Beruflich Dokumente
Kultur Dokumente
No. lectures: Up to 18
Core texts:
1
Assignments:
For example,
Are women with families expected to tend the home as well as achieve
within the workplace?
There is theoretical evidence within the literature that generally supports the view that the woman’s
role is also achieving outside the home, in the workplace, although women are generally regarded as
having less freedom to go to work due to family responsibilities. Some literature describes how this
view is stronger amongst certain classes – for example, within the ‘higher class’ lawyer profession.
Women have a harder time than men balancing work and family responsibilities because women
generally have contrasting attitudes and roles relative to men. Married professional women tend to
regard both their work and family roles with equal priority, rather than dedicating more time to their
work (Wallace, 1999). Men see work as a dominating life-long interest which shapes identity and self-
esteem, whilst fatherhood is regarded an obligation (Watts, 2009). In contrast, in the United States, the
expectation is that women are primarily caretakers, responsible for the home. Hence, the perception is
that women are less committed to work which impacts upon their work opportunities (Shapiro, Ingols,
O’Neill and Blake-Beard, 2009). For example, within the Civil engineering industry, factors such as ‘a
culture of presenteeism’, business trips and the need to win business can damage the professional
identity of part-time women engineers (Watts, 2009). Equally, working class women without
professional qualifications are particularly constrained by a lack of affordable childcare, fewer
qualifications and low quality flexible work (Hebson, 2009). Hence, roles, background and attitudes
can mean that family women can have a harder time competing in the workplace than men.
Never-the-less, statistically there has been a drastic rise in the percentage of women going out to work.
In the USA, 60% of all women over 16 are in the workforce. The numbers of married mothers with
children going to work has risen from 19% in 1960 to 71% in 2007 (Shapiro et al, 2009). In the UK,
government policy has also encouraged dual family incomes - women’s incomes are seen as needed to
avoid poverty and to generate personal pensions (Warren, Fox and Pascall, 2009). Hence, there is a
rising trend in family women who go out to work.
Flexible work arrangements have generally helped women to work. Shapiro et al (2009) concluded that
popular stances adopted by women were telecommuting, negotiation around the boundaries of full-time
jobs, and staying in a job with an acceptable work–life balance. Other suggestions were working
flexible hours, and acceptance of lateral rather than promotional job moves. Employer acceptance of
these approaches has helped women to sustain employment within the workplace whilst maintaining a
family.
The strength of opinion concerning whether to work and the need to work varies according to the
disposition, personal attitudes and social class of people. (Hebson, 2009) postulates that, unlike for
men, women can genuinely choose between ‘family work’ and ‘market work’.
2
Regarding class, women in ‘higher class’ professions, such as lawyers, may more easily cope with
demanding careers because they can afford external sources of child care and domestic assistance costs.
They are also more likely to be able to schedule their work to cope with long hours (Wallace, 1999).
This implies that women in higher classes may more readily be regarded as achievers outside of the
home.
For lower classes, such as families in which the father is a manual worker, a lack of income may drive
the woman out to work as a more pressing concern than balancing work and home life (Emslie and
Hunt, 2009). Women are forced, by necessity, to cope and manage by accepting the work that is
available (Emslie and Hunt, 2009). This perspective supports the view that lower class women have
dual roles both working and maintaining the home.
Emslie and Hunt (2009) propose that middle-class women have resources and freedom to reduce their
working hours to achieve their desired work–life balance in terms of busy work lives and time for
oneself. Middle class women also have a role outside the family but possess the luxury to be more
selective than working class women concerning work time commitments.
In conclusion, evidence from the literature suggests that family women are increasingly achieving both
within the workplace as well as running the home. This may be out of necessity, as for working class
women, or because women from higher classes have the freedom to be able to work, or to choose when
to work. Flexible work arrangements have helped, although achieving a work-life balance is often
difficult due to pressures of work, costs of childcare and women assuming greater family responsibility
than men.
References
Emslie, C. and Hunt, K. (2009). ‘Live to Work’ or ‘Work to Live’? A Qualitative Study of Gender and
Work–life Balance among Men and Women in Mid-life. Gender, Work and Organisation, 16(1), 151-
172. Blackwell Publishing Ltd.
Hebson, G. (2009). Renewing Class Analysis in Studies of the Workplace: A Comparison of Working-
class and Middle-class Women’s Aspirations and Identities. Sociology, 43 (1), 27-44. London: Sage
Publications.
Shapiro, M., Ingols, C., O’Neill, R. and Blake-Beard, S. (2009). Making Sense of Women as Career
Self-Agents: Implications for Human Resource Development. Human Resource Development
Quarterly, 20(4), 477-501. Wiley and Sons.
Wallace, J (1999). Work-to-nonwork Conflict among married male and female lawyers. Journal of
Organisational Behaviour, 20, 797-816. Wiley and Sons.
Warren, T., Fox, E. and Pascall, G. (2009). Innovative Social Policies: Implications for Work–life
Balance among Low-waged Women in England. Gender, Work and Organisation, 16(1), 126-150.
Blackwell Publishing Ltd.
Watts, J (2009). Allowed into a Man’s World’ Meanings of Work–Life Balance: Perspectives of
Women Civil Engineers as ‘Minority’ Workers in Construction. Gender, Work and Organisation,
16(1), 37-57. Blackwell Publishing Ltd.
3
Employability
Personal Skills
1) Discipline skills – technical, subject-based skills and knowledge
2) Enterprise skills – enterprising thinking skills concerning drivers of company
performance related to people, marketing, finance and supply chain
4
Topics:
5
1) Operations Management - Strategy, Planning and Control
Purpose
Issues
- Efficiency vs Effectiveness
- Problems vs solutions
- Questions vs answers
- Data vs information
Planning Process
6
Strategic Planning
7
Decision-making Processes
Outside
change Outside
Alternatives
Set objectives Need for a Problem Search Alternatives Evaluate Choice Implement
decision definition Alternatives
Alternatives
Inside Inside
change Monitor
Feedback
Performance gap
Corporate planning
Business plan
Operational budgets
8
Structure
External
Demography
Economics
Politics
Education Shareholders
Finance Orgs.
Customers The
Suppliers
Ecology Culture
Organisation
Unions Competitors
Employees
Government
Media
Technology
- Land Rover has confrontational shopfloor culture, poor quality, production inefficiency
- Smaller Jaguar models selling insufficient volumes
- Japanese-style working practices at Jaguar Halewood, Land Rover Solihull must follow.
- Hertzberg’s hygiene factors - rest areas, wide aisles, décor - motivation initiatives
- Small work groups with greater autonomy in decision making
- ‘Centres of excellence’
- Open communication to solve problems
- halved defect rate, inventories, improved productivity
9
- Petrol electric hybrid car (Prius) from Toyota; green,environmentally friendly, high tech, new
technology, new production methods
- Low profit
- Government support
- Reliant on consumer-finance business
- Increasing long-term liabilities > unattractive to stock market
“You can have any colour you want so long as it is black” (Henry Ford) - a concept from the past!
Car Production
Britain
France
Germany
80 Italy
2001 2003
- Gap Analysis
Now Future
1) Land Rover
Time Cost/
Budget
Scope
(quality)
Workload
Contingency Estimates
Task
Priorities
Skills Commitment People Equipment
Required
11
Project Investment Decisions
n
DCF = Future Sum/(1+ i)
Where,
i = rate of interest per unit time (usually per annum)
n = number of units of time (usually years) that must pass before the
future sum is realised.
30 30 30 30 30 30 30 30 30 30
Project A YRS
1 2 3 4 5 6 7 8 9 10
100
25 25 25 25 25 27 27 27 27 27
Project B YRS
1 2 3 4 5 6 7 8 9 10
80
Project A
2 10
PV of earnings = 30/(1.12) + 30/(1.12) + … + 30/(1.12) = 169.51
NPV of project = 169.51 – 100 = £69.51
Project B
2 10
PV of earnings = 25/(1.12) + 25/(1.12) + … + 27/(1.12) = 145.35
NPV of project = 145.35 – 80 = £65.35
12
An Example – Engineering a software product used in training
Design
Development
Delivery
Implementation
13
Illustrating Project Management Issues Using A Project Management
Software Tool (Zurich Financial Services, 2002)
Project Objectives
PERT Chart
14
Personnel Allocation
Priorities
15
Estimates of Cost
Gantt Chart
16
Resource Chart
Critical Path
17
Some Advice (IBM UK, 1993)
• Original estimate, January 1986 - £5.4 billion (including £0.9 billion for inflation, £1 billion for
contingencies)
• Revised estimate, February 1990 - £7.5 billion
• Actual cost – almost £10 billion.
18
Bidding – Lowest price wins?
Account Management
The importance of :-
• Quality service/products
• Competence
• Industry expertise
• Strong customer relationships
Requires:-
19
Network Diagrams
Task precedence
Early Early
start finish
0 4 10 12 16 21
A F K
1 4 5 19 2 21 21 5 26
4 10
0 0 11 16 16 20
C
Start G J
5 6 11
0 0 0 11 5 16 16 4 20
0 3
3 4 4 11
B 11 19 20 26 26 29
0 3 3 D E
3 1 4 4 7 11 H L M
12 8 20 20 6 26 26 3 29
20
Float Table
Task A B C D E F G H J K L M
Float 1 0 1 0 0 9 0 1 0 5 0 0
Where float = Late Start – Early Start
t = (a + 4m + b)/6
s = (b – a)/6
Where,
t = expected mean duration
a = most optimistic duration
b = most pessimistic duration
m = most likely duration
s = standard deviation of the distribution
(based upon a beta frequency distribution).
Activity a m B t S Precursor
activity(ies)
A 3 5 9 5.3 1 -
B 4 6 6 6 .67 -
C 5 8 10 7.8 .83 A, B
D 3 6 9 6 1 B
E 6 9 15 9.5 1.5 D
F 3 4 5 4 .33 C
G 8 12 15 11.8 1.17 C, E
H 2 6 8 5.7 1 E
J 4 7 9 6.8 .83 G
K 3 5 10 5.5 1.17 F,G
L 7 9 11 9 .67 J,H
M 10 12 15 12.2 .83 L,K
2 2 2 2 2 2 2
Standard deviation = √(.67 + 1 + 1.5 + 1.17 + .83 + .67 + .83 ) = 2.63
Hence, 2.3% probability duration > 66.3 (mean) + 2 x 2.63 = 71.6 weeks
0.1% probability duration > 66.3 (mean) + 3 x 2.63 = 74.2 weeks
21
3) Project Risk Management
Risk
- A negative but well established term
- A detrimental threat or a beneficial opportunity?
- Minimise threats, maximise opportunities e.g. laying oil pipes during
good weather
- “An uncertain event or condition that, if it occurs, has a positive or
negative effect on a project objective” (PMI, 2000)
- “An uncertain event or set of circumstances that, should it occur, will
have an effect on the achievement of the project’s objectives” (APM,
1997)
- Practitioner’s view: Threat management is norm, opportunity
orientation insufficient
Uncertainty
- Must be managed from the earliest stages of the Project Life Cycle
- Concerns sources of ‘variability’ in cost, duration and quality> hence,
difficult to estimate costs
- Concerns ‘ambiguity’ (lack of clarity) caused by project personnel;
lack of data; insufficient detail, structure, experience, knowledge;
assumptions; ‘known unknowns’; ‘unknown unknowns’; bias;
insufficient effort to achieve clarity> hence, difficulties for design,
logistics, objectives, priorities (commitment of resources to
objectives), inter-personal relationships (responsibilities, roles,
communication, competence, co-ordination, control)
22
Using the Six W’s framework
3) What – what is it the parties are interested in? e.g. design issues to
achieve product superiority
4) Whichway – how is it to be done? e.g order of tasks
5) Wherewithal – what resources are required? e.g. no. people, skills,
equipment
6) When – when does it have to be done? e.g. milestones, deadlines
23
Base plans versus contingency plans
Offshore oil or gas laying in the North Sea in the 1970’s involved a number of serious sources of
uncertainty. If no proactive planning had been undertaken, the potential for overwhelming crisis
management was obvious.
The pipes laid in the North Sea at this time were constructed from sections of rigid steel pipe coated
with concrete, welded to the pipeline on the lay barge, then eased over the stern of the barge by taking
up the tension on sets of bow anchors, maintaining a smooth S shape of pipe between the barge and the
ocean floor. As bow anchors approached the lay barge, they were picked up by tugs, carried ahead and
reset. Improperly controlled lowering of pipeline sections could result in a pipe buckle – a key pipe
laying threat. Excessive waves greatly increased this threat. Barges were classified or designated to
indicate maximum safe wave heights for working (3 metres or 1.6 metres). In the face of excessive
wave heights, the operators would put a cap on the open end of the pipe, and lower it to the ocean floor,
retrieving it when the waves reduced. These lowering and lifting operations could themselves lead to
buckles.
The base plans for laying pipe assumed no major sources of uncertainty (opportunities or threats)
would be realised, only minor day-to-day variations in performance that could be expected to average
out.
The potential opportunity provided by unusually good weather and the potential threat posed by bad
weather were assessed using historical weather records. Control was exercised by monitoring progress
relative to the base plan, aggregating all reasons for being early or late until significant departure from
the base plan occurred. A control response was then initiated through a revised base plan based upon
cost-effective contingency planning options. In the case of pipe buckles, contingency planning
revolved around ensuring that enough pipe was available most of the time, as this was the most cost-
effective alternative (Chapman and Ward, 2003).
24
The Project Life Cycle
25
Risk Management Process (RMP)
Risk Efficiency
Within the North Sea offshore oil project described earlier, hook-up of the pipeline to the platform was
scheduled for August using a barge that could cope with waves up to 1.6m high. Risk analysis
demonstrated that, because this hook-up was late in the overall project sequence there was a significant
chance that hook-up would be delayed until November or December when the chance of waves greater
than 1.6m was very high – delaying the project until Spring. The risk-averse route was to use a 3m
wave height barge which, although had a daily cost that was twice as much, was cheaper than waiting
until Spring.
1.0
3.0 m barge
Cumulative
probability
1.6 m barge
0.5
Cost
Expected cost Expected cost
for 3.0m for 1.6m
barge barge
The 3.0m barge has a lower risk cost because the curve is steeper, and a lower expected cost because there
is less cost variation. On average, the 3.0m barge is cheaper.
26
Risk Efficient Options
Non-feasible
solution area
Cost risk
•A
•G
Feasible solution
•B area
•F
•E
•D •C
Risk-efficient
boundary C - G
Expected
Cost
27
3) Human Resource Management
Management
Leadership
- Leaders vs Managers
• Deciding what to do ….
• Delivery ….
(Kotter)
28
- Types of leader
Some traits:-
Self-confidence
Assertiveness
Vision
Conviction
• Power-orientated
- Path-Goal Theory
29
- Action-centred Leadership
High
Human Democratic
Relations
Showing
consideration
i.e. people
orientated Laissez- Autocratic
faire
Low
Low High
30
- Hersey Blanchard’s Situational Leadership Theory
High
Participating Selling
Leader
Relationship
Behaviour
Delegating Telling
Low
31
- Dealing with conflict
Latent conflict
Manifestation
Aftermath
32
Motivation
Self
Actualisation
Self Esteem
Social
Security
Physiological
This theory has not been validated by research, but generally and widely
accepted.
33
- Alderfer’s Three Factor Theory – or ERG Theory
Existence e.g. Relatedness e.g. Growth e.g. self
Physiological and Social needs esteem and self
safety needs actualisation
Physiological
34
- McClelland’s Theory of Needs
Seek friendship
Seek co-operative situations
35
- McGregor’s Theory X and Theory Y
• Most individuals must be coerced, directed and threatened with punishment to get them to put
forth adequate effort towards the achievement of organisational objectives
• The average person prefers to be directed, wishes to avoid responsibility, has relatively little
ambition and wants security above all
• The average person does not inherently dislike work. Depending on controllable conditions,
individuals may find work satisfying and undertake it voluntarily, or regard it as a source of
punishment and avoid it if possible
• Man will exercise direction and self-control in the service of objectives to which he is
committed
• The average person learns, under appropriate conditions, not only to accept, but to seek
responsibility
• The capacity to exercise a relatively high degree of imagination, ingenuity, and creativity in the
solution of organisational problems is widely, not narrowly distributed in the population
• Under the conditions of modern industrial life, the intellectual potential of the average person is
only partially utilised
36
- Reinforcement Theory
Behaviour Consequence
Reinforcement
People work harder with goals than without. Goals need to be achievable
and challenging, but not too challenging.
The degree of equity that an individual perceives exists within the work
situation is a major input into their job performance and satisfaction i.e.
for each individual, output is related to input leading to perceived
inequity if different relative to others.
Hence, strength of motivation = f (perceived inequity).
Practically, rewards should be linked to performance.
- Expectancy Theory
- Hawthorne Effect
People work harder when they feel that they are being observed.
37
- Some motivational Job Characteristics
• Skill variety
• Tasks – important and defined
• Autonomy
• Feedback – on performance
• See end Product
• Job enrichment - interest
• Job enlargement - scope
- Management by Objectives
• Goals
• Plan to achieve goals
• Corrective actions to keep on target
• Periodic measurements, formal reviews, performance appraisals
38
Teamwork
Accountability
Leadership
Expectations
Co-operation
Open Communication
Roles
Shared Goals
Expertise Information Respect
Empowerment Trust
• Shared goals
• Commitment to group
• Acceptance of group values
• Mutual trust
• Full participation
• Consensus decision making
• Good communication
• Open discussion
• Some conflict
• Non-dominating chair
• Constant evaluation
• Moderate size – optimal size 4 to 6? – lose productivity if too big
• Pre-preparation i.e. hard working culture
39
- Characteristics of Effective Teamwork (Zurich Financial Services)
- Stages of communication
Communication – ‘not just telling it but getting it understood’
Increasing
risk and 1) Peak
trust
2) Feelings,
emotions
40
- The Ground Rules for Human Interaction
41
- Group Problem Solving
• Advantages
More strategies
Increased knowledge and skill
Successful implementation more likely
Snowball effect
Increased legitimacy
Less errors
Positive synergy
• Disadvantages
Leader domination
Groupthink: symptoms
Sense of invulnerability
Pressure to conform
Rationalisation and discounting of warnings
Ambiguous responsibility – social loafing
Clashing ideas
Different goals
Extended decision time
42
- Stages in group development
• Tuckman’s Model
Mature
(efficient
and
effective)
Immature
(inefficient
and
ineffective)
43
- Decision-making techniques
• Company worker
• Shaper
• Resource Investigator
• Team Worker
• Chair
• Plant
• Monitor Evaluator
• Completer Finisher
44