Beruflich Dokumente
Kultur Dokumente
ADVISORY
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
1
Table of Contents
11 Phased land use plan 140 14.3 Organizational improvement plan 266
13.5 Balance sheet analysis 205 1.8 CFS and empties on port land 299
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
2
Chapter 8
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
3
8.1 Client Related Investment Projects
8.1.1 GTI to become fully operational
Summary Coverage
Need for the project JNPT would face capacity shortfall in areas of RMQC, wharf to yard and
gate capacity by 2006-07 due to increase in traffic. GTI which is currently
ramping up its operations should be scaled up to full capacity in 2006-07.
However while capacity is available at GTI it would take 2-3 years for
traffic to match GTIs full capability of 1.3 Mn TEUs.
Technical Description The project would involve GTI adding capacity to JNPT through its new
terminal by adding 8 RMQCs, 4 Reach Stackers, 29 RTGCs, 150 Tractor
Trailers, 270,000 SQM of yard area and 7-8 gates.
Key enablers for the project The successful execution of the project would require development of
processes within JNPT to handle the increasing complexity related to
sharing resources (such as mixed train handling) which would arise due
to addition of a terminal operator. GTI would also need to ramp up its
capabilities to match performance standards of other terminals at JNPT.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
4
8.1 Client Related Investment Projects
8.1.2 Development of 32 Hectares of land for CFS
Summary Coverage
Project to be undertaken Development of 32 Hectares of CFS Land
Year of completion 2007-08
Total Traffic handled at JNPT after 3.7 Mn TEUs by JNPT by 2007-08
completion
Need for the project There is a need for developing CFS as the increase in traffic would
require an additional 10-20 Hectares of CFS area by 2007-08. Currently a
number of CFS have made plans to develop facilities outside the port
area. Although the current plans submitted to the customs department (14
new CFSs with additional 114 Hectares of CFS space) is enough to meet
future requirements of JNPT till 2010-11, there is a risk of some of these
CFS not being able to acquire land and hence develop CFS operations.
This is because the availability of land around the port is becoming a
constraint in light of upcoming SEZs. Also the proposed CFSs are at a
distance of over 5-10 Kms from the port creating delays in transfer.
Hence it is proposed that out of the additional CFS capacity required till
2010 40% should be developed within the port boundaries.
Technical Description In the latter years as availability of land outside the port further reduces it
is proposed that 70% of the additional CFS requirements should be
developed within the port land.
The area earmarked for the CFS operation is shown in Exhibit 8.1.1.
This area is connected to SH54 and would be able to handle the increase
in traffic in light of 4 laning of SH54 which would be completed in 2007-08
(also identified as a project)
JNPT would develop the land (including roads) and lease it to CFS
operator who would develop and operate the facility. Revenues for JNPT
would comprise primarily of lease rentals obtained from the operators.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
5
8.1 Client Related Investment Projects
8.1.2 Development of 32 Hectares of land for CFS
Summary Coverage
Cost of Development for JNPT The cost of development for the land is expected to be around Rs. 114.2
Crore on the basis of a development cost of Rs. 3.3 Crore per hectare
(CIDCO report on reserve pricing of land). This includes the cost of
utilities, leveling, road development etc
Revenues for JNPT Revenues expected by JNPT would be around Rs. 48 lakhs /hectare/year
(based on Rs 40/sq metre /month which is recommended rate by CIDCO,
at a rate lower than this JNPT will be making losses on construction) The
total revenues expected from the 32 hectares of land would be Rs. 16
Crores in 2007-8
Cost of development for CFS Operator The cost of development for the land is expected to be around Rs. 98
Crore on a basis of Rs. 3.06 Crore per hectare (Secondary research on
CFS costs). This includes the cost of equipment, building, contingency
etc.
Revenue for CFS Operator Revenues expected by operator would be around Rs. 1
Crores/hectare/year (Secondary research on CFS costs) The total
revenues expected from the 32 hectares of land would be Rs. 32 Crores
Key enablers for the project The successful execution of the project would require effective road
connectivity between the port and the CFS area. In absence of such road
developments, the CFS infrastructure may lead to congestion. Hence, the
review of CFS development should be done periodically to ensure that it
is line with connectivity at the port and is not causing congestion
32 ha represents requirements of CFS for a three year period between 2007-08 to 2010-11. Keeping in mind that
the action on the plan is likely to begin only after April 2007, the CFS creation at any point of time during this 3
year period may suffice.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
6
Exhibit 8.1.1 : 32 Hectares of CFS land development
32 Hectares of CFS
land (2007-08)
Road
Developments
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
7
8.1 Client Related Investment Projects
8.1.3 330m Extension of current berth
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
8
8.1 Client Related Investment Projects
8.1.3 330m Extension of current berth
330 M Expansion
Approach Roads
Reclaimed Backup
Area of 27 ha for
Container yard
operations
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
9
8.1 Client Related Investment Projects
8.1.3 330m Extension of current berth
Forecast of additional traffic Exhibit 8.1.3 Traffic potential for overall 330m
As the extension would become operational at a time expansion
where demand already exceeds supply of port Year Mn TEUs
infrastructure, it is expected that the berth would reach its
full capacity within a period of three years. Additional 2008-09 0.58
traffic that would be serviced through the 330m as a result
2009-10 0.73
of the expansion is given in Exhibit 8.1.3 and it becomes
stable after 2010-11. 2010-11 0.78
Calculation of Investments 2011-12 0.78
The Investments envisaged for 330 m of berth are shown 2012-13 0.78
in Exhibit 8.1.4. These investments have been calculated
on the basis of discussions with the port as well as 2013-14 0.78
through secondary research.
2014-15 0.78
Apart from this the port would also need to develop CFS
2015-16 0.78
and other supporting infrastructure (hinterland etc) for the
expansion. These projects have been identified separately 2016-17 0.78
and should be completed in time to ensure smooth
operations of the 330 m expansion berth. 2017-18 0.78
It has been assumed that the berthing charges accrue to 2019-20 0.78
JNPT and the terminal operators revenue source is limited
2020-21 0.78
to cargo handling operations
Currently the revenues from cargo handling are around Rs 2021-22 0.78
2650 per TEU. Based on recent trends the revenue per 2026-27 0.78
TEU is expected to be constant till 2013-14 beyond which
it is assumed to increase by a marginal 2.0% per annum. 2031-32 0.78
The marginal growth of revenue/TEU has been taken in 2036-37 0.78
light of the recent competitive pressures and in
discussions with the finance department at JNPT. 2037-38 0.78
2038-39 0.78
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
10
8.1 Client Related Investment Projects
8.1.3 330m Extension of current berth
Calculation of Additional Costs Exhibit 8.1.4 Initial Investment outlay for 330 m of
Operating costs have been assumed to be 30% of the berth
revenues in the initial year. Subsequently these costs
Investments In Rs Mn
have been increased by the rate of inflation (4%) every
year.
Berth Construction 930.24
The equipment has been replaced after 18 years of
operation. The replaced equipment has been depreciated
so that residual value at the end of BOT period is Zero. RMQC (51 m reach QC’s) 1,427.71
The rate of inflation for all costs has been taken as 4%.
TTs 499.70
Infrastructure projects are eligible for a tax holiday for the
initial 10 years of their operation under the tax clause 80I.
This clause however would expire in 2010. As the 330 m Reach Stackers 24.88
berth begins operations before 2010 it has been given tax
benefits. The tax rate has been taken at 33.66%. RTGC 1,063.00
Total 5,308.30
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
11
8.1 Client Related Investment Projects
8.1.3 330m Extension of current berth
Financial Coverage Exhibit 8.1.5 Project NPV and IRR without revenue
The project is proposed to be financed through equity sharing
and debt with a debt: equity ratio of 1:1.
Project NPV
4,697,802,948 @ 12.95%
The WACC has been arrived at using the Zero Coupon (Rs)
Yield Curve. The cost of debt for the project is estimated
to be 9.70% (assuming 100 basis points above the rate IRR 24.263%
of return). Payback Period
6.5
The cost of equity for the project is expected to be (in years)
around 16.20%, this has been arrived at using the
market return rate, beta for infrastructure index and the
risk free rate of return.
NPV and IRR
The project shows a positive NPV and IRR indicating
positive returns for investors in such a project. Exhibit
8.1.5 shows the result of the NPV and IRR calculations.
The NPV IRR calculation have been assumed at a
WACC of 12.95% assuming a Debt to Equity ratio 1:1.
This is in line with TAMP guidelines which indicate a
Debt equity structure of 1:1.
As can be seen the project is profitable and has a
positive NPV as well as a high IRR.
Implementation Schedule
The implementation schedule of the project is 18 months
and is to be completed by 2008-09. This indicates that
the project should be started in 2007 1st quarter to meet
the capacity requirements of the future
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
12
8.1 Client Related Investment Projects
8.1.3 330m Extension of current berth
Summary Cash Flow (In Rs Mn) Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10
Revenue (A) - - 1,533 1,927 2,058 2,105 2,164 2,382 2,285 2,349 2,414
Operating Expenses (B) - - 460 578 617 642 668 694 722 751 781
Depreciation (D)
- - 238 238 238 238 238 238 238 238 238
Tax @ 33.66% of Earnings* (E) - - - - - - - - - - -
Fixed Assets (F) 5,308 - - - - - - - - - -
Net Cash flow (A-B-F-E + D) (5,308) - 1,311 1,587 1,679 1,701 1,734 1,926 1,801 1,836 1,871
Summary Cash Flow (In Rs Mn) Year 11 Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Year 18 Year 19 Year 20
Revenue (A) 2,481 2,550 2,621 2,694 2,769 2,846 2,925 3,006 3,090 3,178
Operating Expenses (B) 812 845 879 914 950 988 1,028 1,069 1,112 1,156
Depreciation (D) 238 238 238 238 238 238 238 238 238 634
Tax @ 33.66% of earnings * (E) - 517 537 556 574 592 609 626 643 352
Fixed Assets (F) - - - - - - - - 5,958 -
Net Cash flow (A-B-F-E + D) 1,907 1,426 1,444 1,463 1,483 1,504 1,526 1,549 (4,385) 2,304
Summary Cash Flow (In Rs Mn) Year 21 Year 22 Year 23 Year 24 Year 25 Year 26 Year 27 Year 28 Year 29 Year 30
Revenue (A) 3,242 3,307 3,373 3,440 3,509 3,579 3,651 3,724 3,798 3,874
Operating Expenses (B) 1,203 1,251 1,301 1,353 1,407 1,463 1,522 1,582 1,646 1,712
Depreciation (D) 634 634 634 634 634 634 634 634 634 634
Tax @ 33.66% of earnings * (E) 407 454 495 530 560 587 610 630 647 662
Fixed Assets (F) - - - - - - - - - -
Net Cash flow (A-B-F-E + D) 2,267 2,236 2,212 2,192 2,176 2,164 2,154 2,146 2,140 2,135
* Tax is calculated on earnings post adjustment for depreciation. Depreciation taken for tax is the tax value of depreciation as per
Indian tax laws.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
13
8.1 Client Related Investment Projects
8.1.3 330m Extension of current berth
Sensitivity Analysis
Exhibit 8.1.6 Project NPV and IRR with decrease in
To assess the profitability of a project a sensitivity traffic
analysis should be carried out. The sensitivity analysis
provides insights on effect of changes in the Project NPV
environment on the profitability of projects. An 3,062,240,841 @ 12.95%
(Rs)
additional scenario has been considered by KPMG to
assess the profitability of project. This is as follows:
IRR 20.639%
z Decrease in traffic by 20%/Tariff reduction by
20%: This scenario assumes a 20% lower traffic Payback Period
8.0
potential/ lower tariff and indicates the feasibility (in years)
of the project under such a situation.
Scenario 1: Decrease in traffic by 20%/ Tariff
reduction by 20%
This scenario assesses the profitability of the project
under a reduced traffic/tariff assumption. The traffic
has been reduced by 20% to arrive at NPV and IRR.
As can be seen in Exhibit 8.1.6 the NPV and IRR of
the project is expected to be positive even under the
reduced revenue assumption.
All other assumptions on costs and revenues are the
same as that of the base case.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
14
8.1 Client Related Investment Projects
8.1.3 330m Extension of current berth
Scenario 1: Decrease in traffic by 20%
Summery Cash Flow (In Rs Mn) Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10
Revenue (A) - - 1,226 1,542 1,646 1,684 1,731 1,906 1,828 1,879 1,931
Operating Expenses (B) - - 368 462 494 514 534 556 578 601 625
Depreciation (D)
- - 238 238 238 238 238 238 238 238 238
Tax @ 33.66% of Earnings* (E) - - - - - - - - - - -
Fixed Assets (F) 5,308 - - - - - - - - - -
Net Cash flow (A-B-F-E + D) (5,308) - 1,097 1,317 1,391 1,409 1,435 1,589 1,489 1,516 1,545
Summery Cash Flow (In Rs Mn) Year 11 Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Year 18 Year 19 Year 20
Revenue (A) 1,985 2,040 2,097 2,155 2,215 2,277 2,340 2,405 2,472 2,543
Operating Expenses (B) 650 676 703 731 760 791 822 855 889 925
Depreciation (D) 238 238 238 238 238 238 238 238 238 634
Tax @ 33.66% of Earnings* (E) - 402 419 436 452 467 482 496 510 216
Fixed Assets (F) - - - - - - - - 5,958 -
Net Cash flow (A-B-F-E + D) 1,573 1,200 1,213 1,226 1,241 1,257 1,274 1,292 (4,647) 2,036
Summery Cash Flow (In Rs Mn) Year 21 Year 22 Year 23 Year 24 Year 25 Year 26 Year 27 Year 28 Year 29 Year 30
Revenue (A) 2,593 2,645 2,698 2,752 2,807 2,863 2,921 2,979 3,039 3,099
Operating Expenses (B) 962 1,001 1,041 1,082 1,125 1,170 1,217 1,266 1,317 1,369
Depreciation (D) 634 634 634 634 634 634 634 634 634 634
Tax @ 33.66% of Earnings* (E) 270 316 355 389 419 444 466 485 502 516
Fixed Assets (F) - - - - - - - - - -
Net Cash flow (A-B-F-E + D) 1,996 1,964 1,937 1,915 1,897 1,883 1,871 1,862 1,855 1,849
* Tax is calculated on earnings post adjustment for depreciation. Depreciation taken for tax is the tax value of depreciation as per
Indian tax laws.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
15
8.1 Client Related Investment Projects
8.1.4 Development of 50 Hectares of land for empty depot operations
Summary Coverage
Project to be undertaken Development of 50 Hectares of land for empty depot operations
Year 2008-09
Traffic to be handled at JNPT 4.42 Mn TEUs by JNPT
Need for the project There is a substantial amount of empties traffic at JN Port (around
17.89% of stuffed containers). Apart from this empties are also produced
due to destuffing operations of import cargo at the CFS (around 75% of
import cargo at the CFS is destuffed at the CFS). The current location of
empty yards is shown in Exhibit 8.1.7. The total area for empties available
at these yards is around 74.4 Hectares (data obtained from Port planning
and development department at JNPT).
As the traffic increases this area would prove to be inadequate and will
have to be increased. The availability of land near the port is limited due
to development of SEZs etc. Hence, it is proposed that the port develops
empties yards within the port land. The expected requirement for empties
between 2008-09 and 2012-13 of around 50 Hectares.
Technical Description The generation of empties is shown in Exhibit 8.1.8. The project
envisages development of empties yard within the port. The empties yard
is located close to the CFS developed inside the port to minimize
movement of empties within the port. The additional traffic generated due
to the empties yard can be handled due to the improved efficiency of
SH54 and other projects such as grade separators which are to be
completed by 2008-09.
The location of the proposed empties yard is shown in Exhibit 8.1.9.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
16
YAN
AL
K
TO
KALAMBOLI - Yards at SH-54
JUNCTION - Yards at NH-4B
- Yards at Gavhan Phata-
3 Chirner
MUMBAI
-Yards at Koproli-Khopta Rd.
PANVEL - Yards at NH-17
GavanMJP
Tank
PALASPE
10 12
1
6 0 11 1
9
4
N
5 2
H
3
-4
J.N.P.T. 2
1
1 CHRLE
54
8 2
- 7 3
SH
DIGHODA
5 4
-17
NH - 4B 6 TO
1 5 PO
NH
3 4 RANSAI DAM ON
2 A
4 KHOPTA-KOPROLI ROAD
1 CONNECTING NH - 17
Khopta Bridge
2 CHIRNER
5 1 1. Gavan Phata – ChirnerRoad.
KOPROLI 2. Koproli – Vasheni Sai Road.
3. Gavan Phata – PanvelRoad.
4. Dastan Phata – Dighoda Road.
2 SAI TO GOA 5. Karal Junction – UranRoad.
VASHENI
Exhibit 8.1.7: Layout plan showing roads leading to port & Empty container yards
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
17
Exhibit 8.1.8: Generation of empties
Destuffed Empties
Empties Yards
Direct to port
Exports by Rail
JNPT
Imports by Rail
Summary Coverage
Cost of Development for JNPT The cost of development for the land is expected to be around Rs 185
Crores in 2008-09 on a basis of Rs 3.3 Crores per hectare (CIDCO report
on reserve pricing in 2005-06). This includes the cost of utilities, leveling
and road development etc
Revenues for JNPT Revenues expected by JNPT would be around Rs. 0.50
Crores/hectare/year (based on CIDCO report on reserve pricing for
JNPT). The total revenues expected from the 50 hectares of land would
be Rs. 25 Crores in 2008-09
Cost of development for empty depot The cost of development for the land is expected to be around Rs. 50
Operator Crore on a basis of Rs. 1 crore per hectare (Secondary research on
empty depot costs. Empty depot operators have lesser investment
requirements). This includes the cost of equipment, building, contingency
etc.
Revenue for empty depot Operator Revenues expected by operator would be around Rs. 0.67
Crores/hectare/year (Secondary research on empty operator costs) The
total revenues expected from the 50 hectares of land would be Rs. 33
Crores
Key enablers for the project The successful execution of the project would require development of
land and connectivity to the empty depot area and ensuring optimal
utilisation of space in the yard. In absence of such connectivity, the empty
container yards development may lead to congestion. Hence, the review
of empty container yard development should be done periodically to
ensure that it is line with connectivity at the port and is not causing
congestion.
50 ha represents requirements of empty yards for a three year period between 2008-09 to 2011-12. Keeping in
mind that the action on the plan is likely to begin only after April 2007, the empty yard creation at any point of time
during this three year period may suffice.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
19
Exhibit 8.1.9 : 50 Hectares of empty depot land development
50 Hectares of
Empties yard (2008-
09)
Road
Developments
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
20
8.1 Client Related Investment Projects
8.1.5 Port Based Logistics and FTZ
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
21
Exhibit 8.1.10 : Proposed Port based Logistics/FTZ
Proposed
Evacuation Roads
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
22
8.1 Client Related Investment Projects
8.1.5 Port Based Logistics and FTZ
Investment details
There are 2 sets of investments involved for creation of
the zone. These are investments made by JNPT to
develop the land as well as investments made by the
lessee to carry out operational activities at the zone. Exhibit 8.1.12 : Construction cost per hectare for
Exhibit 8.1.11 lists approximate current costs of Lessee
investment per hectare required to be made by JNPT to
Industrial building per Rs 83.85 million
develop the land. Exhibit 8.1.12 indicates approximate
hectare
current costs of investment per hectare to develop
industrial and storage facilities. Storage and distribution Rs 83.85 million
land per hectare
Cost of construction for the lessee for 200 hectares of
land works out to Rs 1700 cr in 2008-09 (phased over 3
Source: KPMG research, Industry averages
years) Costs of development of same area of land for
JNPT before leasing out work out to Rs 722 cr in 2007-
08 (phased over 3 years) JNPT would need to develop
the land a year before leasing it.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
23
8.1 Client Related Investment Projects
8.1.5 Port Based Logistics and FTZ
Calculation of revenue
Exhibit 8.1.13 : Annual revenues (in millions)
Revenues for the lessee are calculated on the
basis of revenue per hectare of land. The Year Lessee JNPT Year Lessee JNPT
revenue per hectare of land is taken as Rs 24.95 1 0 0 16 9192 1417
million per hectare annually based on industry
research. 2 2198 437 17 9560 1445
Revenues for JNPT are taken on the basis of 3 3935 774 18 9942 1474
lease rentals of Rs 4.8 million per hectare of land 4 5741 1117 19 10340 1504
as arrived at in the CIDCO report on JNPT land
price fixation. The lease revenues have been 5 5971 1140 20 10754 1534
worked out for a period of 30 years.
6 6210 1162 21 11184 1564
It is assumed that it will take JNPT as well as the
7 6458 1186 22 11631 1596
BOT developer a year each to develop and
construct on the land respectively. 8 6717 1209 23 12096 1628
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
24
8.1 Client Related Investment Projects
8.1.5 Port Based Logistics and FTZ
Financial Coverage
For the given project financial coverage is obtained by calculating as well as making suitable assumptions about the
developer’s capital structure.
The debt-equity structure of the lessee s taken as 1:1 in line with TAMP guidelines.
The lessee cost of debt is estimated by assigning a spread over the zero coupon yield curve for Government bonds as
well as taking into account a repayment period.
Here we assume the repayment period as 10 years and taking the ZCYC curve for 2008 and 2013 as of 11th July 2006
we arrive at the cost of debt for a loan taken in 2009-10. Here the cost of debt arrived at 9.79% on taking a risk spread
of 100 bps over the risk free rate of debt.
Using an equity Beta of 1 we arrive at the contractor’s cost of equity. One is the average infrastructure index Beta
between July 2002 and July 2005 in Indian equity markets. Indian market returns over risk free rate have been 6.5%
historically. Using these assumptions the cost of equity is calculated as 16.29%
Cost of capital arrived at for the project is 13.04% for a D/E ratio of 1.
For JNPT the investments are assumed from port internal resources at an opportunity cost of 9% annually.
Phasing of EPZ
After construction of JNPT financial statements and analysis of cash flows it was observed that the investments in the
FTZ are not sustainable in a single year hence they have been phased out over 3 years of 2008-09 till 2010-11.
Simultaneously the revenue stream to the port from leasing begins a year post investment in a given phase,
beginning from 2008-09. EPZ becomes fully operational in the year 2012-13. This phasing is evident in the financial
model and in the description of the project.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
25
8.1 Client Related Investment Projects
8.1.5 Port Based Logistics and FTZ
IRR/NPV of the project for the Lessee Exhibit 8.1.14 : NPV and IRR for the lessee
The project shows a positive NPV and IRR indicating
positive returns for investors in such a project, as seen in Net present value Rs 13, 681 million
exhibit 8.1.14.
The net present value of the project has been calculated Internal rate of return 23.19%
at a WACC of 13.04% assuming a Debt to Equity ratio 1:1.
This is in line with TAMP guidelines which indicate a Debt Payback Period (in years) 9.3 years
equity structure of 1:1.
The IRR could be substantially higher depending on the
exact nature of the industry activity carried out in the
leased land.
Exhibit 8.1.15 : NPV and IRR for JNPT
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
26
8.1 Client Related Investment Projects
8.1.6 Development of the first phase of 4th Terminal
Year of completion – 2010-11
Project – 1) Development of the first phase of 4th Terminal*
2) Development of Rail ICD for the fourth terminal
3) Development of road for the fourth terminal
4) Relocation of BPCL Jetty
General Description and motivation
JNPT would start experiencing shortage of container handling capacity by 2010-11, when traffic expected is 5.92 Mn
TEUs as compared to capacity of 5.59 Mn TEUs. In the years upto 2014-15, this shortfall could increase up to 2.7m
TEUs. As a result, there exists a case to develop a 4th container terminal.
The 4th Terminal is proposed to be setup to overcome the shortfall perceived in 2010-11 and to handle the increase
expected in subsequent years. It is proposed that the terminal would have a quay length of 1000 m and would be
setup at the location of the BPCL Jetty. The current BPCL jetty (300m) would be extended by 700 m. The developer
will extend the current BPCL jetty and relocate BPCL to a new marine terminal. The cost of relocation will be borne
by the developer.
Along with the fourth terminal the developer would also develop the rail ICD for the terminal as well as the road
leading from the port approach road to the terminal. Maps are shown in exhibit 8.1.16,8.1.17 and 8.1.18.
Technical Description
The berth is proposed to be 1000m long. The berth would extend the current BPCL jetty (300m) by 700m and
expand the existing BPCL jetty for container operations. Apart from this the developer would also bear the cost of
relocating BPCL to the new marine terminal. It is proposed that the developer would reclaim around 200 Ha of land
for cargo related operations
The developer would utilize only part of the reclaimed land for its operations while the remaining would be used by
the second phase of the 4th terminal.
The equipment details proposed for the terminal are given in exhibit 8.1.20. The facility is proposed to be equipped
with 12 RMQCs, 43 RTGCs, 6 Reach Stackers and 250 TTs.
The RMQCs would be capable of double moves. Once the fourth terminal becomes operational the port will be able
to maintain double moves proportion at 10% which would further add capacity to the port.
A summary of Environmental Impact Assessment findings for the project is provided in Annexure 1.5.
* As part of the Interim report a number of options for development of 4th terminal were considered. Post discussions
with the port, the option described herein has been used for the financial model
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
27
Exhibit 8.1.16 : Existing state of JNPT's sea side
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
28
Exhibit 8.1.17 Planned fourth terminal
4th Terminal,
created by shifting
BPCL shifted to the new BPCL and
Marine Terminal extending the Jetty
200 Ha of
reclaimed land for
use as yard
Reclaimed
4 Laning of SH54
Reclaimed area
to be used as
Container yard
Road Leading to
the fourth terminal
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
30
8.1 Client Related Investment Projects
8.1.6 Development of the first phase of 4th Terminal
Forecast of additional traffic Exhibit 8.1.19 Traffic Potential - 4th Terminal Phase 1
Traffic forecast for the 1000m berth has been given Year Mn TEUs
alongside. The traffic expected for the fourth terminal is
0.04 Mn TEU going upto 2.4 Mn TEU in the 4th year of 2010-11 0.04
operations as seen in exhibit 8.1.20. 2011-12 0.86
2012-13 1.81
Calculation of Investments
2013-14 2.31
The Investments envisaged for the project are shown in
2014-15 2.4
Exhibit 8.1.21. These investments have been calculated
on the basis of discussions with the port as well as 2015-16 2.4
through secondary research. These include costs for
strengthening of BPCL jetty to support container ships 2016-17 2.4
as well as cranes. 2017-18 2.4
Apart from this the port would also need to develop CFS 2018-19 2.4
and other supporting infrastructure (hinterland etc) for
the expansion. These projects have been identified 2019-20 2.4
separately and should be completed in time to ensure
2020-21 2.4
smooth operations of the terminal.
2021-22 2.4
2039-40 2.4
2040-41 2.4
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
31
8.1 Client Related Investment Projects
8.1.6 Development of the first phase of 4th Terminal
Calculation of Additional Costs Exhibit 8.1.20 Initial investment & Expenditure - 4th
Terminal Phase1 (in rupees Mn)
Operating costs have been assumed as a
percentage of capital costs. Subsequently these Container Berth (700m X 57.5m) 1,969.64
costs have been increased by the rate of Container Berth (Expansion of BPCL) 377.62
inflation every year.
Approach to container Berths 4 No 290X 21m 1,002.93
The equipment has been replaced after 18
years of operation A BOT has been Buildings 40.82
assumed for 30 years. The replaced equipment
Roads and Pavements 831.54
has been depreciated so that residual value at
the end of BOT period is Zero. Electrical works 477.80
Utilities 128.57
Infrastructure projects are eligible for a tax Rail container depot 77.95
holiday for the initial 10years of their operation
under the tax clause 80I. This clause however RMQC X 8 (54m Reach) 2,969.64
would expire in 2010 and therefore tax rebates RMQC X 4 (63m Reach) 1,606.31
for projects have been considered till 2010. The
tax rate has been taken at 33.66%. RTGC X 43 556.25
Reach Stacker X 6 141.73
Tractor Trailer X 250 1,461.62
Total reclamation (200 Ha) 11,101.40
Total Dredging 2,085.27
Sub Total 24,829.1
BPCL Jetty Costs 3,954.6
Common utilities 825.4
New Landing Jetty 744.8
Total 30,353.1
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
32
8.1 Client Related Investment Projects
8.1.6 Development of the first phase of 4th Terminal
Financial Coverage Exhibit 8.1.21 Project NPV and IRR without revenue
The project is proposed be a BOT over a 30 year period. sharing
The project is proposed to be financed through equity and
Project NPV (in
debt keeping the debt: equity ratio of 1:1. 2,800,899,414 @ 13.15%
Rs)
The WACC has been arrived at using the Zero Coupon
Yield Curve. The cost of debt for the project is estimated IRR 14.236%
to be 9.70% (assuming 100 basis points above the risk
Payback Period
free return rate). 22.3
(in years)
The cost of equity for the project is expected to be around
16.20%, this has been arrived at using the market return
rate, beta for infrastructure index and the risk free return
Implementation Schedule
rate.
The implementation schedule of the project is 24 months
NPV and IRR
and is to be completed by 2010-11. This indicates that the
The project shows a positive NPV and IRR indicating project should be started in 2008 1st quarter to meet the
returns for investors in such a project. Exhibit 8.1.22 capacity requirements of the future
shows the result of the NPV and IRR calculations.
The NPV IRR calculation have been assumed at a WACC
of 13.15% assuming a Debt to Equity ratio 1:1. This is in
line with TAMP guidelines which indicate a Debt equity
structure of 1:1.
As can be seen the project is profitable and has a positive
NPV however the project has a low IRR.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
33
8.1 Client Related Investment Projects
8.1.6 Development of the first phase of 4th Terminal
In Rs Mn Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10
Revenue (A) - - - 827 3,016 5,736 7,715 7,509 7,796 8,093 8,414
Operating Expenses (B) - - - 165 603 1,147 1,543 1,502 1,559 1,619 1,683
Depreciation (D)
- - - 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200
Tax @ 33.66% of Earnings* (E) - - - - - 654 1,289 1,323 1,479 1,628 1,776
Fixed Assets (F) 23,541 - 6,813 - - - - - - - -
Net Cash flow (A-B-F-E + D) (23,541) - (6,813) 1,862 3,613 5,135 6,084 5,885 5,958 6,046 6,155
Year 11 Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Year 18 Year 19 Year 20
Revenue (A) 8,749 9,099 9,463 9,844 10,240 10,655 11,087 11,539 12,048 12,531
Operating Expenses (B) 1,750 1,820 1,893 1,969 2,048 2,131 2,217 2,308 2,410 2,506
Depreciation (D) 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200
Tax @ 33.66% of Earnings* (E) 1,921 2,063 2,204 2,344 2,485 2,626 2,769 2,914 3,072 3,220
Fixed Assets (F) - - - - - - - - - 13,462
Net Cash flow (A-B-F-E + D) 6,279 6,416 6,567 6,731 6,908 7,098 7,301 7,518 7,767 (5,458)
Year 21 Year 22 Year 23 Year 24 Year 25 Year 26 Year 27 Year 28 Year 29 Year 30
Revenue (A) 12,935 13,354 13,787 14,236 14,700 15,180 15,678 16,193 16,726 17,279
Operating Expenses (B) 2,587 2,671 2,757 2,847 2,940 3,036 3,136 3,239 3,345 3,456
Depreciation (D) 2,221 2,221 2,221 2,221 2,221 2,221 2,221 2,221 2,221 2,221
Tax @ 33.66% of Earnings* (E) 2,667 2,897 3,113 3,319 3,517 3,708 3,896 4,080 4,263 4,445
Fixed Assets (F) - - - - - - - - - -
Net Cash flow (A-B-F-E + D) 9,902 10,008 10,138 10,291 10,464 10,657 10,867 11,095 11,339 11,599
* Tax is calculated on earnings post adjustment for depreciation. Depreciation taken for tax is the tax value of depreciation as per
Indian tax laws.
Note: Under reduced traffic the terminal will make a loss of 665 Mn in year 3 (revenue-expenses-depreciation) this loss is offset
against the tax liability in year 4 and 5.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
34
8.1 Client Related Investment Projects
8.1.6 Development of the first phase of 4th Terminal
Sensitivity Analysis
Exhibit 8.1.22 : Project NPV and IRR with decreased
To assess the profitability of a project a sensitivity analysis traffic
should be carried out. The sensitivity analysis provides
insights on effect of changes in the environment on the
profitability of projects. An additional scenario has been Project NPV
116,883,579 @ 13.15%
considered by KPMG to assess the profitability of project. (Rs)
This is as follows:
z Decrease in traffic by 20%/ Tariff reduction by 20%: IRR 13.196%
This scenario assumes a 20% lower traffic potential/
lower tariff and indicates the feasibility of the project
under such a situation. Payback Period
29.5
(in years)
Scenario 1: Decrease in traffic by 20%/ Tariff
reduction by 20%
This scenario assesses the profitability of the project
under a reduced traffic/tariff assumption. The traffic has
been reduced by 20% to arrive at NPV and IRR.
As can be seen in Exhibit 8.1.22 the NPV and IRR of the
project is expected to be positive even under the reduced
traffic/tariff assumption.
All other assumptions on costs and revenues are the
same as that of the base case.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
35
8.1 Client Related Investment Projects
8.1.6 Development of the first phase of 4th Terminal
Scenario 1: Decrease by 20% in traffic
Summery Cash Flow (In Rs Mn) Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10
Revenue (A) - - - 668 2,450 4,687 6,341 6,208 6,483 6,770 7,083
Operating Expenses (B) - - - 134 490 937 1,268 1,242 1,297 1,354 1,417
Depreciation (D)
- - - 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200
Tax @ 33.66% of Earnings* (E) - - - - - - 607 972 1,125 1,272 1,418
Fixed Assets (F) 23,541 - 6,813 - - - - - - - -
Net Cash flow (A-B-F-E + D) (23,541) - (6,813) 1,735 3,160 4,950 5,667 5,195 5,262 5,344 5,449
Summery Cash Flow (In Rs Mn) Year 11 Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Year 18 Year 19 Year 20
Revenue (A) 7,413 7,758 8,121 8,502 8,902 9,323 9,765 10,230 10,760 11,176
Operating Expenses (B) 1,483 1,552 1,624 1,700 1,780 1,865 1,953 2,046 2,152 2,235
Depreciation (D) 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200 1,200
Tax @ 33.66% of Earnings* (E) 1,561 1,702 1,843 1,983 2,124 2,267 2,413 2,562 2,725 2,856
Fixed Assets (F) - - - - - - - - - 13,462
Net Cash flow (A-B-F-E + D) 5,569 5,704 5,854 6,019 6,198 6,391 6,599 6,823 7,083 (6,177)
Summery Cash Flow (In Rs Mn) Year 21 Year 22 Year 23 Year 24 Year 25 Year 26 Year 27 Year 28 Year 29 Year 30
Revenue (A) 11,613 12,068 12,543 13,038 13,554 14,092 14,654 15,240 15,851 16,490
Operating Expenses (B) 2,323 2,414 2,509 2,608 2,711 2,818 2,931 3,048 3,170 3,298
Depreciation (D) 2,221 2,221 2,221 2,221 2,221 2,221 2,221 2,221 2,221 2,221
Tax @ 33.66% of Earnings* (E) 2,311 2,550 2,778 2,996 3,208 3,415 3,620 3,823 4,027 4,233
Fixed Assets (F) - - - - - - - - - -
Net Cash flow (A-B-F-E + D) 9,200 9,325 9,478 9,655 9,856 10,080 10,324 10,589 10,875 11,180
* Tax is calculated on earnings post adjustment for depreciation. Depreciation taken for tax is the tax value of depreciation as per
Indian tax laws.
Note: Under reduced traffic the terminal will make a loss of 665 Mn in year 3 (revenue-expenses-depreciation) this loss is offset
against the tax liability in year 4 and 5.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
36
8.1 Client Related Investment Projects
8.1.7 Marine Chemical terminal – phase 1
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
37
Exhibit 8.1.23 Map of Marine Chemical terminal – 1st phase (300 m berth)
d
cate tty
lo e
Re CL J
B P
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
38
8.1 Client Related Investment Projects
8.1.7 Marine Chemical terminal – phase 1
2016-17 4939
Investment details
2017-18 5248
The investments shown in exhibit 8.1.25 are primarily :
2018-19 5573
• Construction of jetty with associated piling.
2019-20 5915
• Purchase and installation of liquid equipment
including a 16 inch marine loading arms and three 2020-21 5915
12 inch arms.
2021-22 5915
• Dredging costs apportioned to berth of the Marine
2022-23 5915
chemical terminal (MCT) from area dredged for 4th
container terminal, BPCL jetty as well as 1st phase 2023-24 5915
of MCT.
2024-25 5915
2025-26 5915
2026-27 5915
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
39
8.1 Client Related Investment Projects
8.1.7 Marine Chemical terminal – phase 1
Calculation of revenue -
Exhibit 8.1.25 : Investment Details (in Rs
Revenues are calculated using TAMP guidelines on liquid
million)
cargo. The average wharfage charges are taken at Rs 65
per ton of liquid cargo. The revenue per ton is expected to Investment value in
be constant for the till 2013-14 beyond which it is Year 2010-11
assumed to increase by a marginal 2% per annum. The
marginal growth of revenue/ton has been taken in light of Civil Works &
the recent competitive pressures and in discussions with Buildings
the finance department at JNPT.
Jetty Cost (300m,1
Calculation of additional cost – side berthing) 382.71
Based on discussion with JNPT officials it was felt that
Buildings 16.34
operating expenses to revenue ratio for the first year of
liquid cargo operations could be assumed to be 15%. Plant and Machinery
Operating expenses were then grown at 4% annually to
account for inflation. Liquid Bulk Handling
equipment (New
A BOT has been assumed for 30 years. The equipment
Berth) 141.77
has been replaced in year 20 of operations. New marine
loading arms are put in at an inflation-adjusted cost of Rs Channel related
298 million in 2029-30. costs
Depreciation cycle for replaced equipment is kept at 11
Dredging 342.5
years bringing value of equipment on books to zero at end
of BOT period. This is in line with current BOT contracts in
place at JNPT. Dredging carried out by BOT operator is
depreciated over the period of the contract. Total 883.37
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
40
8.1 Client Related Investment Projects
8.1.7 Marine Chemical terminal – phase 1
Financial Coverage – Exhibit 8.1.26 : NPV and IRR for BOT operator
For the given project financial coverage is obtained by without revenue sharing
calculating as well as making suitable assumptions
about the developer’s capital structure. The debt- Net present value Rs 556 million
equity structure of the BOT contractor is taken as 1:1
in line with TAMP guidelines.
The Developer's cost of debt is estimated by assigning
Internal rate of return 19.64 %
a spread over the zero coupon yield curve for
Government bonds as well as taking into account a
repayment period. Here we assume the repayment
period as 10 years and taking the ZCYC curve for Payback period 10.4 years
2009 and 2014 as of 11th July 2006 we arrive at the
cost of debt for a loan taken in 2009-10. Here the cost
of debt arrived at 9.91% on taking a risk spread of 100
bps over the risk free rate of debt. The NPV IRR calculation have been assumed at a
Using an equity Beta of 1 we arrive at the Developer's WACC of 13.19% assuming a Debt to Equity ratio 1:1.
cost of equity. One is the average infrastructure index This is in line with TAMP guidelines which indicate a
Beta between July 2002 and July 2005 in Indian equity Debt equity structure of 1:1.
markets. Indian market returns over risk free rate have
been 6.5% historically. Using these assumptions the This NPV is also an indication of the maximum
cost of equity is calculated as 16.41%. Cost of capital amount that a developer can pay as upfront fee for the
arrived at for the project is 13.17% for a D/E ratio of project under the current assumptions.
1:1.
Implementation schedule –
IRR/NPV of the project – The implementation schedule for this project is
The project shows a positive NPV and IRR indicating contingent on the relocation of BPCL jetty and the
positive returns for investors in such a project. Exhibit associated shifting of pipeline. The period for jetty
8.1.26 shows the result of the NPV and IRR construction and allied activities would be 12 months.
calculations.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
41
8.1 Client Related Investment Projects
8.1.7 Marine Chemical terminal – phase 1
Summery Cash Flow (In Rs Mn) Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10
Revenue (A) 0 0 148 184 201 223 314 341 369 400 433
Operating Expenses (B) 0 0 22 23 24 25 26 27 28 29 30
Depreciation (D)
0 0 33 33 33 33 33 33 33 33 33
Tax @ 33.66% of earnings (E) 0 0 41 53 59 66 96 105 114 124 135
Fixed Assets (F) 883 0 0 0 0 0 0 0 0 0 0
Net Cash flow (A-B-F-E + D) (883) 0 117 141 151 165 224 241 260 279 300
Summery Cash Flow (In Rs Mn) Year 11 Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Year 18 Year 19 Year 20
Revenue (A) 442 450 459 469 478 488 497 507 517 528
Operating Expenses (B) 32 33 34 36 37 38 40 42 43 45
Depreciation (D) 33 33 33 33 33 33 33 33 33 52
Tax @ 33.66% of revenues (E) 138 140 143 146 148 151 154 157 159 162
Fixed Assets (F) 0 0 0 0 0 0 0 0 0 299
Net Cash flow (A-B-F-E + D) 305 310 315 320 325 331 336 342 347 74
Summery Cash Flow (In Rs Mn) Year 21 Year 22 Year 23 Year 24 Year 25 Year 26 Year 27 Year 28 Year 29 Year 30
Revenue (A) 538 549 560 571 583 594 606 618 631 643
Operating Expenses (B) 47 49 51 53 55 57 59 62 64 67
Depreciation (D) 52 52 52 52 52 52 52 52 52 52
Tax @ 33.66% of revenues (E) 165 168 171 175 178 181 184 187 191 194
Fixed Assets (F) 0 0 0 0 0 0 0 0 0 0
Net Cash flow (A-B-F-E + D) 378 384 390 396 402 409 415 421 428 435
* Tax is calculated on earnings post adjustment for depreciation. Depreciation taken for tax is the tax value of depreciation as per
Indian tax laws.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
42
8.1 Client Related Investment Projects
8.1.7 Marine Chemical terminal – phase 1
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
43
8.1 Client Related Investment Projects
8.1.7 Marine Chemical terminal – phase 1
Summery Cash Flow (In Rs Mn) Year 11 Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Year 18 Year 19 Year 20
Revenue (A) 353 360 368 375 382 390 398 406 414 422
Operating Expenses (B) 32 33 34 36 37 38 40 42 43 45
Depreciation (D) 33 33 33 33 33 33 33 33 33 52
Tax @ 33.66% of revenues (E) 108 110 112 114 116 118 120 122 125 127
Fixed Assets (F) 0 0 0 0 0 0 0 0 0 299
Net Cash flow (A-B-F-E + D) 246 250 254 258 262 266 270 274 279 4
Summery Cash Flow (In Rs Mn) Year 21 Year 22 Year 23 Year 24 Year 25 Year 26 Year 27 Year 28 Year 29 Year 30
Revenue (A) 431 439 448 457 466 476 485 495 505 515
Operating Expenses (B) 47 49 51 53 55 57 59 62 64 67
Depreciation (D) 52 52 52 52 52 52 52 52 52 52
Tax @ 33.66% of revenues (E) 129 131 134 136 138 141 143 146 148 151
Fixed Assets (F) 0 0 0 0 0 0 0 0 0 0
Net Cash flow (A-B-F-E + D) 307 311 316 320 325 330 334 339 344 349
* Tax is calculated on earnings post adjustment for depreciation. Depreciation taken for tax is the tax value of depreciation as per
Indian tax laws.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
44
8.1 Client Related Investment Projects
8.1.8 Development of 40 Hectares of land for empty depot operations
Summary Coverage
Project to be undertaken Development of 40 Hectares of land for empty depot operations
Year of completion 2012-13
Traffic to be handled in year of completion 7.67 Mn TEUs by JNPT
Need for the project There is a substantial amount of empties traffic at JN Port (around
17.89% of stuffed containers). Apart from this, empties are also produced
due to destuffing operations of import cargo at the CFS (around 75% of
import cargo at the CFS is destuffed at the CFS). The current location of
empty yards is shown in Exhibit 8.1.28. The total area for empties
available at these yards is around 74.4 Hectares (data obtained from Port
planning and development department at JNPT). Apart from this JNPT
would also have 50 hectares of empties yard inside the port land.
(developed in 2008-09).
As the traffic increases and capacity is expanded through setup of new
terminals (4th terminal phase 1) this area would prove to be inadequate
and will have to be increased. The availability of land near the port is
limited due to development of SEZs etc. Hence it is proposed that the port
develop empties yards within the port land.
Technical Description The generation of empties is shown in Exhibit 8.1.29. The project
envisages development of empties yard within the port. The empties yard
is located close to the CFS developed inside the port to minimize
movement of empties within the port. The additional traffic generated due
to the empties yard can be handled due to the improved efficiency of
SH54 and other projects such as NH4B six laning.
The proposed location of the empties yard is shown in Exhibit 8.1.30.This
area can be given to one of more CFS operators. An analysis of cost and
revenues on an aggregate basis is provided.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
45
YAN
AL
K
TO
KALAMBOLI - Yards at SH-54
JUNCTION - Yards at NH-4B
- Yards at Gavhan Phata-
3 Chirner
MUMBAI
-Yards at Koproli-Khopta Rd.
PANVEL - Yards at NH-17
GavanMJP
Tank
PALASPE
10 12
1
6 0 11 1
9
4
N
5 2
H
3
-4
J.N.P.T. 2
1
1 CHRLE
54
8 2
- 7 3
SH
DIGHODA
5 4
-17
NH - 4B 6 TO
1 5 PO
NH
3 4 RANSAI DAM ON
2 A
4 KHOPTA-KOPROLI ROAD
1 CONNECTING NH - 17
Khopta Bridge
2 CHIRNER
5 1 1. Gavan Phata – ChirnerRoad.
KOPROLI 2. Koproli – Vasheni Sai Road.
3. Gavan Phata – PanvelRoad.
4. Dastan Phata – Dighoda Road.
2 SAI TO GOA 5. Karal Junction – UranRoad.
VASHENI
Exhibit 8.1.28: Layout plan showing roads leading to port & Empty container yards
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
46
Exhibit 8.1.29: Generation of empties
Destuffed Empties
Empties Yards
Direct to port
Exports by Rail
JNPT
Imports by Rail
Summary Coverage
Cost of Development for JNPT The cost of development for the land is expected to be around Rs.
173Crore in 2012-13 on a basis of Rs. 3.3 Crore per hectare (CIDCO
report on reserve pricing in 2005-06). This includes the cost of utilities,
levelling etc
Revenues for JNPT Revenues expected by JNPT would be around Rs. 25 Crore in 2013-14
(based on CIDCO report on lease rentals for JNPT).
Cost of development for empty depot The cost of development for the land is expected to be around Rs. 54
Operator Crore on a basis of Rs. 1.36 crore per hectare (Secondary research on
empty depot costs in 2005-06 Empty yard operators have lesser
investment requirements). This includes the cost of equipment, building,
contingency etc.
Revenue for empty depot Operator Revenues expected by operator would be around Rs. 0.75
Crores/hectare/year (Secondary research on empty depot costs) The total
revenues expected from the 40 hectares of land would be Rs. 30 Crores
Key enablers for the project The successful execution of the project would require development of
land and connectivity to the empty depot area and ensuring optimal
utilisation of space in the yard. In absence of such connectivity, the empty
container yards development may lead to congestion. Hence, the review
of empty container yard development should be done periodically to
ensure that it is line with connectivity at the port and is not causing
congestion.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
48
Exhibit 8.1.30: 40 Hectares of empty depot land development
40 Hectares of
Empties yard (2012-
13)
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
49
8.1 Client Related Investment Projects
8.1.9 Development of 56 Hectares of Land for CFS Operations
Summary Coverage
Project to be undertaken Development of 56 Hectares of CFS Land
Year of completion of the project 2012-13
Traffic to be handled 7.67 Mn TEUs by JNPT
Need for the project Due to the increase in traffic and addition of capacity (4th terminal) JNPT
would face the need for an increase in supporting infrastructure. The
availability of land around JNPT is expected to be limited in the future due
to the development of NMMSEZ, therefore it is proposed that 70% of the
CFS capacity requirement for JNPT would be developed inside the port
land. The remaining 30% is expected to be developed by private players
outside the port.
Technical Description The availability of land around the port is becoming a constraint in light of
the SEZ setup around the port. It is proposed that 70% of the additional
CFS requirements should be developed within the port boundaries. The
remaining capacity is expected to be satisfied by CFS setups outside the
port. The port would require additional 56 Hectares of CFS area between
2012 and 2015.The area earmarked for the CFS operation is shown in
Exhibit 8.1.31.
The CFS area would be developed in two locations, 20 hectare would be
developed near SH54 while 36 hectares would be developed near the
township. The increase in traffic would be managed by the development
of the Khopta Bridge road in the same year (identified project). Apart from
this Six laning of NH4B and addition of EPZ/FTZ road will also aid in
evacuation of traffic.
JNPT would develop the land and lease it to CFS operator who would
develop and operate the facility. Revenues for JNPT would comprise
primarily of lease rentals obtained from the operators. This area can be
given to one or different CFS. An analysis of cost and revenues on an
aggregate basis is provided.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
50
8.1 Client Related Investment Projects
8.1.9 Development of 56 Hectares of Land for CFS Operations
Summary Coverage
Cost of Development for JNPT The cost of development for the land is expected to be around 243 Crore
Rupee in 2013-14 on a basis of 3.3 Crore per hectare (CIDCO report on
reserve pricing ; Base Year- 2005-06). This includes the cost of utilities,
leveling etc
Revenues for JNPT Revenues expected by JNPT would be around Rs. 35.27 Crores/year in
2013-14 (based on CIDCO report on reserve pricing for JNPT; Base
Year- 2005-06).
Cost of development for CFS Operator The cost of development for the land is expected to be around Rs. 225
Crore Rupee on a basis of 4.02 Crore per hectare (Secondary research
on CFS costs; Base Year- 2005-06). This includes the cost of equipment,
building, electrical contingency etc.
Revenue for CFS Operator Revenues expected by operator would be around Rs. 1.3
Crores/hectare/year (Secondary research on CFS costs; Base Year-
2006-07) The total revenues expected from the 56 hectares of land would
be Rs. 74 Crores
Key enablers for the project The successful execution of the project would require development of
land and connectivity to the CFS area. In absence of such connectivity,
the CFS development may lead to congestion. Hence, the review of CFS
development should be done periodically to ensure that it is line with
connectivity at the port and is not causing congestion.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
51
Exhibit 8.1.31: 56 Hectares of CFS land development
56 Hectares of CFS
land (2012-13)
(2013-14)
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
52
8.1 Client Related Investment Projects
8.1.10 Development of the Second phase of 4th Terminal
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
53
Exhibit 8.1.32 Existing state of JNPT's sea side
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
54
Exhibit 8.1.33 : Planned fourth terminal Phase 2
o
e Tw
as
l Ph
mina
r
th Te
4
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
55
4th Terminal, phase 2 Exhibit 8.1.34 Fourth terminal phase two and supporting infrastructure
Reclaimed area
to be used as
Container yard
Addition of rail
terminal
Road Leading to
the fourth terminal
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
56
8.1 Client Related Investment Projects
8.1.10 Development of the Second phase of 4th Terminal
RTGC 5,012.48
Total 20,008.82
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
58
8.1 Client Related Investment Projects
8.1.10 Development of the Second phase of 4th Terminal
Financial Coverage Exhibit 8.1.37 Project NPV and IRR without revenue
The project is proposed be a BOT over a 30 year period. share
The project is proposed to be financed through equity and
Project NPV (In
debt keeping the debt: equity ratio of 1:1. 9,145,856,338 @ 13.27%
Rs)
The WACC has been arrived at using the Zero Coupon
Yield Curve. The cost of debt for the project is estimated IRR 20.51%
to be 10.02% (assuming 100 basis points above the risk
Payback Period
free rate of return). 9.6
(in years)
The cost of equity for the project is expected to be around
16.52%, this has been arrived at using the market return
rate, beta for infrastructure index and the risk rate of
return.
NPV and IRR
The project shows a positive NPV and IRR indicating
returns for investors in such a project. Exhibit 8.1.48
shows the result of the NPV and IRR calculations.
The NPV IRR calculation have been assumed at a WACC
of 13.27% assuming a Debt to Equity ratio 1:1. This is in
line with TAMP guidelines which indicate a Debt equity
structure of 1:1.
As can be seen the project is highly profitable and has a
positive NPV as well as a high IRR.
Implementation Schedule
The implementation schedule of the project is 24 months
and is to be completed by 2014-15. This indicates that the
project should be started in 2012 1st quarter to meet the
capacity requirements of the future
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
59
8.1 Client Related Investment Projects
8.1.10 Development of the Second phase of 4th Terminal
In Rs Mn Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10
Revenue (A) - - - 4,618 6,773 6,961 7,154 7,353 7,558 7,768 7,984
Operating Expenses (B) - - - 1,385 2,032 2,088 2,151 2,215 2,282 2,350 2,421
Depreciation (D) - - - 980 980 980 980 980 980 980 980
Tax @ 33.66% of earnings * (E)
- - - 189 821 971 1,107 1,230 1,344 1,450 1,549
Fixed Assets (F) 6,631 - 13,379 - - - - - - - -
Net Cash flow (A-B-F-E + D) (6,631) - (13,379) 4,023 4,900 4,881 4,877 4,888 4,911 4,947 4,994
Year 11 Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Year 18 Year 19 Year 20
Revenue (A) 8,206 8,434 8,669 8,910 9,164 9,348 9,535 9,725 9,920 10,118
Operating Expenses (B) 2,494 2,568 2,645 2,725 2,806 2,891 2,977 3,067 3,159 3,253
Depreciation (D) 980 980 980 980 980 980 980 980 980 980
Tax @ 33.66% of earnings * (E) 1,643 1,732 1,817 1,899 1,981 2,035 2,087 2,136 2,184 2,231
Fixed Assets (F) - - - - - - - - - 26,399
Net Cash flow (A-B-F-E + D) 5,050 5,114 5,187 5,267 5,357 5,402 5,451 5,502 5,557 (20,785)
Year 21 Year 22 Year 23 Year 24 Year 25 Year 26 Year 27 Year 28 Year 29 Year 30
Revenue (A) 10,321 10,527 10,738 10,952 11,171 11,395 11,623 11,855 12,092 12,334
Operating Expenses (B) 3,351 3,452 3,555 3,662 3,772 3,885 4,001 4,121 4,245 4,372
Depreciation (D) 2,947 2,947 2,947 2,947 2,947 2,947 2,947 2,947 2,947 2,947
Tax @ 33.66% of earnings * (E) 944 1,188 1,402 1,589 1,754 1,901 2,031 2,148 2,254 2,350
Fixed Assets (F) - - - - - - - - - -
Net Cash flow (A-B-F-E + D) 8,973 8,834 8,728 8,648 8,592 8,556 8,537 8,532 8,540 8,559
* Tax is calculated on earnings post adjustment for depreciation. Depreciation taken for tax is the tax value of depreciation as per
Indian tax laws.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
60
8.1 Client Related Investment Projects
8.1.10 Development of the Second phase of 4th Terminal
Sensitivity Analysis
Exhibit 8.1.38 Project NPV and IRR with decreased
To assess the profitability of a project a sensitivity
traffic
analysis should be carried out. The sensitivity
analysis provides insights on effect of changes in the
environment on the profitability of projects. An Project NPV
additional scenario has been considered by KPMG to 5,566,991,002 @ 13.27%
(Rs)
assess the profitability of project. This is as follows:
z Decrease in traffic by 20%/ Tariff reduction by
IRR 17.88%
20%: This scenario assumes a 20% lower traffic
potential/ lower tariff and indicates the feasibility
of the project under such a situation Payback Period
11.8
Scenario 1: Decrease in traffic by 20% / Tariff (in years)
reduction by 20%
This scenario checks the profitability of the project
under a reduced traffic/tariff scenario. The traffic has
been reduced by 20% to arrive at NPV and IRR.
As can be seen in Exhibit 8.1.38 the NPV and IRR of
the project is expected to be positive even under the
reduced revenue assumption. This indicates that the
project is profitable and would maintain its profitability
even if traffic gets effected by around 20%.
All other assumptions on costs and revenues are the
same as that of the base case.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
61
8.1 Client Related Investment Projects
8.1.10 Development of the Second phase of 4th Terminal
Scenario 1: Decrease by 20% in traffic
In Rs Mn Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10
Revenue (A) - - - 3,694 5,418 5,569 5,723 5,883 6,046 6,214 6,387
Operating Expenses (B) - - - 1,108 1,625 1,671 1,721 1,772 1,826 1,880 1,937
Depreciation (D)
- - - 980 980 980 980 980 980 980 980
Tax @ 33.66% of earnings * (E) - - - - 502 643 770 884 989 1,085 1,175
Fixed Assets (F) 6,631 - 13,379 - - - - - - - -
Net Cash flow (A-B-F-E + D) (6,631) - (13,379) 3,566 4,271 4,235 4,213 4,206 4,212 4,229 4,256
Year 11 Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Year 18 Year 19 Year 20
Revenue (A) 6,565 6,747 6,935 7,128 7,332 7,478 7,628 7,780 7,936 8,095
Operating Expenses (B) 1,995 2,055 2,116 2,180 2,245 2,313 2,382 2,453 2,527 2,603
Depreciation (D) 980 980 980 980 980 980 980 980 980 980
Tax @ 33.66% of earnings * (E) 1,258 1,337 1,411 1,483 1,553 1,600 1,645 1,688 1,729 1,769
Fixed Assets (F) - - - - - - - - - 26,399
Net Cash flow (A-B-F-E + D) 4,292 4,336 4,388 4,446 4,514 4,545 4,581 4,619 4,660 (21,696)
Year 21 Year 22 Year 23 Year 24 Year 25 Year 26 Year 27 Year 28 Year 29 Year 30
Revenue (A) 8,257 8,422 8,590 8,762 8,937 9,116 9,298 9,484 9,674 9,867
Operating Expenses (B) 2,681 2,761 2,844 2,929 3,017 3,108 3,201 3,297 3,396 3,498
Depreciation (D) 2,947 2,947 2,947 2,947 2,947 2,947 2,947 2,947 2,947 2,947
Tax @ 33.66% of earnings * (E) 475 712 918 1,098 1,256 1,395 1,518 1,628 1,726 1,814
Fixed Assets (F) - - - - - - - - - -
Net Cash flow (A-B-F-E + D) 8,048 7,896 7,775 7,681 7,611 7,560 7,526 7,506 7,499 7,503
* Tax is calculated on earnings post adjustment for depreciation. Depreciation taken for tax is the tax value of depreciation as per
Indian tax laws.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
62
8.1 Client Related Investment Projects
8.1.11 Development of 49 Hectares of Land for CFS Operations
Summary Coverage
Project to be undertaken Development of 49 Hectares of CFS Land
Year of completion of project 2015-16
Traffic to be handled in year of completion 11 Mn TEUs by JNPT in 2015-16
Need for the project Due to the increase in traffic and addition of capacity (4th terminal phase
two) JNPT would face the need for an increase in supporting
infrastructure. The availability of land around JNPT is expected to be
limited in the future due to the development of NMMSEZ, therefore it is
proposed that 70% of the CFS capacity requirement for JNPT would be
developed inside the port land. The remaining 30% is expected to be
developed by private players outside the port.
Technical Description The availability of land around the port is becoming a constraint in light of
the SEZ setup around the port. It is proposed that 70% of the additional
CFS requirements should be developed within the port boundaries. The
remaining capacity is expected to be satisfied by CFS setups outside the
port. It is expected that the port would require additional 49 hectares of
CFS land between 2015-16 and 2019-20. The area earmarked for the
CFS operation is shown in Exhibit 8.1.39
The CFS area would be developed in two locations, 25 hectare would be
developed near the township while 24 Hectares would be developed near
the EPZ. The increase in traffic would be managed by the development of
the Khopta Bridge road in the same year (identified project). Apart from
this an additional road connecting the EPZ/FTZ to Aamra link road would
be created (project in 2017-18).
JNPT would develop the land and lease it to CFS operator who would
develop and operate the facility. Revenues for JNPT would comprise
primarily of lease rentals obtained from the operators. This area can be
given to one or different CFS. An analysis of cost and revenues on an
aggregate basis is provided.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
63
8.1 Client Related Investment Projects
8.1.11 Development of 49 Hectares of Land for CFS Operations
Summary Coverage
Cost of Development for JNPT The cost of development for the land is expected to be around Rs. 239
Crore in 2015-16 on a basis of Rs 3.3 Crore per hectare (CIDCO report
on reserve pricing ; Base Year- 2005-06). This includes the cost of
utilities, levelling etc
Revenues for JNPT Revenues expected by JNPT would be around Rs. 34.81 Crores /year in
2015-16 (based on CIDCO report on reserve pricing for JNPT; Base
Year- 2005-06).
Cost of development for CFS Operator The cost of development for the land is expected to be around Rs 213
Crore on a basis of Rs 4.35 Crore per hectare (Secondary research on
CFS costs; Base Year- 2005-06). This includes the cost of equipment,
building, electrical contingency etc.
Revenue for CFS Operator Revenues expected by operator would be around Rs 1.42
Crores/hectare/year (Secondary research on CFS costs; Base Year-
2006-07) The total revenues expected from the 49 hectares of land would
be Rs 69 Crores
Key enablers for the project The successful execution of the project would require development of
land and connectivity to the CFS area. In absence of such connectivity,
the CFS development may lead to congestion. Hence, the review of CFS
development should be done periodically to ensure that it is line with
connectivity at the port and is not causing congestion.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
64
Exhibit 8.1.39: 49 Hectares of CFS land development
56 Hectares of CFS
49
land (2015-16)
(2013-14)
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
65
8.1 Client Related Investment Projects
8.1.12 Development of 28 Hectares of land for empty depot operations
Summary Coverage
Project to be undertaken Development of 28 Hectares of land for empty depot operations
Year of completion of project 2015-16
Traffic to be handled in year of completion 11 Mn TEUs by JNPT by 2015-16
Need for the project There is a substantial amount of empties traffic at JN Port (around
17.89% of stuffed containers) apart from this empties are also produced
due to destuffing operations of import cargo at the CFS (around 75% of
import cargo at the CFS is destuffed at the CFS). The current location of
empty yards is shown in Exhibit 8.1.40. The total area for empties
available at these yards is around 74.4 Hectares (data obtained from Port
planning and Development Division at JNPT). Apart from this JNPT
would also have 90 hectares of empties yard inside the port (developed in
2008-09 and 2012-13).
As the traffic increases and capacity is expanded through setup of new
terminals (4th terminal phase 2) this area would prove to be inadequate
and will have to be increased. The availability of land near the port is
limited due to development of SEZs etc. Hence it is proposed that the port
develops empties yards within the port.
Technical Description The generation of empties is shown in Exhibit 8.1.41. The project
envisages development of empties yard within the port. The empties yard
is located close to the CFS developed inside the port to minimize
movement of empties within the port. The additional traffic generated due
to the empties yard can be handled due to the improved efficiency of
SH54 and other projects such as NH4B six laning.
The location of the empties yard is shown in Exhibit 8.1.42.This area can
be given to one or different operator. An analysis of cost and revenues on
an aggregate basis is provided.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
66
YAN
AL
K
TO
KALAMBOLI - Yards at SH-54
JUNCTION - Yards at NH-4B
- Yards at Gavhan Phata-
3 Chirner
MUMBAI
-Yards at Koproli-Khopta Rd.
PANVEL - Yards at NH-17
GavanMJP
Tank
PALASPE
10 12
1
6 0 11 1
9
4
N
5 2
H
3
-4
J.N.P.T. 2
1
1 CHRLE
54
8 2
- 7 3
SH
DIGHODA
5 4
-17
NH - 4B 6 TO
1 5 PO
NH
3 4 RANSAI DAM ON
2 A
4 KHOPTA-KOPROLI ROAD
1 CONNECTING NH - 17
Khopta Bridge
2 CHIRNER
5 1 1. Gavan Phata – ChirnerRoad.
KOPROLI 2. Koproli – Vasheni Sai Road.
3. Gavan Phata – PanvelRoad.
4. Dastan Phata – Dighoda Road.
2 SAI TO GOA 5. Karal Junction – UranRoad.
VASHENI
Exhibit 8.1.40: Layout plan showing roads leading to port & Empty container yards
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
67
Exhibit 8.1.41: Generation of empties
Destuffed Empties
Empties Yards
Direct to port
Exports by Rail
JNPT
Imports by Rail
Summary Coverage
Cost of Development for JNPT The cost of development for the land is expected to be around Rs. 136
Crore in 2015-16 on a basis of Rs. 3.3 Crore per hectare (CIDCO report
on reserve pricing in 2005-06). This includes the cost of utilities, levelling
etc
Revenues for JNPT Revenues expected by JNPT would be around Rs. 19.9 Crores /year
(based on CIDCO report on reserve pricing for JNPT).
Cost of development for Empty Operator The cost of development for the land is expected to be around Rs 43
Crore (Secondary research on empty costs; Base Year- 2005-06). This
includes the cost of equipment, building, electrical contingency etc.
Revenue for empty depot Operator Revenues expected by operator would be around Rs. 0.75
Crores/hectare/year (Secondary research on empty costs) The total
revenues expected from the 28 hectares of land would be Rs. 30 Crores
Key enablers for the project The successful execution of the project would require development of
land and connectivity to the empty depot area and ensuring optimal
utilisation of space in the yard. In absence of such connectivity, the empty
container yards development may lead to congestion. Hence, the review
of empty container yard development should be done periodically to
ensure that it is line with connectivity at the port and is not causing
congestion.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
69
Exhibit 8.1.42: 28 Hectares of empty depot land development
28
28 Hectares
Hectares of
of
Empty yard
Empty yard (2015-
(2015-
16)
16)
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
70
8.1 Client Related Investment Projects
8.1.13 Reducing POL tank farm dwell time
Summary Coverage
Need for the project JNPT existing tank farm capacity for POL products will fall short of the traffic
in POL products at an average dwell time of 30 days. Tank farm operators
will need to either construct additional tanks or turn around tanks with
shorter dwell time of 25 days.
Brief description of the project Tank farm operators will need to construct 15% additional POL tankage
capacity if they want to maintain dwell times. Alternatively they can reduce
dwell times to 25 days by turning around product faster. These tank farms
can be constructed in land reclaimed during 4th container terminal
construction.
Key enablers for the project Acquisition of land for the project will be the key factor for the success of the
project.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
71
8.1 Client Related Investment Projects
8.1.14 Reducing pigging hours
Summary Coverage
Need for the project JNPT will face capacity pressure with total traffic rising to around 11.4 Mtpa
IN 2019-20. Of this 7 Mtpa will require pigging with substantial number of
pigging hours increasing unoperational time.
Brief description of the project JNPT along with terminal operators would need to invest in technology to
reduce pigging hours by 1 hour for each vessel operation. This could be
through improved pig or other improvements.
Key enablers for the project Utilization of technology to enable reduction in pigging hours would be the
key enabler of this project
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
72
8.1 Client Related Investment Projects
8.1.15 Construction of second marine chemical berth
Summary Coverage
Need for the project JNPT will face capacity pressure with total traffic rising to around 12.5 Mtpa
after ONGC crude volumes increasing above 5 Mtpa. The three berths for
liquid chemicals with associated facilities will not be sufficient to handle the
increased traffic creating the need for an additional berth
Brief description of the project A BOT operator would be invited to construct a 300 m berth along with
associated dredging so as to cater to additional liquid traffic. The BOT
operator would also need to deploy marine loading arms as well as
pipelines to cater to the traffic. A pipeline corridor for connecting pipelines to
the berth would also need to be constructed
Key enablers for the project The completion of dredging activity would be the key to the inception of the
project. The revenue sharing agreement between the BOT operator and
JNPT will also determine the success of the project
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
73
8.1 Client Related Investment Projects
8.1.16 Reduction of POL tank farm dwell time
Summary Coverage*
Need for the project JNPT existing tank farm capacity for POL products will fall short of the traffic
in POL products at an average dwell time of 25 days. Tank farm operators
will need to either construct additional tanks or turn around tanks with
shorter dwell time of 20 days.
Brief description of the project Tank farm operators will need to construct 20% additional POL tankage
capacity if they want to maintain dwell times. Alternatively they can reduce
dwell times to 20 days by turning around product faster. These tank farms
can be constructed in land reclaimed during 4th container terminal
construction.
Key enablers for the project Acquisition of land for the project will be the key factor for the success of the
project
Dwell time figure based on absence of any prior tank farm construction in 2018-19
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
74
8.1 Client Related Investment Projects
8.1.17 Reduction of chemical tank farm dwell time
Summary Coverage
Need for the project JNPT existing tank farm capacity for chemicals will fall short of the traffic in
POL products at an average dwell time of 30 days. Tank farm operators will
need to either construct additional tanks or turn around tanks with shorter
dwell time of 25 days.
Brief description of the project Tank farm operators will need to construct 15% additional chemical tankage
capacity if they want to maintain dwell times. Alternatively they can reduce
dwell times to 25 days by turning around product faster. These tank farms
can be constructed in land reclaimed during 4th container terminal
construction.
Key enablers for the project Acquisition of land for the project will be the key factor for the success of the
project
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
75
Chapter 9
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
76
9.1 Planned Public Investment Projects
9.1.1 Hiring of Pilots
Summary Coverage
Financing Source: JNPT Internal Resources
Need for the project JNPT would face an increase in vessel calls with increase in traffic. This
would require additions of pilots, tugs and launches at regular intervals in
line with the increase in vessel calls.
Pilots are required for almost all vessels at JNPT to navigate the JNPT
channel. Each pilot is capable of 4-5 moves a day and based on the
vessel traffic additional pilots would be required.
Technical Description The increase in vessel calls would lead to increase in requirement of
pilots at various points of time. JNPT should plan for the same in advance
and hire pilots to meet future capacity.
Pilots should be trained and capable of handling all vessels operating at
JNPT.
Key enablers for the project The success of the project would depend on obtaining the required
clearances and recruiting and retaining the best talent.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
77
9.1 Planned Public Investment Projects
9.1.2 Hiring of Tugs
Summary Coverage
Financing Source: JNPT Internal Resources
Need for the project JNPT would face an increase in vessel calls with increase in traffic. This
would require additions of pilots, tugs and launches at regular intervals in
line with the increase in vessel calls.
Almost two tugs are required per vessel at JNPT. The tugs are used to
navigate and turn the ship.
Technical Description The increase in vessel calls would lead to increase in requirement of tugs
at various points of time. JNPT should plan for the same in advance and
hire tugs to meet future capacity. The specification of the tugs should be
such that they are capable of handling all vessel sizes at JNPT.
Key enablers for the project The success of the project would depend on obtaining the required
clearances and hiring the tugs with the requisite specifications.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
78
9.1 Planned Public Investment Projects
9.1.3 Hiring of Pilot Launches
Summary Coverage
Financing Source: JNPT Internal Resources
Need for the project JNPT would face an increase in vessel calls with increase in traffic. This
would require additions of pilots, tugs and launches at regular intervals in
line with the increase in vessel calls.
Each ship requires a pilot launch to carry the pilot to the ship and to bring
the pilot back from the ship.
Technical Description The increase in vessel calls would lead to increase in requirement of pilot
launches at various points of time. JNPT should plan for the same in
advance and hire launches to meet future capacity.
The number of launches required can be reduced further by hiring
launches that are capable of faster speeds and therefore can transfer the
pilot to and from the ship faster.
Key enablers for the project The success of the project would depend on obtaining the required
clearances and hiring the launches with the requisite specifications.
* As the speed of pilot launch increases it is probable that the number of pilot launches required would decreases
(this is because with higher speeds the same launch can service more number of vessels)
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
79
9.1 Planned Public Investment Projects
9.1.4 Conversion of a railway track to full operational railway siding inside the port
Summary Coverage
Financing Source: JNPT Internal Resources
Project to be undertaken Conversion of one of the escape tracks at JNPCT to full operational
railway siding.
Need for the project The increase in Rail Capacity outside the port due to addition of a railway
track will lead to increase in Containers coming by Rail. These will require
additional railway siding. JNPCT has already planned for conversion of
one of the railway siding to full operations.
Technical Description The project would entail acquisition of two RMGCs and conversion of one
railway siding into full operations railway track. The output from KPMGs
assessment model also projects the requirement of the project. This
should be completed by 2006-07
Key enablers for the project The success of the project would depend on obtaining the required
clearances on time
Expected capacity addition The project is expected to add capacity to handle additional 350000
TEUs at the Rail ICDs within JNPT
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
80
9.1 Planned Public Investment Projects
9.1.5 Common user pipelines
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
81
Exhibit 9.1.1
Common user
pipeline network
JNP ( At Present)
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
82
Exhibit 9.1.2
Alternate Common
user pipeline
network
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
83
9.1 Planned Public Investment Projects
9.1.5 Common user pipelines
2024-25 1,613.20
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
84
9.1 Planned Public Investment Projects
9.1.5 Common user pipelines
Financial Coverage –
For the given project financial coverage is obtained by assuming financing of the project by JNPT's internal reserves.
This is because the infrastructure being created is common user based.
The cost of debt is estimated by assigning a spread over the zero coupon yield curve for Government bonds as well as
taking into account a repayment period. Here we assume the repayment period as 10 years and taking the ZCYC curve
for 2010 and 2015 as of 11th July 2006 we arrive at the cost of debt for a loan taken in 2010-11. Here the cost of debt
arrived at 8.32% i.e. the risk free rate of debt for a loan in 2010-11 which is also equal to the opportunity cost of JNPT's
cost of capital.
Implementation schedule –
The project implementation should begin at the earliest given the requirement in 2007-08. The period of implementation
could be around 12 months. The project might be pushed back from a conscious decision to operate at higher berth
occupancy till shifting of the BPCL jetty happens in 2009-10.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
85
9.1 Planned Public Investment Projects
9.1.6 4 laning of SH - 54
Summary coverage
Financing source : SPV
Year project is to be operational 2007-08
Need for the project Currently JNPT has only one 4 lane evacuation road – NH4B. For traffic headed
towards Mumbai and Gujarat, the existing 2 lane road of SH-54 and Aamra Marg is
proving to be a capacity bottleneck. This will be especially relevant as GTII begins
operations and traffic serviced rises over the next couple of years. There is need for an
4 lane evacuation road to avoid congestion arising out of the current 2 lane road as seen
in exhibit 9.1.5
Brief description of the project NHAI as part of an SPV Mumbai-JNPT Road Co. Ltd. Is carrying out 4 laning of SH-
54 and Aamra Marg. The details of the project include the4 laning of SH-54 from km
6.400– 14.550 and construction of four lane Aamra Marg including six lane major bridge
across Panvel Creek (Belapur-Gavanphata – 6.202 km).
Financial coverage The coverage of the project is through a Special purpose vehicle with participation from
NHAI, JNPT , CIDCO and PWD. The SPV Mumbai-JNPT road Company Ltd. was
formed to undertake the expansion to 4 lanes of both NH4B and SH-54. The details of
the SPV financing structure are made available in exhibit below. Total cost of the 2
projects of road widening is Rs 3580 million as seen in exhibit 9.1.4
Exhibit 9.1.4: SPV Financing Details
Particulars Rs millions Rs millions
Equity 1460
NHAI 970
JNPT 400
CIDCO 90
Debt by Financial institutions 1430
Subordinate Debt 690
JNPT 600
CIDCO 90
Total 3580
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
86
9.1 Planned Public Investment Projects
9.1.6 4 laning of SH - 54
4 laning of SH- To Aamra
54 and Aamra Marg
ta
Marg
n
ha
ep
El
Port terminals SH54
NH4B
Port Approach
Road
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
87
9.1 Planned Public Investment Projects
9.1.7 Grade separators at Karal and Guvan Phata
Summary coverage
Financing source : SPV
Year project is to be operational 2008-09
Need for the project At present at Karal junction , traffic from SH54 and NH4B headed for the other
highway/CFS tend to cause congestion on the main port road. A significant
share of traffic uses the junction only to change roads but this still blocks access
to the port. At Gavan Phata traffic from NH4B, SH81, Aamra Marg and SH54
headed towards Mumbai, Panvel and the port meet causing congestion. Grade
separators (these allow traffic to flow in all 4 directions at a junction without
hampering traffic headed to any other direction) at these junctions would help in
reducing congestion
Brief description of the project Grade separators at the 2 junctions of Karal and Guvan would help in the free
flow of traffic onto any road/highway from any road without encountering
/obstructing traffic. This would significantly reduce congestion as well as reduce
accidents and help in the highways being utilized at their full capacity.
Financial costs The coverage of the project will be through the same Special purpose vehicle carrying
out widening of NH4B and SH54. The project costs Rs 800 million as per NMDP
plans. Of this JNPT plans to fund Rs 400 million from its internal resources.
In 2008-09 terms the cost of the project will be Rs 865 million.
Key requirements JNPT would need to initiate the formation of an SPV with various partners so as
to facilitate execution of this project
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
88
Exhibit 9.1.6: Grade Separators at Karal and Guvan Phata
To Aamra
Marg
SH54
NH4B
Grade separator
at Karal Phata
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
89
9.1 Planned Public Investment Projects
9.1.8 Increase shallow berth moves to 16 moves per hour
Summary Coverage
Financing Source: JNPT Internal Resources
Project to be undertaken Increase shallow berth moves to 16 moves per hour
Year 2008-09
Traffic to be handled at JNPT in year of 4.43 Mn TEUs by JNPT in 2008-09
completion
Need for the project As seen JNPT would face capacity shortfall in areas of RMQC, wharf to
yard and gate capacity. The shallow water berth can increase its capacity
if RMQCs are deployed on the berth.
Technical Description The shallow water berth is currently being used for containers and bulk. It
primarily serves ships with their own cranes or reach stackers are used to
unload/load cargo.
Conversion of this berth to a container berth would yield benefits to the
port as it would increase the throughput of the port and increase the
efficiency of the port.
The project would involve replacement of two RMQCs on JNPCT and
relocation of the same to the shallow water berth (RMQCs 2 & 7a will be
replaced and these two RMQCs will be shifted to the shallow water berth)
Key enablers for the project Benefits from this project would only be derived if the completion of
expansion of the wharf approach road and improvement of gate capacity
are completed at the same time. Without the development of wharf
approach road and improvement of gate capacity an improvement in
shallow water berth may lead to congestion.
Costs The cost of the project is limited to relocation cost which is expected to be
around 5-10 Crores
Expected capacity addition Increase in moves of shallow water berth is expected to increase the
capacity by 50,000 TEUs
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
90
9.1 Planned Public Investment Projects
9.1.9 Additional Link road
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
91
Exhibit 9.1.7: Additional Link Road
SH54
To Aamra
Marg
Additional Link
Road via Belpada
(2009-10)
NH4B
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
92
9.1 Planned Public Investment Projects
9.1.9 Additional Link road
CIDCO 50
Financial coverage –
It is envisaged that the project use a participative Total 1680
financing approach similar to the financing structure
deployed by the SPV “Mumbai- JNPT Port Road Co
Ltd.” for the expansion of NH4B and SH54.
A possible SPV structure is indicated in exhibit 9.1.8
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
93
9.1 Planned Public Investment Projects
9.1.10 Additional Evacuation Road
Summary Coverage
Financing Source: JNPT Internal Resources
Year 2009-10
Need for the project Due to the construction of the EPZ/FTZ the ratio of Noncommercial
traffic will increase. This would require additional evacuation road to be
constructed in the port.
Technical Description It is proposed that an additional evacuation road is developed which can
also service the EPZ/FTZ that has been developed in 2009-10. This
road would originate from the Y junction and join the additional link road
created out of Ulwe Node. It would enable traffic from EPZ/FTZ to exit
the road without congesting any other roads in the port as seen in exhibit
9.1.9.
Key enablers for the project The success of the project would depend on obtaining the required
clearances on time
Distance and Cost The length of the road is 4.108 Km and the cost for developing a four
lane road is expected to be around Rs 41 Crore (10 Crore/Km for a four
lane road)
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
94
Exhibit 9.1.9: Additional Evacuation Road
fi c
raf
T
Z
EP
Additional Link
Road (2009-10)
Evacuation (EPZ)
Road
(2009-10)
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
95
9.1 Planned Public Investment Projects
9.1.11 Dronagiri link road
Summary Coverage
Financial source : JNPT Internal Resources
Year project is to be operational 2009-10
Need for the project At present traffic from Dronagiri node intended for the port has to use highway
NH4B and traverse through Karal junction. This is a major cause for congestion.
The extension of the road to Dronagiri node will reduce congestion and ease
flow of traffic.
Brief description of the project The project will be a 4 lane road of width 60 m extending to a distance of 2.63
kms. Currently the road will originate from tank farm road and extend to
Dronagiri node. The road will eventually be linked to the 4th container terminal
road at the port end and to the Khopta bridge road (currently being executed) by
the PWD at the Dronagiri node end).
Financial costs This project is likely to be executed by JNPT as the road lies within port
boundaries. The length of the road is 2.63 Km and the cost for developing a four
lane road is expected to be around Rs 26.3 Crore in present value terms (10
Crore/Km for a four lane road). In 2009-10 terms the road can be expected to
cost Rs 29.6 crores.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
96
Exhibit 9.1.10 : Road to Dronagiri Node
Road to Dronagiri
Node (2009-10)
To Dronagiri Node
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
97
9.1 Planned Public Investment Projects
9.1.12 Dredging
Summary Coverage
Financing Source: JNPT Internal Resources and Debt
Project to be undertaken Dredging to enable fully loaded 6000 TEU ships and 7500 TEUs partially
laden ships during tidal window
Need for the project As the average ship size on the Europe Asia route increases, it would be
found that JNPT would not be able to handle more than 20% of the types
of ships in the Europe Asia route. This could lead to some large shippers
moving to other ports. To avoid this JNPT would need to dredge its
channel to enable ships of upto 6000 TEUs at all times and of upto 7500
TEUs at tidal window. This could be undertaken in two phases.
The first phase would involve dredging to enable 6000 TEU fully laden
ships with tidal window and the second phase of dredging can further
deepen the channel to enable a fully laden 6000 TEU vessel to be
serviced at all times.
Technical Description Phase one would involve dredging the channel to a depth of around
12.5m at all times to enable fully laden 6000 TEU vessel to arrive during
the tidal window (at 14 m depth)
The details of the projects would involve the following:
z The total area of dredging required in the JNP/MbP region is
estimated at 1775 ha.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
98
9.1 Planned Public Investment Projects
9.1.12 Dredging
Technical Description z The total quantity of proposed capital dredging works out to
approximately 48.5 million cubic meters with annual maintenance
dredging requirements of 5.0 million cubic meters.
z The total length of the channel along which dredging needs to
take place is 33,525 meters.
z Material that has to be dredged includes 48.10 million cu.m. of
marine clay and 0.47 million cu.m. of rock. (comprising of 0.32
million cu.m of weathered rock and 0.15 million cu.m. of sound
rock requiring pre-treatment)
Cost The costs for the capital dredging are tentatively forecasted at Rs. 800
crores. This is expected to be funded through a mix of debt and ports
internal resources.
Future Plans Phase 2 of the project can be undertaken in the year 2015-16 when JNPT
would again face a limitation on channel depth.
Enablers The success of the project would depend on obtaining the clearances and
attracting larger ships through marketing efforts and other means to
recover the costs of dredging
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
99
9.1 Planned Public Investment Projects
9.1.12 Dredging
Having completed the dredging JNPT would be Exhibit 9.1.11 : Vessels that can be serviced by JNPT
able to accommodate 6000 TEU fully laden
vessels using the tidal window. The proportion 2005-06
of vessels that JNPT would be able to handle Percent (Before
post the dredging is provided alongside accommodation Dredging) Post Dredging
Based on this the estimated proportion of < 750 100% 100%
Europe Asia traffic that JNPT would not be able
to accommodate would be as shown in exhibit 750 - 1750 100% 100%
9.1.12. 1750-3500 100% 100%
As can be seen in 2015-16 the proportion of
traffic that cannot be accommodated increases 3500-5500 38% 71%
to nearly 16.83% and the next phase of dredging 5500-8000 5% 25%
would be required in 2015-16.
8001-13000 0% 0%
Exhibit 9.1.12 Percentage of Europe Asia Vessels that cannot be accommodated by JNPT post Phase I dredging
2008- 2009- 2010- 2011- 2012- 2013- 2014- 2015- 2016- 2017- 2018-
09 10 11 12 13 14 15 16 17 18 19
< 750 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
750 - 1750 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1750-3500 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
3500-5500 4.23% 4.26% 4.18% 4.21% 4.24% 4.28% 4.31% 4.35% 4.38% 4.23% 4.26%
5500-8000 10.65% 11.62% 11.14% 11.26% 11.37% 11.48% 11.60% 11.71% 11.83% 10.65% 11.62%
8001-13000 0.00% 0.00% 0.92% 0.92% 0.92% 0.92% 0.92% 0.92% 0.91% 0.00% 0.00%
Total 14.88% 15.88% 16.24% 16.39% 16.53% 16.68% 16.83% 16.98% 17.13% 14.88% 15.88%
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
100
9.1 Planned Public Investment Projects
9.1.13 Increase RMQC moves at JNPT to 24 moves per hour
Summary Coverage
Financing Source: JNPT Internal Resources
Need for the project JNPT would face capacity pressures in 2009-10 due to increase in traffic.
However in light of the replaced RMQC at JNPCT (project done in 2008-
09) and the presence of double move cranes at GTI it is possible to
augment capacity by increasing the moves per hour to 24
Technical Description The project would involve replacement of three RMQCs on JNPCT. 3
RMQCs that are owned by JNPT since 1989 can be replaced by new
RMQCs as these cranes would have outlived their life by this period. Both
of these RMQCs should be double-move capable so that they can allow
increased capacity in later years.
It will be important to carry out a review of JNPT civil infrastructure to
allow for optimal output from the new RMQC’s. An initiative on this front
should be considered by the port at the time of installing new equipment.
Key enablers for the project The successful execution of the project would require the necessary
training for crane operators for handling double move cranes. Apart from
this, it would also require an increase in automation at gates to reduce
congestion, since traffic would increase. This project should ideally be
taken up after the 330 m wharf expansion project is completed (2008-09)
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
101
9.1 Planned Public Investment Projects
9.1.14 Six Laning of NH4B
Summary coverage
Financial source : SPV
Year project is to be operational 2010-11
Need for the project The link highway of NH4B will need to be widened owing to the sharp increase
in traffic as the first phase of the 4th container terminal begins operations. (The
traffic in 2010-11 goes up to 5.9 million TEUs.) Further there is a need for
additional connecting link roads after the introduction of 4 lanes of approach
road to the port during 2009-10.
Brief description of the project NH-4B 4 laning was completed in end 2005 and this will be widened to 6 lanes
to cater to additional traffic from the port. NHAI is likely to take up this widening
activity. Map is shown in exhibit 9.1.13.
Financial coverage The coverage of the project is likely through a SPV between NHAI, CIDCO and
JNPT. Alternatively a JV with JNPT and NHAI may also be considered. JNPT's
contribution to the total cost of Rs 450 million is likely to be Rs 50 million. In
2010-11 terms the cost of the project would be Rs 468 million.
Key requirements JNPT would need to initiate the formation of an SPV with various partners so as
to facilitate execution of this project.
** - It may be necessary to initiate studies to further expand capacity of NH-4B to 8 lanes by 2013-14. This is in light
of the planned Nava-Sewri trans-harbour link expected to significantly increase traffic from Mumbai to NH4B. This
project is currently in initiation phase and is expected to take 7-8 years for completion. Given the uncertainty and
unavailability of traffic forecasts on NH4B due to the Nava-Sewri link, it is recommended that a study be carried out
on the same when the project plan is clearer.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
102
Exhibit 9.1.13: 6 laning of NH 4B 6 laning of NH4B
To Aamra
Marg
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
103
9.1 Planned Public Investment Projects
9.1.15 Additional road linking port and highways
Summary coverage
Financial source : Internal Resources
Year project is to be operational 2010-11
Need for the project An additional link road will be needed owing to the sharp increase in traffic as
the first phase of the 4th container terminal begins operations. The EPZ/FTZ
and CFS operations within a port will also lead to an increase in the non
commercial traffic. Owing to this an additional road will be required.
Brief description of the project A 4 lane road connecting the port container road to main highways. This road
will pass next to the EPZ/FTZ and near the CFSs to allow for movement of non
TEU carrying traffic without interfering with the port operations.
Financial coverage The project would be funded by JNPT as the road lies within the port
boundaries. The project has been identified by JNPT and planning for the same
has begun. Currently the project is undergoing a techno-economic feasibility
study. The project cost is estimated to be around 45 Crores in present value
terms. In 2010-11 the project would cost Rs 52 crores.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
104
9.1 Planned Public Investment Projects
9.1.15 Additional road linking port and highways
SH54
NH 4B
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
105
9.1 Planned Public Investment Projects
9.1.16 4th container terminal link road
Summary Coverage
Financial source : JNPT Internal Resources
Year project is to be operational 2010-11
Details of Project 4th container terminal road to be extended to existing Drongairi Node road
Need for the project As the 4th container terminal begins operations, traffic from the terminal will need
to be evacuated bypassing the existing port approach road to avoid congestion.
Linking to the Dronagiri link constructed in 2009-10 will allow for easy
evacuation of containers to the CFS zone.
Brief description of the project The project will be a 4 lane road of width 60 m extending to a distance of 3.30
kms. The road will originate from the approach road to the 4th container terminal
made by the BOT operator and join the Dronagiri link node behind the tank
farms. The road will eventually be linked through to the Khopta bridge road
(currently being executed by the PWD) at the Dronagiri node end.
Financial costs This project is likely to be executed by JNPT as the road lies within port
boundaries. The length of the road is3.3 Km and the cost for developing a four
lane road is expected to be around Rs 33.3 Crore (10 Crore/Km for a four lane
road). In 2010-11 terms the road will cost Rs 39 crores.
A map of the 4th container terminal road till Dronagiri link is available in exhibit 9.1.15.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
106
Exhibit 9.1.15 : 4th container terminal link
To
Dronagiri
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
107
9.1 Planned Public Investment Projects
9.1.17 Reduction in vessel unoperational hours
Summary Coverage
Need for the project With increase in number of liquid cargo vessels calling at JNPT, the number
of hours lost due to sampling and other operations will increase significantly.
In order to service the vessels, JNPT would need to reduce these hours
from average of 6 hours per vessel to 4 hours per vessel.
Brief description of the project Vessel unoperational hours will need to be reduced from 6 hours to 4 hours
on an average. This can be done by reduction in the sampling time by
providing sampling facilities closer to the jetty. Simultaneously tank farm
owners have to be encouraged to reduce pre and post discharge hours.
Key enablers for the project Securing cooperation of tank farm owners will be an important success
factor for this project. Incentives may have to be provided to tank farms for
the same.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
108
9.1 Planned Public Investment Projects
9.1.18 Development of Sorting Yard
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
109
9.1 Planned Public Investment Projects
9.1.18 Development of Sorting Yard
P
LI RO
N PO
E SE
D
R
AI
L
EX
LI IST
NE IN
G
RA
IL
SORTING
YARD
FUTURE
INTERSECTION
OF RAIL LINES
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
110
9.1 Planned Public Investment Projects
9.1.18 Development of Sorting Yard
The utilization of this facility by CFS operators and SEZ Reach stackers 4 nos. Rs 46 million
traffic would reduce the pressure on the connecting roads
Buildings Admin Building Rs 14 million
to the port.
Development 12 hectares Rs 156 million
Cost
Calculation of the Investment - 13 million per
hectare
The yard is proposed to be set up by JNPT. JNPT will
need to develop the land and employ approximately 10 Total Rs 356 million
rail operators including a brake certificate man for around
Rs 5 million a year.
Upfront capital costs are estimated at Rs 356 million as
seen in exhibit 9.1.17. These are current capital costs and
would be adjusted for inflation to arrive at 2009-10
investments.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
111
9.1 Planned Public Investment Projects
9.1.18 Development of Sorting Yard
Financial Coverage –
For the given project financial coverage is obtained by calculating as well as making suitable assumptions about the
developer’s capital structure. The debt-equity structure of the BOT contractor is taken as 1:1 in line with TAMP
guidelines.
The Developer's cost of debt is estimated by assigning a spread over the zero coupon yield curve for Government
bonds as well as taking into account a repayment period. Here we assume the repayment period as 10 years and
taking the ZCYC curve for 2009 and 2014 as of 11th July 2006 we arrive at the cost of debt for a loan taken in 2009-10.
Here the cost of debt arrived at 9.91% on taking a risk spread of 100 bps over the risk free rate of debt.
Using an equity Beta of 1 we arrive at the Developer's cost of equity. One is the average infrastructure index Beta
between July 2002 and July 2005 in Indian equity markets. Indian market returns over risk free rate have been 6.5%
historically. Using these assumptions the cost of equity is calculated as 16.41%
Cost of capital arrived at for the project is 13.17% for a D/E ratio of 1.
Implementation schedule –
The implementation schedule for this project is contingent on the construction of the 4th container terminal. The
acquisition of the land pre-allocated to PAPs and issue of alternative land is and important requirement of the project.
The period for construction of sorting yard and allied activities would be 15 months. This would need to be operational
by 1st quarter of 2010-11.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
112
9.1 Planned Public Investment Projects
9.1.19 Increase RMGC Moves per hour
Summary Coverage
Financial source : Port resources
Need for the project The up gradation of RMQCs carried out in the previous year would lead
to an increase in Capacity. This increase in capacity would require
increase in supporting infrastructure. The capacity assessment model
indicates that the RMGCs would act as a constraint to match the
increase in traffic and capacity.
Brief description of the project The project involves up gradation and replacement of the RMGCs to
enable 18 moves/hour on the RMGCs. This can be achieved by
replacing the RMGCs with new and advanced version. These changes
can be clubbed with the up gradation changes that would be required.
Two RMGCs at JNPCT are on hire since 1995-96 and these can be
replaced by new RMGCs to increase moves/hour
Key enablers for the project The success of the project would depend on obtaining the required
clearances on time
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
113
9.1 Planned Public Investment Projects
9.1.20 New Rail track to port
Summary Coverage
Financial source : Public investment
Year project is to be operational 2014-15
Need for the project JNPT will witness significant rise of container cargo in 2013-14 to 8.75 million
TEUs. With the fourth container terminal phase 2 set to begin in 2014-15 , it will
become necessary to have dedicated railway track serving JNPCT / NSICT and
GTI/4th Terminal. The additional railway track will thus help to serve 2 terminals
as well as any traffic that may arise from the SEZ.
Brief description of the project The newly laid track will originate from the sorting yard and run alongside the
port EPZ/FTZ and enter the port next to the container gate. The line will be
extending for a length of 5.6 kms and will be 60 m wide.
Alternatively the existing railway line can also be expanded (given
availability of space for two additional lines) at the current location. This
would avoid the need of any road over bridge over the container road.
Financial costs The laying of the railway line will cost Rs 147 crore in 2014-15 terms assuming a
cost of Rs 20,000 for laying a meter of railway line. The project will be funded by
the Railways with JNPT participation not being envisaged.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
114
9.1 Planned Public Investment Projects
9.1.20 New Rail track to port
PROPOSED
RAILWAY LINE
2014-15
P
LI RO
N PO
E SE
D
R
AI
L
EX
LI IST
NE IN
G
RA
IL
SORTING
YARD
2011-12
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
115
9.1 Planned Public Investment Projects
9.1.21 Dredging
Summary Coverage
Financing Source: JNPT Internal Resources and Debt
Project to be undertaken Dredging to enable fully loaded 6000 TEU ships at all times
Need for the project As the average ship size on the Europe Asia route increases, it would be
found that JNPT would not be able to handle more than 16% of the types
of ships in the Europe Asia route. This could lead to some large shippers
moving to other ports. To avoid this JNPT would need to dredge its
channel to enable ships of upto 6000 TEUs at all times and of upto 7500
TEUs at tidal window. This could be undertaken in two phases.
The second phase of dredging will further deepen the channel to enable a
fully laden 6000 TEU vessel to be serviced at all times.
Technical Description Phase two would involve dredging the channel to a depth of around 14m
from previous 12.5 m to enable fully laden 6000 TEU vessel to arrive at
all times.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
116
9.1 Planned Public Investment Projects
9.1.21 Dredging
Technical Description z The total area of dredging required in the JNP/MbP region is
estimated at 1775 ha.
z The total length of the channel along which dredging needs to
take place is estimated to be similar to the phase 1 length, which
is 33,525 meters.
Cost The costs for the capital dredging are tentatively forecasted at Rs. 800 -
1000 crores at present value. This is expected to be funded through a mix
of debt and ports internal resources. The estimated cost adjusted for
inflation would be around 1200-1300 Crores
Enablers The success of the project would depend on obtaining the clearances and
attracting larger ships through marketing efforts and other means to
recover the costs of dredging
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
117
9.1 Planned Public Investment Projects
9.1.21 Dredging
After having undertaken this dredging JNPT would Exhibit 9.1.19 : Vessels that can be serviced by JNPT
be able to accommodate 6000 TEU fully laden
vessels at all times. The proportion of vessels that 20014-15
JNPT would be able to handle post the dredging is Percent (Before
provided alongside accommodation Dredging) Post Dredging
Based on this the estimated proportion of Europe < 750 100% 100%
Asia traffic that JNPT would not be able to
750 - 1750 100% 100%
accommodate would be as follows:
1750-3500 100% 100%
8001-13000 0% 30%
Exhibit 9.1.20 : Percentage of Europe Asia Vessels that cannot be accommodated by JNPT post Phase II dredging
2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24 2024-25 2025-26 2026-27
< 750 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
750 - 1750 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1750-3500 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
3500-5500 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
5500-8000 8.31% 8.40% 8.48% 8.57% 8.65% 8.74% 8.83% 8.91% 9.00% 9.09% 9.18% 9.28%
8001-13000 0.92% 0.91% 0.91% 0.91% 0.91% 0.91% 0.91% 0.91% 0.91% 0.90% 0.90% 0.90%
Total 9.23% 9.31% 9.40% 9.48% 9.56% 9.65% 9.73% 9.82% 9.91% 10.00% 10.09% 10.18%
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
118
9.1 Planned Public Investment Projects
9.1.21 Increase RMGC Capacity
Summary Coverage
Financing Source: JNPT Internal Resources
Project to be undertaken Increase RMGCs on tracks
Year of completion of project 2016-17
TEUs to be Handled at JNPT 3.2 Mn TEUs – Rail in 2016-17
8.8 Mn TEUs – Road in 2016-17
Need for the project An additional rail tracks would be laid in 2014-15 to JNPT. This would
increase the number of trains that can arrive at JNPT to 36 and would be
able to match the increase in traffic. This will have to be matched with an
increase in train handling capacity within the port. The current number of
internal tracks would be enough to match the increase in capacity,
however, additional RMGCs would be required. The terminals would
therefore need to buy additional RMGCs. The total number of additional
RMGCs required would be 2-3 in number. It is expected that these
additions would be made at JNPCT, GTI and the fourth terminal
Technical Description The project would involve entail acquisition of additional RMGC at
terminals. The increase in RMGCs would reduce turn around times and
would therefore be able to match the increase in capacity required due
to increase in traffic.
Key enablers for the project The success of the project would depend on obtaining the required
clearances on time
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
119
9.1 Planned Public Investment Projects
9.1.23 Road to be constructed to connect the Aamra Marg link road to the port
Summary Coverage
Financing Source: JNPT Internal Resources
Year 2017-18
TEUs to be Handled 3.6 Mn TEUs – Rail
9.7 Mn TEUs – Road
Areas and extent of shortfall Road capacity for approach roads to port is less than the required
capacity and needs to be increased.
Project to be undertaken Road to be constructed to connect the Aamra Marg link road to the port
Need for the project JNPT would face increasing pressure to upgrade its road infrastructure
due to increase in traffic from the port. While the port has a number of
port linking road the capacity is limited by the approach roads. As can be
seen in exhibit 9.1.21, the number of port approach lanes (shown in
Green stripes) is lesser than the number of port linking lanes (in pink)
Technical Description An additional port road should be connected between the port and the
2nd link road this would enable the port to meet its capacity
requirements. Map is indicated in exhibit 9.1.21.
The road is expected to be 60m wide and would be 3.095 Km long. It is
proposed to be a four lane divided road.
Key enablers for the project The success of the project would depend on obtaining the required
clearances on time
Cost The expected cost for the project would be 4.76 Crore / Km and on this
basis the expected cost of the project is 14.75 Crores.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
120
9.1 Planned Public Investment Projects
9.1.23 Road to be constructed to connect the Aamra Marg link road to the port
n ta
ha
2ND LINK TO JNPT
ep
El
SH54
4 Lane
6Lane
6Lane
4 Lane
To Khopta Bridge
Exhibit 9.1.21 : Capacity
mismatch in port roads
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
121
9.1 Planned Public Investment Projects
9.1.23 Road to be constructed to connect the Aamra Marg link road to the port
n ta
ha
2ND LINK TO JNPT
ep
El
Proposed
connection to
link road
SH54
To Khopta Bridge
Exhibit 9.1.22 : Proposed
connection to Link road
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
122
9.1 Planned client related investments
9.1.24 Emergency Berth
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
123
9.1 Planned client related investments
9.1.24 Emergency Berth
Butcher Elephanta
Island
nnel
JNP Cha
SHEVA
EMERGENCY
BERTH (located
adjacent to
Marine chemical
berth set up in
2011-12)
Uran Mud
Flat
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
124
9.1 Planned client related investments
9.1.24 Emergency Berth
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
125
9.1 Planned client related investments
9.1.24 Emergency Berth
Financial Coverage –
For the given project financial coverage is obtained by assuming financing of the project by JNPTs internal reserves.
This is because the infrastructure being created is common user and security oriented.
The cost of debt is estimated by assigning a spread over the zero coupon yield curve for Government bonds as well as
taking into account a repayment period. Here we assume the repayment period as 10 years and taking the ZCYC
curve for 2010 and 2015 as of 11th July 2006 we arrive at the cost of debt for a loan taken in 2010-11. Here the cost of
debt arrived at 8.32% i.e. the risk free rate of debt for a loan in 2010-11 which is also equal to the opportunity cost of
JNPTs cost of capital.
Implementation schedule –
The implementation schedule for this project is contingent on the construction of the 1st marine berth with the
associated relocation of BPCL jetty. The period for jetty construction and allied activities would be 12 months.
A detailed feasibility study would need to be carried out for the location of this emergency berth considering
the profile of cargo at JNPT and navigational safeguards.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
126
Chapter 10
Planned organisational
improvements
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
127
10.1 Planned organizational improvements
10.1.1 Strengthening of marketing team
JNPT currently does not have a full fledged marketing Exhibit 10.1.2 : Marketing team –
section. It is a support section under the administration
department and handles public relations and marketing Annual cost of implementation
activities. It has just one managerial personnel looking Name Nos. Cost (in Rs)
after public relation activities along with 5 administrative
staff . We propose a revised structure with additional
hiring of 3 additional marketing professionals so as to Marketing Rs 20,00,000 per
effectively handle major roles of account management, Budget annum
price negotiation and promotional activities. They will Head of Team 1 Rs 20000 per
report to the head of marketing team who will oversee month
the marketing activities of the port. Besides these an
analyst could be employed to follow customer revenue 3 account 3 Rs 14500 per
managers month
and profitability trends. The marketing team could
continue to operate as a cell under the administration
department. Team structure is shown in exhibit 10.1.1. Analyst 1 Rs 10750 per
month
Description of Benefits
Currently, in the Indian ports sector capacity is far lesser Cost of implementation
than demand resulting in limited focus on marketing and The implementation cost for the marketing team
sales activities. However this has changed with private includes the revamped budget for the cell as well as
ports like Mundra and Pipavav having active marketing the cost of hiring of personnel and their monthly
departments going all out to woo customers through salaries. Monthly salaries will be in line with JNPT
exercises such as presentations, meetings etc with managerial salary levels discussed in the inception
various shipping lines to increase their traffic. report. Costs are shown in exhibit 10.1.2.
In light of that JNPT needs to strengthen its marketing
team. In the medium to long term, marketing and sales Exhibit 10.1.1 : Structure of the Marketing cell.
can be expected to play a significant role in retaining Head of Cell
and acquiring new customers (shipping lines, agents
and other port users, CFS etc) at JNPT. Marketing and
sales will thus help in customer retention, customer
Account Managers Public Relations officer
management as well as communication of the port’s
competitive advantages.
Analyst Admin Staff
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
129
10.1 Planned organizational improvements
10.1.1 Strengthening of marketing department
Financial Coverage
For the given project financial coverage is obtained by assuming financing of the project by JNPT's internal reserves.
Here the cost of debt arrived at 9.00% i.e. the opportunity cost of JNPT's capital.
Implementation schedule
The implementation schedule for this project can be expected to be 6 months and should be operational by 1st quarter
2008-09.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
130
10.1 Planned organizational investments
10.1.2 Automation at the gates
Year of Completion – 2009-10
General Description and motivation
The 4th container terminal is planned to begin operations in 2010-11, the checking time at gates will prove to be a
constraint and to fasten the checking time at the gates it will be necessary to look beyond constructing additional
gates and deploying security personnel.
It is proposed to set up an automation solution to reduce checking time at gates to less than a minute per truck at all
times. This can be done through setting up an automation solution between the various operators, gates and the
CFS operators. This solution would need to be set up and maintained by JNPT on its databases to facilitate fastest
turnaround time for trucks. This would need to be in place by 2009-10 in advance of the 4th container terminal
Technical Description
The automation project essentially involves the design of an web-base portal connected to a high speed ORACLE
database that is accessible by CFS operators and JNPT. Such an IT implementation would need purchase of a
database software, installation of servers and around 9 person months of effort across the entire software
development lifecycle.
The application is proposed to consist of document management software along with a workflow based application
residing on top of it. The trucks can obtain clearances from gates and the terminals before leaving the CFS.
This application can be further integrated with the customs network to obtain clearance from customs also over the
net. Such an application can also be used as an effective communication channel between the CFSs and the
terminal operators for shipping information, container information, container loading plans etc.
Such a process over the long term would enable the terminal operators provide window clearance for trucks arriving
for particular vessels and would enable smooth operations.
Process
On departure of a container truck from JNPT details of the truck such as destination, quantity, goods etc could be
updated into the system which could be checked at the gate before the truck arrives. The CFS operators and
customs could be able to access the system and thus reduce any duplication of information collection. This would
allow significant reduction in dwell times at the CFS operator.
For containers entering JNPT, the reverse procedure would be followed with the customs sharing their information
on the JNPT web based network which would allow automated flow of trucks through the gates without manual
intervention. Hence, regular incidences of congestion at the gates would be reduced.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
131
10.1 Planned organizational investments
10.1.2 Automation at the gates
The total cost of implementation is expected to be Person months 9 months (Rate – Rs 49.5 lakhs
around Rs 1.21 Crores as seen in exhibit 10.1.3. 20 USD per hour)
Financial Coverage Connectivity 2 MBPS VPN 150000/year
Charges
For the given project financial coverage is obtained by
assuming financing of the project by JNPT's internal Total 1.21 Crores
reserves. This is because the infrastructure being
created is common user based.
Here the cost of debt taken at 9.00% which is equal to
the opportunity cost of JNPT's capital.
Implementation schedule
The implementation schedule for this project can be
expected to be 6-9 months and should be operational by
1st quarter 2009-10.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
133
10.1 Planned organizational investments
10.1.3 Training for double moves
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
134
10.1 Planned organizational investments
10.1.4 Automation at the sorting yard
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
135
10.1 Planned organizational investments
10.1.4 Automation at the sorting yard
Description of Benefits
Exhibit 10.1.5 : Automation investments for sorting
The automation and related processes will reduce the yard
turn around times of trains, this will help in increasing
train capacity at JNPT. This is critical as JNPT faces Equipment Description Costs
train capacity pressures 2010-11onwards due to the ORACLE database RDBMS database 50 lakhs
increase in terminals and traffic Oracle 10
An automation system and related processes will enable
JNPT to service the increase in container traffic that is
expected Servers 2 nos. 20 Lakhs
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
136
10.1 Planned organizational investments
10.1.5 Maintenance Service Level agreement (SLA) between the port and road authorities
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
137
Exhibit 10.1.6 Condition of Roads near JNPT
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
138
10.1 Planned organizational improvements
10.1.6 Strengthening of project management capability
Technical Description
The project management group would typically consist of cross functional teams from several departments.
Departments especially involved would be the port planning and development as well as the finance department.
The role would require capabilities/skills in the following areas -
• Capabilities in structuring of projects
• Capabilities in overseeing projects and project management consultants
• Ensuring adherence to project timelines by various parties (consultant/contractors/etc)
• Liasioning with ministry officials for project clearances
• Capabilities in selection of developer
• Capabilities in evaluation of BOT contracts
The extent of hiring and qualifications of personnel would require a detailed study. It is recommended that there be
a detailed study of staffing and skill requirements in light of the massive expansion activities planned at the port. It is
also imperative that a study be carried out on greater delegation of powers to approve and sanction projects be
given to the port to enable them to carry out this detailed business plan.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
139
Chapter 11
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
140
11.0 Land use plan
11.1 Land use distribution
JNPT has a land area of 2584 ha. Of this only 606 ha are Exhibit 11.1.2 : Proposed Land use Distribution for Land
at JNPT
developed with the remaining land of 1978 ha unutilized
and available for development. Exhibit 11.1.1 highlights Sl. Land use Area (in Ha)
current usage of port land. Any development of land has No
to take into cognizance environmental regulations
pertaining to coastal zones. In this regard JNPT has A Developable:
submitted a Coastal Zone Management Plan to the 1 Residential 162
Ministry of Environment and Forests in the month of June
2005. 2 Port operational 670
Activities
The unutilized land has been divided into two major zones
3 Commercial 45.64
a) Coastal zone b) Land use zone
4 Social facilities 2.07
z The coastal regulation zone of 778 ha (further
divided into CRZ-1 and CRZ-2 along the sea coast 5 Open space 3.57
area). Major activities proposed in this zone are 6 Public utilities 61
− Eco park 7 Road network 206
− Nature park 8 Rail network 50
− Mangrove forest Total Developable Area 1200
− Water bodies B Non-Developable
z The land use zone of 1200 ha Area:
JNPT thus has 1200 ha of developable land demarcation 1 Mangrove & Nature 713.5
park
of which into various zones (seven in all) has been carried
out as per CIDCO land report. The port’s proposed land 2 Tree Belt 41
distribution has been highlighted in exhibit 11.1.2
3 Channels 23.50
Total Non Developable 778
area
Total Gross Area 1978
Source: Final Draft Report on Reserve Price fixation for 1200 ha
land at JNPT – CIDCO, May 2006
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
141
Back
Terminals
up Areas Exhibit 11.1.1 : Current land usage of port area
JNPT
Back up
Township
Areas
Railway Lines
and RMGCs
Land use Zones( indicated in map overleaf) z A detailed breakdown of the proposed land distribution
for 1200 ha of developable land is shown in exhibit
z Zone 1: Proposed on the left of SH-54 and on the
11.2.1 . Exhibit 11.2.2 differentiates between land zones
southern side of the port area, This zone is proposed for
for operational and other activities as part of the CIDCO
port operational activities.
land plan.
z Zone 2: Proposed for port operational activities situated
on the eastern side of the existing JNPT rail link
connecting the container terminals.
z Zone 3 & 4: These zones are proposed for rehabilitation
for project affected people of JNPT and situated on the
south east side of JNPT. This zone consists of two
villages Ektaghar and Ranjanpada.
z Zone 5: This is the zone lying west of the existing JNPT
railway line and the only road from Karal phata to
container terminals. The zone has nature park on the
north side, JNPT township on the south side and the
Dronagiri area on the western side of it. The zone is
proposed for port operational activities.
z Zone 6: This is the smallest zone proposed at Karal
junction and adjacent to Jaskhar village and primarily
proposed for amenities and social facilities for township
or port users.
z Zone 7: This is the zone proposed at northern side of
balance developable area of JNPT and adjacent to the
hilly area and custom area near the JNPT
administrative building. The activities that are proposed
in this zone are port operational activities.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
143
Exhibit 11.2.1 : Land Use Zones for 1200 ha of
developable land
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
144
11.0 Land use plan
11.2 Proposed land usage for 1200 ha of land
INAL
RM
TE
. 5th
OP
PR
TO
K
LIN
Y
RL
D
SE
PO
P RO
Marine Park
LIN
K TO
4th
TE RM
IN AL
Public Utilities TO
BE
D IS
CO
NN
EC
TE
D
Operational Activities
ha
4
N LINE
20
4 .5
8 .9
UR URA
7h
a
.BE LAP
12.5%
ha T LIN
E
4
P ROP
.9 J NP
40
ha
5
.1
Nature Park
62
4B
NH
ha
Public Utilities
22
1 6.
D
YAR
NG
SH ALI
MAR
CH
AN
BR
AN
L- UR P ROP OSED
N VE
Y PA T RUCK T ER MINUS
AILWA
AL R
TR
C EN
P UNJAB
Commercial
WAREHO USING CONWARE
CENTRAL WA REHOUSING
CORP ORA TION
Operational Activities
S EC TOR 4
Residential 12.5 %
S EC TOR 14
Operational
S ECTOR 6
activities
Commercial
MSEB
S EC TOR 7
Social Facility
Open Spaces
Public Utilities
S EC TOR 8
CIDCO LTD.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
145
11.0 Land use plan
11.3 Proposed usage for port operational areas
KPMG identified opportunities for usage of 670 ha of port operational land at various points in time. Land divisions and
facilities for non-operational zones had been identified earlier. KPMG has thus focused on identifying usage
requirements within port operational zone of 670 ha.
Exhibit 11.3.1 highlights proposed usage for port operational land by KPMG as part of business plan exercise for the
plan period till 2015-16. Exhibit 11.3.2 highlights JNPT land usage taking into account current and proposed usage post
the 7 year plan period.
Need for Parking space
Post the development of land for operational activities , there will be 124 ha of land available in port operational
boundaries. An identification technical study for parking in the port will be needed to ensure that congestion does not
occur due to the planned developments. This study should be carried out once GTI enters stable operational phase and
should look towards identifying parking for current and future developments.
Need for Periodic review of land use plan
It is important to carry out a periodic review of land use in the port in light of changing competitive scenario. New
developments that pan out over the next few years may result in the need for certain projects or for a review of existing
projects.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
146
Exhibit 11.3.1 :Proposed land
Empty yard 28
Hectares
usage for port operational areas
(2015-16)
(2015-16)
Empty yard 50
hectares (2008-09)
CFS 49 Hectares
(2015-16)
14 Hectares of CFS
land 162 ha of PAP land
Common User & Other Infra 91 Hectares
@ 20% (non port operational
area)
Port operational land
usage suggested over
plan Available
period Land 124 Hectares * JNPT CFS
Non operational land
for PAP resettlement
* This land can be used forEPZ/FTZexpansion, Ro-Ro yard
Existing land use
and activities such as parking etc that the port may require.
Jashkar and
53 Hectares of CFS Karal villages
land
70 Hectares of CFS
land
JNPT
township
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
148
Chapter 12
Plan of Action
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
149
12.1 Plan of Action to Implement Strategy
The strategy arrived upon needs to be converted into set of actionable steps to allow the port to achieve its vision.
Keeping this in mind an action plan for 7 year plan period from 2007-08 to 2014-15 has been prepared. The action
plan attempts to cover the set of projects/ initiatives to be undertaken by the port in the plan period across the
following areas -
• Development of new infrastructure
• Efficiency improvement
• Organizational improvements
• Development of new infrastructure – This details projects resulting in additional infrastructure creation at the
port such as terminals to augment capacity, logistics related facilities , road networks to improve connectivity
• Efficiency improvement – This details initiatives resulting in improvement of process efficiency at the port such
as automation, increase in crane productivity
• Organizational improvements – This details initiatives designed to restructure/ strengthen organizational
performance such as creation of a dedicated marketing cell. training initiatives etc
The overall action plan identifies the various projects that need to be undertaken to implement the strategy of port
and provides guidelines on various aspects of implementation. The major aspects covered in the action plan consists
of the following -
z Time Lines: This is one of the most critical aspects that a plan of action should contain. It provides an estimate of the
time within which an action has to be completed to ensure that the overall development goal is achieved.
z Dependencies: In achieving the goal for a port it is important to realize that there would be interdependencies
between projects. As an example development of a terminal would be fruitless if connectivity is not improved.
Therefore it is paramount that a plan of action identifies and highlights dependencies that exist. This also enables the
planning departments of port authorities to identify areas that need to be addressed to ensure that the development is
within the planned time frame.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
150
12.1 Plan of Action to Implement Strategy
z Critical success factors: This is an aspect that highlights key elements that have to be addressed to ensure
success of the strategies. It consists of factors which are within/beyond the control of the port and helps in identifying
areas that need to developed but are not within the control of the port. These factors can have a significant impact on
the success of a strategy
This section deals with the overall implementation schedule of the 7 year plan along with critical dependencies
between projects. Individual project success factors are highlighted in individual action plans outlined in Section 3. It
is important to note that the implementation schedule for the 7 year plan indicates timeline for actual execution of the
project i.e. from conceptualization to beginning of commercial operations. On the other hand the individual project
action plans in Section 3, are written from JNPT’s perspective. Hence the time frame indicated are highlighted as
JNPT’s timeline of involvement with the project. Hence for certain client investments the time frame in the individual
action plan may appear to be lesser than that indicated in the investment schedule. This is because construction time
periods for such projects would fall outside the purview of JNPT’s active involvement.
Apart from this the plan of action also considered the support infrastructure that would be required outside the port to
support the ports development plans.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
151
12.1 Plan of Action to Implement Strategy
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
152
12.1 Plan of Action to Implement Strategy
Action 12.1.1 Implementation schedule for infrastructure creation
Plan
Exhibit 12.1.1 : Overall implementation schedule for infrastructure creation projects
Capacity
Creation
Infrastucture Creation project Apr-Sep 2007 Oct-Mar 2008 Apr-Sep 2008 Oct-Mar 2009 Apr-Sep 2009 Oct-Mar 2010 Apr-Sep 2010 Oct-Mar 2011
32 hectares of CFS
Grade separators
Org
Improvements 50 Hectares of empty yards
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
153
12.1 Plan of Action to Implement Strategy
12.1.1 Implementation schedule for infrastructure creation
Exhibit 12.1.1 : Overall implementation schedule for infrastructure creation projects (contd.)
Infrastucture Creation project Apr-Sep 2008 Oct-Mar 2009 Apr-Sep 2009 Oct-Mar 2010 Apr-Sep 2010 Oct-Mar 2011 Apr-Sep 2011 Oct-Mar 2012 Apr-Sep 2012 Oct-Mar 2013 Apr- Sep 2013 Oct-Mar 2014
56 hectares of CFS
As can be seen dependencies have been highlighted to emphasize the need of an integrated approach
towards capacity development at the port.
Action
Plan
• Dependencies with Free Trade Zone: Development of the free trade zone in the port area would lead to
increase in traffic within the port and an evacuation mechanism for the same should be in place at the time the
Capacity FTZ starts operation. To ensure that the dependency between the FTZ and the additional evacuation road as
Creation well as the link road to belpada has been highlighted. This would ensure that the additional traffic created has
an evacuation mechanism (through belpada)
Efficiency
improvement • Dependencies for 4th Terminal Phase 1: The phase one of the 4th terminal would add around 1000m of quay
length to the port. This would lead to increase in traffic at the port and an efficient evacuation for the same
would be required. This can be achieved through development of the dronogiri link road and the 4th terminal
Org approach road before the terminal starts operation. This has also been highlighted in the plan of action
Improvements
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
154
12.1 Plan of Action to Implement Strategy
12.1.1 Implementation schedule for infrastructure creation
• Dependencies for 4th Terminal Phase 2: The phase two of the 4th terminal would add around 1000m of quay length
to the port. This would lead to increase in traffic at the port and an efficient evacuation for the same would be
required. Apart from the road capacity increase required this would also require additional railway capacity. This can
be achieved through development of additional railway line as well as through improving efficiency of rail and road
transport (these projects have also been identified as part of the plan of action)
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
155
12.1 Plan of Action to Implement Strategy
12.2.1 Implementation schedule for process improvement
Action
Plan Exhibit 12.2.1 :Overall implementation schedule for process improvement projects
Capacity Process improvement Apr-Sep 2007 Oct-Mar 2008 Apr-Sep 2008 Oct-Mar 2009 Apr-Sep 2009 Oct-Mar 2010
Creation
Increasing shallow berth moves to 16
per hr
Efficiency
improvement Increase RMQC moves to 24 per hour
Process improvement Apr-Sep 2010 Oct-Mar 2011 Apr-Sep 2011 Oct-Mar 2012 Apr-Sep 2012 Oct-Mar 2013
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
156
12.1 Plan of Action to Implement Strategy
12.3.1 Implementation schedule for organizational improvement
Action Exhibit 12.3.1 : Overall implementation schedule for organizational improvement initiatives
Plan
Organizational improvement Apr-Sep 2007 Oct-Mar 2008 Apr-Sep 2008 Oct-Mar 2009 Apr-Sep 2009 Oct-Mar 2010
Efficiency
improvement
Org
Improvements
Organizational improvement Apr-Sep 2010 Oct-Mar 2011 Apr-Sep 2011 Oct-Mar 2012 Apr-Sep 2012 Oct-Mar 2013 Apr- Sep 2013 Oct-Mar 2014 Apr- Sep 2014
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
157
Chapter 13
Financial Plan
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
158
13.0 Introduction to Financial aspects
KPMG has developed the financials for JNPT through a systematic approach and has considered various sources of
revenue, cost centers as well as investment requirements. The major heads considered and a brief description of the
same is provided below
Investment: The total investment outlay for JNPT was considered along with the sources of finance to arrive at the
investment that would be required. These investments would come through JNPT or private operators. Investment
requirements of JNPT (public investments) were analyzed to identify the sources of the finance and the appropriate
cost of capital was used.
Revenues: The major streams for revenues that were considered are
z BOT Income: This was arrived at based on the current contracts with GTI and NSICT. For future projects it is
assumed that the revenue share would be around 20%. The upfront fee has been assumed to be zero. This is
because the amount of upfront fee that would be provided by an operator is speculative and would vary between
operators. Also any amount of upfront fee would affect the financials positively and hence to maintain
conservatism the upfront fee has been assumed to be zero.
z Estate Rentals: This is calculated based on CFS, Empty yard and other estate developments every year. The
revenues from these streams have been calculated as per TAMP guidelines.
z Marine Income: This is derived based on the traffic projections of the vessels and the expected marine charges
as per the latest information from TAMP
z JNPCT Income: Traffic from JNPCT has also been considered to arrive the JNPCT income
z Misc and Financial Income: Apart from the above income from past investments and expected future investments
(based on cash flows) have also been calculated at an average return not larger than previous returns.
Investments have been made primarily in securities, this is in line with port guidelines of investing in securities
that provide a steady cash stream with negligible risk typically provided by government securities.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
159
13.0 Introduction to Financial aspects
z Marine Costs: These costs have been derived on the basis of fixed and variable cost breakup provided by the
finance department and have been increased as per traffic and inflation depending on the nature of the cost
(fixed or variable)
z BOT Expense: This is primarily the utility costs that are borne by JNPT and then recovered from the private
operators. These costs are based on the traffic handled at the BOT operators and have been increased based on
traffic and inflationary increase.
z Financial Expense: This considers the financial expense that JNPT would have to bear and also includes the
payouts of principal and interests on loans.
z Salaries: Salaries at JNPT have been increased as per discussions and the pay commissions. Every year the
salary has been increased by 10% and at the end of the plan period salaries have been increased by 25%
Liabilities: The liabilities that have been considered are social expense, deferred liabilities, pensions etc. These have
been grown at the rate of inflation. It has been assumed that there would be no deferred tax liability once the current
liability has been adjusted for. Loans have also been considered and a moratorium of one year has been assumed.
(The payback period is taken as 5 years).
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
160
13.0 Introduction to Financial aspects
Administrative Risk:
z Risk of projects being delayed: This risk arises from a delay in project approval and implementation due to
administrative delays within and outside the port. This has the potential to adversely affect the business plan and
should be carefully monitored. KPMG has provided timelines for individual projects and these can be used to
ensure that projects are implemented on time and the administrative risk is minimized.
Trade Risk:
z Slow down in economic trade: A slowdown in economic trade can lead to overcapacity at the port although the
probability of such a scenario is limited as the traffic projections used as basis for the business plan have been
conservative. The risk of trade slowdown however has a potential to affect the business plan.
Apart from the risks detailed above the business plan faces risks within each of the individual projects. These have
been covered in the detailed action plan section.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
161
13.0 Introduction to Financial aspects
13.0.1 Assumptions
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
162
13.0 Introduction to Financial aspects
13.0.1 Assumptions
Lease rental growth for Lease rentals are grown at 5% annually as per
GTI 5% current agreement of GTI with port
@ 30%
incld 2%
Current tax rate 30.60% edu cess Current taxes paid out at this rate by JNPT
20,000.0
Fringe benefit tax 0 in 000's Assumed to be constant as per port input
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
163
13.1 Sources of Finance
13.1.1 Sources and cost of finance
The financial strategy of the port provides the guiding principles Exhibit 13.1.1 : Sources of Finance
that enable raising finance for the execution of projects in line
with the vision of the port. Identification and availability of the
Port internal resources
optimal source of financing for various projects would be critical
to the success of a port development strategy. z Investable reserves and surplus
As part of the business planning exercise, JNPT needs to External resources
undertake several developmental projects. These projects could
potentially be financed from a variety of sources. z Loan financing
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
164
13.1 Sources of Finance
13.1.1 Sources and cost of finance
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
165
13.1 Sources of Finance
13.1.1 Sources and cost of finance
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
166
13.1 Sources of Finance
13.1.1 Sources and cost of finance
b) Loan from multilateral lending agencies such as the Asian Development Bank –
JNPT has so far not used loans from multilateral funding agencies. However there has been a precedent with Asian
Development Bank(ADB) having financed specific projects at the Mumbai and Chennai port trusts. Replacement of
submarine oil pipelines along with modernization of 3 existing oil berths and pipelines was carried out at Mumbai
through funding of $97.8 million. Similarly extension of the container berth and upgradation of container yard and cargo
handling equipment at Chennai port was funded through an ADB loan of $15.2 million. The period of amortization of the
loan issued in 1997 was 25 years including a grace period of 5 years.
JNPT can opt for a long term loan from institutions like Asian Development Bank over a 5-15 year period. The loan can
be either Foreign Currency (FCY) or INR based.
Current interest rates indicate that a rupee denominated loan from ADB for a period exceeding 10 years would be
available for a fixed rate of between 9-10% per annum. The exact interest rate at which the loan would be made
available would be contingent on the structuring of the loan.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
167
13.1 Sources of Finance
13.1.1 Sources and cost of finance
c) Issue of Bonds –
JNPT had previously issued unlisted bonds of book Illustrative
value or Rs 1 million with an interest rate of 5.40% for a
period of 18 months. Total capital raised through bond
issues was Rs 55 crores. These bonds were rated as Exhibit 13.1.4 : Illustrative Bond option for JNPT
AAA and redeemed in 2005. Particulars INR Bond
Current Indian interest rates indicate that an INR bond Tenor 10 years
issued for a period of over 10 years is likely to be
available between 9- 9.5% per annum. This is 100 to
125 bps over the government bond rate of 8.16% for a All in cost (p.a.) 9.30%
10 year bond as of August 2006.
Recent regulation requires all bond issues to be listed Effective all in cost (p.a.) L + 2.14%
and this would involve additional transaction costs and
procedures.
Swapped to INR fixed (p.a.) 9.30%
JNPT can opt for issuing bonds as a method to raise
capital as illustrated in exhibit 13.1.4. JNPT can opt for Swapped to USD fixed (p.a.) 7.73%
issue of bonds from short to long term over a period of
1-10 years.
A highly rated bond issue (e.g. AAA/AA+ rating) is
likely to raise capital at slightly lower rates than bank
finance.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
168
13.1 Sources of Finance
13.1.1 Sources and cost of finance
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
169
13.1 Sources of Finance
13.1.1 Sources and cost of finance
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
170
13.1 Sources of Finance
13.1.1 Sources and cost of finance
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
171
13.1 Sources of Finance
13.1.1 Sources and cost of finance
Current BOT contracts at JNPT - Exhibit 13.1.5 : Royalty payment by NSICT to JNPT
JNPT has entered into BOT contracts with 3 Year Royalty per TEU Year Royalty per TEU
organizations NSICT, GTI and BPCL for (in Rs) (in Rs)
revenue/royalty sharing. As landlord of the port JNPT
undertakes expenses to provide these terminals with 1 0 16 2361
certain services. In return JNPT gets revenue/royalty 2 0 17 2510
shares from these operators. The details of the
3 47 18 2670
revenue agreement with each terminal are as
follows – 4 52 19 2840
• NSICT – The agreement is based on royalty per 5 143 20 3022
TEU paid to JNPT for each of the 30 years of
6 157 21 3214
the BOT contract as shown in exhibit 13.1.5.
7 349 22 2419
• BPCL – The agreement is based on royalty on
wharfage revenue. BPCL serves two kinds of 8 379 23 3638
vessels - Public sector unit vessels as well as 9 615 24 3970
private vessels. For public sector vessels 20%
is the share of wharfage revenue paid out to 10 886 25 4119
JNPT, while the share is 50% for private 11 1194 26 4380
vessels.
12 1542 27 4660
• GTI – GTI pays JNPT annual lease rentals for
13 1960 28 4957
the land occupied by it as well as 35.503% of
cargo handling revenues earned. 14 2096 29 5274
JNPT is likely to opt for the BOT model for the Discussions have indicated that the new MCA might suggest a
construction and operation of new terminals at the move from a pure revenue sharing agreement to a combination
port. The model concession agreement currently of an upfront fee and revenue sharing model. This upfront fee
suggested by the government proposes revenue would be a one-time payment by the developer at the beginning
share as a model for BOT contracts. Royalty based of the BOT period. Thus, JNPT's forthcoming BOT contracts
models seem unlikely to be used. The committee on are likely to be a combination of an upfront fee and revenue
infrastructure is currently in the process of redrafting sharing model.
the model concession agreement (MCA) for ports.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
172
13.1 Sources of Finance
13.1.1 Sources and cost of finance
Exhibit 13.1.6 : Illustration of cost of capital for Loans taken in given year
Debt-Equity Ratio 1 1 1 1 1 1
Assumptions – D/E ratio of 1, 10 year loan period, Market return of 6.5%, BOT contractor having avg. infrastructure Beta of 1
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
173
13.1 Sources of Finance
13.1.1 Sources and cost of finance
Public participative finance / Special Purpose Vehicles Exhibit 13.1.7 : Mumbai -JNPT Port Road Co Ltd SPV
Another method of execution of partnerships that has financing details
been used by JNPT is Special Purpose Vehicle (SPV) for
connectivity related projects. To ensure the rapid Particulars Rs millions Rs millions
execution and completion of main evacuation routes from
the port NH4-B and SH54-Aamra Marg, JNPT participated Equity 1460
in a SPV along with National Highways Authority of India
(NHAI), Public Works department and City and Industrial NHAI 970
Development Corporation, Navi Mumbai. The SPV “
Mumbai- JNPT Port Road Co Ltd.” was floated to execute JNPT 400
the project. The project consisted of 2 parts
• Package-I – 4 laning of NH-4B and NH4 CIDCO 90
• Package-II – 4 laning of SH-54 & construction of 4 Debt by Financial institutions 1430
lane Aamra Marg
The project has proved successful in completing widening Subordinate Debt 690
of NH-4B to 4 lanes as per schedule. The second phase
of widening of SH-54 – Aamra Marg to 4 lanes is in JNPT 600
progress and will be completed by 2007. The total project
financing was for Rs 358 crores details of which are CIDCO 90
shown in exhibit 13.1.7.
An SPV structure can be developed for implementation of Total 3580
future projects by JNPT. The exact nature of the SPV
would depend on the kind of project as well as the parties
participating in the project.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
174
13.1 Sources of Finance
13.1.1 Sources and cost of finance
2 Loans Allows initiation of large Requires governmental 9.5-10% for long term
projects that cannot be clearances and creates loan (over 10 year
independently funded by annual cash flow period)
reserves and surplus liabilities
3 Issue of Bonds Cheapest source of Requires listing of bond 9.0-9.5% for 10 year
external capital and allows issues and involves bond
initiation of large projects significant transactional
that cannot be expenses for a
independently funded by government body
reserves and surplus
4 BOT Port can create Port gets lesser Cost of capital ~13% for
infrastructure at minimal revenues from a 10 year loan with D/E
risk to own capital while financially attractive ratio of 1 and 100 bps
enjoying BOT contractor projects via-a-vis over ZCYC cost of debt
expertise financing these projects
independently
5. Partnership Finance/ Port is able to positively Financial returns of Depends on financing
SPV mode influence execution of such investments are arrangement between
projects that impact its limited to the equity players
operations share
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
175
13.1 Sources of Finance
13.2.1 Approach to be adopted for financing projects
As part of discussions during the business planning exercise, certain guiding principles have emerged for financing of
projects. It has been indicated that a preferable mode of financing for the projects would be either port resources or
private participation. Government participation for funding of these projects is unlikely as has been indicated in
discussions at various fora. The guiding principles adopted have been discussed below.
Guiding Principles -
Projects taken up as part of the business plan can be funded from internal resources or by private investment.
Projects that have a clearly identified revenue stream as well as a viable Net present value/Internal rate of return
(NPV/IRR) can potentially involve private sector participation (e.g. through BOT participation)
Projects involving creation of common-user infrastructure or projects that may not show clearly identified revenue
streams or a viable NPV/IRR are likely to be undertaken through port resources. While these projects may not show an
attractive NPV/IRR, they would still benefit the overall operations of the port
Financing method to be used for different projects –
The list of projects identified for financing are limited to those projects identified through the vision and port
development strategy of JNPT. Likely sources of financing have been identified based on guiding principles illustrated
in exhibit 13.1.9.
a) Common user infrastructure – Based on discussions at various fora, it emerged that the creation of all common
user infrastructure allowing operation of various terminal operators would be the responsibility of the port. This is also
in line with the way the landlord port model operates the world over. This common user infrastructure in the case of
JNPT includes -
• Internal connectivity projects ( Road, rail etc.)
• Dredging of main channel and JNPT channel
• Sea side handling (Towage, pilotage etc)
• Other infrastructure ( security etc.)
The financing method for common user infrastructure would depend on the presence of a viable revenue stream for
that infrastructure. As internal connectivity projects may not have a clear revenue stream unless tolled, they are
unlikely to be financed through loans /bond issues and would be funded through port internal resources.
Dredging as a project would result in revenue streams for JNPT in the form of sea side tariffs. Given the fact that
dredging is an expensive proposition JNPT is unlikely to finance the entire project from internal resources. Discussions
with port officials reveal that dredging is likely to be part funded by reserves and partly through loans.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
176
13.1 Sources of Finance
13.2.1 Approach to be adopted for financing projects
As a landlord port JNPT would continue to provide sea side services such as towage and pilotage. Purchase of
equipment and services for servicing rising number of ships are expected to be funded through port reserves and
surplus. Other common user infrastructure provided by the port such as security are likely to be funded via port internal
resources.
b) Future terminals –
Projects that have a clearly identified revenue stream as well as a viable NPV/IRR can potentially involve BOT
participation. All terminal operations would have identified traffic projections and in turn revenue flows. Hence, creation
of new terminals is likely to be through private participation via the BOT route.
c) Warehousing/CFS/free trade zones/Storage facilities –
Projects that have a clearly identified revenue stream as well as a viable NPV/IRR can potentially involve BOT
participation. All warehousing/free trade/CFS operations would be based on the traffic projected at JNPT and would
have clearly identified revenue flows. Hence, creation of warehousing/CFS/free trade zones/storage zones is likely to
be through private participation via the BOT/leasing route.
JNPT as landlord would need to develop the land prior to handing it over to private players for construction and
operation. This development has a clear stream of revenues arising from lease/revenue sharing and hence can
potentially be financed via loans/ port internal resources.
d) External connectivity projects –
JNPT is dependant on external roads/railways connecting it to the immediate hinterland. These networks are critical to
the evacuation of containers and prevention of congestion at the port. Examples of projects that can be executed as
part of this are
• Road projects in the vicinity of the port like Link roads, highways etc
• Railway lines connecting the port to key rail corridors
Stakeholders in such projects include regional land authorities and road/rail developers. Although responsibility for their
execution does not lie on the port it is advocated that they participate in such projects so as to positively influence their
timely execution. Given the multiplicity of stakeholders and the imperative of the project to JNPT, It is suggested that
JNPT participate in these projects through special purpose vehicles with other stakeholders.
d) JNPT operated container terminal –
JNPT owns and operates a container terminal (JNPCT). This terminal will require significant expense in terms of
projects for equipment upgradation/capacity expansion. As these projects are not common-user based and have
clearly identified revenue streams, it is likely that they will be funded via port internal resources or loans.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
177
13.1 Sources of Finance
13.2.1 Approach to be adopted for financing projects
1 Common user infrastructure- Combination of reserves and 9-10% (exact cost dependant on
Dredging surplus as well as bank loans proportion of finance from each
source)
2 Common user infrastructure- Reserves and Surplus Opportunity cost of capital –
Internal roads spread over GoI bond rate
3 Equipment / expense for JN Port Reserves and Surplus Opportunity cost of capital –
owned container terminal (JNPCT) spread over GoI bond rate
4 Construction and operation of Public private partnerships Cost of capital ~13% for a 10
terminals, logistics, distribution and such as BOT year loan with D/E ratio of 1 and
warehousing facilities, free trade 100 bps over ZCYC cost of debt
zones
5. Critical external road/railway Partnership Finance Depends on financing
connections arrangement between players
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
178
13.2 Overview of investments
Total investments expected in the port till 2017-18 Exhibit 13.2.1 : Investment outlay by mode of finance till
are Rs 14556 crores. Investment requirements of 2017-18
the port trust itself are Rs 4530 crore by way of
projects identified in the business plan. However Mode of finance Investment outlay
there are also investment requirements identified as (in Rs crores)*
part of the XI plan outlay internal to the port that will
be required. These include the up gradation of Port resources (Includes internal port 4530
VTMS and the creation of a new anchorage. These resources as well as external
investments as part of the XI plan amount to financing like bank loans, as also the
1398.14 crore. These investments would be port’s expected contribution to
needed in order to fund various projects for building projects undertaken through Special
infrastructure required for serving future traffic Purpose Vehicles)**
potential. These amounts are derived based on BOT/PPP route 8190
financial coverage and other analysis done for
individual projects. Public participative financing/SPV 231.7
(excluding ports contribution)
The financing requirements for upgradation and
replacement as well as costs envisaged for Other public investments 207
equipment hired and personnel costs have not
been included currently.
This outlay can be financed from the sources Other investments ( as part of XI plan 1398
detailed earlier. The approximate outlay through outlay)
each of the sources is tabulated in exhibit 13.2.1
alongside Total investments 14556
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
179
13.2 Overview of investments – Major Projects
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
180
13.2 Overview of investments – Major Projects
Total Financial Outlay
Year Name of project in Rs crore (by all Investor
parties)
Increase productivity to 24 moves per
2009-10 120 JNPT
hour
2009-10 Link road via Dronagiri 29 JNPT
2010-11 Road linking port to highways 39 JNPT
2010-11 Six laning of NH 4B 46.8 JNPT
2010-11 Sorting yard 52 JNPT
2013-14 Increase in RMGC moves 90 JNPT, Other BOT players
2014-15 Creation of additional rail track 147 Public bodies
2015-16 Dredging second phase 1300 JNPT
2016-17 Addition of RMGCs to meet capacity 43 JNPT
Creation of road from Aamra Marg to
2017-18 15 JNPT
port
Table Indicates major investments and their planned expenditure
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
181
13.2 Overview of investments – Annual outflow on projects
Annual Investments by
JNPT in various projects
(in Rs 000) 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
182
13.2 Overview of investments – Annual outflow on projects
Annual Investments by
JNPT in various projects
(in Rs 000) 2012-13 2013-14 2014-15 2015-16 2016-17 2017-18
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
183
13.2 Overview of investments – Annual outflow on projects
Annual Investments by
JNPT in
replacement/acquisition of
container equipment
projects
(in Rs 000) 2008-09 2009-10 2010-11 2011-12 2015-16
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
184
13.2 Overview of investments – Annual outflow on projects
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
185
13.3 Overview of Financial Analysis
The financial analysis of the port has been done on the basis of identified investments and projects till the term of the
action plan (2015-16). The financial projections beyond this time would change depending on the projects that the
port undertakes beyond 2015-16.
The financial analysis of the statement of accounts of the port show that the port would have a healthy CAGR
(compounded annual growth rate) of revenues and profits. The coverage ratios indicate that the port would also be
able to manage its liabilities through the cash generated by it. The output from analysis done on various parameters
is provided below.
The financial model is enclosed alongside as annexure 2.
z Profitability
JNPT is expected to maintain a high profitability. The OPM and GPM shown in Exhibit 13.6.1 indicate that on an
average JNPT would have a OPM of around 70%. This is primarily due to the fact that JNPT would earn significant
profits from revenues share which do not involve a corresponding operating expense. Similarly returns from estate
rentals would also aid in maintaining profitability.
z Revenues
JNPT’s revenue profile over the years is expected to change as can be seen in Exhibit 13.3.3. As is illustrated in the
exhibit a significant portion of the revenues would come from concession fee in the latter ears. This is because JNPTs
share of terminal traffic would decrease over the long term due to increase in total number of terminals. Currently
JNPT operates one out of the three terminals however in the latter years the number of terminals would increase to 5
but JNPT would continue to operate only one. This translates into an increase in concession fee.
The revenue profile of JNPT in the later years is representative of the revenue profile for a landlord port indicating that
JNPT would increasingly act as a landlord. This has a bearing on the skills and capabilities required for managing the
port. This has been considered and training for managerial staff has been included in the action plan.
z Expenses
The growth in expense as shown in Exhibit 13.3.4 indicate that there would be an increase in expenditure at JNPT.
As indicated in Exhibit 13.3.5, the largest increase would be in salaries followed by the increase in BOT expense.
BOT expense is primarily the utility cost of BOT operators (which is recovered from them) and therefore increases in
proportion to traffic. The initial stages (upto 2016) therefore show a larger CAGR on BOT expense as the growth in
traffic is larger till 2016 when the port achieves maximum capacity. Salaries are increased by 8% every year and 25%
increase at the end of a pay commission. The high proportion of salaries in the expense streams in later years is an
area that should be taken up for examination by the port.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
186
13.3 Overview of Financial Analysis
z Return on Capital
Return on Capital Employed at JNPT is expected to remain in the region of 30-35% over the medium to long term.
This is attractive for JNPT and investments in JNPT infrastructure are expected to provide attractive returns. The
ROCE for JNPCT is restricted by TAMP guidelines (15% ROCE limit) and a change in the TAMP guidelines could
further increase or decrease the ROCE of the port.
z Coverage
JNPT is adequately covered with respect to debt repayments. JNPT earns dollar income for marine services and
therefore is naturally hedged with respect to foreign exchange fluctuations. This provides an opportunity for JNPT to
explore the foreign capital markets for raising debts. JNPTs income from marine charges provides it with a natural
hedge for the 1300 crore loan for dredging phase 2 and the 500 Crore loan for dredging phase 1.
JNPT would pay off all its debts by 2020-21 and is expected to be adequately covered with respect to debts.
z Investments
As shown in exhibit 13.4.3, JNPT’s investments would grow at a significant pace through the years. The nature of
investments however is expected to undergo a change. It is expected that a large portion of investments in the early
years would be used for building assets (CFS, empty yard, Roads etc) while the latter years could witness a large
portion of investments being used in securities etc (assuming no other investments once the maximum capacity has
been reached except replacements).
It is also important to note that in certain years JNPT would need to liquidate some investments in securities etc to
match the cash flow requirements for investments into fixed assets. The shortfall in cash flow can be easily met by the
liquidation and would not affect the port.
Overall JNPTs investments would grow over time and the cash and bank balance as well as other investment are
expected to remain at high levels indicating JNPTs ability to meet unexpected future demands as well as planned
expansion needs.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
187
13.3 P& L Analysis
13.3.1 Increase in Revenues
z The primary source of revenue for JNPT is expected to be from concession fee. In line with the increase in traffic the marine
charges (port dues) are expected to rise.
z The suggested EPZ and other land use projects would also contribute to the revenues for JNPT. Shown below is the over all
revenue break up for JNPT between 2006 to 2027.
35,000,000
30,000,000
25,000,000
Rs in 000s
20,000,000
15,000,000
10,000,000
5,000,000
0
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2014-15
2015-16
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
2023-24
2024-25
2025-26
2026-27
Port dues Other dues (Pilotage,berth hire) Storage (at similar % age)
Wharf handling Concession fee Other operational income(estate)
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
188
13.3 P& L Analysis
13.3.1 Increase in Revenues
If the port does not develop any additional infrastructure then the capacity would be limited to the existing
traffic
30,000,000
25,000,000
20,000,000
Rs in 000s
15,000,000
10,000,000
5,000,000
0
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2014-15
2015-16
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
2023-24
2024-25
2025-26
2026-27
Port dues Other dues (Pilotage,berth hire) Storage (at similar % age)
Wharf handling Concession fee Other operational income(estate)
In the absence of infrastructure additions the revenue potential of the port in 2026-27 would be limited to around Rs 2390
crore compared to over Rs 3273 crore in the base case. Also the CAGR of revenue growth would be limited to 5.2% only.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
189
13.3 P& L Analysis
13.3.1 Increase in Revenues
Similarly the absence of supporting infrastructure would limit the growth of the port up till the 330 m only
30,000,000
25,000,000
20,000,000
Rs in 000s
15,000,000
10,000,000
5,000,000
0
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2014-15
2015-16
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
2023-24
2024-25
2025-26
2026-27
Port dues Other dues (Pilotage,berth hire) Storage (at similar % age)
Wharf handling Concession fee Other operational income(estate)
In the absence of infrastructure additions the revenue potential of the port in 2026-27 would be limited to around Rs 2491
crore compared to over Rs 3273 crore in the base case. Also the CAGR of revenue growth would be limited to around
5.5% only.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
190
13.3 P& L Analysis
13.3.1 Revenue - Comparison of Scenarios
The comparison of the above scenarios indicate that the absence of supporting infrastructure and lack of investments
at JNPT would adversely affect the growth rate and revenue potential.
An absence of supporting infrastructure such as the DFC would restrict the growth of the port to the 330 m berth and
terminal beyond the 330m might become infeasible due to absence of connectivity infrastructure. In such a scenario
the port capacity would be limited to around 5.6 Mn TEUs and the revenues would be limited to Rs 2491 Crore in the
year 2026-17 (end of twenty year period). Also the growth of revenues would be at the marginal rate of 5.5%.
If the port does not invest in infrastructure then the growth of the port would be limited to the current terminals and
additional terminals would not develop. In such a scenario the capacity of the port would be limited to 4-5 Mn TEUs.
The revenues of the port in such a scenario would also reduce to Rs 2390 crore at a slow growth of 5.2% (CAGR).
The base case assumes that the port would invest in infrastructure as per the projects identified and supporting
infrastructure would be developed as per the current plans. In such a case the port would witness a significant growth
rate of close to 8% in revenues and would reach over Rs 3273 Crore of revenues in 2026-27.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
191
13.3 P& L Analysis
13.3.2 Growth in Revenue Streams
z Estate Income and concession fee show the highest growth amongst the various revenue streams of the port. Apart from this
Marine charges also are expected to show a CAGR of over 5-6%
20.00%
15.00%
% age
10.00%
5.00%
0.00%
s
g
)
)
)
re
ue
te
in
fe
ag
dl
hi
ta
d
n
an
es
r%
rt
rth
io
Po
ss
h
e(
e
il a
rf
,b
ce
m
ha
sim
co
ge
on
W
in
ta
C
t
ilo
(a
l
na
(P
tio
ag
es
a
or
er
CAGR till 2027 CAGR till 2016
du
St
op
er
er
th
th
O
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
192
13.3 P& L Analysis
13.3.3 Revenue Split
Exhibit 13.3.5 : Revenue split at various points in time
Other dues
Revenue Split - 2016
(Pilotage,bert
Port dues h hire)
Other 3% 9% Storage
operational 1%
income(estate
)
16% Wharf
handling
19%
Concession
Revenue Split-2006 fee
Other
operational 52%
income(estat Revenue Split - 2026 Other dues
e) Port dues Other dues (Pilotage,berth
Port dues hire)
7% 5% (Pilotage,bert
2% 8% Storage
h hire) Other
Concession 1%
17% operational
fee
income(estate)
18%
14% Wharf handling
17%
Storage
4%
Concession
fee
58%
Wharf
handling
49%
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
193
13.3 P& L Analysis
13.3.4 Growth in Expenses
10,000,000.00
9,000,000.00
8,000,000.00
7,000,000.00
Rs in 000s
6,000,000.00
5,000,000.00
4,000,000.00
3,000,000.00
2,000,000.00
1,000,000.00
0.00
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2014-15
2015-16
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
2023-24
2024-25
2025-26
2026-27
Salaries Social charges and Pension premiums
Running costs (container, marine, estate) Adminstrative costs
Other costs (exp on BOT)
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
194
13.3 P& L Analysis
13.3.5 Growth in Expenses Streams
14.00%
12.00%
10.00%
% age
8.00%
6.00%
4.00%
2.00%
0.00%
Salaries Social charges and Running costs Adminstrative costs Other costs (exp on
Pension premiums (container, marine, BOT)
estate)
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
195
13.3 P& L Analysis
13.3.6 Expense Split
The high proportion of salaries in the expense streams in later years is an area that should be taken up for examination by
the port.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
196
13.3 P& L Analysis
13.3.7 Operating Profit
30,000.00
25,000.00
20,000.00
Rs in Crores
15,000.00
10,000.00
5,000.00
0.00
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2014-15
2015-16
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
2023-24
2024-25
2025-26
2026-27
Operational net earnings before depreciation, interest and tax
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
197
13.3 P& L Analysis
13.3.8 Operating Ratio (Op Expenses/ Op Revenues)
40.00%
35.00%
30.00%
25.00%
20.00%
15.00%
10.00%
5.00%
0.00%
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2014-15
2015-16
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
2023-24
2024-25
2025-26
2026-27
Operating Expense/ Operational revenue
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
198
13.3 P& L Analysis
13.3.9 Growth in Profit after tax
25000000
20000000
15000000
Rs in 000s
10000000
5000000
0
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2014-15
2015-16
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
2023-24
2024-25
2025-26
2026-27
PAT
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
199
13.4 Cash flow Analysis
13.4.1 YoY sources of funds
Loan for
Exhibit 13.4.1 : YoY Sources of Funds Dredging
Phase 2
25,000,000.00
Loan for
Dredging Phase
20,000,000.00
1
RS in Crores
15,000,000.00
10,000,000.00
5,000,000.00
0.00
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2014-15
2015-16
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
2023-24
2024-25
2025-26
2026-27
Sources of funds
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
200
13.4 Cash flow Analysis
13.4.2 YoY Loan drawdown
Loan for
Dredging
Phase 1 Loan for
Dredging
Phase 2
Exhibit 13.4.2 : Loan drawdowns
7,000,000.00
6,000,000.00
5,000,000.00
Rs in 000s
4,000,000.00
3,000,000.00
2,000,000.00
1,000,000.00
0.00
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2014-15
2015-16
2016-17
2017-18
Loans
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
201
13.4 Cash flow Analysis
13.4.3 YoY Investment breakup
16,000,000
14,000,000
12,000,000
10,000,000
Rs in 000s
8,000,000
6,000,000
4,000,000
2,000,000
-2,000,000
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2014-15
2015-16
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
2023-24
2024-25
2025-26
2026-27
Investments in fixed assets Special purpose vehicles Investments in securities Sheds to BOT
As can be seen in the graph the initial phase witnesses a huge increase in fixed asset investment due to the large number
of projects being undertaken. In the latter years this reduces and investments in securities (excess cash increases)
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
202
13.4 Cash flow Analysis
13.4.4 Repayment of Loan
800.00
700.00
600.00
Rs in Crores
500.00
400.00
300.00
200.00
100.00
0.00
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2014-15
2015-16
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
Repayment of loans
JNPT would be able to repay all its loan liabilities by the year 2020-21
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
203
13.4 Cash flow Analysis
13.4.5 YoY Balance Cash flow (Sources-Uses)
14,000,000
12,000,000
10,000,000
8,000,000
6,000,000
Rs in 000s
4,000,000
2,000,000
-2,000,000
-4,000,000
-6,000,000
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2014-15
2015-16
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
2023-24
2024-25
2025-26
2026-27
Balance flow of funds (inc in cash)
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
204
13.5 Balance Sheet Analysis
13.5.1 Total Cumulative Investments in securities
8,000.00
7,000.00
6,000.00
5,000.00
Rs in Crores
4,000.00
3,000.00
2,000.00
1,000.00
0.00
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2014-15
2015-16
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
2023-24
2024-25
2025-26
2026-27
Total Investments
As can be seen in the graph, in the initial stages the investment growth is limited due to large investments in fixed assets.
In the latter years however the growth is large due to excess cash. The reduction in 2009-10, 2010-11, 2011-12 is on
account of liquidation of investments which has been done to match the cash requirements
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
205
13.5 Balance Sheet Analysis
13.5.2 Growth in Fixed Assets
Exhibit 13.5.2 :
Growth in Fixed Assets
70,000,000.00
60,000,000.00
50,000,000.00
Rs in 000s
40,000,000.00
30,000,000.00
20,000,000.00
10,000,000.00
0.00
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2014-15
2015-16
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
2023-24
2024-25
2025-26
2026-27
Fixed assets
As can be seen in the graph, in the initial stages the investment growth leads to an asset build up. However post 2017-18
the asset build up is negligible and depreciation lead to a reduction in net asset value.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
206
13.6 Ratio Analysis
13.6.1 Gross Profit Margin and Operating profit margin
80.00%
70.00%
60.00%
50.00%
In % age
40.00%
Fall in OPM and GPM
30.00% due to decrease in
tariffs
20.00%
10.00%
0.00%
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2014-15
2015-16
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
2023-24
2024-25
2025-26
2026-27
Gross profit margin Operating Profit Margin
As can be seen in the graph, the gross profit margin for JNPT remains healthy throughout the years and is over 50%
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
207
13.6 Ratio Analysis
13.6.2 Return on Assets, ROCE and Asset Turnover
90.00%
Increase in Increase in assets
80.00%
assets (dredging phase 2)
70.00%
60.00%
In % age
50.00%
40.00%
30.00%
20.00%
10.00%
0.00%
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2014-15
2015-16
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
2023-24
2024-25
2025-26
2026-27
Return on Assets ROCE Asset Turnover
The return on asset at JNPT maintains a healthy ratio of over 30% except in years where there is a huge asset buildup or
where revenues reduce due to fall in tariffs
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
208
13.6 Ratio Analysis
13.6.3 Interest Coverage ratio & Debt Coverage Ratio
30000.00%
25000.00%
20000.00%
In % age
15000.00%
10000.00%
5000.00%
0.00%
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2014-15
2015-16
2016-17
2017-18
2018-19
2019-20
2020-21
Debt Service Coverage Ratio Interest Coverage Ratio
JNPT over the years would be able to maintain a healthy coverage ratio on debts and interests payable
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
209
13.7 Well defined key figures
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
210
Chapter 14
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
211
14.0 Overview of Action Plan
A detailed set of action plans have been created for all projects from JNPT’s perspective. These action plans outline the
following elements –
• Objective of the plan – Indicates the project to be undertaken
• Project team – Highlights departments and project responsibility at JNPT
• Key Modules - Intermediate stages of the setup phase that need to be completed sequentially
• Timelines – Typical time taken to move from one module to another as well as overall timeline
• Linkages/dependencies – These highlight potential dependencies that exist between projects to the port and
other policy making bodies. This aims to ensure successful completion of the projects on time
• Key risks – These highlight the key risks associated with a project and its impact on the port
An illustration of the format used for each individual action plan is shown in exhibit 3.0.1 indicating the elements
discussed above.
Action plans have been detailed out for projects year-wise for the 7 year plan period from 2007-08 to 2014-15. Action
plans have been organized as follows
• Development of new infrastructure
• Process improvement
• Organizational changes
A summary of all projects identified within each of the above mentioned categories along with their section and page
number for their individual action plans has been included in exhibits 3.0.2 to 3.0.4.
Action plans have been detailed out assuming that approval of business plan by the government implies a pre-
feasibility approval for projects contained in the plan. Feasibility activities post the approval of the business plan are
thus related to the detailed/ technical feasibility of the individual projects. It is logically assumed that the business plan
will come into force from the financial year 2007-08, thus requiring approval of the business plan latest by 31st March
2007. It is assumed that activities on individual plans can thus start from April 1st, 2007. Timelines taken for approval
process are estimates arrived at after discussions with port. Approval process timelines vary with the type of project as
well as investment requirements for the project.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
212
14.0 Overview of Action Plan
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
213
14.0 Overview of Action Plan
Exhibit 14.01 : Illustration of action plan Highlights the objective of
individual plans
Project Manager:
Objective ILLUSTRATIVE
Advisory Managers:
~ x months
Prerequisites / Linkages
* Not determinable– can
vary significantly, only • Prerequisites: None Allows identification of linkages and
JNPT timeline dependencies between projects,
• Linkages: None
highlights need to carry out regular
Indicates timeline of involvement of status check and ensures parallel
JNPT in the project, is the target for development of two projects with
project team at JNPT to focus on Key Risks linkages
Milestones
Highlights to policy makers and the
port the risks faced by the project
such as investment, delays,
Indicates checkpoints/ milestones
permissions etc Contd.
in the project life span
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
214
14.0 Overview of Action Plan
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
215
14.0 Overview of Action Plan
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
216
14.0 Overview of Action Plan
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
217
14.0 Overview of Action Plan
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
218
14.1 Infrastructure creation Action plan
14.1.1 Establishment of 32 hectares of CFS
~ 22 months* • Approvals granted for PMC and consultant for Request for Qualification (RFQ),
Request for Proposal (RFP) and Expression of Interest (EOI) preparation for selection
* Not determinable– can of developer
vary significantly, only
JNPT timeline
Milestones
• Board approval for hiring of
PMC and consultant
• Obtaining required permission
and clearances
• Completion of development by
contractor
• Completion of development by
developer
• Beginning of comm. operations
Contd.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
219
14.1 Infrastructure creation Action plan
14.1.1 Establishment of 32 hectares of CFS
Prerequisites / Linkages
• Prerequisites: None
• Linkages: None
Key Risks
• Delay in obtaining requisite permissions/ clearances will impact timelines and project cost
• Increase in development costs of land / delays in development can substantially reduce JNPT’s
return
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
220
14.1 Infrastructure creation Action plan
14.1.2 Creation of common user pipelines
~ 6 months* Beginning of commercial operations
Contd.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
221
14.1 Infrastructure creation Action plan
14.1.3 Establishment of 50 hectares of empty yard
~ 22 months* • Approvals granted for PMC and consultant for RFQ,RFP,EOI preparation for
selection of developer
* Not determinable– can
vary significantly, only
JNPT timeline
Milestones
• Board approval for hiring of
PMC and consultant
• Obtaining required permission
and clearances
• Completion of development by
contractor
• Completion of development by
developer
• Beginning of comm. operations
Contd.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
222
14.1 Infrastructure creation Action plan
14.1.3 Establishment of 50 hectares of empty yard
Prerequisites / Linkages
• Prerequisites: None
• Linkages: None
Key Risks
• Delay in obtaining requisite permissions/ clearances will impact timelines and project cost
• Increase in development costs of land / delays in development can substantially reduce JNPT’s
return
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
223
14.1 Infrastructure creation Action plan
14.1.4 Extension of 330 m for container operations
Project Manager:
PPD Department Objective
330 m extension for container operations (2009-10)
Advisory Managers:
Representative Finance, Key Modules
Representative Operations,
Representative Estate Initiation of project activities (April 1st 2007)
Representative NSICT Invitation for appointment of consultant for DPR (30 days)
• Framing of TOR
Bid period for consultant (45 days)
~ 15 months* Receipt and scrutiny (45 days)
• Scrutiny and approval of board
* Not determinable– can
vary significantly, only
• Scrutiny and approval of government
JNPT timeline Development of DPR (120 days)
• Identification of facilities and cost estimates
Milestones
• Development of DPR • Identification of revenue sharing mechanism
• Grant of required permission Board approval to DPR and estimates (30 days)
and clearances Obtaining requisite permissions/ clearances (126 days)
• Completion of development by
• Proposal to government for sanction expenditure for port (PIB)
developer
• Beginning of comm. operations • Government approval to estimate (CCEA)
• Simultaneously approval granted for consultant for MCA preparation
Contd.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
224
14.1 Infrastructure creation Action plan
14.1.4 Extension of 330 m for container operations
Prerequisites / Linkages
• Prerequisites: None
• Linkages: None
Key Risks
• Delay in obtaining requisite permissions/ clearances will impact timelines and project cost and
affect port’s ability to handle traffic
• Inability to arrive at an effective revenue sharing agreement might hamper the 330 m extension
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
225
14.1 Infrastructure creation Action plan
14.1.5 Establishment of grade separators
Objective
Project Manager: Establishment of an grade separators (2009-10)
PPD Department
Key Modules
Advisory Managers:
Representative Finance, Initiation of project activities (April 1st 2007)
Representative Estate
Development of DPR (90 days)
Identification of parties involved in setting up Special purpose vehicle
Identification of investment details by party as well as timelines and execution authority
~ 8 months* Identification of possible revenue streams (such as tolling)
Details of project including acquisition of land, area demarcated for the same etc
* Not determinable– can
Obtaining requisite permissions/ clearances for setting up of SPV(126 days)
vary significantly, only
JNPT timeline • Identification of team from port responsible for all negotiations with other organizations
• Identification of team from port to liaison with ministry/various agencies to ensure
Milestones
• Development of DPR clearance on schedule
• Grant of clearance/permission • Applying for requisite governmental permission (Ministry of Shipping, Transport and
• Setting up of SPV Highways)
• Grade separators made • Applications for necessary clearances from other government agencies as well as utility
operational
companies
Setting up of SPV (30 days)
Drafting of MoU with all organizations involved
Signing of MoU to bring SPV into existence
Paying out of funds to SPV Contd.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
226
14.1 Infrastructure creation Action plan
14.1.5 Establishment of grade separators
Prerequisites / Linkages
• Prerequisites: None
• Linkages: Development of FTZ would determine traffic flow through the road
Key Risks
• Delay in obtaining requisite permissions/ clearances will impact timelines and project cost
• Failure in acquiring land for the creation of separators could affect project timeline and impact
evacuation of traffic
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
227
14.1 Infrastructure creation Action plan
14.1.6 Establishment of an additional link road via Belpada
Objective
Project Manager: Establishment of an additional link road via Belpada for evacuation from JNPT (2009-
PPD Department 10)
Key Modules
Advisory Managers:
Representative Finance, Initiation of project activities (April 1st 2007)
Representative Estate
Development of DPR (90 days)
Identification of parties involved in setting up Special purpose vehicle
Identification of investment details by party as well as timelines and execution authority
~ 22 months* Identification of possible revenue streams (such as tolling)
Details of project including acquisition of land, area demarcated for the same etc
* Not determinable– can
Obtaining requisite permissions/ clearances for setting up of SPV(126 days)
vary significantly, only
JNPT timeline • Identification of team from port responsible for all negotiations with other organizations
• Identification of team from port to liaison with ministry/various agencies to ensure
Milestones
• Development of DPR clearance on schedule
• Grant of clearance/permission • Applying for requisite governmental permission (Ministry of Shipping, Transport and
• Setting up of SPV Highways)
• Road made operational • Applications for necessary clearances from other government agencies as well as utility
companies
Setting up of SPV (30 days)
Drafting of MoU with all organizations involved
Signing of MoU to bring SPV into existence
Paying out of funds to SPV Contd.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
228
14.1 Infrastructure creation Action plan
14.1.6 Establishment of an additional link road via Belpada
Prerequisites / Linkages
• Prerequisites: None
• Linkages: Development of FTZ would determine traffic flow through the road
Key Risks
• Delay in obtaining requisite permissions/ clearances will impact timelines and project cost
• Failure in acquiring land outside port boundaries by other agencies could affect project timeline
and impact evacuation of traffic
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
229
14.1 Infrastructure creation Action plan
14.1.7 Establishment of EPZ at JNPT
~ 30 months* Receipt and scrutiny (45 days)
• Scrutiny and approval of board
* Not determinable– can • Scrutiny and approval of government
vary significantly, only
JNPT timeline Development of DPR (120 days)
• Identification of potential industries/ companies for leasing of land
Milestones • Identification of strategy to attract industries to setup facilities at the EPZ
• Development of DPR
• Development of DPR for requisite clearances including leasing details and cost estimates
• Govt. approval to DPR and
estimates • Preparation of tender for hiring PMC as well as detailed engineering designs
• Selection of PMC, Consultant Board approval to DPR and estimates (30 days)
• Completion of development by Obtaining requisite permissions/ clearances (126 days)
contractor
• Proposal to government for sanction expenditure for port (PIB)
• Completion of development by
developer • Government approval to estimate (CCEA)
• Beginning of comm. operations • Simultaneously approvals granted for PMC and consultant for RFQ,RFP,EOI preparation
for selection of developer
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
230
14.1 Infrastructure creation Action plan
14.1.7 Establishment of EPZ at JNPT
Prerequisites / Linkages
• Prerequisites: None
• Linkages: Completion of development of additional link road via Belpada would be required for
evacuation from FTZ. The evacuation road via EPZ would need to be completed as well
Key Risks
• Delay in obtaining requisite permissions/ clearances will impact timelines and project cost
• Slow off take of land on lease significantly increases JNPT’s period of involvement and reduces
its return
• Increase in development costs of land / delays in development can substantially reduce JNPT’s
return
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
231
14.1 Infrastructure creation Action plan
14.1.8 Establishment of evacuation road via EPZ
Objective
Project Manager: Establishment of an evacuation road via EPZ (2009-10)
PPD Department
Key Modules
Advisory Managers:
Representative Finance, Initiation of project activities (October 1st 2007)
Representative Estate
Development of DPR (45 days)
Details of project including acquisition of land, area demarcated for the same etc
Cost estimates for construction
~ 17 months* Identification of possible revenue streams (such as tolling)
Hiring of contractor (45 days)
* Not determinable– can
• Development of criteria for selection
vary significantly, only
JNPT timeline • Invitation for bids
• Selection of contractor
Milestones Development phase (420 days)
• Development of DPR
• Leveling of land
• Hiring of contractor
• Development of road
• Completion of development
• Beginning of commercial
Operational phase
operations
• Regular operational maintenance
Contd.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
232
14.1 Infrastructure creation Action plan
14.1.8 Establishment of evacuation road via EPZ
Prerequisites / Linkages
• Prerequisites: None
• Linkages: Development of FTZ would determine traffic flow through the road
Key Risks
• Failure in acquiring land could affect project timeline and impact evacuation of traffic
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
233
14.1 Infrastructure creation Action plan
14.1.9 First stage of dredging
~ 24 months*
Milestones
• Completion of dredging
activities
* - Dredging contract is expected to be awarded by Dec 31st 2006 with dredging starting
in March 2007, sanction from govt. has already been awarded
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
234
14.1 Infrastructure creation Action plan
14.1.9 First stage of dredging
Prerequisites / Linkages
• Prerequisites: None
• Linkages: None
Key Risks
• Delay in completion of dredging activities will impact the ability of port to handle larger share of
traffic in Europe- Asia and may reduce market share
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
235
14.1 Infrastructure creation Action plan
14.1.10 Establishment of Dronagiri link road
Objective
Project Manager: Establishment of an Dronagiri link road (2009-10)
PPD Department
Key Modules
Advisory Managers:
Representative Finance, Initiation of project activities (October1st 2007)
Representative Estate
Development of DPR (45 days)
Details of project including acquisition of land, area demarcated for the same etc
Cost estimates for construction
~ 17 months* Identification of possible revenue streams (such as tolling)
Hiring of contractor (45 days)
* Not determinable– can
• Development of criteria for selection
vary significantly, only
JNPT timeline • Invitation for bids
• Selection of contractor
Milestones Development phase (420 days)
• Development of DPR
• Leveling of land
• Hiring of contractor
• Development of road
• Completion of development
• Beginning of commercial
Operational phase
operations
• Regular operational maintenance
Contd.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
236
14.1 Infrastructure creation Action plan
14.1.10 Establishment of Dronagiri link road
Prerequisites / Linkages
• Prerequisites: None
• Linkages: None
Key Risks
• Failure in acquiring land could affect project timeline and impact evacuation of traffic
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
237
14.1 Infrastructure creation Action plan
14.1.11 Establishment of 4th container terminal – phase 1
Project Manager:
PPD Department Objective
4th Container terminal Phase 1 (2010-11)
Advisory Managers:
Representative Finance, Key Modules
Representative Operations,
Representative Estate Initiation of project activities (April 1st 2007)
Representative BPCL Invitation for appointment of consultant for DPR (30 days)
• Framing of TOR
Bid period for consultant (45 days)
~ 22 months* Receipt and scrutiny (45 days)
• Scrutiny and approval of board
* Not determinable– can
vary significantly, only
• Scrutiny and approval of government
JNPT timeline Development of Finalized DPR (120 days)
• Identification of construction mechanism
Milestones
• Development of DPR • Identification of facilities and cost estimates
• Obtaining required permission • Identification of revenue sharing mechanism
and clearances Board approval to DPR and estimates (30 days)
• Signing of MCA
Obtaining requisite permissions/ clearances (126 days)
• Completion of development by
BOT developer • Proposal to government for sanction expenditure for port (PIB)
• Beginning of comm. operations • Government approval to estimate (CCEA)
• Simultaneously approval granted for consultant for MCA preparation
Contd.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
238
14.1 Infrastructure creation Action plan
14.1.11 Establishment of 4th container terminal – phase 1
Prerequisites / Linkages
Key Risks
• Delay in obtaining requisite permissions/ clearances will impact timelines and project cost and
affect port’s ability to handle traffic
• 4th container terminal may not be able to attract traffic from the north if DFC is not in place in
time
* - Not part of JNPT timeline
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
239
14.1 Infrastructure creation Action plan
14.1.12 Road linking port and highways
Objective
Project Manager: Establishment of an road linking the port to highways (2010-11)
PPD Department
Key Modules
Advisory Managers:
Representative Finance, Initiation of project activities (October 1st 2008)
Representative Estate
Development of DPR (45 days)
Details of project including acquisition of land, area demarcated for the same etc
Cost estimates for construction
~ 17 months* Identification of possible revenue streams (such as tolling)
Hiring of contractor (45 days)
* Not determinable– can
• Development of criteria for selection
vary significantly, only
JNPT timeline • Invitation for bids
• Selection of contractor
Milestones Development phase (420 days)
• Development of DPR
• Leveling of land
• Hiring of contractor
• Development of road
• Completion of road
development
Operational phase
• Beginning of commercial
• Regular operational maintenance
operations
Contd.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
240
14.1 Infrastructure creation Action plan
14.1.12 Road linking port and highways
Prerequisites / Linkages
• Prerequisites: None
• Linkages: None
Key Risks
• Failure in acquiring land could affect project timeline and impact evacuation of traffic
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
241
14.1 Infrastructure creation Action plan
14.1.13 Establishment of link road to 4th container terminal
Objective
Project Manager: Establishment of a link road to 4th container terminal (2010-11)
PPD Department
Key Modules
Advisory Managers:
Representative Finance, Initiation of project activities (October 1st 2008)
Representative Estate
Development of DPR (45 days)
Details of project including acquisition of land, area demarcated for the same etc
Cost estimates for construction
~ 17 months* Identification of possible revenue streams (such as tolling)
Hiring of contractor (45 days)
* Not determinable– can
• Development of criteria for selection
vary significantly, only
JNPT timeline • Invitation for bids
• Selection of contractor
Milestones Development phase (420 days)
• Development of DPR
• Leveling of land
• Hiring of contractor
• Development of road
• Completion of development
• Beginning of commercial
Operational phase
operations
• Regular operational maintenance
Contd.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
242
14.1 Infrastructure creation Action plan
14.1.13 Establishment of link road to 4th container terminal
Prerequisites / Linkages
• Prerequisites: None
• Linkages: Traffic flow on this road will be linked to completion of 4th container terminal
Key Risks
• Failure in acquiring land could affect project timeline and impact evacuation of traffic
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
243
14.1 Infrastructure creation Action plan
14.1.14 Six laning of NH 4B
Objective
Project Manager: 6 laning of NH 4B (20010-11)
PPD Department
Key Modules
Advisory Managers:
Representative Finance, Initiation of project activities (April 1st 2008)
Representative Estate
Development of DPR (90 days)
Identification of parties involved in setting up Special purpose vehicle
Identification of investment details by party as well as timelines and execution authority
~ 8 months* Identification of possible revenue streams (such as tolling)
Details of project including acquisition of land, area demarcated for the same etc
* Not determinable– can
Obtaining requisite permissions/ clearances for setting up of SPV(126 days)
vary significantly, only
JNPT timeline • Identification of team from port responsible for all negotiations with other organizations
• Identification of team from port to liaison with ministry/various agencies to ensure
Milestones
• Development of DPR clearance on schedule
• Grant of clearance/permission • Applying for requisite governmental permission (Ministry of Shipping, Transport and
• Setting up of SPV Highways)
• Road beginning commercial • Applications for necessary clearances from other government agencies as well as utility
operations
companies
Setting up of SPV (30 days)
Drafting of MoU with all organizations involved
Signing of MoU to bring SPV into existence
Paying out of funds to SPV Contd.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
244
14.1 Infrastructure creation Action plan
14.1.14 Six laning of NH 4B
Prerequisites / Linkages
• Prerequisites: None
• Linkages: Development of FTZ would determine traffic flow through the road
Key Risks
• Delay in obtaining requisite permissions/ clearances will impact timelines and project cost
• Failure in acquiring land outside port boundaries by other agencies could affect project timeline
and impact evacuation of traffic
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
245
14.1 Infrastructure creation Action plan
14.1.15 Sorting yard for rail operations
Objective
Project Manager: Establishment of a sorting yard (2010-11)
PPD Department
Key Modules
Advisory Managers:
Representative Finance, Initiation of project activities (April 1st 2008)
Representative Estate
Representative Operations Development of DPR (45 days)
Details of project including acquisition of land, area demarcated for the same etc
Cost estimates for construction
~ 17 months* Identification of possible revenue streams (such as charges for handling CFS containers)
Hiring of contractor (45 days)
* Not determinable– can
• Development of criteria for selection
vary significantly, only
JNPT timeline • Invitation for bids
• Selection of contractor
Milestones Development phase (420 days)
• Development of DPR
• Leveling of land
• Hiring of contractor
• Procurement of equipment
• Completion of development
• Development of tracks
• Beginning of commercial
Operational phase
operations
• Regular operational maintenance
Contd.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
246
14.1 Infrastructure creation Action plan
14.1.15 Sorting yard for rail operations
Prerequisites / Linkages
• Prerequisites: None
• Linkages: None
Key Risks
• Delay in setting up of sorting yard will impact the handling of containers in the port and lead to
increase in number of mixed trains
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
247
14.1 Infrastructure creation Action plan
14.1.16 Establishment of marine chemical berth
Project Manager:
PPD Department Objective
Establishment of Marine chemical berth (2011-12)
Advisory Managers:
Representative Finance, Key Modules
Representative Operations,
Representative Estate Initiation of project activities (April 1st 2008)
Representative BPCL Invitation for appointment of consultant for DPR (30 days)
• Framing of TOR
Bid period for consultant (45 days)
~ 22 months* Receipt and scrutiny (45 days)
• Scrutiny and approval of board
* Not determinable– can
vary significantly, only
• Scrutiny and approval of government
JNPT timeline Development of Finalized DPR (120 days)
• Identification of construction mechanism
Milestones
• Development of DPR • Identification of facilities and cost estimates
• Obtaining required permission • Identification of revenue sharing mechanism
and clearances Board approval to DPR and estimates (30 days)
• Signing of MCA
Obtaining requisite permissions/ clearances (126 days)
• Completion of development by
developer • Proposal to government for sanction expenditure for port (PIB)
• Beginning of comm. operations • Government approval to estimate (CCEA)
• Simultaneously approval granted for consultant for MCA preparation
Contd.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
248
14.1 Infrastructure creation Action plan
14.1.16 Establishment of marine chemical berth
Prerequisites / Linkages
Key Risks
• Delay in obtaining requisite permissions/ clearances will impact timelines and project cost and
affect port’s ability to handle traffic
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
249
14.1 Infrastructure creation Action plan
14.1.17 Establishment of 56 hectares of CFS
~ 22 months* • Approvals granted for PMC and consultant for RFQ,RFP,EOI preparation for
selection of developer
* Not determinable– can
vary significantly, only
JNPT timeline
Milestones
• Board approval for hiring of
PMC and consultant
• Obtaining required permission
and clearances
• Completion of development by
contractor
• Completion of development by
developer
• Beginning of comm. operations
Contd.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
250
14.1 Infrastructure creation Action plan
14.1.17 Establishment of 56 hectares of CFS
Prerequisites / Linkages
• Prerequisites: None
• Linkages: None
Key Risks
• Delay in obtaining requisite permissions/ clearances will impact timelines and project cost
• Increase in development costs of land / delays in development can substantially reduce JNPT’s
return
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
251
14.1 Infrastructure creation Action plan
14.1.18 Establishment of 50 hectares of empty yard
~ 22 months* • Approvals granted for PMC and consultant for RFQ,RFP,EOI preparation for
selection of developer
* Not determinable– can
vary significantly, only
JNPT timeline
Milestones
• Board approval for hiring of
PMC and consultant
• Obtaining required permission
and clearances
• Completion of development by
contractor
• Completion of development by
developer
• Beginning of comm. operations
Contd.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
252
14.1 Infrastructure creation Action plan
14.1.18 Establishment of 50 hectares of empty yard
Prerequisites / Linkages
• Prerequisites: None
• Linkages: None
Key Risks
• Delay in obtaining requisite permissions/ clearances will impact timelines and project cost
• Increase in development costs of land / delays in development can substantially reduce JNPT’s
return
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
253
14.1 Infrastructure creation Action plan
14.1.19 Additional rail track outside port
Objective
Project Manager: Establishment of a additional rail track outside port (2014-15)
PPD Department
Key Modules
Advisory Managers:
Representative Finance, Initiation of project activities (April 1st 2013)
Representative Estate Development of DPR * (90 days)
Representative Operations
Details of project including acquisition of land, area demarcated for the same etc
Cost estimates for construction
Identification of possible revenue streams (such as charges for handling CFS containers)
~ 17 months*
Hiring of contractor * (45 days)
* Not determinable– can • Development of criteria for selection
vary significantly • Invitation for bids
• Selection of contractor
Milestones Development phase * (420 days)
• Development of DPR • Leveling of land
• Hiring of contractor • Procurement of equipment
• Completion of development
• Development of tracks
• Beginning of commercial
operations Operational phase *
• Regular operational maintenance
Contd.
* - Not part of JNPT timeline as development of rail track is under
purview of Indian railways
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
254
14.1 Infrastructure creation Action plan
14.1.19 Additional rail track outside port
Prerequisites / Linkages
• Prerequisites: None
• Linkages: Establishment of sorting yard
Key Risks
• Delay in setting up of additional track will impact the handling of containers in the port and limit
traffic to the 4 container terminals
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
255
14.1 Infrastructure creation Action plan
14.1.20 Establishment of 4th container terminal – phase 2
Project Manager:
PPD Department Objective
4th Container terminal Phase 2 (2014-15)
Advisory Managers:
Representative Finance, Key Modules
Representative Operations,
Representative Estate Initiation of project activities (April 1st 2011)
Invitation for appointment of consultant for DPR (30 days)
• Framing of TOR
Bid period for consultant (45 days)
~ 22 months* Receipt and scrutiny (45 days)
• Scrutiny and approval of board
* Not determinable– can
vary significantly, only
• Scrutiny and approval of government
JNPT timeline Development of Finalized DPR (120 days)
• Identification of construction mechanism
Milestones
• Development of DPR • Identification of facilities and cost estimates
• Obtaining required permission • Identification of revenue sharing mechanism
and clearances Board approval to DPR and estimates (30 days)
• Signing of MCA
Obtaining requisite permissions/ clearances (126 days)
• Completion of development by
developer • Proposal to government for sanction expenditure for port (PIB)
• Beginning of comm. operations • Government approval to estimate (CCEA)
• Simultaneously approval granted for consultant for MCA preparation
Contd.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
256
14.1 Infrastructure creation Action plan
14.1.20 Establishment of 4th container terminal – phase 2
Prerequisites / Linkages
• Prerequisites: None
• Linkages: The set up of the additional rail track will be imperative for traffic to be efficiently
handled at the 4th container terminal phase 2.
Key Risks
• Delay in obtaining requisite permissions/ clearances will impact timelines and project cost and
affect port’s ability to handle traffic
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
257
14.1 Infrastructure creation Action plan
14.1.21 Creation of emergency berth
~ 28 months* Receipt and scrutiny (45 days)
• Scrutiny and approval of board
* Not determinable– can • Scrutiny and approval of government
vary significantly, only
JNPT timeline Development of DPR (45 days)
• Development of DPR for requisite clearances including cost estimates
• Details of project including area, construction mechanism
Milestones • Preparation of tender for hiring PMC as well as detailed engineering designs
• Development of DPR
Board approval to DPR and estimates (30 days)
• Govt. approval to DPR and
estimates Obtaining requisite permissions/ clearances (126 days)
• Selection of PMC • Proposal to government for sanction expenditure for port (PIB)
• Completion of development by • Government approval to estimate (CCEA)
contractor
• Simultaneously approvals granted for Project management consultant (PMC)
• Beginning of operations
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
258
14.1 Infrastructure creation Action plan
14.1.21 Creation of emergency berth
Prerequisites / Linkages
• Prerequisites: None
• Linkages: None
Key Risks
• Delay in obtaining requisite permissions/ clearances will impact timelines and project cost
• Increase in development costs of berth vs. utilization expected could significantly impact viability
of project and needs to be carefully analysed
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
259
14.2 Process improvement Action plan
14.2.1 Increasing shallow berth moves to 16 per hour
Project Manager:
Operations department Objective
Increasing shallow berth moves to 16 per hour (2008-09)
Advisory Managers:
Representative Finance, Key Modules
Representative PPD,
Representative Estate Initiation of project activities (October 1st 2008)
Identification of requirements and estimate of construction costs (30 days)
Board approval to estimates and shifting (30 days)
Hiring of contractor (45 days)
~ 6 months* • Development of criteria for selection
• Invitation for bids
* Not determinable– can • Selection of contractor
vary significantly, only
JNPT timeline Operations / Shifting phase * (90 days)
Shifting of RMQC from container berth
Milestones
Fine-tuning of operations
• Hiring of contractor
• Shifting of equipment Beginning of operations
• Beginning of comm. operations
Prerequisites / Linkages
• Prerequisites: None
• Linkages: None
Key Risks
• Delay in shifting equipment will impact the port’s ability to handle traffic in the initial
years of the plan period
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
260
14.2 Process improvement Action plan
14.2.2 Increasing RMQC moves to 24 per hour
Project Manager:
Operations department Objective
Increasing main berth container moves to 24 per hour (2009-10)
Advisory Managers:
Representative Finance, Key Modules
Representative PPD,
Representative Estate Initiation of project activities (October 1st 2009)
Identification of requirements and estimate of construction costs (30 days)
Board approval to estimates (30 days)
Hiring of contractor (45 days)
~ 6 months*
• Development of criteria for selection
* Not determinable– can • Invitation for bids
vary significantly, only • Selection of contractor
JNPT timeline
Operations phase * (90 days)
Milestones Procurement of new equipment
• Hiring of contractor Installation of new equipment
• Shifting of equipment Fine-tuning of operations
• Beginning of comm. operations
Beginning of operations
Prerequisites / Linkages
• Prerequisites: None
• Linkages: None
Key Risks
• Delay in increasing moves per hour will impact the port’s ability to meet market
demands
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
261
14.2 Process improvement Action plan
14.2.3 Automation between gate and terminal operators
Project Manager:
IT(MS) Department Objective
Automation between gate and terminal operators (2008-09)
Advisory Managers:
Representative Finance, Key Modules
Representative Operations,
Representative Estate Initiation of project activities (April 1st 2007)
Representative PPD Invitation for appointment of consultant for estimating requirements (30 days)
• Framing of requirements
Bid period for consultant (45 days)
Receipt and scrutiny (45 days)
~ 23 months*
• Scrutiny and approval of port
* Not determinable– can Development of requirements and estimate (90 days)
vary significantly, only
JNPT timeline
• Identification of automation requirements
• Identification of automation/ IT estimates
Milestones • Identification of structure to implement automation
• Hiring of consultant
Board approval to requirements and estimates (30 days)
• Board approval of estimates
• Hiring of firm to deploy Hiring of IT services firm to implement automation (45 days)
automation solution • Development of criteria for selection
• Deployment of automation • Invitation for bids
solution
• Selection of contractor
Development of IT solution for automation in the port, terminals and gates (400 days)
• Development of comprehensive automation solution
• Deployment of solution in port
• Training of port personnel
• Fine-tuning post deployment
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
262
14.2 Process improvement Action plan
14.2.3 Automation between gate and terminal operators
Prerequisites / Linkages
• Prerequisites: None
• Linkages: None
Key Risks
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
263
14.2 Process improvement Action plan
14.2.4 Increasing RMGC moves to 20 per hour
Project Manager:
Operations department Objective
Increasing RMGC moves to 20 per hour (2009-10)
Advisory Managers:
Representative Finance, Key Modules
Representative PPD,
Representative Estate Initiation of project activities (October 1st 2013)
Beginning of process --- October 2013 ----
Identification of requirements and estimate of construction costs (30 days)
Board approval to estimates (30 days)
~ 6 months*
Hiring of contractor (45 days)
* Not determinable– can • Development of criteria for selection
vary significantly, only
• Invitation for bids
JNPT timeline
• Selection of contractor
Milestones Operations phase * (90 days)
• Hiring of contractor Procurement of new equipment
• Shifting of equipment
Installation of new equipment
• Beginning of comm. operations
Fine-tuning of operations
Prerequisites
Beginning of operations
/ Linkages
• Prerequisites: None
• Linkages: None
Key Risks
• Delay in increasing moves per hour will impact the port’s ability to handle transportation
of containers by rail
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
264
14.2 Process improvement Action plan
14.2.5 Automation between sorting yard and port
Project Manager:
IT(MS) Department Objective
Automation between sorting yard and port (2013-14)
Advisory Managers:
Representative Finance, Key Modules
Representative Operations,
Representative Estate Initiation of project activities (April 1st 2011)
Representative PPD Invitation for appointment of consultant for estimating requirements (30 days)
• Framing of requirements
Bid period for consultant (45 days)
~ 23 months* Receipt and scrutiny (45 days)
• Scrutiny and approval of port
* Not determinable– can Development of requirements and estimate (90 days)
vary significantly, only
JNPT timeline • Identification of automation requirements
• Identification of automation/ IT estimates
Milestones
• Identification of structure to implement automation
• Hiring of consultant
• Board approval of estimates Board approval to requirements and estimates (30 days)
• Hiring of firm to deploy Hiring of IT services firm to implement automation (45 days)
automation solution • Development of criteria for selection
• Deployment of automation
• Invitation for bids
solution
• Selection of contractor
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
265
14.3 Organizational improvement Action plan
14.3.1 Strengthening of marketing dept.
Project Manager:
Administration/HR Objective
department
Strengthening of marketing dept. (2009-10)
~ 11 months* • Identification of no. of personnel along with pay scales
Board approval to DPR and estimates (30 days)
* Not determinable– can Obtaining requisite permissions/ clearances (126 days)
vary significantly, only
JNPT timeline • Proposal to government for sanction expenditure for port (PIB)
• Government approval to estimate (CCEA)
Milestones
Hiring of personnel (60 days)
• Development requirements for
marketing dept. • Hiring of adequate personnel
• Board approval to hiring • Beginning of operations of marketing cell
• Govt. approval to hiring
• Beginning of operations of
marketing cell Prerequisites / Linkages
• Prerequisites: None
• Linkages: None
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
266
14.3 Organizational improvement Action plan
14.3.2 Strengthening of project management capabilities
Project Manager:
PPD Department Objective
Strengthening of project management capabilities (2009-10)
Advisory Managers:
Representative Finance, Key Modules
Representative
Administration/HR Initiation of project activities (April 1st 2009)
Development of Requirements for project mgmt. (120 days)
• Identification of need for strengthening of project mgmt. capabilities
• Identification of qualifications of personnel
~ 11 months* • Identification of no. of personnel along with pay scales
Board approval to DPR and estimates (30 days)
* Not determinable– can
vary significantly, only
Obtaining requisite permissions/ clearances (126 days)
JNPT timeline • Proposal to government for sanction expenditure for port (PIB)
• Government approval to estimate (CCEA)
Milestones
• Development requirements for Hiring of personnel (60 days)
project management • Hiring of adequate personnel
capabilities
• Board approval to hiring
• Govt. approval to hiring Prerequisites / Linkages
• Beginning of operations of
marketing cell • Prerequisites: None
• Linkages: None
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
267
14.3 Organizational improvement Action plan
14.3.2 Development of maintenance SLA for roads
Objective
Project Manager: Establishment of maintenance SLA for the roads around JNPT (2013-14)
PPD Department
Key Modules
Advisory Managers:
Representative Finance, Initiation of project activities (April 1st 2012)
Representative Estate
Development of DPR (45 days)
Identification of parties involved in the SLA
Identification of payment for services rendered
~ 6 months* Obtaining board approval for entering into SLA ( 30 days)
Development of SLA (75 days)
* Not determinable– can
• Identification of team from port responsible for all negotiations with other organizations
vary significantly, only
JNPT timeline • Development of SLA in conjunction with other organizations (NHAI, PWD)
Signing of SLA (30 days)
Milestones
• Development of DPR Signing of SLA by all organizations
• Development of SLA
• Signing of SLA
Prerequisites / Linkages
• Prerequisites: None
• Linkages: None
Key Risks
• Delay in setting up of SLA will impact the quality of roads and cause congestion around
port
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
268
Annexure 1
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
269
Annexure 1.1
Impact of VAT and the future of CFS
z The introduction of VAT can lead to changes in the logistics and distribution industry in India. Indian retailers and
manufacturers have been following a distribution and warehousing model wherein a warehouse or distribution centre
was setup in almost every state to cater to demand.
z This was primarily done to avoid the disparate taxes that existed between states and hence movement between
states could lead to extra taxes. Large scale warehousing and distribution in India was therefore sub optimal
z However the introduction of VAT has led to the possibility of players setting up large scale distribution hubs. These
hubs would require 3PL operators or SCM personnel for their management and support. Many players international
and domestic have already entered the sector. Examples include Reliance, Tata, Mahindra and Mahindra, TVS
Group and Essar Shipping apart from this Bluedart Safexpress have also entered the logistics market
z The logistics framework near the ports would also undergo some changes as a result of the growth in the logistics
industry. It is expected that CFS would continue to play an important role however the nature of their role would
change. Currently the CFS provides custom clearance as its core service while in the future the CFS would become
an integral part of the supply chain and would take care of warehousing and distribution needs as well.
z There exists a possibility that CFSs may further move inland as road and rail connectivity improves. This has been
considered in the projections and only 50-60% of the actual CFS demand has been developed within the port. This
ensures that the CFS development within the port considers the possibility of CFS moving inland.
z CFS moving inland fundamentally depend on two issues in the Indian context –
z Availability of customs officials in areas further inland – In the Indian context where availability of customs
officials is limited, clustering of several CFS happens in areas where customs officials are available. This tends
to be in areas around the port.
z Aggregation/ De-aggregation requirements of area – JNPT’s captive hinterland of Maharashtra has a large
proportion of LCL cargo that originates or is destined for these areas. It is easier to aggregate/de-aggregate at
the port as compared to inland areas of the state. This is because CFS operators can aggregate LCL cargoes
from different parts of the state arriving at various points in time easiest at the point of departure.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
270
Annexure 1.2
Detailed assessment of opportunities – Liquid cargo
Liquid traffic The forecasts for liquid traffic as shown below were used to assess the opportunity. A detailed set of forecasts
forecast are covered in Section 2.2.
18.0
15.4
16.0
14.0
13.5
14.0 13.1
12.8
in Million tonnes per annum
11.1 11.4
12.0 10.7
10.1 10.4
5.2 5.5 \
6.0 4.7 5.0
3.3 3.5
4.0
2.0
0.0
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2014-15
2015-16
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
2023-24
2024-25
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
271
Annexure 1.2
Detailed assessment of opportunities – Liquid cargo
Assessment of Liquid Cargo opportunity
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
272
Annexure 1.2
Detailed assessment of opportunities – Containers
The forecasts for container traffic as shown below was used to assess the opportunity. A detailed set of forecasts
are covered in Section 2.2. The dotted line indicates the potential saturation in terms of capacity at JNPT after all
development activities are undertaken.
30.00
25.45
25.00 24.21
22.70
21.29
19.98
20.00 18.76
17.63
16.32
14.65
15.00
13.34
Mn TEUs
12.11
11.00
9.95 10.9 Million TEU’s
10.00 8.75
7.70
6.75
5.93
5.19
4.43
5.00 3.77
3.22
2.68
0.00
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
2011-12
2012-13
2013-14
2014-15
2015-16
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
2022-23
2023-24
2024-25
2025-26
2026-27
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
273
Annexure 1.2
Detailed assessment of opportunities – Containers
The states that constitute JNPT's hinterland currently send significant proportions of the traffic to JNPT. With the
increase in development of other ports in the western region, it is expected these other ports will attract a portion of
northern traffic thus reducing the share coming to JNPT. The percentages of traffic expected from various states to
JNPT as shown below are arrived at from a qualitative gravity model and discussions with importers/exporters and
shipping agents.
Maharashtra 90 % 80 %
Uttaranchal 80% 40 %
Delhi 75 % 40 %
Punjab 80 % 40 %
Andhra Pradesh 10 % 5%
Karnataka 37 % 5%
Gujarat 60 % 10 %
Madhya Pradesh 60 % 40 %
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
274
Annexure 1.2
Detailed assessment of opportunities – Containers
Assessment of Container opportunity
Strength & Weakness Revenue Potential
Strength - Revenue potential is expected to be around (assuming a
JNPT has significant competencies in handling container traffic conservative Rs 2000/TEU) Rs 1100 crore in 2009-10
on a large scale Out of this the revenue from Non Maharashtra region is
Weaknesses - expected to be around Rs 345 Cr in 2009-10
JNPT will face increasing competition for northern traffic
The limited space for sea side expansion may limit the Revenue potential of the opportunity is expected to be high
opportunity
The trans-shipment opportunity was assessed by JNPT as part of the overall opportunity assessment landscape for the
vision exercise
Opportunity description
There is an export import imbalance between Mid-East Europe trade. The ships returning from Mid East are mostly
empty and this can create transshipment opportunities for JNPT. JNPT can act as the regional hub where cargo
destined for Mid East and Karachi arrives and this cargo is then transshipped via feeder vessels to its destination.
The UNESCAP model for transshipment projects around 9 Million TEU of trans-shipment traffic to be generated in
South Asia. If Europe Asia route generates around 40% (3.6 Mn TEU) of this traffic then the traffic potential for
transshipment is around 3.5 Million TEUs.
This Transshipment traffic of 3.6 Million TEUs on the Europe Asia route would be primarily distributed between ports of
Western India, Karachi and Salalah.
The transshipment traffic at the Western ports is expected to be low because of
• Distance from the Major shipping routes
• High sea side costs
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
276
Annexure 1.2
Detailed assessment of opportunities – Transshipment
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
277
Annexure 1.2
Detailed assessment of opportunities – Transshipment
Stability
Growth
The transhipment traffic depends primarily on shipping costs
The traffic is expected to grow at a CAGR of around 7 – 8% for
and any changes in tariffs of competing ports can affect the
the next 20 years in the South Asian region
stability of the revenues
z The growth potential of the opportunity is below 10% and is
Due to the unstable nature of the revenues stability has been
rated as medium
rated as medium
Projects Required
Reduction in tariffs to become competitive with international ports competing for transshipment traffic
Value added services to counter the additional cost of deviation such as speedier turn around times (at least 20-25% better than
Salalah and other ports)
Increase in infrastructure on Sea-side to accommodate larger vessels
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
278
Annexure 1.2
Detailed assessment of opportunities – Free trade zone/Export processing zone
Opportunity Description
• Maharashtra is one of the economic power houses of India and is a large consumption as well as production base.
Maharashtra’s strength in consumption and production can be gauged from the following:
• The Special Economic Zone ("SEZ") Policy, announced by GoI enables the creation of SEZs in the country to
provide competitive and conducive environment for exports.
• Maharashtra has more than 23,000 working factories and nearly 1 million factory workers with 94 major industrial
estates
• Maharashtra’s per capita gross output is 2.5 times the national average and per capita income is more than the
national average.
• Maharashtra contributes upto 22% of country's net value added and 30% of software.
• Maharashtra received investment worth Rs. 1,686 billion (around USD 33 billion) and 392 foreign direct
investment proposals worth Rs 94.6 billion. UK, Italy, France, Germany and Mauritius are major investors in the
state
• One of the largest SEZs in India is being set-up in Navi Mumbai and is spread over 50 square kilometers
The growth in Maharashtra is supported by conducive policies of the Government as well as foreign direct investment
in the state. Due to these reasons there is an opportunity in Maharashtra to setup a logistics focussed processing
zone. This could be in the form of a distribution hub, EPZ, FTZ etc. The absence of any such hub in the vicinity
presently also increases the attractiveness of such an opportunity
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
279
Annexure 1.2
Detailed assessment of opportunities – Free trade zone/Export processing zone
Projects Required
Development of connectivity between FTZ/EPZ and port
Extension of port network to the FTZ/EPZ
Development of dry port to handle traffic generated by FTZ/EPZ
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
280
Annexure 1.2
Detailed assessment of opportunities – Distribution hub/ logistics hub
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
281
Annexure 1.2
Detailed assessment of opportunities – Distribution hub/ logistics hub
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
282
Annexure 1.2
Detailed assessment of opportunities – Distribution hub/ logistics hub
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
283
Annexure 1.2
Detailed assessment of opportunities – Distribution hub/ logistics hub
Globally industries have set up Import Distribution centers (IDC) close to ports. Importers in US have an import
processing centre near the port which further distributes the goods to various regional distribution centers in the country
above.
These IDC’s function primarily as
• Warehouses
• Destuffing Centers
JNPT has a locational advantage to serve as an IDC and, with the entry of players such as Walmart and the projected
boom in the retail segment (Reliance etc), can evaluate opportunities in developing IDC near the port which will help in
• Generating Revenues
• Retaining and attracting traffic
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
284
Annexure 1.2
Detailed assessment of opportunities – Distribution hub/ logistics hub
Revenue Potential
JNPT's Strength & Weakness Estimated revenue potential for land used for distribution could
JNPT has a locational advantage to serve as a distribution hub be Rs 2.2* Crores per built up hectare of land.
JNPT can make land available (670 hectares) to exploit such an Assuming a 40 hectare built up area the revenue could around
opportunity Rs 80 Crores
JNPT lies close to major consumption centers such as This does not include revenues that will occur due to additional
Maharashtra traffic attracted by such a hub.
*This could be higher incase JNPT develops and executes the
Due to JNPT's inherent advantages, the strengths in the hub itself instead of leasing land to a third party
opportunity were rated as High The revenue potential from this opportunity is above 100
Crores and is therefore rated as medium
Stability
Growth
The revenue is expected to be stable as it is directly related to
Although the growth rate of the logistics industry is high JNPT's
India’s export and import trade which is expected to be stable
revenue from such an opportunity would be driven by rentals
over the medium term
and therefore would be fixed in nature.
Due to the stable nature of the revenues and the stable
Due to the fixed nature of the revenues the growth has
predictions for the hinterland this has been rated medium
been rated as low
to high
Projects Required
Development of land with utilities
Tie up with 3PL and directly with large importers (retailers etc) and specific industries such as machinery/ textiles.
Increase in automation – Port net extended to the warehouse
Rail and road connectivity to the warehouse
Bonded warehousing setup within the facility
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
285
Annexure 1.2
Detailed assessment of opportunities – Distribution hub/ logistics hub
Distribution Hub
distribution hub. However the logistics hub would be
broader in its scope by encompassing warehousing,
distribution, packaging and assembly.
Warehousing
Due to its broader nature JNPT can target specific
industries and retain their traffic. Some of the industries
that are expected to witness a growth in export/imports
Logistics Hub
are: Distribution
Machinery
FTZ
•
• Textiles
• Consumer goods Packaging
• Food processing
These industries can be targeted by JNPT to generate
captive traffic.
Assembly
Similarly, JNPT can attract and retain northern traffic by
introducing value added services for specific industries in
the north (automobile, textiles etc) .
Manufacturing
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
286
Annexure 1.2
Detailed assessment of opportunities – Distribution hub/ logistics hub
Distriparks at the Port of Rotterdam as seen below are advanced logistics parks having -
Case Study: Value
added Services – • Facilities for distribution operations at a single location close to the cargo terminals
Distriparks at Port
• Multimodal transport facilities for transit shipment
of Rotterdam
• Latest information and communications technology
Distriparks offer broadly two sets of services -
• Warehousing and forwarding facilities (including storage/stuffing/stripping of containers)
• Value added services – processing of goods according to specific customer and country-of-destination
requirements, packing and re-packing, labeling and assembly, sorting and invoicing
Warehousing &
Botlek Distripark Prologis en DHL/Exel ,
distribution
1990 165 Damco Maritime,
companies with a
Holland Veem
chemical focus
Maasvlakte Centralized
1st phase - 1988 848 Reebok, Epson,
Distripark warehousing and
Nippon Express,
2nd phase - 1998 1017 distribution with a
Canon
container focus
Total 2267
Reebok’s state-of-the-art logistics centre in Rotterdam illustrates how a value-added service generated employment for
Case Study: Value
300 personnel and contributing $6 million in direct income was created
added services –
Alliance between
Port of Rotterdam Restructuring of Reebok’s logistics activities
and Reebok In 1995, Reebok decided that warehousing and distribution activities in Europe should be consolidated. Instead of
separate warehousing facilities, a bulk logistics facility would be established in mainland Europe to supply pick-and-
pack warehouses in the U.K. and Spain, as well as directly supply other markets in Europe
80-90% of product flow to the European market would pass through this logistics centre. After considering France and
Belgium, Reebok decided to locate the logistics centre at newly created Distripark 3 in Maasvlakte at the ocean edge of
the port property.
The Port along with the municipality, proactively pursued Reebok and provided strong incentives to locate the facility in
Maasvlakte such as the following –
• The port funded construction of the state-of-the-art 700,000 sq. ft. logistics facility.
• Port created infrastructure to connect the facility to the adjacent container terminal
• Transport bus service in line with the plant shift system
• Dedicating a contact person to handle the needs of Reebok
Revenue Potential
JNPT's Strength & Weakness Estimated revenue potential for land used for distribution could
JNPT has a locational advantage to serve as a distribution hub be Rs 2.5* Crores per built up hectare of land.
There is availability of land (670 hectares) for development at Assuming 40 hectare built up area the revenue is around Rs 90
JNPT Crores
JNPT lies close to major consumption as well as production This does not include revenues that will occur due to additional
centers such as Mumbai, Nagpur etc traffic attracted by such a hub.
*This could be higher incase JNPT develops and executes the
logistics hub itself instead of leasing land to a third party
Due to JNPT's strength in the opportunity it is rated as High The revenue potential from this opportunity is above 100
Crores and is therefore rated as medium
Stability
Growth
This could also be a stable revenue as it is directly related to
Although the growth rate of the logistics industry is high JNPT's
India's export and import trade which is expected to be stable
revenue from such an opportunity would be driven by rentals
over the medium term
and therefore would be fixed in nature.
Due to the stable nature of the revenues and the stable
Due to the fixed nature of the revenues the growth has
predictions for the hinterland this has been rated medium
been rated as low
to high
Projects Required
Development of land with utilities
Tie up with 3PL and directly with large importers (retailers etc) and specific industries such as machinery/ textiles
Increase in automation – Port net extended to the warehouse
Rail and road connectivity to the warehouse
Bonded warehousing setup within the facility
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
289
Annexure 1.3
Traffic from various regions
Uttaranchal 1.38% 1.36% 1.34% 1.32% 1.30% 1.29% 1.28% 1.26% 1.25% 1.24% 1.24% 1.23%
Uttar Pradesh 11.66% 11.69% 11.72% 11.75% 11.77% 11.81% 11.82% 11.82% 11.83% 11.85% 11.88% 11.86%
Rajasthan 2.27% 2.28% 2.29% 2.30% 2.30% 2.31% 2.31% 2.31% 2.31% 2.31% 2.32% 2.32%
Punjab 2.21% 2.17% 2.13% 2.10% 2.06% 2.03% 2.01% 2.00% 1.98% 1.96% 1.93% 1.93%
Maharashtra 19.68% 19.78% 19.87% 19.96% 20.05% 20.13% 20.18% 20.24% 20.30% 20.36% 20.41% 20.43%
Madhya Pradesh 3.39% 3.38% 3.37% 3.37% 3.36% 3.35% 3.34% 3.34% 3.33% 3.32% 3.31% 3.31%
Kerala 1.83% 1.81% 1.79% 1.76% 1.74% 1.73% 1.71% 1.70% 1.68% 1.67% 1.66% 1.65%
Haryana 5.55% 5.61% 5.67% 5.73% 5.79% 5.82% 5.87% 5.92% 5.98% 6.00% 6.03% 6.07%
Karnataka 4.99% 4.95% 4.92% 4.89% 4.87% 4.83% 4.83% 4.82% 4.81% 4.79% 4.77% 4.78%
Himachal Pradesh 0.74% 0.74% 0.74% 0.74% 0.73% 0.73% 0.73% 0.73% 0.73% 0.73% 0.73% 0.73%
Gujarat 16.15% 16.24% 16.32% 16.39% 16.45% 16.55% 16.56% 16.58% 16.60% 16.66% 16.72% 16.68%
Delhi 0.98% 0.98% 0.98% 0.98% 0.99% 0.99% 0.99% 0.99% 0.99% 0.99% 1.00% 1.00%
Chandigarh 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06%
Andhra Pradesh 7.11% 7.02% 6.94% 6.86% 6.78% 6.72% 6.67% 6.62% 6.57% 6.52% 6.48% 6.46%
Others 22.01% 21.94% 21.86% 21.80% 21.74% 21.66% 21.64% 21.61% 21.58% 21.54% 21.49% 21.50%
Total Imports (Mn
TEUs)* 1.58 1.86 2.25 2.73 3.32 4.02 4.72 5.54 6.49 7.58 8.86 10.03
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
290
Annexure 1.3
Traffic from various regions
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
291
Annexure 1.3
Traffic from various regions
Uttaranchal 1.49% 1.45% 1.42% 1.38% 1.35% 1.32% 1.30% 1.28% 1.26% 1.24% 1.22% 1.21%
Uttar Pradesh 10.22% 10.25% 10.29% 10.32% 10.35% 10.39% 10.40% 10.41% 10.43% 10.46% 10.48% 10.47%
Rajasthan 2.96% 3.01% 3.06% 3.10% 3.15% 3.19% 3.21% 3.24% 3.26% 3.29% 3.32% 3.32%
Punjab 3.90% 3.85% 3.79% 3.74% 3.69% 3.64% 3.61% 3.58% 3.54% 3.51% 3.47% 3.46%
Maharashtra 18.28% 18.39% 18.51% 18.62% 18.74% 18.84% 18.91% 18.99% 19.08% 19.16% 19.24% 19.27%
Madhya Pradesh 3.15% 3.18% 3.21% 3.23% 3.26% 3.29% 3.30% 3.32% 3.33% 3.35% 3.37% 3.37%
Kerala 2.53% 2.52% 2.51% 2.50% 2.49% 2.49% 2.48% 2.47% 2.46% 2.46% 2.45% 2.44%
Haryana 5.09% 5.10% 5.12% 5.13% 5.15% 5.15% 5.17% 5.19% 5.22% 5.22% 5.22% 5.25%
Karnataka 6.62% 6.61% 6.60% 6.59% 6.59% 6.58% 6.58% 6.57% 6.57% 6.57% 6.57% 6.57%
Himachal Pradesh 0.80% 0.81% 0.82% 0.83% 0.84% 0.85% 0.85% 0.86% 0.86% 0.87% 0.87% 0.87%
Gujarat 11.12% 11.14% 11.16% 11.18% 11.20% 11.23% 11.23% 11.24% 11.24% 11.26% 11.28% 11.27%
Delhi 1.35% 1.36% 1.36% 1.37% 1.37% 1.38% 1.38% 1.38% 1.39% 1.39% 1.39% 1.39%
Chandigarh 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11%
Andhra Pradesh 7.35% 7.26% 7.17% 7.09% 7.00% 6.92% 6.88% 6.82% 6.75% 6.71% 6.66% 6.63%
Others 25.02% 24.94% 24.87% 24.79% 24.72% 24.64% 24.59% 24.55% 24.50% 24.42% 24.35% 24.35%
Total Exports (Mn
TEUs)* 1.57 1.86 2.21 2.63 3.13 3.74 4.35 5.04 5.85 6.76 7.82 8.82
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
292
Annexure 1.3
Traffic from various regions
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
293
Annexure 1.4
Pipeline and Tankage details
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
294
Annexure 1.5
Environmental Impact Assessment
EIA of the 4th container terminal and MCT Environmental impact assessment of 4th container
A detailed EIA of the proposed 4th container terminal terminal and Marine chemical terminal
(Phase 1 and 2) and MCT was carried out by CES Parame
(India) Pvt. Limited in their report of 2006. The EIA Evaluation Environ Environ
of EIUs ter
was carried out by systematic identification, prediction ment ment
Importa Change
and evaluation of potential benefits of proposed Environme quality quality
activities with reference to physical, biological, cultural nce in EQ
ntal (EQ) (EQ)
and socio-economic components of the environment. units
attributes before after
A four stage process was carried out the results of (PIU)
which are shown alongside for completeness–
Identification of impact
Physical
z 333 288.40 269.60 -18.80
resources
z Prediction of impact
z Evaluation of impact
Ecological
z Environmental evaluation 267 258.40 233 -25.40
resources
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
295
Annexure 1.5
Environmental Impact Assessment
Human
As can be seen the overall environmental impact of 188 134.00 161.0 +27.00
proposed project activities is positive with a
use values
contribution of 0.60% to the environment.
Quality of
146 99.50 120.65 +21.15
life values
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
296
Annexure 1.6
Benchmarking with international ports
Mundra 17 720
Pipavav 17 453
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
297
Annexure 1.7
Rail and Road Split at JNPT
Rail and road are expected to remain as the primary modes of connectivity. The traffic for JNPT would be divided
between these two modes. The Report of the Committee of Secretaries on Road Rail Connectivity of Major Ports
suggests that the average 55% of the Containers come by road and the remaining come by Rail. However, due to
JNPTs proximity to major production centers in regions of Gujarat & Maharashtra the proportion of road traffic is
expected to be expected higher. The current pressures on rail corridors also limit the proportion of rail traffic over the
short term.
Rail Road Traffic from states other than Maharashtra
It has been assumed in the model that 65% of cargo from states other than Maharashtra would come by Road and
the remaining would come by Rail. Also it is assumed that the proportion of traffic arriving by road would gradually
reduce to around 52% which is in line with the break up in the Report on Rail and Road connectivity.
Rail Road Traffic from states other than Maharashtra
The proportion of traffic arriving by road from Maharashtra at JNPT is expected to be around 90%.
Impact on JNPT
JNPT is expected to lose some share of its northern traffic to competitors and the share of Maharashtra traffic at
JNPT would increase. As a result the effect of a shift toward rail traffic from Northern areas would be limited at JNPT.
As can be seen below the proportion of traffic arriving by rail at JNPT would increase however the increase would not
be very high because it is expected that over the years proportion of Maharashtra traffic at JNPT would increase and
this traffic arrives primarily by road.
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
298
Annexure 1.8
Case for CFS and empty container yards on port land
z CFS and empties development through lease of port land has been envisaged owing to –
z Unavailability of space in the vicinity of JNPT owing to development of Reliance Special Economic zone. This
has created shortage of area for operators to set up CFS/empty yards
z CFS and empty yard operations can result in substantial revenues for the port in the form of leasing and revenue
shares (if agreements are entered into for the same)
z Setting up of such operations helps the port further integrate into the container handling value chain as
envisaged in the vision of the port
z In absence of CFS/empty yard operations the land is likely to be unutilized and not yield any revenues to the port
z Incase land is not made available for CFS operations, new CFS are likely to develop in remote locations and
transport of containers may lead to delays in operations. In such a scenario customs operations may also
emerge as bottlenecks
z Key issues need to be taken into consideration before leasing land for these activities. The same have been
considered while developing the integrated port development plan:
z Presence of adequate road connectivity to evacuate additional traffic from these operations
z Contract management to ensure that utilization of land by these operators is optimal. Underutilization of port land
is likely to impact port operations
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
299
Annexure 2
Financial statements
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
300
Projected Profit and Loss Accounts 1.00 2.00 3.00 4.00 5.00 6.00 7.00
In 000's 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12 2012-13 2013-14
Revenue
Port dues 321,806 350,070 314,532 348,517 386,196 417,631 457,485 494,324 531,523
Other dues (Pilotage,berth hire) 1,125,847 1,207,842 1,094,333 1,177,572 1,313,716 1,431,975 1,581,693 1,727,153 1,878,564
Storage (at similar %age) 249,901 236,502 213,152 265,464 267,335 269,222 271,125 273,043 299,141
Wharf handling 3,311,038 3,133,506 2,824,131 3,517,237 3,542,029 3,567,028 3,592,237 3,617,657 3,963,432
Concession fee 1,226,691 2,327,433 3,261,790 3,467,658 5,301,715 6,287,387 7,065,260 7,954,640 8,909,002
Other operational income (estate) 467,934 491,330 675,702 1,380,085 1,739,465 2,106,844 2,166,897 2,758,362 2,833,282
Total operating revenue 6,703,216 7,746,683 8,383,640 10,156,533 12,550,457 14,080,089 15,134,697 16,825,179 18,414,945
Expenses
Salaries 465,638 502,889 628,611 678,900 733,212 791,869 855,219 923,636 997,527
Social charges and Pension premiums 128,066 158,297 172,895 187,603 204,556 223,122 237,664 255,606 274,179
Running costs (container, marine, estate) 1,407,831 1,521,227 1,629,918 1,844,091 1,977,088 2,108,089 2,256,458 2,411,824 2,620,172
Administrative costs 344,832 358,626 372,971 387,890 403,405 419,541 436,323 453,776 471,927
Other costs (exp on BOT) 121,476 159,861 203,515 220,493 253,412 290,240 320,568 352,590 383,792
Total operating costs 2,467,844 2,700,900 3,007,910 3,318,977 3,571,674 3,832,861 4,106,232 4,397,432 4,747,598
Depreciation 301,190 328,441 356,958 463,105 653,314 792,475 956,072 967,872 995,145
Net earnings before interest and tax 3,934,182 4,717,342 5,018,772 6,374,452 8,325,468 9,454,753 10,072,393 11,459,875 12,672,202
Add fin and misc income 889,794 702,513 800,865 912,986 1,040,804 1,186,516 1,352,629 1,541,997 1,757,876
Less fin and misc exp 453,582 638,678 351,214 351,214 397,834 320,134 242,434 164,734 87,034
Net earnings before tax 4,371,567 4,781,177 5,468,423 6,936,224 8,968,439 10,321,136 11,182,588 12,837,138 14,343,044
Tax 202,280 1,483,040 1,693,337 2,142,484 2,764,342 3,178,268 3,441,872 3,948,164 4,408,972
Net earnings 4,169,287 3,298,137 3,775,086 4,793,739 6,204,096 7,142,868 7,740,716 8,888,974 9,934,073
Net earnings with write back of prov. 3,553,444 3,775,086 4,793,739 6,204,096 7,142,868 7,740,716 8,888,974 9,934,073
In 000's 2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23
Revenue
Port dues 572405 594932 574615 574928 575291 575793 579059 579598 580252
Other dues (Pilotage,berth hire) 2047452 2152527 2105753 2135152 2166181 2197301 2240081 2276607 2315334
Storage (at similar %age) 288117 305951 314218 322711 331437 340403 349615 359080 370829
Wharf handling 3817373 4053664 4163189 4275719 4391337 4510129 4632182 4757589 4913257
Concession fee 10370237 11009742 11529504 12103992 12712204 13357626 14182591 14827980 15549108
Other operational income (estate) 2910688 3441220 3532911 3627579 3725340 3826318 3930639 4038435 4149847
Total operating revenue 20006272 21558035 22220190 23040080 23901790 24807568 25914167 26839289 27878628
Expenses
Salaries 1077329 1163515 1256597 1570746 1696405 1832118 1978687 2136982 2307941
Social charges and Pension premiums 286134 311780 322436 332244 335254 341115 338217 331348 336020
Running costs (container, marine, estate) 2758670 2937889 3019979 2842447 2961793 3086390 3220599 3356294 3503465
Administrative costs 490804 510436 530854 552088 574171 597138 621024 645865 671699
Other costs (exp on BOT) 424985 463401 481890 459234 457900 456595 455280 454036 452425
Total operating costs 5037923 5387021 5611755 5756759 6025523 6313355 6613807 6924524 7271550
Depreciation 1007909 1185183 1220488 1234845 1249777 1265306 1281456 1298252 1315720
Net earnings before interest and tax 13960441 14985831 15387947 16048476 16626490 17228907 18018904 18616512 19291359
Add fin and misc income 2003979 2284536 2604371 2968983 3384640 3858490 4398679 5014494 5716523
Less fin and misc exp 40414 545464 949504 747484 545464 343444 141424 40414 40414
Net earnings before tax 15924006 16724903 17042814 18269975 19465666 20743954 22276159 23590592 24967468
Tax 4892746 5137820 5235101 5610612 5976494 6367650 6836505 7238721 7660045
Net earnings 11031260 11587083 11807713 12659363 13489172 14376304 15439654 16351871 17307423
Net earnings with write back of prov. 11031260 11587083 11807713 12659363 13489172 14376304 15439654 16351871 17307423
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
302
Projected Profit and Loss Accounts 17.00 18.00 19.00 20.00
Revenue
Expenses
Net earnings before interest and tax 20021797 20812774 21618059 22478024
Net earnings with write back of prov. 18369764 19551878 20832566 22252257
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
303
Projected balance sheet 1.00 2.00 3.00 4.00 5.00 6.00 7.00
In 000's 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12 2012-13 2013-14
Assets
Fixed assets 8,803,680 8,875,799 10,728,712 17,261,060 29,924,993 36,811,933 43,055,865 47,199,496 47,476,783
Current assets 4,605,625 3,525,625 3,525,625 3,525,625 3,525,625 3,525,625 3,525,625 3,525,625 3,525,625
Total Investments 4,162,580 4,865,093 5,665,957 4,958,943 2,620,747 1,759,263 2,111,892 3,653,889 5,411,765
Total assets 24,457,063 21,844,719 25,619,805 31,013,544 36,217,641 42,360,509 49,101,225 56,990,199 66,324,272
Equity 0 0 0 0 0 0 0 0 0
Reserves & Surplus 13,854,263 16,327,707 20,102,793 24,896,532 31,100,628 38,243,497 45,984,213 54,873,186 64,807,259
Provisions 255,307 0 0 0 0 0 0 0 0
Long term loans 8,401,164 4,000,000 4,000,000 4,600,000 3,600,000 2,600,000 1,600,000 600,000 0
Short term liabilities 1,517,012 1,517,012 1,517,012 1,517,012 1,517,012 1,517,012 1,517,012 1,517,012 1,517,012
Total equity and liabilities 24,457,063 21,844,719 25,619,805 31,013,544 36,217,641 42,360,509 49,101,225 56,990,199 66,324,272
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
304
Projected balance sheet 8.00 9.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00
In 000's 2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23
Assets
Fixed assets 47,450,580 64,701,166 65,082,421 65,202,124 65,173,752 65,144,783 65,115,193 65,084,957 65,054,049
Current assets 3,525,625 3,525,625 3,525,625 3,525,625 3,525,625 3,525,625 3,525,625 3,525,625 3,525,625
Total Investments 7,415,744 9,700,279 12,304,650 15,273,633 18,658,273 22,516,763 26,915,442 31,929,936 37,646,458
Investments in SPV 1,353,000 1,353,000 1,353,000 1,353,000 1,353,000 1,353,000 1,353,000 1,353,000 1,353,000
Equity 0 0 0 0 0 0 0 0 0
111,892,67 125,381,85 139,758,15 155,197,80 171,549,67 188,857,10
Reserves & Surplus 75,838,519 87,425,602 99,233,315 7 0 4 8 9 1
Provisions 0 0 0 0 0 0 0 0 0
Short term liabilities 1,517,012 1,517,012 1,517,012 1,517,012 1,517,012 1,517,012 1,517,012 1,517,012 1,517,012
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
305
Projected balance sheet 17.00 18.00 19.00 20.00
Assets
Equity 0 0 0 0
207,226,86 226,778,74 247,611,31 269,863,56
Reserves & Surplus 6 4 0 7
Provisions 0 0 0 0
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
306
Projected fund flow 1 2 3 4 5 6 7
In 000's 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12 2012-13 2013-14
Source of funds
Net earnings 4,371,567 3,298,137 3,775,086 4,793,739 6,204,096 7,142,868 7,740,716 8,888,974 9,934,073
Depreciation 301,190 328,441 356,958 463,105 653,314 792,475 956,072 967,872 995,145
Cash flow 4,672,757 3,626,578 4,132,044 5,256,844 6,857,411 7,935,343 8,696,788 9,856,846 10,929,218
Total sources of funds 10,672,757 3,626,578 6,132,044 10,756,844 10,657,411 10,035,343 9,696,788 9,856,846 10,929,218
Use of funds
Investments (1,000,368) 1,103,073 5,010,736 11,788,438 9,779,051 8,917,931 8,552,632 6,653,500 3,030,308
Repayment of loans 7,343,300 4,401,164 2,000,000 2,400,000 1,000,000 1,000,000 1,000,000 1,000,000 600,000
Total use of funds 7,602,032 5,933,553 7,010,736 14,188,438 10,779,051 9,917,931 9,552,632 7,653,500 3,630,308
Liquid means beginning of year 6,885,178 4,578,202 3,699,510 267,916 146,276 263,687 407,843 2,611,189
Liquid means end of year 4,578,202 3,699,510 267,916 146,276 263,687 407,843 2,611,189 9,910,098
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
307
Projected fund flow 8 9 10 11 12 13 14 15 16
In 000's 2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23
Source of funds
Net earnings 11,031,260 11,587,083 11,807,713 12,659,363 13,489,172 14,376,304 15,439,654 16,351,871 17,307,423
Depreciation 1,007,909 1,185,183 1,220,488 1,234,845 1,249,777 1,265,306 1,281,456 1,298,252 1,315,720
Cash flow 12,039,169 12,772,266 13,028,201 13,894,208 14,738,950 15,641,610 16,721,110 17,650,123 18,623,143
Interest income
Liquidation of Investments
Total sources of funds 18,539,169 19,272,266 13,028,201 13,894,208 14,738,950 15,641,610 16,721,110 17,650,123 18,623,143
Use of funds
Investments 9,485,684 14,220,305 4,206,114 4,323,531 4,606,046 5,094,827 5,650,545 6,282,510 7,001,335
Interest payments
Total use of funds 9,485,684 15,520,305 6,806,114 6,923,531 7,206,046 7,694,827 6,950,545 6,282,510 7,001,335
Liquid means beginning of year 9,910,098 18,963,583 22,715,543 28,937,630 35,908,308 43,441,211 51,387,994 61,158,560 72,526,173
Liquid means end of year 18,963,583 22,715,543 28,937,630 35,908,308 43,441,211 51,387,994 61,158,560 72,526,173 84,147,981
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
308
Projected fund flow 17 18 19 20
Source of funds
Interest income
Loans
Liquidation of Investments
Use of funds
Repayment of loans
Interest payments
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
309
Annexure 3
List of abbreviations
© 2006 KPMG Advisory Services Private Limited, an Indian private limited company and a member firm of the KPMG network of independent member firms affiliated with KPMG International, a Swiss cooperative. All rights reserved.
310
List of Abbreviations