COMPLAINT
Plaintiff states:
4. Plaintiff has paid Defendant the sum of $35,000 pursuant to the contract.
7. Defendant did not complete construction of the building and advised Plaintiff on
[date], that it was unwilling or unable to complete the construction. Defendant also
did not replace the double-paned glass with triple-paned glass.
10. Plaintiff has been damaged by Defendant’s breach in the amount of $16,500,
which consists of the increased price Plaintiff has had to pay, plus the amount of
$9,500 in rent that Plaintiff had to pay for another greenhouse during the two and
one-half month delay that Defendant’s nonperformance caused.
PLAINTIFF REQUESTS that this court enter judgment in her favor and against
Defendant in the amount of $26,000, plus interest at the statutory rate from the date of
filing and that the court grant her such other and different relief as the court deems
warranted.
[Firm name]
By: /s/____________________________
Dated: ____________________ [Typed name of attorney] (P________)
Attorney for Plaintiff
[Address, telephone]