Beruflich Dokumente
Kultur Dokumente
By Ron Risner
In my last two columns we addressed make revisions. If these revisions are unforeseen conditions may include
the various reports and logs which help the result of errors or omissions by the building code changes, local or state tax
control the construction management architect (rework), then the architect law changes, unforeseen field conditions,
process, control project risks, and would be expected to pay for the changes. escalating materials prices, and owner
maintain the financial stability of a However, if the owner requests changes, scope changes. Knowing these situations
project. One of the concepts which we the architect will make the drawing can and do occur, to attempt to control
addressed was contingency. In this revisions and charge the owner—usually their financial risk, the contractor
column we will define contingency; look on an hourly basis. It is likely that will typically include an amount of
at why contingency is risky business; look design changes will occur, so the owner contingency in their bid documents. As
at the various types of contingency; and will often set aside a pool of funds to needed, the contractor has the discretion
then look further at how to both control cover the added design costs (a design to use their contingency to fund the
and audit contingency usage. contingency). It should be noted that in changes. There are several ways to
those cases where the design concept determine whether or not the contractor
Contingency Defined has not been finalized by the owner, the has a discretionary contingency: 1) read
Contingency is an amount of money owner may pay for errors or omissions. the proposal, 2) read the construction
reserved by the architect, contractor, agreement, 3) look for a contingency line
Contractor Contingency item on the Schedule of Values attached
or owner to pay for unforeseen design
or construction costs in the project. A contractor is keenly aware that there to their payment application, or 4) ask the
Contingency funds are usually included will be unknown situations which will contractor or project manager directly.
in the construction budget. occur as the project progresses. These Keep in mind that the contractor likes to
use the contingency—because they make
In my estimation, there are several more money—therefore I maintain that
types of contingency. They are: design the use of any contingency funds must
contingency, contractor contingency, be approved by the owner even if it is
owner contingency, contractor/owner discretionary.
contingency and program contingency.
Let’s look at these individually and Owner Contingency
determine the characteristics of each. Most owners are also aware there will
be unforeseen situations that occur on
Design Contingency
a project. Therefore, they include the
Architects and engineers try as hard as contingency as a separate line item in
possible to develop a set of construction the construction budget. For instance,
drawings that are infallible. However, no owner discretionary changes may
matter how hard they try there are almost change the type of windows for the
always errors or omissions embedded building, the layout of the lobby, or the
in their drawings. Sometimes, at the face of the building. It is not unusual on
last minute, the owner decides to make a construction project for the owner to
changes in how the building is designed include the owner contingency in their
(for instance, the owner may want the budget, but not tell the contractor such a
lobby to be laid out in a different fashion contingency exists. Owners who “hide”
than was originally agreed upon). In their contingency believe that a contractor
either case the architect must literally will attempt to use the contingency for
go “back to the drawing board” and change orders should they know it exists.