Sie sind auf Seite 1von 2

Construction Auditing

Auditing Construction Contingency

By Ron Risner

In my last two columns we addressed make revisions. If these revisions are unforeseen conditions may include
the various reports and logs which help the result of errors or omissions by the building code changes, local or state tax
control the construction management architect (rework), then the architect law changes, unforeseen field conditions,
process, control project risks, and would be expected to pay for the changes. escalating materials prices, and owner
maintain the financial stability of a However, if the owner requests changes, scope changes. Knowing these situations
project. One of the concepts which we the architect will make the drawing can and do occur, to attempt to control
addressed was contingency. In this revisions and charge the owner—usually their financial risk, the contractor
column we will define contingency; look on an hourly basis. It is likely that will typically include an amount of
at why contingency is risky business; look design changes will occur, so the owner contingency in their bid documents. As
at the various types of contingency; and will often set aside a pool of funds to needed, the contractor has the discretion
then look further at how to both control cover the added design costs (a design to use their contingency to fund the
and audit contingency usage. contingency). It should be noted that in changes. There are several ways to
those cases where the design concept determine whether or not the contractor
Contingency Defined has not been finalized by the owner, the has a discretionary contingency: 1) read
Contingency is an amount of money owner may pay for errors or omissions. the proposal, 2) read the construction
reserved by the architect, contractor, agreement, 3) look for a contingency line
Contractor Contingency item on the Schedule of Values attached
or owner to pay for unforeseen design
or construction costs in the project. A contractor is keenly aware that there to their payment application, or 4) ask the
Contingency funds are usually included will be unknown situations which will contractor or project manager directly.
in the construction budget. occur as the project progresses. These Keep in mind that the contractor likes to
use the contingency—because they make
In my estimation, there are several more money—therefore I maintain that
types of contingency. They are: design the use of any contingency funds must
contingency, contractor contingency, be approved by the owner even if it is
owner contingency, contractor/owner discretionary.
contingency and program contingency.
Let’s look at these individually and Owner Contingency
determine the characteristics of each. Most owners are also aware there will
be unforeseen situations that occur on
Design Contingency
a project. Therefore, they include the
Architects and engineers try as hard as contingency as a separate line item in
possible to develop a set of construction the construction budget. For instance,
drawings that are infallible. However, no owner discretionary changes may
matter how hard they try there are almost change the type of windows for the
always errors or omissions embedded building, the layout of the lobby, or the
in their drawings. Sometimes, at the face of the building. It is not unusual on
last minute, the owner decides to make a construction project for the owner to
changes in how the building is designed include the owner contingency in their
(for instance, the owner may want the budget, but not tell the contractor such a
lobby to be laid out in a different fashion contingency exists. Owners who “hide”
than was originally agreed upon). In their contingency believe that a contractor
either case the architect must literally will attempt to use the contingency for
go “back to the drawing board” and change orders should they know it exists.

March 2010 Association of Healthcare Internal Auditors New Perspectives 37


one of several variables. If the construction A third way to control the use of
There are drawings are incomplete when a project contingency is to set up a contingency
breaks ground or it is a fast-track project, log. The log should show the original
several types of then an owner is likely to set aside more contingency amount, the amount of
contingency. money for unforeseen conditions. Likewise, each usage, the date of use, the purpose
if material prices are escalating, the amount of use and how much contingency
of contingency will likely be increased. remains. For each usage there should be
Keep in mind that change orders are
an associated contingency usage form.
a source of increased revenues for the Contingency as a Risk Keep in mind that most contingency is
contractor. I have seen completed projects
As an auditor, you may have already funded through a change order (e.g.,
where the contractor never knew the
deduced that money set aside for future as the contingency is drawn down it
owner had their own contingency.
use is risky business. Untapped funds is added to the amount owed on the
Combined Owner/Contractor become a potential source for contractors contractor’s Schedule of Values). Owner
Contingency to increase profitability. If they can use contingency usage however, can be
contingency for unnecessary change deducted directly on the budget as an
Sometimes a contractor and an owner
orders, their profits will increase. Why? “actual” cost, so be aware that several
decide to share a contingency. Under this
Because change orders are often inflated, scenarios exist when accounting for
approach they use the funds to share in
and contractors include both an overhead contingency usage.
changes which may occur on the project.
and profit markup.
Again, for control purposes the owner
should approve all uses.

Program Contingency Typically, total contingency will range from 1–3%


Sometimes an owner may have several of the project budget.
ongoing projects. Rather than set aside a
specific contingency for each project, the
owner may elect to include an overall Controlling Contingency Usage Conclusion
program contingency which can be used
As an auditor, you want to review Contingency usage is a high risk area
for any of the projects. The program
the controls surrounding any type of on a construction project because it is
contingency is controlled by the owner—
contingency. The first way to control a source of untapped funds. It should
again with or without the knowledge of
contingency usage is to make sure a be closely reviewed by an auditor
the contractor.
contingency usage form exists. For a during a construction audit. The best
Determination of Contingency contingency to be used, no matter who way to control contingency is through
Funding owns it—a form must be completed a contingency usage form, an approval
and signed by all appropriate parties. matrix, and a contingency log. NP
The amount of contingency set aside varies
I suggest that a contractor contingency
from project to project. I am not aware Ron Risner is founder and president of Risner
always be signed by the contractor,
of any rule of thumb that owners use to Consulting Group, Inc., of Orlando, Florida.
architect, and owner.
determine the contingency amount for He was formerly the Vice President of Internal
the architect, contractor, or themselves. Second, owner personnel that have Audit for a large commercial banking firm in
Typically, total contingency will range the authority to use the contingency Florida where he managed 50 auditors directly
from 1–3% of the project budget. Often should always sign owner and design and 100 indirectly. Risner Consulting provides
the owner arbitrarily sets aside a lump contingencies. An approval matrix based domestic and international professional construc-
sum amount. However, determining the on dollar thresholds is another means to tion consulting and audit services. The firm’s
amount of contingency is often driven by control contingency usage. website is found at www.risnerconsulting.com.

38 New Perspectives Association of Healthcare Internal Auditors March 2010

Das könnte Ihnen auch gefallen