Sie sind auf Seite 1von 9

REPORTS ON SCIENCE AND TECHNOLOGY 61/1999

A New LNG Baseload Process and


Manufacturing of the Main Heat Exchanger
Wolfgang Förg, Wilfried Bach, Rudolf Stockmann, Linde AG
Roy Scott Heiersted, Pentti Paurola, Dr. Arne Olav Fredheim, Den norske stats oljeselskap a. s. (Statoil)

Introduction exchangers cannot be purchased on a which have been built and operated until
competitive basis. today:

The formation of the Statoil-Linde LNG The installation of the LNG plant on a ● the classical cascade
Technology alliance reflects the LNG purpose-built barge will shorten the ● the single flow mixed refrigerant
industry’s desire for reduced costs and construction time under the specific process and
schedules for baseload plants. conditions set by remote locations. ● the propane-precooled mixed
refrigerant process.
The evaluation of existing liquefaction
processes led to the development of a
new LNG baseload process. LNG Process Design
The capability of manufacturing large
cryogenic heat exchangers is necessary Historically, we can distinguish between
for building LNG plants, since such heat three different liquefaction processes

The classical cascade has been established at three locations:


Process Year of
startup

Arzew Algeria TEAL 1965 [1]


Kenai Alaska Phillips Petroleum 1969 [2]
Point Fortin Trinidad & Tobago Phillips Petroleum 1999 [3]

The single flow mixed refrigerant process has also been used three times:

Process Year of
startup

Marsa el Brega Libya APCI 1970 [4] [5]


Skikda Algeria TEALARC 1972 [6]
Skikda Algeria PRICO 1981 [7]

The three latter processes may have of the entire LNG value chain. The Alliance Heavy hydrocarbon removal and N2
remarkable differences in their designs, but therefore scrutinized and compared the rejection were not considered in this
they have in common that one mixed existing processes in order to find a evaluation. It was assumed that their
refrigerant stream is compressed by one benchmark for further improvements. influence on each process would be
single compressor. similar, which means they would not affect
The conditions for the comparison were the process comparison.
The most successful process so far, set as follows:
however, has been the propane precooled Natural gas composition (mol-%): N2 2.0; Figure 1 shows the classical cascade
mixed refrigerant process of APCI, which C1 89.0; C2 5.5; C3 2.5; C4 1.0. process (CCP). A three-stage propane
has been used with start-up dates from precooling cycle is followed by a three-
1972 to 1999 in eight different countries [8]. Natural gas inlet temperature: 13 °C; inlet stage ethylene liquefaction cycle and a
pressure 60 bar; gross flow rate: 4 million three-stage methane subcooling cycle.
The liquefaction plant represents tons per annum of LNG; cooling water While propane is compressed leaving the
approximately 50% of the investment cost temperature: 6 °C. different suction drums at its dewpoint,

3
REPORTS ON SCIENCE AND TECHNOLOGY 61/1999

separator D3 and used as refrigerant in the


second cryogenic heat exchanger E2. The
gas from the third compressor stage is
partially condensed in the first cryogenic
heat exchanger E1. The condensate from
separator D4 is subcooled, expanded in
liquid expansion turbine X1 and used as
refrigerant in the third cryogenic heat
exchanger E3. The gas from separator D4
is condensed in the third cryogenic heat
exchanger E3, subcooled in the fourth
cryogenic heat exchanger E4 and then
used for final cooling in the fourth
cryogenic heat exchanger E4 after throttle
expansion. All refrigerants are
subsequently vaporized and warmed up in
heat exchangers E4, E3, E2 and E1 before
being compressed in compressor C1/C2.

Figure 3 depicts the well-known propane


precooled mixed refrigerant process
(C3MRC). Precooling is achieved by a
Figure 1 — Classical cascade process three-stage propane cycle compressor C1
and precooling heat exchangers E1A, E1B
and E1C. Liquefaction and subcooling are
accomplished by two-stage mixed
ethylene and methane are vaporized and mixed refrigerant is composed of N2, CH4, refrigerant compressor C2/C3, separator
superheated before being compressed. C2H6, C3H8 and n-C4H10. The condensate D1, liquefier E2A and subcooler E2B. For
from separator D1 downstream from first large plant capacities a liquid turbine X1 is
Figure 2 shows the single flow mixed compressor stage C1 and water cooler advantageous.
refrigerant process (SFMRP) which was the CW1 is pumped to the discharge of the
result of extensive optimization work. It was second compressor stage. The conden- Figure 4 represents a sketch of the
not the intention to compare the three sate from separator D2 of this stage is Alliance’s LNG baseload process
different processes mentioned above, but used as refrigerant in the first cryogenic consisting of three mixed refrigerant cycles,
we have selected our own design as heat exchanger E1. The condensate from called mixed fluid cascade process
representative for this type of process. The the third compressor stage is collected in (MFCP). The precooling cycle consisting of

Figure 2 — Single flow mixed refrigerant process Figure 3 —Propane precooled mixed refrigerant process

4
REPORTS ON SCIENCE AND TECHNOLOGY 61/1999

Figure 4 — Under these assumptions the compressor


Mixed fluid cascade shaft power at 100% adiabatic efficiency
process for the refrigeration cycles turned out to be
70.4 MW for the mixed fluid cascade
process. If one compares the compressor
shaft power with real adiabatic efficiencies
the advantage of the MFCP versus the
C3MRC may disappear, because no axial
machine can be applied at the MFCP,
while compressor C2 within the C3MRC
can be built as an axial machine, with
higher adiabatic efficiency.

In spite of this fact we see an advantage


for the MFCP, since heat exchangers E2
and E3 of this process are of similar size
and well within the limits of manufactur-
ability of spiral wound heat exchangers.
With other words, those heat exchangers
are not the limiting factor for the size of
one liquefaction train.

As far as the SFMRP is concerned we


believe that the limits of manufacturability
are exceeded in several areas, e. g.,
suction line, separators D1 to D4 and
compressor C1. Therefore, the SFMRP is
suitable for smaller train capacities than 4
a mixture of C2H6 and C3H8 is compressed E1B, E2 and E3, expanded in liquid turbine million tons per annum only.
in compressor C1, liquefied in sea water X1 and used as refrigerant in subcooler E3.
cooler CW1 and subcooled in cryogenic All compressor suction fluids are slightly
heat exchanger E1A. One part is throttled superheated above their dewpoints.
to an intermediate pressure and used as Manufacturing of Cryogenic
refrigerant in E1A. The other part is further A comparison of the main data of the
subcooled in heat exchanger E1B, throttled above processes is given in table 1.
Heat Exchangers
to the suction pressure of compressor C1
and used as refrigerant in heat exchanger Special effort was made to investigate the For the cryogenic process section plate-fin
E1B. The liquefaction cycle is compressed different processes on a comparable basis. heat exchangers as well as spiral wound
in compressor C2, cooled in sea water Linde’s proprietary design optimization heat exchangers can be applied.
coolers CW2A and CW2B, further cooled in program, Optisim® was used for this
heat exchangers E1A, E1B and E2. It is purpose [9]. It was attempted to have Aluminum plate-fin heat exchangers
throttled and used as a refrigerant in similar heat transfer surfaces for all (PFHE) have been installed in air
liquefier E2. The subcooling cycle is processes within the cooling water and the separation, in gas separation, and in the
compressed in compressor C3, cooled in cryogenic section. This was not always cryogenic section of ethylene plants as
sea water coolers CW3A and CW3B, possible as the limitation of a minimum well as natural gas separation and LNG
further cooled in heat exchangers E1A, temperature pinch was given priority. peak-shaving plants for several decades.

MFCP C3MRC SFMRP CCP


Compressor shaft power at 100% adiabatic efficiency % 100 103,3 114,2 115,5
Heating surface cooling water section % 100 100 88,4 105,1
Heating surface refrigerant section % 100 99,1 106,8 94,2
Heating surface total % 100 99,4 100,5 98,0
Number of compressor casings 3 3 2 3
Number of suction lines 4 4 1 9
3/h
Maximum flow in the suction line, approximately m eff. 120.000 200.000 315.000 112.000

Table 1: principal data of the four processes to be compared

5
REPORTS ON SCIENCE AND TECHNOLOGY 61/1999

For approximately 20 years Linde has been


manufacturing such heat exchangers [10]
using the vacuum-brazing process as
shown in Figure 5.

Raw materials for separator plates, fins and


side-bars are measured, cut and stamped.
All parts are washed to remove oil, dried
and stacked. They are brazed in a vacuum
furnace under precise temperature control
at approximately 600 °C. Thereafter,
headers and nozzles are welded to the
block to complete the heat exchanger.
Before shipment the final product is
subjected to X-ray, helium leakage, flow
and pressure testing. More than 4,000
blocks have been built until now.

PFHEs are well-suited for applications in


LNG baseload plants. They are, however,
sensitive to large and rapid temperature
changes and are therefore regarded as
less robust in comparison to spiral wound
heat exchangers. Also the two-phase flow
distribution to a battery of blocks is
considered to be more difficult when
compared to a single spiral wound heat
exchanger.

In the precooling section of an LNG


baseload plant, however, vacuum-brazed
aluminum PFHEs are a good choice.
Figure 6 shows four assemblies of four
blocks each, finally forming one heat
exchanger unit.

Spiral wound heat exchangers (SWHE) or


coiled tubular heat exchangers [11] as they
are called sometimes have been used in
the cryogenic industry since the early days.
The heat exchanger used by Carl von
Linde when he liquefied air on an
industrial scale for the first time in Munich
in May 1895 consisted of two concentric
tubes, which were wound to form a coil
[12].
Figure 5 — Manufacturing of vacuum brazed aluminium plate-fin heat exchangers
Until today, more than a thousand SWHEs
have been manufactured in Linde’s
workshops. Copper has been the
traditional material for many decades. It on many heat exchangers in low- the individual streams by calculating the
has been almost completely replaced by temperature service for more than 25 years. heat transfer coefficients, pressure drops
stainless and low temperature alloy steels and temperature differentials as driving
and by aluminum. For weight reasons and For the thermodynamic, hydraulic and forces for discrete elements. The number
since the service can be kept clean and geometrical design Linde’s proprietary of elements used in the calculation is
free from corrosive substances aluminum computer program Genius is used [13]. determined dynamically and depends on
is the material of choice for the liquefier Process data as flows, pressures, temper- the accuracy required and by the non-
and subcooler of an LNG baseload plant. atures and temperature differences are linearity of the enthalpy-temperature curves
Many of the construction details and provided by the process calculation using of the individual streams. The dew and
fabrication procedures such as tube Optisim®. Pressure drops are set by an bubble points as well as the composition
support system and tube spacing iterative optimization. Genius determines of each stream are taken into account by
arrangements are proven design gained the temperature and pressure profiles of the simulation. All methods used for heat

6
REPORTS ON SCIENCE AND TECHNOLOGY 61/1999

transfer and pressure drop implemented


into the program have been carefully
tested.

Our own research is complemented by


evaluation of literature (e. g., [14], [15], [16])
and cooperation with major research and
development institutions like Heat Transfer
Research Inc. (HTRI) and Heat Transfer and
Fluid Flow Service (HTFS). Especially for
falling film evaporation at the shell-side of
the SWHE Linde and Statoil [17] have
performed their own measurements and
evaluated available literature [18] and
produced corresponding calculation
methods. As the final product, Genius
calculates the number and length of the
tubes for the individual streams, the
number of layers, the dimensions of the
spacer bars and the distribution of the
tubes to the different layers, resulting in the
geometry of the bundle.
Figure 6 — 4 x 4 blocks to be assembled to form one heat exchanger
The manufacturing procedure of the SWHE
is as follows (Figure 7): It starts with the
core cylinder or mandrel (1.1), which can
be rotated on a winding bench by means
of two race rings in horizontal position.
Support arms and liquid distribution trays
are connected to what will be the upper
side of the heat exchanger (1.2) when it is
erected to its final vertical position. Tube
sheets are brought into their position at
both ends of the heat exchanger. Spacer
bars will keep the designed distance
between the mandrel and the first layer of
tubes.

Now the winding of the inner layer of tubes


can begin. Therefore, each tube of this
layer is inserted into its tube sheet at one
side, wound onto the mandrel and then
inserted into the corresponding tube sheet
at the other side (2.1). When the winding of
the first layer is performed from left to right,
the next layer is performed from right to left
(2.2), and so on. Proper distance between Figure 7 — Manufacturing procedure for spiral wound heat exchangers
the individual layers is kept by spacer bars
(2.3).

To avoid a by-pass at the shell side the The upper part is added, and the closing Processing plant on purpose-
bundle is wrapped into a shroud (2.4). After seams and nozzles are welded to the shell
the tubes have been welded to the tube (3.4). Figure 10 shows the SWHE in its final built barge
sheets, bonnets are welded to the tube upright position.
sheets (2.5). During the work of the Statoil-Linde LNG
Figure 11 shows on the left-hand side a Technology Alliance, it was assumed that
Parallel to the manufacturing of the bundle mandrel equipped with tube sheets, future LNG baseload plants are to be
the lower (3.1) and the upper part (3.2) of support arms and liquid distribution tray. In installed in remote locations without the
the shell are being fabricated. During the foreground and in the background two availability of infrastructure and subjected
assembly the completed bundle is bundles during different phases of the to extreme weather conditions. It was
inserted into the lower part of the shell and winding process can be seen. envisaged at an early stage that for this
the shroud is connected to the shell (3.3). purpose a conventional construction

7
REPORTS ON SCIENCE AND TECHNOLOGY 61/1999

Conclusion

The work done by the Statoil - Linde LNG


Technology Alliance with respect to
process design, selection of main
compressors and drivers, manufacturing of
cryogenic heat exchangers along with the
installation of the process plant on a
purpose built barge has led to significant
savings in investment cost and a
considerable shortening of the project
execution time.

Literature
[1] Operating Experience of the Arzew
Plant; Pierot, M.
LNG 1, Chicago, Illinois, USA, April 7-12,
1968; Session No. 2, Paper 10b
[2] Phillips Optimized Cascade LNG
Process
Houser, C. G.; Krusen, L. C. (Phillips
Petroleum Co.)
Gastech ‘96, 17th Int. LNG/LPG Conf.,
Vienna, Dec. 3-6, 1996, Conf. Papers
[3] The LNG Industry 1996; GIIGNL;
page 9
[4] Esso Libya Venture; Latimer, D. M.
LNG 1, Chicago, Illinois, USA, April 7-12,
1968; Session No. 3, Paper 15
[5] The Design, Fabrication and Operation
of Large Cryogenic Heat Exchangers
Gaumer, L. S.; Geist, J. M.; Harnett, G.
J.; Pfannenstiel, L. L.
LNG 3, Washington D. C., Sept. 24-28,
Figure 8 — Manufacturing procedure for spiral wound heat exchangers 1972; Session II, Paper 15
[6] Experience of Arzew and its Effect on
the Design of the Skikda Natural Gas
approach would not be cost and time both during construction and plant Liquefaction Plant; Bourget, J. M.
effective. Therefore, one of the most operation. Likewise the barge is also used LNG 3, Washington D. C., Sept. 24-28,
fundamental process decisions was to as a transportation vessel, when the fully 1972; Session V, Paper 6
install the major part of the LNG process tested, mechanically completed and [7] PRICO - A Simple, Flexible Proven
plant in a most compact format on a precommissioned plant is towed from the Approach to Natural Gas Liquefaction
purpose built barge (Figure 15), thereby construction/assembly yard to the Price, B. C.; Mortko, R. A. (Pritchard
minimizing construction work on site. The production site. Here the barge is brought Corp.)
installation takes place within a into a prepared dock and settled down on Gastech ‘96, 17th Int. LNG/LPG Conf.,
strategically well located shipyard making ground. The dock will then be closed to Vienna, Dec. 3-6, 1996, Conf. Papers
use of local skilled labor force and weather seaside, filled with gravel and hooked up
protected dock facilities. This in turn meant with other site systems. [8] The Air Products Propane Precooled/
that basic engineering, design methods Mixed Refrigerant LNG Process
and project execution strategies had to be It was also realized during the work that an Bronfenbrenner, James C. (Air Pro-
tailored to meet the specific constraints of alliance type of project execution and ducts and Chemicals, Inc.)
this barge-mounted concept. contract strategy is a necessity to LNG Journal, Nov./Dec. 1996,
accomplish construction and scheduling page 25-27
The barge serves as a permanent base flexibility, which is required to achieve the [9] The Design of Optimal Air Separation
and foundation for the LNG process plant, reduced cost and schedule of the plant. and Liquefaction Processes with the

8
REPORTS ON SCIENCE AND TECHNOLOGY 61/1999

Figure 9 — Manufacturing procedure for spiral wound heat exchangers

Figure 11 — Three coiled heat exchangers during manufacturing Figure 12 — Subcooler on a winding bench during production
on winding benches

9
REPORTS ON SCIENCE AND TECHNOLOGY 61/1999

Figure 13 — Transition from the liquefier to the subcooler

Figure 14 — Three coiled heat exchangers installed in a common shell

Figure 10 — Spiral wound heat exchanger


in its final upright position

10
REPORTS ON SCIENCE AND TECHNOLOGY 61/1999

Figure 15 — Liquefaction plant built on a special-purpose barge

OPTISIM equation-oriented Simulator W. [16] Condensation of Hydrocarbon


and its Application to on-line and off- MUST 1996, Refrigeration Science and Mixtures in Coil-Wound LNG Heat
line Plant Optimization; Burr, Peter S. Technology Proceedings Exchangers
AIChE Spring National Meeting, Munich (Germany) Oct. 10-11, 1996 Neeraas, B. O.
Houston, Texas, April 7-11, 1991; Paper Ph. D. Thesis, University of Trondheim,
[13] Optimised Calculation of Helical-
50a Norwegian Inst. of Technology, 1993
Coiled Heat Exchangers in LNG Plants
[10] The Manufacture of Plate-Fin Heat Steinbauer, M.; Hecht T. [17] Thermal Design of Coil-Wound LNG
Exchangers; Diery, W. Eurogas 96 Conference, Trondheim, Heat Exchangers
Linde Reports on Science and Norway, June 3-5, 1996 Shell-Side Heat Transfer and Pressure
Technology 37/1984 Drop; Fredheim, A. O.
[14] Coiled Tubular Heat Exchangers;
Ph. D. Thesis, University of Trondheim,
[11] Coiled Tubular Heat Exchangers; Abadzic, E. E.; Scholz, H. W.
Norwegian Inst. of Technology, 1994
Scholz, W. H. Advances in Cryogenic Engineering,
Linde Reports on Science and Vol. 18, Plenum Press, 1973 [18] Echange de Chaleur et Pertes de
Technology 18/1973 Charges en Ecoulement Diphasique
[15] Wärmeuebertragung im Gegenstrom,
dans la Calandre des Echangeurs
Gleichstrom und Kreuzstrom
[12] The History of Air Separation; Foerg, Bobines; Barbe et al.
Hausen, H.; Springer Verlag, 1950
Proceedings of the XIII International
Congress on Refrigeration, Vol. 2

11

Das könnte Ihnen auch gefallen