Sie sind auf Seite 1von 312

HOA BINH CORPORATION

DAILY REPORT
Date:19/7/2010 Monday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm

V3 6:00 -10:00pm
(Tower)

Cleaning, material moving GW 15 6:00 -10:00pm


V6 L7 col. rebar install R 25 6:00 -10:00pm
(Tower) L8 floor beam f/w install FW 40
Con
6:00 -10:00pm

V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm

80

V3-Zone A 6:00 -10:00pm


(Base)

6:00 -10:00pm

V3-Zone B 6:00 -10:00pm


(Base) 6:00 -10:00pm

6:00 -10:00pm

V6-Zone C 6:00 -10:00pm


(Base) 6:00 -10:00pm
6:00 -10:00pm
6:00 -10:00pm

V5-Zone D 6:00 -10:00pm


(Base)

Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 459 Grade 200 m3
Site Manager 1 466 Grade 300 m3
D.Site Manager 2 864 Grade 350 m3 365
Administration 2 1,026 Grade 400 m3 5,784
Shopdrawing 3 2,120 Lean concrete: Unit Quantity Cumulation
QA/QC 2 659 Grade 200 m3 3,005
Site Engineer 32 12,735 Grade 250 m3 -
Surveyor 9 3,572 Rebar Unit Quantity Cumulation
56 13,775 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 25 49,127 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 3,961 D22 ton -
Fabrication workshop 5 2,940 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,602 D32 ton 190
Formworker 40 40,759 ton
General workers 15 34,648
Security 19 128,714
Sub Total 133 266,432

Page 1
Total 241 - 1,143.34

Page 2
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 3
Page 4
HOA BINH CORPORATION
DAILY REPORT
Date:19/7/2010 Monday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm

V3 R 7:30am - 5:00pm
(Tower) FW 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm
V6 T3 opening: col install R 15 7:30am - 5:00pm
(Tower) FW 7:30am - 5:00pm
Con
7:30am - 5:00pm

V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
30

V3-Zone A 7:30am - 5:00pm


(Base)

7:30am - 5:00pm

V3-Zone B 7:30am - 5:00pm


(Base) 7:30am - 5:00pm

7:30am - 5:00pm

V6-Zone C 7:30am - 5:00pm


(Base) 7:30am - 5:00pm
7:30am - 5:00pm
7:30am - 5:00pm

V5-Zone D 7:30am - 5:00pm


(Base) FW
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 460 Grade 200 m3
Site Manager 1 467 Grade 300 m3
D.Site Manager 2 866 Grade 350 m3 365
Administration 2 1,028 Grade 400 m3 5,784
Shopdrawing 3 2,123 Lean concrete: Unit Quantity Cumulation
QA/QC 2 661 Grade 200 m3 3,005
Site Engineer 32 12,767 Grade 250 m3 -
Surveyor 9 3,581 Rebar Unit Quantity Cumulation
56 13,831 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 15 49,219 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 3,976 D22 ton -
Fabrication workshop 5 2,945 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,616 D32 ton 190
Formworker - 40,809 ton
General workers 15 34,751
Security 19 128,733
Sub Total 83 266,730

Page 5
Total 191 - 1,143.34

Page 6
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 7
Page 8
HOA BINH CORPORATION
DAILY REPORT
Date:3/8/2010 Tuesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers

V3 R 6:00 -10:00pm
(Tower) FW
Con
Cleaning, material moving GW 15 6:00 -10:00pm
V6 L7 col., core rebar install R 30 6:00 -10:00pm
(Tower) FW
Con
6:00 -10:00pm

V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
45

V3-Zone A 6:00 -10:00pm


(Base)

6:00 -10:00pm

V3-Zone B 6:00 -10:00pm


(Base) 6:00 -10:00pm

6:00 -10:00pm

V6-Zone C 6:00 -10:00pm


(Base) 6:00 -10:00pm
6:00 -10:00pm
6:00 -10:00pm

V5-Zone D 6:00 -10:00pm


(Base)

Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 461 Grade 200 m3
Site Manager 1 468 Grade 300 m3
D.Site Manager 2 868 Grade 350 m3 365
Administration 2 1,030 Grade 400 m3 5,784
Shopdrawing 3 2,126 Lean concrete: Unit Quantity Cumulation
QA/QC 2 663 Grade 200 m3 3,005
Site Engineer 32 12,799 Grade 250 m3 -
Surveyor 9 3,590 Rebar Unit Quantity Cumulation
56 13,887 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 30 49,249 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 3,991 D22 ton -
Fabrication workshop 5 2,950 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,630 D32 ton 190
Formworker - 40,809 ton
General workers 15 34,766
Security 19 128,752
Sub Total 98 266,828

Page 9
Total 206 - 1,143.34

Page 10
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 11
Page 12
HOA BINH CORPORATION
DAILY REPORT
Date:4/8/2010 Wednesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm

V3 R 7:30am - 5:00pm
(Tower) FW 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm
V6 L8-9 col. core rebar install R 30 7:30am - 5:00pm
(Tower) L8 floor beam f/w install FW 30 7:30am - 5:00pm
Con
7:30am - 5:00pm

V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
75

V3-Zone A 7:30am - 5:00pm


(Base)

7:30am - 5:00pm

V3-Zone B 7:30am - 5:00pm


(Base) 7:30am - 5:00pm

7:30am - 5:00pm

V6-Zone C 7:30am - 5:00pm


(Base) 7:30am - 5:00pm
7:30am - 5:00pm
7:30am - 5:00pm

V5-Zone D 7:30am - 5:00pm


(Base)

Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 462 Grade 200 m3
Site Manager 1 469 Grade 300 m3
D.Site Manager 2 870 Grade 350 m3 365
Administration 2 1,032 Grade 400 m3 5,784
Shopdrawing 3 2,129 Lean concrete: Unit Quantity Cumulation
QA/QC 2 665 Grade 200 m3 3,005
Site Engineer 32 12,831 Grade 250 m3 -
Surveyor 9 3,599 Rebar Unit Quantity Cumulation
56 13,943 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 30 49,279 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,006 D22 ton -
Fabrication workshop 5 2,955 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,644 D32 ton 190
Formworker 30 40,839 ton
General workers 15 34,781
Security 19 128,771
Sub Total 128 266,956

Page 13
Total 236 - 1,143.34

Page 14
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 15
Page 16
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:4/8/2010 Wednesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm

V3 R 6:00 -10:00pm
(Tower) FW
Con
Cleaning, material moving GW 15 6:00 -10:00pm
V6 L8-9 col. core rebar install R 30 6:00 -10:00pm
(Tower) L8 floor beam f/w install FW 15
Con
6:00 -10:00pm

V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
60

V3-Zone A 6:00 -10:00pm


(Base)

6:00 -10:00pm

V3-Zone B 6:00 -10:00pm


(Base) 6:00 -10:00pm

6:00 -10:00pm

V6-Zone C 6:00 -10:00pm


(Base) 6:00 -10:00pm
6:00 -10:00pm
6:00 -10:00pm

V5-Zone D 6:00 -10:00pm


(Base)

SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 463 Grade 200 m3
Site Manager 1 470 Grade 300 m3
D.Site Manager 2 872 Grade 350 m3 365
Administration 2 1,034 Grade 400 m3 5,784
Shopdrawing 3 2,132 Lean concrete: Unit Quantity Cumulation
QA/QC 2 667 Grade 200 m3 3,005
Site Engineer 32 12,863 Grade 250 m3 -
Surveyor 9 3,608 Rebar Unit Quantity Cumulation
56 13,999 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 30 49,309 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,021 D22 ton -
Fabrication workshop 5 2,960 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,658 D32 ton 190
Formworker 15 40,854 ton
General workers 15 34,796
Security 19 128,790
Sub Total 113 267,069

Page 17
Total 221 - 1,143.34

Page 18
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 19
Page 20
HOA BINH CORPORATION
DAILY REPORT
Date:5/8/2010 Thursday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm

V3 R 7:30am - 5:00pm
(Tower) FW 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm
V6 L7-8 floor beam, core rebar install R 25 7:30am - 5:00pm
(Tower) L7-8 floor beam, core f/w install FW 70 7:30am - 5:00pm
Con
7:30am - 5:00pm

V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
110

V3-Zone A 7:30am - 5:00pm


(Base)

7:30am - 5:00pm

V3-Zone B 7:30am - 5:00pm


(Base) 7:30am - 5:00pm

7:30am - 5:00pm

V6-Zone C 7:30am - 5:00pm


(Base) 7:30am - 5:00pm
7:30am - 5:00pm
7:30am - 5:00pm

V5-Zone D 7:30am - 5:00pm


(Base)

Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 464 Grade 200 m3
Site Manager 1 471 Grade 300 m3
D.Site Manager 2 874 Grade 350 m3 365
Administration 2 1,036 Grade 400 m3 5,784
Shopdrawing 3 2,135 Lean concrete: Unit Quantity Cumulation
QA/QC 2 669 Grade 200 m3 3,005
Site Engineer 32 12,895 Grade 250 m3 -
Surveyor 9 3,617 Rebar Unit Quantity Cumulation
56 14,055 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 25 49,334 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,036 D22 ton -
Fabrication workshop 5 2,965 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,672 D32 ton 190
Formworker 70 40,924 ton
General workers 15 34,811
Security 19 128,809
Sub Total 163 267,232

Page 21
Total 271 - 1,143.34

Page 22
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 23
Page 24
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:5/8/2010 Thursday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm

V3 R 6:00 -10:00pm
(Tower) FW
Con
Cleaning, material moving GW 15 6:00 -10:00pm
V6 L7-8 floor beam, core rebar install R 30 6:00 -10:00pm
(Tower) L7-8 floor beam, core f/w install FW 15
Con
6:00 -10:00pm

V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
60

V3-Zone A 6:00 -10:00pm


(Base)

6:00 -10:00pm

V3-Zone B 6:00 -10:00pm


(Base) 6:00 -10:00pm

6:00 -10:00pm

V6-Zone C 6:00 -10:00pm


(Base) 6:00 -10:00pm
6:00 -10:00pm
6:00 -10:00pm

V5-Zone D 6:00 -10:00pm


(Base)

SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 465 Grade 200 m3
Site Manager 1 472 Grade 300 m3
D.Site Manager 2 876 Grade 350 m3 365
Administration 2 1,038 Grade 400 m3 5,784
Shopdrawing 3 2,138 Lean concrete: Unit Quantity Cumulation
QA/QC 2 671 Grade 200 m3 3,005
Site Engineer 32 12,927 Grade 250 m3 -
Surveyor 9 3,626 Rebar Unit Quantity Cumulation
56 14,111 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 30 49,364 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,051 D22 ton -
Fabrication workshop 5 2,970 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,686 D32 ton 190
Formworker 15 40,939 ton
General workers 15 34,826
Security 19 128,828
Sub Total 113 267,345

Page 25
Total 221 - 1,143.34

Page 26
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 27
Page 28
HOA BINH CORPORATION
DAILY REPORT
Date:6/8/2010 Friday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm

V3 R 7:30am - 5:00pm
(Tower) FW 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 12 7:30am - 5:00pm
V6 L7-8 floor beam, core rebar install R 40 7:30am - 5:00pm
(Tower) L7-8 floor beam, core f/w install FW 40 7:30am - 5:00pm
Con
GW 7:30am - 5:00pm

V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
92

V3-Zone A 7:30am - 5:00pm


(Base)

7:30am - 5:00pm

V3-Zone B 7:30am - 5:00pm


(Base) 7:30am - 5:00pm

7:30am - 5:00pm

V6-Zone C 7:30am - 5:00pm


(Base) 7:30am - 5:00pm
7:30am - 5:00pm
7:30am - 5:00pm

V5-Zone D 7:30am - 5:00pm


(Base)

Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 466 Grade 200 m3
Site Manager 1 473 Grade 300 m3
D.Site Manager 2 878 Grade 350 m3 365
Administration 2 1,040 Grade 400 m3 5,784
Shopdrawing 3 2,141 Lean concrete: Unit Quantity Cumulation
QA/QC 2 673 Grade 200 m3 3,005
Site Engineer 32 12,959 Grade 250 m3 -
Surveyor 9 3,635 Rebar Unit Quantity Cumulation
56 14,167 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 40 49,404 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,066 D22 ton -
Fabrication workshop 5 2,975 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,700 D32 ton 190
Formworker 40 40,979 ton
General workers 12 34,838
Security 19 128,847
Sub Total 145 267,490

Page 29
Total 253 - 1,143.34

Page 30
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 31
Page 32
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:6/8/2010 Friday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
GW 6:00 -10:00pm

V3 R 6:00 -10:00pm
(Tower) FW
Con
Cleaning, material moving GW 12 6:00 -10:00pm
V6 L7-8 slab beam, core rebar install R 35 6:00 -10:00pm
(Tower) L7-8 slab beam, core f/w install FW 25
Con
GW 6:00 -10:00pm

V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
72

V3-Zone A 6:00 -10:00pm


(Base)

6:00 -10:00pm

V3-Zone B 6:00 -10:00pm


(Base) 6:00 -10:00pm

6:00 -10:00pm

V6-Zone C 6:00 -10:00pm


(Base) 6:00 -10:00pm
6:00 -10:00pm
6:00 -10:00pm

V5-Zone D 6:00 -10:00pm


(Base)

SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 467 Grade 200 m3
Site Manager 1 474 Grade 300 m3
D.Site Manager 2 880 Grade 350 m3 365
Administration 2 1,042 Grade 400 m3 5,784
Shopdrawing 3 2,144 Lean concrete: Unit Quantity Cumulation
QA/QC 2 675 Grade 200 m3 3,005
Site Engineer 32 12,991 Grade 250 m3 -
Surveyor 9 3,644 Rebar Unit Quantity Cumulation
56 14,223 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 35 49,439 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,081 D22 ton -
Fabrication workshop 5 2,980 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,714 D32 ton 190
Formworker 25 41,004 ton
General workers 12 34,850
Security 19 128,866
Sub Total 125 267,615

Page 33
Total 233 - 1,143.34

Page 34
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 35
Page 36
HOA BINH CORPORATION
DAILY REPORT
Date:7/8/2010 Saturday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm

V3 R 7:30am - 5:00pm
(Tower) FW 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm
V6 L8 slab beam, core rebar install R 35 7:30am - 5:00pm
(Tower) L8 slab beam, core f/w install FW 32 7:30am - 5:00pm
Con
7:30am - 5:00pm

V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
82
GW

V3-Zone A 7:30am - 5:00pm


(Base)

7:30am - 5:00pm

V3-Zone B 7:30am - 5:00pm


(Base) 7:30am - 5:00pm

7:30am - 5:00pm

V6-Zone C 7:30am - 5:00pm


(Base) 7:30am - 5:00pm
7:30am - 5:00pm
7:30am - 5:00pm

V5-Zone D 7:30am - 5:00pm


(Base)

Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 468 Grade 200 m3
Site Manager 1 475 Grade 300 m3
D.Site Manager 2 882 Grade 350 m3 365
Administration 2 1,044 Grade 400 m3 5,784
Shopdrawing 3 2,147 Lean concrete: Unit Quantity Cumulation
QA/QC 2 677 Grade 200 m3 3,005
Site Engineer 32 13,023 Grade 250 m3 -
Surveyor 9 3,653 Rebar Unit Quantity Cumulation
56 14,279 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 35 49,474 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,096 D22 ton -
Fabrication workshop 5 2,985 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,728 D32 ton 190
Formworker 32 41,036 ton
General workers 15 34,865
Security 19 128,885
Sub Total 135 267,750

Page 37
Total 243 - 1,143.34

Page 38
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 39
Page 40
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:7/8/2010 Saturday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
GW 6:00 -10:00pm

V3 R 6:00 -10:00pm
(Tower) FW
Con
Cleaning, material moving GW 15 6:00 -10:00pm
V6 L8 slab beam, core rebar install R 15 6:00 -10:00pm
(Tower) L8 slab beam, core f/w install FW 10
Con
6:00 -10:00pm

V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
40
GW

V3-Zone A 6:00 -10:00pm


(Base)

6:00 -10:00pm

V3-Zone B 6:00 -10:00pm


(Base) 6:00 -10:00pm

6:00 -10:00pm

V6-Zone C 6:00 -10:00pm


(Base) 6:00 -10:00pm
6:00 -10:00pm
6:00 -10:00pm

V5-Zone D 6:00 -10:00pm


(Base)

Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 469 Grade 200 m3
Site Manager 1 476 Grade 300 m3
D.Site Manager 2 884 Grade 350 m3 365
Administration 2 1,046 Grade 400 m3 5,784
Shopdrawing 3 2,150 Lean concrete: Unit Quantity Cumulation
QA/QC 2 679 Grade 200 m3 3,005
Site Engineer 32 13,055 Grade 250 m3 -
Surveyor 9 3,662 Rebar Unit Quantity Cumulation
56 14,335 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 15 49,489 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,111 D22 ton -
Fabrication workshop 5 2,990 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,742 D32 ton 190
Formworker 10 41,046 ton
General workers 15 34,880
Security 19 128,904
Sub Total 93 267,843

Page 41
Total 201 - 1,143.34

Page 42
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 43
Page 44
HOA BINH CORPORATION
DAILY REPORT
Date:8/8/2010 Sunday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
GW 7:30am - 5:00pm

V3 R 7:30am - 5:00pm
(Tower) FW 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm
V6 L8 slab beam rebar inspection R 35 7:30am - 5:00pm
(Tower) L8 slab beam f/w inspection FW 32 7:30am - 5:00pm
Con
7:30am - 5:00pm

V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
82

V3-Zone A 7:30am - 5:00pm


(Base)

Con
GW 7:30am - 5:00pm

V3-Zone B R 7:30am - 5:00pm


(Base) FW 7:30am - 5:00pm
Con
GW 7:30am - 5:00pm

V6-Zone C R 7:30am - 5:00pm


(Base) FW 7:30am - 5:00pm
Con 7:30am - 5:00pm
GW 7:30am - 5:00pm

V5-Zone D R 7:30am - 5:00pm


(Base) FW
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 470 Grade 200 m3
Site Manager 1 477 Grade 300 m3
D.Site Manager 2 886 Grade 350 m3 365
Administration 2 1,048 Grade 400 m3 5,784
Shopdrawing 3 2,153 Lean concrete: Unit Quantity Cumulation
QA/QC 2 681 Grade 200 m3 3,005
Site Engineer 32 13,087 Grade 250 m3 -
Surveyor 9 3,671 Rebar Unit Quantity Cumulation
56 14,391 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 35 49,524 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,126 D22 ton -
Fabrication workshop 5 2,995 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,756 D32 ton 190
Formworker 32 41,078 ton
General workers 15 34,895
Security 19 128,923
Sub Total 135 267,978

Page 45
Total 243 - 1,143.34

Page 46
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 47
Page 48
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:7/8/2010 Saturday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm

V3 R 6:00 -10:00pm
(Tower) FW
Con
Cleaning, material moving GW 10 6:00 -10:00pm
V6 Casting con'c slab beam L8 R 15 6:00 -10:00pm
(Tower) Casting con'c slab beam L8 FW 20
Con
6:00 -10:00pm

V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm

45

V3-Zone A 6:00 -10:00pm


(Base) FW
Con
GW 6:00 -10:00pm

V3-Zone B R 6:00 -10:00pm


(Base) FW 6:00 -10:00pm
Con
GW 6:00 -10:00pm

V6-Zone C R 6:00 -10:00pm


(Base) FW 6:00 -10:00pm
Con 6:00 -10:00pm
GW 6:00 -10:00pm

V5-Zone D R 6:00 -10:00pm


(Base) FW
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 471 Grade 200 m3
Site Manager 1 478 Grade 300 m3
D.Site Manager 2 888 Grade 350 m3 365
Administration 2 1,050 Grade 400 m3 5,784
Shopdrawing 3 2,156 Lean concrete: Unit Quantity Cumulation
QA/QC 2 683 Grade 200 m3 3,005
Site Engineer 32 13,119 Grade 250 m3 -
Surveyor 9 3,680 Rebar Unit Quantity Cumulation
56 14,447 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 15 49,539 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,141 D22 ton -
Fabrication workshop 5 3,000 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,770 D32 ton 190
Formworker 20 41,098 ton
General workers 10 34,905
Security 19 128,942
Sub Total 98 268,076

Page 49
Total 206 - 1,143.34

Page 50
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 51
Page 52
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:9/8/2010 Monday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm

V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm
V6 L8 slab beam, core rebar install R 35 7:30am - 5:00pm
(Tower) L8 slab beam, core f/w install FW 32 7:30am - 5:00pm
Con
7:30am - 5:00pm

V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
82
GW

V3-Zone A 7:30am - 5:00pm


(Base)

7:30am - 5:00pm

V3-Zone B 7:30am - 5:00pm


(Base) 7:30am - 5:00pm

7:30am - 5:00pm

V6-Zone C 7:30am - 5:00pm


(Base) 7:30am - 5:00pm
7:30am - 5:00pm
7:30am - 5:00pm

V5-Zone D 7:30am - 5:00pm


(Base)

Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 472 Grade 200 m3
Site Manager 1 479 Grade 300 m3
D.Site Manager 2 890 Grade 350 m3 365
Administration 2 1,052 Grade 400 m3 5,784
Shopdrawing 3 2,159 Lean concrete: Unit Quantity Cumulation
QA/QC 2 685 Grade 200 m3 3,005
Site Engineer 32 13,151 Grade 250 m3 -
Surveyor 9 3,689 Rebar Unit Quantity Cumulation
56 14,503 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 35 49,574 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,156 D22 ton -
Fabrication workshop 5 3,005 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,784 D32 ton 190
Formworker 32 41,130 ton
General workers 15 34,920
Security 19 128,961
Sub Total 135 268,211

Page 53
Total 243 - 1,143.34

Page 54
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 55
Page 56
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:9/8/2010 Monday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
GW 6:00 -10:00pm

V3 R 6:00 -10:00pm
(Tower) FW
Con
Cleaning, material moving GW 15 6:00 -10:00pm
V6 inspection slab opening L3 R 25 6:00 -10:00pm
(Tower) Casting con'c col. slab opening FW 10
Con
6:00 -10:00pm

V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
50

V3-Zone A 6:00 -10:00pm


(Base)

6:00 -10:00pm

V3-Zone B 6:00 -10:00pm


(Base) 6:00 -10:00pm

6:00 -10:00pm

V6-Zone C 6:00 -10:00pm


(Base) 6:00 -10:00pm
6:00 -10:00pm
6:00 -10:00pm

V5-Zone D 6:00 -10:00pm


(Base) FW
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 473 Grade 200 m3
Site Manager 1 480 Grade 300 m3
D.Site Manager 2 892 Grade 350 m3 365
Administration 2 1,054 Grade 400 m3 5,784
Shopdrawing 3 2,162 Lean concrete: Unit Quantity Cumulation
QA/QC 2 687 Grade 200 m3 3,005
Site Engineer 32 13,183 Grade 250 m3 -
Surveyor 9 3,698 Rebar Unit Quantity Cumulation
56 14,559 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 25 49,599 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,171 D22 ton -
Fabrication workshop 5 3,010 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,798 D32 ton 190
Formworker 10 41,140 ton
General workers 15 34,935
Security 19 128,980
Sub Total 103 268,314

Page 57
Total 211 - 1,143.34

Page 58
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 59
Page 60
HOA BINH CORPORATION
DAILY REPORT
Date:10/8/2010 Tuesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm

V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm
V6 L8 slab beam, L3 slab beam opening install R 35 7:30am - 5:00pm
(Tower) L8 col., slab L9 install FW 32 7:30am - 5:00pm
Remove col. f/w opening Con
7:30am - 5:00pm

V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
82
GW

V3-Zone A 7:30am - 5:00pm


(Base)

7:30am - 5:00pm

V3-Zone B 7:30am - 5:00pm


(Base) 7:30am - 5:00pm

7:30am - 5:00pm

V6-Zone C 7:30am - 5:00pm


(Base) 7:30am - 5:00pm
7:30am - 5:00pm
7:30am - 5:00pm

V5-Zone D R 7:30am - 5:00pm


(Base) FW
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 474 Grade 200 m3
Site Manager 1 481 Grade 300 m3
D.Site Manager 2 894 Grade 350 m3 365
Administration 2 1,056 Grade 400 m3 5,784
Shopdrawing 3 2,165 Lean concrete: Unit Quantity Cumulation
QA/QC 2 689 Grade 200 m3 3,005
Site Engineer 32 13,215 Grade 250 m3 -
Surveyor 9 3,707 Rebar Unit Quantity Cumulation
56 14,615 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 35 49,634 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,186 D22 ton -
Fabrication workshop 5 3,015 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,812 D32 ton 190
Formworker 32 41,172 ton
General workers 15 34,950
Security 19 128,999
Sub Total 135 268,449

Page 61
Total 243 - 1,143.34

Page 62
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 63
Page 64
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:10/8/2010 Tuesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm

V3 6:00 -10:00pm
(Tower)

Con
Cleaning, material moving GW 15 6:00 -10:00pm
V6 L8-9 col.,core install R 30 6:00 -10:00pm
(Tower) L8-9 core f/w install FW 15
Con
6:00 -10:00pm

V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
60

V3-Zone A 6:00 -10:00pm


(Base)

6:00 -10:00pm

V3-Zone B 6:00 -10:00pm


(Base) 6:00 -10:00pm

6:00 -10:00pm

V6-Zone C 6:00 -10:00pm


(Base) 6:00 -10:00pm
6:00 -10:00pm
6:00 -10:00pm

V5-Zone D R 6:00 -10:00pm


(Base) FW
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 475 Grade 200 m3
Site Manager 1 482 Grade 300 m3
D.Site Manager 2 896 Grade 350 m3 365
Administration 2 1,058 Grade 400 m3 5,784
Shopdrawing 3 2,168 Lean concrete: Unit Quantity Cumulation
QA/QC 2 691 Grade 200 m3 3,005
Site Engineer 32 13,247 Grade 250 m3 -
Surveyor 9 3,716 Rebar Unit Quantity Cumulation
56 14,671 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 30 49,664 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,201 D22 ton -
Fabrication workshop 5 3,020 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,826 D32 ton 190
Formworker 15 41,187 ton
General workers 15 34,965
Security 19 129,018
Sub Total 113 268,562

Page 65
Total 221 - 1,143.34

Page 66
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 67
Page 68
HOA BINH CORPORATION
DAILY REPORT
Date:11/8/2010 Wednesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm

V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm
L3 opening install, core wall install. R 40 7:30am - 5:00pm
V6
(Tower) L3 slab beam opening & L9 slab beam col FW 50 7:30am - 5:00pm
install
Remove col. f/w opening Con

V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm

105
GW

V3-Zone A 7:30am - 5:00pm


(Base)

7:30am - 5:00pm

V3-Zone B 7:30am - 5:00pm


(Base) 7:30am - 5:00pm

7:30am - 5:00pm

V6-Zone C 7:30am - 5:00pm


(Base) 7:30am - 5:00pm
7:30am - 5:00pm
7:30am - 5:00pm

V5-Zone D 7:30am - 5:00pm


(Base) FW
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 474 Grade 200 m3
Site Manager 1 481 Grade 300 m3
D.Site Manager 2 894 Grade 350 m3 365
Administration 2 1,056 Grade 400 m3 5,784
Shopdrawing 3 2,165 Lean concrete: Unit Quantity Cumulation
QA/QC 2 689 Grade 200 m3 3,005
Site Engineer 32 13,215 Grade 250 m3 -
Surveyor 9 3,707 Rebar Unit Quantity Cumulation
56 14,615 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 40 49,639 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,186 D22 ton -
Fabrication workshop 5 3,015 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,812 D32 ton 190
Formworker 50 41,190 ton
General workers 15 34,950
Security 19 128,999
Sub Total 158 268,472

Page 69
Total 266 - 1,143.34

Page 70
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 71
Page 72
HOA BINH CORPORATION
DAILY REPORT
Date:11/8/2010 Wednesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm

V3 6:00 -10:00pm
(Tower)

Con
Cleaning, material moving GW 15 6:00 -10:00pm

V6 L3 opening install, core wall install. R 40 6:00 -10:00pm


(Tower) L9 slab beam core wall install FW 45
Remove col. f/w opening Con
6:00 -10:00pm

V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
100
GW

V3-Zone A 6:00 -10:00pm


(Base)

6:00 -10:00pm

V3-Zone B 6:00 -10:00pm


(Base) 6:00 -10:00pm

6:00 -10:00pm

V6-Zone C 6:00 -10:00pm


(Base) 6:00 -10:00pm
6:00 -10:00pm
6:00 -10:00pm

V5-Zone D 6:00 -10:00pm


(Base) FW
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 475 Grade 200 m3
Site Manager 1 481 Grade 300 m3
D.Site Manager 2 894 Grade 350 m3 365
Administration 2 1,056 Grade 400 m3 5,784
Shopdrawing 3 2,165 Lean concrete: Unit Quantity Cumulation
QA/QC 2 689 Grade 200 m3 3,005
Site Engineer 32 13,215 Grade 250 m3 -
Surveyor 9 3,707 Rebar Unit Quantity Cumulation
56 14,615 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 40 49,639 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,186 D22 ton -
Fabrication workshop 5 3,015 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,812 D32 ton 190
Formworker 45 41,185 ton
General workers 15 34,950
Security 19 128,999
Sub Total 153 268,467

Page 73
Total 261 - 1,143.34

Page 74
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 75
Page 76
HOA BINH CORPORATION
DAILY REPORT
Date:12/8/2010 Thursday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm

V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm

V6 L3 opening install, core wall install. R 40 7:30am - 5:00pm


(Tower) L9 slab beam core wall install FW 45 7:30am - 5:00pm
Remove col. f/w opening Con

V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
100
GW

V3-Zone A R 7:30am - 5:00pm


(Base)

7:30am - 5:00pm

V3-Zone B 7:30am - 5:00pm


(Base) 7:30am - 5:00pm

7:30am - 5:00pm

V6-Zone C 7:30am - 5:00pm


(Base) 7:30am - 5:00pm
7:30am - 5:00pm
7:30am - 5:00pm

V5-Zone D 7:30am - 5:00pm


(Base) FW
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 476 Grade 200 m3
Site Manager 1 482 Grade 300 m3
D.Site Manager 2 896 Grade 350 m3 365
Administration 2 1,058 Grade 400 m3 5,784
Shopdrawing 3 2,168 Lean concrete: Unit Quantity Cumulation
QA/QC 2 691 Grade 200 m3 3,005
Site Engineer 32 13,247 Grade 250 m3 -
Surveyor 9 3,716 Rebar Unit Quantity Cumulation
56 14,671 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 40 49,679 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,201 D22 ton -
Fabrication workshop 5 3,020 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,826 D32 ton 190
Formworker 45 41,230
General workers 15 34,965
Security 19 129,018
Sub Total 153 268,620

Page 77
Total 261 - 1,143.34

Page 78
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 79
Page 80
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:12/8/2010 Thursday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm

V3 6:00 -10:00pm
(Tower)

Con
Cleaning, material moving GW 15 6:00 -10:00pm

V6 L3 opening install, core wall install. R 30 6:00 -10:00pm


(Tower) L9 slab beam core wall install FW 15
Casting con'c staircase Con 10
6:00 -10:00pm

V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
70

V3-Zone A 6:00 -10:00pm


(Base)

6:00 -10:00pm

V3-Zone B 6:00 -10:00pm


(Base) 6:00 -10:00pm

6:00 -10:00pm

V6-Zone C 6:00 -10:00pm


(Base) 6:00 -10:00pm
6:00 -10:00pm
6:00 -10:00pm

V5-Zone D 6:00 -10:00pm


(Base)

Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 477 Grade 200 m3
Site Manager 1 483 Grade 300 m3
D.Site Manager 2 898 Grade 350 m3 365
Administration 2 1,060 Grade 400 m3 5,784
Shopdrawing 3 2,171 Lean concrete: Unit Quantity Cumulation
QA/QC 2 693 Grade 200 m3 3,005
Site Engineer 32 13,279 Grade 250 m3 -
Surveyor 9 3,725 Rebar Unit Quantity Cumulation
56 14,727 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 30 49,709 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,216 D22 ton -
Fabrication workshop 5 3,025 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,840 D32 ton 190
Formworker 15 41,245 ton
General workers 15 34,980
Security 19 129,037
Sub Total 113 268,733

Page 81
Total 221 - 1,143.34

Page 82
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 83
Page 84
HOA BINH CORPORATION
DAILY REPORT
Date:13/8/2010 Friday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm

V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm

V6 L3 opening install,L9 slab beam install. R 40 7:30am - 5:00pm


(Tower) L9 slab beam core,col. install FW 45 7:30am - 5:00pm
Con

V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
100

V3-Zone A 7:30am - 5:00pm


(Base)

7:30am - 5:00pm

V3-Zone B 7:30am - 5:00pm


(Base) 7:30am - 5:00pm

7:30am - 5:00pm

V6-Zone C 7:30am - 5:00pm


(Base) 7:30am - 5:00pm
7:30am - 5:00pm
7:30am - 5:00pm

V5-Zone D R 7:30am - 5:00pm


(Base) FW
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 478 Grade 200 m3
Site Manager 1 484 Grade 300 m3
D.Site Manager 2 900 Grade 350 m3 365
Administration 2 1,062 Grade 400 m3 5,784
Shopdrawing 3 2,174 Lean concrete: Unit Quantity Cumulation
QA/QC 2 695 Grade 200 m3 3,005
Site Engineer 32 13,311 Grade 250 m3 -
Surveyor 9 3,734 Rebar Unit Quantity Cumulation
56 14,783 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 40 49,749 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,231 D22 ton -
Fabrication workshop 5 3,030 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,854 D32 ton 190
Formworker 45 41,290 ton
General workers 15 34,995
Security 19 129,056
Sub Total 153 268,886

Page 85
Total 261 - 1,143.34

Page 86
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 87
Page 88
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:13/8/2010 Friday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm

V3 6:00 -10:00pm
(Tower)

Cleaning, material moving GW 15 6:00 -10:00pm

V6 L3 opening install,L9 slab beam install. R 35 6:00 -10:00pm


(Tower) L9 slab beam core,col. install FW 15
Con
6:00 -10:00pm

V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
65

V3-Zone A 6:00 -10:00pm


(Base)

6:00 -10:00pm

V3-Zone B 6:00 -10:00pm


(Base) 6:00 -10:00pm

6:00 -10:00pm

V6-Zone C 6:00 -10:00pm


(Base) 6:00 -10:00pm
6:00 -10:00pm
6:00 -10:00pm

V5-Zone D R 6:00 -10:00pm


(Base) FW
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 479 Grade 200 m3
Site Manager 1 485 Grade 300 m3
D.Site Manager 2 902 Grade 350 m3 365
Administration 2 1,064 Grade 400 m3 5,784
Shopdrawing 3 2,177 Lean concrete: Unit Quantity Cumulation
QA/QC 2 697 Grade 200 m3 3,005
Site Engineer 32 13,343 Grade 250 m3 -
Surveyor 9 3,743 Rebar Unit Quantity Cumulation
56 14,839 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 35 49,784 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,246 D22 ton -
Fabrication workshop 5 3,035 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,868 D32 ton 190
Formworker 15 41,305 ton
General workers 15 35,010
Security 19 129,075
Sub Total 118 269,004

Page 89
Total 226 - 1,143.34

Page 90
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 91
Page 92
HOA BINH CORPORATION
DAILY REPORT
Date:14/8/2010 Saturday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm

V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 18 7:30am - 5:00pm

V6 L3 open install,L9 slab beam& inspection R 52 7:30am - 5:00pm


(Tower)
L9 slab beam install & inspec, L3 open inst FW 50 7:30am - 5:00pm
Con

V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm

120

V3-Zone A 7:30am - 5:00pm


(Base)

7:30am - 5:00pm

V3-Zone B 7:30am - 5:00pm


(Base) 7:30am - 5:00pm

7:30am - 5:00pm

V6-Zone C 7:30am - 5:00pm


(Base) 7:30am - 5:00pm
Con 7:30am - 5:00pm
GW 7:30am - 5:00pm

V5-Zone D R 7:30am - 5:00pm


(Base) FW
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 480 Grade 200 m3
Site Manager 1 486 Grade 300 m3
D.Site Manager 2 904 Grade 350 m3 365
Administration 2 1,066 Grade 400 m3 5,784
Shopdrawing 3 2,180 Lean concrete: Unit Quantity Cumulation
QA/QC 2 699 Grade 200 m3 3,005
Site Engineer 32 13,375 Grade 250 m3 -
Surveyor 9 3,752 Rebar Unit Quantity Cumulation
56 14,895 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 52 49,836 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,261 D22 ton -
Fabrication workshop 5 3,040 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,882 D32 ton 190
Formworker 50 41,355 ton
General workers 18 35,028
Security 19 129,094
Sub Total 173 269,177

Page 93
Total 281 - 1,143.34

Page 94
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 95
Page 96
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:14/8/2010 Saturday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm

V3 6:00 -10:00pm
(Tower)

Con
Cleaning, material moving GW 15 6:00 -10:00pm

V6 L3 open install,L9 slab beam defect R 45 6:00 -10:00pm


(Tower)
L9 slab beam install & defect, L3 open inst FW 25
Con
6:00 -10:00pm

V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
85

V3-Zone A 6:00 -10:00pm


(Base)

6:00 -10:00pm

V3-Zone B 6:00 -10:00pm


(Base) 6:00 -10:00pm

6:00 -10:00pm

V6-Zone C 6:00 -10:00pm


(Base) 6:00 -10:00pm
6:00 -10:00pm
6:00 -10:00pm

V5-Zone D 6:00 -10:00pm


(Base)

Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 481 Grade 200 m3
Site Manager 1 487 Grade 300 m3
D.Site Manager 2 906 Grade 350 m3 365
Administration 2 1,068 Grade 400 m3 5,784
Shopdrawing 3 2,183 Lean concrete: Unit Quantity Cumulation
QA/QC 2 701 Grade 200 m3 3,005
Site Engineer 32 13,407 Grade 250 m3 -
Surveyor 9 3,761 Rebar Unit Quantity Cumulation
56 14,951 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 45 49,881 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,276 D22 ton -
Fabrication workshop 5 3,045 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,896 D32 ton 190
Formworker 25 41,380 ton
General workers 15 35,043
Security 19 129,113
Sub Total 138 269,315

Page 97
Total 246 - 1,143.34

Page 98
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 99
Page 100
HOA BINH CORPORATION
DAILY REPORT
Date:15/8/2010 Sunday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm

V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm

V6 L3 open install,L9 slab beam install R 52 7:30am - 5:00pm


(Tower)
L9 slab beam reinfore & inspection FW 30 7:30am - 5:00pm
Con

V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
97

V3-Zone A 7:30am - 5:00pm


(Base)

7:30am - 5:00pm

V3-Zone B 7:30am - 5:00pm


(Base) 7:30am - 5:00pm

7:30am - 5:00pm

V6-Zone C 7:30am - 5:00pm


(Base) 7:30am - 5:00pm
7:30am - 5:00pm
7:30am - 5:00pm

V5-Zone D 7:30am - 5:00pm


(Base)

SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 482 Grade 200 m3
Site Manager 1 488 Grade 300 m3
D.Site Manager 2 908 Grade 350 m3 365
Administration 2 1,070 Grade 400 m3 5,784
Shopdrawing 3 2,186 Lean concrete: Unit Quantity Cumulation
QA/QC 2 703 Grade 200 m3 3,005
Site Engineer 32 13,439 Grade 250 m3 -
Surveyor 9 3,770 Rebar Unit Quantity Cumulation
56 15,007 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 52 49,933 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,291 D22 ton -
Fabrication workshop 5 3,050 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,910 D32 ton 190
Formworker 30 41,410 ton
General workers 15 35,058
Security 19 129,132
Sub Total 150 269,465

Page 101
Total 258 - 1,143.34

Page 102
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 103
Page 104
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:15/8/2010 Sunday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm

V3 6:00 -10:00pm
(Tower)

Con
Cleaning, material moving GW 15 6:00 -10:00pm

V6 L3 open install,L9 slab beam defect R 45 6:00 -10:00pm


(Tower)
L9 slab beam install & defect, L3 open inst FW 25
Con
6:00 -10:00pm

V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
85

V3-Zone A 6:00 -10:00pm


(Base)

6:00 -10:00pm

V3-Zone B 6:00 -10:00pm


(Base) 6:00 -10:00pm

6:00 -10:00pm

V6-Zone C 6:00 -10:00pm


(Base) 6:00 -10:00pm
6:00 -10:00pm
6:00 -10:00pm

V5-Zone D 6:00 -10:00pm


(Base)

Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 483 Grade 200 m3
Site Manager 1 487 Grade 300 m3
D.Site Manager 2 906 Grade 350 m3 365
Administration 2 1,068 Grade 400 m3 5,784
Shopdrawing 3 2,183 Lean concrete: Unit Quantity Cumulation
QA/QC 2 701 Grade 200 m3 3,005
Site Engineer 32 13,407 Grade 250 m3 -
Surveyor 9 3,761 Rebar Unit Quantity Cumulation
56 14,951 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 45 49,881 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,276 D22 ton -
Fabrication workshop 5 3,045 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,896 D32 ton 190
Formworker 25 41,380 ton
General workers 15 35,043
Security 19 129,113
Sub Total 138 269,315

Page 105
Total 246 - 1,143.34

Page 106
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 107
Page 108
HOA BINH CORPORATION
DAILY REPORT
Date:16/8/2010 Monday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm

V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm

V6 L9-10 col.,core install,L3 beam open install R 35 7:30am - 5:00pm


(Tower)
L8 col.,core remove, L3 open f/w install FW 40 7:30am - 5:00pm
Con

V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
90

V3-Zone A 7:30am - 5:00pm


(Base)

7:30am - 5:00pm

V3-Zone B 7:30am - 5:00pm


(Base) 7:30am - 5:00pm

7:30am - 5:00pm

V6-Zone C 7:30am - 5:00pm


(Base) 7:30am - 5:00pm
7:30am - 5:00pm
7:30am - 5:00pm

V5-Zone D 7:30am - 5:00pm


(Base)

Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 484 Grade 200 m3
Site Manager 1 487 Grade 300 m3
D.Site Manager 2 906 Grade 350 m3 365
Administration 2 1,068 Grade 400 m3 5,784
Shopdrawing 3 2,183 Lean concrete: Unit Quantity Cumulation
QA/QC 2 701 Grade 200 m3 3,005
Site Engineer 32 13,407 Grade 250 m3 -
Surveyor 9 3,761 Rebar Unit Quantity Cumulation
56 14,951 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 35 49,871 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,276 D22 ton -
Fabrication workshop 5 3,045 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,896 D32 ton 190
Formworker 40 41,395 ton
General workers 15 35,043
Security 19 129,113
Sub Total 143 269,320

Page 109
Total 251 - 1,143.34

Page 110
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 111
Page 112
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:16/8/2010 Monday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm

V3 6:00 -10:00pm
(Tower)

Con
Cleaning, material moving GW 15 6:00 -10:00pm

V6 L9-10 col.,core install,L3 beam open install R 40 6:00 -10:00pm


(Tower)
FW
Con
6:00 -10:00pm

V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm

55

V3-Zone A 6:00 -10:00pm


(Base)

6:00 -10:00pm

V3-Zone B 6:00 -10:00pm


(Base) 6:00 -10:00pm

6:00 -10:00pm

V6-Zone C 6:00 -10:00pm


(Base) 6:00 -10:00pm
6:00 -10:00pm
6:00 -10:00pm

V5-Zone D 6:00 -10:00pm


(Base)

Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 485 Grade 200 m3
Site Manager 1 488 Grade 300 m3
D.Site Manager 2 908 Grade 350 m3 365
Administration 2 1,070 Grade 400 m3 5,784
Shopdrawing 3 2,186 Lean concrete: Unit Quantity Cumulation
QA/QC 2 703 Grade 200 m3 3,005
Site Engineer 32 13,439 Grade 250 m3 -
Surveyor 9 3,770 Rebar Unit Quantity Cumulation
56 15,007 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 40 49,911 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,291 D22 ton -
Fabrication workshop 5 3,050 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,910 D32 ton 190
Formworker - 41,395 ton
General workers 15 35,058
Security 19 129,132
Sub Total 108 269,428

Page 113
Total 216 - 1,143.34

Page 114
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 115
Page 116
HOA BINH CORPORATION
DAILY REPORT
Date:17/8/2010 Tuesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm

V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm

L9-10 col.,core install,L3 beam open install R 50 7:30am - 5:00pm


V6
(Tower) L8 col.,core remove, L9-10 core,col. f/w FW 45 7:30am - 5:00pm
install
L3 slab beam opening install Con 10

V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
120

V3-Zone A 7:30am - 5:00pm


(Base)

7:30am - 5:00pm

V3-Zone B 7:30am - 5:00pm


(Base) 7:30am - 5:00pm

7:30am - 5:00pm

V6-Zone C 7:30am - 5:00pm


(Base) 7:30am - 5:00pm
7:30am - 5:00pm
7:30am - 5:00pm

V5-Zone D R 7:30am - 5:00pm


(Base) FW
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 486 Grade 200 m3
Site Manager 1 489 Grade 300 m3
D.Site Manager 2 910 Grade 350 m3 365
Administration 2 1,072 Grade 400 m3 5,784
Shopdrawing 3 2,189 Lean concrete: Unit Quantity Cumulation
QA/QC 2 705 Grade 200 m3 3,005
Site Engineer 32 13,471 Grade 250 m3 -
Surveyor 9 3,779 Rebar Unit Quantity Cumulation
56 15,063 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 50 49,961 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,306 D22 ton -
Fabrication workshop 5 3,055 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,924 D32 ton 190
Formworker 45 41,440 ton
General workers 15 35,073
Security 19 129,151

Page 117
Sub Total 163 269,591
Total 271 - 1,143.34

Page 118
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 119
Page 120
HOA BINH CORPORATION
DAILY REPORT(After 5: 00 pm)
Date:17/8/2010 Tuesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm

V3 6:00 -10:00pm
(Tower)

Con
Cleaning, material moving GW 15 6:00 -10:00pm

V6 L9-10 col.,core rebar install R 35 6:00 -10:00pm


(Tower)
L9 col.,slab beam f/w install FW 40
Con
6:00 -10:00pm

V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
90

V3-Zone A 6:00 -10:00pm


(Base)

6:00 -10:00pm

V3-Zone B 6:00 -10:00pm


(Base) 6:00 -10:00pm

6:00 -10:00pm

V6-Zone C 6:00 -10:00pm


(Base) 6:00 -10:00pm
6:00 -10:00pm
6:00 -10:00pm

V5-Zone D R 6:00 -10:00pm


(Base) FW
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 487 Grade 200 m3
Site Manager 1 490 Grade 300 m3
D.Site Manager 2 912 Grade 350 m3 365
Administration 2 1,074 Grade 400 m3 5,784
Shopdrawing 3 2,192 Lean concrete: Unit Quantity Cumulation
QA/QC 2 707 Grade 200 m3 3,005
Site Engineer 32 13,503 Grade 250 m3 -
Surveyor 9 3,788 Rebar Unit Quantity Cumulation
56 15,119 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 35 49,996 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,321 D22 ton -
Fabrication workshop 5 3,060 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,938 D32 ton 190
Formworker 40 41,480 ton
General workers 15 35,088
Security 19 129,170
Sub Total 143 269,734

Page 121
Total 251 - 1,143.34

Page 122
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 123
Page 124
HOA BINH CORPORATION
DAILY REPORT
Date:18/8/2010 Wednesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm

V3 6:00 -10:00pm
(Tower)

Cleaning, material moving GW 15 6:00 -10:00pm

V6 L9-10 col.,core rebar inst,inspec slab open R 35 6:00 -10:00pm


(Tower)
L9 col.,slab beam f/w install FW 40
Con
6:00 -10:00pm

V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
90

V3-Zone A 6:00 -10:00pm


(Base)

6:00 -10:00pm

V3-Zone B 6:00 -10:00pm


(Base) 6:00 -10:00pm

6:00 -10:00pm

V6-Zone C 6:00 -10:00pm


(Base) 6:00 -10:00pm
Con 6:00 -10:00pm
6:00 -10:00pm

V5-Zone D R 6:00 -10:00pm


(Base) FW
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 488 Grade 200 m3
Site Manager 1 491 Grade 300 m3
D.Site Manager 2 914 Grade 350 m3 365
Administration 2 1,076 Grade 400 m3 5,784
Shopdrawing 3 2,195 Lean concrete: Unit Quantity Cumulation
QA/QC 2 709 Grade 200 m3 3,005
Site Engineer 32 13,535 Grade 250 m3 -
Surveyor 9 3,797 Rebar Unit Quantity Cumulation
56 15,175 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 35 50,031 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,336 D22 ton -
Fabrication workshop 5 3,065 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,952 D32 ton 190
Formworker 40 41,520 ton
General workers 15 35,103
Security 19 129,189
Sub Total 143 269,877

Page 125
Total 251 - 1,143.34

Page 126
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 127
Page 128
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:18/8/2010 Wednesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm

V3 6:00 -10:00pm
(Tower)

Con
Cleaning, material moving GW 15 6:00 -10:00pm

V6 L10 slab beam rebar install R 35 6:00 -10:00pm


(Tower)
L10 slab beam f/w install FW 20
Casting con'c slab beam opening L3 Con 10
6:00 -10:00pm

V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
80

V3-Zone A 6:00 -10:00pm


(Base)

6:00 -10:00pm

V3-Zone B 6:00 -10:00pm


(Base) 6:00 -10:00pm

6:00 -10:00pm

V6-Zone C 6:00 -10:00pm


(Base) 6:00 -10:00pm
6:00 -10:00pm
6:00 -10:00pm

V5-Zone D 6:00 -10:00pm


(Base)

Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 489 Grade 200 m3
Site Manager 1 492 Grade 300 m3
D.Site Manager 2 916 Grade 350 m3 365
Administration 2 1,078 Grade 400 m3 5,784
Shopdrawing 3 2,198 Lean concrete: Unit Quantity Cumulation
QA/QC 2 711 Grade 200 m3 3,005
Site Engineer 32 13,567 Grade 250 m3 -
Surveyor 9 3,806 Rebar Unit Quantity Cumulation
56 15,231 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 35 50,066 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,351 D22 ton -
Fabrication workshop 5 3,070 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,966 D32 ton 190
Formworker 20 41,540 ton
General workers 15 35,118
Security 19 129,208
Sub Total 123 270,000

Page 129
Total 231 - 1,143.34

Page 130
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 131
Page 132
HOA BINH CORPORATION
DAILY REPORT
Date:19/8/2010 Thursday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm

V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm

V6 L10 slab beam rebar install R 35 7:30am - 5:00pm


(Tower)
L10 slab beam f/w install FW 40 7:30am - 5:00pm
Con

V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
90

V3-Zone A 7:30am - 5:00pm


(Base)

7:30am - 5:00pm

V3-Zone B 7:30am - 5:00pm


(Base) 7:30am - 5:00pm

7:30am - 5:00pm

V6-Zone C 7:30am - 5:00pm


(Base) 7:30am - 5:00pm
7:30am - 5:00pm
7:30am - 5:00pm

V5-Zone D 7:30am - 5:00pm


(Base)

Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 490 Grade 200 m3
Site Manager 1 493 Grade 300 m3
D.Site Manager 2 918 Grade 350 m3 365
Administration 2 1,080 Grade 400 m3 5,784
Shopdrawing 3 2,201 Lean concrete: Unit Quantity Cumulation
QA/QC 2 713 Grade 200 m3 3,005
Site Engineer 32 13,599 Grade 250 m3 -
Surveyor 9 3,815 Rebar Unit Quantity Cumulation
56 15,287 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 35 50,101 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,366 D22 ton -
Fabrication workshop 5 3,075 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,980 D32 ton 190
Formworker 40 41,580 ton
General workers 15 35,133
Security 19 129,227
Sub Total 143 270,143

Page 133
Total 251 - 1,143.34

Page 134
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 135
Page 136
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:19/8/2010 Thursday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm

V3 6:00 -10:00pm
(Tower)

Con
Cleaning, material moving GW 5 6:00 -10:00pm

V6 L10 slab beam rebar install R 40 6:00 -10:00pm


(Tower)
L10 slab beam f/w install FW 25
Con
6:00 -10:00pm

V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm

70

V3-Zone A 6:00 -10:00pm


(Base)

6:00 -10:00pm

V3-Zone B 6:00 -10:00pm


(Base) 6:00 -10:00pm

6:00 -10:00pm

V6-Zone C 6:00 -10:00pm


(Base) 6:00 -10:00pm
6:00 -10:00pm
6:00 -10:00pm

V5-Zone D 6:00 -10:00pm


(Base)

Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 491 Grade 200 m3
Site Manager 1 494 Grade 300 m3
D.Site Manager 2 920 Grade 350 m3 365
Administration 2 1,082 Grade 400 m3 5,784
Shopdrawing 3 2,204 Lean concrete: Unit Quantity Cumulation
QA/QC 2 715 Grade 200 m3 3,005
Site Engineer 32 13,631 Grade 250 m3 -
Surveyor 9 3,824 Rebar Unit Quantity Cumulation
56 15,343 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 40 50,141 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,381 D22 ton -
Fabrication workshop 5 3,080 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,994 D32 ton 190
Formworker 25 41,605 ton
General workers 5 35,138
Security 19 129,246
Sub Total 123 270,266

Page 137
Total 231 - 1,143.34

Page 138
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 139
Page 140
HOA BINH CORPORATION
DAILY REPORT
Date:20/8/2010 Friday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm

V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm

V6 L10 slab beam rebar install R 30 7:30am - 5:00pm


(Tower)
L10 slab beam f/w install FW 40 7:30am - 5:00pm
Con

V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
85

V3-Zone A 7:30am - 5:00pm


(Base)

7:30am - 5:00pm

V3-Zone B 7:30am - 5:00pm


(Base) 7:30am - 5:00pm

7:30am - 5:00pm

V6-Zone C 7:30am - 5:00pm


(Base) 7:30am - 5:00pm
7:30am - 5:00pm
7:30am - 5:00pm

V5-Zone D 7:30am - 5:00pm


(Base)

Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 492 Grade 200 m3
Site Manager 1 495 Grade 300 m3
D.Site Manager 2 922 Grade 350 m3 365
Administration 2 1,084 Grade 400 m3 5,784
Shopdrawing 3 2,207 Lean concrete: Unit Quantity Cumulation
QA/QC 2 717 Grade 200 m3 3,005
Site Engineer 32 13,663 Grade 250 m3 -
Surveyor 9 3,833 Rebar Unit Quantity Cumulation
56 15,399 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 30 50,171 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,396 D22 ton -
Fabrication workshop 5 3,085 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,008 D32 ton 190
Formworker 40 41,645 ton
General workers 15 35,153
Security 19 129,265
Sub Total 138 270,404

Page 141
Total 246 - 1,143.34

Page 142
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 143
Page 144
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:20/8/2010 Friday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm

V3 6:00 -10:00pm
(Tower)

Cleaning, material moving GW 10 6:00 -10:00pm

V6 L10 slab beam rebar install R 30 6:00 -10:00pm


(Tower)
L10 slab beam f/w install FW 25
Con
6:00 -10:00pm

V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
65

V3-Zone A 6:00 -10:00pm


(Base)

6:00 -10:00pm

V3-Zone B 6:00 -10:00pm


(Base) 6:00 -10:00pm

6:00 -10:00pm

V6-Zone C 6:00 -10:00pm


(Base) 6:00 -10:00pm
Con 6:00 -10:00pm
6:00 -10:00pm

V5-Zone D R 6:00 -10:00pm


(Base) FW
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 493 Grade 200 m3
Site Manager 1 496 Grade 300 m3
D.Site Manager 2 924 Grade 350 m3 365
Administration 2 1,086 Grade 400 m3 5,784
Shopdrawing 3 2,210 Lean concrete: Unit Quantity Cumulation
QA/QC 2 719 Grade 200 m3 3,005
Site Engineer 32 13,695 Grade 250 m3 -
Surveyor 9 3,842 Rebar Unit Quantity Cumulation
56 15,455 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 30 50,201 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,411 D22 ton -
Fabrication workshop 5 3,090 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,022 D32 ton 190
Formworker 25 41,670 ton
General workers 10 35,163
Security 19 129,284
Sub Total 118 270,522

Page 145
Total 226 - 1,143.34

Page 146
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 147
Page 148
HOA BINH CORPORATION
DAILY REPORT
Date:21/8/2010 Saturday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm

V3 7:30am - 5:00pm
(Tower) FW 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm

V6 L10 slab beam rebar defect & inspection R 30 7:30am - 5:00pm


(Tower)
L10 slab beam f/w defect & inspection FW 15 7:30am - 5:00pm
Con

V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
60

V3-Zone A 7:30am - 5:00pm


(Base)

7:30am - 5:00pm

V3-Zone B 7:30am - 5:00pm


(Base) 7:30am - 5:00pm

7:30am - 5:00pm

V6-Zone C 7:30am - 5:00pm


(Base) 7:30am - 5:00pm
7:30am - 5:00pm
7:30am - 5:00pm

V5-Zone D 7:30am - 5:00pm


(Base) FW
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 494 Grade 200 m3
Site Manager 1 497 Grade 300 m3
D.Site Manager 2 926 Grade 350 m3 365
Administration 2 1,088 Grade 400 m3 5,784
Shopdrawing 3 2,213 Lean concrete: Unit Quantity Cumulation
QA/QC 2 721 Grade 200 m3 3,005
Site Engineer 32 13,727 Grade 250 m3 -
Surveyor 9 3,851 Rebar Unit Quantity Cumulation
56 15,511 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 30 50,231 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,426 D22 ton -
Fabrication workshop 5 3,095 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,036 D32 ton 190
Formworker 15 41,685 ton
General workers 15 35,178
Security 19 129,303
Sub Total 113 270,635

Page 149
Total 221 - 1,143.34

Page 150
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 151
Page 152
HOA BINH CORPORATION
DAILY REPORT
Date:21/8/2010 Saturday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
GW 6:00 -10:00pm

V3 R 6:00 -10:00pm
(Tower) FW
Con
Cleaning, material moving GW 15 6:00 -10:00pm

V6 L10 slab beam rebar defect & inspection R 30 6:00 -10:00pm


(Tower)
L10 slab beam f/w defect & inspection FW 20
Con
6:00 -10:00pm

V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
65

V3-Zone A 6:00 -10:00pm


(Base)

6:00 -10:00pm

V3-Zone B 6:00 -10:00pm


(Base) 6:00 -10:00pm

6:00 -10:00pm

V6-Zone C 6:00 -10:00pm


(Base) 6:00 -10:00pm
6:00 -10:00pm
6:00 -10:00pm

V5-Zone D 6:00 -10:00pm


(Base) FW
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 495 Grade 200 m3
Site Manager 1 498 Grade 300 m3
D.Site Manager 2 928 Grade 350 m3 365
Administration 2 1,090 Grade 400 m3 5,784
Shopdrawing 3 2,216 Lean concrete: Unit Quantity Cumulation
QA/QC 2 723 Grade 200 m3 3,005
Site Engineer 32 13,759 Grade 250 m3 -
Surveyor 9 3,860 Rebar Unit Quantity Cumulation
56 15,567 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 30 50,261 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,441 D22 ton -
Fabrication workshop 5 3,100 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,050 D32 ton 190
Formworker 20 41,705 ton
General workers 15 35,193
Security 19 129,322
Sub Total 118 270,753

Page 153
Total 226 - 1,143.34

Page 154
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 155
Page 156
HOA BINH CORPORATION
DAILY REPORT
Date:21/8/2010 Saturday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
GW 7:30am - 5:00pm

V3 R 7:30am - 5:00pm
(Tower) FW 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm

V6 L10 slab beam rebar defect & inspection R 30 7:30am - 5:00pm


(Tower)
L10 slab beam f/w defect & inspection FW 20 7:30am - 5:00pm
Con

V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
65

V3-Zone A 7:30am - 5:00pm


(Base)

7:30am - 5:00pm

V3-Zone B 7:30am - 5:00pm


(Base) 7:30am - 5:00pm

7:30am - 5:00pm

V6-Zone C 7:30am - 5:00pm


(Base) 7:30am - 5:00pm
7:30am - 5:00pm
7:30am - 5:00pm

V5-Zone D R 7:30am - 5:00pm


(Base) FW
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 496 Grade 200 m3
Site Manager 1 499 Grade 300 m3
D.Site Manager 2 930 Grade 350 m3 365
Administration 2 1,092 Grade 400 m3 5,784
Shopdrawing 3 2,219 Lean concrete: Unit Quantity Cumulation
QA/QC 2 725 Grade 200 m3 3,005
Site Engineer 32 13,791 Grade 250 m3 -
Surveyor 9 3,869 Rebar Unit Quantity Cumulation
56 15,623 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 30 50,261 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,441 D22 ton -
Fabrication workshop 5 3,100 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,050 D32 ton 190
Formworker 20 41,705 ton
General workers 15 35,193
Security 19 129,322
Sub Total 118 270,753

Page 157
Total 226 - 1,143.34

Page 158
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 159
Page 160
HOA BINH CORPORATION
DAILY REPORT
Date:21/8/2010 Saturday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
GW 6:00 -10:00pm

V3 R 6:00 -10:00pm
(Tower) FW
Con
Cleaning, material moving GW 15 6:00 -10:00pm

V6 L10 slab beam rebar defect & inspection R 30 6:00 -10:00pm


(Tower)
L10 slab beam f/w defect & inspection FW 20
Con
6:00 -10:00pm

V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
65

V3-Zone A 6:00 -10:00pm


(Base)

6:00 -10:00pm

V3-Zone B 6:00 -10:00pm


(Base) 6:00 -10:00pm

6:00 -10:00pm

V6-Zone C 6:00 -10:00pm


(Base) 6:00 -10:00pm
6:00 -10:00pm
6:00 -10:00pm

V5-Zone D R 6:00 -10:00pm


(Base) FW
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 497 Grade 200 m3
Site Manager 1 500 Grade 300 m3
D.Site Manager 2 932 Grade 350 m3 365
Administration 2 1,094 Grade 400 m3 5,784
Shopdrawing 3 2,222 Lean concrete: Unit Quantity Cumulation
QA/QC 2 727 Grade 200 m3 3,005
Site Engineer 32 13,823 Grade 250 m3 -
Surveyor 9 3,878 Rebar Unit Quantity Cumulation
56 15,679 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 30 50,291 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,456 D22 ton -
Fabrication workshop 5 3,105 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,064 D32 ton 190
Formworker 20 41,725 ton
General workers 15 35,208
Security 19 129,341
Sub Total 118 270,871

Page 161
Total 226 - 1,143.34

Page 162
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 163
Page 164
HOA BINH CORPORATION
DAILY REPORT
Date:23/8/2010 Monday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm

V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm

V6 L10-11 core,col rebar install R 35 7:30am - 5:00pm


(Tower)
L10-11 core,col f/w install FW 45 7:30am - 5:00pm
Con

V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
95

V3-Zone A 7:30am - 5:00pm


(Base)

7:30am - 5:00pm

V3-Zone B 7:30am - 5:00pm


(Base) 7:30am - 5:00pm

7:30am - 5:00pm

V6-Zone C 7:30am - 5:00pm


(Base) 7:30am - 5:00pm
Con 7:30am - 5:00pm
GW 7:30am - 5:00pm

V5-Zone D R 7:30am - 5:00pm


(Base) FW
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 498 Grade 200 m3
Site Manager 1 501 Grade 300 m3
D.Site Manager 2 934 Grade 350 m3 365
Administration 2 1,096 Grade 400 m3 5,784
Shopdrawing 3 2,225 Lean concrete: Unit Quantity Cumulation
QA/QC 2 729 Grade 200 m3 3,005
Site Engineer 32 13,855 Grade 250 m3 -
Surveyor 9 3,887 Rebar Unit Quantity Cumulation
56 15,735 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 35 50,326 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,471 D22 ton -
Fabrication workshop 5 3,110 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,078 D32 ton 190
Formworker 45 41,770 ton
General workers 15 35,223
Security 19 129,360
Sub Total 148 271,019

Page 165
Total 256 - 1,143.34

Page 166
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 167
Page 168
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:23/8/2010 Monday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm

V3 6:00 -10:00pm
(Tower)

Con
Cleaning, material moving GW 15 6:00 -10:00pm

V6 L10 slab beam rebar defect & inspection R 30 6:00 -10:00pm


(Tower)
L10 slab beam f/w defect & inspection FW 35
Con
6:00 -10:00pm

V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
80

V3-Zone A 6:00 -10:00pm


(Base)

6:00 -10:00pm

V3-Zone B 6:00 -10:00pm


(Base) 6:00 -10:00pm

6:00 -10:00pm

V6-Zone C 6:00 -10:00pm


(Base) 6:00 -10:00pm
6:00 -10:00pm
6:00 -10:00pm

V5-Zone D 6:00 -10:00pm


(Base)

Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 499 Grade 200 m3
Site Manager 1 502 Grade 300 m3
D.Site Manager 2 936 Grade 350 m3 365
Administration 2 1,098 Grade 400 m3 5,784
Shopdrawing 3 2,228 Lean concrete: Unit Quantity Cumulation
QA/QC 2 731 Grade 200 m3 3,005
Site Engineer 32 13,887 Grade 250 m3 -
Surveyor 9 3,896 Rebar Unit Quantity Cumulation
56 15,791 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 30 50,356 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,486 D22 ton -
Fabrication workshop 5 3,115 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,092 D32 ton 190
Formworker 35 41,805 ton
General workers 15 35,238
Security 19 129,379
Sub Total 133 271,152

Page 169
Total 241 - 1,143.34

Page 170
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 171
Page 172
HOA BINH CORPORATION
DAILY REPORT
Date:24/8/2010 Tuesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm

V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
7:30am - 5:00pm
Cleaning, material moving GW 17 7:30am - 5:00pm

V6 L10-11 col.,core rebar install R 40 7:30am - 5:00pm


(Tower)
L11 slab beam f/w install FW 45 7:30am - 5:00pm
Con

V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
102

V3-Zone A 7:30am - 5:00pm


(Base)

7:30am - 5:00pm

V3-Zone B 7:30am - 5:00pm


(Base) 7:30am - 5:00pm

7:30am - 5:00pm

V6-Zone C 7:30am - 5:00pm


(Base) 7:30am - 5:00pm
7:30am - 5:00pm
7:30am - 5:00pm

V5-Zone D 7:30am - 5:00pm


(Base)

Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 500 Grade 200 m3
Site Manager 1 503 Grade 300 m3
D.Site Manager 2 938 Grade 350 m3 365
Administration 2 1,100 Grade 400 m3 5,784
Shopdrawing 3 2,231 Lean concrete: Unit Quantity Cumulation
QA/QC 2 733 Grade 200 m3 3,005
Site Engineer 32 13,919 Grade 250 m3 -
Surveyor 9 3,905 Rebar Unit Quantity Cumulation
56 15,847 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 40 50,396 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,501 D22 ton -
Fabrication workshop 5 3,120 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,106 D32 ton 190
Formworker 45 41,850 ton
General workers 17 35,255
Security 19 129,398
Sub Total 155 271,307

Page 173
Total 263 - 1,143.34

Page 174
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 175
Page 176
HOA BINH CORPORATION
DAILY REPORT
Date:24/8/2010 Thuesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm

V3 6:00 -10:00pm
(Tower)

Cleaning, material moving GW 15 6:00 -10:00pm

V6 L10-11 col.,core rebar install R 40 6:00 -10:00pm


(Tower)
L11 slab beam f/w install FW 30
Con
6:00 -10:00pm

V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
85

V3-Zone A 6:00 -10:00pm


(Base)

6:00 -10:00pm

V3-Zone B 6:00 -10:00pm


(Base) 6:00 -10:00pm

6:00 -10:00pm

V6-Zone C 6:00 -10:00pm


(Base) 6:00 -10:00pm
6:00 -10:00pm
6:00 -10:00pm

V5-Zone D 6:00 -10:00pm


(Base)

Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 500 Grade 200 m3
Site Manager 1 503 Grade 300 m3
D.Site Manager 2 938 Grade 350 m3 365
Administration 2 1,100 Grade 400 m3 5,784
Shopdrawing 3 2,231 Lean concrete: Unit Quantity Cumulation
QA/QC 2 733 Grade 200 m3 3,005
Site Engineer 32 13,919 Grade 250 m3 -
Surveyor 9 3,905 Rebar Unit Quantity Cumulation
56 15,847 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 40 50,396 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,501 D22 ton -
Fabrication workshop 5 3,120 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,106 D32 ton 190
Formworker 30 41,835 ton
General workers 15 35,253
Security 19 129,398
Sub Total 138 271,290

Page 177
Total 246 - 1,143.34

Page 178
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 179
Page 180
HOA BINH CORPORATION
DAILY REPORT
Date:25/8/2010 Thuesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm

V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
7:30am - 5:00pm
Cleaning, material moving GW 17 7:30am - 5:00pm

V6 L10-11 col.,core rebar install R 40 7:30am - 5:00pm


(Tower)
L11 slab beam f/w install FW 45 7:30am - 5:00pm
Con

V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm

102

V3-Zone A 7:30am - 5:00pm


(Base)

7:30am - 5:00pm

V3-Zone B 7:30am - 5:00pm


(Base) 7:30am - 5:00pm

7:30am - 5:00pm

V6-Zone C 7:30am - 5:00pm


(Base) 7:30am - 5:00pm
7:30am - 5:00pm
7:30am - 5:00pm

V5-Zone D 7:30am - 5:00pm


(Base)

Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 500 Grade 200 m3
Site Manager 1 503 Grade 300 m3
D.Site Manager 2 938 Grade 350 m3 365
Administration 2 1,100 Grade 400 m3 5,784
Shopdrawing 3 2,231 Lean concrete: Unit Quantity Cumulation
QA/QC 2 733 Grade 200 m3 3,005
Site Engineer 32 13,919 Grade 250 m3 -
Surveyor 9 3,905 Rebar Unit Quantity Cumulation
56 15,847 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 40 50,396 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,501 D22 ton -
Fabrication workshop 5 3,120 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,106 D32 ton 190
Formworker 45 41,850 ton
General workers 17 35,255
Security 19 129,398
Sub Total 155 271,307

Page 181
Total 263 - 1,143.34

Page 182
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 183
Page 184
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:25/8/2010 Thursday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm

V3 6:00 -10:00pm
(Tower)

Con
Cleaning, material moving GW 15 6:00 -10:00pm

V6 L11 slab beam rebar install R 40 6:00 -10:00pm


(Tower)
L11 slab beam f/w install FW 30
Con
6:00 -10:00pm

V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
85

V3-Zone A 6:00 -10:00pm


(Base)

6:00 -10:00pm

V3-Zone B 6:00 -10:00pm


(Base) 6:00 -10:00pm

6:00 -10:00pm

V6-Zone C 6:00 -10:00pm


(Base) 6:00 -10:00pm
6:00 -10:00pm
6:00 -10:00pm

V5-Zone D 6:00 -10:00pm


(Base)

Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 501 Grade 200 m3
Site Manager 1 504 Grade 300 m3
D.Site Manager 2 940 Grade 350 m3 365
Administration 2 1,102 Grade 400 m3 5,784
Shopdrawing 3 2,234 Lean concrete: Unit Quantity Cumulation
QA/QC 2 735 Grade 200 m3 3,005
Site Engineer 32 13,951 Grade 250 m3 -
Surveyor 9 3,914 Rebar Unit Quantity Cumulation
56 15,903 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 40 50,436 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,516 D22 ton -
Fabrication workshop 5 3,125 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,120 D32 ton 190
Formworker 30 41,880 ton
General workers 15 35,270
Security 19 129,417
Sub Total 138 271,445

Page 185
Total 246 - 1,143.34

Page 186
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 187
Page 188
HOA BINH CORPORATION
DAILY REPORT
Date:26/8/2010 Thursday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm

V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm

V6 L10-11 col.,core rebar defect & inspection R 35 7:30am - 5:00pm


(Tower)
L11 slab beam f/w defect & inspection FW 40 7:30am - 5:00pm
Con

V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
90

V3-Zone A 7:30am - 5:00pm


(Base)

7:30am - 5:00pm

V3-Zone B 7:30am - 5:00pm


(Base) 7:30am - 5:00pm

7:30am - 5:00pm

V6-Zone C 7:30am - 5:00pm


(Base) 7:30am - 5:00pm
7:30am - 5:00pm
7:30am - 5:00pm

V5-Zone D 7:30am - 5:00pm


(Base) FW
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 502 Grade 200 m3
Site Manager 1 505 Grade 300 m3
D.Site Manager 2 942 Grade 350 m3 365
Administration 2 1,104 Grade 400 m3 5,784
Shopdrawing 3 2,237 Lean concrete: Unit Quantity Cumulation
QA/QC 2 737 Grade 200 m3 3,005
Site Engineer 32 13,983 Grade 250 m3 -
Surveyor 9 3,923 Rebar Unit Quantity Cumulation
56 15,959 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 35 50,471 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,531 D22 ton -
Fabrication workshop 5 3,130 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,134 D32 ton 190
Formworker 40 41,920 ton
General workers 15 35,285
Security 19 129,436
Sub Total 143 271,588

Page 189
Total 251 - 1,143.34

Page 190
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 191
Page 192
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:26/8/2010 Thursday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm

V3 6:00 -10:00pm
(Tower)

Cleaning, material moving GW 15 6:00 -10:00pm

V6 R 6:00 -10:00pm
(Tower)
L11 slab beam casting con'c FW 10
Con
6:00 -10:00pm

V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm

25

V3-Zone A 6:00 -10:00pm


(Base)

6:00 -10:00pm

V3-Zone B 6:00 -10:00pm


(Base) 6:00 -10:00pm

6:00 -10:00pm

V6-Zone C 6:00 -10:00pm


(Base) 6:00 -10:00pm
6:00 -10:00pm
6:00 -10:00pm

V5-Zone D 6:00 -10:00pm


(Base)

Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 503 Grade 200 m3
Site Manager 1 506 Grade 300 m3
D.Site Manager 2 944 Grade 350 m3 365
Administration 2 1,106 Grade 400 m3 5,784
Shopdrawing 3 2,240 Lean concrete: Unit Quantity Cumulation
QA/QC 2 739 Grade 200 m3 3,005
Site Engineer 32 14,015 Grade 250 m3 -
Surveyor 9 3,932 Rebar Unit Quantity Cumulation
56 16,015 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium - 50,471 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,546 D22 ton -
Fabrication workshop 5 3,135 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,148 D32 ton 190
Formworker 10 41,930 ton
General workers 15 35,300
Security 19 129,455
Sub Total 78 271,666

Page 193
Total 186 - 1,143.34

Page 194
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 195
Page 196
HOA BINH CORPORATION
DAILY REPORT
Date:27/8/2010 Friday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm

V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 17 7:30am - 5:00pm

V6 R 7:30am - 5:00pm
(Tower)
FW 7:30am - 5:00pm
Casting con'c slab beam L11 Con 15

V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
32

V3-Zone A 7:30am - 5:00pm


(Base)

7:30am - 5:00pm

V3-Zone B 7:30am - 5:00pm


(Base) 7:30am - 5:00pm

7:30am - 5:00pm

V6-Zone C 7:30am - 5:00pm


(Base) 7:30am - 5:00pm
7:30am - 5:00pm
7:30am - 5:00pm

V5-Zone D 7:30am - 5:00pm


(Base)

SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 504 Grade 200 m3
Site Manager 1 507 Grade 300 m3
D.Site Manager 2 946 Grade 350 m3 365
Administration 2 1,108 Grade 400 m3 5,784
Shopdrawing 3 2,243 Lean concrete: Unit Quantity Cumulation
QA/QC 2 741 Grade 200 m3 3,005
Site Engineer 32 14,047 Grade 250 m3 -
Surveyor 9 3,941 Rebar Unit Quantity Cumulation
56 16,071 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium - 50,471 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,561 D22 ton -
Fabrication workshop 5 3,140 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,162 D32 ton 190
Formworker - 41,930 ton
General workers 17 35,317
Security 19 129,474
Sub Total 70 271,736

Page 197
Total 178 - 1,143.34

Page 198
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 199
Page 200
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:27/8/2010 Friday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 12 6:00 -10:00pm

V3 Install col.,core L17-18 R 20 6:00 -10:00pm


(Tower) Remove col. L17 FW 38
Con
Cleaning, material moving GW 15 6:00 -10:00pm

V6 R 6:00 -10:00pm
(Tower)
FW
Casting con'c slab beam L11 Con 15
Cleaning, material moving GW 10 6:00 -10:00pm

V5 L13 col. fabrication R 10 6:00 -10:00pm


(Tower) L12 slab beam casting con'c FW 5 6:00 -10:00pm
L12 slab beam casting con'c Con 15
140
Cleaning, material moving GW 10

V3-Zone A Slab beam,staircase rebar install R 26 6:00 -10:00pm


(Base) FW
Con
Cleaning, material moving GW 4 6:00 -10:00pm

V3-Zone B R 6:00 -10:00pm


(Base) Install core wall tank FW 6 6:00 -10:00pm
Con
GW 6:00 -10:00pm

V6-Zone C Hanger wall rebar install R 4 6:00 -10:00pm


(Base) Remove septic tank f/w FW 10 6:00 -10:00pm
Con 6:00 -10:00pm
Cleaning, material moving GW 4 6:00 -10:00pm

V5-Zone D Hanger wall rebar install R 6 6:00 -10:00pm


(Base) Hanger wall,staircase f/w install FW 10
Con
SUM 80
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 505 Grade 200 m3
Site Manager 1 508 Grade 300 m3
D.Site Manager 2 948 Grade 350 m3 365
Administration 2 1,110 Grade 400 m3 5,784
Shopdrawing 3 2,246 Lean concrete: Unit Quantity Cumulation
QA/QC 2 743 Grade 200 m3 3,005
Site Engineer 32 14,079 Grade 250 m3 -
Surveyor 9 3,950 Rebar Unit Quantity Cumulation
56 16,127 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 66 50,537 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,576 D22 ton -
Fabrication workshop 5 3,145 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,176 D32 ton 190
Formworker 69 41,999 ton
General workers 55 35,372
Security 19 129,493
Sub Total 243 271,979

Page 201
Total 351 - 1,143.34

Page 202
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 203
Page 204
HOA BINH CORPORATION
DAILY REPORT
Date:28/8/2010 Saturday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 12 7:30am - 5:00pm

V3 L18 slab beam rebar install R 40 7:30am - 5:00pm


(Tower) L18 slab beam f/w install FW 40 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm

V6 L12 col.,core rebar install R 25 7:30am - 5:00pm


(Tower)
Remove col.,core FW 30 7:30am - 5:00pm
Casting con'c slab beam L11 Con 15
Cleaning, material moving GW 10

V5 L13 core,col, rebar install R 10 7:30am - 5:00pm


(Tower) Remove f/w slab beam L12 FW 20 7:30am - 5:00pm
Con
217
Cleaning, material moving GW 6

V3-Zone A Defect slab beam opening U2-U5 g-f R 5 7:30am - 5:00pm


(Base) Slab beam opening install FW 5
Con
Cleaning, material moving GW 10 7:30am - 5:00pm

V3-Zone B R 7:30am - 5:00pm


(Base) Defect core wall tank FW 4 7:30am - 5:00pm
Con
GW 7:30am - 5:00pm

V6-Zone C Hanger wall rebar install R 4 7:30am - 5:00pm


(Base) Remove septic tank f/w FW 18 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 4 7:30am - 5:00pm

V5-Zone D Hanger wall rebar install R 6 7:30am - 5:00pm


(Base) Hanger wall,staircase f/w install FW 7
Con
SUM 69
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 506 Grade 200 m3
Site Manager 1 509 Grade 300 m3
D.Site Manager 2 950 Grade 350 m3 365
Administration 2 1,112 Grade 400 m3 5,784
Shopdrawing 3 2,249 Lean concrete: Unit Quantity Cumulation
QA/QC 2 745 Grade 200 m3 3,005
Site Engineer 32 14,111 Grade 250 m3 -
Surveyor 9 3,959 Rebar Unit Quantity Cumulation
56 16,183 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 90 50,627 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,591 D22 ton -
Fabrication workshop 5 3,150 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,190 D32 ton 190
Formworker 124 42,123 ton
General workers 57 35,429
Security 19 129,512
Sub Total 324 272,303

Page 205
Total 432 - 1,143.34

Page 206
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 207
Page 208
HOA BINH CORPORATION
DAILY REPORT
Date:28/8/2010 Saturday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 12 6:00 -10:00pm

V3 L18 slab beam rebar install R 40 6:00 -10:00pm


(Tower) L18 slab beam f/w install FW 36
Con
Cleaning, material moving GW 10 6:00 -10:00pm

V6 L12 col.,core rebar install R 30 6:00 -10:00pm


(Tower)
FW
Casting con'c slab beam L11 Con
Cleaning, material moving GW 5 6:00 -10:00pm

V5 L13 core,col, rebar install R 30 6:00 -10:00pm


(Tower) Remove f/w slab beam L12 FW 20 6:00 -10:00pm
Con
183
Cleaning, material moving GW 10

V3-Zone A R 6:00 -10:00pm


(Base) Slab beam opening install FW 10
Con
Cleaning, material moving GW 4 6:00 -10:00pm

V3-Zone B R 6:00 -10:00pm


(Base) Defect core wall tank FW 6 6:00 -10:00pm
Casting con'c core wall tank Con 10
GW 6:00 -10:00pm

V6-Zone C Hanger wall rebar install R 4 6:00 -10:00pm


(Base) Remove septic tank f/w FW 18 6:00 -10:00pm
Con 6:00 -10:00pm
Cleaning, material moving GW 4 6:00 -10:00pm

V5-Zone D Hanger wall rebar install R 6 6:00 -10:00pm


(Base) Hanger wall,staircase f/w install FW 7
Con
SUM 79
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 507 Grade 200 m3
Site Manager 1 510 Grade 300 m3
D.Site Manager 2 952 Grade 350 m3 365
Administration 2 1,114 Grade 400 m3 5,784
Shopdrawing 3 2,252 Lean concrete: Unit Quantity Cumulation
QA/QC 2 747 Grade 200 m3 3,005
Site Engineer 32 14,143 Grade 250 m3 -
Surveyor 9 3,968 Rebar Unit Quantity Cumulation
56 16,239 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 110 50,737 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,606 D22 ton -
Fabrication workshop 5 3,155 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,204 D32 ton 190
Formworker 97 42,220 ton
General workers 45 35,474
Security 19 129,531
Sub Total 305 272,608

Page 209
Total 413 - 1,143.34

Page 210
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 211
Page 212
HOA BINH CORPORATION
DAILY REPORT
Date:30/8/2010 Monday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 12 7:30am - 5:00pm

V3 L18 slab beam rebar defect & inspection R 10 7:30am - 5:00pm


(Tower) L18 slab beam f/w defect & inspection FW 10 7:30am - 5:00pm
L11 bay window install Con 6 7:30am - 5:00pm
Cleaning, material moving GW 20 7:30am - 5:00pm

V6 L12 col.,core rebar install R 30 7:30am - 5:00pm


(Tower)
FW 7:30am - 5:00pm
Casting con'c slab beam L11 Con
Cleaning, material moving GW 8

V5 L12-13 core rebar install R 32 7:30am - 5:00pm


(Tower) L13 slab beam f/w install FW 30 7:30am - 5:00pm
Con
158
Cleaning, material moving GW 5

V3-Zone A R 7:30am - 5:00pm


(Base) Staircase f/w install (ground-floor) FW 5
Con
Cleaning, material moving GW 10 7:30am - 5:00pm

V3-Zone B R 7:30am - 5:00pm


(Base) Defect core wall tank FW 6 7:30am - 5:00pm
Con
Cleaning, material moving GW 6 7:30am - 5:00pm

V6-Zone C Col. rebar install R 10 7:30am - 5:00pm


(Base) Fabrication & install slab beam f/w FW 8 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 6 7:30am - 5:00pm

V5-Zone D Hanger wall rebar install & defect R 8 7:30am - 5:00pm


(Base) Staircase f/w install B1-> B2 FW 5
Con
SUM 69
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 508 Grade 200 m3
Site Manager 1 511 Grade 300 m3
D.Site Manager 2 954 Grade 350 m3 365
Administration 2 1,116 Grade 400 m3 5,784
Shopdrawing 3 2,255 Lean concrete: Unit Quantity Cumulation
QA/QC 2 749 Grade 200 m3 3,005
Site Engineer 32 14,175 Grade 250 m3 -
Surveyor 9 3,977 Rebar Unit Quantity Cumulation
56 16,295 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 90 50,827 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,621 D22 ton -
Fabrication workshop 5 3,160 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,218 D32 ton 190
Formworker 64 42,284 ton
General workers 67 35,541
Security 19 129,550
Sub Total 274 272,882

Page 213
Total 382 - 1,143.34

Page 214
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 215
Page 216
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:30/8/2010 Monday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
L18 slab beam casting con'c GW 5 6:00 -10:00pm

V3 R 6:00 -10:00pm
(Tower) L18 slab beam casting con'c FW 5
L18 slab beam casting con'c Con 30
Cleaning, material moving GW 20 6:00 -10:00pm

V6 L12 col.,core rebar install R 30 6:00 -10:00pm


(Tower)
FW
Casting con'c slab beam L11 Con
Cleaning, material moving GW 5 6:00 -10:00pm

V5 L13 slab beam rebar install R 20 6:00 -10:00pm


(Tower) L13 slab beam f/w install FW 30 6:00 -10:00pm
Con
145
Cleaning, material moving GW 8

V3-Zone A R 6:00 -10:00pm


(Base) Staircase f/w install (ground-floor) FW 6
Casting con'c : slab beam Con 5
Cleaning, material moving GW 8 6:00 -10:00pm

V3-Zone B R 6:00 -10:00pm


(Base) Defect core wall tank FW 6 6:00 -10:00pm
Con
Cleaning, material moving GW 10 6:00 -10:00pm

V6-Zone C Col. rebar install R 6 6:00 -10:00pm


(Base) Slab beam f/w install FW 8 6:00 -10:00pm
Con 6:00 -10:00pm
Cleaning, material moving GW 10 6:00 -10:00pm

V5-Zone D Hanger wall rebar install & defect R 8 6:00 -10:00pm


(Base) Staircase f/w install B1-> B2 FW 5
Con
SUM 80
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 509 Grade 200 m3
Site Manager 1 512 Grade 300 m3
D.Site Manager 2 956 Grade 350 m3 365
Administration 2 1,118 Grade 400 m3 5,784
Shopdrawing 3 2,258 Lean concrete: Unit Quantity Cumulation
QA/QC 2 751 Grade 200 m3 3,005
Site Engineer 32 14,207 Grade 250 m3 -
Surveyor 9 3,986 Rebar Unit Quantity Cumulation
56 16,351 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 64 50,891 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,636 D22 ton -
Fabrication workshop 5 3,165 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,232 D32 ton 190
Formworker 60 42,344 ton
General workers 66 35,607
Security 19 129,569
Sub Total 243 273,125

Page 217
Total 351 - 1,143.34

Page 218
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 219
Page 220
HOA BINH CORPORATION
DAILY REPORT
Date:31/8/2010 Tuesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 12 7:30am - 5:00pm

V3 L18 col.rebar install R 40 7:30am - 5:00pm


(Tower) L18 col.f/w install FW 20 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 10 7:30am - 5:00pm

V6 L12 col.,core rebar install R 30 7:30am - 5:00pm


(Tower)
L12 col.,core f/w install FW 35 7:30am - 5:00pm
Casting con'c slab beam L11 Con 10
Cleaning, material moving GW 8

V5 L13 slab beam rebar install R 30 7:30am - 5:00pm


(Tower) L13 slab beam f/w install FW 35 7:30am - 5:00pm
Con
230
Cleaning, material moving GW 6

V3-Zone A R 7:30am - 5:00pm


(Base) Staircase f/w install (ground-floor) FW 3
Con
Cleaning, material moving GW 5 7:30am - 5:00pm

V3-Zone B R 7:30am - 5:00pm


(Base) Defect core wall tank FW 5 7:30am - 5:00pm
Con
Cleaning, material moving GW 5 7:30am - 5:00pm

V6-Zone C R 7:30am - 5:00pm


(Base) Slab beam f/w install FW 10 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 4 7:30am - 5:00pm

V5-Zone D Hanger wall rebar install & defect R 4 7:30am - 5:00pm


(Base) Staircase f/w install B1-> B2 FW 6
Con
SUM 48
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 510 Grade 200 m3
Site Manager 1 513 Grade 300 m3
D.Site Manager 2 958 Grade 350 m3 365
Administration 2 1,120 Grade 400 m3 5,784
Shopdrawing 3 2,261 Lean concrete: Unit Quantity Cumulation
QA/QC 2 753 Grade 200 m3 3,005
Site Engineer 32 14,239 Grade 250 m3 -
Surveyor 9 3,995 Rebar Unit Quantity Cumulation
56 16,407 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 104 50,995 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,651 D22 ton -
Fabrication workshop 5 3,170 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,246 D32 ton 190
Formworker 114 42,458 ton
General workers 50 35,657
Security 19 129,588
Sub Total 321 273,446

Page 221
Total 429 - 1,143.34

Page 222
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 223
Page 224
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:31/8/2010 Tuesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 12

V3 L18 col.rebar install R 35 6:00 -10:00pm


(Tower) Remove col.,core f/w FW 20
Con
Cleaning, material moving GW 10 6:00 -10:00pm

V6 L12 slab beam install R 40 6:00 -10:00pm


(Tower)
L11-12 col.,core f/w install FW 15
Con
Cleaning, material moving GW 8 6:00 -10:00pm

V5 L13 slab beam rebar install R 10 6:00 -10:00pm


(Tower) L13 slab beam f/w install FW 30 6:00 -10:00pm
Con
180
Cleaning, material moving GW 5

V3-Zone A R 6:00 -10:00pm


(Base) FW
Con
Cleaning, material moving GW 5 6:00 -10:00pm

V3-Zone B R 6:00 -10:00pm


(Base) FW 6:00 -10:00pm
Con
Cleaning, material moving GW 6 6:00 -10:00pm

V6-Zone C R 6:00 -10:00pm


(Base) FW 6:00 -10:00pm
Con 6:00 -10:00pm
Cleaning, material moving GW 10 6:00 -10:00pm

V5-Zone D Hanger wall rebar install R 6 6:00 -10:00pm


(Base) Hanger wall f/w install FW 14
Con
SUM 46
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 511 Grade 200 m3
Site Manager 1 514 Grade 300 m3
D.Site Manager 2 960 Grade 350 m3 365
Administration 2 1,122 Grade 400 m3 5,784
Shopdrawing 3 2,264 Lean concrete: Unit Quantity Cumulation
QA/QC 2 755 Grade 200 m3 3,005
Site Engineer 32 14,271 Grade 250 m3 -
Surveyor 9 4,004 Rebar Unit Quantity Cumulation
56 16,463 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 91 51,086 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,666 D22 ton -
Fabrication workshop 5 3,175 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,260 D32 ton 190
Formworker 79 42,537 ton
General workers 56 35,713
Security 19 129,607
Sub Total 279 273,725

Page 225
Total 387 - 1,143.34

Page 226
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 227
Page 228
HOA BINH CORPORATION
DAILY REPORT
Date:1/9/2010 Wednesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 12 7:30am - 5:00pm

V3 L18 col.rebar install R 45 7:30am - 5:00pm


(Tower) L17-18 col. f/w removove FW 35 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 20 7:30am - 5:00pm

V6 L11 slab beam rebar install & inspection R 30 7:30am - 5:00pm


(Tower)
L11 slab beam f/w install & inspection FW 40 7:30am - 5:00pm
Con
Cleaning, material moving GW 9

V5 L13 slab beam rebar install R 35 7:30am - 5:00pm


(Tower) L13 slab beam f/w install & inspection FW 26 7:30am - 5:00pm
Con
252
Cleaning, material moving GW 7

V3-Zone A R 7:30am - 5:00pm


(Base) Hanger wall rebar install FW 5
Con
Cleaning, material moving GW 5 7:30am - 5:00pm

V3-Zone B R 7:30am - 5:00pm


(Base) Core wall tank install FW 8 7:30am - 5:00pm
Con
GW 7:30am - 5:00pm

V6-Zone C R 7:30am - 5:00pm


(Base) Remove slab beam B1 FW 4 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 3 7:30am - 5:00pm

V5-Zone D R 7:30am - 5:00pm


(Base) Staircase f/w install B1-> B2 FW 8
Con
SUM 40
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 512 Grade 200 m3
Site Manager 1 515 Grade 300 m3
D.Site Manager 2 962 Grade 350 m3 365
Administration 2 1,124 Grade 400 m3 5,784
Shopdrawing 3 2,267 Lean concrete: Unit Quantity Cumulation
QA/QC 2 757 Grade 200 m3 3,005
Site Engineer 32 14,303 Grade 250 m3 -
Surveyor 9 4,013 Rebar Unit Quantity Cumulation
56 16,519 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 110 51,196 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,681 D22 ton -
Fabrication workshop 5 3,180 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,274 D32 ton 190
Formworker 126 42,663 ton
General workers 56 35,769
Security 19 129,626
Sub Total 345 274,070

Page 229
Total 453 - 1,143.34

Page 230
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 231
Page 232
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:1/9/2010 Wednesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 12 6:00 -10:00pm

V3 L18 col.rebar install R 45 6:00 -10:00pm


(Tower) L17-18 col. f/w removove FW 35
Con
Cleaning, material moving GW 20 6:00 -10:00pm

V6 L11 slab beam rebar install & inspection R 30 6:00 -10:00pm


(Tower)
L11 slab beam f/w install & inspection FW 40
Con
Cleaning, material moving GW 9 6:00 -10:00pm

V5 L13 slab beam rebar install R 35 6:00 -10:00pm


(Tower) L13 slab beam f/w install & inspection FW 26 6:00 -10:00pm
Con
252
Cleaning, material moving GW 7

V3-Zone A R 6:00 -10:00pm


(Base) Hanger wall rebar install FW 5
Con
Cleaning, material moving GW 5 6:00 -10:00pm

V3-Zone B R 6:00 -10:00pm


(Base) Core wall tank install FW 8 6:00 -10:00pm
Con
GW 6:00 -10:00pm

V6-Zone C R 6:00 -10:00pm


(Base) Remove slab beam B1 FW 4 6:00 -10:00pm
Con 6:00 -10:00pm
Cleaning, material moving GW 3 6:00 -10:00pm

V5-Zone D R 6:00 -10:00pm


(Base) Staircase f/w install B1-> B2 FW 8
Con
SUM 40
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 513 Grade 200 m3
Site Manager 1 516 Grade 300 m3
D.Site Manager 2 964 Grade 350 m3 365
Administration 2 1,126 Grade 400 m3 5,784
Shopdrawing 3 2,270 Lean concrete: Unit Quantity Cumulation
QA/QC 2 759 Grade 200 m3 3,005
Site Engineer 32 14,335 Grade 250 m3 -
Surveyor 9 4,022 Rebar Unit Quantity Cumulation
56 16,575 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 110 51,306 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,696 D22 ton -
Fabrication workshop 5 3,185 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,288 D32 ton 190
Formworker 126 42,789 ton
General workers 56 35,825
Security 19 129,645
Sub Total 345 274,415

Page 233
Total 453 - 1,143.34

Page 234
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 235
Page 236
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:1/9/2010 Wednesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 12 6:00 -10:00pm

V3 L18 col.rebar install R 45 6:00 -10:00pm


(Tower) L17-18 col. f/w removove FW 35
Con
Cleaning, material moving GW 20 6:00 -10:00pm

V6 L11 slab beam rebar install & inspection R 30 6:00 -10:00pm


(Tower)
L11 slab beam f/w install & inspection FW 40
Con
Cleaning, material moving GW 9 6:00 -10:00pm

V5 L13 slab beam rebar install R 35 6:00 -10:00pm


(Tower) L13 slab beam f/w install & inspection FW 26 6:00 -10:00pm
Con
252
Cleaning, material moving GW 7

V3-Zone A R 6:00 -10:00pm


(Base) Hanger wall rebar install FW 5
Con
Cleaning, material moving GW 5 6:00 -10:00pm

V3-Zone B R 6:00 -10:00pm


(Base) Core wall tank install FW 8 6:00 -10:00pm
Con
GW 6:00 -10:00pm

V6-Zone C R 6:00 -10:00pm


(Base) Remove slab beam B1 FW 4 6:00 -10:00pm
Con 6:00 -10:00pm
Cleaning, material moving GW 3 6:00 -10:00pm

V5-Zone D R 6:00 -10:00pm


(Base) Staircase f/w install B1-> B2 FW 8
Con
SUM 40
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 514 Grade 200 m3
Site Manager 1 517 Grade 300 m3
D.Site Manager 2 966 Grade 350 m3 365
Administration 2 1,128 Grade 400 m3 5,784
Shopdrawing 3 2,273 Lean concrete: Unit Quantity Cumulation
QA/QC 2 761 Grade 200 m3 3,005
Site Engineer 32 14,367 Grade 250 m3 -
Surveyor 9 4,031 Rebar Unit Quantity Cumulation
56 16,631 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 110 51,416 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,711 D22 ton -
Fabrication workshop 5 3,190 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,302 D32 ton 190
Formworker 126 42,915 ton
General workers 56 35,881
Security 19 129,664
Sub Total 345 274,760

Page 237
Total 453 - 1,143.34

Page 238
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 239
Page 240
HOA BINH CORPORATION
DAILY REPORT
Date:4/9/2010 Saturday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 10 7:30am - 5:00pm

V3 L19 slab beam rebar install R 45 7:30am - 5:00pm


(Tower) L19 slab beam f/w install FW 40 7:30am - 5:00pm
L10-11 bay window f/w install 6 7:30am - 5:00pm
Cleaning, material moving GW 20 7:30am - 5:00pm

V6 L11 slab beam rebar install & inspection R 30 7:30am - 5:00pm


(Tower)
L11 slab beam f/w install & inspection FW 40 7:30am - 5:00pm
Con
Cleaning, material moving GW 9

V5 L14 col. slab beam rebar install R 40 7:30am - 5:00pm


(Tower) L14 col. slab beam f/w install FW 35 7:30am - 5:00pm
Con
275
Cleaning, material moving GW 8

V3-Zone A R 7:30am - 5:00pm


(Base) Hanger wall f/w install B1->B2 FW 9
Con
Cleaning, material moving GW 7 7:30am - 5:00pm

V3-Zone B R 7:30am - 5:00pm


(Base) FW 7:30am - 5:00pm
Con
Cleaning, material moving GW 5 7:30am - 5:00pm

V6-Zone C Slab beam rebar install R 13 7:30am - 5:00pm


(Base) Reinfore, decfect slab beam opening B1 FW 8 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 5 7:30am - 5:00pm

V5-Zone D R 7:30am - 5:00pm


(Base) FW
Con
SUM 55
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 515 Grade 200 m3
Site Manager 1 518 Grade 300 m3
D.Site Manager 2 968 Grade 350 m3 365
Administration 2 1,130 Grade 400 m3 5,784
Shopdrawing 3 2,276 Lean concrete: Unit Quantity Cumulation
QA/QC 2 763 Grade 200 m3 3,005
Site Engineer 32 14,399 Grade 250 m3 -
Surveyor 9 4,040 Rebar Unit Quantity Cumulation
56 16,687 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 128 51,544 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,726 D22 ton -
Fabrication workshop 5 3,195 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,316 D32 ton 190
Formworker 132 43,047 ton
General workers 64 35,945
Security 19 129,683
Sub Total 377 275,137

Page 241
Total 485 - 1,143.34

Page 242
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 243
Page 244
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:4/9/2010 Saturday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 12 6:00 -10:00pm

V3 L19 slab beam rebar install R 45 6:00 -10:00pm


(Tower) L19 slab beam f/w install FW 40
L10-11 bay window f/w install 6
Cleaning, material moving GW 10 6:00 -10:00pm

V6 L12 slab beam rebar install R 20 6:00 -10:00pm


(Tower)
L12 slab beam f/w install FW 30
Con
Cleaning, material moving GW 8 6:00 -10:00pm

V5 L14 slab beam rebar install R 30 6:00 -10:00pm


(Tower) L14 slab beam f/w install FW 30 6:00 -10:00pm
Con
231
Cleaning, material moving GW 6

V3-Zone A R 6:00 -10:00pm


(Base) Hanger wall f/w install B1->B2 FW 9
Con
Cleaning, material moving GW 8 6:00 -10:00pm

V3-Zone B R 6:00 -10:00pm


(Base) FW 6:00 -10:00pm
Con
Cleaning, material moving GW 5 6:00 -10:00pm

V6-Zone C Slab beam rebar install R 10 6:00 -10:00pm


(Base) Reinfore, decfect slab beam opening B1 FW 6 6:00 -10:00pm
Con 6:00 -10:00pm
Cleaning, material moving GW 5 6:00 -10:00pm

V5-Zone D R 6:00 -10:00pm


(Base) FW
Con
SUM 49
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 516 Grade 200 m3
Site Manager 1 519 Grade 300 m3
D.Site Manager 2 970 Grade 350 m3 365
Administration 2 1,132 Grade 400 m3 5,784
Shopdrawing 3 2,279 Lean concrete: Unit Quantity Cumulation
QA/QC 2 765 Grade 200 m3 3,005
Site Engineer 32 14,431 Grade 250 m3 -
Surveyor 9 4,049 Rebar Unit Quantity Cumulation
56 16,743 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 105 51,649 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,741 D22 ton -
Fabrication workshop 5 3,200 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,330 D32 ton 190
Formworker 115 43,162 ton
General workers 54 35,999
Security 19 129,702
Sub Total 327 275,464

Page 245
Total 435 - 1,143.34

Page 246
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 247
Page 248
HOA BINH CORPORATION
DAILY REPORT
Date:6/9/2010 Monday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 10 7:30am - 5:00pm

V3 L19 slab beam rebar defect R 10 7:30am - 5:00pm


(Tower) L19 slab beam f/w defect FW 9 7:30am - 5:00pm
L10-11 bay window f/w install 6 7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm

V6 L13 slab beam rebar install R 35 7:30am - 5:00pm


(Tower)
L13 slab beam f/w install FW 40 7:30am - 5:00pm
Con
Cleaning, material moving GW 7

V5 L14 slab beam rebar install R 35 7:30am - 5:00pm


(Tower) L14 slab beam f/w install FW 30 7:30am - 5:00pm
Con
197
Cleaning, material moving GW 5

V3-Zone A R 7:30am - 5:00pm


(Base) FW
Con
Cleaning, material moving GW 8 7:30am - 5:00pm

V3-Zone B R 7:30am - 5:00pm


(Base) Slab beam,core wall tank install FW 10 7:30am - 5:00pm
Con
Cleaning, material moving GW 8 7:30am - 5:00pm

V6-Zone C R 7:30am - 5:00pm


(Base) Hanger wall f/w install FW 6 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 2 7:30am - 5:00pm

V5-Zone D R 7:30am - 5:00pm


(Base) Staircase install B1->GF FW 5
Con
SUM 44
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 517 Grade 200 m3
Site Manager 1 520 Grade 300 m3
D.Site Manager 2 972 Grade 350 m3 365
Administration 2 1,134 Grade 400 m3 5,784
Shopdrawing 3 2,282 Lean concrete: Unit Quantity Cumulation
QA/QC 2 767 Grade 200 m3 3,005
Site Engineer 32 14,463 Grade 250 m3 -
Surveyor 9 4,058 Rebar Unit Quantity Cumulation
56 16,799 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 80 51,729 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,756 D22 ton -
Fabrication workshop 5 3,205 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,344 D32 ton 190
Formworker 100 43,262 ton
General workers 55 36,054
Security 19 129,721
Sub Total 288 275,752

Page 249
Total 396 - 1,143.34

Page 250
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 251
Page 252
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:6/9/2010 Monday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
L19 slab beam casting con'c GW 11 6:00 -10:00pm

V3 R 6:00 -10:00pm
(Tower) L19 slab beam casting con'c FW 4
L19 slab beam casting con'c 30
Cleaning, material moving GW 15 6:00 -10:00pm

V6 L13 slab beam rebar install R 25 6:00 -10:00pm


(Tower)
L13 slab beam f/w install FW 30
casting con'c Podium L1 Con 5
Cleaning, material moving GW 10 6:00 -10:00pm

V5 L14 -15 col.,core rebar fabrication R 10 6:00 -10:00pm


(Tower) L14 slab beam f/w install , casting con'c Podium L1 FW 20 6:00 -10:00pm
Con
160
Cleaning, material moving GW 5

V3-Zone A R 6:00 -10:00pm


(Base) FW
Con
Cleaning, material moving GW 8 6:00 -10:00pm

V3-Zone B R 6:00 -10:00pm


(Base) Slab beam,core wall tank install FW 10 6:00 -10:00pm
Con
Cleaning, material moving GW 8 6:00 -10:00pm

V6-Zone C R 6:00 -10:00pm


(Base) Hanger wall f/w install FW 6 6:00 -10:00pm
Con 6:00 -10:00pm
Cleaning, material moving GW 2 6:00 -10:00pm

V5-Zone D R 6:00 -10:00pm


(Base) Staircase install B1->GF FW 5
Con
SUM 44
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 518 Grade 200 m3
Site Manager 1 521 Grade 300 m3
D.Site Manager 2 974 Grade 350 m3 365
Administration 2 1,136 Grade 400 m3 5,784
Shopdrawing 3 2,285 Lean concrete: Unit Quantity Cumulation
QA/QC 2 769 Grade 200 m3 3,005
Site Engineer 32 14,495 Grade 250 m3 -
Surveyor 9 4,067 Rebar Unit Quantity Cumulation
56 16,855 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 35 51,764 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,771 D22 ton -
Fabrication workshop 5 3,210 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,358 D32 ton 190
Formworker 75 43,337 ton
General workers 59 36,113
Security 19 129,740
Sub Total 222 275,974

Page 253
Total 330 - 1,143.34

Page 254
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

SET 2
Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 255
Page 256
HOA BINH CORPORATION
DAILY REPORT
Date:7/9/2010 Tuesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 10 7:30am - 5:00pm

V3 L19-20 col.,core slab beam rebar fabrication R 42 7:30am - 5:00pm


(Tower) L19-20 col. f/w remove FW 40 7:30am - 5:00pm
7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm

V6 L13 col.,core rebar install & defect R 25 7:30am - 5:00pm


(Tower)
L13 slab beam f/w install & defect FW 30 7:30am - 5:00pm
Con
Cleaning, material moving GW 7

V5 L14 slab beam rebar defect & inspection R 30 7:30am - 5:00pm


(Tower) L14 slab beam f/w defect & inspection FW 35 7:30am - 5:00pm
Con
234
Cleaning, material moving GW 4

V3-Zone A R 7:30am - 5:00pm


(Base) FW
Con
Cleaning, material moving GW 5 7:30am - 5:00pm

V3-Zone B R 7:30am - 5:00pm


(Base) Slab beam,core wall tank install FW 8 7:30am - 5:00pm
Con
Cleaning, material moving GW 5 7:30am - 5:00pm

V6-Zone C R 7:30am - 5:00pm


(Base) Hanger wall f/w install FW 8 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 3 7:30am - 5:00pm

V5-Zone D R 7:30am - 5:00pm


(Base) Staircase install B1->GF FW 6
Con
SUM 39
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 519 Grade 200 m3
Site Manager 1 522 Grade 300 m3
D.Site Manager 2 976 Grade 350 m3 365
Administration 2 1,138 Grade 400 m3 5,784
Shopdrawing 3 2,288 Lean concrete: Unit Quantity Cumulation
QA/QC 2 771 Grade 200 m3 3,005
Site Engineer 32 14,527 Grade 250 m3 -
Surveyor 9 4,076 Rebar Unit Quantity Cumulation
56 16,911 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 97 51,861 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,786 D22 ton -
Fabrication workshop 5 3,215 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,372 D32 ton 190
Formworker 127 43,464 ton
General workers 49 36,162
Security 19 129,759
Sub Total 326 276,300

Page 257
Total 434 - 1,143.34

Page 258
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 259
Page 260
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:7/9/2010 Tuesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 10 6:00 -10:00pm

V3 L19-20 col.,core slab beam rebar fabrication R 38 6:00 -10:00pm


(Tower) L19-20 col. f/w remove FW 30

Cleaning, material moving GW 10 6:00 -10:00pm

V6 R 6:00 -10:00pm
(Tower)
L13 slab beam inspection & casting FW 10
Casting con'c slab beam L13 Con 15
Cleaning, material moving GW 10 6:00 -10:00pm

V5 L14 slab beam rebar defect & inspection R 8 6:00 -10:00pm


(Tower) L14 slab beam f/w defect & inspection & casting FW 5 6:00 -10:00pm
Con
136
Cleaning, material moving GW 4

V3-Zone A R 6:00 -10:00pm


(Base) Ramp f/w install FW 6
Con
Cleaning, material moving GW 5 6:00 -10:00pm

V3-Zone B R 6:00 -10:00pm


(Base) Remove slab beam FW 4 6:00 -10:00pm
Col. casting con'c Con 5
Cleaning, material moving GW 5 6:00 -10:00pm

V6-Zone C R 6:00 -10:00pm


(Base) Hanger wall casting con'c FW 16 6:00 -10:00pm
Con 6:00 -10:00pm
Cleaning, material moving GW 3 6:00 -10:00pm

V5-Zone D R 6:00 -10:00pm


(Base) FW 6
Casting con'c staircase Con 3
SUM 57
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 520 Grade 200 m3
Site Manager 1 523 Grade 300 m3
D.Site Manager 2 978 Grade 350 m3 365
Administration 2 1,140 Grade 400 m3 5,784
Shopdrawing 3 2,291 Lean concrete: Unit Quantity Cumulation
QA/QC 2 773 Grade 200 m3 3,005
Site Engineer 32 14,559 Grade 250 m3 -
Surveyor 9 4,085 Rebar Unit Quantity Cumulation
56 16,967 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 46 51,907 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,801 D22 ton -
Fabrication workshop 5 3,220 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,386 D32 ton 190
Formworker 77 43,541 ton
General workers 47 36,209
Security 19 129,778
Sub Total 223 276,523

Page 261
Total 331 - 1,143.34

Page 262
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 263
Page 264
HOA BINH CORPORATION
DAILY REPORT
Date:8/9/2010 Wednesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 10 7:30am - 5:00pm

V3 L19-20 col.,core slab beam rebar fabrication R 40 7:30am - 5:00pm


(Tower) L19-20 col. f/w remove FW 36 7:30am - 5:00pm
7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm

V6 R 7:30am - 5:00pm
(Tower)
Remove col. f/w slab beam L14 FW 30 7:30am - 5:00pm
Con
GW

V5 L14-15 col. fabrication R 10 7:30am - 5:00pm


(Tower) FW 7:30am - 5:00pm
Con
141
Cleaning, material moving GW 4

V3-Zone A R 7:30am - 5:00pm


(Base) Remove slab beam g-f FW 8
Con
Cleaning, material moving GW 5 7:30am - 5:00pm

V3-Zone B R 7:30am - 5:00pm


(Base) Ramp f/w install FW 6 7:30am - 5:00pm
Con
Cleaning, material moving GW 5 7:30am - 5:00pm

V6-Zone C R 7:30am - 5:00pm


(Base) Hanger wall install & casting con'c FW 4 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 3 7:30am - 5:00pm

V5-Zone D R 7:30am - 5:00pm


(Base) FW
Con
SUM 35
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 521 Grade 200 m3
Site Manager 1 524 Grade 300 m3
D.Site Manager 2 980 Grade 350 m3 365
Administration 2 1,142 Grade 400 m3 5,784
Shopdrawing 3 2,294 Lean concrete: Unit Quantity Cumulation
QA/QC 2 775 Grade 200 m3 3,005
Site Engineer 32 14,591 Grade 250 m3 -
Surveyor 9 4,094 Rebar Unit Quantity Cumulation
56 17,023 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 50 51,957 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,816 D22 ton -
Fabrication workshop 5 3,225 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,400 D32 ton 190
Formworker 84 43,625 ton
General workers 42 36,251
Security 19 129,797
Sub Total 229 276,752

Page 265
Total 337 - 1,143.34

Page 266
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 267
Page 268
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:8/9/2010 Wednesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 10 6:00 -10:00pm

V3 L19-20 col.,core slab beam rebar fabrication R 35 6:00 -10:00pm


(Tower) L19-20 col. f/w remove FW 30
Con
Cleaning, material moving GW 15 6:00 -10:00pm

V6 R 6:00 -10:00pm
(Tower)
Remove col. f/w slab beam L14 FW 30
Con
GW 6:00 -10:00pm

V5 L14-15 col. fabrication R 10 6:00 -10:00pm


(Tower) FW 6:00 -10:00pm
Con
130
Cleaning, chipping GW 9

V3-Zone A R 6:00 -10:00pm


(Base) Ramp f/w install FW 10
Con
Cleaning, material moving GW 8 6:00 -10:00pm

V3-Zone B R 6:00 -10:00pm


(Base) FW 6:00 -10:00pm
Con
Cleaning, material moving GW 6 6:00 -10:00pm

V6-Zone C Slab opening R 6 6:00 -10:00pm


(Base) Remove slab beam,slab opening FW 18 6:00 -10:00pm
Con 6:00 -10:00pm
GW 6:00 -10:00pm

V5-Zone D R 6:00 -10:00pm


(Base) FW
Con
SUM 57
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 522 Grade 200 m3
Site Manager 1 525 Grade 300 m3
D.Site Manager 2 982 Grade 350 m3 365
Administration 2 1,144 Grade 400 m3 5,784
Shopdrawing 3 2,297 Lean concrete: Unit Quantity Cumulation
QA/QC 2 777 Grade 200 m3 3,005
Site Engineer 32 14,623 Grade 250 m3 -
Surveyor 9 4,103 Rebar Unit Quantity Cumulation
56 17,079 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 51 52,008 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,831 D22 ton -
Fabrication workshop 5 3,230 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,414 D32 ton 190
Formworker 88 43,713 ton
General workers 48 36,299
Security 19 129,816
Sub Total 240 276,992

Page 269
Total 348 - 1,143.34

Page 270
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 271
Page 272
HOA BINH CORPORATION
DAILY REPORT
Date:9/9/2010 Thursday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 10 7:30am - 5:00pm

V3 L20 slab beam rebar install R 40 7:30am - 5:00pm


(Tower) L20 slab beam f/w install FW 40 7:30am - 5:00pm
7:30am - 5:00pm
Cleaning, material moving GW 10 7:30am - 5:00pm

V6 L13-14 col.,core rebar install R 40 7:30am - 5:00pm


(Tower)
L13-14 col.,core f/w install,remove slab L13 FW 50 7:30am - 5:00pm
Con
Cleaning, material moving GW 8

V5 L15 slab beam rebar install R 30 7:30am - 5:00pm


(Tower) L15 slab beam f/w install FW 30 7:30am - 5:00pm
Con
258
Cleaning, material moving GW 6

V3-Zone A R 7:30am - 5:00pm


(Base) Remove slab beam g-f FW 8
Con
Cleaning, material moving GW 6 7:30am - 5:00pm

V3-Zone B R 7:30am - 5:00pm


(Base) Ramp f/w install FW 8 7:30am - 5:00pm
Con
Cleaning, material moving GW 5 7:30am - 5:00pm

V6-Zone C Slab opening R 6 7:30am - 5:00pm


(Base) Remove slab beam,slab opening FW 13 7:30am - 5:00pm
Con 7:30am - 5:00pm
GW 7:30am - 5:00pm

V5-Zone D R 7:30am - 5:00pm


(Base) FW
Con
SUM 52
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 523 Grade 200 m3
Site Manager 1 526 Grade 300 m3
D.Site Manager 2 984 Grade 350 m3 365
Administration 2 1,146 Grade 400 m3 5,784
Shopdrawing 3 2,300 Lean concrete: Unit Quantity Cumulation
QA/QC 2 779 Grade 200 m3 3,005
Site Engineer 32 14,655 Grade 250 m3 -
Surveyor 9 4,112 Rebar Unit Quantity Cumulation
56 17,135 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 116 52,124 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,846 D22 ton -
Fabrication workshop 5 3,235 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,428 D32 ton 190
Formworker 149 43,862 ton
General workers 45 36,344
Security 19 129,835
Sub Total 363 277,355

Page 273
Total 471 - 1,143.34

Page 274
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 275
Page 276
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:9/9/2010 Thursday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 11 6:00 -10:00pm

V3 L20 slab beam rebar install R 20 6:00 -10:00pm


(Tower) L20 slab beam f/w install FW 20

Cleaning, material moving GW 15 6:00 -10:00pm

V6 L13-14 col.,core rebar install R 35 6:00 -10:00pm


(Tower)
L13-14 col.,core f/w install,remove slab L13 FW 30
Con
Cleaning, material moving GW 7 6:00 -10:00pm

V5 L15 slab beam rebar install R 10 6:00 -10:00pm


(Tower) L15 slab beam f/w install FW 25 6:00 -10:00pm
Con
173
Cleaning, material moving GW 5

V3-Zone A R 6:00 -10:00pm


(Base) FW
Con
Cleaning, material moving GW 10 6:00 -10:00pm

V3-Zone B R 6:00 -10:00pm


(Base) Ramp f/w install FW 5 6:00 -10:00pm
Con
Cleaning, material moving GW 10 6:00 -10:00pm

V6-Zone C Slab opening R 8 6:00 -10:00pm


(Base) Remove slab beam,slab opening FW 16 6:00 -10:00pm
Con 6:00 -10:00pm
GW 6:00 -10:00pm

V5-Zone D R 6:00 -10:00pm


(Base) FW
Con
SUM 54
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 524 Grade 200 m3
Site Manager 1 527 Grade 300 m3
D.Site Manager 2 986 Grade 350 m3 365
Administration 2 1,148 Grade 400 m3 5,784
Shopdrawing 3 2,303 Lean concrete: Unit Quantity Cumulation
QA/QC 2 781 Grade 200 m3 3,005
Site Engineer 32 14,687 Grade 250 m3 -
Surveyor 9 4,121 Rebar Unit Quantity Cumulation
56 17,191 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 73 52,197 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,861 D22 ton -
Fabrication workshop 5 3,240 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,442 D32 ton 190
Formworker 96 43,958 ton
General workers 58 36,402
Security 19 129,854
Sub Total 280 277,635

Page 277
Total 388 - 1,143.34

Page 278
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 279
Page 280
HOA BINH CORPORATION
DAILY REPORT
Date:10/9/2010 Friday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 11 7:30am - 5:00pm

V3 L20 slab beam rebar install R 45 7:30am - 5:00pm


(Tower) L20 slab beam f/w install FW 38 7:30am - 5:00pm
7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm

V6 L14 slab beam rebar install R 12 7:30am - 5:00pm


(Tower)
L13-14 col.,core f/w install FW 45 7:30am - 5:00pm
Con
Cleaning, material moving GW 8

V5 L15 core,W1,2,5,6 rebar install R 40 7:30am - 5:00pm


(Tower) L15 core, col.slab beam f/w install FW 25 7:30am - 5:00pm
Con
239
Cleaning, material moving GW 5

V3-Zone A R 7:30am - 5:00pm


(Base) FW
Con
Cleaning, material moving GW 8 7:30am - 5:00pm

V3-Zone B R 7:30am - 5:00pm


(Base) Ramp f/w install FW 7 7:30am - 5:00pm
Con
Cleaning, material moving GW 5 7:30am - 5:00pm

V6-Zone C Slab opening R 8 7:30am - 5:00pm


(Base) Remove slab beam,slab opening FW 13 7:30am - 5:00pm
Con 7:30am - 5:00pm
GW 7:30am - 5:00pm

V5-Zone D R 7:30am - 5:00pm


(Base) FW
Con
SUM 46
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 525 Grade 200 m3
Site Manager 1 528 Grade 300 m3
D.Site Manager 2 988 Grade 350 m3 365
Administration 2 1,150 Grade 400 m3 5,784
Shopdrawing 3 2,306 Lean concrete: Unit Quantity Cumulation
QA/QC 2 783 Grade 200 m3 3,005
Site Engineer 32 14,719 Grade 250 m3 -
Surveyor 9 4,130 Rebar Unit Quantity Cumulation
56 17,247 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 105 52,302 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,876 D22 ton -
Fabrication workshop 5 3,245 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,456 D32 ton 190
Formworker 128 44,086 ton
General workers 52 36,454
Security 19 129,873
Sub Total 338 277,973

Page 281
Total 446 - 1,143.34

Page 282
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 283
Page 284
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:10/9/2010 Friday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 11 6:00 -10:00pm

V3 L20 slab beam rebar install R 15 6:00 -10:00pm


(Tower) FW

Cleaning, material moving GW 15 6:00 -10:00pm

V6 L14 slab beam rebar install R 25 6:00 -10:00pm


(Tower)
L13-14 col.,core f/w install FW 30
Con
Cleaning, material moving GW 10 6:00 -10:00pm

V5 L15 core,W1,2,5,6 rebar install R 40 6:00 -10:00pm


(Tower) L15 core, col.slab beam f/w install FW 30 6:00 -10:00pm
Con
176
Cleaning, material moving, chipping GW 5

V3-Zone A R 6:00 -10:00pm


(Base) FW
Con
Cleaning, material moving GW 8 6:00 -10:00pm

V3-Zone B R 6:00 -10:00pm


(Base) FW 6:00 -10:00pm
Con
GW 5 6:00 -10:00pm

V6-Zone C R 8 6:00 -10:00pm


(Base) FW 13 6:00 -10:00pm
Con 6:00 -10:00pm
GW 6:00 -10:00pm

V5-Zone D R 6:00 -10:00pm


(Base) FW
Con
SUM 39
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 526 Grade 200 m3
Site Manager 1 529 Grade 300 m3
D.Site Manager 2 990 Grade 350 m3 365
Administration 2 1,152 Grade 400 m3 5,784
Shopdrawing 3 2,309 Lean concrete: Unit Quantity Cumulation
QA/QC 2 785 Grade 200 m3 3,005
Site Engineer 32 14,751 Grade 250 m3 -
Surveyor 9 4,139 Rebar Unit Quantity Cumulation
56 17,303 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 88 52,390 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,891 D22 ton -
Fabrication workshop 5 3,250 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,470 D32 ton 190
Formworker 73 44,159 ton
General workers 54 36,508
Security 19 129,892
Sub Total 268 278,241

Page 285
Total 376 - 1,143.34

Page 286
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 287
Page 288
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:11/9/2010 Saturday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm

V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm

V6 L14 slab beam rebar install, slab opening L4 R 55 7:30am - 5:00pm


(Tower)
L13-14 col.,core f/w install FW 45 7:30am - 5:00pm
Con

V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
115

V3-Zone A 7:30am - 5:00pm


(Base)

7:30am - 5:00pm

V3-Zone B 7:30am - 5:00pm


(Base) 7:30am - 5:00pm

7:30am - 5:00pm

V6-Zone C R 7:30am - 5:00pm


(Base) FW 7:30am - 5:00pm
Con 7:30am - 5:00pm
GW 7:30am - 5:00pm

V5-Zone D R 7:30am - 5:00pm


(Base) FW
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 527 Grade 200 m3
Site Manager 1 530 Grade 300 m3
D.Site Manager 2 992 Grade 350 m3 365
Administration 2 1,154 Grade 400 m3 5,784
Shopdrawing 3 2,312 Lean concrete: Unit Quantity Cumulation
QA/QC 2 787 Grade 200 m3 3,005
Site Engineer 32 14,783 Grade 250 m3 -
Surveyor 9 4,148 Rebar Unit Quantity Cumulation
56 17,359 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 55 52,445 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,906 D22 ton -
Fabrication workshop 5 3,255 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,484 D32 ton 190
Formworker 45 44,204 ton
General workers 15 36,523
Security 19 129,911
Sub Total 168 278,409

Page 289
Total 276 - 1,143.34

Page 290
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 291
Page 292
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:11/9/2010 Saturday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 11 6:00 -10:00pm

V3 L20 slab beam casting con'c R 7 6:00 -10:00pm


(Tower) L20 slab beam casting con'c FW 5
L20 slab beam casting con'c 30
Cleaning, material moving GW 10 6:00 -10:00pm

V6 L14 slab beam rebar install, slab opening L4 R 45 6:00 -10:00pm


(Tower)
L13-14 col.,core f/w install FW 40
Con
Cleaning, material moving GW 10 6:00 -10:00pm

V5 L15 slab beam rebar install R 30 6:00 -10:00pm


(Tower) L15 slab beam f/w install FW 20 6:00 -10:00pm
Con
208
Cleaning, material moving GW 5

V3-Zone A R 6:00 -10:00pm


(Base) FW
Con
Cleaning, material moving GW 6 6:00 -10:00pm

V3-Zone B R 6:00 -10:00pm


(Base) FW 6:00 -10:00pm
Con
Cleaning, material moving GW 5 6:00 -10:00pm

V6-Zone C R 6:00 -10:00pm


(Base) FW 6:00 -10:00pm
Con 6:00 -10:00pm
GW 6:00 -10:00pm

V5-Zone D R 6:00 -10:00pm


(Base) FW
Con
SUM 16
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 528 Grade 200 m3
Site Manager 1 531 Grade 300 m3
D.Site Manager 2 994 Grade 350 m3 365
Administration 2 1,156 Grade 400 m3 5,784
Shopdrawing 3 2,315 Lean concrete: Unit Quantity Cumulation
QA/QC 2 789 Grade 200 m3 3,005
Site Engineer 32 14,815 Grade 250 m3 -
Surveyor 9 4,157 Rebar Unit Quantity Cumulation
56 17,415 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 82 52,527 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,921 D22 ton -
Fabrication workshop 5 3,260 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,498 D32 ton 190
Formworker 65 44,269 ton
General workers 47 36,570
Security 19 129,930
Sub Total 247 278,656

Page 293
Total 355 - 1,143.34

Page 294
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 295
Page 296
HOA BINH CORPORATION
DAILY REPORT
Date:13/9/2010 Monday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 11 7:30am - 5:00pm

V3 L21 col, core slab beam rebar install R 40 7:30am - 5:00pm


(Tower) L21 col. slab beam f/w install FW 40 7:30am - 5:00pm
L11 bay window install 8 7:30am - 5:00pm
Cleaning, material moving GW 10 7:30am - 5:00pm

V6 Slab beam opening L4 R 15 7:30am - 5:00pm


(Tower)
L13-14 col.,core f/w remove FW 15 7:30am - 5:00pm
Con
Cleaning, material moving GW 9

V5 R 7:30am - 5:00pm
(Tower) L15 slab beam f/w install & inspection FW 30 7:30am - 5:00pm
Con
178
GW

V3-Zone A R 7:30am - 5:00pm


(Base) FW
Con
Cleaning, material moving GW 22 7:30am - 5:00pm

V3-Zone B Slab beam ramp rebar install R 10 7:30am - 5:00pm


(Base) Slab beam ramp f/w install FW 6 7:30am - 5:00pm
Con
GW 7:30am - 5:00pm

V6-Zone C R 7:30am - 5:00pm


(Base) FW 7:30am - 5:00pm
Con 7:30am - 5:00pm
GW 7:30am - 5:00pm

V5-Zone D R 7:30am - 5:00pm


(Base) FW
Con
SUM 38
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 529 Grade 200 m3
Site Manager 1 532 Grade 300 m3
D.Site Manager 2 996 Grade 350 m3 365
Administration 2 1,158 Grade 400 m3 5,784
Shopdrawing 3 2,318 Lean concrete: Unit Quantity Cumulation
QA/QC 2 791 Grade 200 m3 3,005
Site Engineer 32 14,847 Grade 250 m3 -
Surveyor 9 4,166 Rebar Unit Quantity Cumulation
56 17,471 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 65 52,592 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,936 D22 ton -
Fabrication workshop 5 3,265 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,512 D32 ton 190
Formworker 91 44,360 ton
General workers 52 36,622
Security 19 129,949
Sub Total 261 278,917

Page 297
Total 369 - 1,143.34

Page 298
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 299
Page 300
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:13/9/2010 Monday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 11

V3 R 6:00 -10:00pm
(Tower) L20 -21 col. slab beam f/w install FW 38

Cleaning, material moving GW 10 6:00 -10:00pm

V6 Slab beam opening L4 R 15 6:00 -10:00pm


(Tower)
L13-14 col.,core f/w remove FW 15
Con
Cleaning, material moving GW 9 6:00 -10:00pm

V5 R 6:00 -10:00pm
(Tower) L15 slab beam f/w install & inspection FW 30 6:00 -10:00pm
Con
128
Cleaning, material moving GW 4

V3-Zone A R 6:00 -10:00pm


(Base) FW
Con
GW 6:00 -10:00pm

V3-Zone B R 6:00 -10:00pm


(Base) FW 6:00 -10:00pm
Con
Cleaning, material moving GW 6 6:00 -10:00pm

V6-Zone C Defect slab rebar opening L2 R 4 6:00 -10:00pm


(Base) Defect slab f/w opening L2,col. f/w install FW 6 6:00 -10:00pm
Con 6:00 -10:00pm
GW 6:00 -10:00pm

V5-Zone D R 6:00 -10:00pm


(Base) FW
Con
SUM 20
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 530 Grade 200 m3
Site Manager 1 533 Grade 300 m3
D.Site Manager 2 998 Grade 350 m3 365
Administration 2 1,160 Grade 400 m3 5,784
Shopdrawing 3 2,321 Lean concrete: Unit Quantity Cumulation
QA/QC 2 793 Grade 200 m3 3,005
Site Engineer 32 14,879 Grade 250 m3 -
Surveyor 9 4,175 Rebar Unit Quantity Cumulation
56 17,527 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 19 52,611 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,951 D22 ton -
Fabrication workshop 5 3,270 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,526 D32 ton 190
Formworker 89 44,449 ton
General workers 40 36,662
Security 19 129,968
Sub Total 201 279,118

Page 301
Total 309 - 1,143.34

Page 302
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 303
Page 304
HOA BINH CORPORATION
DAILY REPORT
Date:14/9/2010 Tuesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 11 7:30am - 5:00pm

V3 L21 slab beam rebar install R 40 7:30am - 5:00pm


(Tower) L20 -21 col. slab beam f/w install FW 40 7:30am - 5:00pm
7:30am - 5:00pm
Cleaning, material moving GW 10 7:30am - 5:00pm

L13-14 col.,core f/w install R 40 7:30am - 5:00pm


V6
(Tower) L13-14 col.,core f/w install, remove slab FW 55 7:30am - 5:00pm
opening L3
Con
Cleaning, material moving GW 9

V5 L15-16 col. rebar fabrication R 30 7:30am - 5:00pm


(Tower) L14-15 col.,core f/w remove FW 20 7:30am - 5:00pm
Con
255
Cleaning, material moving GW 4

V3-Zone A R 7:30am - 5:00pm


(Base) Ramp f/w install FW 6
Con
GW 7:30am - 5:00pm

V3-Zone B R 7:30am - 5:00pm


(Base) FW 7:30am - 5:00pm
Con
Cleaning, material moving GW 4 7:30am - 5:00pm

V6-Zone C Defect slab rebar opening L2 R 2 7:30am - 5:00pm


(Base) Defect slab f/w opening L2,col. f/w install FW 4 7:30am - 5:00pm
Con 7:30am - 5:00pm
GW 7:30am - 5:00pm

V5-Zone D R 7:30am - 5:00pm


(Base) FW
Con
SUM 20
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 531 Grade 200 m3
Site Manager 1 534 Grade 300 m3
D.Site Manager 2 1,000 Grade 350 m3 365
Administration 2 1,162 Grade 400 m3 5,784
Shopdrawing 3 2,324 Lean concrete: Unit Quantity Cumulation
QA/QC 2 795 Grade 200 m3 3,005
Site Engineer 32 14,911 Grade 250 m3 -
Surveyor 9 4,184 Rebar Unit Quantity Cumulation
56 17,583 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 112 52,723 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,966 D22 ton -
Fabrication workshop 5 3,275 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,540 D32 ton 190
Formworker 125 44,574 ton
General workers 38 36,700
Security 19 129,987

Page 305
Sub Total 328 279,446
Total 436 - 1,143.34

Page 306
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 307
Page 308
HOA BINH CORPORATION
DAILY REPORT
Date:14/9/2010 Tuesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 11 7:30am - 5:00pm

V3 R 7:30am - 5:00pm
(Tower) L20 -21 col. slab beam f/w install FW 38 7:30am - 5:00pm
7:30am - 5:00pm
Cleaning, material moving GW 10 7:30am - 5:00pm

V6 Slab beam opening L4 R 15 7:30am - 5:00pm


(Tower)
L13-14 col.,core f/w remove FW 15 7:30am - 5:00pm
Con
Cleaning, material moving GW 9

V5 R 7:30am - 5:00pm
(Tower) L15 slab beam f/w install & inspection FW 30 7:30am - 5:00pm
Con
128
Cleaning, material moving GW 4

V3-Zone A R 7:30am - 5:00pm


(Base) FW
Con
GW 7:30am - 5:00pm

V3-Zone B R 7:30am - 5:00pm


(Base) FW 7:30am - 5:00pm
Con
Cleaning, material moving GW 6 7:30am - 5:00pm

V6-Zone C Defect slab rebar opening L2 R 4 7:30am - 5:00pm


(Base) Defect slab f/w opening L2,col. f/w install FW 6 7:30am - 5:00pm
Con 7:30am - 5:00pm
GW 7:30am - 5:00pm

V5-Zone D R 7:30am - 5:00pm


(Base) FW
Con
SUM 20
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 530 Grade 200 m3
Site Manager 1 533 Grade 300 m3
D.Site Manager 2 998 Grade 350 m3 365
Administration 2 1,160 Grade 400 m3 5,784
Shopdrawing 3 2,321 Lean concrete: Unit Quantity Cumulation
QA/QC 2 793 Grade 200 m3 3,005
Site Engineer 32 14,879 Grade 250 m3 -
Surveyor 9 4,175 Rebar Unit Quantity Cumulation
56 17,527 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 19 52,611 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,951 D22 ton -
Fabrication workshop 5 3,270 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,526 D32 ton 190
Formworker 89 44,449 ton
General workers 40 36,662
Security 19 129,968
Sub Total 201 279,118

Page 309
Total 309 - 1,143.34

Page 310
Equipments

Description Unit Quantity Remark


Bending machine SET 16
Cutting machine SET 15
Drilling machine SET 10
Concrete vibrator SET 10
Concrete breaker SET 10
Welding machine SET 11
Theodolite SET 3
Gradienter SET 0
SET 2

Crane truck SET 2


Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200

Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000

Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)

Page 311
Page 312

Das könnte Ihnen auch gefallen