DAILY REPORT
Date:19/7/2010 Monday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm
V3 6:00 -10:00pm
(Tower)
V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
80
6:00 -10:00pm
6:00 -10:00pm
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 459 Grade 200 m3
Site Manager 1 466 Grade 300 m3
D.Site Manager 2 864 Grade 350 m3 365
Administration 2 1,026 Grade 400 m3 5,784
Shopdrawing 3 2,120 Lean concrete: Unit Quantity Cumulation
QA/QC 2 659 Grade 200 m3 3,005
Site Engineer 32 12,735 Grade 250 m3 -
Surveyor 9 3,572 Rebar Unit Quantity Cumulation
56 13,775 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 25 49,127 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 3,961 D22 ton -
Fabrication workshop 5 2,940 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,602 D32 ton 190
Formworker 40 40,759 ton
General workers 15 34,648
Security 19 128,714
Sub Total 133 266,432
Page 1
Total 241 - 1,143.34
Page 2
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 3
Page 4
HOA BINH CORPORATION
DAILY REPORT
Date:19/7/2010 Monday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm
V3 R 7:30am - 5:00pm
(Tower) FW 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm
V6 T3 opening: col install R 15 7:30am - 5:00pm
(Tower) FW 7:30am - 5:00pm
Con
7:30am - 5:00pm
V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
30
7:30am - 5:00pm
7:30am - 5:00pm
Page 5
Total 191 - 1,143.34
Page 6
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 7
Page 8
HOA BINH CORPORATION
DAILY REPORT
Date:3/8/2010 Tuesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
V3 R 6:00 -10:00pm
(Tower) FW
Con
Cleaning, material moving GW 15 6:00 -10:00pm
V6 L7 col., core rebar install R 30 6:00 -10:00pm
(Tower) FW
Con
6:00 -10:00pm
V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
45
6:00 -10:00pm
6:00 -10:00pm
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 461 Grade 200 m3
Site Manager 1 468 Grade 300 m3
D.Site Manager 2 868 Grade 350 m3 365
Administration 2 1,030 Grade 400 m3 5,784
Shopdrawing 3 2,126 Lean concrete: Unit Quantity Cumulation
QA/QC 2 663 Grade 200 m3 3,005
Site Engineer 32 12,799 Grade 250 m3 -
Surveyor 9 3,590 Rebar Unit Quantity Cumulation
56 13,887 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 30 49,249 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 3,991 D22 ton -
Fabrication workshop 5 2,950 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,630 D32 ton 190
Formworker - 40,809 ton
General workers 15 34,766
Security 19 128,752
Sub Total 98 266,828
Page 9
Total 206 - 1,143.34
Page 10
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 11
Page 12
HOA BINH CORPORATION
DAILY REPORT
Date:4/8/2010 Wednesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm
V3 R 7:30am - 5:00pm
(Tower) FW 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm
V6 L8-9 col. core rebar install R 30 7:30am - 5:00pm
(Tower) L8 floor beam f/w install FW 30 7:30am - 5:00pm
Con
7:30am - 5:00pm
V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
75
7:30am - 5:00pm
7:30am - 5:00pm
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 462 Grade 200 m3
Site Manager 1 469 Grade 300 m3
D.Site Manager 2 870 Grade 350 m3 365
Administration 2 1,032 Grade 400 m3 5,784
Shopdrawing 3 2,129 Lean concrete: Unit Quantity Cumulation
QA/QC 2 665 Grade 200 m3 3,005
Site Engineer 32 12,831 Grade 250 m3 -
Surveyor 9 3,599 Rebar Unit Quantity Cumulation
56 13,943 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 30 49,279 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,006 D22 ton -
Fabrication workshop 5 2,955 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,644 D32 ton 190
Formworker 30 40,839 ton
General workers 15 34,781
Security 19 128,771
Sub Total 128 266,956
Page 13
Total 236 - 1,143.34
Page 14
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 15
Page 16
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:4/8/2010 Wednesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm
V3 R 6:00 -10:00pm
(Tower) FW
Con
Cleaning, material moving GW 15 6:00 -10:00pm
V6 L8-9 col. core rebar install R 30 6:00 -10:00pm
(Tower) L8 floor beam f/w install FW 15
Con
6:00 -10:00pm
V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
60
6:00 -10:00pm
6:00 -10:00pm
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 463 Grade 200 m3
Site Manager 1 470 Grade 300 m3
D.Site Manager 2 872 Grade 350 m3 365
Administration 2 1,034 Grade 400 m3 5,784
Shopdrawing 3 2,132 Lean concrete: Unit Quantity Cumulation
QA/QC 2 667 Grade 200 m3 3,005
Site Engineer 32 12,863 Grade 250 m3 -
Surveyor 9 3,608 Rebar Unit Quantity Cumulation
56 13,999 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 30 49,309 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,021 D22 ton -
Fabrication workshop 5 2,960 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,658 D32 ton 190
Formworker 15 40,854 ton
General workers 15 34,796
Security 19 128,790
Sub Total 113 267,069
Page 17
Total 221 - 1,143.34
Page 18
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 19
Page 20
HOA BINH CORPORATION
DAILY REPORT
Date:5/8/2010 Thursday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm
V3 R 7:30am - 5:00pm
(Tower) FW 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm
V6 L7-8 floor beam, core rebar install R 25 7:30am - 5:00pm
(Tower) L7-8 floor beam, core f/w install FW 70 7:30am - 5:00pm
Con
7:30am - 5:00pm
V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
110
7:30am - 5:00pm
7:30am - 5:00pm
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 464 Grade 200 m3
Site Manager 1 471 Grade 300 m3
D.Site Manager 2 874 Grade 350 m3 365
Administration 2 1,036 Grade 400 m3 5,784
Shopdrawing 3 2,135 Lean concrete: Unit Quantity Cumulation
QA/QC 2 669 Grade 200 m3 3,005
Site Engineer 32 12,895 Grade 250 m3 -
Surveyor 9 3,617 Rebar Unit Quantity Cumulation
56 14,055 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 25 49,334 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,036 D22 ton -
Fabrication workshop 5 2,965 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,672 D32 ton 190
Formworker 70 40,924 ton
General workers 15 34,811
Security 19 128,809
Sub Total 163 267,232
Page 21
Total 271 - 1,143.34
Page 22
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 23
Page 24
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:5/8/2010 Thursday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm
V3 R 6:00 -10:00pm
(Tower) FW
Con
Cleaning, material moving GW 15 6:00 -10:00pm
V6 L7-8 floor beam, core rebar install R 30 6:00 -10:00pm
(Tower) L7-8 floor beam, core f/w install FW 15
Con
6:00 -10:00pm
V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
60
6:00 -10:00pm
6:00 -10:00pm
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 465 Grade 200 m3
Site Manager 1 472 Grade 300 m3
D.Site Manager 2 876 Grade 350 m3 365
Administration 2 1,038 Grade 400 m3 5,784
Shopdrawing 3 2,138 Lean concrete: Unit Quantity Cumulation
QA/QC 2 671 Grade 200 m3 3,005
Site Engineer 32 12,927 Grade 250 m3 -
Surveyor 9 3,626 Rebar Unit Quantity Cumulation
56 14,111 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 30 49,364 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,051 D22 ton -
Fabrication workshop 5 2,970 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,686 D32 ton 190
Formworker 15 40,939 ton
General workers 15 34,826
Security 19 128,828
Sub Total 113 267,345
Page 25
Total 221 - 1,143.34
Page 26
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 27
Page 28
HOA BINH CORPORATION
DAILY REPORT
Date:6/8/2010 Friday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm
V3 R 7:30am - 5:00pm
(Tower) FW 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 12 7:30am - 5:00pm
V6 L7-8 floor beam, core rebar install R 40 7:30am - 5:00pm
(Tower) L7-8 floor beam, core f/w install FW 40 7:30am - 5:00pm
Con
GW 7:30am - 5:00pm
V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
92
7:30am - 5:00pm
7:30am - 5:00pm
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 466 Grade 200 m3
Site Manager 1 473 Grade 300 m3
D.Site Manager 2 878 Grade 350 m3 365
Administration 2 1,040 Grade 400 m3 5,784
Shopdrawing 3 2,141 Lean concrete: Unit Quantity Cumulation
QA/QC 2 673 Grade 200 m3 3,005
Site Engineer 32 12,959 Grade 250 m3 -
Surveyor 9 3,635 Rebar Unit Quantity Cumulation
56 14,167 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 40 49,404 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,066 D22 ton -
Fabrication workshop 5 2,975 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,700 D32 ton 190
Formworker 40 40,979 ton
General workers 12 34,838
Security 19 128,847
Sub Total 145 267,490
Page 29
Total 253 - 1,143.34
Page 30
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 31
Page 32
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:6/8/2010 Friday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
GW 6:00 -10:00pm
V3 R 6:00 -10:00pm
(Tower) FW
Con
Cleaning, material moving GW 12 6:00 -10:00pm
V6 L7-8 slab beam, core rebar install R 35 6:00 -10:00pm
(Tower) L7-8 slab beam, core f/w install FW 25
Con
GW 6:00 -10:00pm
V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
72
6:00 -10:00pm
6:00 -10:00pm
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 467 Grade 200 m3
Site Manager 1 474 Grade 300 m3
D.Site Manager 2 880 Grade 350 m3 365
Administration 2 1,042 Grade 400 m3 5,784
Shopdrawing 3 2,144 Lean concrete: Unit Quantity Cumulation
QA/QC 2 675 Grade 200 m3 3,005
Site Engineer 32 12,991 Grade 250 m3 -
Surveyor 9 3,644 Rebar Unit Quantity Cumulation
56 14,223 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 35 49,439 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,081 D22 ton -
Fabrication workshop 5 2,980 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,714 D32 ton 190
Formworker 25 41,004 ton
General workers 12 34,850
Security 19 128,866
Sub Total 125 267,615
Page 33
Total 233 - 1,143.34
Page 34
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 35
Page 36
HOA BINH CORPORATION
DAILY REPORT
Date:7/8/2010 Saturday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm
V3 R 7:30am - 5:00pm
(Tower) FW 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm
V6 L8 slab beam, core rebar install R 35 7:30am - 5:00pm
(Tower) L8 slab beam, core f/w install FW 32 7:30am - 5:00pm
Con
7:30am - 5:00pm
V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
82
GW
7:30am - 5:00pm
7:30am - 5:00pm
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 468 Grade 200 m3
Site Manager 1 475 Grade 300 m3
D.Site Manager 2 882 Grade 350 m3 365
Administration 2 1,044 Grade 400 m3 5,784
Shopdrawing 3 2,147 Lean concrete: Unit Quantity Cumulation
QA/QC 2 677 Grade 200 m3 3,005
Site Engineer 32 13,023 Grade 250 m3 -
Surveyor 9 3,653 Rebar Unit Quantity Cumulation
56 14,279 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 35 49,474 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,096 D22 ton -
Fabrication workshop 5 2,985 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,728 D32 ton 190
Formworker 32 41,036 ton
General workers 15 34,865
Security 19 128,885
Sub Total 135 267,750
Page 37
Total 243 - 1,143.34
Page 38
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 39
Page 40
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:7/8/2010 Saturday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
GW 6:00 -10:00pm
V3 R 6:00 -10:00pm
(Tower) FW
Con
Cleaning, material moving GW 15 6:00 -10:00pm
V6 L8 slab beam, core rebar install R 15 6:00 -10:00pm
(Tower) L8 slab beam, core f/w install FW 10
Con
6:00 -10:00pm
V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
40
GW
6:00 -10:00pm
6:00 -10:00pm
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 469 Grade 200 m3
Site Manager 1 476 Grade 300 m3
D.Site Manager 2 884 Grade 350 m3 365
Administration 2 1,046 Grade 400 m3 5,784
Shopdrawing 3 2,150 Lean concrete: Unit Quantity Cumulation
QA/QC 2 679 Grade 200 m3 3,005
Site Engineer 32 13,055 Grade 250 m3 -
Surveyor 9 3,662 Rebar Unit Quantity Cumulation
56 14,335 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 15 49,489 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,111 D22 ton -
Fabrication workshop 5 2,990 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,742 D32 ton 190
Formworker 10 41,046 ton
General workers 15 34,880
Security 19 128,904
Sub Total 93 267,843
Page 41
Total 201 - 1,143.34
Page 42
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 43
Page 44
HOA BINH CORPORATION
DAILY REPORT
Date:8/8/2010 Sunday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
GW 7:30am - 5:00pm
V3 R 7:30am - 5:00pm
(Tower) FW 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm
V6 L8 slab beam rebar inspection R 35 7:30am - 5:00pm
(Tower) L8 slab beam f/w inspection FW 32 7:30am - 5:00pm
Con
7:30am - 5:00pm
V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
82
Con
GW 7:30am - 5:00pm
Page 45
Total 243 - 1,143.34
Page 46
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 47
Page 48
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:7/8/2010 Saturday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm
V3 R 6:00 -10:00pm
(Tower) FW
Con
Cleaning, material moving GW 10 6:00 -10:00pm
V6 Casting con'c slab beam L8 R 15 6:00 -10:00pm
(Tower) Casting con'c slab beam L8 FW 20
Con
6:00 -10:00pm
V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
45
Page 49
Total 206 - 1,143.34
Page 50
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 51
Page 52
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:9/8/2010 Monday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm
V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm
V6 L8 slab beam, core rebar install R 35 7:30am - 5:00pm
(Tower) L8 slab beam, core f/w install FW 32 7:30am - 5:00pm
Con
7:30am - 5:00pm
V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
82
GW
7:30am - 5:00pm
7:30am - 5:00pm
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 472 Grade 200 m3
Site Manager 1 479 Grade 300 m3
D.Site Manager 2 890 Grade 350 m3 365
Administration 2 1,052 Grade 400 m3 5,784
Shopdrawing 3 2,159 Lean concrete: Unit Quantity Cumulation
QA/QC 2 685 Grade 200 m3 3,005
Site Engineer 32 13,151 Grade 250 m3 -
Surveyor 9 3,689 Rebar Unit Quantity Cumulation
56 14,503 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 35 49,574 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,156 D22 ton -
Fabrication workshop 5 3,005 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,784 D32 ton 190
Formworker 32 41,130 ton
General workers 15 34,920
Security 19 128,961
Sub Total 135 268,211
Page 53
Total 243 - 1,143.34
Page 54
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 55
Page 56
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:9/8/2010 Monday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
GW 6:00 -10:00pm
V3 R 6:00 -10:00pm
(Tower) FW
Con
Cleaning, material moving GW 15 6:00 -10:00pm
V6 inspection slab opening L3 R 25 6:00 -10:00pm
(Tower) Casting con'c col. slab opening FW 10
Con
6:00 -10:00pm
V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
50
6:00 -10:00pm
6:00 -10:00pm
Page 57
Total 211 - 1,143.34
Page 58
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 59
Page 60
HOA BINH CORPORATION
DAILY REPORT
Date:10/8/2010 Tuesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm
V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm
V6 L8 slab beam, L3 slab beam opening install R 35 7:30am - 5:00pm
(Tower) L8 col., slab L9 install FW 32 7:30am - 5:00pm
Remove col. f/w opening Con
7:30am - 5:00pm
V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
82
GW
7:30am - 5:00pm
7:30am - 5:00pm
Page 61
Total 243 - 1,143.34
Page 62
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 63
Page 64
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:10/8/2010 Tuesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm
V3 6:00 -10:00pm
(Tower)
Con
Cleaning, material moving GW 15 6:00 -10:00pm
V6 L8-9 col.,core install R 30 6:00 -10:00pm
(Tower) L8-9 core f/w install FW 15
Con
6:00 -10:00pm
V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
60
6:00 -10:00pm
6:00 -10:00pm
Page 65
Total 221 - 1,143.34
Page 66
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 67
Page 68
HOA BINH CORPORATION
DAILY REPORT
Date:11/8/2010 Wednesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm
V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm
L3 opening install, core wall install. R 40 7:30am - 5:00pm
V6
(Tower) L3 slab beam opening & L9 slab beam col FW 50 7:30am - 5:00pm
install
Remove col. f/w opening Con
V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
105
GW
7:30am - 5:00pm
7:30am - 5:00pm
Page 69
Total 266 - 1,143.34
Page 70
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 71
Page 72
HOA BINH CORPORATION
DAILY REPORT
Date:11/8/2010 Wednesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm
V3 6:00 -10:00pm
(Tower)
Con
Cleaning, material moving GW 15 6:00 -10:00pm
V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
100
GW
6:00 -10:00pm
6:00 -10:00pm
Page 73
Total 261 - 1,143.34
Page 74
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 75
Page 76
HOA BINH CORPORATION
DAILY REPORT
Date:12/8/2010 Thursday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm
V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm
V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
100
GW
7:30am - 5:00pm
7:30am - 5:00pm
Page 77
Total 261 - 1,143.34
Page 78
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 79
Page 80
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:12/8/2010 Thursday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm
V3 6:00 -10:00pm
(Tower)
Con
Cleaning, material moving GW 15 6:00 -10:00pm
V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
70
6:00 -10:00pm
6:00 -10:00pm
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 477 Grade 200 m3
Site Manager 1 483 Grade 300 m3
D.Site Manager 2 898 Grade 350 m3 365
Administration 2 1,060 Grade 400 m3 5,784
Shopdrawing 3 2,171 Lean concrete: Unit Quantity Cumulation
QA/QC 2 693 Grade 200 m3 3,005
Site Engineer 32 13,279 Grade 250 m3 -
Surveyor 9 3,725 Rebar Unit Quantity Cumulation
56 14,727 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 30 49,709 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,216 D22 ton -
Fabrication workshop 5 3,025 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,840 D32 ton 190
Formworker 15 41,245 ton
General workers 15 34,980
Security 19 129,037
Sub Total 113 268,733
Page 81
Total 221 - 1,143.34
Page 82
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 83
Page 84
HOA BINH CORPORATION
DAILY REPORT
Date:13/8/2010 Friday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm
V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm
V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
100
7:30am - 5:00pm
7:30am - 5:00pm
Page 85
Total 261 - 1,143.34
Page 86
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 87
Page 88
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:13/8/2010 Friday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm
V3 6:00 -10:00pm
(Tower)
V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
65
6:00 -10:00pm
6:00 -10:00pm
Page 89
Total 226 - 1,143.34
Page 90
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 91
Page 92
HOA BINH CORPORATION
DAILY REPORT
Date:14/8/2010 Saturday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm
V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 18 7:30am - 5:00pm
V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
120
7:30am - 5:00pm
7:30am - 5:00pm
Page 93
Total 281 - 1,143.34
Page 94
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 95
Page 96
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:14/8/2010 Saturday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm
V3 6:00 -10:00pm
(Tower)
Con
Cleaning, material moving GW 15 6:00 -10:00pm
V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
85
6:00 -10:00pm
6:00 -10:00pm
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 481 Grade 200 m3
Site Manager 1 487 Grade 300 m3
D.Site Manager 2 906 Grade 350 m3 365
Administration 2 1,068 Grade 400 m3 5,784
Shopdrawing 3 2,183 Lean concrete: Unit Quantity Cumulation
QA/QC 2 701 Grade 200 m3 3,005
Site Engineer 32 13,407 Grade 250 m3 -
Surveyor 9 3,761 Rebar Unit Quantity Cumulation
56 14,951 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 45 49,881 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,276 D22 ton -
Fabrication workshop 5 3,045 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,896 D32 ton 190
Formworker 25 41,380 ton
General workers 15 35,043
Security 19 129,113
Sub Total 138 269,315
Page 97
Total 246 - 1,143.34
Page 98
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 99
Page 100
HOA BINH CORPORATION
DAILY REPORT
Date:15/8/2010 Sunday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm
V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm
V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
97
7:30am - 5:00pm
7:30am - 5:00pm
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 482 Grade 200 m3
Site Manager 1 488 Grade 300 m3
D.Site Manager 2 908 Grade 350 m3 365
Administration 2 1,070 Grade 400 m3 5,784
Shopdrawing 3 2,186 Lean concrete: Unit Quantity Cumulation
QA/QC 2 703 Grade 200 m3 3,005
Site Engineer 32 13,439 Grade 250 m3 -
Surveyor 9 3,770 Rebar Unit Quantity Cumulation
56 15,007 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 52 49,933 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,291 D22 ton -
Fabrication workshop 5 3,050 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,910 D32 ton 190
Formworker 30 41,410 ton
General workers 15 35,058
Security 19 129,132
Sub Total 150 269,465
Page 101
Total 258 - 1,143.34
Page 102
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 103
Page 104
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:15/8/2010 Sunday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm
V3 6:00 -10:00pm
(Tower)
Con
Cleaning, material moving GW 15 6:00 -10:00pm
V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
85
6:00 -10:00pm
6:00 -10:00pm
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 483 Grade 200 m3
Site Manager 1 487 Grade 300 m3
D.Site Manager 2 906 Grade 350 m3 365
Administration 2 1,068 Grade 400 m3 5,784
Shopdrawing 3 2,183 Lean concrete: Unit Quantity Cumulation
QA/QC 2 701 Grade 200 m3 3,005
Site Engineer 32 13,407 Grade 250 m3 -
Surveyor 9 3,761 Rebar Unit Quantity Cumulation
56 14,951 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 45 49,881 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,276 D22 ton -
Fabrication workshop 5 3,045 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,896 D32 ton 190
Formworker 25 41,380 ton
General workers 15 35,043
Security 19 129,113
Sub Total 138 269,315
Page 105
Total 246 - 1,143.34
Page 106
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 107
Page 108
HOA BINH CORPORATION
DAILY REPORT
Date:16/8/2010 Monday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm
V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm
V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
90
7:30am - 5:00pm
7:30am - 5:00pm
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 484 Grade 200 m3
Site Manager 1 487 Grade 300 m3
D.Site Manager 2 906 Grade 350 m3 365
Administration 2 1,068 Grade 400 m3 5,784
Shopdrawing 3 2,183 Lean concrete: Unit Quantity Cumulation
QA/QC 2 701 Grade 200 m3 3,005
Site Engineer 32 13,407 Grade 250 m3 -
Surveyor 9 3,761 Rebar Unit Quantity Cumulation
56 14,951 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 35 49,871 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,276 D22 ton -
Fabrication workshop 5 3,045 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,896 D32 ton 190
Formworker 40 41,395 ton
General workers 15 35,043
Security 19 129,113
Sub Total 143 269,320
Page 109
Total 251 - 1,143.34
Page 110
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 111
Page 112
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:16/8/2010 Monday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm
V3 6:00 -10:00pm
(Tower)
Con
Cleaning, material moving GW 15 6:00 -10:00pm
V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
55
6:00 -10:00pm
6:00 -10:00pm
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 485 Grade 200 m3
Site Manager 1 488 Grade 300 m3
D.Site Manager 2 908 Grade 350 m3 365
Administration 2 1,070 Grade 400 m3 5,784
Shopdrawing 3 2,186 Lean concrete: Unit Quantity Cumulation
QA/QC 2 703 Grade 200 m3 3,005
Site Engineer 32 13,439 Grade 250 m3 -
Surveyor 9 3,770 Rebar Unit Quantity Cumulation
56 15,007 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 40 49,911 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,291 D22 ton -
Fabrication workshop 5 3,050 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,910 D32 ton 190
Formworker - 41,395 ton
General workers 15 35,058
Security 19 129,132
Sub Total 108 269,428
Page 113
Total 216 - 1,143.34
Page 114
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 115
Page 116
HOA BINH CORPORATION
DAILY REPORT
Date:17/8/2010 Tuesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm
V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm
V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
120
7:30am - 5:00pm
7:30am - 5:00pm
Page 117
Sub Total 163 269,591
Total 271 - 1,143.34
Page 118
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 119
Page 120
HOA BINH CORPORATION
DAILY REPORT(After 5: 00 pm)
Date:17/8/2010 Tuesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm
V3 6:00 -10:00pm
(Tower)
Con
Cleaning, material moving GW 15 6:00 -10:00pm
V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
90
6:00 -10:00pm
6:00 -10:00pm
Page 121
Total 251 - 1,143.34
Page 122
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 123
Page 124
HOA BINH CORPORATION
DAILY REPORT
Date:18/8/2010 Wednesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm
V3 6:00 -10:00pm
(Tower)
V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
90
6:00 -10:00pm
6:00 -10:00pm
Page 125
Total 251 - 1,143.34
Page 126
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 127
Page 128
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:18/8/2010 Wednesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm
V3 6:00 -10:00pm
(Tower)
Con
Cleaning, material moving GW 15 6:00 -10:00pm
V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
80
6:00 -10:00pm
6:00 -10:00pm
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 489 Grade 200 m3
Site Manager 1 492 Grade 300 m3
D.Site Manager 2 916 Grade 350 m3 365
Administration 2 1,078 Grade 400 m3 5,784
Shopdrawing 3 2,198 Lean concrete: Unit Quantity Cumulation
QA/QC 2 711 Grade 200 m3 3,005
Site Engineer 32 13,567 Grade 250 m3 -
Surveyor 9 3,806 Rebar Unit Quantity Cumulation
56 15,231 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 35 50,066 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,351 D22 ton -
Fabrication workshop 5 3,070 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,966 D32 ton 190
Formworker 20 41,540 ton
General workers 15 35,118
Security 19 129,208
Sub Total 123 270,000
Page 129
Total 231 - 1,143.34
Page 130
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 131
Page 132
HOA BINH CORPORATION
DAILY REPORT
Date:19/8/2010 Thursday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm
V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm
V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
90
7:30am - 5:00pm
7:30am - 5:00pm
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 490 Grade 200 m3
Site Manager 1 493 Grade 300 m3
D.Site Manager 2 918 Grade 350 m3 365
Administration 2 1,080 Grade 400 m3 5,784
Shopdrawing 3 2,201 Lean concrete: Unit Quantity Cumulation
QA/QC 2 713 Grade 200 m3 3,005
Site Engineer 32 13,599 Grade 250 m3 -
Surveyor 9 3,815 Rebar Unit Quantity Cumulation
56 15,287 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 35 50,101 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,366 D22 ton -
Fabrication workshop 5 3,075 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,980 D32 ton 190
Formworker 40 41,580 ton
General workers 15 35,133
Security 19 129,227
Sub Total 143 270,143
Page 133
Total 251 - 1,143.34
Page 134
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 135
Page 136
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:19/8/2010 Thursday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm
V3 6:00 -10:00pm
(Tower)
Con
Cleaning, material moving GW 5 6:00 -10:00pm
V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
70
6:00 -10:00pm
6:00 -10:00pm
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 491 Grade 200 m3
Site Manager 1 494 Grade 300 m3
D.Site Manager 2 920 Grade 350 m3 365
Administration 2 1,082 Grade 400 m3 5,784
Shopdrawing 3 2,204 Lean concrete: Unit Quantity Cumulation
QA/QC 2 715 Grade 200 m3 3,005
Site Engineer 32 13,631 Grade 250 m3 -
Surveyor 9 3,824 Rebar Unit Quantity Cumulation
56 15,343 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 40 50,141 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,381 D22 ton -
Fabrication workshop 5 3,080 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 5,994 D32 ton 190
Formworker 25 41,605 ton
General workers 5 35,138
Security 19 129,246
Sub Total 123 270,266
Page 137
Total 231 - 1,143.34
Page 138
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 139
Page 140
HOA BINH CORPORATION
DAILY REPORT
Date:20/8/2010 Friday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm
V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm
V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
85
7:30am - 5:00pm
7:30am - 5:00pm
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 492 Grade 200 m3
Site Manager 1 495 Grade 300 m3
D.Site Manager 2 922 Grade 350 m3 365
Administration 2 1,084 Grade 400 m3 5,784
Shopdrawing 3 2,207 Lean concrete: Unit Quantity Cumulation
QA/QC 2 717 Grade 200 m3 3,005
Site Engineer 32 13,663 Grade 250 m3 -
Surveyor 9 3,833 Rebar Unit Quantity Cumulation
56 15,399 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 30 50,171 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,396 D22 ton -
Fabrication workshop 5 3,085 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,008 D32 ton 190
Formworker 40 41,645 ton
General workers 15 35,153
Security 19 129,265
Sub Total 138 270,404
Page 141
Total 246 - 1,143.34
Page 142
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 143
Page 144
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:20/8/2010 Friday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm
V3 6:00 -10:00pm
(Tower)
V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
65
6:00 -10:00pm
6:00 -10:00pm
Page 145
Total 226 - 1,143.34
Page 146
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 147
Page 148
HOA BINH CORPORATION
DAILY REPORT
Date:21/8/2010 Saturday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm
V3 7:30am - 5:00pm
(Tower) FW 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm
V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
60
7:30am - 5:00pm
7:30am - 5:00pm
Page 149
Total 221 - 1,143.34
Page 150
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 151
Page 152
HOA BINH CORPORATION
DAILY REPORT
Date:21/8/2010 Saturday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
GW 6:00 -10:00pm
V3 R 6:00 -10:00pm
(Tower) FW
Con
Cleaning, material moving GW 15 6:00 -10:00pm
V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
65
6:00 -10:00pm
6:00 -10:00pm
Page 153
Total 226 - 1,143.34
Page 154
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 155
Page 156
HOA BINH CORPORATION
DAILY REPORT
Date:21/8/2010 Saturday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
GW 7:30am - 5:00pm
V3 R 7:30am - 5:00pm
(Tower) FW 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm
V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
65
7:30am - 5:00pm
7:30am - 5:00pm
Page 157
Total 226 - 1,143.34
Page 158
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 159
Page 160
HOA BINH CORPORATION
DAILY REPORT
Date:21/8/2010 Saturday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
GW 6:00 -10:00pm
V3 R 6:00 -10:00pm
(Tower) FW
Con
Cleaning, material moving GW 15 6:00 -10:00pm
V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
65
6:00 -10:00pm
6:00 -10:00pm
Page 161
Total 226 - 1,143.34
Page 162
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 163
Page 164
HOA BINH CORPORATION
DAILY REPORT
Date:23/8/2010 Monday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm
V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm
V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
95
7:30am - 5:00pm
7:30am - 5:00pm
Page 165
Total 256 - 1,143.34
Page 166
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 167
Page 168
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:23/8/2010 Monday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm
V3 6:00 -10:00pm
(Tower)
Con
Cleaning, material moving GW 15 6:00 -10:00pm
V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
80
6:00 -10:00pm
6:00 -10:00pm
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 499 Grade 200 m3
Site Manager 1 502 Grade 300 m3
D.Site Manager 2 936 Grade 350 m3 365
Administration 2 1,098 Grade 400 m3 5,784
Shopdrawing 3 2,228 Lean concrete: Unit Quantity Cumulation
QA/QC 2 731 Grade 200 m3 3,005
Site Engineer 32 13,887 Grade 250 m3 -
Surveyor 9 3,896 Rebar Unit Quantity Cumulation
56 15,791 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 30 50,356 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,486 D22 ton -
Fabrication workshop 5 3,115 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,092 D32 ton 190
Formworker 35 41,805 ton
General workers 15 35,238
Security 19 129,379
Sub Total 133 271,152
Page 169
Total 241 - 1,143.34
Page 170
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 171
Page 172
HOA BINH CORPORATION
DAILY REPORT
Date:24/8/2010 Tuesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm
V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
7:30am - 5:00pm
Cleaning, material moving GW 17 7:30am - 5:00pm
V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
102
7:30am - 5:00pm
7:30am - 5:00pm
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 500 Grade 200 m3
Site Manager 1 503 Grade 300 m3
D.Site Manager 2 938 Grade 350 m3 365
Administration 2 1,100 Grade 400 m3 5,784
Shopdrawing 3 2,231 Lean concrete: Unit Quantity Cumulation
QA/QC 2 733 Grade 200 m3 3,005
Site Engineer 32 13,919 Grade 250 m3 -
Surveyor 9 3,905 Rebar Unit Quantity Cumulation
56 15,847 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 40 50,396 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,501 D22 ton -
Fabrication workshop 5 3,120 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,106 D32 ton 190
Formworker 45 41,850 ton
General workers 17 35,255
Security 19 129,398
Sub Total 155 271,307
Page 173
Total 263 - 1,143.34
Page 174
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 175
Page 176
HOA BINH CORPORATION
DAILY REPORT
Date:24/8/2010 Thuesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm
V3 6:00 -10:00pm
(Tower)
V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
85
6:00 -10:00pm
6:00 -10:00pm
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 500 Grade 200 m3
Site Manager 1 503 Grade 300 m3
D.Site Manager 2 938 Grade 350 m3 365
Administration 2 1,100 Grade 400 m3 5,784
Shopdrawing 3 2,231 Lean concrete: Unit Quantity Cumulation
QA/QC 2 733 Grade 200 m3 3,005
Site Engineer 32 13,919 Grade 250 m3 -
Surveyor 9 3,905 Rebar Unit Quantity Cumulation
56 15,847 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 40 50,396 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,501 D22 ton -
Fabrication workshop 5 3,120 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,106 D32 ton 190
Formworker 30 41,835 ton
General workers 15 35,253
Security 19 129,398
Sub Total 138 271,290
Page 177
Total 246 - 1,143.34
Page 178
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 179
Page 180
HOA BINH CORPORATION
DAILY REPORT
Date:25/8/2010 Thuesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm
V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
7:30am - 5:00pm
Cleaning, material moving GW 17 7:30am - 5:00pm
V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
102
7:30am - 5:00pm
7:30am - 5:00pm
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 500 Grade 200 m3
Site Manager 1 503 Grade 300 m3
D.Site Manager 2 938 Grade 350 m3 365
Administration 2 1,100 Grade 400 m3 5,784
Shopdrawing 3 2,231 Lean concrete: Unit Quantity Cumulation
QA/QC 2 733 Grade 200 m3 3,005
Site Engineer 32 13,919 Grade 250 m3 -
Surveyor 9 3,905 Rebar Unit Quantity Cumulation
56 15,847 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 40 50,396 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,501 D22 ton -
Fabrication workshop 5 3,120 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,106 D32 ton 190
Formworker 45 41,850 ton
General workers 17 35,255
Security 19 129,398
Sub Total 155 271,307
Page 181
Total 263 - 1,143.34
Page 182
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 183
Page 184
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:25/8/2010 Thursday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm
V3 6:00 -10:00pm
(Tower)
Con
Cleaning, material moving GW 15 6:00 -10:00pm
V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
Con
85
6:00 -10:00pm
6:00 -10:00pm
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 501 Grade 200 m3
Site Manager 1 504 Grade 300 m3
D.Site Manager 2 940 Grade 350 m3 365
Administration 2 1,102 Grade 400 m3 5,784
Shopdrawing 3 2,234 Lean concrete: Unit Quantity Cumulation
QA/QC 2 735 Grade 200 m3 3,005
Site Engineer 32 13,951 Grade 250 m3 -
Surveyor 9 3,914 Rebar Unit Quantity Cumulation
56 15,903 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium 40 50,436 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,516 D22 ton -
Fabrication workshop 5 3,125 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,120 D32 ton 190
Formworker 30 41,880 ton
General workers 15 35,270
Security 19 129,417
Sub Total 138 271,445
Page 185
Total 246 - 1,143.34
Page 186
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 187
Page 188
HOA BINH CORPORATION
DAILY REPORT
Date:26/8/2010 Thursday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm
V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm
V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
90
7:30am - 5:00pm
7:30am - 5:00pm
Page 189
Total 251 - 1,143.34
Page 190
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 191
Page 192
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:26/8/2010 Thursday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
6:00 -10:00pm
V3 6:00 -10:00pm
(Tower)
V6 R 6:00 -10:00pm
(Tower)
L11 slab beam casting con'c FW 10
Con
6:00 -10:00pm
V5 6:00 -10:00pm
(Tower) 6:00 -10:00pm
25
6:00 -10:00pm
6:00 -10:00pm
Con
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 503 Grade 200 m3
Site Manager 1 506 Grade 300 m3
D.Site Manager 2 944 Grade 350 m3 365
Administration 2 1,106 Grade 400 m3 5,784
Shopdrawing 3 2,240 Lean concrete: Unit Quantity Cumulation
QA/QC 2 739 Grade 200 m3 3,005
Site Engineer 32 14,015 Grade 250 m3 -
Surveyor 9 3,932 Rebar Unit Quantity Cumulation
56 16,015 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium - 50,471 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,546 D22 ton -
Fabrication workshop 5 3,135 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,148 D32 ton 190
Formworker 10 41,930 ton
General workers 15 35,300
Security 19 129,455
Sub Total 78 271,666
Page 193
Total 186 - 1,143.34
Page 194
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 195
Page 196
HOA BINH CORPORATION
DAILY REPORT
Date:27/8/2010 Friday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm
V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con 7:30am - 5:00pm
Cleaning, material moving GW 17 7:30am - 5:00pm
V6 R 7:30am - 5:00pm
(Tower)
FW 7:30am - 5:00pm
Casting con'c slab beam L11 Con 15
V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
32
7:30am - 5:00pm
7:30am - 5:00pm
SUM 0
Manpower
Staffs Quantity Cumulation Concrete: Unit Quantity Cumulation
Project Manager 1 504 Grade 200 m3
Site Manager 1 507 Grade 300 m3
D.Site Manager 2 946 Grade 350 m3 365
Administration 2 1,108 Grade 400 m3 5,784
Shopdrawing 3 2,243 Lean concrete: Unit Quantity Cumulation
QA/QC 2 741 Grade 200 m3 3,005
Site Engineer 32 14,047 Grade 250 m3 -
Surveyor 9 3,941 Rebar Unit Quantity Cumulation
56 16,071 D6 ton
Safety 108 18,445 D8 ton
Workers Quantity Cumulation D10 ton 135
Carpenters - Tower - D12 ton 143
Carpenters - Podium - 280 D14 ton -
Rebar - Tower - - D16 ton 297
Rebar - Podium - 50,471 D18 ton 3
Concrete - Tower - 389 D20 ton 96
Concrete - Podium 15 4,561 D22 ton -
Fabrication workshop 5 3,140 D25 ton 87
Welders - 12 D28 ton 193
Electricians 14 6,162 D32 ton 190
Formworker - 41,930 ton
General workers 17 35,317
Security 19 129,474
Sub Total 70 271,736
Page 197
Total 178 - 1,143.34
Page 198
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 199
Page 200
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:27/8/2010 Friday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 12 6:00 -10:00pm
V6 R 6:00 -10:00pm
(Tower)
FW
Casting con'c slab beam L11 Con 15
Cleaning, material moving GW 10 6:00 -10:00pm
Page 201
Total 351 - 1,143.34
Page 202
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 203
Page 204
HOA BINH CORPORATION
DAILY REPORT
Date:28/8/2010 Saturday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 12 7:30am - 5:00pm
Page 205
Total 432 - 1,143.34
Page 206
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 207
Page 208
HOA BINH CORPORATION
DAILY REPORT
Date:28/8/2010 Saturday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 12 6:00 -10:00pm
Page 209
Total 413 - 1,143.34
Page 210
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 211
Page 212
HOA BINH CORPORATION
DAILY REPORT
Date:30/8/2010 Monday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 12 7:30am - 5:00pm
Page 213
Total 382 - 1,143.34
Page 214
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 215
Page 216
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:30/8/2010 Monday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
L18 slab beam casting con'c GW 5 6:00 -10:00pm
V3 R 6:00 -10:00pm
(Tower) L18 slab beam casting con'c FW 5
L18 slab beam casting con'c Con 30
Cleaning, material moving GW 20 6:00 -10:00pm
Page 217
Total 351 - 1,143.34
Page 218
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 219
Page 220
HOA BINH CORPORATION
DAILY REPORT
Date:31/8/2010 Tuesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 12 7:30am - 5:00pm
Page 221
Total 429 - 1,143.34
Page 222
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 223
Page 224
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:31/8/2010 Tuesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 12
Page 225
Total 387 - 1,143.34
Page 226
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 227
Page 228
HOA BINH CORPORATION
DAILY REPORT
Date:1/9/2010 Wednesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 12 7:30am - 5:00pm
Page 229
Total 453 - 1,143.34
Page 230
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 231
Page 232
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:1/9/2010 Wednesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 12 6:00 -10:00pm
Page 233
Total 453 - 1,143.34
Page 234
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 235
Page 236
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:1/9/2010 Wednesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 12 6:00 -10:00pm
Page 237
Total 453 - 1,143.34
Page 238
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 239
Page 240
HOA BINH CORPORATION
DAILY REPORT
Date:4/9/2010 Saturday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 10 7:30am - 5:00pm
Page 241
Total 485 - 1,143.34
Page 242
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 243
Page 244
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:4/9/2010 Saturday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 12 6:00 -10:00pm
Page 245
Total 435 - 1,143.34
Page 246
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 247
Page 248
HOA BINH CORPORATION
DAILY REPORT
Date:6/9/2010 Monday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 10 7:30am - 5:00pm
Page 249
Total 396 - 1,143.34
Page 250
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 251
Page 252
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:6/9/2010 Monday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
L19 slab beam casting con'c GW 11 6:00 -10:00pm
V3 R 6:00 -10:00pm
(Tower) L19 slab beam casting con'c FW 4
L19 slab beam casting con'c 30
Cleaning, material moving GW 15 6:00 -10:00pm
Page 253
Total 330 - 1,143.34
Page 254
Equipments
SET 2
Saw machine SET 14
Formwork
Description Unit Quantity Cumulation Remarks
Euroform 300x600 200
Euroform 400x600 250
Euroform 450x600 120
Euroform 600x600 300
Euroform 200x1200 2
Euroform 250x1200 1
Euroform 300x1200 614
Euroform 350x1200 15
Euroform 400x1200 754
Euroform 450x1200 632
Euroform 500x1200 31
Euroform 550x1200 202
Euroform 600x1200 1,944
Angle V 65x65x1200 100
Angle V 65x65x2400 100
Angle (100+100)x600 208
Angle (100+150)x1200 200
Angle (150+150)x1200 200
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 255
Page 256
HOA BINH CORPORATION
DAILY REPORT
Date:7/9/2010 Tuesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 10 7:30am - 5:00pm
Page 257
Total 434 - 1,143.34
Page 258
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 259
Page 260
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:7/9/2010 Tuesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 10 6:00 -10:00pm
V6 R 6:00 -10:00pm
(Tower)
L13 slab beam inspection & casting FW 10
Casting con'c slab beam L13 Con 15
Cleaning, material moving GW 10 6:00 -10:00pm
Page 261
Total 331 - 1,143.34
Page 262
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 263
Page 264
HOA BINH CORPORATION
DAILY REPORT
Date:8/9/2010 Wednesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 10 7:30am - 5:00pm
V6 R 7:30am - 5:00pm
(Tower)
Remove col. f/w slab beam L14 FW 30 7:30am - 5:00pm
Con
GW
Page 265
Total 337 - 1,143.34
Page 266
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 267
Page 268
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:8/9/2010 Wednesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 10 6:00 -10:00pm
V6 R 6:00 -10:00pm
(Tower)
Remove col. f/w slab beam L14 FW 30
Con
GW 6:00 -10:00pm
Page 269
Total 348 - 1,143.34
Page 270
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 271
Page 272
HOA BINH CORPORATION
DAILY REPORT
Date:9/9/2010 Thursday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 10 7:30am - 5:00pm
Page 273
Total 471 - 1,143.34
Page 274
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 275
Page 276
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:9/9/2010 Thursday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 11 6:00 -10:00pm
Page 277
Total 388 - 1,143.34
Page 278
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 279
Page 280
HOA BINH CORPORATION
DAILY REPORT
Date:10/9/2010 Friday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 11 7:30am - 5:00pm
Page 281
Total 446 - 1,143.34
Page 282
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 283
Page 284
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:10/9/2010 Friday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 11 6:00 -10:00pm
Page 285
Total 376 - 1,143.34
Page 286
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 287
Page 288
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:11/9/2010 Saturday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
7:30am - 5:00pm
V3 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
7:30am - 5:00pm
Cleaning, material moving GW 15 7:30am - 5:00pm
V5 7:30am - 5:00pm
(Tower) 7:30am - 5:00pm
Con
115
7:30am - 5:00pm
7:30am - 5:00pm
Page 289
Total 276 - 1,143.34
Page 290
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 291
Page 292
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:11/9/2010 Saturday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 11 6:00 -10:00pm
Page 293
Total 355 - 1,143.34
Page 294
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 295
Page 296
HOA BINH CORPORATION
DAILY REPORT
Date:13/9/2010 Monday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 11 7:30am - 5:00pm
V5 R 7:30am - 5:00pm
(Tower) L15 slab beam f/w install & inspection FW 30 7:30am - 5:00pm
Con
178
GW
Page 297
Total 369 - 1,143.34
Page 298
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 299
Page 300
HOA BINH CORPORATION
DAILY REPORT(After 5:00 pm)
Date:13/9/2010 Monday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 11
V3 R 6:00 -10:00pm
(Tower) L20 -21 col. slab beam f/w install FW 38
V5 R 6:00 -10:00pm
(Tower) L15 slab beam f/w install & inspection FW 30 6:00 -10:00pm
Con
128
Cleaning, material moving GW 4
Page 301
Total 309 - 1,143.34
Page 302
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 303
Page 304
HOA BINH CORPORATION
DAILY REPORT
Date:14/9/2010 Tuesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 11 7:30am - 5:00pm
Page 305
Sub Total 328 279,446
Total 436 - 1,143.34
Page 306
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 307
Page 308
HOA BINH CORPORATION
DAILY REPORT
Date:14/9/2010 Tuesday Weather: Sunny Temperature:
Works carried out :
Time schedule
Work done Work schedule Q. of Workers
Cleaning, material moving GW 11 7:30am - 5:00pm
V3 R 7:30am - 5:00pm
(Tower) L20 -21 col. slab beam f/w install FW 38 7:30am - 5:00pm
7:30am - 5:00pm
Cleaning, material moving GW 10 7:30am - 5:00pm
V5 R 7:30am - 5:00pm
(Tower) L15 slab beam f/w install & inspection FW 30 7:30am - 5:00pm
Con
128
Cleaning, material moving GW 4
Page 309
Total 309 - 1,143.34
Page 310
Equipments
Angle (100+100)x1200 -
Timber 45x90 16,240
Timber 50x50 4,268
25,039
Wedge Pin General 200,000
S/Q Hook (Small) 5,000
S/Q Hook (Big) 5,000
Checked by Approved by
Site manager (Hoa Binh corporation) Site manager (Seoyong Vina)
Page 311