Beruflich Dokumente
Kultur Dokumente
University of Phoenix
Span System
Memo
To: Span Systems Management
From:
Date:
(C-S). The project was going as planned until Leon Ther of C-S brought forth a
dispute over the quality and schedule of deliverables. Keep in mind that this project
is worth $6 million. Leon Ther of C-S is claiming that Span Systems is in breach of
contract and asserted that C-S can’t afford schedule slips because of deadlines. He
has asked for immediate transfer of all unfinished code and has asserted the
rescission of the contract. I am writing this memo to brief all managers on how we
were able to amend some of the clauses within the contract and come to an
agreement with C-S. I will also briefly discuss some of the risks that associated with
this issue.
before all parties agree to the contract. Once agreed upon it is called concurrence of
wills and both parties are bound to the contract. One of the risks we took was
agreeing to a contract with uncertainties still present within the contract. In light of
this issue before we enter into another contract, Span Systems will have legal
personnel review and revise contracts until all uncertainties are clear and
After review of the original contract, we found several clauses that would have
been considered a breach of the contract. The first clause was a breach of
performance. The contract stated the neither party could cancel the agreement after
50% of the work was complete. The programming was well over 50% complete at
the time Leon Ther of C-S wanted to cancel the contract. One thing that Leon was
correct about was the quality of work. He had every right to cancel based on the
The clause that helped us the most is the Internal Escalation Procedure for
Dispute. This clause states that “prior to the filling of formal proceedings with respect
to a dispute, the party believing itself aggrieved (the “invoking Party”) shall call for
the other party” University of Phoenix. (2011). If this would have ended up in court,
C-S would have been in violation of this clause when Leon Ther called a rescission
of the contact. I would like all management to take note of how this clause helped us
negotiate a solution.
I would like to inform you on a clause that caused us the most trouble. The
possible within regular business hours. Due to the quality of the product this clause
may be used against Span because the clause was not clearly defined. The problem
began when C-S made changes to the project management structure, which caused
the need for change in the product. The changes were not in the original plan
therefor causing delays. Even thou the contract did state there would be scheduled
status meetings, the contract did not state how those status updates would be
I would like to conclude this memo on this thought. If this had gone to court, the
outcome would have been devastating to this company. We would have lost time,
money and one of best clients. Span Systems was able to renegotiate the contract
Thank you all for your time and dedication to this company
Heather Miller
HM
Project Manager