Beruflich Dokumente
Kultur Dokumente
3ULZER¬4URBO¬3ERVICES¬HAS¬ALWAYS¬
3ULZER¬(ICKHAM¬)NC
PUSHED¬THE¬BOUNDARIES¬OF¬REPAIR 3ULZER¬4URBO¬3ERVICES
¬/LD¬,A0ORTE¬2D
AND¬WILL¬CONTINUE¬TO¬DO¬SO¬IN¬THE¬FIELDS¬OF ,A0ORTE¬48¬
3ULZER¬4URBO¬3ERVICES
3ULZER¬(ICKHAM¬)NC 3ULZER¬%LBAR¬"6 3ULZER¬2EPCO¬"6 3ULZER¬%NPRO¬)NC 04¬3ULZER¬(ICKHAM
)NDONESIA
WWWSULZERHICKHAMCOM WWWSULZERELBARCOM WWWREPCONL WWWSULZERENPROCOM WWWPTHICKHAMCOM
0HONE¬¬¬ ¬¬¬ 0HONE¬ ¬ ¬¬¬ 0HONE¬¬¬ ¬¬ 0HONE¬¬¬ ¬¬¬ 0HONE¬ ¬ ¬¬
&AX¬¬ ¬ ¬¬ &AX¬¬ ¬ ¬¬¬ &AX¬¬¬ ¬ ¬¬ &AX¬¬ ¬ ¬¬ &AX¬¬¬ ¬ ¬¬
%
MAIL¬ SALES HICKHAMCOM %
MAIL¬¬MAIL ELBARCOM %
MAIL¬ SULZERREPCO SULZERCOM %
MAIL¬¬SALES SULZERENPROCOM %
MAIL¬ PTHICKHAM SULZERCOM
7EA Users Group
the specification called for. Lead
decreases the melting point of bab-
bitt. While the average lead content
was in spec for the damaged lower
half (some sections were high, others
low), copper content was high by at
least 25%. Copper, which raises the
melting point of babbitt, was particu-
larly visible along the grain boundar-
ies of some cracks.
Metallographic examination
showed good bonding of babbitt
1. Rail wear on turbine third-stage 2. Internal misalignment also is con- material. But it also revealed that
buckets is one indicator of possible ducive to honeycomb seal wear babbitt formed to the contour of the
internal misalignment backing-materials arrangement,
indicating that it was under high
stress.
Conclusions of the RCA were that
No. 1 bearing failure was a result of
(1) reduced fatigue strength of the
babbitt material because of the high
lead content (even though the dam-
aged bottom half was high in copper)
and (2) possible internal misalign-
ment. The OEM recommended that
bearings be checked if their tempera-
tures exceed 230F.
3. Rubbing of compressor-blade 4. Lower bearing half shows consid- At another 7EA in the control
tips against the casing in the area of erable damage after only 1407 hours group, operators noted that the
rows five to 10 is yet another sign of of fired operation temperature of the No. 1 bearing
possible internal misalignment of the was trending upward over a period of
7EA machine weeks and the machine was removed
from service for inspection after only
a session on bearing problems of con- Machine 1. Bearing metal tem- 1884 fired hours. As for the previous
cern to at least several users. Dis- perature (BMT) was 275F on restart case, damage was found on the lower
cussion focused on a control group following a unit trip at 99 MW half of this bearing while the upper
of 7EA GTs that had the following caused by fuel interruption. Less half remained in good condition.
experience with No. 1 bearings over than a week later, temperature Data gathered on this machine
the last five years: reached 300F on another restart, but indicated that on the accessory-gear
n Increasing temperature of bear- settled at 165F during steady-state end, horizontal alignment was 34
ing metal. operation. Operations personnel mils out of spec, with face readings
n High bearing-metal tempera- carefully tracked BMT for the next 1 mil out in the horizontal plane; on
tures. three months; an outage was taken the generator end, vertical readings
n Bearings replaced on three GTs. after bearing temperature spiked were 55 mils out of spec, horizontal
Internal misalignment of the rotor above the 265F limit specified by the 20 mils, and the face closed 2 mils at
was suspect as the primary source of OEM. The machine was opened and the bottom.
the No. 1 bearing problem, for the plant personnel found the No. 1 bear- Babbitt analysis showed high lev-
following reasons: ing damaged (Fig 4). The bearing els of copper, lead, and iron in the
1. Bearing-wear patterns and failed with only 1407 fired hours on top half of the bearing; copper at the
seal-clearance data were indicative the machine. high end of the spec limit (possibly
of misalignment. A root-cause analysis (RCA) was slightly higher according to one test)
2. N o . 1 b e a r i n g s e x h i b i t e d performed by the OEM. The com- and lead double the spec limit in the
increasing temperature trends on pany checked external alignment lower half. High concentrations of
nearly 70% of the units surveyed. data, analyzed bearing babbitt mate- lead were found in babbitt cracks
3. Specified angularity checks are rial, and conducted a metallographic as well as in areas surrounding the
not conducted at the factory. Factory examination. Regarding alignment cracks. Lead precipitated along the
clearance data on the control group (turbine to accessory gear), horizon- grain boundaries. Metallographic
indicated that a majority were out tal readings were 7 mils out of spec; inspection revealed cracks in the
of spec. face readings were 1.5 mils out of babbitt approximately four-thou-
4. Rail rubs (Fig 1) and honey- spec in the horizontal plane. Find- sandths of an inch below the surface;
comb-seal wear (Fig 2) often were ings were dramatically different on bonding was satisfactory.
observed on turbine third-stage the generator end of the machine, Investigators offered the following
buckets; tip rubs on compressor with vertical alignment 50 mils out conclusions after careful analysis:
blades in stages five through 10 (Fig of spec, horizontal 8 mils; face read- n External misalignment was not
3). ings were closed 4 mils at the bot- considered a contributor to bear-
Specific details on three individu- tom. ing failure, even though the gen-
al machines were offered by attend- Chemical analysis of the upper erator was sitting lower than the
ees to provide insights necessary for bearing half, which was in good GT. Reason: Such a condition
problem evaluation and the formula- condition, indicated a high content would have increased the load on
tion of a solution: of lead—at least 50% higher than the No. 3 bearing and reduced the
COMBINED CYCLE JOURNAL, Fourth Quarter 2005
7EA Users Group
load on the No. 1 bearing. the jerky operation of the ratchet hours of GT operation a threshold of
n Internal misalignment was a pos- installed on this unit is conducive to concern? Should it be?
sible cause of the bearing failure. low-speed wear. Owner halved ratch- Certainly, there are “hard” hours
n Oil condition was satisfactory and et use to 30 minutes every 24 hours (cycling service) and “easy” hours
bearing surfaces exhibited no for- the unit is idle to minimize its impact (baseload operation) for GTs just as
eign-object wear. on bearing wear. Voith Turbo Inc, autos have their hard (city) and easy
n Analysis of subsurface cracks York, Pa, which supplies ratchets (highway) miles. Most well-engi-
revealed lead content that exceed- told the editors of the COMBINED neered vehicles should get around
ed 45% in some areas. Lead par- CYCLE Journal that ratchets should 200,000 miles today with normal
ticles were observed surrounding provide smooth shaft rotation. If this maintenance. Why shouldn’t GTs
the cracks. is not the case, adjustment and/or run for 200-, 300-, or 400-thousand
The OEM was said to have recom- maintenance is necessary. hours when operated on gas and
mended that bearing temperatures maintained properly?
be monitored closely with an alarm if Bruning, the former chairman
the babbitt reaches 240F. Shutdown Profiling a 100,000-hr of the 7EA Users Group is proactive
was recommended at 250F; bearing outage when it comes to sharing GT O&M
replacement if the babbitt hits 265F. experience. “We all learn from each
Operators responsible for Many large frame machines are other,” he says, “and all benefit from
a third 7EA in the control group approaching 100,000 hours of service open collaboration.” Having com-
observed a step change in bearing and there is widespread interest in pleted in June the second major at
temperature from 185F to 230F the experience of owner/operators Sumas, the Washington-state plant
during one run and the unit was that have conducted their second he manages, Bruning was primed for
removed from service for inspec- “major” inspection/overhaul, which a speaking engagement at the Las
tion. Visual examination after 2177 usually is done at about the 96,000- Vegas meeting. He was accompanied
fired hours of operation revealed no hr mark. by Operations Supervisor Stu Keck.
physical damage to either bear- Sumas is a gas-only, 135-MW,
ing half, but wear at bottom dead 1 × 1 combined cycle owned by
center indicated a low-speed National Energy Systems Co
wear condition. (NESCO), Kirkland, Wash, and
This unit had only slight operated by Calpine Corp, San
horizontal misalignment on the Jose, Calif. It supplies base-
accessory-gear end—nothing load power under a long-term
significant enough to explain the purchase agreement to Puget
temperature step change. Bab- Energy Inc (PSE); process steam
bitt analysis revealed a metal to SOCCO Forest Products. The
chemistry consistent with ASME plant operates under an LTSA/
B23 Type 3 babbitt, which is CSA (long-term service agree-
harder and more wear resis- ment/continuing service agree-
tant than the Type 2 material ment) with GE Energy, Atlanta,
specified. The wear pattern was for “major” parts, technical assis-
indicative of low-speed (turning tance, and outage labor.
gear/ratchet) operation. The scope of work and sched-
Another important observation: 5. Gas-turbine rotor is lifted out of ule for a Sumas major are dictated
spalling and subsurface cracking the casing for inspection and refur- by the GT’s maintenance cycle. It
with iron contamination. Possible bishment requires rotor removal and inspec-
cause of this condition is lubricat- tion every six years, based on unit
ing-oil film loss during turning gear/ Obvious questions about machine operating time and starting fre-
ratchet operation, allowing the shaft reliability arise at this point, with quency. Primary goal of the outage
to directly contact babbitt material. O&M personnel wondering about the was to complete the work required
Keep in mind that iron does alter the long-term health of specific parts and in a manner that supports anoth-
babbitt material and cause prema- of materials in general. er six years of reliable, base-load
ture spalling and cracking. However, Perhaps there’s something com- operation. A four-week outage was
the degree of spalling and cracking pelling about the number 100. The planned, Bruning said.
present for this machine was not suf- human body, if it survives, is pretty He credited Keck and Mainte-
ficient to have caused the dramatic well worn out after a century of ser- nance Supervisor Rob Bertschinger
temperature step change observed, vice. The reliability of an automobile with having done most of the plan-
investigators said. on long trips typically is debated ning. They relied on an MS Project
Investigators concluded that the at 100,000 miles, etc. Is 100,000 database to communicate schedul-
temperature step change recorded ing, procurement, and manpower
was caused by either (1) internal requirements. This electronic tool
misalignment or (2) the thermo- summarizes outage results and
couple short identified during labo- includes a record of pictures taken
ratory examination. Regarding the and provides a basis for planning
second possible cause, operators future outages. The combined cycle
questioned why both thermocouples returned to service within 28 days.
were reading temperatures over The preliminaries. Immedi-
225F. Possibly, the shorted ther- ately prior to the outage, contractors
mocouple was damaged in bearing were mobilized and briefed on site
removal or shipment. safety requirements. GE assisted
Another conclusion was that Bruning Keck with generator testing at this time.
COMBINED CYCLE JOURNAL, Fourth Quarter 2005
GE Energy
A winning performance
starts with expert service.
7. Transition pieces are reinstalled as reassembly nears 8. Rotating field for the GT generator is eased out of the
completion machine
COMBINED CYCLE JOURNAL, Fourth Quarter 2005
Parts Ad 11-2005.qxd 12/15/05 6:45 PM Page 1
1-800-752-HRSG
DELTAK PARTS 763-557-6966 (fax)
parts@deltak.com
For your next outage, remember, “Precision parts purchased promptly prevent problems.”
Braden Retrofit
Solutions Exhaust
Inlet Air
Cooling
Systems
Stack
The OEMs’ Preferred Source
Since 1970, Braden has designed, engineered and manufactured hundreds
of GT auxiliary systems as the preferred supplier for turbine OEMs.
Comprehensive Retrofit Solutions
Braden’s full array of engineers (structural, mechanical, electrical
and acoustical) scrutinize every aspect of your retrofit design.
©2005 Braden Manufacturing, LLC
Inlet Ductwork
with one requiring less ammonia, allow parallel generator operation Activities in the circulating water
having a lower pressure drop, and through transformers serving both system focused on inspection of fans,
less likely to cause downstream foul- the GT and ST. The interconnecting gearboxes, and system piping. A vari-
ing. Repairs were made to the ammo- cables required for the reactor were able-frequency drive for one of the
nia storage tank as well. installed during the outage. fans was replaced. Cooling-tower fill
High-voltage electrical sys- Valves, instruments, and con- had been replaced during a previous
tem. Bruning said that preventive trols. Independent outside contrac- outage and the basin cleaned. The
maintenance of high-voltage (HV) tors played a major role in the inspec- main condenser and heat exchangers
electrical gear was conducted dur- tion and adjusting of valves and for both lube-oil and generator cool-
ing the outage and the 13.8-kV bus I&C components. A specialty valve ing were inspected and cleaned.
enclosure was replaced because it contractor inspected internally and Pumps and motors. Critical
showed signs of overheating. Clean- adjusted most major valves, extensive pumps and motors—including those
ing and inspection of transformers, instrumentation checks were con- for the circ-water and lube-oil sys-
insulators, breakers, backup battery ducted by another service firm with tems—were cleaned and inspected.
systems, and protective relays was plant staff assisting. Maintenance Most large motors were removed to a
routine, he continued; no problems and modifications to the plant distrib- GE shop for this work.
were identified. uted control system (DCS) and the The rewards and pitfalls of
The electrical scope of work was Mark V turbine/generator controls restart. Bruning rated the major a
expanded when problems were found were performed by GE and a Port- success in terms of personnel safety
with the interconnecting cable and land-based engineering firm. and post-outage operations. There
bus. Specifically, cable connections Valves, pressure regulators, and were no reportable injuries and no
had been overheated and a section filters for the gas supply line were lost time. All components inspected
of bus between the GT generator cleaned and inspected as well. Fil- either were found in good condition
and its accessory compartment was ters were found in good condition or repaired to a condition that would
misaligned. The misalignment was and line pigging was not considered allow them to operate reliability
corrected. necessary for at least another year. at least until the next scheduled
However, only temporary repairs Makeup and circ water. The maintenance outage. Cleaning of,
were made to the cable insulation makeup water treatment system and repairs on, the GT produced
and plans prepared for thorough was overhauled and reverse-osmosis immediate results: Plant output
testing after the major was com- membranes replaced. Results of this increased by more than 2% follow-
pleted. Bruning and his staff also work were particularly rewarding, ing restart.
decided to postpone fixing problems according to Bruning. Water quality But as everyone who has par-
with cable supports in the tray to a and system reliability were improved ticipated in a major outage knows,
latter date. Finally, a reactor was and the system is now easier to oper- it takes some tuning and follow-
ordered for future installation to ate and maintain. on work to get the plant operating
COMBINED CYCLE JOURNAL, Fourth Quarter 2005 11
LOOK TO
FOR RELIABILITY – DEPENDABILITY – 24/7 SERVICE
exactly the way you want it to. At after field fixes were complete to Find any chunks of
Sumas, the plant was ready for guide work necessary in future
restart 26 days after the outage outages and to minimize plant
green plastic material in
started, but a few of the seemingly thermal-efficiency losses. your turbine oil?
inevitable glitches required correc- n An alignment problem with the
tion and delayed synchronization by breaker for the GT generator was Hard to believe that some owner/
a day. For example: identified on restart and correct- operators do not participate in one
n A faulty solenoid on a compres- ed. or more of the user groups serving
sor bleed valve stuck in the closed n NOx distribution across the stack the GT-based generation sector. The
position, causing the compressor revealed that adjustments made networking is invaluable, akin to
to surge before it reached full to the SCR’s ammonia injection free consulting from experts. Con-
speed. When full speed finally grid required some correction. sider the following question posted
was achieved, air leakage from This has since been done and the to the 7EA Users Group online bul-
the wrapper joints and bearing system is working as planned. letin board last May by one plant
drain flange was excessive. n One circ-pump motor failed on manager:
n ST vibration levels were higher restart. It was removed and sent While performing a routine main
than normal on restart. This was out for rewind. lube-oil filter change, we were unable
attributed to the tight clearances n The starting motor for the GT to completely pump down the filter
associated with new packing. developed signs of bearing wear. housing. The unit was not operating
Vibration persisted on restarts for This was corrected during the at the time and the transfer valve
the next month, but disappeared August follow-on outage. was cycled one time to see if the
after that. End notes. Valve repairs made valve would seat off. Leakage into
n ST output was less than expected. after the major outage increased ST the housing was too great to open
The shortfall was traced to valve output a small amount over the pre- the filter. After the transfer valve
problems attributed to age, duty, outage capability. Remaining areas was cycled, chunks of plastic-type
and contractor errors. High- and of concern are the reliability of the material started coming through the
low-pressure steam dump, steam- HV cable between the generators drain on the inlet side of the filter
seal dump, and steam-letdown and transformers, installation of the housing. The material apparently is
valves all were leaking. A plan reactor, and losses through turbine from the transfer-valve sealing shoe.
was developed to correct problems control valves. Valve recondition- It appears that the material has
during planned “clean-up” out- ing will be a focus of the plant staff, chemically degraded to the point that
ages in July and August. Bruning Bruning said in wrapping up, to its mechanical properties have been
and his staff also agreed to hire assure maximum electrical and ther- compromised.
another specialty valve contrac- mal output at the highest efficiency I am very concerned that the shoes
tor to measure leakage remaining possible. also have degraded on the down-
12 COMBINED CYCLE JOURNAL, Fourth Quarter 2005
10938 CC OIA Ad 22/8/05 10:35 Page 1
stream side of the filter. The unit valve seals were urethane and they several more failures, GE was asked
was installed in 2001 and all oil have been changed to a Viton mate- to issue a TIL. No TIL had been
tests have been good. Has anyone else rial and are performing well: No released by the time the 7EA Users
experienced this problem? deterioration noted upon inspection Group met in Las Vegas; however,
Two replies were posted to the of the shoe that had been in ser- the OEM recommended that the
bulletin board less than three hours. vice the longest. The urethane seals shoes be replaced with ones made
Would anyone other than a plant col- swelled, cracked, and eventually of Viton A. Note that the issue is a
league have responded so quickly? large chunks came off the valve seat. generic one, also impacting machines
Reply 1: We have experienced On one unit, we had to contract with made by Siemens Power Genera-
the same problem on one a borescope retrieval com- tion Inc, Orlando, as well as other
of our units. We noticed pany to locate and remove OEMs.
a high differential across the chunks from the piping Information gathered by 7EA
our filters and were going downstream of the filter dis- users revealed that every plant
to do a filter change-out. charge transfer valve. reporting failures had lube-oil
When we got started, we The dialog continued from transfer valves with shoes made
noticed that we were get- when the question was first of polyurethane (Figs 11, 12); also
ting flow through both of asked publicly in May 2005 that hundreds of units were at risk.
our filters. We were able to until an outreach session, Initially, the problem was thought
drain about 100 gallons of moderated by Pat Myers, the to be limited to GTs installed in
oil, which was enough to plant manager at Reliant 2000 or later, but problems have
Myers
open one of the filter hous- Energy’s Ceredo Generating been reported on 1999 machines as
ings. We are due for a combustor can Station, was conducted at the Las well. The response from the plant
inspection this fall and are going to Vegas meeting. By the time Myers community on this issue has been
pull the transfer valve as well. We convened the session, much had significant.
think that it is sealing-shoe mate- been accomplished by users work- Symptoms. Representatives of
rial. This unit also was installed in ing collaboratively, including the plants impacted by the issue reported
2001. following: that the first indication of a problem
Reply 2: Our company has four n The transfer-valve manufacturer usually was that the filter housing
7EAs that were installed between and the GT OEM were contacted could not be completely drained dur-
2002 and 2004. The transfer valves in May; both said they were ing a routine filter-element change-
for the lube-oil coolers and filters unaware of the problem. out. Another indicator: A visible oil
have the same GE part number that n The two vendors were sent failed stream impinging on the bulls-eye
you have. Our original problem was shoes and samples of lube oil for sight glasses installed in both the
the inability to isolate a lube-oil analysis and RCA. online and offline filter housing. In
cooler for inspection. The original After the user network identified most cases, the transfer valve was
COMBINED CYCLE JOURNAL, Fourth Quarter 2005 13
7EA Users Group
rial analysis revealed both thermal
degradation (discoloration) and
chemical incompatibility (volume
swell). These mechanisms acting in
concert would accelerate failure by
breaking down the polymer chains
that give the material its strength.
RCA aside, the bottom line is
that the 7EA users collectively have
identified what appears to be a very
practical and immediate solution to
Shoe Port the shoe deterioration problem.
First recommendation is that if
you find shoe seal material in your
12. Deterioration of transfer valves, do not switch the
polyurethane shoe valve position until you inspect the
material illustrates that transfer valve. Next, completely
this valve has lost its flush the lube/hydraulic oil system
ability to prevent fluid as you would a new installation—
Shoe Port
flow between online this to ensure that hideout loca-
and offline filter com- tions are swept clean and all debris
partments is removed. Finally, replace the
degraded shoes with ones of Viton
11. Shoe locations are identified in simplified sketch A. In fact, it probably is appropriate
of a transfer valve to switch to Viton A as soon
as convenient. Replacement
Material recovered
from screen serving shoes only cost about $300
No. 1 bearing each.
Shoe removal and replace-
ment is a relatively easy task.
Here are the simple steps:
n Remove plugs at the lube
oil pumps.
n Pump oil from filter com-
partments into the main
sump.
n Remove the valve from its
13. Pieces of polyurethane were 14. Where has all the seat material body.
collected in the screen protecting the gone? Answer is obvious: every- n Replace “O” rings.
No. 1 bearing on one machine where. At left are particles found in n Install new shoes.
the main tank, in the center is debris n Reinstall valve.
cycled to see if it would seat. After from the generator tank, at right are
cycling, chunks of green plastic-type large chunks removed from the lube-
material flowed through the drain on oil filter Locking in rocking
the filter housings. vanes, blades
Once the 7EA users began col- but unanimity had not been achieved
laborating, other interesting facts prior to the Las Vegas session. Here It wasn’t long ago that Rodger Ander-
came into light: are the thoughts of some experts: son and his colleagues at DRS-Power
n Some users had “quietly” replaced n Glycol contamination of the oil Technology Inc (PTI), Schenectady,
their shoes with another material caused a chemical reaction with NY, revealed to 7EA owner/operators
thinking that the original mate- the polyurethane. (and later to 7FA users) a cost-effec-
rial may have been overheated n Oil temperature exceeded the tive method for solving the “loose
during oil flushing of the system. material’s thermal rating (200F blade” problem adversely impacting
n Others had noticed the symptoms for polyurethane, 350F for Viton the operation of many compressors in
of deterioration, but were not sure A, the recommended replace- the 7EA fleet. Anderson (randerson@
of the cause. ment) drs-pt.com, 978-353-5318) specifi-
n The OEM had replaced transfer- n Lube oil was chemically incom- cally addressed the use of PTI’s “fix”
valve shoes on some machines patible with polyurethane. (patent pending) to fifth-stage stator
under warranty as early as Sep- n Glue/epoxy used in manufactur- vanes at the 2004 annual meeting.
tember 2004. ing filter elements reacted with At that time the solution had been
There was much discussion of the oil. applied to a dozen machines; now
polyurethane shoe deterioration dur- n Transfer valve was installed prior the total exceeds 20. Plus, nearly
ing the annual meeting. Plant man- to chemical cleaning of the system half a dozen 7FAs have applied the
agers were very concerned about the at the factory. technique—successfully, according
possibility of damage resulting from n Chemicals from pipe fabrication to Anderson.
the restriction or interruption of oil weren’t completely flushed from Of particular interest at the
flow to bearings, servos, valve actua- the system. 2005 meeting was a short report by
tors, etc, caused by pieces of entrained Formal research suggested that Heather Regnier, PE, a GT engineer
shoe material (Figs 13, 14). the valve shoes most likely failed in TransAlta’s technical services
Root-cause theories abound, because of “stress overload.” Mate- group, Calgary, Alta, on the success-
14 COMBINED CYCLE JOURNAL, Fourth Quarter 2005
ful implementation of the PTI solu- migrate 1/8 in. or more into the flow sioned in 1999 and had accumulated
tion by qualified personnel employed stream, which can initiate a flow about 48,000 hours of operation. Both
by the energy company. disturbance that produces a strong operate base-load on natural gas
But before summariz- once-per-revolution stimu- without steam or water injection.
ing Regnier’s presentation, lus at the tips of down- Turbine inlet temperature at the two
here’s some background for stream rotor blades. plants is 2035F.
those unfamiliar with PTI’s In the extreme, when Inspection revealed evidence of
pinning technique. Ander- sufficient wear occurs at the classic Stage 5 vane rock (dam-
son offers this explanation shim tabs—often referred age to both the slot and vane plat-
for why vanes may rock over to as “ears”—because of forms) and shim migration. Trans-
time: blade movement and the Alta considered the PTI fix as well
n During operation, indi- sharp corners in the casing as the OEM’s patch-ring repair to
vidual vanes are loaded groove, shims can release eliminate rocking—both viable solu-
by pressure forces and Anderson into the flow stream. Result tions. Pinning was selected for two
react against the case. is downstream foreign- reasons: It could be accomplished
n Loading is dynamic, as object damage (FOD). within the time allocated for the out-
pressure fluctuates about The PTI solution recently age and it was about one-quarter the
the mean. implemented by TransAlta cost of the patch-ring repair. Trans-
n When the machine is involved machining holes Alta implemented the fix itself with
shut down, the load is partway into the base of long-distance direction by PTI—the
removed. each vane (Fig 15). Holes first end user to so.
n Loading/unloading/fluc- were drilled on the two sides The TransAlta inspection team
tuation result in relative of the base perpendicular to also found damage on the back end
motion. the direction of air flow such of one compressor.
n The sliding and ham- that PTI’s engineered spring Specifically, there was a crack
mering that result from Regnier dowel pin could be inserted completely though the shroud (Fig
motion wear the vane into adjacent blades pre- 16) on the first row of exit guide
base and casing groove. venting their movement. Of course, vanes (EGV)—the row closest to the
Wear and blade motion allow any shims were drilled so they too are rotor. The complete row of vanes was
shims installed between adjacent retained by the dowel. replaced. In addition, a vane in the
vanes to work their way into the Regnier reported that in Septem- second row of EGVs was found dis-
flow path—even in the lower half of ber and October of 2005 TransAlta placed (Figs 17, 18). Investigators
the compressor. Performance suffers completed majors on two 7EA units concluded that it had been “rocked”
as the shims protrude into the flow (one in Alberta, the other in Sas- out of position. The vane segment
path. Shims have been observed to katchewan) that had been commis- was replaced.
COMBINED CYCLE JOURNAL, Fourth Quarter 2005 15
MAXimize your return on investment.
A single 770MAX Multiparameter Analyzer/Transmitter
can simultaneously measure, display, alarm and output:
� Specific Conductivity
� Cation Conductivity
� pH direct electrode
THORNTON
Leading Pure Water Analytics
800-510-PURE
www.thorntoninc.com/cycle
To add rigidity to vanes at the locking-in vanes by inserting a set in each slot (R17, EGV1, and EGV2).
back end of the compressor—row screw through the base ring and up Olaf Barth, an engineer in
17, and the two rows of exit guide into the center of the each vane’s Dominion Resources Services Inc’s
vanes—TransAlta selected the base. Another part of the procedure combustion-turbine operation servic-
OEM’s “set-screw mod.” It involves is to double stake and peen the vanes es unit, Glen Allen, Va, took a turn
at the podium to
address bucket
rock. He spoke
of severe bucket
rock on at least
one of Dominion’s
GTs equipped
with a turning
gear. It had oper-
ated for about
75,000 hours at a
slow roll (about 30
Barth rpm). Wear was
15. Addition of pin retains both shim 16. Crack in EGV1 shroud extends so significant that seal pins were lib-
and vane. Shim’s retaining ears are through weld erated. The question he posed to the
maintained in mint condition because group: What do you fix, and how?
vane movement is stopped Barth said he knew of instances
where owner/operators replaced
wheels in an effort to eliminate the
problem. Also mentioned was switch-
ing from a conventional turning gear
that typically is operated continu-
ously to a ratchet. Some users have
done this modification to get to cur-
rent design.
He suggested as an interim fix
the metal spraying of bucket roots to
lock them into the wheel. But even-
tually, Barth continued, the wheel
must be fixed. Build-up on the wheel
17, 18. Displaced blade in EGV2 was thought to have been “rocked” loose of a very hard material is another
16 COMBINED CYCLE JOURNAL, Fourth Quarter 2005
7EA Users Group
possible alternative to replacement.
Barth said he and colleagues were
still trying to determine the root
cause of the specific condition. Indus-
try experience is that the softer (than
the buckets) wheels usually take
80%-90% of the wear; buckets the
remainder. However, data from this
recent case show the opposite! Conventional liquid
fuel check valve
19. Standard installation for a liq- 20. Example of coking in a ball-and-
Vendor solutions uid-fuel check valve shows close
proximity of valve to high-temperature
spring check valve that can cause
operational problems
surfaces
Improvements in fuel-
system valves the new valve.
McElrath said this performance
Schuyler McElrath of Jansen’s Air- shows that by eliminating coking,
craft Systems Controls Inc (JASC), the check valves seal properly and
Tempe, Ariz, was behind the podi- prevent evacuation of the liquid fuel
um at the 7EA meeting updating lines. The Valero retrofit proves the
the industry on user experience point conclusively, he suggested:
with the company’s water-cooled After running on gas for as long as 21. Coking is the primary cause of
liquid-fuel check valve, which has 22 consecutive days, Valero still was failures that occur when attempting to
gotten considerable attention of able to transfer to and start on liquid transfer from gas to oil
late. Cited advantage of this prod- fuel without a problem.
uct is its ability to operate reliably Next, he discussed the future
in dual-fuel service without the of actively cooled fuel controls, some-
coking that can cause spurious GT thing that had not been articulated
trips and other operational upsets. in a public forum before the Las
A good backgrounder on the valve is Vegas meeting. McElrath introduced
available in the 3Q/2005 issue of the the company’s so-called actively
COMBINED CYCLE Journal (p 27) cooled combining valve which replac-
as part of the magazine’s coverage es in a single housing purge-air, liq-
of the CTOTF (Combustion Turbine uid-fuel, and fuel distribution valves
Operations Task Force) meeting (Figs 23, 24).
(available at www.psimedia.info/ By eliminating coking and con-
ccjarchives.htm). tamination-related failures (an inte-
McElrath discussed the past, gral fuel strainer removes particu-
present, and future of lates that could cause seal 22. Production water-cooled liq-
fuel control, including failures), he claimed that uid-fuel check valve exhibits robust
a historical perspective the new valve would require design
on why liquid-fuel check service only during regularly
valves have failed and scheduled outages. Specifi- were replaced—regardless of the
how past deficiencies cally, valve maintenance usage frequency between intervals.
can be overcome through would be conducted when In wrapping-up, McElrath said
innovative design (Figs combustor-can end covers that both valves are easily installed
19-21). He then updated
the experience with the
water-cooled valve (Fig
22) at the Valero Energy McElrath
beta site described in the
article cited above. By the end of
October, the Delaware facility had
accumulated more than 8000 actual
operating hours on both gas and
liquid fuel—6500 gas and 1500 oil.
This represents more than 96,000
total hours without a failure of any
kind.
Based on the Valero experience,
McElrath said designers expect the
check valve to have a reliable life-
time of, perhaps, as long as 20 years.
He reported that there has been a
2500% improvement in Valero’s abil-
ity to transfer between gas and liq-
uid fuels and that all of the facility’s
turbine starts on liquid fuel have
23, 24. Combining valve easily bolts on to the engine
been successful since installation of
COMBINED CYCLE JOURNAL, Fourth Quarter 2005 17
7EA Users Group