Beruflich Dokumente
Kultur Dokumente
A F R I C A
November 2005
Table of Contents
Acronyms ....................................................................................................................................................... 4
1.0 INTRODUCTION ................................................................................................................................ 5
1.1 Background to the Study ................................................................................................................ 5
1.2 Justification for the Study ............................................................................................................... 5
1.3 Study Objectives ............................................................................................................................ 6
1.4 Study Methodology......................................................................................................................... 6
2.0 TYPES & NATURE OF EXISTING ORGANISATION MODALITIES ................................................ 7
2.1 Project committees......................................................................................................................... 7
2.2 Petty contractors ............................................................................................................................ 7
2.3 Co-operatives ................................................................................................................................. 8
2.4 Other community structures ........................................................................................................... 8
2.4.1 Project management boards........................................................................................................ 8
2.4.2 Resident development committees.............................................................................................. 8
2.5 Emerging issues for guidelines ...................................................................................................... 9
3.0 CONTEXTUAL, INSTITUTIONAL & LEGAL FRAMEWORKS ....................................................... 11
3.1 Community contracts.................................................................................................................... 11
3.2 Procurement systems and regulations.............................................................................................. 13
3.2.1 Procurement at national level .................................................................................................... 13
3.2.2 Procurement at community level................................................................................................ 14
3.2.3 Registration process of contractors ........................................................................................... 15
3.3 Constraints and opportunities....................................................................................................... 16
3.3.1 Constraints ................................................................................................................................. 16
3.3.2 Opportunities................................................................................................................................ 17
3.4 Emerging issues for guidelines .................................................................................................... 17
4.0 OPERATIONAL PROCEDURES AND FRAMEWORKS ................................................................ 18
4.1 Mobilization process..................................................................................................................... 18
4.2 Contract sums .............................................................................................................................. 19
4.3 Negotiations and terms ................................................................................................................ 19
4.4 Recruitment criteria and procedures ............................................................................................ 20
4.5 Standards and productivity norms................................................................................................ 22
4.6 Payment systems/procedures ...................................................................................................... 23
4.7 Contract management.................................................................................................................. 24
4.8 Capacity building skills development ........................................................................................... 25
4.9 Gender Considerations ................................................................................................................ 25
4.10 Emerging issues for guidelines .................................................................................................... 26
5.0 PERCEPTIONS ON INCENTIVES AND SHARED BENEFITS....................................................... 30
5.1 Between communities and contracting parties............................................................................. 30
5.2 Between community contractors and the beneficiary community ................................................ 31
5.3 Emerging issues for Guidelines ................................................................................................... 31
6.0 ASSESSMENT OF KEY ISSUES .................................................................................................... 32
6.1 Existing potential .......................................................................................................................... 32
6.2 Constraints ................................................................................................................................... 32
6.3 Opportunities ................................................................................................................................ 33
6.4 Emerging issues for guidelines .................................................................................................... 34
References ................................................................................................................................................... 35
Appendices .................................................................................................................................................. 36
2
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
3
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
Acronyms
4
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
1.0 INTRODUCTION
The global Employment Intensive-Investment Programme (EIIP) of the ILO promotes and
supports the generation of productive and decent employment through local resource-based
investment policies and programmes in infrastructure to contribute to poverty reduction, economic
development and social progress. ASIST Africa (Advisory Support, Information Services and
Training) has held the role of the delivery mechanism for EIIP in Eastern and Southern Africa. The
programme has been considered fairly successful and is believed to have had significant impact,
particularly when it comes to the delivery of infrastructure and services using the labour-based
technology through small and micro-enterprises. Nevertheless, some work has still to be done to
ensure effective participation of the local communities in decision making and implementation of
interventions to improve their livelihoods.
The ongoing decentralisation reforms in several countries in the region calls for the need to match
the transfer of development responsibilities to the local authorities and communities with
adequate responsive measures to strengthen capacities for beneficiary involvement at local level.
Community empowerment e.g. through training, employment creation, social dialogue, etc. forms
an important part of this process. Community contracting is one of the very encompassing tools
for community empowerment which combines technical, institutional and socio-political aspects of
development. Community contracting is one area that ILO has been involved with in the recent
past, but needs further exploring to be able to scale-up and mainstream the approach in the
development processes as a core strategy for community empowerment and poverty reduction.
Community contracting involves a contract between a client (e.g. the local authority) and the
community, for a remunerated employment package. It is a people-centred approach for
infrastructure and service delivery where both or all parties to development recognise the
benefits. Community contracting for physical implementation of works of which they are the direct
beneficiaries helps to retain substantial portion of any external funding into their hands as well as
helping to build their self-esteem. Community groups are also best involved in project
identification, priority setting and formulation, which in effect reinforce the ownership aspect. The
community contracting approach responds to the needs of the community on a longer - term
period through emphasis on optimisation of local resources, better organisation, accountability
and ownership at local level. This is unlike conventional approaches which may have more
benefits to service providers.
A body of knowledge already exists in ILO with regard to community contracting. However, this is
mainly from the urban context where most of the recent projects have been or are being
implemented, and hence the justification for this rural-based study. In this regard, the following
issues are worth noting:
¾ To address increasing demand: - Owing to the need for development approaches and
interventions that directly address poverty at local level, there is an increasingly high
demand for community contracting information, procedures and/or guidelines by
practitioners in the region to facilitate effective community organization for development
work in both urban and rural areas.
5
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
¾ To fill the knowledge gap: - Community contracting is a slightly new concept which
needs further development based on the existing practical experiences. Consequently
there is paucity of comprehensive knowledge and documented practical examples and
case studies in relation to the rural contexts of Sub-Saharan Africa.
(i) To identify and document prominent examples and lessons from the past and ongoing
community contracting practices and community organization modalities for public works
development initiatives in rural areas of selected study countries.
(ii) To develop draft guidelines and test strategies that will provide applicable solutions in
different rural contexts and open to adaptations to local conditions. These will be based on
the examples of good practices and lessons for improvement. The guidelines will enable
practitioners and communities to design and incorporate community contracting system
into public development projects, and also serve as training materials.
(iii) To promote and advocate the benefits of community contracting as a potential tool for
local community empowerment, poverty reduction and sustainable development, e.g.
through employment creation, enhancing social dialogue, social security, transparency,
accountability and ownership.
The methodology used in the study encompassed a desk-work study of key/available information
on community contracting. In addition, a fieldwork study was conducted with the aim to cover a
survey of past and ongoing initiatives so as to extract and document practices and lessons.
During the fieldwork study the following were undertaken: (i) Semi-structured interviews with key
players involved in funding and giving contracts to urban and rural areas; and, (ii) case studies of
selected communities involved in community contracting. Exploratory visits together with semi-
structured interviews and focus group discussions were held with key community groupings,
project committees undertaking community investment programmes and petty contractors.
Appendix 1a and 1b provides a list of all organisations and community key players consulted in
this study.
6
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
Current organisations involved in community contracting in rural areas of Zambia use various
forms of modalities/structures. The study identified such modalities used for community
contracting and these are listed below:
1) Project committees;
2) Petty contractors;
3) Cooperatives;
4) Other community groupings.
The identified modalities are each discussed in turn and their status is summarized in Table 1.
Committees were the most common structures for community contracting being used by the
organisations assessed. These committees include the following four;
• Project Committee,
• Project Management Committee,
• Works Committee and,
• Resident Development Committee (RDC).
Project committees are informal groups, with no legal status. The committees consist of 10 to 12
members who are democratically elected by the community. All the project committees visited
indicated that at least 50% of the members are women.
In all cases reviewed, each committee has a chairperson, secretary and treasurer who in most
cases act jointly as bank signatories. All the elected members work in a voluntary capacity.
The project committee is ad hoc, set up specifically for the project at hand, with in-built flexibility in
its functions. Because the committees are not permanent and lack a legal status, inconsistencies
are likely to arise in the way activities are conducted.
Petty contractors were not common in the sampled communities. Kabile school construction, a
project under Christian Children’s Fund in Mumbwa District, was the only case where a petty
contractor was hired within the community. This was not a situation where the contracting
organisation contracted directly but rather, a situation where the project committee subcontracted
the local contractor.
The general feeling by some of the communities visited as to why petty contractors are not used
was that skills are usually not available locally and so they have to contract out.
7
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
2.3 Co-operatives
Programmes implemented under the Ministry of Agriculture and Cooperatives (MACO) use this
structure. Cooperatives by their nature are formal groups with a legal status. Among the
organizations visited, only the Japanese International Cooperative Agency (JICA) and the Rural
Investment Fund (RIF) use this structure. RIF has set it as a condition to only fund co-operatives
that are registered with the Registrar of Cooperatives under the Ministry of Agriculture and
Cooperatives.
When an organisation is dealing with agricultural based pubic works, a cooperative is one of the
best structures to use because members are likely to have specialised skills. However, the
danger in using this structure is that the cooperative may be seen as an elite group having a
monopoly over subprojects related to agriculture.
The Project management boards are community based and used by CCF Zambia. These are
made up of representatives from the target community and members of the contracting
organisation based at the community level. The project management board is responsible for
community contracting and is in charge of planning, budgeting, implementation, hiring skilled
labour, monitoring and evaluation. Unlike the project committee, the project management board is
a permanent structure and tends to be there as long as the contracting organisation is operating
within the community.
Table 1 below summarizes the existing organizational modalities and status and status at
community level.
8
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
¾ Nature of existing modalities: It has emerged that most organisations using community
contracting use ad hoc committees such as the project committee. The advantage of using this
kind of arrangement is that it is representative of the community and allows for flexibility. In
addition, it is fairly easy to establish. However, the disadvantage is that it is not sustainable and
usually leads to confused responsibilities. For instance, in one community visited (Chipindani
community), it was observed that there were different project committees dealing with different
projects under ZAMSIF, CCF and JICA. The problem with this as was observed, is that one of
the project committees seemed to have placed itself as an elite group in the community. To
avoid this, the issue then becomes the need to establish a permanent group within the
communities which can act as a representative body for voicing opinions and advocating
community contracting as a tool for community empowerment.
It would be beneficial to use existing permanent structures such as the Area Development
Committees (ADCs) to coordinate community contracting to avoid potential conflict.
9
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
The community representatives that form the ADC are leaders of the various committees
existing at the ward and sub-ward level. An ADC is further sub-divided into zones. Each zone
has a Zone Development Committee (ZDC). Like the ADC, this is a committee of
representatives which in turn consists of community leaders drawn from Village Development
Committees (VDCs) in the zone. Affiliated to the VDC are community based committees
formed around areas of specific interest such as the Village Water and Sanitation Health
Education committee (V-WASHE), Neighbourhood Health Committee (NHC) and Parents
Teachers Association (PTA).
The Government has recognized that the ADC will increasingly play a prominent role in
facilitating development at grassroot level. With the government’s deliberate drive towards
decentralization, the typical direction in which ADCs appear to be evolving could play a leading
role in community contracting. As permanent structures, ADCs have the advantage of serving
as a reservoir for community contracting experience.
10
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
The type of community contracts used by the various community structures were assessed using
the following definitions provided by ILO1.
a. Labour- only contracts: The community is only responsible for the provision and
organisation of the labour input. The contracting authority or external assistance group is
responsible for the timely provision of materials and equipment in sufficient quantity and
quality.
b. Labour and material contracts: The community is responsible for both the labour and
materials input for a certain construction activity.
c. Full contract: Under a full contract the community provides the labour, materials and the
necessary equipment, and is also responsible for overall management, sub-contracts etc.
The local government or contracting organisation provides technical assistance.
An assessment of the types of community contracts used for different public works development
initiatives in rural areas revealed the existence of different types of contracts. Table 2 illustrates
the type of contracts and contractors and processes used in selecting a community contractor.
1
ILO ASIST Africa Regional Programme, Tournée J., van Esch W. Community contracts in urban infrastructure works; pg 29; Geneva,
International Labour Office, 2001.
11
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
Generally, it was observed that community contracts were either provided directly to the
community or were provided to a sub-contractor contracted by the community. The former which
involves channeling of funds to be managed entirely by the community was the most common.
However, in situations where more complex technological project deigns are chosen (such as
construction of a dam as in the case of the Lunywa dam, a ZAMSIF sub-project), the latter is the
preferred approach. Here the community enters into a contract with the sub-contractor using a
financing agreement drawn up by the contracting organisation. There was only one isolated case
involving the construction of a community school and centre, where a labour only contract was
used.
Some organisations like ZAMSIF (Zambia Social Investment Fund) and RIF (Rural Investment
Fund) use a combination of contracts. This depends on the project type as well as the institutional
capacity of the communities. Organisations were also assessed in terms of the form of contracts
they use. Only ZAMSIF and RIF had the practice of drawing up simple standard community
contracts. In all cases, these contracts were not legally binding. Other organisations use financial
agreements as contracts.
An assessment of the type of contracts communities prefer was carried out with the aim of
conducting a comparative analysis of the pros and cons of the 3 types of contracts. Out of the 9
communities visited, only 1 community expressed its preference of the labour and material
contract, the remaining 8 indicated they would prefer the full contract approach (see Appendix 4).
Reason provided for the preference of labour and material contract was based on the need to
have technical expertise to carry out complex technological projects. The advantage of this type
of contract is that it provides communities with an opportunity to manage human and material
resources. This ultimately enhances their management skills which are necessary for providing
sustainability. However, the presence of external contractors and technical experts in this type of
contract robs the communities the opportunity to enhance their skills in the full management of
projects.
Reasons provided for preference of a full contract were similar in most cases, the major ones
including:
It builds capacity
It equips communities with skills particularly in financial, technical and administration
management
It provides a sense of ownership
It creates employment
Some communities were, however, quick to add that the full contract should consider the
involvement of a technical supervisor coming from the local government or from the contracting
organisation. As they observed, a technical supervisor is important especially when the
community lacks skills or technical knowledge to manage the implementation of an infrastructure
project. Clearly this is also true in situations where a community is undertaking public works for
the first time. On the other hand due to the involvement of the technical staff, communities may be
constrained in fully participating in the management of the contract and undertaking project
activities.
The labour only contract was the least preferred contract model because it does little to promote
skills and capacity which are essential for sustainability of projects. However, one advantage of
this type of contract is that it frees the community of the burden of providing materials, resources
and technical skill especially where capacity building has not been undertaken.
12
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
The procurement of works at country level, which is undertaken by the Zambia Tender Board, are
concerned with Civil Engineering, Construction and the Supply and installation of Plant and
Equipment. Examples include the following:
The Board has set thresholds, where the estimated minimum value of the procurement is $1,100
but does not exceed $3,300. This is set for informal tenders who are invited, evaluated and
authorised for acceptance by the District Tender committees. Procurement above $3,300 is
authorised by the Central Tender Committee.
In the public sector, the procurement of works is undertaken when the concerned institution
identifies the need to provide infrastructure that is intended to enhance the operating efficiency of
the user institutions. The procedure that is taken for the procurement of works is further
elaborated in Box 1.
Procurement processes are regulated by the Zambia National Tender Board Act, 1982, Section
27.
13
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
Among the organisations visited, ZAMSIF has the most comprehensive, well structured
procurement system laid out for the community level. Box 2 gives a description of this system.
The bulk of the works procured at the community level consist of minor works. These are
managed differently as was observed. The most preferred approach used by communities is
engaging qualified and skilled labourers within the community. As works at community level are
not complex in nature and are small in size and value, most communities prefer to implement
these utilising this approach.
Where a community subcontracts, the contracting organisation or the district council assists in
advertising for contractors. It was a common practice among organisations to engage contractors
on the basis of quotations obtained in response to a written invitation. The group or committee,
14
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
with the guidance from the district officers or contracting organisation, evaluates and awards the
work on the basis of qualification, experience and the least cost.
The responsibility for procurement at the community level mainly rests with the
communities’ Project Committees. These are trained in procurement prior to and during
implementation of the sub-projects. In situations where ZAMSIF wants to ensure quality,
cost efficiency and durability, procurement is undertaken centrally by ZAMSIF
Management Unit (MU).
Procurement forms used by the communities are part of the Financing Agreement entered
into with the communities by ZAMSIF MU. All tender documentation related to a sub-
project is maintained either by the community or/ and ZAMSIF MU.
Potential bidders may be procured on the basis of quotations obtained from three qualified
domestic contractors in response to a written invitation. The bidders are at least given one
week to submit their quotation. The Committee or group opens the bids in a public forum
and the name of the bidders and the price are read out. The qualifying contractor is then
awarded a contract on the basis of qualification, experience and the least cost.
In some cases, the workers hired will require supervision by a qualified and experienced
technical person. The selection of the technical supervisor is on the basis of qualification
and experience. ZAMSIF’s experience indicates that these typically amount to the
equivalent of US$1,500 per contract. The Project Committee will prepare terms of
reference for the Technical Supervisor and will solicit at least three quotations.
Responsibility for selection rests with the Project Committee, and will require
endorsement by the District.
In Zambia, the registration of contractors is carried out by the National Council for Construction
(NCC). The NCC is an advisory body, affiliating and representing all trade organisations and
professional bodies within the Zambian construction industry.
The NCC ACT No. 13 of 2003 was established to empower the National Council for Construction
to register and regulate all contractors and consultants in the Zambian construction industry. The
NCC runs a registration scheme for all contractors and consultants engaged in construction
activities in Zambia. Box 3 provides the registration process potential contractors are required to
go through. The processes include the costs2 and time taken for registration.
The advantage of the NCC is that it facilitates the creation of opportunities for contractors
according to their category and capacity. It also provides a basis for focused and effective
capacity building programmes.
2
Costs are provided in US dollars at the prevailing exchange rate.
15
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
3.3.1 Constraints
Institutional frameworks
There are insufficient institutional arrangements for community contracting with respect to
planning and operational modalities. Structures to support community contracting are not fully
developed such that integration of the different aspects of community contracting, particularly
procurement processes, is still weak. To a large extent this situation can be attributed to the
inadequate administrative decentralization as well as the low capacity of local government to
enter into community level contracts. In Zambia, these processes are still evolving.
The formulation of national government policies still favours urban areas. For example, the
country’s procurement system does not cover small local organisations based in rural areas.
Therefore, decisions on procurement and general contracting issues are influenced by the
contracting organisations which isolate the local groups and organisations from the process.
Ideally, the contracting organisation should only act in an advisory capacity and the final decisions
on contracting should be made by the community. Consequently, there is need to develop policies
that suit rural communities in community contracting procedures.
Presently, most groups involved in community contracting are not registered as associations,
CBOs or contractors. The lack of legal status for the committees and other groups entails that
they are not protected from unfavorable conditions that might be imposed upon them by various
actors such as the contracting organisation, local government, private contractors and suppliers of
goods and services.
Lack of Information
could be available for them. It is critical that information is made available to the communities to
facilitate their effective participation.
There is lack of training facilities to assist community groups and committees to acquire skills
necessary to carryout contractual arrangements with the contracting organisations or local
government departments. Communities need to have a thorough understanding of the stages
involved in community contracting. Lack of training has implications on the extent to which
community groups can effectively participate in the various stages of community contracting.
3.3.2 Opportunities
Existing Partnerships
A number of organisations have started using direct project support and have also been building
their own participatory structures at the community level. This approach provides an opportunity
for communities to independently undertake community contracting especially when investment
funds are solely managed by the community, committee or group.
Due to the drive towards decentralisation, CBOs are now being recognized as key players in the
development process. This is seen as an opportunity for CBOs to slowly be integrated into the
institutional framework for public procurement of works at community level.
¾ Legal environment for community contracting: The creation of a legal association or CBO
can act as a formal link with government public procurement system, as this would eventually
manage collective funds, and award or execute contracts. Establishing a legal environment
also serves the community as well as the contracting organisation a reference point with
regards to activities undertaken.
¾ Tailor-made contracts: Contracts should be awarded after an assessment of the capacity and
skills of a community contracting group. The contracts drawn should not only be simple but
comprehensive, including areas that will promote the broader objectives and purposes. They
should not only be limited to responsibilities, conditions on contributions, work to be
undertaken, or disbursement arrangements, but should also include issues such as legal
obligations etc.
The mobilization process was identified in the study as occurring at two levels.
Level 1: Through key leaders, the community is mobilized with the view to identifying projects
which follow an examination of community problems by communities themselves. A group is
identified or a committee is elected to oversee the project. The group or project committee is
responsible for making an application. Application forms are then submitted to the relevant local
government department. Once a proposal is approved, the contracting organisation makes all
contractual arrangements with the community group or project committee.
Level 2: The contracting organisation visits selected communities and makes contacts with
individuals and representatives of local social and cultural groups. Through district and sub-district
staff, councilors, church, CBOs and other community groups, communities are informed of the
opportunities made available. The group’s influence is used to mobilize the community. Certain
communities already have an active community group. The contracting organisation will introduce
the infrastructure programme to the community group and assess their interest in such a
programme. Box 4 provides common stages in the mobilisation process that are undertaken by
communities assessed in this study.
18
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
The study has revealed that, contract sums are based on rates determined by each contracting
organisation. The financial analyst or accountant prepares a financing plan or a bill of quantity.
This provides very detailed unit costs of materials and labour required. Table 3 shows the
contract sums for various public works development initiatives reviewed.
In all the communities sampled, there were no groups that had been involved in determining the
contract sum and this was attributed to the lack of technical skills to undertake an accurate cost
assessment of the project.
It was evident that negotiation was absent in the projects looked at. None of these communities
have reached such a stage where they can negotiate for themselves. The study, firstly, revealed
that contracting organisations seemed to be rigid. Secondly, the negotiation process is not well
organized and only provides communities with an opportunity to engage in negotiations related
only to their social interests. Thus, communities were only involved in the negotiation process
during the identification of the project. This varied among the communities. They were those
communities who would be approached by the contracting organisation (in the case of Kabile
school construction and Ndeke water piping). Through participatory rural appraisal (PRA)
activities, the communities are provided with an opportunity to negotiate for the type of
intervention they need. In other instances, communities would identify their need and then
approach the contracting organisation or the district council to explain their project to them. This
gives again communities the chance to negotiate for what they want.
However, it is imperative that the negotiation process should extend to other aspects such as
contract sums, conditions and implementation processes e.t.c. This is important in changing the
status of the poor and empowering them to be actors in development.
These communities fall short of participatory meetings where all the stakeholders can be provided
with the opportunity to participate in discussing the contract. The danger in failing to achieve this
is that people make their own conclusions and interpretations which can lead to confused roles
and responsibilities.
Apart from the identification of an intervention, the negotiation of terms is another critical stage
that sets out whether the informal group or committee will get funding. The terms and conditions
19
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
under which funds would be made available varied in some cases under this study. The main
issues pointed out by the communities visited were mainly contributions, responsibilities, timing of
construction and maintenance.
The most common issue for present funding in most of the communities sampled is based on a
25% contribution by the community, with the remaining 75% provided by the contracting agency.
Other terms are that a community has to demonstrate its commitment to the project by providing
their share of the first batch of the works before building can start.
Cost sharing arrangements is a condition that ZAMSIF has usually demanded for. A community is
expected to have contributed about 15% of labour and locally available materials to the project
and should demonstrate the existence of self reliance. Communities felt this condition was unfair
because it limited their level of involvement in the process of development. Communities who
have been involved in this process complained of the difficulty to fulfill this condition because not
everyone in the community was willing to contribute. This would in most cases delay the
application process.
The recruitment processes and criteria used among the communities varied depending on the
staff required and type of contract approach used. It was generally observed that most contracting
organisations strive to create an opportunity for small local contractors or individual labourers
within the community to be involved in public works contacts. The recruitment process will,
therefore, be assessed in light of the contract approach used by the various contracting
organisations, community groups and committees.
Contracting for technical and more sophisticated services, such as the construction of overhead
tanks, dams and drilling boreholes largely used contractors outside a community. All communities
visited, which have used a technical supervisor, stated that where they see an absence of skills
locally, they opt to go for an outside registered private contractor. This type of contracting is
mostly done by the districts or the contracting organisation with minimal involvement of the
community group or project committee. The technical supervisor is in most cases recommend by
the contracting organisation or by the local government department involved in the project.
There was only one community among those sampled, where the project committee had insisted
on recruiting a technical supervisor from within the community. This was Chipindani community
where ZAMSIF had approved funding for an improvement in their water and sanitation. The
project committee felt that there was readily available skilled manpower within the community to
take on the role of a technical supervisor. The project committee called for community members
with potential in technical supervision to attend interviews. The person selected was the one who
had the best references. The advantage with this approach is that it empowered the community
and provided employment. However, this approach does not ensure quality of work. But in the
example given the community were happy with the quality of the construction of the bathrooms
and toilets. Figure 1 shows the toilet and bathrooms constructed.
20
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
Figure 1: Example of type of bathrooms & VIP toilets constructed in Chipindani community
The study revealed that, contracting for skilled services, such as bricklaying, carpenters, fitters,
plumbers and masons is mainly done at the community level by the committee or group in charge.
As opposed to the urban set up, recruitment of skilled labour in rural areas mostly involves a
verbal agreement.
When the community decides to hire skilled labour from within itself, invitations are made either
directly to individuals in the community who are known to possess such skills and at other times
invitations would be made during community meetings. Those who then feel they posses the
required skills would go before the group or committee in charge to be assessed.
The advantage of using local skills is that it generates local employment. Apart from the
generation of local employment, it also enhances the already available skills as well as provides a
sense of ownership. This approach also provides the community with greater control on
expenditures.
It was generally observed that similar formal contracting processes are used across the
organisations and communities sampled, when it came to sub-contracting. The contracting
organisation and the districts especially, play a proactive role in this kind of contracting to help
groups or committees identify and select the right contractors.
When the community decides to sub contract, formal contracting processes are used, which
usually include inviting bids and awarding contracts on the basis of quality and price. The
contracts are awarded on the basis of at least three quotations obtained from qualified local or
private contractors in response to a written invitation. The invitations mostly include a detailed
description of the works, relevant drawings in some cases, including basic specifications, required
completion date, a contract format which has been cleared and agreed to by contracting
organization. The award is made to the contractor who offers the lowest price quotation for the
required work. In some cases as it was noted, the district officers also look at the contractor that
has the necessary experience and resources to successfully complete the contract.
21
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
In all cases looked at, it was noted that contractors are encouraged or obliged to employ local
people as labour wherever possible. The advantage also in this is that those involved in building
will benefit directly from the completed works. Apart from employment creation, quality in
construction is expected to be achieved when a private contractor is used. This approach,
however, robs the community of much needed experience.
Field assessment revealed that most of the projects visited have safeguards to ensure quality in
the services provided, materials procured and implementation of each particular project. Active
participation of district officers as well as the provision of a technical supervisor plays an important
role in guiding communities in the processes of labour provision within the community,
procurement of materials and construction.
Two areas where achieving standards is critical is the procurement of materials and the
construction process. In all the project areas visited, it was revealed that district officers, technical
supervisors or contracting organisations guide the group or committee to identify and select the
right materials for construction. Where procurement of materials is done by the community, the
community group or project committee members decide on the materials to be purchased and
nominate two to four representatives to be involved in the purchase of these materials. In some
cases like RIF, the agriculture extension camp officer is also a member of the procurement
committee. In case of other organisations such as ZAMSIF, the technical supervisor is the key
person. The committee conducts a market survey of manufacturers and authorized dealers
stocking materials needed and collects quotations from them. The approval process of collecting
the quotations varied among the projects, but were mostly at three levels, namely:
The district, contracting organisation or committee verifies the costs on the basis of the market
prices. ZAMSIF ensures that before the materials are dispatched from the dealer or supplier to
the community, the technical supervisor samples and looks at the quality of the material being
dispatched.
Lessons drawn from the field assessment reveal that the key to achieving high standard and
productivity norms lies in the following:
ZAMSIF was noted among all the organisations assessed to have high quality building
constructions undertaken by the communities themselves (see Figure 2 for a rural health centre
constructed by skilled labourers obtained within the community).
22
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
Payment procedures across the organisations involved in these projects had slight variations and
these related to the contract approach used, i.e. whether it involved skilled labour within the
community or a private sub-contractor. Table 4 presents payment systems used by the
organisations sampled.
23
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
Funding in most cases commenced once the project committee or group has opened a bank
account, solely for the project's use, and a copy of the relevant Financing Agreement, signed by
all parties concerned, has been received by the contracting organisation. It was established in the
study that some organisations disburse funds directly to the beneficiary community project bank
account. Others use the district which disburses funds.
The main area of concern with the communities was not the channel used for disbursement but
rather, the procedures and time taken to disburse the funds. Among the projects assessed, RIF
and JICA were the only two organisations who disburse funds in one lump sum. Other
organisations would disburse funds in installments. For instance, ZAMSIF would advance an
initial 36% of funds to the community project bank account. Thereafter, each successive
installment would be paid only after justification of 75 % of the previous installment and 100% of
all installments before that. Where a contractor is used, disbursements follow certification of
works and a retention fee is held until the end of the project.
Communities visited generally expressed a lot of negative than positive elements to the
installment payment systems. The major complaints noted were:
• There were delays in releasing funds in most cases. This often slowed down the
implementation process and the delay would at times be for long periods of time. The
implications of this are that the skilled labour hired or sub- contractor would lose interest as
well as money.
• Due to the delay in the release of funds, prices of materials would be higher than what is in
the bill of quantities due to high Inflation. This is also more likely to affect the pace at which
the project is implemented.
However, paying out money in installments can have positive elements. For example, it allows
groups or committees to gradually build their expertise in handling large sums of money.
Contract management, includes looking at the responsibility and contract requirements related to
activities that groups and project committees are obligated to perform. Contract management
hinges on the capacity of the group involved in community contracting. Except for ZAMSIF funded
projects, the other projects assessed lacked capacity building.
Financial control is another aspect to be considered. The committees have to bear financial
management, especially in relation to procurement of goods. If therefore, they lack capacity in
this area, financial management becomes a struggle. This is clearly so when the group is
managing a contract for the first time. All groups and committees talked to, except the RDCs,
indicated that it was their first time to handle a contract. Experience by the RDCs in Ndeke
community shows that, with time they have gained experience in the management of contracts.
24
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
One of the key assumptions when adopting a community contracting model in project
implementation is that along with the responsibility of the contracting agency, the community must
have the capacity to undertake community contracting.
Among the organisations visited, only ZAMSIF had a deliberate focus on building the capacity of
the project committees. ZAMSIF, through the Regional Facilitators and district officers, train
committees implementing projects. Capacity building is done in the following areas: training in
simple project management, bookkeeping, banking systems, gender issues, monitoring and
evaluation. A Project Implementation Manual is made available to all beneficiary communities.
Training is also provided to the technical supervisors.
Other organisations hold orientation sessions with the group or committee contracted to explain
the details of the contract or financial agreement and the roles and responsibilities of each
member. Other organisations, like Plan Zambia and CCF train the beneficiary communities in
PRA methodologies to assist them in the identification process of their projects.
It was clearly evident that communities who have not undertaken capacity building had struggles
in issues of contract management. For example, the case of Kabile school project led to
procurement of low quality materials due to lack of training in procurement processes and
financial management (see Box 5). The issue then is that, if responsibilities specified in the
community contracts have to be managed effectively, there is need to build the strength and
internal capacity of the community contractors in all key areas.
The project committee was contracted and was in charge of mobilizing, procuring,
implementing, monitoring and supervising the various activities. Prior to the start of the
project, the project committee had only been oriented to what their responsibilities
would be. This, however, did not involve any capacity building.
When it came to procuring materials the treasurer, secretary & chairman were
specifically responsible. The three got quotations based on the cheapest materials they
could get. The main reason for this was that they were trying to make savings. The
cheapest quotation was approved by the project committee. Materials were then
procured but were of very inferior quality. Because of the low quality of materials, the
school building was of very low standards. The community was initially happy but with
time they realized that the work was of poor quality.
To determine the level of gender considerations in the various steps of community contracting, an
exercise was carried out in some communities. Using a decision making checklist, the participants
were split into two groups, one comprising of women only and the other of men only. The two
groups were then each asked to distribute 10 points between women and men according to their
share in the activities of community contracting.
According to the findings of the 6 groups (3 groups of women and 3 groups of men) assessed,
there was gender balance in a number of processes relating to community contracting (see
Appendix 3). However, women’s participation was inadequate during the negotiation and
25
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
procurement processes. With regards to contributions, 5 out of the 6 groups revealed that women
made greater contributions to the carrying of sand, stones, while men’s involvement would only
be limited to moulding bricks. Of the 6 groups, 5 stated that men were more responsible for
community contracting than women. Related to this, it was pointed out by the 6 groups that men
were the ones involved in the signing of contracts. It was further revealed that, men were more
involved in maintenance work than women.
Areas that had equal participation by men and women: Identification of subprojects, training,
bank signatories, keeping funds and hiring of labour. Although there was equal participation
between men and women with respect to hiring of labour, one community felt this area should be
left to men because men are the only ones who are hired for skilled labour.
There is evidence that women are often more disadvantaged than men and, therefore,
should benefit more from direct support programmes. This point cannot be over-
emphasized in low income countries which tend to be characterized by, among other
things, inequality against women with respect to accessibility to productive resources
(including credit and land).
Programmes that take into account the gender dimension of transfer programmes tend to
benefit more household members due to the critical position women occupy in household
welfare. There is evidence that putting more resources under women’s control has a more
positive impact on household well-being.
Mobilization process
¾ The process by which communities identify, plan and manage subprojects should be
evaluated. There should be evidence of widespread support and participation within the
community. This is particularly important in projects with the specific objective of empowering
the community.
¾ Key organisations identified with potential to support community contracting should be tasked
to ensure that common interest of the wider community and other groupings or associations
are synergized.
¾ There should be a gradual move towards facilitating communities to negotiate contract sums.
This would allow committees to eventually build expertise in negotiation and other relevant
skills, including the capacity to handle large sums of money.
¾ There is need to have a more participatory approach towards negotiations. Participation of the
wider community was inadequate and only undertaken during project identification.
Participation of the marginalized groups should also be considered. It is important to identify
26
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
the views of the most vulnerable in the communities to ensure that they are represented during
the negotiation process.
¾ A simple but comprehensive framework should be created for negotiation to guide both the
contracting organisation and community based organisations in contracting processes.
Guidelines of negotiating and contracting should be developed and applied:
¾ The study revealed that groups and project committees recruit skilled labour through verbal
communication. Contracting organisations should assist communities design simple standard
contracts for hiring of skilled labour. Contracts should be simple but comprehensive, targeting
among others, the following areas:
¾ It was indicated by communities assessed that they prefer to recruit locally. Communities
should, therefore, be encouraged to recruit locally to avail them greater choice and bargaining.
While some organizations have made an effort to enforce this, it is not the case in most
organizations.
¾ Reliance on unpaid volunteer labor for public works initiative is not sustainable and leads to
confused responsibilities. The issue then is that contracting agencies should allow
communities to pay hired skill market value prices and not those determined by the contracting
organisations.
¾ A quality assurance system needs to be put in place and well developed for public works
development initiatives.
¾ Quality control should be maintained through external supervision. The ZAMSIF approach on
making a spot quality check of material reaching the community should be adopted in the
procurement of goods. Sub-standard materials should be rejected and the suppliers should
take responsibility for replacing them.
27
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
Payment systems/procedures
¾ According to the review, most of the organization’s financial procedures affected the releases
and resulted in delays in disbursements of funds to beneficiary communities. It may be useful
to negotiate with communities different financing packages that can be tailored to their
capacities to implement projects.
¾ Contracting organisations should take issues of timely disbursements seriously. For instance,
the approval process for funding should be shortened. In addition, every effort should be made
to ensure timely allocation and disbursement of budgeted resources. Disbursed funds should
be reduced to at the most two installments.
Contract management
¾ Contracting processes need to be simplified and improved upon for the committees and groups
to manage.
¾ There should be clear roles and responsibilities for those involved in contract management.
¾ There should be rules regarding the groups’ and committees’ accountability to the community
to make them more responsible for contract management.
¾ It is important to provide information to communities on contract management in areas where
communities are deficient such as:
– recruiting,
– managing contractors,
– procedures for community management, and
– rights and obligations that communities have to fulfill.
¾ One training model may not suit all community groups and project committees. Therefore,
considerations should be made to design training programs that are based on the assessment
of the community’s capacity.
Gender Considerations
¾ There should be need to identify and enforce specific roles for women in community
contracting. This process should include enhancing women’s involvement in negotiation
processes.
¾ Community contracting should be made to accommodate the needs of participating women, for
instance, by targeting periods they would be most free to participate in project activities and by
ensuring availability of technologies that are friendly to women.
¾ Most importantly, the development of a gender policy for community contracting should be
given much attention. This would provide a platform for local government and community
groups to incorporate gender concerns in community contracting.
28
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
29
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
The general findings from the study indicate that when community skilled labour is hired directly,
contracting organisations tend to largely reduce the cost of administration. In other words, the
cost of administering support becomes minimal when community contracting is channelled
through established community structures, such as the project committee. For instance, costs
going towards paying direct skilled labour from the community tend to be lower compared to fees
paid to a hired private contractor. On the other hand, the active involvement of community groups
or project committees in community contracting as opposed to partial labour or food-for-
work/asset approaches, has positive implications on enhancement of ownership leading to
improved sustainability.
5.1.2 Incentive costs
The participation of local communities in community contracting usually requires incentives aimed
at encouraging their participation. As an incentive, funds that are not utilised from the contract
sum should be given to the community to be utilised for other identified areas of need. This
approach provides the financing institution greater capacity to finance more projects because of
the savings that will have been made. This in turn leads to greater benefits accruing to the
community.
From the study, communities who were allowed to retain the unutilized funds were able to put the
money to good use, thereby benefiting the wider community. For instance, the Lukoshi camp (a
JICA funded community) managed the contract strictly resulting in savings which were used to
buy small livestock as an income generating activity. With the money generated, the project
committee was able to commit savings towards the improvement of community livelihood. For
instance, input and output marketing was supported by such a facility that was established.
5.1.3 Sustainability
Full participation of the community in the design and planning of public works development
initiatives provides an incentive to the community. It builds a deep sense of ownership which
leads to sustainability.
Community contracting enhances the use of local skills to the benefit of the whole local
community. It eventually leads to enhanced technical, administration and management skills,
critical for sustainable development. This will also benefit the local government in the sense that
skilled manpower will be readily available for future development initiatives.
30
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
One of the derived benefits between community contractors and the beneficiary community is the
generation of income. For example, one of the communities sampled had constructed a dam. The
water from the reservoir was further used to fill-up constructed fish ponds as well as for gardening
purposes. From the fish and vegetables sold, other community members were able to benefit.
The dam also generated benefits for cattle and other livestock owners. Similarly, in another
community visited, the installation of a grinding mill has resulted in benefits for the wider
community, as community members are now able to access the grinding mill easily saving time
which has a cost. The time spent walking long distances to a grinding mill has since reduced
thereby providing potential to engage in other productive ventures.
As opposed to food-for work/asset, direct community contracting approach also provides skilled
labour that gets a salary. At the end of the day money paid for skilled labour finds its way to the
rest of the community because the salaried community members buy food and other items from
within their local environment, leading to a boosted local economy.
¾ Delivery system: There is need for further work on improving grassroots level delivery
systems by, for instance, reviewing roles and responsibilities of various players at community
level, to ensure there are no gaps. Full community participation is a great incentive to
enhancing skills and is better achieved through direct hired labour than food-for work or partial
labour.
31
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
It was generally pointed out by community groups and project committees in this study that
artisan labour was readily available. The example provided of Chipindani community, is a case in
point, where skilled labour was provided by the community at both technical supervisory and
artisan levels.
Through the use of PRA exercises, communities are able to identify their key constraints,
prioritize them and identify appropriate interventions to deal with the identified constraints. The
communities are also able to engage in planning and implementation processes.
The cost sharing approach is an indicator of community participation. This approach is being
widely used by a number of development practioners in Zambia. The communities are ready to
choose their own development initiatives and thereby provide ready ground for community
contracting.
The fact that some communities have handled community contracts well despite so many
constraints demonstrates that there is a lot of potential for communities to do even better. Past
experience also shows that community managed projects may take long to implement, but they
are manageable and easy to control and, therefore, may hold greater potential for meaningful
local level sustainable development.
6.2 Constraints
Stakeholders do not have a forum where they can exchange information. There is need to have a
forum where contracting organisations and community organisations involved in community
contracting can share information and experiences.
32
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
Apart from ZAMSIF which has clear procedures, the rest of the organisations do not have any
existing mechanism to conduct training. Since most groups and committees involved in
community contracting are doing it for the first time, contracting organisations should have a
capacity building programme.
Due to lack of political will, government initiatives fail short of promoting community managed
contracts. There has to be a strong political will to encourage government agencies in drawing up
community based programmes so as to make community contracting more applicable to rural
areas. This can be in form of policy. Because this is lacking, external organisations dealing with
communities do not feel obliged to promote community managed contracts. Additionally, the
Government could also formulate and enforce community contracting guidelines.
Experience shows that present structures under which community contracting is undertaken come
and go with projects. This has made it difficult to retain experience and lessons learning due to
the lack of institutional memory. Consequently, building on lessons and experience tends to be ad
hoc and rather a big challenge.
6.3 Opportunities
6.3.1 Decentralization
This has a deliberate focus on engaging local communities. The Government has embarked on
building structures at district and sub-district levels that allow for more accountability of officials
and participation of district and community level players. An example of a sub-district level
structure is the ADC.
Due to decentralisation, various donors are now emerging and giving their support to these
emerging structures. Donors as well as NGOs are now able to actually reach the ground and
provide direct project support and resources to marginalized communities. Organisations that
have emerged and are using community contracting as an alternative to community
empowerment in Zambia include the following:
33
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
a) Organisational management and leadership. This should include: (i) the structure
and functions of the community contractor (or committee); (iii) strategy
implementation; (iv) co-ordination and control; and, (v) leadership and human
resource management.
¾ Training for enhancing community contracting: Some of the areas that need to be
dealt with include:
34
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
References
ILO ASIST Africa Regional Programme, Tournée J., van Esch W. Community contracts
in urban infrastructure works; pg 29; Geneva, International Labour Office, 2001.
Zambia Social Investment Fund, Operations manual, Ministry of Finance and Economic
Development, Lusaka, Zambia, March 2000.
35
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
Appendices
36
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
37
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
38
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
39
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
Classification Grade 1 2 3 4 5 6
Initial Application form 4.7 4.7 4.7 4.7 4.7 4.7
Renewal form 2.3 2.3 2.3 2.3 2.3 2.3
Initial Scrutiny Fee 93 46.5 23.3 11.6 4.6 3.5
Secondary Scrutiny Fee 46.5 23.3 11.6 5.8 2.3 1.7
for re-application and
renewal of Annual
membership
NCC Fee = Annual Fee 348.8 174.4 116 69.8 34.9 23.3
3
The ruling rate used is US $ 1 = K4,300 (October 2005)
40
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
[Note = Distribute 10 points between women and men according to their share in the activity]
Question Monze district Chongwe district Mumbwa district
Malundu women Malundu men Chipindani women Chipindani men Kabile women Kabile men
Women Men Women Men Women Men Women Men Women Men Women Men
Identification of subprojects 7 2 2 8 5 5 7 3 5 5 5 5
Responsibility for community contracting 5 5 4 6 2 8 2 8 2 8 0 10
Contributions? 7 3 7 3 8 2 5 5 6 4 6 4
Who is involved in the negotiation process 5 5 5 5 5 5 3 7 2 8 0 10
Who signs the contract? 5 5 5 5 5 5 1 9 2 8 0 10
Who is involved in training? 5 5 5 5 5 5 4 6 5 5 3 7
Who are the bank signatories? 5 5 5 5 4 6 5 5 5 5 3 7
Who keeps the funds? 5 5 0 10 5 5 6 4 5 5 4 6
Who decides what to procure? 4 6 5 5 5 5 2 8 4 6 2 8
Who procures it? 5 5 5 5 5 5 5 5 4 6 0 10
Who approves what is procured? 5 5 5 5 4 6 5 5 4 6 2 8
Who hires labour? 5 5 5 5 5 5 4 6 5 5 0 10
Who determines wage rates? 5 5 5 5 5 5 6 4 5 5 2 8
Who monitors & supervises? 5 5 5 5 3 7 1 9 5 5 3 7
Who is involved in the maintenance? 5 5 4 6 6 4 5 5 4 6 2 8
41
Community Contracting and Organisational Practices in Zambia and Malawi
A case study of Zambia
43