Sie sind auf Seite 1von 110

INDEX

Page 1 of 110
Page: Page 2 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

SectionⅠ General Description of Boiler

ChapterⅠ The function of boiler

The production enterprise is called power plant. The simple flowing chart of the production
procedure of fossil fired power plant can be expressed by figure 1-1. Fuel is burning in boiler
1, the released heat will heat the water in boiler, and this water will be evaporated and
overheated into superheat steam with certain temperature and pressure. This superheat steam
will go into turbine2 through pipes. The steam will work in turbine by expansion and roll up
the steam turbine to rotate the generator 3 to generate electricity. After work in turbine, the
steam will be exhausted into
condenser 4, and cooled by the Superheat steam
cooling water supplied by circulating
water pump 11 into condensate
water. After rising pressure by
condensate water pump 5, this
condensate water will go into LP Making
up water
heater 6 to be heated. After removing
oxygen in deaerator 7, the pressure
of it will be raised by feed water
pump 8, and then it will be heated by
HP heater and then go back to boiler
to go on doing the above circulating
course. The heating source of water
in heater and deaerator comes from
the extraction 10 of turbine.

From the above circulation, we Cooling water


will know there is a energy
transformation course of three kinds
of energy in power plant: the 1—boiler 2—steam turbine 3—generator 4—condenser
chemical energy in the fuel is 5—condensate water pump 6— LP heater 7— deaerator
transferred into the heat energy of 8—feed water pump 9— extraction of steam turbine 10
steam in boiler; the heat energy of —circulating water pump
steam is transferred into mechanical Figure 1—1
energy in steam turbine; the Production procedure of thermal power plant
mechanical energy is transferred into
electric energy in generator. The important equipment in the course of energy transformation
---- boiler, turbine and generator are called three main equipments in fossil fired power plant.

Boiler is the most basic energy transformation equipment in these three main equipments in
fossil fired power plant. Its function is burning the fuel in boiler to release heat, and heat the
medium ---- water in boiler into superheat steam with enough amounts and certain quality
(temperature and pressure) to supply to turbine.

Page 2 of 110
Page: Page 3 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

ChapterⅡ Classification of boiler

Ⅰ. Classify according to the volume of boiler

Boiler is classified into small-scale, middle-scale and large-scale according to the evaporation
volume, but there is no fixed boundary between them. Along with the development of boiler
industry, the volume of boiler is increased gradually. The large-scale boiler in past is just a
middle-scale or even small-scale boiler in nowadays. According to the condition at present,
generally, D≤400t/h is considered as small-scale boiler, and D≥670t/h is considered as large-
scale boiler.

Ⅱ. Classify according to the parameters of steam

According to the pressure of steam, boiler can be classified into: low pressure boiler
(P≤2.45Mpa gauge pressure) / middle pressure boiler (P=2.94-4.92Mpa gauge pressure), high
pressure boiler (P=7.84-10.8Mpa gauge pressure), superheat pressure boiler (P=11.8-14.7Mpa
gauge pressure), critical pressure boiler (P=15.7-19.6Mpa) and supercritical pressure boiler
(P≥22.1Mpa) and so on.

Ⅲ. Classified according to the method of combustion

According to the combustion method of method in boiler is different, boiler can be


classified into: cyclone furnace boiler and fluidized bed boiler and so on.

Ⅳ. Classified according to the circulating method of water

According to the different source of the main power that make work medium flow on the
evaporating heat surface, boiler can be classified into natural circulating boiler, control
circulating boiler and once-through boiler generally.

Ⅴ. Vikram thermal power plant

The boiler used in Vikram thermal power plant is HP, natural circulating, small-scale fluidized
bed according to the above classification method of boiler.

The mode of the boiler used in Vikram thermal power plant is DGJ130/9.81-Ⅱ1; it is 130t/h
single drum, HP natural circulation, insulation cyclone separator, J valve back material
device, water cooling air room, full welding steel structure boiler support, circulating
fluidized bed combustion type boiler designed and produced by Dongfang Boiler Industry
Group Co., Ltd for M/s. Vikram Cement Indian.

Chapter Ⅲ The composition and principle of CFB boiler

Ⅰ The composition of boiler

Page 3 of 110
Page: Page 4 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Boiler is very complicated in modern thermal power plants, and it consists of boiler proper
and a series of auxiliary equipments.

Boiler proper is the main part of a boiler; it consists of a “pot” and a “furnace”. The “pot”
consists of economizer; drum, down comers, water walls, super-heaters and their accessories,
etc. its task is to make water absorb heat and evaporate it into steam, and become into certain
pressure and temperature superheat steam at last; the “furnace” consists of furnace chamber,
flue, firing equipments and air preheater, etc. so as to produce flame and flue gas with high
temperature. The flue gas produced in pulverized coal combustion will be discharged into
atmosphere after removing dusts.

Except boiler proper, ID fans, FD fans, exhausters, chimney, dust and slag removal
equipments, coal pulverization equipments, thermal instruments, and automation devices
belong to auxiliary equipments of boiler.

In order to pledge the safe and economic operation of boiler, some accessories as safety
valves, water level indicators, sootblowers, water level alarm, furnace protection, etc, are
equipped.

Ⅱ. The working principle of circulating fluidized bed boiler

The technology of circulating fluidized bed boiler (CFB) is a new technology development in
the 70th s. Its prime power is the appreciation for the environment protection of human
society. The technology of circulating fluidized bed is a kind of clean combustion technology.
Its special combustion way reduced the releasing amount of SO2 and NOx in coal fired power
plant that are the main source of air pollution in world, i.e. it solve the problem of acid rain
fundamentally. At the same time, the circulating fluidized bed boiler also has wide
conformance for fuel and good accommodation for load, and the investment and operation
cost are also lower compared with other. So this technology develops fast and strongly as one
of the three directions of the development of energy technology in the world.

Fluidization refers to the air flow cross the material on air arrangement device under certain
speed to make the particle of material contact with air flow to transfer into the state that is
similar with fluid. The type of fluidized bed is depended on the flow velocity on the section of
empty bed. Along with the rising of the velocity of air flow, the drag force produced by air
flow to the material particle in bed is balanced with the gravity and buoyancy worked on the
particles; the material in bed gets to rapid fluidized state from static bed condition through
boiling, 节涌 and turbulent state.

The technology of circulating combustion is developed on the base of boiling fluidized bed
combustion; the fundamental distinction of circulating combustion and boiling bed
combustion is that the multiple circulating combustion of solid material in fluidized bed is
realized. Vikram thermal power plant

The boiling fluidized bed is operated under the condition that the speed of the section of air
flow empty bed is lower than 2~3m/s, and there is obvious parting surface on the layer of bed.
After the speed of air flow is increased and exceed the speed of boiling, the lay of bed begin

Page 4 of 110
Page: Page 5 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

to expand, and a large amount of solid particle is thrown into the suspending space over the
bed layer, and the surface of bed lay tends to diffusion, and there is no obvious parting surface
at this time, but the concentration increased along the height of combustion room is lower and
lower. The air flow velocity inside of circulating fluidized bed is generally at 3.5-8m/s, the
mixture of the material in bed is uniform and the fluidization is stable. The material in bed is
brought out of furnace by high speed air, and it is caught by “air – solid” separator, and then
this part of material is sent into fluidized bed to combust again by material returning system.
After multiple circulation, the combustion efficiency of solid material is very high, and the air
flow with high concentration of dust strengthen the heat transformation; at the same time, the
temperature of bed is controlled by the pressure of bed and the arrangement of primary air and
secondary air so that the low temperature combustion at 850-950℃ is realized; the
productions of SO2 and NOx are also limited effectively by adding desulphurization agent and
adopting hierarchical air arrangement to make the emission of boiler meet the standard of
environment protection.

Ⅲ. The technological process of circulating fluidized bed boiler

The main component parts of circulating fluidized bed boiler are as follows:

 The main loop of the circulation of solid particle includes furnace, cyclone separator,
and material return device.
 Tail vertical shaft (include high temperature superheater, low temperature
superheater, economizer and air preheater)

In the technological process of circulating fluidized bed boiler, the combustion and
desulphurization take place at the bed lay whose temperature is lower that is composed by a
large amount of ash particle, and the improvement of combustion efficiency and the efficiency
of desulphurization should be taken into consideration in the choose of temperature. These
fine particles or solid particles is suspending in furnace supported by the ascending flue gas
stream produced by primary air through air arrangement plate, and the secondary air is
divided into two layers to send into furnace, so the hierarchical combustion can be realized.

After overwhelming majority of solid particles is separated from gas – solid flow by cyclone
separator, it will be sent back into furnace again and attend combustion. This forms the main
loop of circulating fluidized bed boiler. The characteristics of the main loop of circulating
fluidized bed are: strong disturbance and mixture, inside circulation and outside circulation of
high concentration of solid particle, high velocity of solid/ gas and longer staying time; the
above characteristic supplied good outside condition for heat transferring and chemical
reaction.

The good performance of reducing the pollution of SO 2 of circulating fluidized bed boiler can
be described as follow:

The sulfur in the coal used in circulating fluidized bed boiler reacts with the CaO in the coal
ash or the added limestone so that the desulphurization can be realized in furnace directly. The
limestone added in furnace is decomposed into CaO, and then CaO reacts with SO2 and
produce CaSO4, shown in following:

Page 5 of 110
Page: Page 6 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

CaO + CO2 CaCO3

CaO + SO2 + 1/2 O2 CaSO4

The best temperature of this reaction is about 850℃. The temperature of furnace should be
controlled at 850℃ when the changing range of load is larger. The hierarchical combustion
and lower temperature of furnace can reduce the emission of NOx farthest at the same time.

The characteristic of the technological process of circulating fluidized bed boiler are as
follow:

 The particle of material mixes uniformly and the temperature of bed distributes
uniformly.
 The fuel stays in furnace for longer time.
 Keep the temperature of furnace at the best temperature of removing SO2.

The above characteristic can guarantee the realization of following performances:

 The combustion rate of carbon is higher and the efficiency of desulphurization is


higher;
 Low emission of NOX and better conformance

Ⅳ. Integral arrangement of DGJ130/9.81-Ⅱ1type boiler

This boiler is single drum, natural circulation, circulating fluidized bed combustion way, and
it is out door.

The boiler is composed by one diaphragm water wall furnace, one insulation cyclone
separator and one heat recovery area (HRA) covered by steam cooling wall enclosure

There are two plates of platen superheater in furnace. There are two coal feeders and two
limestone feeding mouths in boiler and all of them are set in front of boiler and equipped at
the compressed section at the lower part of the water wall of front wall in the direction of
width. There is water cooling air room made by the pipes of water wall at the bottom of
furnace; it is connected with two sets of air duct igniters; and one oil igniter is arranged in the
air duct igniter.

Between the furnace and tail vertical well, a insulation cyclone separator is arranged here, and
a “J” valve material returning device is equipped under it. High temperature superheater, low
temperature superheater, economizer, and horizontal air preheater are quipped in tail vertical
well from up to down. There is secondary water jet attemperator is set in superheater system.

The whole boiler is symmetrical from its left side to right side, and it is supported by boiler
steel support.

Attached drawing 3 is the side view of boiler and attached drawing 4 is the top view of boiler.
The important structure sides and components are shown in these drawings.
Page 6 of 110
Page: Page 7 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Section Ⅱ Fuel and Combustion Equipment

Chapter Ⅰ Fuel

Ⅰ Coal

1. The composition of coal

The composition of coal can be researched by ultimate analysis method and proximate
analysis method.

The composition of ultimate analysis of coal include carbon (C), hydrogen (H), oxygen (O),
nitrogen (N), sulfur (S), ash (A), water (W). Carbon, hydrogen, and partial sulfur are
combustible, other parts are incombustible. Carbon is the main combustible component in
coal.

The proximate analysis method of coal includes water, volatile matter, fixed carbon, and ash.
The components of volatile matter have some combustible material such as CO, H2, CH4, H2S
and so on and incombustible material such as CO2, O2, N2 and so on.

The main characteristics of coal include heat value, volatile matter, coking property, grind-
ability, and ash melting point.

The coals used Vikram thermal power plant are ignite, Indian coal, imported coal, and coke.

2. The characteristic of fuel of Vikram power plant

Characteristic of fuel
Carbon Car % 29.82
Hydrogen Har % 2.41
Oxygen Oar % 10.69
Nitrogen Nar % 0.41
Sulfur Sar % 2.06
Water Mar % 50
Ash Aar % 4.61
Volatile matter Vdaf % 27.13
Low heating value LHV kJ/kg 10292
Grind-ability index HGI /
Characteristics of limestone

Page 7 of 110
Page: Page 8 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

CaCO3 % 75
MgCO3 % 3
H2O % 2
Other % 20

3. The combustion of fuel and limestone of two units of Vikram power plant

Item Performance Best Worst


lignite lignite lignite
The consumption amount of fuel per hour (t) 74 76.6 66.8
The consumption amount of fuel per day (t) 1776 1838.4 1603.2
The consumption amount of limestone per hour (t) 18.2 18.2 6.2
The consumption amount of limestone per day (t) 436.8 436.8 148.8
Note: The above data is calculated under the condition of the unit operates 24h/per day at 100%
BMCR.

Ⅱ. Fuel oil

The physical characteristic of fuel oil includes viscosity, solidifying point, flash point, ignition
temperature and so on.

Viscosity refers to the resistance produced by oil to the flow of itself; it can express the flow
characteristic.

The phenomenon of the liquid material is changed into solid state is called solidification, and
the temperature when begin to solidify is called solidifying point. The temperature of fuel oil
should be controlled above the solidifying point to avoid the solidification of fuel oil to block
the pipes.

When the fuel oil is heated to a certain temperature, oil vapor will appear on the surface of oil.
When the mixture of oil and air gets a certain concentration, if there is fire near them, the blue
light of fire will be produced and this blue light will disappear instantaneously. This
temperature is called the flash point of oil. The temperature of fuel oil should be controlled
under flash point to avoid explosion.

The oil vapor molecule on the surface of fuel oil trends to saturate when the temperature of oil
rises to a certain temperature. if the mixture of it and air reaches certain concentration and
there is fire nearly, it can be burned and continuous combustion can be kept. This temperature
is called ignition temperature.

The under bed ignition method is adopted by Vikram power plant. 0# light diesel is used in
ignition. The parameters of the oil used in ignition are as follows:

Serial No. Analysis item Unit Standard requirement


1 Kinetic viscosity (200C) m2/s 3×10-6~×8×10-6

Page 8 of 110
Page: Page 9 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

2 Low heating value kJ/kg 41868


3 Flash point in closed up ℃ No less than 65
4 Solidifying point ℃ 0
5 Ash % No more than 0.025
6 Sulfur % No more than 0.2

Chapter Ⅱ Coal preparation equipment and coal feeding equipment

Ⅰ. Coal crusher

Two reversible hammer coal crushers are set in the coal crushing part in the coal conveying
system in Vikram power plant; one is operating and one is standby. After crushing, the coal
will go into the sieve equipment to sieve, and then it will be sent into the coal conveyor in
next section, and the coal left on mesh will be sent back to the inlet of crusher by bucket
elevator to crush again.

The graininess of fuel after grading should satisfy the following requirements:

Size of grading Petroleum coke Imported coal Indian coal and ignite Limestone

The percentage left on sieve (total accumulation)

+ 90 mm 0.0 0.0 0.0 -

+ 75 mm - 4.12 20.64 3.0

+ 60 mm 1.91 8.87 12.5

+ 50 mm - - 35.58 15.0

+ 40 mm 2.56 14.16 41.21 23.0

+ 32 mm 5.47 22.74 - 32.0

+ 25 mm 25.93 30.14 46.53 38.0

+ 20 mm 34.62 41.62 - -

+ 12.5 mm - - 53.56 -

+ 10 mm 51.32 58.55 - 65.0

+ 6.3 mm 60.48 68.90 68.38 80.0

+ 4.0 mm 69.37 75.89 71.08 -

+2.8mm 74.71

+ 2.0 mm 80.46 81.65 94.0

Page 9 of 110
Page: Page 10 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

+ 1.0 mm 85.00 85.00 84.00 95.0

Ⅱ. Coal feeding equipment

The coal feeding equipment has coal bunker, limestone silo, coal feeder, and pneumatic
conveying device.

1. Coal bunker

The main task of coal bunker is coal storage and guaranteeing the necessary amount of coal
needed by coal feeder. In design, the volume of coal bunker can be used by boiler for
supporting 6~8 hours continuous operation.

The coal bunker is arranged from 27.5m to 1m in front of coal feed in Vikram thermal power
plant. It is divided into two parts: the first one is used for petroleum coke/ limestone, and the
other part is used for Indian coal/ imported coal; and the effective volume of every part is
300m3. Coal bunker is reinforced concrete structure and SS304 inside lining whose min.
thickness is 3mm is set at cone.

Limestone bunker is placed in front of coal feeder from 27.5m to 15m. It is divided into two
parts, and the effective volume of every part is 171m3. It can meet the required amount of
limestone under the condition of boiler is operating for 18.8 hours under BMCR. The
limestone bunker is reinforced concrete structure and SS304 inside lining whose min.
thickness is 3mm is set at cone.

2. Coal feeder

The task of coal feeder is mixing the raw coal that has be produced and has proper grading
with limestone and sending them into boiler to burn.

Coal and limestone is mixed inside of coal feeder. Four fully-enclosed electronic weighing
belt coal feeders whose accuracy are set 15meters layer for every boiler; and the amount of
coal feeding is changed depending on the rotating speed of pole slip operating motor. The
compatibility of this kind of coal feeder is good, and the amount of conveying is large, the
structure of it is simple, the maintenance of it is easy, and the cost of it is lower; the new
closed box structure is suitable for the operation under positive and negative pressures. The
shortage of it is the wearing of it is serious, its belt is sliding and easy to deviate, and it is easy
to leaks coal and so on. Coal feeder is installed at 15.00m place of BC span in main factory
building. Two coal feeders in every lay whose length are same should be arranged
symmetrical.

3. Pneumatic conveying device

Two pneumatic coal distributed devices are arranged at the lower part of the front wall of
furnace along the direction of width. After fuel goes into conveyor belt from coal bunker, it
falls down into wind power distributed device by gravity. Three coal distributed wind streams

Page 10 of 110
Page: Page 11 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

arranged under coal distributed device blow the fuel into furnace to combust. This coal
distributed wind is supplied by boost air fan.

The inner wall of coal feeding chamfer is spliced by 1Cr18Ni9Ti stainless steel plate.

Chapter Ⅲ Combustion Equipment

Ⅰ. Furnace

The furnace of Vikram Thermal Power Plant is 26554 mm (height) ×5791.2mm (width) ×
5791.2mm (depth) combustion chamber; it is composed by front wall, rear wall and two side
walls. At the bottom of furnace, the pipes of rear become sparse and from the bottom of air
room and the air arrangement plate of fluidized bed, which form the water cooling air room
with the water walls at two sides; the elevation of air arrangement plate is 7000mm; at the top
of furnace, the front wall is bent to the back of furnace to form the top of furnace; and the
pipes is connected with the outlet header of the water wall of front wall behind the furnace;
the highest elevation of the top of furnace is 51228mm. A down header of the water wall of
front wall and a bottom header of water wall of air room at the same level are positioned at
the place of 5000mm elevation at the lower part of furnace; there is one outlet header of the
water wall of front wall, and also on outlet header of water wall of rear wall, the elevation of
them are 38860mm; one up header and one down header are set for every side wall; the
elevation of the down header of side wall is 5000mm, and the elevation of the up header of
side wall is 38460mm. The whole furnace can be divided into three parts: up, middle, down.
Take 15511.1 elevation as boundary, because the water wall of front wall and rear wall
intersect the horizontal level to form 80°angle and then form a trapezoid. At the horizontal air
arrangement plate whose elevation is 7000mm, the depth of furnace is 2895mm. Wearing
material is laid on the water wall at the down density phase area, rear wall near the outlet of
up flue gas, two side walls and roof to avoid wearing, and the thickness of this wearing
material is 51mm (to the central line of pipe). The boiler water is sent to every loop from
drum by two central draining water pipes.

The pitches of the pipes of front wall (including the top of boiler), rear wall and the water
walls at two sides are 76.2mm, and the sizes areΦ51. The pipes of front wall and rear wall are
75, and the pipes of two side walls are 75. The air distribution plate is composed by 38 inner
screwed pipes whose pitches are 152.4mm and sizes areΦ63.5; the bottom of air room is
composed by 38 pipes membrane wall whose pitch is 152.4mm and size is Φ51. The sizes of
the outlet and inlet headers of all water walls are Φ219.

Two coal feeding openings and two limestone openings are set at the front wall of furnace
above air distributed plate. Two rows of secondary air openings are installed at the front wall
and rear wall of furnace; there are 5 up secondary air opening at single side, and 6 down
secondary air opening at single side. There are three ash extraction openings installed evenly
at the bottom of furnace, the middle one is emergency ash extraction opening; the outlet of
flue gas of furnace is at the top of rear wall.

Ⅱ. The flue gas duct at the inlet of cyclone separator and cyclone separator

Page 11 of 110
Page: Page 12 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

One inlet flue duct of cyclone separator is installed in boiler. It connects the outlet of flue gas
of back wall of furnace with cyclone separator, and form a air seal flue gas duct.

The upper half part of cyclone separator is cylinder, and the lower half part is cone. The outlet
of flue gas is cylindrical steel plate forming a cyclone whose end is opening and whose length
will reach the certain position of cyclone separator. The fine particle and flue will flow to the
bottom of cylinder, and then flow awards to leave cyclone separator. The coarse particles fall
into the vertical pipes connected with J shape material returning device directly.

The cyclone separator is adiabatic type structure, wearing layer is laid inside of it, and its
thickness is 350mm. The size of cyclone separator isФ2576, and it is made by high strength,
anticorrosive, wearing Durimet RA-253MA steel plate.

Ⅲ. Lighting-up burner

Two air duct igniters are installed under bed for every boiler in Vikram Thermal Power Plant;
the heat capacity of ignition burner is designed according to 30% BMCR output; and it is
arranged at 5785mm elevation place of two side walls. The fuel used for ignition is fuel high-
speed diesel oil, and the oil gun is mechanical central oil back type, there are two oil guns.
The rated capacity of single oil gun is 1350kg/h, and the designed air amount of single burner
is 40380Nm3/h.

Ⅳ. “J” valve material returning device

The bed material and ash separated by steel plate type cyclone separator flow downwards
through back material vertical pipes laying fire-resistive material and are discharged to “J”
valve. “J” valve material back device is installed under cyclone separator, and it is supported
on the beam of framework. The connection between separator and material returning device,
material returning device and lower part furnace are flexible expansion joint connection. It
has two key functions: make the re-circulating bed material return to furnace continuously
and stably from cyclone separator; supply seal between the negative pressure of cyclone
separator and positive pressure of lower burner. The static pressure of separator is very near to
the atmospheric pressure, the pressure of the material returning point of burner is very high
because of primary air, so the seal between them must be supplied, or the flue gas of burner
will flow back to separator. This seal is realized by building material level in vertical pipe by
the material at the outlet at the bottom of separator by J valve. The air used by material
returning device is send by individual HP J valve, the J valve air goes into J valve through the
bottom air tank and the four layers of aeration mouth, the aeration pipes on every layer have
their own air amount measuring point that can show exact flow. The air distribution is
adjusted by manual and motor-driven governing valves to realize sending certain amount of
air. Pressure measuring point is set on vertical pipes to realize the monitor for material level.
The making up inlet of startup material is also set at the top of J valve. Emergency ash
removing opening also set at the bottom of J valve material returning device used to remove
the ash and slag under the condition of repair and emergency condition; it is not included in
ash removing system.

The “J” valve material running device and material returning vertical pipe are made by steel

Page 12 of 110
Page: Page 13 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

plate laying wearing and adiabatic layer whose inner diameter is ∅1120mm.

Section Ⅲ Principle of Circulation of Natural Water and Evaporation


Equipment

Chapter Ⅰ Composition and principle of natural water circulation system

Natural water circulation system is the important composition part of steam boiler. It is
composed by drum, down comer, water wall, header and connected pipes. Its task is absorbing
the heat released by fuel and making the saturated water become saturated steam.

In the circulation loop composed by drum, down comer, header, ascension pipe (water wall)
and so on, the ascension pipe is heated in boiler, the water is heated to saturated temperature
and produces a part of steam; the down comer is set at the outside of boiler and does not
heated, the water in pipes is saturated water or non saturated water. So the density of steam
and water mixture in ascension pipe is smaller than the density in down comer, and that will
produce differential weight of liquid bar at two sides of the center of down heater. It will
thrust the mixture of water and steam moves award along the ascension pipe, and the water
moves downwards along down comer. The movement of working medium in the loop from
drum, down comer, down header, ascension pipe, up header, to connected pipes and then to
drum is caused by its differential density. So this kind of circulation of working medium is
called natural circulation.

ChapterⅡDrum

Ⅰ. The function of drum

Drum is one of the most important equipments in natural circulation boiler. It is connected
with the outlet pipe of upper header of water wall, outlet pipe of economizer, and the outlet
pipe of centralized down comer and the outlet pipe of saturated steam. In one hand, it
composes the circulation loop for evaporation; in the other hand, it accepts the feed water
coming from economizer and sends saturated steam to superheater. So it is key position for
the connection of heating, evaporation, and superheat. It is a cylinder shape metal container
collected boiler water and saturated steam, has certain heat storing and relief ability.

Ⅱ. The arrangement of drum and the inside structure

The drum in Vikram Thermal Power Plant is positioned at the middle of the top of boiler
across the width of boiler. Separating device, dosing medicine pipe, feed water distribution
pipe and blowdown pipe are installed inside of it. The setup inside of drum is shown in

Page 13 of 110
Page: Page 14 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

appendix drawing 7. The inner diameter of drum is 1600mm, the length of the straight section
of drum is 5m (not include ball shape head). The main equipments inside of it have:

 Horizontal steam and water separator-----totally 32, arranged in two balanced row
 Dry tank -----“W” type vertical wave plate dry tank, totally 12..
 Distributed pipe of feed water ---- single end of feed water pipe is leaded into drum,
and two multi hole water distributed pipe along the length of drum is connected out
of it using three-way valve.
 Continuous blowdown pipe ---- it is multi hole pipe, and it is leaded out from one
end after merging into single pipe in the middle of drum by three-way valve.
 Dosing pipe ----- It is multi hole pipe, and it is leaded out from one end after merging
into single pipe in the middle of drum by three-way valve.

Arc dampers are installed along the straight part of the whole drum and these arc dampers
form a jacket room at the lower half of drum. The mixture of steam and water coming out
from the outlet pipe of water wall goes into this jacket, and then goes into horizontal steam
and water separator to separate, the steam goes into the upper room through central guide pipe
and then goes into drying tank; water goes down to the bottom of drum through drainage
outlet and iron wire net along water wall. The iron wire net reduces the kinetic energy of
draining water and make the brought steam overwing to steam room. The second separation
of steam is finished in drying tank. Because the flow velocity of steam gone into drying tank
is lower, and the direction of steam flow changed suddenly for many times, the water droplets
brought by steam can adhere on the wave plate better and these water droplets can flow to the
bottom of drum by gravity. After second separation, the steam will go into steam collection
room, and it will be guide out by the connection pipe at the top of drum. The separated water
goes into drum, and goes into the centralized water draining pipe through anti-eddy device to
attend the next circulation.

Ⅲ. The water level in drum

The water levels of drum can influent the safe operation of boiler. The water level of drum is
controlled by adjust the feed water pump or the governing valve of feed water by operator.
The normal water level of boiler in Vikram Thermal Power Plant is at 76mm below the central
line of drum. The long-time operation under the condition of higher or lower this water level
will influent the performance of separator. If the water level of drum is 125mm higher than
normal water level (the highest safe water level or high alarm water level), DCS will alarm; if
it is 200mm higher than normal water level (The Max. highest water level or high water level
trip), the boiler will be shutdown by itself. High water level will flood the horizontal separator
and the ability of separating steam and water will be reduced; the low water level also can
reduce the efficiency of separator. The wet steam will leave the drum and go into superheating
system. If the water level in drum is 200mm lower than the normal water level (the lowest
safe water level or low alarm water level), DCS will alarm; if the water level is 280mm lower
than normal water level (lowest lowest water level or low water level trip), the boiler will be
shutdown by itself. The moisture in steam will make the solid impurities deposit on the pipe
wall of superheater and the blade of steam turbine, that will influent the safe and economic
operation of power plant seriously. So the operator should monitor the water level of drum
usually.

Page 14 of 110
Page: Page 15 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Ⅳ. Water level indicator

In order to monitor and adjust the water level and guarantee the normal water level, various
kinds of water level indicators are installed on drum.

a. Local close-up water level indicator

The local visual water level indicator is equipped near the drum of boiler. The steam and
water guide pipes are equipped in the steam and water room in drum to the outside of drum,
and then these steam and water pipes are connected and form a closed connecting device.
Transparent material such as mica is set in connection pipes, which can reflect the real water
level of drum visually. It is real and reliable.

No bland zone double color water level indicator is equipped on the drum in Vikram Thermal
Power Plant. They are installed at two sides of boiler, there is one at every left end plate and
right end plate as lock water level indicator to monitor and check the water level of drum.

b. Differential pressure type water level indicator

The differential pressure water level indicator transfers the water level signal into differential
pressure signal by a balanced container, and then it will be reflected by differential pressure
meter, thus we can know the water level and the varying condition.

Two double room balanced containers are equipped on the drum of boiler in Vikram Thermal
Power Plant, and there are one on every left end plate and right end plate. It is used with
differential pressure transmitter together to monitor the water level of drum and output the
differential pressure signal when the water level is changed.

c. Remote level indicator

The remote level indicator measures the water level based on the difference of the
conductivity of steam and water. After the electrode of water level container is powering, it
will transfer the water level signal into electric signal. Electrode will become water level on
water level container. The insulation between the core of electrode and cover of water level
container should be good. Because the conductivity of steam is very small, and the resistance
is big, the electric circuit of the electrode in steam is blocked. The conductivity of water is
big, and its resistance is smaller, the electrode immersed in water connects with the shell, the
AC current will bright the indicating light by water. So the water level decides the amount of
electrodes immersed in water. If the water level is high, the electrode immersed in water will
be more, and the bright indicating lights will be more. We can know the water level from the
amount of bright indicating lights.

Remote level indicator is equipped on the drum of boiler in Vikram Thermal Power Plant, and
it is equipped at two sides of the drum of boiler. One is equipped on left end plate and one is
equipped on right end plate. There are 19 electric junctions, and there also have the functions
such as visual and audible alarm, output of lock out signal and so on as the alarm, indication,
and protection of water level.

Page 15 of 110
Page: Page 16 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Chapter Ⅲ Water wall and down comer

Water wall is the important steam heating surface that is arranged around the furnace, top of
furnace and air arrangement plate. Water wall can absorb the radiating heat released in the
combustion of fuel in furnace, and then transfer this heat to the water or mixture of steam and
water in pipes to evaporate a part of water. The pitch between the pipes of the water wall of
front wall (including the top of furnace), rear wall and side wall of boiler is 76.2mm and the
size of it is Φ51mm. The pipes of front wall and rear wall are 75 respectively; the air
arrangement plate is composed by 38 inside screw pipes whose size is Φ63.5mm pitch is
152.4mm. The bottom of air room is composed by 38 Φ51mm whose pitch is 152.4mm. the
sizes of the outlet and inlet header of all water wall are Φ219mm.

Down comer is an equipment that can send the water in drum into the down header of water
wall and then into water wall continuously without interruption. Two pipes that can lead water
into every down header of water wall respectively are adopted by the boiler in Vikram thermal
power plant. The arrangement of the centralized down comer and draining water connected
pipe are shown in attached drawing 8.

Chapter Ⅳ Economizer

Ⅰ. The function of economizer

Economizer is a kind of equipment that uses the heat energy of fuel gas at the end of boiler to
heat the feed water. After adopting economizer, the Gas temperature leaving AH is reduced;
and the temperature of feed water is increased; the material is saved, and the differential
temperature between feed water and the wall of drum is reduced.

Ⅱ. The arrangement of economizer

The economizer in Vikram thermal power plant is arranged inside of the vertical well of
boiler, and it is composed by three horizontal pipes; the pipe is Φ32 SA-210M A1 bare pipe;
there are 76 sheets along the direction of width, and the horizontal pitch is 74, and it is
arranged in the type of two cycle in-line position.

The routine wearing protection measures adopted by the pipes of economizer: current
distribution plate is equipped between the inlet of pipe team of economizer and the walls
around to prevent flue gas from deviating; the pipes in the front row of every pipe team adopt
wearing cover plate.

The feed water is led from the left side of inlet header and flows through the pipe team of
economizer, and it is led into drum through connecting pipe at the right side of outlet header
at last.

Ⅲ. Recirculation of economizer

Because economizer is heated equipment, after shutdown or when the water is not supplied in

Page 16 of 110
Page: Page 17 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

the beginning time of starting up boiler, in order to avoid static vaporization of the water
inside of the pipes of economizer, the re-circulating valve of economizer should be open using
the water in drum to cool the economizer. One end of the re-circulating pipe of economizer in
Vikram Thermal Power Plant is connected with down comer and the other end is connected
with the distributed header of the inlet header of economizer. A motor-driven valve is installed
on this pipe. It is closed when the operation of boiler is normal to prevent the feed water from
going into drum directly and avoid threatening the safety of economizer and drum.

Chapter Ⅴ Feed water system

Feed water system is the important compositing part of drum. It is composed of feed water
pipe, economizer, drum, re-circulating pipe and relevant parts. Its task is supplying water to
boiler and absorbing the heat of flue gas to improve the temperature of feed water.

The feed water of the boiler in Vikram Thermal Power Plant is guided to the inlet header of
the economizer in tail flue duct firstly, and then the feed water refluxes upwards into the outlet
header through the pipe teams of economizer that are horizontally arranged, and then the feed
water goes into drum from the right end plate of drum through the guide out pipe of
economizer

The feed water coming from machine side should be inducted into control desk of feed water.
The adjustment and control of boiler feed water are realized by the control desk of feed water.
There are three feed water pipes on the control desk of feed water in Vikram Thermal Power
Plant; and motor-driven stop valves, motor-drive drop gates and governing valves are
equipped on every feed water pipe to control the feed water of boiler.

Before the feed water pipes are put into operation, the air valve and the air vent valve to
atmosphere on steam header must be open, and other valves on pipes must be closed. Then
start up the feed water pump and open its outlet valve to feed water; this valve cannot be
closed until water overflows the dewatering outlet. In addition, when switch over the feed
water pipes, the motor-driven valve of the feed water pipe that is prepared to put into
operation must be open first and then the motor-driven valve of the feed water pipe that is
prepared to stop using can be closed.

The switchover procedures of feed water pipe are:

A. Open the motor-driven valve of feed water pipe that is prepared to put into operation.

B. Turn down the governing valve of feed water pipe that is prepared to stop using, and turn
up the governing valve of feed water pipe that is going to be put into operation till the
governing valve of the feed water pipe that is going to stop using is closed completely. The
flow of feed water should be not changed.

C. Close the motor-driven valve of feed water pipe that is prepared to stop using.

Chapter Ⅵ Blowdown of Boiler

Page 17 of 110
Page: Page 18 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

The feed water gone into boiler has salt content, and the boiler water will corrode the boiler to
produce corrosion product. So, the boiler water will contain various dissolved and un-
dissolved impurities more or less. Although the impurity content and corrosion produce in the
feed water of boiler is very small, but the salt content brought away by every kilogram of
steam is smaller than the salt content brought in by every kilogram of water. So the amount of
salt and water dross will be increased gradually along with the evaporation of boiler water.
The too big salt content in boiler water not only pollutes the steam but also scales on the
heating surface of water wall or even corrodes the heating surface.

In order to maintain the salt content in boiler water in allowable range, a part of boiler water
should be discharged in operation, and some clear feed water should be supplied into boiler to
instead of this part of boiler water in order to remove a part of salt and water dross. This kind
of method is called blowdown.

Blowdown of boiler is one of the most important methods to improve the quality of steam. In
power plant, there are two blowdown methods: periodic blowdown and continuous
blowdown.

Periodic blowdown is done at the down header under the water wall of boiler. Its task is
removing the water dross accumulated at the lower part of boiler and the soft deposition
produced after phosphate treatment. The time of periodic blowdown is very short, but the
ability of removing the deposition in boiler is very strong.

The continuous blowdown can blowdown the boiler water whose thickness is biggest from
the surface of boiler water continuously. Its aim is reducing the salt content in boiler water
and preventing the too high thickness of boiler water from affecting the quality of steam.

Page 18 of 110
Page: Page 19 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Section Ⅳ Superheated and Steam Temperature Adjustable Equipment

Chapter Ⅰ Superheater

Ⅰ. Classification of superheater

Superheater is the important compositing part of boiler. Its function is heating the saturated
steam coming from drum to superheated steam with certain temperature and pressure. The
superheater can be divided into three kinds: radiation, half radiation, and convection
according to the different heat exchanging methods. The arrangement of superheater can be
divided into three ways: co-current, countercurrent, and mixed-flow according to the relative
direction of steam and flue gas.

Ⅱ. The working characteristics of superheater

The working characteristic of superheater is called steam temperature characteristic; it refers


to the variation relationship between the load of boiler and the temperature of steam.
Generally, the temperature of the steam of convection superheater will be increased along
with the increasing of load. When the load is increasing, the consuming speed of fuel is
accelerated, and the heating transferring ratio increase; the temperature of flue gas of the
outlet of furnace increases too, so the differential temperature of heat transformation is
increased. The heat absorbing amount of unit steam increases, so the temperature of
superheater steam rises.

The steam temperature characteristic of radiation superheater is that the temperature of steam
will be reduced if the load is increased. When the load is increased, the amount of steam will
be increased; the radiation heat obtained by radiation superheater is not increased along with
the increase of steam amount in direct proportion; the amount absorbed by unit steam reduces
so the temperature of steam is reduced.

Ⅲ. The flow of superheater system

In Vikram Power Plant, after leading out from drum, the saturated steam is leaded into the
upper header at the inlet flue duct of insulation cyclone separator by saturated steam
connected pipes; it goes into the down header of the inlet duct after going downwards into
cooling flue duct; and then it is guided into the bottom ring header of cyclone separator by
Page 19 of 110
Page: Page 20 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

connected pipes; and then it is leaded into the upper header at the front enclosure of tail
vertical well from the upper ring header of cyclone separator through connected pipe after
going upwards into cooling separator. It passes through front enclosure superheater, two sides
enclosure superheater, rear enclosure superheater and collects in the inlet header of low
temperature superheater, after flowing downwards into the tube bunch of low temperature
superheater that is horizontal arranged, it is guided into the platen superheater from the left
side of boiler by connected pipe; and then it returns the high temperature superheater in the
tail vertical well from the right side of boiler by connected pipe; at last the qualified superheat
steam is leaded from the outlet header of high temperature superheater. Water spraying
temperature reduction whose adjustment is flexible is adopted for superheater system to adjust
the temperature of steam and protection the pipes of heating surface of every stages. There are
two stages of water spraying in the whole superheater system. The primary attemperator is
installed on the pipe from the outlet of low temperature superheater to the inlet of platen
superheater for coarse adjustment; the secondary attemperator is fixed on the connected pipes
between the platen superheater to high temperature superheater for fine adjustment. The
above two stages of water jet attemperator can reaches the aim of eliminate the deviation of
the temperature of steam by the method of adjusting the amount of spraying water.

1. Enclosure superheater

The walls of enclosure superheater are connected by the inlet and outlet headers; at the inlet
of flue gas at the upper part of front wall of enclosure superheater, the pipes are sparse to
make the pitch increase to 360 from 120 and form the inlet flue gas access; the upper part of
the pipes of rear wall bend to the direction of front wall and form the roof of tail vertical well;
the front wall and rear wall are composed by 46 pipes respectively, the size of pipe isΦ42, and
the size of suspending pipes at the inlet flue window of front wall isΦ60; The walls at two
sides are composed by 31Φ42 pipes respectively. Except the size of the upper heater and
down header of front enclosure and the inlet header of superheater isΦ273, the size of other
headers of enclosure superheater is Φ219.

The characteristic of enclosure superheater is convection heat exchange.

2. Low temperature superheater

The low temperature superheater is fixed in the flue duct of tail convection vertical well. The
low temperature superheater is composed by 46 pieces of double winding horizontal pipe
rings arranged along the width direction of boiler which is sequential and downstream
arrangement and whose size is ∅38. Routine wearing protection measures is adopted by low
temperature superheater. Flow blocking board is fixed between the inlet of the pipe team of
low temperature superheater and the around wall to prevent deflection of flue gas. The
wearing cover plate is adopted at the windward surface for the pipe of front row of low
temperature superheater. The ∅273 outlet header of low temperature superheater is arranged
at the vertical rigid beam at the rear wall of vertical flue duct.

The characteristic of low temperature superheater is convection heat exchanging.

3. Platen superheater

Page 20 of 110
Page: Page 21 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

The platen superheater has two pieces arranged at the upper part of furnace and near to the
front wall of furnace. The superheater is membrane structure; the pitch of pipes is 63.5mm.
There are 24Φ42 pipes for every piece. Wearing material is laid at the lower part of platen
superheater. The whole platen superheater expands from the lower part to upper part. The
outlet header of platen superheater is installed at the upper part of furnace.

The characteristic of platen superheater is radiation heat exchanging.

4. High temperature superheater

The steam comes out from secondary water spraying attemperator and then flow into the high
temperature superheater installed at the upper part of tail flue duct through connected pipes.
The steam is leaded from the right side of the inlet header of high temperature superheater
outside the boiler, and after flowing through the high temperature superheater in the reverse
direction of flue gas, it goes into the outlet header of high temperature superheater. The high
temperature superheater is double winding four circles worm tube bunch whose outer
diameter isΦ38; and there are 46 pieces of tube bunch along the direction of width.

The characteristic of high temperature superheater is convection heat exchange.

ChapterⅡAttemperating water system

The temperature of steam is one of the most important parameters that have to be monitored
and controlled in the operation of boiler as water level. If the temperature of steam is too high,
it will accelerate the creep deformation of metal and affect the security of boiler and steam
turbine directly; if the temperature is too low, the thermal efficiency of steam turbine will be
reduced, the humidity of the steam at the last stages of steam turbine will be increased to
corrode the blade of steam turbine even produce water impact when serious; so the
temperature of steam has to be controlled in regulated range. The adjustment of steam has two
aspects: adjustment at steam side and adjustment at flue gas side. Attemperator is the common
equipment used to adjust the temperature at steam side.

There are two kinds of attemperator: mixed attemperator and surface attemperator. The mixed
attemperator is water and steam mixture device; and surface attemperator is heat exchanger.
The attemperator used in Vikram Thermal Power Plant is mixed attemperator.

Ⅰ. Primary attemperator

Primary spraying water attemperator is installed in the steam connected pipe from the outlet
header of low temperature superheater to the inlet header of plant superheater at the front wall
of furnace. Spraying pipe and mixed sleeve are installed inside of it. The mixed sleeve is
installed at the downstream of spraying pipe used to prevent the attemperator from heat
impact. Temperature and flow measuring device is installed on attemperating water pipes to
measure the amount of water spraying entering into attemperator and the temperature behind
attemperator.

Ⅱ. Secondary attemperator

Page 21 of 110
Page: Page 22 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

The secondary spraying water attemperator is installed in the steam connected pipe from the
outlet header of platen superheater to the inlet header of high temperature superheater of tail
convection flue duct. The temperature of superheat steam can be adjusted further in the
secondary spraying water attemperator. The structure of secondary attemperator is same with
the primary attemperator basically.

Ⅲ. The application of attemperator

When the temperature is variable, the primary attemperator is used for coarse adjustment and
the protection of platen superheater to prevent the pipe wall from exceeding temperature. The
secondary attemperator is nearest with the outlet of superheater. When the temperature of
superheat steam is changed, it is used for fine adjustment and it can adjust the temperature of
steam in regulated range soon; in addition, it also can protection the convection superheater in
thermal section to prevent this superheater from exceeding temperature.

The temperature of the steam whose temperature is reduced by water spraying entering into
the inlet header of platen superheater and the inlet header of high temperature superheater
should be 11℃ higher than the saturated temperature under the pressure of the inlet of pipe.

In the initial stages of the startup of boiler, the temperature of steam is low, and the superheat
degree is also very small, the thermal load of furnace is not big, the flow of steam is small, the
flow velocity is low, and the speed of temperature rising is controlled within 1~1.5℃ usually.
This temperature rising speed should be controlled by combustion instead of controlled by
spraying water, and attemperator should not be used at this time. In the startup of boiler, when
the pressure of steam raises to 1.0~1.2MPa, the attemperator should be back washed 反 冲 .
The aim of this is prevent attemperator from blocking. The washing should be done in single
loop way that is benefit for the effect of washing. When the fire in boiler is flame out, the
attemperator should be paralleled off immediately to prevent the temperature of steam from
going down rapidly. After discharging water of boiler, the water deposited in the water pipes
of attemperator should be discharged that is benefit for the anticorrosion of pipes.

Page 22 of 110
Page: Page 23 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Section Ⅴ Air and Gas System

Chapter Ⅰ Ventilating device

Ⅰ. The method of ventilation

In the combustion course of boiler, the air needed by combustion has to be sent into furnace
unceasingly, and the product of combustion should be removed continuously. This kind of
procedure is called ventilation of boiler.

The ventilation methods of boiler are four: natural ventilation, negative ventilation, boost
ventilation, and balanced ventilation. The one adopted by Vikram Power Plant is balanced
ventilation. In air and gas system, there are IDF and FDF. The resistance in airway is gotten
over by FDF, and the resistance of flue duct is gotten over by IDF.

The working condition of air fan will affect the operation of boiler greatly. The load of boiler
is usually limited by the insufficient output or insufficient pressure so that the reliability of the
operation of boiler unit becomes bad.

One primary air fan, one FDF, and one IDF will be supplied for every boiler in Vikram Power
plant. Every one of them can operate independently under 100% BMCR. Two “j” valve air
fan and one pressure air fan are supplied for every boiler.

Ⅱ. The classification and function of the air system of circulating fluidized bed boiler

1. Primary air

Function: Fluidize the bed material in furnace, and send a certain amount of oxygen to the
dense phase area at the bottom of furnace to support the combustion at the same time.

The head pressure of primary air is decided by the content and density of material, the size of
solid particles, the thickness of bed material, the temperature of bed layer, and so on. The
amount of primary air is decided by the speed of fluidization, the characteristic of fuel, the
combustion in furnace, the heat transformation, and so on. The amount of primary air is
40~70% of total air amount.

One single induction centrifugal primary air fan will be supplied for every boiler in Vikram
Power Plant. The model of this air fan is G9-19-11 N0 20.6D.

Page 23 of 110
Page: Page 24 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

2. Secondary air

Function: make up the oxygen combusted in boiler and strengthen the mixture of material; in
addition, it also can adjust the distribution of the temperature field in boiler properly. It can
prevent from too high temperature of flue gas in partial area and reducing the discharging
amount of NOx. The layered secondary air entered also can reduce the temperature of bed.

One single induction centrifugal secondary air fan (FDF) will be supplied for every boiler in
Vikram Power Plant. Its model is G6-25-14 N0 20D.

3. Sowing coal air

Function: The coal feeding can go into furnace uniformly; the combustion efficiency can be
improved to make the temperature in furnace become uniform. And it also can seal the coal
chute.

The secondary air was used as sowing coal air in past commonly, but primary air is used as
sowing coal air now. Because the air pressure of primary air is not enough, one boosting
pressure air fan should be supplied to boost the pressure.

One single induction centrifugal boosting pressure air fan is set for every boiler in Vikram
Power Plant, and its model is G9-12-11NO11.2D.

4. Returning material air

Blow the material in material returning device become loose to make the material in material
returning air room fluidize slightly and make the returning material can drop into furnace
smoothly.

Two Roots material returning air fan (J valve air fan) are set of every boiler in Vikram Power
Plant, and their model is 3L52WC.

Ⅲ. The operation of ventilation device

The air fan should be checked before startup to confirm the cooling water and lubricating oil
are normal. The inlet damper should be closed when start up the centrifugal air fan; the outlet
and inlet dampers should be open when start up Roots material returning air fan, and then, the
air fan can be started up to prevent from startup with load. After the monitor is normal, the
inlet damper can be opened gradually.

The adjustment of air fan is changing the working condition of air fan manually to make the
working flow amount can meet the necessary of the working condition of air power in boiler.
The common adjusting methods have throttle adjustment, guiding adjustment and speed
variation adjustment. The IDF and FDF used in Vikram Power Plant adopt guide adjustor;
governing valve is set at the axial direction in front of the air inlet of air fan, and governing
guide blades are installed on governing valve that are fixed evenly on circle, the guide blade
is supported by juncture bearing; the steam amount can be adjusted by changing the openness

Page 24 of 110
Page: Page 25 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

of blade so that the working characteristic of air fan can be changed. This kind of adjusting
method is convenient and economic.

Chapter Ⅱ Air Preheater

Air preheater uses the residual heat of flue gas to raise the temperature of air, that improves
the thermal efficiency of boiler greatly and strengthen the combustion in boiler. The air
preheater can be divided into two kinds: regeneration and surface, and the second type also
can be divided into platen preheater and tube preheater.

The air preheater used in Vikram Thermal Power Plant is platen air preheater. The
arrangement of it is horizontal type, and it is positioned under the flue duct of tail vertical
well. The pipes of it are Φ45×2.5mm, Φ45×3.5mm normal carbon steel pipes; these pipes are
sequentially arranged; the transverse pitch of the pipe tanks of primary air and secondary
pipes is 76mm; and the longitudinal pitch is 60mm. Every two pipe tanks are connected by a
connecting tank to form two independent accesses from each other. The primary air and
secondary air go through these two accesses with different pressures in pipes and exchange
heat with the flue gas flowing outside the pipes. The arrangement of flue gas and air is
crossed. The temperature of the air at outlet is 199℃.

Chapter Ⅲ Flow of air and gas system

The circulation of the material inside of the circulating fluidized bed boiler in Vikram
Thermal Power Plant is startup and maintained by the kinetic energy supplied by IDF and
FDF. Balanced ventilation is adopted by for boiler, and the balanced point of pressure is
positioned at the outlet of furnace.

After the air coming from primary air fan is heated by air preheater, the first part of it goes
into the air room at the bottom of furnace, and fluidizes the bed by the blast cap arranged on
air distributed plate, and forms upward two phases flow of gas and solid that will go through
furnace; two high speed diesel oil igniting burners under bed are equipped on this road. After
heated by air preheater, the second road of hot air will be boosted by coal feeding booster fan
using for pneumatic coal distribution. The air coming from secondary air fan is divided into
two roads. After heating by air preheater, the first road is sent into furnace through the
secondary wind box at the upper part of furnace directly; the second road is not heated by
preheater, and this part of air is used as the seal wind of belt conveyor. The air fan should be
equipped for slag cooler respectively, and this air fan supplies fluidized air to slag cooler. The
wind gone out of slag cooler is leaded into boiler a secondary air.

The flue gas and the solid particles brought by it leave the furnace and go into cyclone
separator through the flue duct of the inlet of cyclone separator installed on the rear wall of
water wall. In separator, overwhelming majority material particles are separated from the flow
of flue gas, and the flue gas is guided out through the central barrel of cyclone separator, and
guide into the flue duct of tail vertical well from the flue duct of the outlet of separator; and it
enters from the flue window of front enclosure and flows downwards to wash the horizontal
convection heating surface pipe team arranged in it to transfer the heat to heating surface; and
then the flue gas flows through the horizontal air preheater and goes into dust remover; at last
Page 25 of 110
Page: Page 26 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

it extracts into chimney by IDF and vents into atmosphere.

There are three Roots fan with high pressure head installed for two “J” valve material
returning devices of boiler; the output of every air fan is 100%. In normal operation, every
boiler uses one air fan, and the last one is used to standby for two boilers. The air fan is fixed
capacity type, so the adjusting principle of the air amount of returned material is sending the
residual air through bypass into the air duct of first road of primary air.

Section Ⅵ Dust Removing and Slag Disposal System

After burning in boiler, the coal becomes ash. The ash can be divided into two parts: one part
is exhausted out of boiler along with flue gas, and the other part is deposited in boiler. The
former is called fly ash, and the latter is called slag.

If a large amount of fly ash is exhausted into atmosphere, it will cause serious harm: first, the
thickness of dust in atmosphere will be raised, and the environmental health will be affected
that is bad for the health of human; second, the fly ash is bad for the power plant itself, it will
aggravate the wearing of FDF and reduce the insulation level of electric equipment.

In order to reduce the thickness of dust in atmosphere and prevent from sharp wearing of
FDF, the fly ash must be collected by dust remover. So dust remover is the indispensable
auxiliary equipment of coal-fired boiler.

The slag collected in boiler and the fly ash collected by dust remover must be snapped out in
time and rapidly. Or the safe and economic operation and the environmental health on site
will be affected. So, a set of ash handing and removing system must be equipped for coal-
fired boiler.

Ⅰ. Dust remover

In order to satisfy the requirement of environment protection, bag filter is used in Vikram
Power Plant; the efficiency of dust remover is 99.9%. #1 and #2 boilers are connected with a
same chimney at the same time (the height is 110m, and the diameter of the outlet of every
flue duct is 3m).

Ⅱ. Bottom ash handling system

1. Fixed slag removing pipe

There are three fixed slag outlet (∅159) along the width direction of air distributed plate at the
bottom of furnace. The slag is removed from the slag outlet of water wall in air room at the
bottom of furnace. The evaporation of slag outlet is 4400. There is one emergency slag outlet
among them. The advantages of bottom slag removing are the operation is safe and reliable,
and the operation is simply and convenient.

2. Slag cooler

Page 26 of 110
Page: Page 27 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

There are two multi-pipe water cooling type drum slag cooler arranged under the normal slag
outlet at the bottom of furnace; the slag is removed from the bottom of wind water wall; bell
jar type blast cap is installed on the air distributed steel plate of slag entering pipe; the smooth
transportation of slag from furnace to slag cooler can be guaranteed by the uniform
arrangement by blast cap.

Multi-pipe water cooling drum slag cooler adopts several small barrel built-in spiral blade to
transfer cooled slag at the same time; the high temperature material rotates along with the
small barrel of several built-in spiral blade, and the material is transferred continuously; the
cooling water goes through the intermediate layer between small barrels continuously and
uniformly and exchange heat with the high temperature slag indirectly, in this way the high
temperature material is cooled; the temperature of cooling water rises and it can be used
again. The heat exchanging surface of this structure is large, the heat exchange is rapid, and
the efficiency is high. There is no fly ash and heat radiation because the material feeding and
discharging device and rotating barrel adopt seal structure.

The slag cooler is composed by material feeder, heat exchanging barrel, discharging device,
driving device, base frame, rotating joint, and control tank and so on. The variable frequency
governing speed control is adopted, the speed can be governed continuously according to the
carbon content in a large range of slag, and it is benefit for steadying the pressure of bed.

Ⅲ. The principle of impulse bag filter:

The flue gas goes into the ash hopper from the inlet, and then it will go into the bag filter. The
dust will adhere on the outside surface of filter and the purified gas will be discharged into
atmosphere through the air exhaustion pipe and then through the stack by air fan. The
resistance of bag filter will be increased continuously along with the increasing of the dust
adhered in bag filter. When the resistance is 1500-1800pa, the dust in bag filter should be
removed so that the bag filter can work continuously. The filtrate bag is arranged in a straight
line. One pulse valve is used to control the compressed air pulse to remove the dust. And the
pulse valve is controlled by program controller. In the process of removing dust, the dust
removing controller will send order to make the pulse valve release 0.5----0.7Mpa
compressed air in the same time of the action of pulse valve. This compressed air will go into
the filtrate bag through the small holes that face to the filtrate bag directly on the blowing
pipe; at the same time, and secondary gas flow is also produced at this time, so that a transient
impact will be produced and it will spread along the direction of the length of the whole filter;
so that the dust depositing on the outside of bag will drop. The dust will fall into the material
hopper and be sent into the ash yard by ash conveying system. The lasting time of pulse can
be adjusted to suit the characteristics of the different dust.

There are four rooms of the bag filter used in this power plant. There are 288 bags in each
room. The total numbers of bags is 1152, and the filtrate area is 4052 m 2. The specification of
bag is ∮ 140 × 800 mm.

Page 27 of 110
Page: Page 28 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Section Ⅶ Hydraulic Test of Boiler

Hydraulic test is a method that can check the tightness of bearing components of boiler, and it
is also a test for the strength of bearing components. The hydraulic test must be done after
new installation or overhaul of boiler in order to check the unit thoroughly. It is a examine
method to guarantee the safe operation of bearing components of boiler.

Ⅰ The classification of hydraulic test

1. The hydraulic test at working pressure

The hydraulic test at working pressure is generally done after repair and overhaul of boiler.
The test pressure is the working pressure of drum, i.e. 10.98Mpa.

2. The hydraulic test at over pressure

According to the “Supervisory Regulation of The Safe Technology of Steam Boiler” issued by
Labor and Personnel Ministry of PRC, the hydraulic test has to be done in the first operation
and after any repair of any bearing component. The test pressure is 1.25 times of the working
pressure of drum, i.e. 10.98×1.25=13.725MPa. The over pressure test of boiler is harm for the
service life of it, and this test is dangerous, so it should be done as less as possible.

Ⅱ The requirements for water quality in hydraulic test:

 The boiler in hydraulic test has been filled treated water fully. The water used in the
hydraulic test in Vikram power plant should be condensate water or demineralised
water.
 The temperature of the test water should be in the range of 20~70℃, but it should be
higher than the temperature of environment. The temperature of water should be near
to the temperature of the metal wall of drum at the beginning of filling water, and the
temperature of other bearing components should be no less than 20℃. The aim of it
is to guarantee the hydraulic test can be finished at the temperature higher than the
transferring temperature of metal from brittleness to plasticity.

Ⅲ. The qualified standard of hydraulic test

Raise the pressure to test pressure, close the valves on feed water pipes; after stop the feed
water pump, the pressure reducing of drum is not bigger than 0.5Mpa in every 5 minutes;

Page 28 of 110
Page: Page 29 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

there is no leakage on the metal wall and welding place of compression components, and
there is also no obvious deformation.

Ⅳ. The operation procedure of hydraulic test:

1. The check before hydraulic test:

1) All impurities and tools have been left.


2) There is nobody in unit.
3) The pressure gauge has been calibrated correctly and it has been installed on the
drum correctly; its valves are in opening condition.
4) Any component that does not bear the pressure of hydraulic test in design has
been insulated or divided properly.
5) The action states of all valves are at correct position.
6) All spring hanging pins are fixed on a fixed position in steam system.
7) All safety valves have been insulated.
8) The emergency water discharging valve and exhaustion valve to atmosphere in
order to depressurize over pressure;

2. Fill water into boiler

1) After the water quality is qualified proved by analysis, close the water discharging
valve of drain water tank, re-circulating valve of drain water pump, stop valve gone
to deaerator, and open the demineralised water valve, and keep the water level of
drain water tank above 1/2.
2) Close the drain water valve of feed water system, discharging water valve of
economizer, emergency water discharging valve, back washing valve of superheater,
valves on the pipes of attemperator, and drain water valve.
3) Open the inlet valve of drain water pump, exhaustion valve to atmosphere, stop
valve of the water feeding to cold boiler, general valve of periodic blowdown
station, and every branch valve.
4) Start up drain water pump, and control the speed of water feeding at outlet valve.
After seen water in drum, open the re-circulating valve of economizer to supply
water into economizer till the water in bearing components is full; after the air in
main steam system is discharged clearly, close air valve, exhaustion valve to
atmosphere, and the valves in cold boiler water feeding system in succession; stop
the operation of drain water pump, and close the outlet valve of pump and the water
approaching valve of demineralised water. At the same time, when seen water in
drum, put steam into operation to increase the temperature till 50-70ºC. If cold boiler
water feeding system of drain water pump is in trouble, should use small bypass to
feed water and go another way.
5) In order to reach these temperatures of hydraulic test, the temperature of water can
be raised by the following ways:
 When the oil ignition system under the bed of boiler cannot be put into
operation (such as in the beginning of operation), if the temperature of the
medium in drum is lower than 20℃, saturated steam can be put into drum by
blowdown of drum or through medicine dosing pipe to heat the water and barrel

Page 29 of 110
Page: Page 30 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

to the necessary temperature. when the operating water level in drum is normal,
the water should be heated till its temperature is 2~5℃ higher than the
recommended temperature to guarantee the final temperature of water is not
lower than the smallest recommended value.
 If the igniter under the bed of boiler can be put into operation, after the filling
water of unit reaches the normal water level, the high speed diesel oil igniter can
be fired to raise the temperature of drum till it is 2~5℃ higher than the
recommended value. Flame out and fill water continuously.

3. Raising pressure

1) After filling water fully, the feed water pump is used to pressuring the bearing
component. The adjustment for the speed of main raising pressure is controlled by
the governing valve of small bypass. In hydraulic test, the raising and reducing of
pressure should be slow. When the pressure is lower than working pressure, the
raising and reducing speed cannot exceed 0.196~0.29Mpa/min; and when the
pressure is near to the working pressure, the speed should be slower; and after
exceeding the working pressure, the raising and reducing speed cannot exceed
0.098Mpa/min. Because water does not have compactibility, every component will
bear equal pressure. The emergency water discharging valve can be used to control
the pressure release.
2) The pressure raising cannot be stopped till it reaches 1.0-1.5 MPa, and then a total
check should be done.
3) The pressure is raised to working pressure, close the governing valve and motor-
driven valve at small bypass; and stop the raising pressure to check completely; stop
the operation of feed water pump after confirming there is no problem, and write
down the speed of pressure reducing.
4) Over pressure hydraulic test.
 All water level monitoring instruments do not attend the over pressure
hydraulic test, and they should be paralleled off when reaching working
pressure.
 When the pressure raises to working pressure, the raising pressure
should be stopped to check completely; after there is no problem, the pressure
should be raised till 1.25 times working pressure; after keeping for 20 minutes,
it should be reduced to working pressure, and check it completely.

4. Pressure release

After checking, the pressure can be reduced, and the speed of pressure reducing can be
controlled at no more than 0.3Mpa/minute by emergency water discharging valve. When the
pressure reduces to normal, open the air valve, drain water valve, pulse safety valve, steam
coming valve of steam system; and use emergency to discharge water till normal water level
in drum. After finish the test, the blind or block on safety valve should be demolished, and all
positioning bin of spring hanger should be removed.

After the hydraulic test is finished, the boiler water should be discharged clearly and the
anticorrosion and maintenance measures should be set down in time; if the environment

Page 30 of 110
Page: Page 31 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

temperature is lower than 5℃, the antifreeze measures also should be adopted.

Section Ⅷ Normal Startup, Shutdown and Operation of Boiler

Chapter Ⅰ Startup of CFB boiler

The startup of boiler include “drying out”, “boiling out”, “first time startup”, “normal startup”
for new installed unit. The normal startup of boiler can be divided into two kinds: cold state
startup and hot state startup. The cold startup refers to the startup after repair or long time
standby under the condition without pressure and the temperature is normal; the hot startup
refers to the startup under the condition of boiler has standby for short time, and it still keeps
certain pressure and temperature. The courses of hot startup and cold startup is same mainly,
just some working contents can be omit or simplify.

The cold startup of boiler include: the checks and preparation before startup, ignition,
boosting, warm up pipes, adding load and so on.

Ⅰ. The preparation before startup of circulating fluidized boiler

Before ignition of boiler, a thorough external check has to be done for boiler to guarantee the
security of equipment and person.

1. The following checks should be finished before the startup of boiler.

1) All air fans must be able to put into operation; the lubricating system must be able to
put into operation at any moment; the equipment should be operated normally under
the condition whose vibration is in the allowable deviation range.
2) All dampers, operators, and actuators have to be checked thoroughly; these auxiliary
equipments have to be able to satisfy the requirements of all operating working
condition without cementing or blocked. Conform the dampers can reach its right
position according to the requirement of control.
3) Guarantee the dust removing system has been connected with slag cooler and the
slag cooler has been prepared well to put into operation.
4) All remote operating valve and sliding drop gates can be able to operation. Check the
position limit switch to confirm whether the installation is correct or not and supply
the exact position indication.

Page 31 of 110
Page: Page 32 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

5) The trial runs of all transferring devices have to be done to guarantee its normal
operation.
6) All key flow devices have to be calibrated.
7) The ignition device under bed and flame detector and interlock device must be under
the condition of preparing to operation.
8) All key thermocouples and pressure transducers have to be checked to confirm their
connections are correct and make sure they are able to operate.
9) All flue ducts, airways, pipes, grooves, or guide pipes of air, flue gas, water, steam,
and solid fluid have to be connected correctly and reliably.
10) All expansion joints have to be check to confirm the correct connection.
11) The dust remover has to be checked to confirm the system can operate normally.
12) All electric joints must be checked to prove that they have been installed correctly
and they have good insulation.
13) Check the remote water level indicator of drum is working; compare its reading with
the local water level indicator exactly. This procedure should be done periodically.

2. The following works have to be done well before operation.

1) Before operation, when the water level of drum is lower than the lowest sighted point
of double color water level indicator, the water inside of water level indicator should
be drained completely. Whenever the water level indicator is repaired or replaced,
whether draining water of it is normal or not should be checked.
2) The blowdown pipes of balance container and water level indicator should be
connected to safety area, and the blowdown valve has to be closed. Suitable light
should be supplied for double color water level indicator in order to benefit the
operator on operating plate to obvious the reading of water level indicator.
3) All exhaustion pipes drain water pipes and blowdown pipes have to be benefit for
operation and should be connected to blowdown container or other safe place
correctly to prevent from threatening the security of operator at any time.
4) The valves between the drum and water level indicator have to be locked at fully
opening position.
5) The blinds of all safety valves and hydraulic test have to be demolished. The valves
must be under the good working condition; the dump steam of safety valve and the
drain water pipe must be arranged and supported according to the recommendation of
the manufactory of safety valve.
6) The components inside of drum must be installed correctly according to drawings to
guarantee there is not any steam short cut.
7) All necessary junctions used for measure have already been installed.
8) The seal test of air and gas system of boiler has to be done to eliminate all leakage.
9) The heat emission area of boiler must be adiabatic or using robe to fence out it to
protect the operators.
10) All thermal expansion equipments are not disturbed by erecting frame, ladder,
fragment, and the left construction material.

3. The following checks should be done before operation:

3.1 The proper of boiler

Page 32 of 110
Page: Page 33 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

1) The proper of boiler, auxiliary equipment, and main equipments have been
installed completely; the step trail operation has been finished and the startup
condition is met.
2) The surface of the boiler wall is level and the appearance is complete without
crack so that the seal quality can be guaranteed. This is very important for the normal
operation of boiler.
3) The observation hole, poke hole, and manhole are completely well, and they can
be operated flexibly. They should be closed fully after check. Especially the hole at
the pulverized combustion part in furnace should be closed tightly.
4) There is no depositing ash and impurities in the flue duct, airway and ash
remover.
5) There is no oil leakage in the fuel oil system and the pipes and valve in this
system; the atomizing quality of the nozzle of oil gun is good; the heat flue gas
producer should be good and not broken; there should be enough oil in oil storage
tank; and before ignition, should check whether it is blocked or not.
6) There is enough coal storage in coal bunker; the coal feeder is not blocked; the
flex of belt is suitable; and the foot screw is firm.
7) There is enough storage in ash silo; the outside insulation of material circulating
system is good.
8) Check the installation of blast cap should be correct and the hole of blast cap is
not blocked.
9) There are no impurities in air room, the slag removing pipe is blocked and clear,
and it can open and closed flexibly.
10) The operation of slag cooler is normal, and the circulation of cooling circulating
water is normal.
11) The IDF, FDF, secondary air fan should rotate without load, the lubricating oil
level of bearing should be normal (the oil level should be in the range of 1/2—3/4).
The cooling water is unblocked; the safety cover is firm; the foot anchor is not loose;
the grounding of motor is well; and the damper of IDF is at close position.

3.2 The I&C operation panel of boiler

1) The panels are clear, and there are not any tools and sundries on them.
2) All operating switches have been installed completely. And the startup and
shutdown light are complete.
3) The installation of all I&C control instrument, electric instrument are finished
completely; their indications are correct. And the calibrations of them are qualified.
4) The sound of alarm in test is loud.
5) The signs of name are correct and complete, the script are clear.
6) The components of remote devices (valves, dampers, tie rods) should be
complete. After check, the power should be sent for them to do fully opening and
close test; the action of them should be flexible, the indication and action should be
coincident. The fully open and fully close positions should be reached. And the
operation charger should supervise this test.
7) The papers and ink should be prepared well for auto recording instrument.
8) The illumination inside of operating room and the emergency illumination are
good.

Page 33 of 110
Page: Page 34 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

9) The I&C instrument, valves, and components are complete.

3.3 The construction quality of the installation for the devices inside of drum

1) The devices inside of boiler should be installed according to drawings strictly. It


is confirmed there is no weld missing.
2) The local water level indicator, steam valve, and water valve are tight without
leakage; the switches are flexible. The installation positions are correct and the signs
are obvious. The water level indicator should be at operating condition. The water
valve and steam valve should be open and the water discharging valve should be
closed.
3) The safety valve on drum and superheater must be adjusted and calibrated
according to the regulated pressure.
4) For the boiler that has superheater, the safety valves that are adjusted according
to lower pressure have to be on superheater.
5) The opening pressure the safety valve of economizer should be adjusted to 1.10
times of the working pressure of fixed place.
6) Check the lever safety valve. The device that can prevent from self-moving of
counter weight should be supplied; the spring safety valve should has lifting
handhold and the device that can avoid screwing the screw at random.
7) Check whether all water discharging valves, drain water valves and blowdown
valves can open and close flexibly or not. After check, they should be closed.
8) Check whether the actions of all valves on feed water pipes are flexible or not.
All valves except the main feed water valve in front of economizer should be open.
The main feed water valve should be open when supply water into boiler.
9) The pressure gauges should be clear and clean, the red line on scale plate should
indicate its working pressure. And there should be good illumination. The check of
pressure gauge expresses it is qualified.
10) The support hanger frames of steam system, feed water system, and blowdown
system are firm and dependable, the insulation is complete. The hand-hole, manhole
of boiler should be sealed tightly. The installations of every expansion indicator are
correct, and its indicating pin should be at zero position in cold state.

4. Supply water to boiler

After the checks before ignition of boiler are finished, water can be supplied into boiler.
The following items should be paid attention to in this period.

1) The air valve of steam and water system should be open before supplying water
in order to exhaust the air in boiler. The temperature of water cannot be higher,
and the water supply should be done slowly. This period should be lasted at least
2 hours in summer and at least 4 hours in winter from no water in boiler to
reaching the lowest water level indicating place on the water level indicator of
drum.
2) In the process of water feeding, the manhole cover, hand-hole cover, jointing
surface of flange and blowdown valve should be checked to confirm whether
they leak to not. If it does, it should be repaired in time.

Page 34 of 110
Page: Page 35 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

3) When the water level of drum rises to the lowest water level indication of water
level indicator, the water feeding should be stopped. The water level inside of
boiler should be kept not changed inside of boiler after stopping water feeding. If
the water level goes down, the reason of it should be found out in time, the
leakage place should be found out and eliminated try best. If the water level
rises, that express the feed water valve leaks water, it should be repaired or
replaced.

Ⅱ. The ignition method of circulating fluidized bed boiler

The ignition process of circulating fluidized bed boiler refers to the process of the bed
material inside of burner is heated to certain temperature by some method, and the bed
material become fluidized state by air till the fuel feed by coal feeder can combust
continuously and stably. The ignition method of circulating fluidized bed boiler is different
from the common boiler. It seems difficult to master for the staff who never contact the
circulating fluidized bed boiler. It is easy to cause foul or flame out for them. So the staff of
boiler section must be trained in advance.

The ignition methods of circulating fluidize bed boiler can be divided into two kinds: wood
ignition or oil ignition on bed and oil ignition under bed. The last method is adopted in
Vikram Thermal Power Plant. This kind of method has the following advantages: the
combustion of oil is small; the startup is fast; the success rate is high; the environmental
health is good; and the labor intensity of workers is low. The oil ignition under bed is
fluidized ignition, and the whole startup process is proceeding under fluidized state. First,
400mm-500mm bed material should be laid on the air distribution plate composed by
membrane water wall; because the heat energy is sent into the material layer from air
distribution plate uniformly, the whole heating startup process is finished under fluidized state
that cannot cause low temperature or high temperature foul.

Ⅲ. The cold startup procedure of the circulating fluidized bed boiler in Vikram Power Plant

1 The preparation before startup

Attention: before startup, at least two person have been patrol inspect the
equipments of the whole unit to verify all equipments have meet the startup
condition. Fill material into fluidized bed and “J” valve.

1.1 Put the blowing out system of piezometer into operation

The blow out system of piezometer should be put into operation; a little amount of air can be
put into boiler by it; manual blow out should be done for it periodically using compressed air
used for instrument. The frequency of blow out should be decided according to experience.
The relevant valves should be closed in order to protect the instrument of blowing out system
when it is blowing out.

The similar procedure can be taken for other pressure measuring pipes at air side and flue gas
side of boiler.

Page 35 of 110
Page: Page 36 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

1.2 Check and confirm the plugs or blinds used in the hydraulic test for safety valves have
been demolished.

1.3 Check the common system, kinetic and ignition fuel and main fuel and the supplying
condition of feed water after treatment; and confirm they are qualified and can be used.

1.4 Check the operation conditions of all valves and dampers.

1.5 Check the high speed diesel oil igniter under bed and all auxiliary equipments of boiler,
and confirm all relative valves are under proper opening or closed position.

1.6 Check that the thermocouples used for measure the temperature of wall of drum are good.

1.7 After confirm there is no person inside of boiler, all manholes and obvious holes should be
closed, and all safety sign on the equipment that is prepared to operate should be taken away.

1.8 Before supplying water to unit, the relevant valves of boiler including air vent valve, drain
water valve and the valves using for instruments should be under the following conditions:

The name and description of valves State


Pulse safety device of the outlet pipe of high temperature
Tuning at 10.3MPa (gauge pressure)
superheater
Pulse safety device of drum Tuning at 10.6MPa (gauge pressure)

Stop valve fixed on the pulse safety device Open

Drop gate on the main feed water pipes Close

Non-return valve on the main feed water pipes Auto

Air vent valve on the saturated steam guide pipe Open

Stop valve used to transmit the pressure of drum Open


Stop valve at water side and steam side of high, low water level
Open
indicators of drum
Drain water valve of high, low water level indicators of drum Close

Stop valve used for dosing in boiler water Close

Emergency water discharge valve of drum Close

Continuous blowdown valve of drum Close

Sampling valve of boiler water Close

Three way valve used of the pressure gauge of drum Open

Sampling water of saturated steam Close

Drain water stop valve of centralized down-comer of boiler Close

Page 36 of 110
Page: Page 37 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Stop valve of re-circulating pipe Open

Routine blowdown of the down header of water wall Close

Cooling steam exhaust valve of upper header of cyclone separator Auto


Drain water valve of the inlet connected pipe of lower part ring
Open
header of cyclone separator
Air vent valve of the upper header of front wall and rear wall Open
Drain water valve of the down header of front wall, rear wall, left
Open
side wall, and right side wall.
Drain water valve of the inlet header of screen superheater Open

Air vent air of the outlet header of screen superheater Open

Drain water valve of the inlet header of HT superheater Open

Air vent valve of the outlet header of HT superheater Open


Three way valve used for the pressure gauge of connected pipe of
Open
the outlet of HT superheater
Steam exhaust valve to atmosphere of the connected pipe of the
Open
outlet of HT superheater
Manual stop valve of water jet attemperator Close

Stop valve of main feed water bypass Close

1.9 The feeding water should pass the bypass valve of main feed water and go through the
economizer system, and then go into boiler in first time.

1.10 In the period of feeding water, when the air vent valves discharge water of corresponding
components, this air vent valve should be closed. And the temperature of water feeding should
be controlled in the range of 20℃~70℃, and it should be not lower than the temperature of
drum.

1.11 Check the operating condition of electric contact water level indicator of drum in main
control room, and compare its reading with the reading of double color water level indicator
exactly.

31.12 Check whether all pressure gauges and draft meter are calibrated, and whether their
functions are proper.

1.13 Check all safety interlock devices to guarantee the actions are correct.

1.14 Validate the water level shown by double color water level indicator of drum is clear to
see.

Page 37 of 110
Page: Page 38 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

1.15 Check the lubricating and cooling systems of all driven device satisfy the technical
requirements of the manufactory. The cooling water has to be obtained at the places needed to
cool.

1.16 The position of the dampers of flue duct and airway are as follows. The positions of
dampers are shown in main control room. All dampers of fuel, limestone and other manual
insulation and / or sliding drop gate should be in the following state:

The position of damper State

Guide blade of the inlet of IDF Open

Guide blade of the inlet of primary and secondary air fan Open

Inlet of limestone Close

Air nozzle of the slag pipe of slag cooler Close

The inlet of the cooling air of slag cooler Open

Supply secondary air Open


Manual stop valve of the inlet of the boost air fan of coal
Open
feeding
The stop valve of the bypass of the boost air fan of coal
Close
feeding
Motor-driven stop valve of the outlet of coal feeder Open

Motor-driven stop valve at the inlet of coal feeder Close

Under bed oil igniter and fluidized air of furnace Open


The fluidized air of the upper and lower material legs of “J”
Open
valve
The fluidized air at the bottom of “J” valve Open

Lower secondary air Open

Sliding valve of the inlet of coal feeder Close


Bypass governing valve from the outlet of “J” valve to
Open
primary air flue duct
Purging air of fuel Open

Seal air of the coal feeder of fuel Open

Rotating valve of the outlet of slag cooler Close

2. Blow out

Before blowing out of boiler and oil ignition under bed, the check for the airway behind the
oil igniter under bed and the inside of air room are very important; the purpose is checking the

Page 38 of 110
Page: Page 39 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

leaking of bed material. All bed material leaked in airway and air room should be removed to
prevent the blast cap from blocking in blowing out. Before startup of every time and before
the startup after cutting off the main fuel, the furnace, cyclone separator and the tail heating
surface area have to be blown out (except hot startup); the blowing out must be prepared
according to the following procedure:

2.1 Confirm there is not hot startup working condition (the even temperature of bed is lower
than 650℃).

2.2 Confirm the boil is under the condition that the main fuel is cut off, and there is not the
working condition of main fuel trip.

2.3 Confirm the steam supplying valve of the oil igniter under bed is closed.

2.4 Verify all limestone and fuel feeder are at cut off condition and the bed material ash
removing system is closed.

2.5 The IDF, FDF and coal feeding booster air fan and “J” valve air fan should be started up
according to the following methods.

2.5.1 Before start up every air fan, the air way from the inlet of IDF to chimney should be
unblocked to prevent from breaking the furnace and flue gas way caused by the positive
pressure and negative pressure

2.5.2 The sequence is start up one “J” valve air fan firstly, and then start up IDF, primary air
fan and secondary air fan and one coal feeding booster air fan; and then build the air flow
required for blow out, and put all air fans under auto control method. After blow out, all of
these air fans should be kept at the following startup condition.

2.5.3 Guarantee all dampers of fuel and flue gas way are at the position mentioned in 1.16
clause.

2..5.4 Start up one “J” valve air fan, and the ventilation rate of the air nozzle of “J” valve of
every road should be controlled at the value given in form 1 (93℃).

2.5.5 In trial operation stage, the auto control of the operation of “J” valve is realized by the
procedure input into the operating system of “J” valve. In the operation period of unit, the
adjustment of air flow of every air opening is not very important, but the operating condition
of “J” valve should be monitored closely to avoid abnormal condition and trouble in the next
step.

2.5.6 In startup, it should be operated according to the following procedure (the ventilation
rate should be adjusted slightly). What is necessary to explain is “J” has the function of self-
balance; after the commission of unit is finished, the air flow of every air opening is not
needed to adjust. The following procedures just focus on the commission and startup.

1) The correct operating parameter is shown in attached form 1 and attached

Page 39 of 110
Page: Page 40 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

drawing 13 “J” valve pipe connected drawing.


2) Put the control of the air flow of the air flow of the ascension pipe and down
comer pipe of “J” valve at auto state.
3) Put the pressure governing valve of “J” valve air fan at auto way, and check
whether its function is normal or not.
4) Put the openness of every valve of inflatable pipe at 65%.
5) Put the flow controls of every inflatable pipes of ascension pipes and down-
comer pipes at auto state.
6) Confirm the flow of every vent opening pipe.

If non flow indication appears in any above pipe, it may be caused by the block of
vent opening. The method of eliminating the accident is adopt high pressure air to
blow out this pipe to guarantee the unobstructed of pipes. Mechanical method cannot
be used to evacuate the blocked pipe in the operating period of unit.

7) Record every ventilation rate, temperature of “J” valve, and compare it with
attached form 1.
8) When the ventilation rate is far from the given value in attached form 1, it should
be adjusted till it reaches the satisfied value. The control of ventilation should be
put at manual operation way. The air flow should be adjusted according to
14Nm3/h increment at the same time of recording the differential pressure value.
The air flow should be built on the basis on steadying the lowest differential
pressure value.
9) In order to evacuate many inflation inlets that are blocked or out of service,
shutdown the boiler as soon as possible is necessary. If the vent openings that are
out of service or blocked have been found out, and there is no blocked
phenomenon with the other horizontal or vertical vent openings near it, the unit
can be maintained for operating for short time. When it is verified there are
several vent opening cannot work, the unit should be shutdown forcedly to avoid
block of “J” valve.
10) Record the air flow of “J” valve under 40%, 60%, 80% and 100% MCR loads
respectively. If it is necessary, adjust it according to step (8).

2.5.7 Start up IDF. Close the governing guide blade of the inlet of IDF, close the tripping
switch of IDF, and start up the motor of IDF. Once this motor is operating and reaches the
regulated rotating speed, govern the governing air valve of IDF to adjust the negative pressure
of furnace.

2.5.8 Startup secondary air fan, primary air fan, close the inlet governing air fan of air fan,
close the tripping switch of FDF to operate the motor. After the operation of the motor of air
fan is normal, adjust the governing air valve of the inlet of air fan to adjust the combustion. In
this step, the secondary air fan should be started up firstly, after the startup of secondary is
finished, the secondary air flow should be governed to minimum, and then start up primary air
fan.

2.5.9 Start up one coal feeding booster air fan. Close the governing damper of the inlet of this
coal feeding booster air fan, close the tripping switch to operate the motor. After the operation

Page 40 of 110
Page: Page 41 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

of motor is normal, open the damper of blowing out air fan to make the air fan can operate
normally, and open the outlet closed damper of this air fan at the same time.

2.5.10 The unit is adjusted to the condition of “prepare to blow out” by control system
automatically.

2.6 Add initial bed material to “J” valve and air distributed plate of furnace according to the
following methods:

2.6.1 When begin to fill “J” valve, the seal should be formed between the up material leg and
down material leg by using “J” valve (it is realized of bed material filling). The bed material
should be filled from the filling opening of “J” valve. “J” valve air fan has to be put into
operation to supply necessary air flow at this time, and the grain size of bed material must be
fit.

2.6.2 When filling material to the air distributed plate of furnace, the initial bed material can
be limestone and also can be slag, and the grain size is 0~3mm. The filling amount should be
decided according to the size of furnace, and the height of reduced static material layer is
about 380mm. the filling material into furnace cannot be stopped until the pressure of bed
reaches 3300Pa.

2.7 The unit should be blown out at 25% total air flow (cannot exceed 40%) for at least 5
minutes.

2.8 After the blowing out of boiler is finished, the condition of MFT (main fuel trip) should be
recovered and the following items should be carried out:

2.8.1 All governing dampers of secondary air should be at the position of min openness.

2.8.2 Maintain the fluidized air flow at ~1.2m/s.

2.8.3 The following equipments should be prepared well at given position:

 Put the governing dampers of high speed diesel oil igniter under bed and the governing
damper of the fluidized air of furnace (to air room) at the prepared position to build
proper combustion air amount.
 Adjust the air valve of the inlet of IDF to build 23940m 3/h min fluidized air flow
(attached drawing 11, 1.2m/s, 600℃).
 Guarantee the supply of fuel to oil igniter under bed is not interrupt, and the blow out
pipes are expedite.

2.8.4 The even temperature at the cold end of air preheater should be kept at 80℃.

3 Ignition and warm machine

3.1 Before ignition, there must be bed material on the air distributed plate of furnace. The unit
has been blown out, and there must be bed material in “J” valve.

Page 41 of 110
Page: Page 42 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

3.2 Attached drawing 14 is the corresponding curve of the height of static bed material and
the differential pressure of bed layer; and the attached drawing 11 is the corresponding curve
of the fluidized rate and air amount. The fluidizing rate can be confirmed under fixed bed
temperature using figure 11 by measuring the air amount passed through the bed layer under
furnace. When using mixed fuel, the surface fluidized speed cannot be lower than 1.2m/s; this
speed of the min surface fluidized speed required for maintaining the fluidization. The
differential pressure can be read on the panel in main control room.

3.3 In order to avoid over heat stress, the differential temperature of the upper wall and lower
wall of drum cannot exceed 50℃. Monitor the differential temperature of the upper wall and
lower wall of drum according to the reading of metal wall temperature displaying meter.

3.4 Confirm the two re-circulating stop valves from the inlet of economizer to the down
centralized down-comer are at opening position. The following drain water valve should be at
closed condition, and then they should be turn on at 1/2 cycle.

1) Drain water valve of the lower header of front enclosure


2) Drain water valve of the lower header of the left and right enclosure
3) Drain water valve of the lower header of rear enclosure
4) Drain water valve of the inlet header of screen superheater
5) Drain water valve of the inlet header of high temperature superheater

3.5 Ignite the oil igniter under bed, obverse the ignition condition through the observation
window to confirm good combustion (fame quality).

3.6 The limestone feeding system should be put into operation at min speed manually
(including the limestone feeding air fan). Before startup, in startup and in operation, the
operating condition of every rotating device should be verified and monitored. The bed
material should be made up according to the specific condition in operating period.

3.7 Monitor the oxygen amount to confirm whether the complete combustion is realized. The
temperature of the flue duct wall of oil igniter under bed should be controlled under 1500℃
according to the requirements of the oil igniter under bed.

3.8 After confirming the ignition of oil igniter under bed, on the basis of min combustion
speed, the auto temperature control system should be put into operation.

3.9 The pressure of drum is raised by heating the bed material. The booster of drum should
controlled by adjusting the combustion speed of oil igniter under bed; and the temperature
rising velocity cannot exceed 50℃/h.

3.10 The temperature of the flue gas at the outlet of oil igniter under bed should be controlled
under 980℃ by adjusting the combustion. In this period, the temperature rising rate cannot
exceed 28℃/per 20~30min (the oil igniter under bed is 15% MCR heat output).

3.11 When the unit is header and the pressure of drum has been built; the temperature of the
metal wall of drum and water level should be checked.

Page 42 of 110
Page: Page 43 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

3.12 Rise the temperature of bed to 468℃, and maintain the combustion air amount at
23940Nm3/h. In the heating period of unit, the water level will be raised. The water level of
drum should be maintained in allowable range by continuous blowdown valve and the feed
water governing speed pump. In order to maintain the water level in drum, the emergency
water discharging and continuous blowdown can be used at the same time when necessary.
The blowdown valve and the drain water valve of water wall cannot be used as water
discharging valve under any condition.

3.13 When the pressure of drum reaches 0.069 ~ 0.103MPa (gauge pressure), the following
air vent valve should be closed:

1) Air vent valve of the saturated steam guide pipe.


2) Air vent valve of the upper header of front enclosure.
3) Air vent valve of the upper header of rear enclosure.
4)Air vent valve of the outlet header of screen superheater.
5) Air vent valve of the outlet header of high temperature superheater

Close the following drain water valves:

1) Drain water valve of the lower header of front and rear enclosures.
2) Drain water valve of the lower header of left and right enclosures.
3) Drain water valve of the inlet header of screen superheater.
4) Drain water valve of the inlet header of high temperature superheater.

3.14 Every drain water valve on the main steam connected pipe should be still opened to
guarantee the water in all steam loops can be drained at this time.

3.15 When the pressure of drum reaches about 0.17Mpa (gauge pressure), check the water
level indication of double colors water level indicator of drum with the help of short time
blowdown. In the period of blowdown for double colors water level indicator/ water level
component, it is necessary to test whether the fuel cut off protection under low water level can
work or not in order to get rid of unnecessary cut off. The visible water level of double colors
water level indicator should be kept. The water level in drum will rise because of the
expansion of water in system, the continuous blowdown valve and emergency discharging
water valve of drum can be opened according to necessary to discharge the water in drum.

3.16 Put the control of the water level of drum under the unit auto control condition.

3.17 In boosting process and in normal operation, the silicon content and slat content in boiler
water should be kept in allowable range of value.

3.18 If the silica content or slat content in boiler water exceeds the standard limitation, the
continuous blowdown valve of drum should be opened to blowdown the boiler water till it
goes down to within the allowable range. If the content exceeds the recommended value
under relevant pressure, it is forbidden to go on boosting.

3.19 Heat continuously to build the pressure of drum and maintain 470℃ bed temperature. If

Page 43 of 110
Page: Page 44 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

it is necessary, limestone can be put into furnace to maintain the total amount of bed material
in the period of warming machine. The total amount of bed material should be decided
according to the signal of bed pressure.

3.20 If it is necessary to discharge water from high temperature superheater, the atmospheric
relief valve on the main steam connected pipe can be opened discontinuously; but this method
cannot be used until the pressure of boiler reaches 3.45MPa (gauge pressure).

4 Startup (supply coal)

4.1 Put the ash removing system into operation.

4.2 Open the manual stop valve of water spraying attemperator.

4.3 Put the steam temperature control loop at auto way, and set the expected temperature.

4.4 Start up two coal feeders, and adjust their outputs to 15% of the rated fuel amount of
furnace. After operating for 5 minutes, stop their operating, these coal feeders should be
stopped; the oxygen amount and even bed temperature should be monitored. In the first
several minutes, the even bed temperature will go down totally, and then it will rise. And the
oxygen amount will be kept without change, and then it will be reduced before the even bed
temperature rising. The time cycle of combusting all fuel in furnace completely should be
recorded from the beginning of fuel feeding to the highest even bed temperature and the
lowest oxygen amount appear. After practice on site, this cycle should be set, but this cycle
should be changed if the coal qualities are different. In the above process, the bed temperature
thermocouple should be monitored; the partial temperature near fuel feeding place will go
down usually; the further from the coal feeding place, the higher the temperature is.

4.5 Start up two coal feeders again, and adjust their output to 15% of the rated fuel amount of
furnace; and then stop these coal feeders after supplying material for 5 minutes. Monitor the
even bed temperature and oxygen amount. Start up the coal feeder with 15% output before the
temperature of bed increasing to the peak value, and then add into fuel and keep for 5
minutes.

4.6 Repeat the procedure 4.4 and 4.5 to make the even bed temperature increases to 760℃
gradually. When the relevant relationship between the even bed temperature and oxygen
amount is good, the coal feeder can be put into operation normally. The increasing of the load
of boiler can be realized by increasing the output of material feed. The combustion rate of
primary material feeding will be increased along with the increasing of even bed temperature
that will shorten the coal feeding cycle actually. Some measures must be adopted to prevent
from feeding too much material along with the increasing of coal feeding amount, or the
indication on some indicating instruments will show the coal feeding is out of proportion. The
oxygen amount must be reduced rapidly maybe reduced to zero, and the even bed temperature
will be increased substantially and continuously. Some measures can be adopted respectively
according to the different conditions of excess coal feeding.

 Wait the fuel is combusted completely, but it is forbidden to add into additional

Page 44 of 110
Page: Page 45 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

fuel. Monitor this trend.


 Increase the making up rate of limestone and bed material that can absorb the
increasing heat.
 Reduce the air amount of fluidized bed to make the furnace under the condition
of insufficient combustion.

4.7 When the amount of oxygen is reduced continuously and the temperature of bed increase
to 790℃, the combustion air amount should be increased gradually to make it reaches above
23940Nm3/h; the temperature of airway burner should be decreased to 540℃ at this time and
the ratio of air and coal should be kept.

4.8 In startup, the required superheat steam temperature should be maintained by the
following method:

The superheater degree of the steam temperature goes into screen superheater and high
temperature superheater after going through the primary and secondary attemperator at least is
about 11℃. The min limited value of the steam temperature behind water spraying de-
superheat is shown in attached drawing 14----the min limited value of steam temperature after
water spraying de-superheat.

4.9 When the steam pressure and steam temperature are proper, the warming, rolling up, and
acceleration of steam turbine can be done.

4.10 When the rotating speed of turbine reaches to the synchronized rotating speed and the
flow of feeding water is stable, or the steam flow is bigger than 7%, the stop valve on the re-
circulating pipes from economizer to down comer should be closed.

4.11 When the steam amount entered in steam turbine is 10% of rated steam amount, the drain
water valve of the outlet header of high temperature superheater and the pipes behind it
should be closed.

4.12 If the operating conditions are satisfied, the water level of drum, the temperature of
superheat steam, and the air amount can be controlled automatically.

4.13 When the coal feeding is increased gradually, the output of the high speed diesel oil
igniter under bed should be reduced gradually till the temperature of bed is higher than 830℃
and the oxygen content is stable.

4.14 When stop the operation of high speed diesel oil igniter under bed, the combustion air
flow and coal amount should be adjusted to make the temperature of bed reaches about 900℃
and the oxygen amount should be kept at 3.5% at the same time.

4.15 In normal operation, the supplying amount of limestone will be changed along with the
amount of coal feeding in proportion. The ratio of limestone and coal should be amended
according to the thickness of SO2 in smoke.

The attached drawing 3 is the relationship curves of the variation of the height of static bed

Page 45 of 110
Page: Page 46 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

material and the differential temperature of fluidized bed, cold state test should be done to
verify these curves before startup or in trial operation. The fluidized speed cannot be lower
than 1.2m/s in the period of combustion.

4.16 The slag cooler should be put into operation according to the following procedures.

a) Confirm the operation of ash removing system is normal and the water spraying cooling
system has the condition of auto operation.
b) The correct operation of water spraying system is shown in 1.4.14.
c) Confirm the insulation valve on the header of slag pipe is closed, and the governing valve
is opened partially.
d) When one slag cooler is on fault, the other slag cooler can operate with 100% output.

Ⅳ. Hot startup

The boiler in Vikram Thermal Power Plant can be shutdown for some time and be in hot
standby condition (banking fire hot standby). The hot standby of boiler refers to the condition
of the even bed temperature (after banking fire) is still higher than 650℃. If the even bed
temperature is lower than 650℃, the cold startup procedure should be followed in the next
startup.

1 Banking fire

When the boiler is banking fire, the supply of coal should be stopped firstly, and the oxygen
amount at the outlet of boiler should be monitored. Once the oxygen amount begins to
increase, the air supply to furnace should be stopped to reduce the heat loss of fluidized bed to
minimum. The increasing of oxygen amount expresses most fuel in material layer has been
combusted completely, so the banking fire hot standby can be done safely by reducing the air
flow to zero. And then, IDF, FDF, coal feeding boosting air fan, and the air fans in limestone
feeding system should be stopped. But the operation of “J” valve air fan should be kept after
the above air fans and other air fans stop operating. The “J” valve air fan cannot be stopped
until the temperature of “J” is reduced to lower than 260℃ in order to prevent the
components of “J” valve from breaking. All valves and dampers should be closed to reduce
the thermal loss to minimum. The pressure of drum will be decreased because there is no
combustion in furnace, but the water level in drum must be kept at proper value.

The attached drawing 13 shows the relationship between the height of static bed material and
the differential pressure of bed. The attached drawing 11 shows the relationship between
fluidization speed and air flow. According to the measured air flow, the fluidization speed on
surface should be fixed using attached drawing 11 under the given temperature of bed; when
using designed fuel, the fluidization speed cannot be lower than 1.2m/s. The so called hot
standby of boiler refers to the condition of the even bed temperature is still higher than 650℃
after banking fire. If the even bed temperature is lower than 650℃, the cold start up
procedure mentioned above should be followed in the next startup.

When banking fire, because the heat capacity of boiler is bigger, the water level of drum
should be paid attention to. The steam exhaustion valve should be closed to maintain a certain

Page 46 of 110
Page: Page 47 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

pressure. the damper of IDF and all manholes should be closed after banking fire as soon as
possible to prevent cold air from entering in order to reduce the heat losses released from
material layer and guarantee the boiler wall does not be cooled suddenly in the period of
banking fire.

The time of banking fire is decided by the decreasing speed of the temperature of static
material layer. If the material layer is thicker, the temperature before banking fire is higher,
the temperature decreasing of static material layer after banking fire will be slower; the heat
loss of the static material layer after banking fire will be smaller; and the time of banking fire
will be longer. The time of primary banking fire can be maintained for 8-10 hours. If it is
necessary to prolong time, the bed can be started up again when the temperature of bed is not
lower than 700℃; and banking fire should be done again after the temperature of material
layer is increased.

2. Startup after banking fire

After banking fire, it should be started up again according to the different condition.

If the temperature of material is lower than 500℃ and the material layer is thicker, the cold
ash on the surface of material layer should be scooped out till the thickness of the left material
layer is about 350-400mm; and then a layer of red charcoal fire should be made as doing in
cold startup of boiler. If oil ignition under bed is adopted, the oil gun can be put into operation
directly and it can be started up rapidly.

If the temperature of material layer is lower than 700℃ but higher than 500℃, the cold
static material layer on surface should be scooped out till the thickness of left material layer is
about 350-400mm; and then small air flow should be used to loose the material layer. Start up
the air blower and IDF to adjust the air flow to critical fluidized air flow; the material layer
may be declined at this time, and it will be ascended after the bituminous coal is burned. The
air flow should be increased gradually along with the increasing of temperature. The coal
feeder should be started up. And then it should be transited to normal operating condition
gradually.

If the temperature of the static material layer is higher (not lower than 700℃), the air flow
can be increased to a little higher than the lowest air flow in operating, and then the coal
feeder can be started up.

What should be emphasized is the IDF should be started up firstly under any condition in the
start up process after banking fire, and then the primary FDF can be started up; the main
steam valve should be opened in time according to the steam pressure before the startup of
banking fire, and the water level, steam temperature and steam pressure should be monitored
closely.

3. In the hot startup of boiler, it should obey the following procedures:

1) Check the water level in drum. If it is necessary, the water level of drum should be
adjusted to normal water level (at 76mm below the central line of drum).

Page 47 of 110
Page: Page 48 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

2) The fuel and limestone system and ash removing system should be prepared well to
operate.
3) Start up J valve air fan, and set proper air flow to obtain suitable speed of fluidization.
The air fan should be under auto control condition. Start up IDF, FDF and coal feeding
boosting air fan according to the procedure in cold startup.
4) If there are large numbers of carbon particles that is not combusted completely or we
suspect there are, the combustion air flow has to be increased gradually to blow out the
bed layer and get the aim of controlling combustion efficiency.
5) Adjust the combustion air to the working condition of 25% BMCR. When all air fans are
put into operation, the coal feeder should be operated again and the corresponding air
flow should be built. Because the temperature of bed may reduce rapidly, it is very
important to build proper air flow and feeding rate of fuel. Or, the temperature and the
amount of oxygen will be not the expected one. If there is not expected response given by
unit to the proper air flow and material feeding, the hot start up should be stop to do cold
startup. It should be confirmed the blowing out has been done before the ignition of high
speed oil igniter under bed.
6) If the fuel supplied to fluidized bed is too much, the temperature of bed is high and the
fuel is not combusted completely in the period of hot startup again, the temperature of
bed maybe rise rapidly and the amount of oxygen will be reduced rapidly. If this
condition appears, the fuel cannot be supplied into furnace until the condition of fluidized
bed is stable. If the temperature of bed rises rapidly and nearly above 950℃, the
following items should be done before the temperature reached 950℃.
a) The air supplied to bed should be reduced to control the combustion.
b) If it is shown that the combustion of unit is unstable according to the oxygen amount
and the temperature of bed, the damper of the primary airway at the bottom of boiler
should be closed to lack the oxygen in combustion.
7) The temperature of bed maybe reduce rapidly when built the air flow again under the
condition of hot startup; the secondary air should be supplied firstly, and then the primary
air can be supplied to reduce the heat loss.
8) When the temperature of bed does not rise after 5 minutes of coal feeding, the hot startup
is failed. The coal feeding should be stopped and the blowing out should be done again;
and then normal cold startup of boiler will begin.

4. The operation in the procedure of ignition

After the ignition of boiler, the operators should do the relevant operation and checks under
differential pressure according certain requirement along with the rising of pressure gradually.
The time of these works is regulated clearly in the operation regulation. When the large-scale
boiler is boosting pressure, when the pressure reaches 0.19~0.39Mpa, the water at the bottom
of boiler can be discharged to make the heating surface of every part can be heated evenly and
discharge deposits to improve the quality of boiler water; and whether the water discharging
system is unblocked or not of water wall also should be checked. In the procedure of water
discharging, the variation of water level in drum should be paid more attention to; in order to
built normal water circulation, in the initial procedure of igniting boosting pressure, the time
of water discharging for the lower heater of water wall can be longer. When the pressure of
high pressure boiler goes to 1.47~2.9Mpa, the water should be discharged again. In addition,
in the medium-period of pressure boosting, the water can be discharged for one or two times

Page 48 of 110
Page: Page 49 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

according to the temperature of the wall of drum and the expansion of water wall. The water
discharging should be strengthened especially for the header whose expansion is small. When
the pressure of steam rises near to 0.29Mpa, it should be stayed for a while to check whether
there is leakage or not. The demolished manhole cover, hand-hole cover and the connected
bolt of flange should be twist tightly once again because when the temperature is high they
will become loose. The feed water of boiler should be supplied from blowdown. In
blowdown, the water level should be observed; it cannot be lower than the lowest safety water
level of water level indicator. After blowdown, the blowdown valve should be closed tightly
and whether there is water leakage or not should be checked.

When the pressure of boiler boosts to above 50% of working pressure, the thorough check
should be done for the boiler unit; if some faults are found, they should be eliminated in time;
the boosting pressure cannot be done until every thing is normal.

When the pressure boosts to 1/3 of working pressure, the works of draining water and
warming pipes should be done to avoid from water hammer when sending steam.

In the period of boosting pressure, the exhaustion valve and drain water valve of
superheater should be opened to cool the superheater properly by the flow of steam in it.

When boost the pressure of boiler, the main steam valve and its bypass valve should be
closed till the boosting pressure is near to the working pressure; and then open the bypass
valve to warm the pipes; the main steam valve cannot be opened until the pressure in pipes
are same with the pressure of boiler.

When several boilers are operated at the same time, the steam of other boilers has been sent
into the steam manifold, the boiler that is ignited newly open the bypass valve of main steam
valve slowly to warm pipes and balance the pressures at two sides after the steam temperature
and pressure reach the condition of combining steam; the motor-driven valve of main steam
should be turned up after the pressure is uniform, and then the bypass valve and the drain
water valve on the manifold of steam and on the main steam pipe should be closed to finish
the operation of steam combination. The steam pressure and water level should be kept
normally in the steam combination. If there is water hammer in pipes, the water should be
drained before steam combination.

Ⅴ Sliding parameter startup

The sliding parameter startup is generally adopted when the boiler and steam turbine are
started up at the same time. Its characteristic is: when the parameters of boiler are low, the
steam turbine can be started up; the procedure of the rising pressure of boiler is the procedure
of warming up, rolling, rising speed, taking load of steam turbine; while the pressure of boiler
reaches rated pressure, the steam turbine takes rated load.

In sliding parameter startup, the startup of steam turbine relates with boiler closely, and the
requirements of the heating for components of steam turbine is stricter, so the procedures of
temperature rising and pressure rising should take the heating requirement of steam turbine as
basis.

Page 49 of 110
Page: Page 50 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

The advantages of sliding parameter startup are:

1) The steam turbine and boiler are started up at the same time, so the total startup time is
shorten.
2) It increases the dependability of security. The whole unit rises temperature from low to
high at the same time, the condition of heating expansion of components will be better;
the working condition of the circulation of the boiler water is proved; and the cooling
condition of superheater is also good.
3) It improves the economy. Because the startup time is short, the loss of fuel and working
material will be reduced, and the unit can take load earlier to generate more electricity.

Chapter Ⅱ Shutdown of CFB Boiler

I. The classification of shutdown of boiler

The operating method of shutdown boiler is same with the method of banking fire basically.
The difference between them is air is still sending after the coal feeding is stopped; the fuel in
the middle layer of material lays is combusted basic completely; after the temperature of bed
decreases (generally, it is below 700℃), the supply air valve should be closed; the IDF, FDF
should be stopped. The ash exhausting pipe of slag chute should be open at last to remove the
all slag in bed.

The shutdown of boiler can be divided into three kinds: temporary shutdown, normal
shutdown and emergency shutdown.

1. Temporary shutdown

The temporary shutdown is also called banking fire shutdown. When the load of boiler is
zero temporarily, after banking fire for a certain time, the startup can be done at any time.
Water induction and blowdown should be done for boiler in the period of banking fire to
make the water level is a little higher than the normal water level. After the steam supply of
boiler is stopped, the main steam valve should be closed. The water level indicator should be
washed once according to the normal operation procedure after banking fire. The steam
pressure and the variation of water level in boiler should be checked usually in the period of
banking fire; whether the closes of the damper of flue gas way and air way are closed or not
should be checked to prevent the temperature of bed from decreasing too fast in the period of
banking fire.

2. Normal shutdown

The normal shutdown of boiler is the designed repair shutdown. Its operating procedures are:

1) Decrease load gradually, reduce the coal feeding amount and air amount. The coal
feeding, air entering, and air induction should be stopped while the load is zero. The main
steam valve should be closed. And the water in steam pipes should be drained.
2) The water level should be kept a little higher than normal water level before shutdown
completely. Because the temperature of furnace is very high, boiler water is still going on

Page 50 of 110
Page: Page 51 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

evaporated, if the steam and water system is not tight, the water level of boiler will be
decreased gradually that may even cause water shortage of boiler. The damper of flue gas
way should be closed to prevent the boiler from cooling sharply. When the pressure of
boiler is decreased lower than the pressure of atmosphere, the air vent valve or lift safe
valve should be open.
3) After shutdown of boiler, blinds should be set in the pipes of steam, feed water, blow
down, and so on. The thickness of blind should be met that is cannot be open by the
pressure in the pipes of steam and feed water and blowdown pressure of boiler in parallel
operation to make sure it is isolated with other operating boiler. No one is allowed to
work in drum before that.
4) The fouling at the water side of heating surface should be cleaned in time after
discharging water in shutdown. After the cooling of boiler, manhole should be opened
and it should be checked roundly to clean the ash deposit and ash fouling at the flue gas
side of every heating surface should be cleaned in time. Its maintaining method should be
confirmed according to the off-duty time of boiler.

3. Emergency shutdown

Emergency shutdown is emergency measure in order to prevent the accident from expanding
when the boiler or relevant equipment is on fault.

3.1 When one of the following conditions appears in the operation of boiler, the emergency
shutdown should be done:

1) The water level of boiler is lower than the visual border of the lower part of water level
indicator.
2) The feeding water amount is increased continuously and other measures are adopted, but
the water level still goes on declining.
3) The water level of boiler exceeds the highest visual water level (full water), and the water
level still cannot be seen after discharging water.
4) All water feed pumps are out of control or the water feeding system is on fault and it
cannot supply water to boiler.
5) All water level meters or safety valves are out of control.
6) The components of boiler are broken that threaten the security of operator.
7) The combustion equipment is broken, the wall of furnace is dilapidated, or the structure
of boiler is burned to become red and so on.
8) Other abnormal conditions appear that will threaten the safe operation of boiler.

3.2 The operation procedures of emergency shutdown of boiler are as follows:

1) Stop coal feeding immediately; and stop the air sending and air induction when the
temperature of bed layer decreases to lower than 400℃.
2) If the steam pressure of boiler is very high or has the trend of increasing rapidly, the
exhaustion valve of superheater should be opened to decrease the pressure of steam.
3) Open the valve of furnace after shutdown to prompt the convection of air and accelerate
the cooling of furnace.
4) When it needs emergency shutdown caused of water shortage, it is forbidden to feed

Page 51 of 110
Page: Page 52 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

water into boiler and the vent valve or lifting safety valve to exhaust steam can not be
done to prevent the accident from expanding by the variation of the temperature or
pressure suffered suddenly by boiler. If there is no water shortage, the pressure decreasing
method by alternation of water induction and blowdown can be adopted.
5) The feeding water should be stopped immediately in emergency shutdown caused by the
accident of full water in boiler. The blowdown valve should be open to discharge water to
reduce the water level properly. And the drain water valve on main steam pipe should be
opened to drain water.

Ⅱ. Normal shutdown of the boiler in Vikram Thermal Power Plant

1) Normal shutdown refers to reduce the load of boiler orderly to make the steam turbine
parallel off with boiler without the large fluctuation of temperature and pressure and
make the boiler to be under the hot standby condition as possible as it can, and the load
decreasing of unit can be finished automatically completely.
2) Blow out should be done before reducing load and shutdown boiler.
3) In the process of shutdown, the differential temperature between the upper wall and lower
wall of drum should be paid attention to control without exceeding 50 ℃.
4) If it is necessary, the temperature at the outlet of superheater can be governed by the
adjustment of the spraying water amount of attemperator. When it is not necessary to
decrease temperature, the stop valve on the attemperating pipe should be closed.
5) Check the drum and keep the normal water level in drum.
6) The load of unit should be reduced to the min stable load that should be maintained for
about 30 minutes to cool the fire resistant material of cyclone gradually. The main control
of boiler should be switched over to manual control method.
7) Close all stop valves at the outlet of the fuel material bunker, and the fuel of coal feeder
should be removed completely (if the operation of boiler should be stopped for a long
time). And the fuel in the fuel storage bunker should be reduced to the lowest safe storage
level.
8) The operation of limestone feeding system is stopped.
9) Monitor the oxygen amount and the temperature of bed. When the oxygen amount
increases and the temperature of bed decreases, the damper of the air valve to the bottom
of furnace should be closed, and the air sending to the large air tank to the bottom of
furnace should be stopped.
10) When the load of boiler be decreased to below about 10% of rated load, the drain water
valve on the main steam pipe at the outlet of high temperature superheater should be
open. And you should pay more attention to control the cooling velocity of boiler. These
drain water valve cannot be closed completely until the steam is not produced here.
11) After flame out of boiler, the IDF, FDF and blow out air fan and the fuel feeding blow out
air fan should go on operating for 5 minutes at least in order to blow out the combustible
material in furnace, and then they can be stopped.
12) After the operation of boiler is stopped, if it is necessary to maintain the pressure of
boiler, every air fan should be closed after blowing out. All dampers of relevant air fans
should be closed to make the unit go into hot standby condition. When the pressure of
drum has been decreased to below the lowest tuning pressure of safety valve and there is
not enough accumulated heat to produce steam so that the safety valve moved, the drain
water valve on the main steam pipe at the outlet of high temperature superheater should

Page 52 of 110
Page: Page 53 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

be closed. When there is not combustion in furnace, the drain water valve and vent valve
should be closed.
13) Before the combustion that is be done in order to keep pressure, the drain water valve on
the connected pipe of main steam at the outlet of high temperature superheater should be
opened. In the process of combustion, all of these valves should be open. The feed water
system should be put into operation once the steam is produced from boiler. The water
level of drum should be maintained to near the normal indicating value of water level
indicator in combustion.
14) If it needs the boiler to stop using for a long time or it needs repair, the boiler should be
cooled by air fan and the bed material should be removed by slag cooler. The drain water
valve at the downstream of the outlet header of high temperature superheater can be used
to drain water with the drain water valves of other superheater in order to decrease the
pressure of drum according to the requirement; cooling of unit should be done as uniform
as possible; the residual heat of the boiler wall and the components of boiler will produce
steam in a certain long time. In this period, the water level in drum should be kept near
the upper limited value of the visual measuring travel of the water level indicator. Once
all bed material is removed from boiler, the boiler should be blown out for 5 minutes.
And then, the slag cooler should exit the operation. When the boiler is cold enough to be
entered, the operation of air fan can be stopped.
15) The damper of fluidized air of slag cooler should be closed. The air sending of “J” valve
on the slag entering pipes of slag cooler also should be stopped.
16) The operation of material feeding system should be closed. The operation of FDF, IDF,
and coal feeding boost air fan should be stopped.
17) After the operations of FDF, IDF, and coal feeding boosting air fan are stopped, the air
fan of “J” valve should be gone on operating. The operation of “J” valve air fan cannot be
stopped until the temperature of “J” valve is cooled to below 260℃.
18) Cut off ash removing system.
19) If the steam and water inside of boiler should be removed completely, when the pressure
of drum decreases to 0.1MPa (gauge pressure), all vent valves and drain water valves
should be open to drain water in boiler. The temperature of the boiler water cannot be
higher than 120℃ in the period of drain water. It is suggested that the water draining
should be done when the boiler still has pressure even it is very small. The residual heat
of boiler is good for drying the inner surface of the pipes of boiler.
20) When the boiler is shutdown for short time, the drain water valve and vent valve of the
header of superheater should be opened.
21) It is not allowable to keep partial water filling for a long time in the period of shutdown
of boiler. The boiler should be filled fully with anticorrosion hydrazine deoxygenation
alkali water. If the shutdown period will last for several weeks or several months or the
condition of climate is not allowable to fill water into boiler, drain water and drying
should be done for drum. Several thin pans with certain amount of silica get should be
placed inside of drum to absorb the water content in drum to keep the inner surface dry. If
the shutdown period will just last for several days or little longer, all ash deposit inside of
boiler should be removed, because the ash deposit has sulfur content will absorb water
content so that to corrode the pipes. Under common condition, the ash in boiler should be
soot blown before the shutdown of boiler.

Chapter Ⅲ Operation of CFB boiler


Page 53 of 110
Page: Page 54 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Ⅰ. The characteristic of the adjustment of circulating fluidized bed boiler

The operator should adjust the working condition of combustion according to the
requirements and the quality of coal to guarantee the safe and economic operation of boiler
after it transfers from ignition into normal coal feeding of circulating fluidized bed boiler.

The operation of the steam and water part of circulating fluidized bed boiler is same with
common boiler that should be carried out according to the relevant safety operation rules that
will not introduced here. The performance of the material circulating system in the
combustion method of circulating fluidized bed boiler related with the heating transformation
of heating surface and the combustion of material closely, so its adjustment of combustion is
different from other boiler completely.

In the design and operation of circulating fluidized bed boiler, two problems should be paid
more attention to: one is the balance of material, and the other is the balance of heat. After
cracking, the coal and limestone will form certain size and they will be sent into the lower
part of combustion of material feeding device. The coal whose size is bigger will be left to
combust at the lower part, and some fine coal and limestone will be taken to the upper part to
finished combustion. It will go into separator at the outlet of burner, the fly ash that is not
collected by separator will be exhausted out of boiler through tail flue duct, the material
collected by separator will return to the lower part of burner to form the circulation of ash.

This has produced the distribution problem for the combustion quantum, i.e. the production
and absorption of every part of heat in the burner of circulating fluidized bed are balanced at
which temperature. The burner of circulating fluidized bed boiler can be divided into two
areas: one is the dense phase area at lower part, ad the other one is rare phase area at upper
part. The space rate of rare phase area is far greater than the dense phase area. The heat
released in the combustion of coal is also be divided into two parts; the fuel goes into the
dense phase bed area at lower part completely, and volatilization is released firstly that will be
combusted immediately; ad then fixed carbon is combusted followed it. The combustion of
the carbon of coarse particle appears in dense phase bed layer, but partial coke of fine particle
will be taken to rare phase area to combust. Because air is sent from the stages with different
height from furnace, the primary air amount is sent into dense phase bed area from the blast
cap from the bottom air room of bed, so the dense phase bed area can be under the reducing
atmosphere by controlling the proportion of the total air amount of primary air under the
condition of the quality of fluidization is guaranteed; the incomplete combustion of the
particles of carbon will form CO that will turn into CO2 in the further combustion by mixing
with secondary air at the upper part of furnace that will change the combustion quantum of
dense phase are to make higher temperature at the upper part f furnace. It is benefit for
combusting the fine particles of carbon fully.

The distribution of the combustion quantum is also decided by the cracking condition, the
content of volatilization, and the distributed ratio of primary and secondary air besides related
with the quality and quantity of the material circulation. If the coal is fine, the volatilization is
high, the proportion of primary air is small, the combustion quantum of rare will be bigger,
and the combustion quantum of dense phase area will be smaller. For the given fuel, in order
to steady the operation with full load, the coal whose size is 0~1mm is expected to more than

Page 54 of 110
Page: Page 55 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

40%. The lower the volatilization is, the bigger the proportion of the coal whose size is 0-mm
should be. After the side and quality of coal is confirmed, the primary air has heavy influence
to the adjustment of operation.

In dense phase bed area, the heat released by the combustion of coal is absorbed by three
parts: one is the heat taken away by the hot flue gas formed by primary air; the heat absorbed
by the around water wall; and the heater taken away by circulating ash. This is heat balance.

It can be known by calculation, in these three parts of heat, the heat taken away of the hot flue
gas formed by primary air is the most; the heat taken away by circulating ash is the second
one; the heat absorbed by the around water wall is min.

If the combustion quantum in dense phase area is confirmed, the heat taken away of primary
air and the heat taken away by the heating surface of the around water wall in dense phase
area are confirmed for given temperature of bed; the heat balance for reaches the temperature
of bed which is the heat taken away by circulating ash.

The heat taken away of circulating ash is decided by the circulating ash amount and the
temperature of circulating ash returning to dense phase area. The more the circulating ash
amount is, the lower the temperature of circulating ash is. And the bigger the differential
temperature of it and the dense phase is, the bigger the heat taken away by circulating ash is.
This will produce the balance problem of circulating material. The main functions of material
circulating system is collect the material whose particle is finer and send them to furnace to
control the combustion quantum in dense phase area effectively and improve the heating
transferring ratio in main loop. The quality and quantity of the material circulation have direct
relationship with the flow in main loop, combustion, and heat transformation, there exist a
balance.

The circulating ash amount is decided by the material bring rate adopted in the design of
boiler, and this rate is decided by the cracking condition of raw coal, the cracking and adding
amount of limestone, the air flow of furnace adopted in design and the type of separator and
so on.

1. The air sending amount and the ratio of primary and secondary air

In order to reduce the exhaustion amount of NOx, stage air sending is adopted in the
combustion of circulating fluidized bed to make the combustion is be done under the
condition of lower excessive air ratio. The primary air amount is 55 % 一 65 % of the
operating air amount under common condition, and the secondary air is 35%一 45%. For the
bituminous coal whose volatilization is higher, the primary air ratio can take the low limited
value. For meager coal and anthracite, the primary air ratio can choose the up limited value.

When the load is reduced, the secondary air can be reduced along with it. In the process of
the load is decreased from 100% to 70%, the coal distributed air and primary air cannot be
change, and just the secondary should be reduced till the cooling of the air opening is met. In
the process of going on reducing load, the primary air amount should be decreased properly
till to about 90% of the primary air amount in the operation with 100% load, and it can be

Page 55 of 110
Page: Page 56 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

operated under the condition of going on reducing load. But for the 0-8mm fuel, the velocity
cannot be lower than 0.7-0.8m/s that is the lowest limited value of primary air. i.e. when the
load is low, the operation should be done under high excessive air ratio. In order to steady the
operation, air amount and air pressure gauges should be installed in the primary and
secondary air way and the air way of material returning valve, and they should be calibrated.

The control of the air flow in combustion chamber should be 1.1m/s under the cold
condition without load. For example, for 75t/h circulating fluidized bed, the area of bed is 18
m2, the total operating air amount is 70000~80000Nm3/h, the area of circulating fluidized bed
is 32 m2, the total operating air amount is 130000~135000Nm3/h. what has to be explained is
what can decide the quality of fluidization is the air flow instead of the static pressure of air
room. Only there is enough fluidization speed, there will be good fluidizing condition. So in
operation, the air amount must be taken as the basis.

2. The thickness of material layer

The thickness of the material layer is decided by the head of FDF in the operation of
circulating fluidized bed, it is necessary to maintain certain thickness of material layer. The
thickness of material can be judged according to the variation of the static pressure of air
room. When the air amount is fixed, the static pressure increases that expresses the resistance
become bigger, and the material layer become thicker and vice visa. When the head of FDF is
fixed, the thickness of operating material layer is decided by the density of bed material and
the operating load. If the density of bed material is smaller, the thickness of material layer can
be thicker and vice visa. When the load is full, if the circulating amount of material is bigger,
the material layer should be thicker. When the load is lower, if the circulating amount is less,
the material layer should be thin. For 130t/h circulating fluidized bed boiler, the thickness of
material layer can be controlled at 700-1000mm commonly that can be adjusted according to
the static pressure of air room. When the fluidization of bed layer is normal, the indicating pin
of the static pressure of air room will swing cyclically. When the thickness of material layer is
too thick, the indicating pin of the pressure of air room cannot swing that expresses the
fluidization is bad, partial slag should be removed to decrease the thickness of material layer.
When the indicating pin of the pressure of air room fluctuate substantially, slag maybe
appears or a large amount of slag may deposit at the bottom of boiler; it should be removed in
time. If the bed material in operation becomes thin by itself, additional bed material should be
added in.

The continuous or half continuous slag removing method should be adopted for circulating
fluidized bed boiler as possible as it can, i.e. the times of slag removing should be more, and
the amount of slag removing should be less. The material layer of bed can be steadied by this
way to prevent the effective circulating particles from losing and it is benefit for the stable
operation of boiler.

In the operation, the primary air amount should be kept unchanged along with the increasing
of load. If the thickness of material layer become thicker and the indication of air amount
gauge decreases, the air valve should be turned up properly to maintain the primary air
amount. It is prohibit to turn up the air valve at random and just to use the static pressure of
air room as the monitoring method of operation.

Page 56 of 110
Page: Page 57 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

3. The temperature of material layer

The variation of the temperature of the material layer should be paid more attention to in
operation. If the temperature is higher than 1000℃, it is easy to slag and influent the
exhaustion of NOx and reduce the efficiency of desulphurization. If the temperature is too
low, it is bad for combusting all fuel and also bad for the output. If the temperature is too low
(600~700℃), it is easy to flame out. The normal operating temperature is 850-950℃. In this
range of temperature, the exhaustion of NOx is the lowest, and the efficiency of
desulphurization is the best. It can be increased or decreased according to its ash fusion point
and the combustion condition.

In order to guarantee the normal operation of circulating fluidized bed boiler, besides the
factors of air amount, air pressure, bed temperature, and so on, the more important is building
a stable and reliable material circulating procedure. A large amount of circulating ash can
transfer heat and increase the combustion quantum in furnace, and bring much heat to the
whole furnace so that the temperature of furnace can be reduce and the range adjusted by load
can be increased. The circulating material is composed by the ash in coal, desulphurization
agent limestone and additional material such as slag and sand and so on. For the coal of
middle and high sulfur content, limestone is used as desulphurization agent and also as the
circulating material. The grain size of limestone should be 0~1mm; if the grain size is too big,
the reaction of desulphurization will be bad. If the grain size is too bad, the staying time in
bed will be too short and it is also bad for the efficiency.

For the bituminous coal whose heat value is very high, and sulfur content is very low, it is
not necessary to adding limestone into desulphurization. Because the ash content in coal is
very low, it is not enough for meeting the need of circulating material just depending on the
ash of itself, some additional material from outside should be made up to instead the loss of
circulating material, so good coal pulverization and ash system should be supplied for
circulating fluidized bed. The coal pulverization system should meet the requirement of the
grain size of as-fired coal is 0-8mm in which the coal whose grain size is 0~1mm should be
get 40%~50%. The ash produced by this kind of fuel can become the material that can attend
the circulation.

For ash system, an ash bunker that has certain capacity should be set at the proper position
in front of boiler to storage the material that has certain grain size. If the fuel is changed,
when the ash content in raw coal is very low, the making up material can be sent into furnace
through ash bunker with raw coal to attend the circulating combustion. The circulating
amount should be adjusted at any time by adjusting the adding ash amount at outside
according to the variation of load to satisfy the demand of normal combustion. The ash
without carbon content needed in ignition can be added into bed directly through ash bunker
that reduce the labor intensity of manual laying bottom material largely. The more the
capacity of boiler is, the more obvious the function is.

The temperature of bed is taken as the main parameter in the adjustment of the load of
circulating fluidized bed boiler. The suitable operating temperature should be set according to
the necessary of coal and desulphurization by user. In order to make the boiler is operated
under the condition of the requirement of load can be met, the combustion must be adjusted to

Page 57 of 110
Page: Page 58 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

keep higher temperature and certain circulating amount at the upper part of furnace. When the
load is changed, just the air amount and the coal feeding amount should be changed. There is
self adaptability between the circulating system of material and the load.

The load bears on the efficiency of separator. The temperature of furnace will decrease
along with the decreasing of load, so the efficiency of separator will reduced, the carbon
content in the fly ash will increase. Put this part of fly ash return to furnace to combust can
reduce the carbon content in fly ash and improve the efficiency of combustion.

J valve is a kind of self balanced valve whose material level does not need to be monitored.
The disadvantages of it is if the ash level in the material leg is high, it is difficult to start up it
again; the air needed by it should has higher head; it should be started up at the beginning of
hot startup and is operated with constant air amount to avoid slag in material leg.

Ⅱ. The combustion adjustment of the operation of the boiler in Vikram Power Plant

1. Task of the combustion adjustment of boiler

Keep the evaporation of boiler conforming to the regulated load curve.

1) Balance the water induction and keep the normal water level.
2) Guarantee the quality of steam is qualified.
3) Maintain the normal bed temperature, bed pressure, steam temperature, and steam
pressure.
4) The discharging amount of SO2 and NOX should be in regulated range.
5) The security and economy of the operation of boiler should be guaranteed.

2. Adjustment of load

The adjustment of load is realized by change the feeding fuel amount and the corresponding
air amount. The adjustment of air and coal should be done fore many times but the adjusting
amount should be less to avoid the fluctuation of bed temperature.

1) When increasing load, the primary air amount and secondary air amount should be
increased a little, and then the coal feeding amount can be increased a little to increase the
differential pressure between material layers gradually, and then increase the air amount
and coal feeding amount, and adjust them alternatively till the necessary output.
2) When the load is reduced, the coal feeding amount should be reduced firstly, and then the
primary air amount and secondary air amount can be reduced properly, and a part of
circulating ash can be removed slowly to reduce the differential pressure between
material layers. This process should be done again and again till the output is necessary.
3) The controlling of the thickness of bed layer and the temperature of bed can be used as
the auxiliary method for the adjustment of load.

3. Adjustment of bed temperature

1) The temperature of bed is measured by the thermocouple placed on the air distributed

Page 58 of 110
Page: Page 59 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

plate. The operation range of the normal temperature of bed of this boiler is 790~920℃.
The temperature of bed should be monitored strictly in the operation, and the operation of
boiler should be done in this range of temperature. The high value alarming point of the
temperature of bed is 955℃. When the temperature is 990℃, the main fuel will be
tripped automatically. The lowest operating temperature of bed is 790℃, it is forbidden
that the temperature of bed is lower than this value under the condition of no assist
combustion. The alarming point of the low temperature of bed is 760℃. When the
temperature of bed is lower than 650℃, the main fuel will be tripped automatically
unless the air duct ignition burner is put into operation. But when the temperature of bed
decreases to below 540℃, no matter the air duct ignition burner operates or not, the coal
feeder will be cut off automatically. The actual operating temperature of the bed of boiler
can be increased higher than the above requirement properly under the premise of no
fouling in boiler along with the accumulation of the experiences of the operation of boiler
and the particular stress on the combustion efficiency or desulphurization efficiency and
the mastery of the characteristic of coal.
2) If the temperature of the bed layer is too high and the lasting time is too long, the bed
material will slag and the operation cannot go on. On the contrary, if the temperature of
bed layer is too low, the combustion will be not completely and even flame out. The main
method of the adjustment for the temperature of bed layer is to adjust the coal feeding
amount and the primary air amount; and the temperature of bed also can be adjusted by
change the limestone feeding amount and the slag removing amount.
3) When the temperature of bed exceeds the normal range, the air mixture and coal feeding
should be adjusted. When the temperature of bed is higher, the coal feeding amount
should be decreased properly, and the fluidized air amount should be increased properly;
and vice versa.
4) In order to prevent from too high temperature of bed, the feeding amount of limestone
can be increased and the operation of slag cooler should be stopped to increase the
amount of bed material to decrease the temperature of bed and the load till the
temperature of bed begin to decrease and vice versa.

4. Adjustment of bed pressure

Bed pressure is important parameters monitored in CFB boiler, and it is the important index
monitored the quality of fluidization of bed layer and the thickness of material layer.

1) When the operation of boiler is normal, the pressure of bed should be controlled about
6KPa.
2) Under common condition, the pressure of bed can be maintained normally according to
change the slag removing amount and limestone amount.
3) When the pressure of bed is higher, the primary air rate can be increased to make it is
easy to remove slag to reduce the pressure of bed to normal value.
4) When the bed pressure is too high, whether there is slag or not on bed layer should be
paid attention to.
5) When the bed pressure is lower, the slag removing amount and limestone feeding amount
should be reduced.

5. Adjustment of the discharging thickness of NOx, SO2

Page 59 of 110
Page: Page 60 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

1) Check the exhaustion of SO2; adjust the feeding rate of limestone manually or
automatically, guarantee the exhaustion value of SO2 is conformed with the local rules; it
is forbidden that the exhaustion value of SO2 is lower than 75% of standard value
because it can make the boiler operating with low efficiency.
2) Adjusting the temperature of bed is one of the methods of controlling the exhaustion
value of NOx in flue gas. When the temperature of bed is higher than 940℃, the NOx
will be increased obviously. It can be adjusted by changing the mixture ratio of primary
and secondary airs and the secondary air and the surplus air ratio and so on. When the
temperature of bed is in the range of 820~900℃, the exhaustion value of NOx is the
lowest.

6. Adjustment of mixture of air

The principles of the adjustment of primary and secondary airs are:

1) The fluidization, temperature of bed and pressure of bed is adjusted by primary air.
2) The total air amount is controlled by secondary air. Under the premise of the primary air
is enough for the demands of fluidization, temperature of bed, and the differential
pressure of material layer, when the total air amount is not enough, the secondary air
valve can be opened gradually; the amount of secondary air flow will be increased
gradually along with the increasing of load.
3) When it is conclude that partial bed materials have been not fluidized yet, the primary air
flow and the amount of slag removing should be increased temporarily.
4) The working condition of fluidization in bed, the combustion condition, and the material
returning condition should be paid attention to; if any problem is found, it should be
eliminated in time. When the temperature is increased or decreased, the ratio of primary
air and secondary air, the coal feeding amount and so on should be adjusted in time.

7. Others

1) Before the temperature of bed is decreased to 800℃, the startup burner should be put into
operation.
2) The variation of the temperature of resistance of every part should be observed in the
operation of boiler. When the temperature or resistance is abnormal, should check
whether it is caused by air leakage, too much surplus air, fouling and abnormal
combustion, and some measures should be taken to eliminate it.
3) Blow out should be done once by every shift.
4) The variation of the quality of coal should be paid attention to in operation; and the
operation of boiler should be adjusted according to the condition of the quality of coal.

8. Points for attention in the combustion adjustment

1) The main methods of changing the load of boiler are adjusting the coal feeding amount
and air amount. The temperature of bed is allowable to change in the range of 790℃ ~
911℃, and it is allowable to change substantially in short time. The temperature of bed
and the upper and lower differential temperature are adjusted by the mixture ratio of
primary air and secondary air; besides reducing load, the temperature of bed and the

Page 60 of 110
Page: Page 61 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

upper and lower differential temperature of furnace can be decreased by increasing the
amount of primary air. The differential temperature in furnace is better to keep min when
the load is high. When the steam flow is the required one, the temperature of bed should
be steadied at bout 900℃ again, and it should be kept by adjusting the amount of bed
material and adjusting the velocity of combustion. If it is possible, the best method is to
keep a fixed temperature of bed when the load of boiler is changed. Under any condition,
the mixture ratio of air and coal and the normal combustion should be guaranteed.
2) Monitor and control the oxygen amount at tail continuously to maintain the normal
combustion. The attached drawing 10 shows the control requirements for the oxygen
amount under different load.
3) The exhaustion amount of SO2 should be monitored and measured. The exhaustion
amount of it should be controlled in allowable range by adjusting the feeding amount of
limestone.
4) If the temperature of furnace is in the normal range in operation, the low exhausting value
of NOx is the characteristic of this boiler. Along with the increasing of the temperature of
furnace, the exhausting value of NOx also will increase with it, so the exhaustion of NOx
should be checked regularly in the continuous exhaustion monitor system. If it is
necessary, the operating temperature of furnace should be adjusted, and the distribution of
the air amount of secondary air also should be adjusted at the same time.
5) The fluidizing condition of bed layer should be checked periodically to check whether the
fluidization is uniform or not. If any thermocouple on air distributed plate shows low
temperature that expresses the bed material may be in bad fluidizing condition. If partial
bed layer loss fluidization, the air flow amount of bed layer has to be increased and the
slag removing amount should be increased temporarily. If the above measures cannot
improve the effect of fluidization, it is necessary to shutdown the boiler to check whether
the blast cap of air distributed plate is blocked or not or whether the bed material is
fouling or not, or whether the condition of the bed materials whose size is big are
accumulated together.
6) The differential pressure at the flue gas side of convection heating surface should be
monitored continuously; the ash depositing condition on heating surface should be
checked periodically.
7) Check whether the fuel and limestone feeding systems are blocked or not, whether there
is abnormal sound, vibration or not periodically. The belt transferring system, lubricating
and temperature measured points should be checked.
8) Monitor the height of the material level of fluidized bed continuously, the normal
fluidized height should be maintained by adding in limestone and removing more slag.
The purpose of removing of bed slag is in order to keep the proper total amount of
material and proper composition of material and also in order to control the exhaustion
amount of SO2.
9) Monitor the differential pressure of air distributed plate continuously. If this differential
pressure decreases obviously, the operation of instrument should be checked to confirm
whether its operation is normal or not, and whether the sensing line is blocked or not. If
the instruments and sensing line are normal, the operation of boiler should be stopped to
check the condition of air distributed plate.

Ⅲ. Blow out

Page 61 of 110
Page: Page 62 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

In order to guarantee the boiler gets rated load and high efficiency, the outer surface of all
pipes and components must be soot blew to keep clear and no ash.

1. After the boiler is put into operation, sootblower can be used to remove ash. The
sootblowing should be done according to the sequence without consider the load of boiler.
But the operation way of IDF and FDF should be changed to manual operation in sootblowing
period when the boiler is operated below 50% load.

2. The operation of blow out is one part of the operation of boiler; in order to get the best
cleaning effect; the following items should be monitored and checked:

2.1 During the period of shutdown of boiler, the ash depositing condition in convection pass
should be checked.

2.2 Monitor the temperature of the wall of pipe of high temperature superheater and the
temperature of the steam at outlet.

2.3 Monitor the change of the flow of spray water of attemperator.

2.4 Monitor the temperature of flue gas at the outlet of economizer and air preheater.

2.5 Monitor the change of the differential pressure between the air side and flue gas side of air
preheater.

2.6 Monitor the resistance at the flue gas side through the tail heating surface.

In conclusion, the above parameters of boiler should be monitored when the blow out system
is put into operation for the first time. And a kind of better blow out procedure should be
adopted. The system should be monitored periodically to avoid emergency shutdown out of
plan.

Ⅳ. The adjustment of steam temperature (water jet attemperating)

The temperature of the steam that goes into the inlet header of screen superheater and the inlet
header of high temperature superheater and then goes through water spraying attemperator
should be 11℃ higher than the saturated temperature under the pressure of the inlet of
connected pipe (Shown in attached drawing 15).

1 The factors that can influent the temperature of steam:

1) The amount of fuel changes;


2) The negative pressure of furnace changes;
3) The proportion of primary air and secondary air changes;
4) The changes of excess air coefficient;
5) The changes of the pressure and temperature of feed water;
6) The changes of load;
7) The changes of the quality of coal;

Page 62 of 110
Page: Page 63 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

8) The changes of the amount of de-superheating water;


9) The ash collection, foul, ash blowing out on heating surface;
10) The boiler leaks air and has leakage;
11) The water level of drum changes;
12) The pressure of superheated steam changes;
13) The fineness of coal particle changes;
14) The temperature and pressure of bed change;
15) The operation and stop of limestone system;
16) The material returning system is abnormal.

2. Adjustment of steam turbine

1) The water jet attemperators of primary superheater and secondary superheater are
adopted to adjust the steam temperature of boiler; the primary is used as coarse
adjustment and the secondary is used as fine adjustment.
2) The temperature of the outlet of superheater should be maintained at 540+-105℃;
3) Pay attention to the influence of the change of pressure to the temperature of steam and
the influence of the pressure of feed water to the amount of de-superheating water, master
its law and adjust it in advance;
4) The temperature of steam can be increased by blowing out by superheater;
5) In the course of the adjustment of the temperature of steam, the temperature of the wall of
every pipe section should be controlled in the allowable range strictly;
6) The change of the temperature of steam should be paid attention to under the following
conditions:

 When the load is reduced;


 When the combustion is unstable;
 When the HP heater is put into operation or exit the operation;
 When the change of the kind of coal is big;
 When the change of the pressure of feed water is big.

Ⅴ. The adjustment of the pressure of steam

Except the startup and shutdown of boiler, in the normal operation, when adopt the operation
with constant pressure, the pressure of superheated steam should be maintained
at9.81±0.1MPa. When adopt the operation way of constant-sliding-constant, sliding pressure
operation should be adopted at 50%~90% rated load; and constant pressure operation way
should be recovered when the load is lower than 50% rated load.

1. Stabilize the combustion of boiler and control the fluctuating range of the pressure of steam
by adjusting the amount of coal feeding to boiler according to the demands of the height of
bed and temperature of bed under different load.

2. Pay attention to the corresponding relation among the pressure of steam, load and the
differential pressure of furnace; the differential pressure of furnace expresses the particle
concentration at dilute phase area and it has very important function for the control of
pressure and load.
Page 63 of 110
Page: Page 64 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Ⅵ. Adjustment of water level

1. The water supply should be even and continuously in operation as possible as it can; and
the water level of drum should be kept normally.

2. The zero water level of drum is at 76mm below the central line of drum, and the water level
of drum is maintained between ±50mm. the limitation of the water level of drum: when the
water level of drum reaches -200n or +120mm, the visual and audible alarm should be sent;
when the water level of drum reaches -2810mm or +200mm, the MFT will act.

3. When the water feeding is at automatic state, the variations of its operation and water level
should be monitored strictly. If the automatic control of it is out of control, it should be
switched over to manual adjustment in time.

4. The normal water level should be kept in operation. The variation rules of the steam flow,
feed water flow, and feed water pressure should be paid attention to obvious usually. The
difference of the feed water flow and steam flow should be obtained; when the water level
changes, it should be adjusted in time.

5. The local water level indicator should be taken as the water level of boiler. The secondary
water level indicator is taken as the basis of monitor and adjustment.

6. The water level meter should be washed and calibrated once every shift under normal
condition;

Section Ⅸ Emergency Treatment of Boiler

The accident in power plant is one of the misfortunes for the production of industry and
agriculture. The emergency shutdown of power plant not only makes the power plant itself
suffers damage, but also influent the production of other occupation and the lift of human
directly.
Page 64 of 110
Page: Page 65 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Quite a few accidents in fossil fired power plant are caused by the accidents of boiler. The
reasons of the accidents appears in boiler section are many: such as the qualities of design,
manufacture, installation, and maintenance of equipment are bad; the technology of the
operators are not skillful, the operators work careless and the judges and operations are wrong
and so on when accident is found. The first responsibility of the operators of boiler section is
preventing the accident actively to avoid the accident of boiler as possible as he can. So, the
operators should familiar with the conditions of equipment and master the operation technique
skillfully, maintain the equipment carefully, operate correctly; when accident appears, the
operators should be composed and even-tempered, judge it correctly, deal with it accurately
and rapidly, eliminate the root of accident as soon as possible, insulate the accident place to
prevent from expanding.

Chapter Ⅰ General principle of emergency treatment

1. When accident happens, the operator should eliminate the root of accident as soon as
possible to limit the development of accident to release the from the threaten to human
and equipment;
2. Under the precondition of guaranteeing the security of human and the equipment is not
broken; the operation of unit should be maintained as possible as you can;
3. The operators are required to be level-headed, composed and even-tempered and to judge
the condition rapidly and deal with it decidedly to eliminate the accident at embryonic
stage to prevent from expanding;
4. The time, phenomenon, treatment procedure of the accident should be recorded
specifically and report to relevant leaders in time.

Chapter Ⅱ Important preventive measure of the operation of boiler

1. Furnace gate

In operation, the furnace gate at the positive pressure area at the bottom of furnace is not
allowable to open to prevent from hurting person.

2. Limitation of the pressure of furnace

The unit and auxiliary equipment will be broken seriously caused by too large negative
pressure or too large positive pressure of furnace, so the pressure of furnace has to be
controlled in operation, and the following controls can put into operation dependably before
startup.

1) The negative pressure of furnace should be monitored (measured at the balanced point of
the outlet of furnace), and this negative pressure should be controlled in the range of -127
~+245Pa automatically.
2) The main fuel trip should be set at ±2489Pa of the pressure value at the outlet of furnace
(the inlet of cyclone separator) with 5 seconds delay.
3) The trip of IDF and FDF should be set at±3744Pa of the pressure value of furnace area
without delay.

Page 65 of 110
Page: Page 66 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

3. The water level and differential temperature of the water level of drum

The normal water level of drum is at 76mm below the central line of drum; the alarm water
level is adjusted at -200mm and +125mm of corresponding to normal water level; the
shutdown water level should be adjusted at -280mm and +200mm corresponding to normal
water level.

When the drum is under low low water level working condition (lower than normal water
level 280mm), or high high water level working condition (higher than normal water level
200mm), main fuel trip, and the IDF and FDF trip; in order to prevent the boiler from
suffering too large hot stress, the differential temperature of the upper wall and lower wall of
drum should be controlled not exceed 50℃. The temperatures of upper wall and lower wall
should be monitored in the main control room, and there should be differential temperature
indicator in main control room.

The dependability of the all water level indicators of drum should be paid more attention to. It
is suggested to check once at every shift. The contents of check include all double color water
level indicator, electric contact water level indicator, and water level record instrument. The
water level of drum can be changed in check in order to obvious the reactions of all indicator
and water level indicator.

4. Safety valve

All safety valves are adjusted by its manufactory, but it should be calibrated again under real
operating conditions at the first startup of boiler and boosting pressure. If some safety valve
does not trip or return sit improper when its nameplate pressure is reached, this valve has to
be adjusted again. It is forbidden to change the tuning value at random.

5. Requirement for excess air

In order to maintain good combustion, should pay attention to control the excess air ratio of
furnace to guarantee the proper proportion of air and coal in combustion. The excess air ratio
at the outlet of furnace in operation is controlled by measuring the oxygen amount at the
outlet of tail flue duct. The corresponding oxygen amount value is controlled about 3.5% at
rated output (volume ratios, take wet flue gas as basis). The relationship of this oxygen
amount with the load of boiler is shown in attached drawing 10. The above measured value of
oxygen is just a reference; the best value should be set by combustion adjustment. The
operation whose excess air is lower than the one set above is bad for the good combustion and
safety operation of boiler. The oxygen analyzer should be repaired and calibrated before the
startup at any time of boiler and periodically.

6. Distribution of the temperature of bed

The temperature of bed is measured by the thermocouple arranged on air distributed plate.
The normal bed temperature range of this boiler is 790~920℃. The temperature of bed should
be monitored strictly in operation and the boiler should be operated in this range. The high
value alarming point of the temperature of bed is 955℃. When the temperature reaches

Page 66 of 110
Page: Page 67 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

990℃, the main fuel will be tripped automatically. The lowest operating bed temperature is
790℃. Under the condition of no auxiliary combustion, it is not allowable to lower than this
level. The low value alarming point of the temperature of bed is 760℃, when the temperature
of bed is lower to 650℃, the main fuel will be tripped automatically, unless the airway
ignition burner is put into operation. But when the temperature of bed goes down to below
540℃, no matter the airway ignition burner is operating or not, the coal feeder will be tripped
automatically.

Along with the accumulation of the operation experience of boiler and the mastery for the
characteristic of coal, the actual operating temperature of bed can be increased properly that is
higher than the above demand.

7. The temperature of heating surface

Wall thermocouples are set at the relevant positions of steam loop. The positions of these
thermocouples are as follows:

Steam temperature
Part Position Number
alarm limitation
Drum Top and bottom 2 for every one

Screen superheater Outlet pipe ring 8 468℃

Low temperature superheater Outlet pipe ring 6 540℃

High temperature superheater Outlet pipe ring 9 452℃

The above thermocouples are positioned at the area that is not scoured by flue gas, so the
temperature obtained by them means the temperature of medium, these thermocouples and all
other thermocouples (including the indicator in control room) should be checked, and all of
them can be put into operation at any time. In the operation process of unit, the continuous
operation of unit can be kept if the steam temperature does not exceed the alarm limited value
shown on the above meter. When alarm appears, the operators should adjust it according to
the working condition to protect the security of equipment.

8. In the stopping operation of boiler every time, the ash depositing condition at the flue gas
side of tail heating surface should be checked; if serious ash deposits is found here, the
heating surface should be cleaned before startup again.
9. In order to prevent from blocking, rusting and oxidation and operation accident of
equipment, the air used for the operation of boiler, no matter used as seal air, inject or
automation should be no dust, no oil, and no water.
10. Before start up IDF, all HP safety interlock devices of furnace should be checked to
confirm they can supply proper values and correct switchover actions, and all of these
safety interlock devices have to be put into operation.
11. It is not allowable that the fluidized speed of furnace is lower than 1.2m/s (this is the min
fluidized velocity required to maintain the normal fluidization), shown in attached
drawing

Page 67 of 110
Page: Page 68 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Chapter Ⅲ Typical emergency treatment of boiler

1. Emergency shutdown of boiler


1.1 Emergency shutdown of boiler should be done when one of the following conditions
appears:

1) When the water level in drum is high and to +250mm;


2) When the water level in drum is low and to -200mm;
3) When the pipes on heating surface is broken and the water level cannot be maintained;
4) When the main pipes of feed water and the pipes of main steam explodes;
5) When the slag in boiler is very serious;
6) When all water level indicator of boiler are broken and the water level in drum cannot be
monitored;
7) When re-combustion appears in the flue gas duct in behind of the outlet of boiler and the
temperature of smoke removing rises abnormally to 200℃;
8) When the wall of boiler is broken and it may be collapse, and the security of person and
equipment are threatened;
9) When the system eject load and the pressure of steam exceeds the limited value, and the
safety valve refuse to act, and the exhaustion is not enough to relief pressure;
10) When the safety valve does not go back to original position after acting, and the
temperature and pressure of steam goes down to the unallowable value of turbine;
11) When all operator station of DCS system are in trouble and there is no dependable
standby operation monitor method;
12) When the power of I&C instrument is cut off, and the main operating parameters cannot
be monitored and adjusted;
13) When MFT should act but it refuse to act;
14) When fire appears in the boiler unit and it threaten the safe operation of boiler directly.

1.2 The procedure of emergency shutdown:

1) When the condition of emergency shutdown is satisfied, MFT will act. Deal with it
according to the action of MFT.
2) If MFT does not act, push down two “MFT” buttons to shutdown the boiler manually.
Confirm stopping to supply all fuel into boiler, and open the exhaustion to atmosphere of
superheater.
3) Change the auto operation to manual operation; control the water level of drum,
temperature of bed, temperature and pressure of steam well; turn down or close the de-
superheating water manual valve according to the temperature of steam.
4) After closing the feed water valve, when the water feeding of boiler is stopped, the
recirculation of economizer should be started up (except the condition that the
economizer explodes.)
5) If the end flue gas duct is burning again, the air fan should e stopped immediately. Close
the flue gas damper. And the ventilation is forbidden.
6) Adopt measures to eliminate trouble rapidly, and the preparation to recover the operation
should be done well. Report to superior, and write down the condition of trouble.
7) When it cannot be recovered in short time, feed water to high water level of drum (except
when the pipe of boiler explodes and the water level cannot be maintained), close the

Page 68 of 110
Page: Page 69 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

feed water valve, tell turbine section to stop the feed water pump and close the
continuous secondary blowdown valve, secondary adding valve and secondary sampling
valve.

1.3 Apply for shutdown the boiler

When one of the following conditions occurs, should apply for stopping the operation of
boiler:

1) When leakage appears in the steam and water pipes of water wall, superheater,
economizer and so on, and the water level still can be maintained;
2) When the qualities of the feed water of boiler, boiler water and steam go to bad seriously,
and the treatments taken for them are not effect;
3) When the temperature of the wall of superheater exceed the limited value, and the
treatments for it are not effect;
4) When all remote water level indicators are out of work, and they cannot work again in
short time;
5) When all oxygen meter is out of work;
6) When the slag appears in boiler, and the adjustments used for it are not effect, and the
normal operation cannot be maintained;
7) When the temperature of bed exceeds the regulated value, and it is not effect after
adjustments by many parties;
8) The quality of fluid is bad, and the adjustments of it are not effect;
9) When the slag removing system is in trouble and the slag cannot be removed after
treatments.
10) When the J valve material returning device is blocked, and the carried out measures are
not effect;
11) When the insulation of material returning device breaks off, and the wall of pipes is
heated to red;
12) The ash remover is in trouble and cannot work.

1.4 Main fuel trip (MFT)

Phenomenon:

1) MFT acts, sending alarm;


2) All coal feeder trip; the limestone system is cut off; the ignition system under bed is cut
off; the fast closing valve of fuel oil is closed;
3) The temperature and pressure of bed is reducing;
4) The temperature and pressure of steam go down; the flow of steam reduces seriously and
the water level of drum goes down firstly and then raise;
5) All air flow should be changed to manual operating method, and it should be kept at last
position;
6) Unless the air fan cuts off itself, or all air fan control should be changed to manual control
method, and keep the last position. If it trips because of the low level of drum, the guide
blade at the inlet of primary air fan should be closed to 0. Under the condition of the air
fan is cut off by itself, the air fan should obey its logical control procedure;

Page 69 of 110
Page: Page 70 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

7) The output signal of combustion control limits the auto control of IDF; the pressure of
furnace is guaranteed not exceed the limited value;
8) Unless the boiler is under hot restart up condition, or the logic of “regulated boiler blow
out” is built up;
9) The printer prints the time and reason of the action of MFT.

2. Reason:

1) Push down two MFT buttons of boiler at the same time.


2) The temperature of bed is higher than 980℃ (signal comes from the self combustion
control system).
3) Loss logical control power source.
4) Two in three logic controls display the pressure of furnace is high high value (+2489Pa)
(time delay).
5) Two in three logic controls display the pressure of furnace is low low value (-2489Pa)
(time delay).
6) Two in three logic controls display the water level of boiler is high high value (higher
than normal water level 200mm) (time delay).
7) Two in three logic controls display the water level of boiler is low low value (lower than
the normal water level 280mm) (time delay)
8) FDF trips.
9) The primary air fan and secondary air fan trip.
10) The total air flow is too low, and it is lower than 25% (with time delay). (the signal comes
from self combustion control system).
11) The combustion control system losses power source (signal comes from self combustion
control system).
12) The high-speed diesel oil igniter under bed is not put into operation, and the temperature
of bed is lower than 650℃.
13) The pressure to the air room of furnace is too high (with time delay) (the signal comes
from the self combustion control system).
14) Cut off of turbine.
15) The level of medium of cyclone barrel is high high value (with time delay).
16) All coal feeding booster fan is stopped, and the bypass is not open (with time delay).
17) The temperature is lower than 540℃.

3. The following action is followed with the cut off of main fuel;

1) Cut off of material feeder;


2) Cut off of limestone system;
3) Cut off of high speed diesel igniter under bed.
4) Cut off of rotating slag removing valve of slag cooler.
5) All controls of air flow are changed to manual control way, and keep the last position.
6) Unless the air fan is cut off by itself, or all controls of air fan should be changed to
manual control way and keep the last position. Under the condition of self cut off, the air
fan should obey its logic control procedure.
7) The output signal sending to combustion control to limit the auto control of IDF, thus the
pressure of furnace is guaranteed not exceeding the limited value.

Page 70 of 110
Page: Page 71 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

8) Unless the boiler is under hot restart up condition or the logic of “regulated boiler blow
out” is built up.

4. Treatment after the action of MFT:

If it is not caused by the trip of IDF, primary air fan and secondary air fan and the trouble
of DCS system, it should be solved according to the following principles:

1) Adjust the damper of air fan, and keep the normal negative pressure of furnace;
2) Adjust the flow of feed water and keep the water level of drum normally;
3) Find out the reason of the action of MFT rapidly;
4) If the reason of the action of MFT cannot be found out or eliminated in short time, the
operation of boiler should be stopped, and the boiler should be kept under hot standby
condition;
5) If the reason of the action of MFT can be found out and eliminated in short time, the hot
start up of boiler can be done to recover the operation of it;
6) If the boiler is shutdown because of the re-combustion of end flue gas duct, ventilation is
forbidden and all air fan should be stopped.
7) If it is caused by the trip of IDF, primary air fan and secondary air fan, the partial stacking
of bed material and stagnancy of fluidization should be taken into consideration in the
treatment beside above principles.

Phenomenon:

1) One or many displays of the value of bed temperature is large different from other
displays of the value;
2) All displaying value of bed pressure is static reading (the normal displaying value of bed
pressure is fluctuant value).

The procedure of self fluidization of bed material;

1) Put the adjustment of the air flow of boiler under the operating way of manual operation;
2) Turn up the general valve of primary air rapidly, and then recover it to original position;
observe whether the display of bed pressure return to normal or not;
3) If it has be done three times in 10 minutes and it is not effect, the further measures of the
arrangement of bed material should be taken to fluidize the bed material till satisfied;
4) Put the adjustment of air flow of boiler under the condition of auto control.
5) The operator must pay attention to that the unit has a large amount of energy in operation,
and it also has very large amount of energy after main fuel trip. So the water level of
drum and the proper steam amount controlled the pressure of steam must be kept.

The temperature of bed is too high or too low.

1. Phenomenon:

1) The measuring point of every bed displays high or low;


2) The alarm of high or low temperature of bed is sending;

Page 71 of 110
Page: Page 72 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

3) The pressure of main steam goes up or reduces;


4) The temperature of the outlet of furnace is higher or lower;
5) When the temperature of bed is serious high, it may cause fouling of bed
material or even slag in large area;
6) The temperature of bed is too low and the combustion is unstable.

2. Reason:

1) The graininess of coal is too big or too small and the quality of coal changes too
much;
2) The measure of thermocouple of the temperature of bed is in trouble;
3) The work of coal feeder is abnormal;
4) The distribution of secondary air is imbalance;
5) The slag removing system is in trouble;
6) The material returning system is blocked;
7) The limestone system cannot operate normally.

3. Treatment measures;

1) Check the thermocouple of the temperature of bed;


2) When the temperature of bed is high, the amount of coal feeding should be
reduced to reduce the output of boiler to make the temperature of bed keep at
920±40℃;
3) When the temperature of bed is low, the amount of coal feeding should be
increased to increase the temperature of bed;
4) Check whether the operation and control of coal feeder are normal or not;
5) Distribute the air reasonably, and adjust the proportion of primary and secondary
air;
6) When the combustion is not stable caused by the too low temperature of bed, oil
gun should be put into operation to help combustion;
7) Check the crushing system of coal; if it is in trouble, solve it in time;
8) If the high temperature of bed is caused by the block of material returning
system, some measures should be taken to evacuate the material returning device
smoothly; when it cannot be evacuate, the boiler should be shutdown.

Ⅴ The pressure of bed is high or low.

1. Phenomenon;

1) The alarm of high bed pressure or low bed pressure is sent;


2) The indication of bed pressure goes down or raises;
3) The amount of slag removing of slag cooler is too large or too small;
4) The indication of the pressure of water cooling air room is too high or too low.

2. Reason:

1) The trouble of the measure of bed pressure;

Page 72 of 110
Page: Page 73 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

2) The slag cooler is in trouble; the amount of slag removing is too small or too
large;
3) The amount of limestone feeding and the amount of fuel are abnormal;
4) The amount of primary air is abnormal;
5) The material returning system is blocked;
6) The crushing system of material is in trouble;
7) The increasing and reducing of the load of boiler are too fast or the quality of
coal changes too much.

3. Treatment measures:

1) The bed pressure is too high, the amount of slag removing should be increased
and the amount of material feeding should be reduced; when the pressure of bed is
too low, the amount of slag removing should be reduced; and if it is necessary,
increase the supplying amount of limestone or add bed material into boiler;
2) Check the pressure measuring point of bed, if there is any problem, eliminate it
in time;
3) When the crashing system is in trouble, it should be solved in time to make the
grain size of material in the qualified range;
4) If the material returning system is in trouble, relative measures should be taken
to solve this problem in time.

Ⅵ Water shortage of boiler

1. Phenomenon:

1) The water level of drum is lower than normal water level or the water level
cannot be seen from sight hole;
2) The water level alarm send the alarming signal of low water level;
3) The flow of feed water is smaller than the flow of steam abnormally (when the
water wall or economizer explodes, the flow of steam is smaller than the flow of feed
water).

2. Reason:

1) The feed water pump team is in trouble or trip; and the pressure of the manifold
of feed water reduces;
2) The equipment is on fault, such as the auto water feeding is out of service or the
water level indicator is blocked to form false water level;
3) The water level transmitting device is in trouble that cause the sudden change of
water level;
4) The operator is neglectful of the monitor and control of water level;
5) The drain water system and blowdown system of boiler leak or the amount of
discharging is excessive;
6) The range of load changing is big and the adjustment is not in time;
7) The feed water pipe or heating surface of boiler are explodes.

Page 73 of 110
Page: Page 74 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

3. Treatment measures:

1) First, compare the indicating values of all water level indicators to judge the
authenticity of the accident of water shortage and the condition of it;
2) Strengthen the water feeding manually to make the water level recover to
normal;
3) If blowdown is doing at this time, it should be stopped;
4) If the water level goes on reducing, the load should be reduced and the pressure
of drum should be reduced;
5) If necessary, start up the standby feed water pump;
6) The water level goes down to -200mm; emergency shutdown of boiler should be
done at this time;
7) The water feeding after serious water shortage should be approved by general
technical superintendent.

Ⅶ Accident of full water:

1. Phenomenon:

1) The water level cannot seen from the sight window of water level meter; and the
color of boiler water is dark;
2) The water level alarm send high water level alarm signal;
3) The flow of steam is smaller than the flow of feed water abnormally;
4) When serious, the temperature of superheat steam reduces, and water impact
appears.

2. Reason:

1) The auto adjustment of feed water is out of control or the pressure of feed water
is too high;
2) The operators is neglect of monitor and control the water level;
3) The changing range of load is too big and the adjustment of it is not in time.

3. Treatment:

1) First, compare the indicating condition of several water level indicators to judge
the true and false of full water and the condition of it;
2) The auto adjustment of feed water should be exchanged into manual adjustment
of feed water to reduce feed water;
3) When it is slight, can adjust it manually and increase the blowdown;
4) When the water level is +150mm, open the emergency water discharging valve,
and close it until normal;
5) When the water level raises to +250mm, emergency shutdown of boiler should
be done.

Ⅷ The pipes of water wall explode.

Page 74 of 110
Page: Page 75 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

1. Phenomenon:

1) When the pipes broken slightly and leakage occurs at the welding point, the
fizzle of steam will appear and the flow of feed water will increase a little;
2) When it is serious, there is obvious exploding sound at the exploded place; the
negative pressure of furnace become positive; the water level of drum reduces
sharply; and the flow of feed water is bigger than the flow of steam abnormally;
3) When the negative pressure control of furnace is at auto control condition, the
adjusting damper of IDF open abnormally, and the current of IDF increases;
4) The temperatures of the smoke at the inlet and outlet of cyclone separator
reduce, and the material back temperature of bin leg reduces;
5) The temperature of smoke emission reduces and the slag removing is difficult;
6) The pressure of bed increases; the differential pressure of bed increases; the
material of bed lumps; and the distribution of the temperature of bed is not uniform.

2. Reason:

1) The qualities of boiler water and feed water are not qualified for a long time, and
this unqualified water make scale in side of pipes that cause the partial heat resistance
increases.
2) The water circulation is bad caused partial over heat;
3) The material of pipes is unqualified and the quality of welding is bad;
4) The wearing of the outer wall of pipes is serious;
5) The water shortage of boiler is serious.

3. Treatment measures;

1) When the broken of water wall is not serious; Increase the amount of feed water
and maintain the water level of drum; the load of boiler can be reduced and apply for
shutdown according to the condition;
2) Oil should be put into operation to help combustion in time when the combustion
is not stable.
3) When the broken of water wall is broken seriously and the normal water level
cannot maintained; Emergency shutdown the boiler, and stop the water feeding to
boiler;
4) After shutdown, the power source of ESP should be cut;
5) Keep the operation of IDF, discharging the steam inside of boiler; if the reducing
rate of the temperature of bed exceeds the allowable value, IDF should be stopped;
6) After shutdown, the bed material inside of boiler should be removed as soon as
possible, and the ash deposits at the bottom of ESP and air preheater should be
removed completely;
7) Other operations should be done according to the normal shutdown of boiler.

Ⅸ The pipes of superheater explode.

1. Phenomenon;

Page 75 of 110
Page: Page 76 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

1) There is the sound of the steam spraying at superheater, and the flow of feed
water is bigger than the flow of steam;
2) The negative pressure of furnace reduces or changes, and the pressure of
superheat steam reduces;
3) The adjusted damper of IDF turns up abnormally, and the current of IDF
increases;
4) The temperature of flue gas reduces at leaking side.

2. Reason:

1) Scale occurs on the inner wall of superheater or the impurities blocks the pipes
that cause the heat transferring is bad;
2) The outer wall of pipe is wearing or occurs high temperature corrosion;
3) The structure of superheater is bad that cause the temperature of steam or
temperature of wall exceeds the limitation for a long time;
4) The quality of pipe material is not qualified, and the quality of welding is bad.

3. Treatment measures:

1) If the explosion of pipes is not serious, operate under the condition of reducing
pressure and load properly, and apply for shutdown.
2) When the pipes explode;
3) Emergency shutdown the boiler, and keep the operation of IDF, control the
reducing rate of bed temperature does not exceed the regulated value;
4) Keep the normal water level;
5) Other operations should be done according to normal shutdown of boiler.

Ⅹ Leakage of economizer

1. Phenomenon:

1) The water level of drum reduces; and the flow of feed water is bigger than the
flow of steam abnormally;
2) There is abnormal sound at the leaking place; and there is smoking and wet at
the un-tight place of flue gas duct;
3) The adjusting damper of IDF turns up abnormally, and the current of IDF
increases;
4) The temperature of the flue gas reduces at leaking side and the temperature of
hot air reduces;
5) When the pipes explode seriously; it is difficult to keep the water level.

2. Reason:

1) The quality of feed water is not qualified that cause corrosion and scale in pipes;
2) The flow and temperature of feed water always fluctuate in large range;
3) The material of pipe is not qualified, and the quality of welding is bad;
4) The wearing of the outer wall of pipes is serious;

Page 76 of 110
Page: Page 77 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

5) In the startup and shutdown of boiler, the use of the re-circulating valve of
economizer is improper;
6) Secondary combustion occurs near the economizer.

3. Treatment:

1) When the broken is not serious, the amount of feed water should be increase to
maintain the water level in drum; operates under the condition of reducing pressure
and load properly and apply for shutdown;
2) When the leakage is serious and the normal water level cannot be maintained,
emergency shutdown should be done;
3) Maintain the operation of IDF, and discharge the steam inside of boiler;
4) It is forbidden to feed water into boiler and open the re-circulating valve of
economizer;
5) After shutdown, notice the ESP section to stop the operation of every electric
field;
6) After shutdown, the ash deposits at the bottom of ESP and air preheater should
be removed as soon as possible;
7) Other operations should be done according to normal shutdown of boiler.

Ⅺ Slag in bed surface:

1. Phenomenon:

1) There is white spark in fluidized bed;


2) CRT displays the distribution of the temperature of bed and the pressure of bed is
not uniform extremely;
3) Slag can be seen from the sight hole; the bed material moves abnormally in
boiler or the color of fluidized bed is too dark;
4) The combustion is not stable extremely, and the relative parameters fluctuate too
much and the deviation is too big.

2. Reason:

1) The temperature of bed of boiler is too high;


2) In the operation of boiler, the proportion of air and coal is not proper for a long
time.
3) Before startup of boiler, the fluidized nozzles are blocked too many, or there are
some impurities that is fire resistant left in boiler;
4) In the course of shutdown, the fuel is not combustion completely and the tar
evolution cause low temperature slag;
5) In the course of startup, the fluidization is bad because partial superheating slag.

3. Treatment;

1) Increase the amount of primary air;


2) Reduce the temperature of bed properly; especially should pay attention to the

Page 77 of 110
Page: Page 78 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

temperature rising and the rate of temperature rising cannot seriously rise too much
when feeding coal;
3) Strengthen the exchange of bed material; remove the bad fluidized bed material
in time and fill new bed material;
4) After adjusting, if this phenomenon still does not improved, the boiler should be
shutdown immediately.

Ⅻ Re-combustion of flue gas duct

1. Phenomenon:

1) The temperature of smoke emission raises abnormally;


2) When re-combustion in horizontal flue duct, the amount of oxygen in flue gas
reduces and the temperature of main steam raises abnormally;
3) When re-combustion occurs in the vertical shaft flue gas duct, the temperature of
primary air and secondary air raise, and the temperature of the water at the outlet of
economizer raises;
4) The fluctuation of the negative pressure of furnace is big;
5) The un-tight place of fuel duct smokes.

2. Reason:

1) The proportion of air and coal in operation is imbalance;


2) In the startup course, the atomization of oil gun is bad, and the fuel oil operates
for a long time at the same time;
3) The coal particle is too fine or the negative pressure of furnace is too big;
4) After the slag of bed surface, the coal feeding is not stopped in time;
5) The flow velocities of the flue gas of firing, shutdown and low load operation are
low; and the combustibles that is not complete combustion is stacked in flue gas duct.

3. Treatment;

1) Blowing out should be done for the heating surface at the flue gas duct of
combustion section; if necessary, the load should be reduced;
2) If it is not effect after treatment, when the temperature of smoke emission raises
200℃, the emergency shutdown of boiler should be done;
3) All air fans should be stopped; and the combustion and air and gas system of
boiler should be closed;
4) Keep the continuous water induction of boiler.

ⅩⅢ The fluidization is bad.

1. Phenomenon;

1) The distribution of bed temperature is not uniform.


2) The air pressure in air room is not stable, and the fluctuation of the negative
pressure of boiler is big;

Page 78 of 110
Page: Page 79 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

3) The changes of discharging value of NOX,CO,SO⁴ are big;


4) The temperature of steam and pressure and flow of steam reduce.

2. Reason:

1) The bed material is too much or too small;


2) The air flow is too high or too low;
3) The fire resisting and wearable material inside of boiler falls off.
4) The blast cap is blocked;
5) The air fan is in trouble or the air valve moves wrongly or the operator operates
wrongly;
6) The slag removing and material returning system is in trouble;
7) Partial clogging appears;
8) The grain size of material is too coarse or too fine.

3. Treatment:

1) Adjust the fluidized air flow and air pressure, and the primary air flow can be
increased temporarily;
2) Adjust the coal feeding or limestone feeding in this area;
3) Strengthen the slag removing of this area or replace the bed material as soon as
possible;
4) When the measures are not effect and it develops seriously, apply for shutdown.

XIV The load reduces suddenly.

1. Phenomenon:

1) The flow of steam goes down seriously, and the pressure of main steam rises sharply;
2) When the pressure of steam is too high, the safety valve acts;
3) The water level of drum goes down firstly and then it raises;
4) Relative protection sends visual and audible alarm.

2. Reason:

1) The system of electric power network is in trouble;


2) The main switch of generator trips;
3) The main steam valve of turbine closes.

3. Treatment:

1) The coal feeding should be reduced rapidly or a part of coal feeds can be
stopped; when necessary, oil gun should be put into operation to stabilize the
combustion;
2) Open the exhaustion to atmosphere according to pressure;
3) The monitor and adjustment of water level should be strengthened;
4) When necessary, the material should be discharged through the emergency ash

Page 79 of 110
Page: Page 80 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

removing pipe of material returning device;


5) The preparation of taking load again should be done well; if it cannot be
recovered for a long time, should apply for shutdown the boiler.

XV J valve material returning device is blocked.

1. Phenomenon:

1) The level of medium in cyclone barrel goes up, and the differential pressure and
density of J valve raise;
2) The temperature of the bed of boiler raises and the pressure of bed goes down;
3) The temperature of material returning reduces; the air flow of air room reduces;
the pressure of air raises; and the temperature of the flue gas at the outlet of cyclone
barrel raises.

2. Reason:

1) The air flow and air pressure of the air room of material returning device is not enough;
2) The insulation and wearing material of cyclone fall off;
3) The blast cap of A and B air room of material returning device are blocked, the
loose air month is blocked;
4) Slag appears in bin leg;
5) The particle is too small.

3. Treatment:

1) Turn down the overflow valve, increase the air flow to the air room of material
returning device;
2) Blow out by compressed air;
3) Reduce the load of boiler properly and reduce the fluidized air flow of primary
air, improve the size of coal particle;
4) When serious, the emergency ash discharging valve should be open; and the
level of medium of J valve should be paid attention to in ash removing;
5) If the measures are not effect, apply for shutdown.

ⅩⅥ The auxiliary power is broken down.

1 Phenomenon:

1) The current of all rotating equipment goes back to zero, and visual and audible
alarm is sending;
2) The MFT of boiler acts;
3) The pressure of steam increases and the safety valve acts;
4) The temperature of steam reduces, and the water level reduces.

2 Treatment;

Page 80 of 110
Page: Page 81 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

1) Close the damper at the inlet and outlet of every air fan manually;
2) Parallel off the desuperheating water and the continuous blowdown;
3) Close the general valve of feed water;
4) Close the intake oil valve and back oil valve of fuel oil;
5) Reset every tripped rotating machine and put them at manual operation position;
6) If the power source cannot be recovered in short time, the boiler should be
shutdown;
7) After the power source is recovered, the feeding water of boiler should be
approved by general technical superintendent.

ⅩⅦ Others

The trips of IDF, HP fluidized air fan, primary air fan, secondary air fan and main fuel of
boiler occur, the boiler should be shutdown.

Page 81 of 110
Page: Page 82 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Section Ⅹ Boiling Out and Chemical Cleaning of CFB Boiler

Chapter I Boiling out and drying out of CFB boiler

Ⅰ. The aims of boiling out and drying out

The aim of boiling out is clean the oil and grease inside of boiler. The cleaning medium is
usually alkali solution. A very thin layer of oil, grease, grease membrane and its re-solvent on
the heating surface of boiler will resistant the heating transferring seriously. The adiabatic
membrane blocks the fast transfer of heat energy from metal to medium, and make the
temperature of metal wall raise caused the pipes of boiler superheat and bag even explode
when serious.

The aim of drying out is removing the water content in fire-resistive material after the
installation of circulating fluidized bed boiler.

Generally speaking, boiling out, and drying out can be done at the same time.

Ⅱ. The preparation of boiling out and drying out

Page 82 of 110
Page: Page 83 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Drying out should be done after the following conditions are met: The assembly of boiler
and its auxiliary equipment have been finished and the cold state trial operation has been
finished; various electric device, I&C instruments, and auto adjusting device have been
installed; and some of them have been commissioned and they can met the requirement of
drying out; the boiler wall, flue duct and air way have been installed well, and the insulation
of the pipes of boiler has been fixed. All valves and holes on the boiler wall should be open to
dry naturally for certain time to prepare for drying out. The maintenance time of the fire
resistant, wearing, and insulating materials have been get the natural maintenance time
required by the supplier of material. Before drying out, it should be isolated with other
operating boilers, and the impurities and ash deposits inside of the furnace, flue duct, and air
way should be removed completely. The soft water after treatment should be add in boiler to
the low water level of water level indicator; and then the water level indicator should be
washed according to the normal procedure. Check whether the economizer is filled with soft
water fully.

Set the operation procedure of drying out and draw the curve of drying out.

Ⅲ. Attention points in boiling out and drying out

1) Before boiling out and drying out, the preparation and organization of boiling out
and drying out should be done well. The drying out procedure should be made well
and the curve of drying out should be drawn well that should be obeyed in the whole
process of drying out with the requirements of drying out according to the different
type of boiler and the different structure of the boiler wall. The operation procedure
of drying out and boiling out should be carried out strictly, the velocity of
temperature increasing cannot be too fast that should be done as even as possible to
prevent the boiler wall from breaking and out of shape caused by the too fast
temperature increasing velocity. When the high temperature cyclone is sued, the
influence of the temperature increasing rate to the stability of the expansion of fire
resistant material should be paid attention to.
2) In the procedure of drying out, should check whether there is broken or slump
phenomenon. The temperature of drying out should be controlled strictly. All valves
and holes of the boiler wall that needs drying out should be open to make it is dried
naturally before drying out.
3) In the drying out procedure, the checks should be done strictly, and it should be
adjusted in time to prevent from rising too fast of the temperature at partial part of
boiler wall. The dead area which the flue gas cannot reach should be paid more
attention to in drying out.
4) In the whole drying out procedure, the temperature of every part should be recorded
on the special tables and these tables should be kept well. After mending the fire-
resistant material at the partial part of boiler; to do drying out or not should be taken
into consideration according to the mended area and the drying out plan should be
made.
5) In the procedure of boiling out, the double color water level indicator may change
color seriously and may be permanent erosion. After boiling out and chemical clean,
all broken components should be replaced before next supplying water to unit.
6) The chemical medicines should be dissolved in water before dosing into boiler, and

Page 83 of 110
Page: Page 84 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

they cannot be dosed into boiler with solid state; when deal with the corrosive
material, the operation should be carefully to prevent from splashing eyes, skin, or
clothes. The operators should use protective goggles, rubber gloves, and cotton
clothes to protect themselves while mixing these materials.
7) The chemical reagents should not be added to boiler by dosing system with high
concentration, because the solution with high concentration may block the dosing
pipes and valves.
8) If the chemical medicines used for boiling out have to be filled into the drum of
boiler by the dosing system, before the chemical medicine are supplied to pump, the
concentration of the solution in mixing container should be diluted to 5%; after the
filling is finished, the pump and the dosing pipes should be washed thoroughly.
9) When there is high chemical concentration water inside of boiler, the safety valve
cannot be tuning until the chemical concentration of boiler water is near to normal
value at the initial startup stage.

Ⅳ. The chemical medicines used in boiling out

The alkali chemical medicines are usually used in boiling out of unit such as soda and sodium
hydroxide, because these reagents have the saponification ability of oil and grease and
produce soap compounds; these compounds are easy to remove by high pressure blowdown in
the procedure washing by cold water by high pressure soft pipe after the boiling out of boiler
is finished. Phosphate also can be used to clean the furnace of boiler thoroughly (i.e.
trisodium phosphate and disodium phosphate adding some soda or sodium hydroxide); at this
time, some brittle suppressant and economic “humid agent” should be added to the boiling out
solution. Caustic embrittlement is caused by sodium hydroxide in relative short boiling out
period. The concentration of alkaline in the boiler water is higher than the concentration in the
standard feed water of boiler, so, it is necessary safety protection measures adding to enough
brittle suppressants in the water of boiler, and sodium nitrate is better than other reagent.

In order to remove the oil dirt on the surface of the metal of boiler effectively, “humid agent”
should be blended into the admixture of boiling out. These reagents can increase the
“humectation” ability of water by reducing the surface tension, so that the adherence of oil
and grease can be reduced to the lowest condition. The admixture of “humid agent” and the
common boiling out chemical material will destroy the adherence of oil dirt so that the oil and
grease on the surface of metal can be removed.

The agents of boiling out are as follows:

Trisodium phosphate
5.25 g/1kg water
(crystalline state)
Soda powder 1.0 g/1kg water
Sodium nitrate 0.15 g/1kg water
Moistening agent 0.10 g/1kg water

Page 84 of 110
Page: Page 85 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

If there is no trisodium phosphate, it is allowed to use disodium phosphate (without water) to


instead of it. The weight of this kind of chemical medicine should take 2.5g/1kg water as
etalon.

Ⅴ The procedure of boiling out

1. Preparation of boiling out

The following procedures is worked out supposes using trisodium phosphate solution
(Na3PO4-12H2O). The drying out and boiling out are doing at the same time.

1) In order to remove all metal fritter, borings, wood flour, tools, fuzz, and other
impurities, the inner and outer surfaces of boiler and the auxiliary equipment should
be cleaned and checked carefully. The removing of these impurities before boiling
out is very important, or they may influent the operation of blowdown valve or the
operation of boiler.
2) The startup bed material can be added before boiling out or after boiling out.
3) Insulate the low reading water level indicator, pressure connecting components,
transmitters, and anything that may be broken in the period of boiling out. The water
filling should be finished used the feed water pump and pipes system that will be
used in normal operation so that the washing for the pipes and auxiliary equipment
in front of boiler can be done.
4) Except the connecting valves and air vent valves of instrument, all other valves of
drum should be closed.
5) Utilize the drain water pipe of main feed water pipe or the drain water pipe of
economizer to fill the chemical agent of boiler into the feed water pipes behind the
main feed water pump and in front of economizer. The filling of chemical agent just
can be done when there is main feed water flow, and the filling is better to be
finished before the water level of drum reaches the required level in order the
chemical agent in the feed water pipes of boiler can be washed clearly at the last
stage of water filling circulation of boiler.
6) Raise the water level to the lowest position that can be shown in the water level
indicator.
7) When water level in drum reaches the required water level, the bypass valve of the
feed water operating plate of boiler should be closed.

2. The procedure of boiling out

1) The sequence of procedure is startup the IDF and FDF, and then blow out the boiler.
2) Fix the combustion air damper to maintain enough air flow to the high speed diesel
burner under bed.
3) When the operation of high speed diesel oil igniter under bed is stable with low load,
the combustion rate can be increased according to demand to boost the pressure.
4) In order to prevent the drum from suffering too large heat stress, in the startup and
normal operation, the differential temperature of the wall between the top of drum

Page 85 of 110
Page: Page 86 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

and the bottom should be controlled in 50℃.


5) When the pressure of boiler reaches 0.1Mpa, the air vent valve of drum should be
closed.
6) The combustion of the high speed diesel burner under bed cannot be stopped until
the boiling out pressure is same with the designed pressure of this unit. Figure 9 is
the boiling out pressure recommended under differential designed pressure.
煮炉压力(MPa)

4
3.5
Boil 3
ing 2.5
out
pres 2
sure
1.5
1
0.5
0
0 5 10 15 20 25
Designed设
pressure
计压力( M
Pa)

Figure 9 The recommended boiling out pressure under different designed pressure

7) The operating feed water pump of boiler can guarantee that it can supply water to
boiler at any time.
8) The high speed diesel burner under bed should be operated intermittent according to
the requirement to maintain the pressure of boiling out of drum at least for 8 hours.
9) The water level should be raised to about 51mm from the top of double color water
level indicator.
10) When the water level reaches the high water level and the pressure is the boiling out
pressure of boiler, the high speed diesel oil igniter under bed should be closed.
11) Open the blowdown valve of boiler and the drain water valve of the lower header of
water wall to blowdown. When the blowdown pipes is using to blowdown, the valve
nearest to boiler should be open first and close last. The second valve on pipes
should be used to control the flow. The effect blowdown can be finished by open and
close these valves. The time of blowdown should be about 10 seconds.
12) Check the phosphate, PH value, silica, and total alkalinity of the sample of the boiler
water taken from drum and record its chemical concentration.
13) When the water level of drum goes down to the range within 51mm above the
bottom of double color water level indicator, make up water into the drum and ignite
the high speed diesel oil igniter under bed to maintain the boiling out pressure of
boiler.
14) Repeat the 11th clause and 12th clause at every four hours in 24 hours till there is no
oil appears in the sample of boiler water. If the water is needed to make up, it should
be done according to the 13th clause.
15) After boiling out, the drum should be checked and the deposits should be removed

Page 86 of 110
Page: Page 87 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

after the boiler is cooled and the water is discharged. In order to remove the deposits
further, the header should be checked. When there is no hand-hole supplied for
check on header, the end of the junction of feed water pipes or ascension pipes and
bend it to the other side. If there is no any impurity in header, it can be cleaned by
hand or washed by high pressure water by soft pipe. The inner surface of metal also
should be checked to confirm there is no oil adhering on it.
16) After the drum and headers have been cleaned and checked completely, the unit can
be closed, and the new manhole gasket can be fixed on drum. The hand-hole pipe
cover on header or the tube cutoff used for cleaning and check should be replaced.
Soft water or condensate water should be filled into unit and its pressure should be
boosted to near to the pressure of hydraulic test to do hydraulic test; and then the
water of this unit should be drained to normal water level of drum.

Chapter Ⅱ Chemical washing of economizer and evaporation system

Ⅰ. Treatment of feed water and the water in boiler

The samples of feed water and boiler water have to be tested to satisfy the demands of water
quality.

The quality of feed water should satisfy the regulation of the qualities of HP water in
GB/T12145-1999 “Quality Standard of Water and Steam of Fossil Fired Generating Unit and
Steam Driven Equipment”. The manufactory of boiler does not have the responsibility for the
corrosion, water scale, and explosion of pipes of boiler caused by unqualified quality of feed
water. The scale in the pipes of boiler will also influent the heat transferring and influent the
performance of boiler directly.

Ⅱ. The aim of chemical cleaning

It is a very effective method that using chemical solvent to clean the modern parameter boiler
unit. The new unit can be cleaned before initial operation, or in order to remove rolling fritter,
the cleaning can be done in the very short time after initial operation. A very thin layer of
uniform ferric oxide protective layer will be formed on the surface of heating surface after
cleaning. It is better to clean the new unit after operating for a short time, because a large
amount of air scale and silicon oxide material will go into boiler from feed water system and
condensate water system at the course of initial operation unless the chemical cleaning has
been done for front boiler system.

The requirement of different power plant for whether it is necessary to clean the operation
deposit of the unit that has been put into operation is different. It depends on the composition
of feed water system, and the history and quality of make-up water. Because the material of
operation fouling is very much, its cleaning is more complex than the cleaning of rolling
fritter. If scale appears on heating surface, the boiler cannot be operated reliably.

Page 87 of 110
Page: Page 88 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Ⅲ. Make sure the chemical cleaning is necessary

The cleaning before operation is necessary or not depends on the estimation of the rusty
condition of all circulating components in the course of installation. The factors influencing
the rusty condition have the measures of storage and the weather of power plant. Rust, loose
rolling fritter and the siliceous dioxide material will be removed from boiler in the period of
alkaline boiling out. Alkaline boiling out should be done for every unit. If other parts of
circulating loop are not cleaned completely, the impurities will be taken into the boiler, so it
maybe needs cleaning.

The deposit formed in operation is various and it is difficult to identify. Pipe cutting sample
should be done once at every year or every two years; and the weight of deposit should be
measured. Generally, the difference of the component of deposit is not taken into
consideration. If the deposit at working medium side in furnace of unit gets 20~40mg/cm 2; the
chemical cleaning should be taken into consideration in the next maintenance.

Ⅳ. Agent system of chemical cleaning

Two aspects should be taken into consideration in the chose of solvent: firstly, the
compatibility for the material should be taken into consideration; secondly, whether it is
suitable for removing the deposit should be taken into consideration. And these two aspects
are not separated from each one, because the dissolve of solvent to deposit may corrode the
pipe, but this phenomenon does not exist when there is no deposit.

Inorganic acid such as hydrogen chloride is usually taken as the solvent of cleaning residue
and scraps or the deposit in operation. If there is copper in deposit, the compound agent must
be used at the same time because copper will deposit on the surface of metal in acid solution.
The intensity is decided by the analysis, weight, and structure of deposit.

When hydrogen chloride is used in the cleaning before operation, the following conditions
should be satisfied:

Concentration of hydrogen chloride Max. value 5% (calculated with weight)

Temperature of metal and solvent 68℃

Contacting time of solvent 6 times

Concentration of anticorrosive agent Decide according to the conditions

Ⅴ. The operation of chemical cleaning

1) The chemical cleaning cannot be done by the operator without experience. If the
condition is out of control or the material used here is not comfortable, it will be
very dangerous. So deliberate plan must be made for it to guarantee getting the

Page 88 of 110
Page: Page 89 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

required chemical working condition and prevent from producing the dangers for
person and property.
2) In order to get the temperature of cleaning, condensate water or soft water can be
filled into unit and heated according to appointed method. Drum thermocouple (if it
is necessary, should use temporary thermocouple) is used for monitoring the
temperature to guarantee no temperature of any area exceeding the limitation of
temperature of solvent system and all anticorrosive agents. These limitations must be
specified by the supplier of solvent system. After the temperature is satisfied, the
water can be discharged into storage tank.
3) Before add the solvent into pump, should check whether the anticorrosive agent is
right or not; when the water is filled into boiler again, if the temperature of water
must be adjusted, the steam should be filled before the filling of solvent to avoid
corrosion for the mixed equipment.
4) It is forbidden to ignite when there is acid in unit, because that will make the
anticorrosive agent loss effect.
5) When there is solvent in unit, the intensity of acid, concentration of iron,
temperature and any condition or content needed for the controlling of special
solvent system should be monitored and surveyed regularly. When it is confirmed
that the cleaning is finished according to the indication the concentration of iron, the
solvent should be discharged out of the unit under the condition of filling nitrogen.
6) The solvent in the cleaned area can be cleaning once or many time by the feed water
and drain water of unit; iron composite agent should be added in cleaning water to
prevent from iron depositing on the cleaned surface.
7) When cleaning has been finished, alkaline solution should be filled into unit to
neutralize the residual solvent and passivate the surface to prevent from getting
rusty. The alkaline solution should be heated before filling.
8) Once passivation is finished, the drain water of unit should be checked and all
temporary pipes should be demolished.

Ⅵ. Chemical cleaning of superheater

1) Generally, chemical cleaning is not necessary for superheater system.


2) Under the following conditions, the chemical cleaning of superheater should be
done: the demand of special circulation; the cleaning before the operation of power
plant; or the cleaning to remove the deposits produced in abnormal operating
condition.
3) The cleaning should obey the general law of the compatibility of solvent and the
compatibility between solvent and structure material, i.e. it is same with the
demands of evaporation system.

Page 89 of 110
Page: Page 90 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Page 90 of 110
Page: Page 91 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Section Ⅺ Air Test of Boiler System

After the installation of new boiler is finished, the air test has to be done for it to check the air
and flue gas leaking condition of boiler system. These leakages should be mended in time to
guarantee the air tightness and safe operation. The procedures are as follows:

1) One blind should be installed at the inlet of IDF


2) Close all man-holes and observation holes.
3) Block all connecting places of all instruments.
4) Open all passage ways that are waiting for measure.
5) Operate the FDF to increase the pressure of system to 76.2mmH2O
6) Use proper visual and audible equipment to check the whole system. Soap
membrane, smoke bomb, and sound tester are very usable. These methods can be
used together.
7) Check and confirm all leakage.
8) Reduce pressure of system.
9) Mend all leakage.
10) If any leakage is found, after repairing it well, the air test should be done again.
11) Demolish all blind and blocked cover.

Page 91 of 110
Page: Page 92 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Section Ⅻ Appendix

Attached list Ⅰ Gas filling amount of “J” valve air nozzle

Temperature (℃) 93 843

Air flow of down-comer (Nm3/h)

NA Blast cap 290.02 132.18

A17~A20 Air filling hole 64.45 39.66

A13~A16 Air filling hole 64.45 39.66

A1~A4 Air filling hole 104.73 60.81

A5~A8 Air filling hole 32.22 13.22

Subtotal: 555.87 285.53

Air flow of riser pipe (Nm3/hr)

NB Blast cap 233.63 84.6

A9~A12 Air filling hole 32.22 13.22

Subtotal: 265.85 97.82

Total: 821.72 283.35

Page 92 of 110
Page: Page 93 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Attached list Ⅱ Thermal calculation summary table of designed coal of boiler

1. 100%B-MCR working condition of designed coal

Characteristic of fuel Parameter of boiler Thermal parameter


Carbon Car % 29.82 Flow of superheat steam D t/h 130 Volume of furnace Vt m3 969.3
Temperature of
Hydrogen Har % 2.41 t ℃ 540 Area of section of furnace Ft m2 33.54
superheat steam
Pressure of the outlet of Radiant heating area of
Oxygen Oar % 10.69 Pgr MPa.a 9.91 H m2 497.8
superheat furnace
Temperature of feed Heating load of the volume
Nitrogen Nar % 0.41 tw ℃ 210 Qv kw/m3 106.3
water of furnace
Air-intake temperature Heating load of the area of
Sulfur Sar % 2.06 ta ℃ 30 Qf kw/m2 3071.9
of air preheater section of furnace
Efficiency of
Water Mar % 50 ηt %  90.4
Performance parameter desulphurization
Ash Aar % 4.61 Loss of smoke emission q2 % 7.44 Working pressure of ddrum Pa MPa.a 11.09
Loss of chemical
Volatile matter Vdaf % 27.13 q3 % 0.05 Tempering method Secondary spray water desuperheat
incomplete combustion
Low heating Loss of physical Pressure of desuperheating
LHV kJ/kg 10292 q4 % 2.61 P MPa.a 11.53
value incomplete combustion water supply
Grindability Radiation and Amount of primary
HGI / q5 % 0.6 D1 t/h 5.915
index   convection loss desuperheating water
Physical heat loss of Amount of secondary
q6 % 0.6 D2 t/h 3.185
Characteristic of limestone slag desuperheating water
Thermal efficiency of Air amount of the inlet of
CaCO3   % 75 η % 88.51 Qa Nm3/h 130941.9
boiler (low heat value) boiler
Flue gas flow of the outlet
MgCO3   % 3 Combustion of fuel B t/h 36.94 Qg Nm3/h 169577.6
of boiler
Molar ratio of calcium
H2 O   % 2 Ca/s / 2.64 Temperature of bed θa ℃ 867
and sulfur

Page 93 of 110
Page: Page 94 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Consumption of
Other   % 20   t/h 9.07 Bottom ash ratio of fly ash / / 7:3
limestone

Up Up Down Down
High Low
Platen Convection Turning secondary primary secondary primary
Name Symbol Unit Furnace Separator temperature temperature economizer
superheater tube bunch room air air air air
superheater superheater
preheater preheater preheater preheater
Temperature
of flue gas at θ' ℃ / / / 853 841 812 673 508 257 238 199 162
inlet
Temperature
of flue gas at θ" ℃ 853 / / 841 812 681 508 257 238 199 162 137
outlet
Temperature
of working
t' ℃ 317 414 / 317 321 446 354 210 147 91 30 30
medium at
inlet
Temperature
of working
t" ℃ 317 468 / 321 / 540 452 313 198 192 147 91
medium at
outlet
Excess steam
α / 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.22 1.235 1.235 1.25 1.25
index

Page 94 of 110
Page: Page 95 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Attached drawingⅠCurve of the grain size of as-fired coal


Granularity distribution of coal

Designed graininess
distribution

Allowable range of variation


Screen percentage (%)

Grain-size (μm)

Page 95 of 110

Grain-size (μm)
Page: Page 96 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Attached drawing Ⅱ Curve of the grain size of as-fired limestone


Screen percentage (%)

Granularity distribution of
limestone

Designed graininess
distribution

Allowable range of variation

Page 96 of 110

Grain-size (μm)
Page: Page 97 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Attached drawing Ⅲ Side view of boiler

Page 97 of 110
Page: Page 98 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Attached drawing Ⅳ Top view of boiler


Page 98 of 110
Page: Page 99 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Page 99 of 110
Page: Page 100 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Attached drawing Ⅴ Diagram of steam and water system of boiler

Page 100 of 110


Page: Page 101 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Attached drawing Ⅵ Diagram of air and gas system

Page 101 of 110


Page: Page 102 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Page 102 of 110


Page: Page 103 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Attached drawing Ⅶ Equipment inside of drum

(2)

(1)
(3)

(4)

(14)

(13)
(12)

(11)
(5)

(10) (6)

(9)

(7)

(8)

(1) Uniform steam orifice (2) Steam receiving room

(3) Louver separator (4) Horizontal separator

(5) Wire mesh separator (6) Ascension pipe

(7) Anti-rotating device (8) Down comer

(9) Jacketed space

(10) The lowest water level (low water level trip)

(11) The lowest safe water level (low alarming water level)

(12) Normal water level


Page 103 of 110
Page: Page 104 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

(13) The highest safe water level (high alarming water level)

(14) The highest water level (high water level trip)

Attached drawing Ⅷ Layout diagram of centralized down comer &


draining connected pipe

Lower steam header of left side water


wall

wall
Low water
er back
stea er of
m head
head m
er of stea
front er
water Low
wall

Lower steam header of right side water


wall

Page 104 of 110


Page: Page 105 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Attached drawing Ⅸ Recommended boiling out pressure under different


design pressure

Page 105 of 110


Page: Page 106 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

煮炉压力(MPa) 4
3. 5
Boiling out pressure

3
2. 5
2
1. 5
1
0. 5
0
0 5 10 15 20 25
设计压力(MPa)
Designed pressure

Attached drawing Ⅹ Relation curves among flue gas wet volume %, oxygen
amount and load %

7
6
Oxygen amount

5
氧4

3
2
1

0
0 20 40 60 80 100
Load of boiler % MCR
锅炉负荷%MCR

Page 106 of 110


Page: Page 107 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Attached drawing Ⅺ Relation between the air amount of fluidized bed and
fluidized speed

120
/h×103)

100
至炉底风室风量(mn

80
3

600℃
60 750℃
900℃
Air
40 1000℃
amou
nt to
botto 20
m air
room 0
0 1 2 3 4 5 6
Fluidized air speed in furnace (m/s)
炉膛流化风速( m/s)

Page 107 of 110


Page: Page 108 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Attached drawing Ⅻ Cold startup curve

Cold startup curve of boiler


Temperature
Pressure

Load

Flow

Pressure of main steam Pgr


Temperature of main steam Tgr
Flow of main steam Ggr
Electric power of unit Ne
Thermal power of ignition burner Ni
Thermal power of fuel Nf
Temperature of bed Tb

Initial condition of ignition

Rolling up parameter of turbine

Time (hour)
Ignition

Synchronization
Rolling up

Page 108 of 110


Page: Page 109 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Attached drawing ⅩⅢ “J” valve jointing pipe

Page 109 of 110


Page: Page 110 of 110
Training Material for
Revision: A
VC 2x23MW Thermal Power
Project Date: 04th April, 2007

Attached drawing XIV Relation between the height of static bed material
and differential pressure of bed material

Heig
ht of
static
bed
mate
rial
on
air
plate
mm
Differential pressure
of bed material Pa

Attached drawing XV Min. value of steam temperature after reducing


temperature by sprayed water

390
380 Saturated
370 steam
饱和汽温
360 temperature

350 ℃
蒸汽温度℃

Ste 340
am 330 The lowest
tem steam
pera
320
310 喷水减温
temperature
ture after
℃ 300 后的最低
reducing
汽温
290 temperature
Ts+11℃
280 by spraying
270 water
Ts+11℃
260
0 1 2 3 4 5 6 7 8 9 101112131415161718192021Pressure
锅筒压力 of M
drum
Pa
MPa

Page 110 of 110

Das könnte Ihnen auch gefallen