0 Bewertungen0% fanden dieses Dokument nützlich (0 Abstimmungen)
291 Ansichten5 Seiten
NDPL has a pool of 59 Grid stations operating at 66 / 33 KV level, 8500 RMU's and a population of about 9000 distribution transformers. It has standardized protection philosophy for all Grid equipments and developed its testing fleet with Latest testing devices. It provides the following to improve the reliability of the Power system network: faster operation of protection relays with correct indication along with real time stamping.
Originalbeschreibung:
Originaltitel
Protection Requirement for Power Distribution NDPL Case Studies
NDPL has a pool of 59 Grid stations operating at 66 / 33 KV level, 8500 RMU's and a population of about 9000 distribution transformers. It has standardized protection philosophy for all Grid equipments and developed its testing fleet with Latest testing devices. It provides the following to improve the reliability of the Power system network: faster operation of protection relays with correct indication along with real time stamping.
Copyright:
Attribution Non-Commercial (BY-NC)
Verfügbare Formate
Als DOCX, PDF, TXT herunterladen oder online auf Scribd lesen
NDPL has a pool of 59 Grid stations operating at 66 / 33 KV level, 8500 RMU's and a population of about 9000 distribution transformers. It has standardized protection philosophy for all Grid equipments and developed its testing fleet with Latest testing devices. It provides the following to improve the reliability of the Power system network: faster operation of protection relays with correct indication along with real time stamping.
Copyright:
Attribution Non-Commercial (BY-NC)
Verfügbare Formate
Als DOCX, PDF, TXT herunterladen oder online auf Scribd lesen
5th International Conference on Power System Protection and Automation, 8-9 December 2010, New Delhi.
Protection Requirement for Power
Distribution: NDPL Case Studies Consequently, it provides the following to improve the reliability of the Power system network • Faster operation of Protection relays with correct Nil indication along with real time stamping esh • Improvement in system restoration time with faster N. Corrective and Preventive Actions and defect Ka analysis. ne, • Efficient and Correct Fault Discrimination in S respective protection zones Na • Online Diagnosis and relay setting ved • IED with Protection/Control and Metering Function Ma soo d, No rth Del hi Po we r Fig. 1. Circuit Breakers as inherited Ltd .
Abstract— System reliability and availability is the main focus
of a Power distribution utility, thus Protection and control system and its timely and correct operation during faults is an important and crucial aspect in efficient and successful operation of Power distribution Utilities. Fig. 2. After GSAS: View of a 11KV Control and Relay I. INTRODUCTION Panel
N DPL has a pool of 59 Grid stations operating at 66/33 KV
level, 8500 RMU’s and a population of about 9000 Distribution transformers. Coordination of protection I. IMPLEMENTATION NDPL continually strived for excellence and in this process; functions is the most desirable aspect for the reliability of we explored numerous abilities of the existing IED’s that took network. our protection coordination to newer heights thus increasing Journey of NDPL comprises three main phases: reliability of our network. • Transformation from Erstwhile Power System to NDPL has standardized Protection philosophy for all Grid Automated Network. equipments and developed its Testing fleet with Latest testing • Implementation of Relaying (IED) features for devices. Improvement in System Reliability. NDPL has regularly reviewed its philosophy and amended • A Way ahead with utilization of special features of suitably based on field experience. Like recently we switched Numerical Relay’s for intelligent System Analysis and to line differential instead of Distance protection for better improvement in performance of the network. reliability of our short lines. A. Protection Philosophy and Standardization I. TRANSFORMATION Standardization has always helped in increasing the reliability NDPL has completed its GSAS (Grid Substation of the network. NDPL has developed a protection philosophy Automation Scheme) project in 2005 with all Grids were for allocating protections/schemes to specific commissioned/retrofitted with IED’s that were compatible to equipments/circuits. Following is the summary of the schemes SCADA used: This transformation from Electromechanical/Static to Numerical relays lead to better system reliability. 2 5th International Conference on Power System Protection and Automation, 8-9 December 2010, New Delhi.
S Secondary consumers. Relay coordination was very difficult with the
No Equipment Primary Protection Protection provided margins of around 300ms, esp. for high-set faults 1 Power Transformer Differential +REF O/C + E/F above 5 KA. Short Lines Line Differential O/C + E/F Fig. 3. Logic for Reverse Blocking scheme 2 Lines Medium+ Long Distance O/C + E/F To mitigate the problem, Reverse Blocking scheme was O/C + U/V + 3 Capacitor Banks Neutral Unbalance O/V introduced that provided us with enough time margins for better coordination. In case of any fault in Outgoing feeders, 4 11 KV Incomer O/C + E/F Reverse Blocking command is given by the associated relay to Series Trip 11 KV O/G feeders O/C + E/F Protection incomers/Bus-couplers to Block tripping of Incomers.
Table 1. General Protection schemes used at NDPL
Table 3. Reduction in tripping of 11KV incomer feeders NDPL has also developed its state of the art testing facility with latest equipments for Preventive and Predictive Reduction in 70% tripping of 11 KV Incomers along with maintenance along with testing facility for analysis during Outgoing feeders due to racing and attributed to High intensity breakdown checks. fault or Summation of faults developed on feeders in vicinity. NDPL also continuously strives for excellence in its maintenance activities; we have developed several algorithms that correlate results of various tests like HV tan C. Directional Protection for parallel feeders delta/LCM/DGA analysis with Residual life analysis for reliable analysis/protection of system equipments. Parallel feeders are protected with the help of a combination Various equipments used by NDPL are as given in table 2: of directional as well as non-directional relays; these are also helpful in cases where we have stiff margins in long feeders through a series of grid stations. S Equipment Application No 1 HV/LV tan delta Assessment of Insulation of Power It is worthwhile to mention that Tri-mode settings in Transformer 3 CT Analyzer Magnetic char. Of CT + ratio etc Directional relays are effectively used for protection of Line as well as Bus-Bar with proper coordination in grids where Bus 4 CRM/DCRM Breaker maintenance bar differential scheme is not present. 5 Omicron Relay testing NDPL has implemented Bus bar differential Scheme in 6 Wdg Resistance Meter Transformer some of the new 66 KV SCADA Compatible stations. 7 Transformer turns Transformer Ratio Meter D. Effective Distribution Protection 8 DGA Analyzer Transformer oil
Various characteristics like NI/VI/EI have been effectively
Table 2. Testing used from grid to RMU to accommodate stiffer relay setting Equipments and their application coordination of even 250ms and to address issues like B. Reverse Blocking – For Better Coordination Unbalance loading and recurring faults. Specifications of RMU Relays improvised with addition of In the vast network of our 59 Grid stations we have around additional elements and features like Inrush restraint eight hundred outgoing feeders operating at 11KV that feed experienced during on load charging. various Distribution transformers through a series of switching stations. It has been observed in 2002-03 that 11KV incomers tripped on a fault in outgoing feeders thus affecting bulk 3 5th International Conference on Power System Protection and Automation, 8-9 December 2010, New Delhi.
We did a number of projects that ensure maximum
utilization of the available inventory. Some of the projects are listed below: A. Transformer Monitoring Units
Reliability of supply is followed by Quality. TMU’s were
introduced to ensure voltage regulation at consumer’s end by operation of on load tap changers. Use of TMUs as IED in system has made the Transformer functionality more accurate and redundant one. Some of the important features of TMU are: • Voltage control/Regulation through various logics • High speed Forward Backward Switching of OLTC for Voltage control • Fan control through temperature settings. • Event log of the selected functions. Table 4. Reduction in escalation of tripping to Grid stations. • Recorder mode monitoring of OTI /WTI/ VOLTAGE/ CURRENT in Dual Parameters at a Time. • Correct calculation based on Algorithm for WTI with E. New Soft Logics for enhanced Protection input of OTI/LOAD OF Transformer/Winding exponent/Time constant of winding Soft logics are developed for saving on wiring/probability of wiring defects lead to evaluation of various fool proof schemes. A CBFP scheme was also designed with two stage fault Fig. 5. Improvement in voltage profile with TMU control. current detection for increased reliability. Introduction of OLTC concept lead us to increase in Tap change operations drastically that caused involvement of high maintenance costs along with equipment breakdowns.
A. Conditioning Monitoring of Lightning Arrestors
At NDPL we used to monitor the LA’s through regular
maintenance checks. During these checks following activities are done annually: • Visual Check • Cleaning • IR value of HV contact to earth (> 200 M Ohm) • LA leakage Current Fig. 4. CBFP logic with current discrimination. In addition to these activities Protection and Testing Some other schemes that are implemented for increasing Department has done a thorough monitoring of the following system reliability are: attributes to check the efficiency of the metal oxide arrestors • Integration of Back-up series trip relays in Numerical in service and to assist the Residual life analysis of the relay for SCADA Communication for understanding Lightning Arrestors operating at 66 and 33 KV levels. defects in unmanned grids. • True RMS of the total leakage current. • Effective use of Latched/Unlatched contacts of Relay • Peak value of the total leakage current. element- UV Element made self latched for effective • True RMS of the third harmonic. Reactive compensation with minimal manual intervention for capacitor switching. These online tests were performed by using a Metal Oxide I. EXPLOITATION OF AVAILABLE RESOURCES Surge Arrester Test Set (SCAR-10, make-ISA) which performs the tests according to IEC standards. NDPL tried it’s very best to exploit more and more of its Based on the test results, algorithms were developed that available inventory and assets to deliver the most cost helped us to categorize the whole fleet of LA’s into different effective and reliable power to its consumers. categories with different levels of attention for regular maintenance. 4 5th International Conference on Power System Protection and Automation, 8-9 December 2010, New Delhi.
A. Remote Relay Parameterization
Before commissioning of SCADA Central control in
NDPL, We were using Software’s available from different vendors to connect to their respective IED’s from remote locations. At that time we were able to have simple operational controls over the relays using that infrastructure. In 2007, we shift to SCADA Control to achieve uniformity and reliability. The control Station shifted to CENNET and now we are controlling our Grid stations using the new SCADA facility. The existing infrastructure of the older control system is now being used by us for Remote Relay Parameterization.
In this project we are connecting to the relays using the
infrastructure of the erstwhile Micro-SCADA Control for the Fig. 6. A view of Fault Studies on E-Tap software. following purpose: • Downloading of Fault Data Records B. Performance Measurement • Changing the Relay settings according to Power flow • Configuration changes in the relays • Mitigating issues pertains to n/w changes NDPL has developed and maintained a Performance Index of Protection since 2004 on a monthly basis. Protection ADVANTAGES OF RRP System Reliability has improved from 98.4% to 99.66% and reduction of uncoordinated tripping by 3-4 no’s every month. On successful full implementation of the above said project, NDPL also measures two other indices namely Reliability NDPL would be one of the very few distinguished Utilities to index and dependability index which give information about implement such a high end technique. Several advantages are equipment health listed below: • Downloading of Fault data from a central location save considerable amount of manpower and time that is currently used for this job. (There will be saving of about Fig. 7. Protection Performance Index: Benchmarking the 20-25 Km run daily along with daily saving of 8-10 man- Performance hours) • Relay settings can be changed quickly after any update in I. WAY AHEAD
NOC to save on MU’s lost in case of uncoordinated
tripping due to inappropriate settings. After stabilization of the Sub-transmission/Distribution network, we are in a process to explore further into higher A. Power System Analysis on E-Tap level studies of our network. We have done some very useful studies that played in important role in further strengthening our protection coordination and help us a lot in increasing With the increasing complexity of the network, fault levels system reliability. Some important studies are: need to be accessed and analyzed for coordinated relaying. NDPL is one of the very few Electrical distribution utility in • ∑KA2 Study of the data collected from various breakers India that analyzed its total network for fault levels using for analysis of their residual life. Algorithms were latest software’s like E-Tap and using the results for effective developed based on the tripping data that helped us a lot relay coordination. to reschedule our breaker maintenance activities. Relay coordination is been done using E-Tap software for perfect relaying on any type of fault. • Harmonic analysis of the NDPL network helped us to categorize different sections of our network with penetration of specific order of harmonics. In the second phase of the project we are trying to develop suitable filters to mitigate the effects of harmonics at places where they exceed IEEE limits.
• We have improved the reliability of the Protection System
By providing Dedicated Power Pack to extend uninterrupted Auxiliary Power to 11 KV Incomers. 5 5th International Conference on Power System Protection and Automation, 8-9 December 2010, New Delhi.
Fig. 8. A screenshot from a FDR analysis tool showing DC
• We have also developed intelligent use of Auto Re- ingress in Relay AC circuitry. closures to be used on certain 11 KV outgoing feeders for better reliability and availability of the network. • CT saturation leading to tripping on differential protection A New feature of the Numerical relay indicated that I. CASE STUDIES Transformer has tripped on Saturation Discrimination. Saturation of CT Cores causes flow of differential current through operating coil of the transformer.
It indicated that knee point voltage of PS Class CT Core has
got reduced due to Saturation. Difference of Saturation curve is indicated in Diagram. Fig. 9. FDR Analysis showing event of CT saturation There are many interesting case studies in which there was an intelligent usage of Relay features for faster restoration and reliability. Some of them are given below: • Tripping of 11KV incomer along with outgoing ACKNOWLEDGMENT feeders- Summation of Faults Even on successful operation of reverse blocking, it was Author thanks the management of NDPL for providing state observed that 11KV incomers are getting tripped along with of the art technology to help Protection and Testing outgoing feeders. Department in tackling with the ever-increasing complexity of On analysis, it was found that two of the feeders were the network. Author appreciate the valuable support and having simultaneous fault that was being fed by incomer even guidance of Mr. Ajai Nirula (COO, NDPL), Mr. R Pillai after the specified reverse block time. (Head Operational services), Mr. Sanjay Banga (HOD, Numerical relay DFR Analysis helped in timely analysis Automation and Network Engineering) and Mr. R.N. Kumar and field correction by pinpointing problems like Clearances (GM, HOD Protection and Testing Department) and the hard on Poles work of all the executives and technicians, without their hard work this quality experience would have never been a reality. • Mixing of AC and DC in relay Waveform of one of the particular event was showing that tripping was purely due to DC Component of the current in CT Circuit. It also shows that after decay of the DC Current Output REFERENCES relay got reset. It was confirmed that Tripping was due to [1] Distribution Arrester Research; M.V.Lat, J.Kortshinski; intermittent DC Ingress in Secondary of CT Circuit especially. IEEE Transaction on Power Apparatus and Systems, Vol. In modular type Duo-bias relay, two separate modules are PAS-100-No.7, July 1981. there for power supply as Well as CT Circuit. It was found [2] Tamil Nadu Electricity Board; Engineers Handbook. that DC is getting mixed up in CT Circuit within the relay. [3] IEC standard 60099-5 A1 ED. 1.0 Section 6: “Diagnostic CAPA Relay was got repaired for failure of the Isolation indicators of metal-oxide surge arresters in service – Method between two modules. B1 and B2” [4] International Conference IEC 61850; The Future of Substation Protection and Automation; “The introduction of IEC 61850 & its impact on Protection and Automation within Substations”
AUTHORS
Nilesh N. Kane S Manager at Protection and Testing Department, NDPL
S Naved Masood Executive at Protection and Testing Department, NDPL