2. Procurement Assumptions
Most of the furniture and other material required for the laboratory
will be available in university facilities, other labs or store. The exact
extent of availability of material is not available but there is high
probability of finding the right furniture within the university campus.
3. Procurement Constraints
1
4. Market Research and Conditions
All the need for furniture demand will be met through university
facilities. There is plenty of furniture available. And above all the
owner require the material to be functionally superior to aesthetics,
thus with enhanced options due to this fact will help in material
procurement.
2
Marchand and his team. There will be no requirement for extra
manpower.
For cleaning the premises Bee clean services will be used as the
only quality option available.
Lump sum project (fixed fee contract) will be best to meet the
demand of the customer as scale of the project is small and our
team will be involved in planning phase of the contract only. Rest of
the project, execution, monitoring, control and completion would be
done by owner. Specifically all other phases of project will be done
with the movement of all machinery and equipments.
Dr Lipsett and Roger will go and inspect the required material with
the University facilities. The material selected would be delivered to
new facility by University personnel as required.
8. Procurement Justification
Only services from Bee Clean for cleaning up the premises before
moving in would be used from resources other than University. This
is a common practice so it is justified.
3
Personnel Roles Responsibility