap value at upward section in full length shall be determined to make
sure the requirement on adjustment is perfectly satisfied.

5.14.3 The inspection switch is used for operation. While the escalator is running
upwards and downwards, the gap at single side between the side of step and skirt
panel shall be no greater than 4mm and also the sum of gaps at both sides is no
greater than 7mm.(above drawing)
5.14.4 Inspection of avoiding handrail belt from heating and wearing (following
drawing)
5.14.4.1 While the escalator is running, check if handrail is running with step
synchronously. The speed of handrail belt should be 0% to +2% faster than that of
step in normal state;
5.14.4.2 When the escalator is running upwards, a force of 35 Kilogram is exerted on
the lower side of handrail; if the handrail can not be run normally and continuously;
5.14.4.3 A force of 35 kilogram is exerted on the upper revolving position of
handrail; handrail belt should move 5-10mm;
5.14.4.4 After the escalator is running upwards for 3 circles, the sag of the handrail
between two adjacent rollers shall be measured. The sag should be kept within 5-
10mm in value;
5.14.4.5 View whether there is the gap among handrail and guide rail of each part (or
bracket) and among end pulley groups (See following drawing).
5.14.4.6 If any item of requirements isn’t needed in above 4 items, each pulley group
and pressing device shall be adjusted according to corresponding items in item 9.9
and 9.10. Repeat the operation until requirements can be met.

5.14.5 Operate with inspection switch and the escalator runs upwards and
downwards, and also makes sure that no abnormal sound can be heard around. If this
is the case, the tension of the step at both sides, the compression of lower tension
spring at both sides shall be strictly inspected, as well as, check if the cross section of
guide rail and joints of each guide rail are smoothened; otherwise, the subsequent
adjustment shall be implemented upon the right reason found for that until the
requirement concerned can be fully satisfied (See following drawing).
5.14.6 With the operation of inspection switch, the escalator is running upwards and
downwards, and checks if the tread can be collided with comb plate. If this is the
case, comb plate should be adjusted by hexagon socket bolt (as shown in the scheme
below).The side gap between the teeth of the comb plate and step pedal shall be
ensured to be over 1mm; the stud on the sliding guide of the comb plate shall be used
to adjust the height of the comb plate, and the depth of engagement between comb
plate and step pedal shall be no less than 4mm.

5.14.7 The tension of main drive sheave chain shall be adjusted in order to reduce the
vibration.
5.14.7.1 Run escalator downwards for 10 seconds at first and then stops.
5.14.7.2 Exert the force on upper drive chain and view chain variation when forcing
upwards and downwards.
5.14.7.3 Loosen 4 bolts for fixing, and adjust direction from front to rear and bolts.
View above vibration. The value shall be between 10mm and 20mm.
5.14.7.4 Measure and adjust level bar of broken chain protection in order that the
minimum distance between it and right upper chain shall be 30mm.
5.14.7.5 Screw up 4 bolts for fixing firmly after adjusting.
5.15 Inner cover plate installation

5.15.1 Safety requirements on installation


5.15.1.1 The cover plate should avoid scratching with other parts of escalator when
carrying. The work will be in hand on the premise that the installation personnel are
safe.
5.15.1.2 When connecting operation is carried out, the tools concerned shall be kept
in safe place to prevent persons from being hurt on job site.
5.15.1.3 When connecting section needs to be polished, it shall be careful not to be
hurt by angle portion at two sides of cover plate (required to wear safety gloves
during on site operation), and safety spectacles are also required in case of getting the
connecting section polished.
5.15.1.4 Installing tools: open-spanner, ratchet spanner, rubber hammer, tape, weight,
angular grinder, hand file, square, handsaw and protective spectacles.
5.15.2 Installation of front panel
5.15.2.1 Prior to the installation of the front panel, the relative electrical elements
shall be installed completely.
5.15.2.2 Immobilized support angle pieces installation for fixing are installed, and
then the screws concerned shall not be screwed tightly (so that delicate adjustment to
the position of front panel and cover plate at arch section of skirt panel can be
implemented in case of need).
5.15.2.3 Installation of front panel at outer side
The cutting of the front panel shall insert into bolts on the bracket. Ensure the parallel
distance between the bottom of the front panel and upper surface of step at front edge
plate to be no greater than 1mm.The bolts with rhombus block drive through the front
panel at outer/inner side and installing hole on the glass, and then the nuts are used to
get the bolts fixed firmly. Be careful to prevent the glass from being damaged.

5.15.2.4 Be careful not to damage the plate concerned while installing front panel at
inner side (as shown in the drawing below).

5.15.3 Installation of inner cover plate (Generally inner cover plate at joints shall be
only needed to install.)
5.15.3.1 Inner cover plate shall be installed in conformance with the drawings 1 to 4
as shown down below.
Where
: Inner cover plate at lower R section;
: Inner cover plate at standard section;
: Inner cover plate at upper R section;
: Inner cover plate at non-standard section

5.15.3.2 Inner cover plate is inserted into the groove of inserter of cover plate, and
sunk screws are used to get the inner cover plate connected with skirt panel. The
dimension of the skirt panel shall be ensured to be absolutely correct to prevent it
from deformation.

5.15.3.3 The space between inner cover plates and drop height shall be both no more
than 0.3mm.
5.15.3.4 The joint space between inner/outer cover plates and decorative elements at
the end shall be no more than 0.3mm.
5.15.3.5 The dimension used to install horizontal section of inner/outer cover plates
and decorative elements at the end shall be up to 1.5mm; the dimensions shall be kept
within 1-1.5mm by adjusting immobilized angle members at the top of the outer
cover plate. While the parallel joint at upper plane is carried out on the job site, the
drop height difference concerned shall be: |D1-D2|≤0.3mm . The value of the
difference shall be kept consistent with one another for the same escalator.
5.15.3.6 External side of outer cover plate shall be parallel and level to decorative
plate at end as required.
5.16 Stick safety signs for running

To ensure the escalator runs safely, two safety signs shall be stuck on the glass of
entrance as shown in the picture below and one sign shown in the picture below shall
be stuck on the right outer deck of the upper of the escalator with 3M tape which shall
be elegant and convenient to view.

5.17 Running of escalator

The escalator can only run after various electric parameters have been confirmed and
adjusted before operation. Related instruction document for adjustment is
“Adjustment Manual”.
Clean up any dirty stuff inside the escalator after the above work on installation and
inspection has been finished. The inspection switch and key are used for switching
on/off the escalator respectively. Tread shall be well erected and safety caution fence
shall be removed to finish the installation of the escalator after the confirmation of
normal running.