Beruflich Dokumente
Kultur Dokumente
of Project Management
PMI-ISSIG Webinar
PMI-ISSIG Webinar
Presented
Presented By
By
Gopal
Gopal K.
K. Kapur,
Kapur, President
President
®®
Center for Project Management
Center for Project Management
One
One Annabel
Annabel Lane,
Lane, Suite
Suite 108
108
San
San Ramon,
Ramon, CACA 94583
94583
gkapur@center4pm.com
gkapur@center4pm.com www.center4pm.com
www.center4pm.com
1
© 1995 Center for Project Management® Rev: December 8, 2003
State Of IT Project Management
®
2
© 1995 Center for Project Management® Rev: December 8, 2003
7 Deadly Sins
®
3
© 1995 Center for Project Management® Rev: December 8, 2003
Sin 1: Half-Baked Ideas as Projects
®
EXEC
H-B Idea
Deadline
Manager
PM
T E A M
Progressive
ProgressiveRegression
Regression
4
© 1995 Center for Project Management® Rev: December 8, 2003
Filter Half-Baked Ideas
®
5 1
13% 1% 2
20%
4
17%
3
49%
Data
Datawas
wascollected
collectedat
atthe
theSF-PMI May
SF-PMI May2003
2003Regional
RegionalConference.
Conference.
7
© 1995 Center for Project Management® Rev: December 8, 2003
Sin 2: Inadequate Due Diligence
®
Reason:
Reason: Lack
Lack of
of due
due diligence.
diligence.
8
© 1995 Center for Project Management® Rev: December 8, 2003
Stakeholders
®
Policy Implementation
Project
Project
Management Customers
End-users
9
© 1995 Center for Project Management® Rev: December 8, 2003
Policy-Level Stakeholders
®
SH SH
Comatose Champion
SH Project Sponsor
Nemesis
SH SH
Champion Neutral
Those
Those who
who “shape”
“shape” the
the project.
project.
10
© 1995 Center for Project Management® Rev: December 8, 2003
Implementation-Level Stakeholders
®
SH SH
Comatose Champion
SH Project SH
Nemesis Nemesis
Expectations
Degree of
Change
SH SH
Champion Neutral
Level of
Readiness
Those
Thosewho
whowill
willbe
be“shaped”
“shaped”by
bythe
theproject.
project.
11
© 1995 Center for Project Management® Rev: December 8, 2003
Project proposals undergo appropriate and effective
levels of due diligence.
®
1
2
1%
9%
5
24%
3
25%
4
41%
Data
Datawas
wascollected
collectedat
atthe
theSF-PMI May
SF-PMI May2003
2003Regional
RegionalConference.
Conference.
12
© 1995 Center for Project Management® Rev: December 8, 2003
Sin 3: Ineffective Sponsorship
®
Sponsorship
Sponsorship means
means more more than
than
approving
approving the
the budget.
budget. ItIt means
means having
having
one’s
one’s “skin”
“skin” in
in the
the game.
game.
13
© 1995 Center for Project Management® Rev: December 8, 2003
Role of the Sponsor - A Partial List
®
Inflatable
Inflatable Sponsor!
Sponsor!
15
© 1995 Center for Project Management® Rev: December 8, 2003
Sponsors in my organization commit their political
capital, personal time, and resources to their projects.
®
5 1
9% 6% 2
13%
4
36%
3
36%
Data
Datawas
wascollected
collectedat
atthe
theSF-PMI May
SF-PMI May2003
2003Regional
RegionalConference.
Conference.
16
© 1995 Center for Project Management® Rev: December 8, 2003
Sin 4: Under Skilled Project Managers
®
“Why
“WhyInformation
InformationSystem
SystemProjects
Projectsare
areAbandoned:
Abandoned:
AALeadership
Leadershipand
andCommunication
CommunicationTheory
Theoryand and
Exploratory
ExploratoryStudy.”
Study.”EEffy
ffyOz
Ozand
andJohn
JohnJ.
J.Sosik,
Sosik,Journal
Journalof
of
Information
InformationSystems,
Systems,Fall
Fall2000.
2000.
17
© 1995 Center for Project Management® Rev: December 8, 2003
Project Manager Skills Survey - 47 PMs
®
Developing Compre-
hensive Project Plans Skill Gap
Developing Realistic
Skill Gap
Estimates & Sched.
Project Complexity
Tracking Project
Skill Gap
Progress
Managing
Skill Gap
Expectations
Managing The Team
Skill Gap
(Leadership)
0 1 2 3 4
Novice Expert
19
© 1995 Center for Project Management® Rev: December 8, 2003
Project managers in my organization have the necessary skills
to do their jobs effectively and efficiently.
®
1 2
2% 4%
5
39%
3
26%
4
29%
Data
Datawas
wascollected
collectedat
atthe
theSF-PMI May
SF-PMI May2003
2003Regional
RegionalConference.
Conference.
20
© 1995 Center for Project Management® Rev: December 8, 2003
Under Skilled PMs - Typical Solution
®
Mounting
Mounting afterburners
afterburners on
on aa mule.
mule.
21
© 1995 Center for Project Management® Rev: December 8, 2003
PM Skills Development Program
®
22
© 1995 Center for Project Management® Rev: December 8, 2003
Sin 5: Lack of a Robust PM Process
®
Project
ProjectProcess
ProcessArchitecture™
Architecture™(PPA
(PPA™
™))
Vision
66 Stages,
Stages, 33
33 Steps
Steps
Scalable
Scalable Model
Model
23
© 1995 Center for Project Management® Rev: December 8, 2003
Project Process Architecture™
®
Vision Project
Idea
Request
√ 1. Idea Statement
√ 2. Project Request
√√ Recommended
Recommended for
for all
all projects
projects
24
© 1995 Center for Project Management® Rev: December 8, 2003
Project Process Architecture™
®
Project Project
Pre-Launch
Request Charter
25
© 1995 Center for Project Management® Rev: December 8, 2003
Project Process Architecture™
®
26
© 1995 Center for Project Management® Rev: December 8, 2003
Project Process Architecture™
®
√ 27. Schedules
√ 28. Progress Review and Control
Between
Between 6060 to
to 70
70 percent
percent ofof project
project
effort
effort and
and time
time is
is spent
spent in
in this
this stage.
stage.
27
© 1995 Center for Project Management® Rev: December 8, 2003
Project Process Architecture™
®
Schedule Completed
Implement
& Track Project
28
© 1995 Center for Project Management® Rev: December 8, 2003
Project Process Architecture™
®
Completed
Operation Production
Project
29
© 1995 Center for Project Management® Rev: December 8, 2003
My organization uses a robust well-defined process
to manage its projects.
®
5 1
12% 4%
2
27%
4
23%
3
34%
Data
Datawas
wascollected
collectedat
atthe
theSF-PMI May
SF-PMI May2003
2003Regional
RegionalConference.
Conference.
30
© 1995 Center for Project Management® Rev: December 8, 2003
Sin 6: Not Monitoring the Vital Signs
®
Fantasy
% Complete =
Fantasy
George Glaser
Fantasy
% Complete =
Lie
Gopal Kapur
Percent
Percent Complete
Complete is
is Insidious.
Insidious.
31
© 1995 Center for Project Management® Rev: December 8, 2003
Project Vital Signs
®
1. Strategy Alignment
2. Customer Buy-In
3. Technology Viability
4. Sponsor’s Commitment and Time
5. Value-To-Business
6. Vendor Viability
7. Disposition of the Team
8. Status of the Critical Path
9. Milestone Hit Rate
10. Deliverables Hit Rate
11. Issues
12. Actual Cost vs. Estimated Cost
13. Actual Res. vs. Planned Res.
14. High Probability, High Impact Risk Events
15. Overtime Usage
32
© 1995 Center for Project Management® Rev: December 8, 2003
Vital Signs – Report Card (Example)
®
All is well
Run Away Condition
Shut Down Condition
AAWhite
WhitePaper
Paperononthe
thesubject
subjectis
isavailable
availablethrough
throughthe
the
Center’s
Center’sweb
website:
site:www.center4pm.com
www.center4pm.com
34
© 1995 Center for Project Management® Rev: December 8, 2003
Our project managers monitor a set of well-defined Vital Signs
of their projects.
®
1
2
2%
14%
5
32%
3
21%
4
31%
Data
Datawas
wascollected
collectedat
atthe
theSF-PMI May
SF-PMI May2003
2003Regional
RegionalConference.
Conference.
35
© 1995 Center for Project Management® Rev: December 8, 2003
Vital Sings - Benefits
®
36
© 1995 Center for Project Management® Rev: December 8, 2003
Sin 7: Absence of a Comprehensive Project
Portfolio
®
CEO Concerns:
How much are we spending on
projects?
Do the right projects get approved?
How many projects are being executed?
What is the status of the various
projects?
What is the total project capacity of the
organization?
37
© 1995 Center for Project Management® Rev: December 8, 2003
Project Portfolio Dashboard
®
II I II I
SG SG SG SG SG
1 2 3 4 5
Suspended
Expiration Expiration
Date Date IV III IV III
Request Charter Plan & Development Deployment Canceled
Estimate
Demand Capacity
SG Stage Gate
In Progress
Unaligned Project
Low Customer Buy-in
Schedule Overrun
Budget Overspend
Resource Under Allocation
Shutdown Condition
Portfolio Stress
39
© 1995 Center for Project Management® Rev: December 8, 2003
My organization has a well-structured project portfolio.
®
1
30%
2
70%
Data
Datawas
wascollected
collectedat
atthe
thePMI -ISSG June
PMI-ISSG June2003,
2003,San
SanAntonio,
Antonio,TX.
TX.
40
© 1995 Center for Project Management® Rev: December 8, 2003
Elements of Project Success
®
Vital Portfolio
Signs Management
Sound
Project Filter
PM
Success H-B Ideas
Process
41
© 1995 Center for Project Management® Rev: December 8, 2003
Absence of a Disciplined PM Process
®
Results:
– High “body count”
42
© 1995 Center for Project Management® Rev: December 8, 2003
References
®
43
© 1995 Center for Project Management® Rev: December 8, 2003
Center for Project Management™
®
Services
– ProjectSCAN™
– ProjectHALT™
– Executive Briefings
– Seminars and Workshop
– Consulting and Mentoring Services
– Tools and Templates
– White Papers
– Project Manager Certification Program
– Train-the-Trainer Program
– Best Practices Development and Deployment
Contact
ContactRaj
RajKapur,
Kapur,VP
VPSales
Salesat
at800 -510-1535, Ext.
800-510-1535, Ext.11
11
rkapur@center4pm.com
rkapur@center4pm.com
44
© 1995 Center for Project Management® Rev: December 8, 2003