EDCON/EHV/L-37-38 Erection Schedule

Price breakup towards erection of materials/ equipment etc.


Service Tax
Unit Rate Total Amount Rate Service Tax
Sl. no. Description of Items Unit Provisional Quantity (Rs.) (Rs.) (Rs.) Amount (Rs.)
Mejia-Kly
LILO at IISCO
Burnpur Feeder Total
1 2 3 a b 4=a+b 5 6 7 8
1 Survey
a) Detail survey including preliminary survey, Km 4 0.5 4.5
plotting of towers in the route profile drawing,
line chart, towerschedule etc. for approval.

b) Check survey including preparation & sub- Km 18.5 1.2 19.7


mission of profile drawing, tower spotting, line
chart etc. for approval.

c) Forest survey as mentioned in specification Km 1 0.5 1.5

2 Earth work in excavation in foundation


Trenches, drains etc. including dressing of
sides & ramming of bottoms, lift upto 3.0 m,
including getting out the excavated soil &
disposal of surplus excavated soils as
directed within a lead of 50m complete as per
specifications, drawing & instruction of
Engineer-in-charge:
a) Ordinary soil Cum 6000 1250 7250
b) Slushy soil Cum 5000 250 5250
c) Hard soil mixed with gravel & moorum Cum 500 50 550
d) Ordinary rock Cum 500 50 550
e) Hard rock (requiring blasting) Cum 100 10 110
f) Hard rock (blasting prohibited) Cum 50 10 60

3 Extra over item (2) above for excavation in


foundation for every additional lift of 1.5m or
part thereof over the initial lift of 3.0m:
a) Ordinary soil Cum 900 250 1150
b) Slushy soil Cum 750 50 800
c) Hard soil mixed with gravel & moorum Cum 75 10 85

Page 1 Signature with stamp of Bidder


EDCON/EHV/L-37-38 Erection Schedule
Service Tax
Unit Rate Total Amount Rate Service Tax
Sl. no. Description of Items Unit Provisional Quantity (Rs.) (Rs.) (Rs.) Amount (Rs.)
Mejia-Kly
LILO at IISCO
Burnpur Feeder Total
1 2 3 a b 4=a+b 5 6 7 8
d) Ordinary rock Cum 75 10 85
e) Hard rock (requiring blasting) Cum 0 0 0
f) Hard rock (blasting prohibited) Cum 0 0 0
4 Earthwork in filling in excavated pits, trenches,
plinth&sides of foundation etc. in layers not
exceeding 200mm in depth, consolidating &
dressing each deposited layer by ramming and
watering, including cost of supply &
carriage of materials etc. complete as per
drgs., specifications & directions.
a) with earth obtained from excavation of Cum 9000 1250 10250
foundation (excluding rock)
b) with sand Cum 500 100 600
c) with earth obtained from borrow pits inclusive Cum 1000 50 1050
of excavation & carriage/haulage/
transportation.
5 Fitting of template and setting of stub (4 stubs
per tower)--stub to be upplied by DVC free of
cost:
A For 220 kV Tower
a) A type tower (maximum deviation 2 degree) Per Tower 37 1 38
b) S type tower (maximum deviation 15 degree) Per Tower 4 1 5
c) B type tower (maximum deviation 30 degree) Per Tower 5 0 5
d) C type tower (maximum deviation 60 degree) Per Tower 12 0 12
e) D type tower (maximum deviation 90 degree) Per Tower 6 5 11
f) Special Line Crossing Tower Per Tower 0 0 0
(maximum deviation 5 degree)

Page 2 Signature with stamp of Bidder


EDCON/EHV/L-37-38 Erection Schedule
Service Tax
Unit Rate Total Amount Rate Service Tax
Sl. no. Description of Items Unit Provisional Quantity (Rs.) (Rs.) (Rs.) Amount (Rs.)
Mejia-Kly
LILO at IISCO
Burnpur Feeder Total
1 2 3 a b 4=a+b 5 6 7 8
6 Supplying, straightening, cutting, bending, MT 42 5 47
cranking, hooking, fixing,binding & placing at
any position in superstructure, foundation, &
plnth with M/S/ Torsteel reinforcements in all
works of concrete, masonry etc.including
supply of binding wire with 18SWG (1.05mm)
galvanised wire twisted tight and/or welding
the splices where necessary as per IS codes
or direction and holding in position with steel
rod spacer/chairs/horses etc. complete.
7 Hiring, erecting, centering, supporting, stiking, Sqm 500 100 600
cleaning etc.of formwork of approved design
with staging, props and supports for plain &
RCC works with all accessories and at all
heights including removal of forms as per
drawings, specificvations & directions.
8 Charges for shoring & strutting of pits includ- Sqm 50 10 60
ing cost of materials required for this purpose
& fixing in position during excavation and/or
concreting works as per specifications and
directions.
9 Providing and laying in position plain cement
concrete in foundation &plinth with coarse sand
& 20mm & down stone aggregates of approved
quality, well graded, washed and screened
including cost of supply & transport of all
materials to site, mixing, laying, vibrating, curing
etc. complete but excluding centering &
shuttering as per drawings, specification &
direction with:
a) Mix 1:4:8 Cum 2 1 3
b) Mix 1:3:6 Cum 5 3 8
c) Mix 1:2:4 Cum 3 2 5

Page 3 Signature with stamp of Bidder


EDCON/EHV/L-37-38 Erection Schedule
Service Tax
Unit Rate Total Amount Rate Service Tax
Sl. no. Description of Items Unit Provisional Quantity (Rs.) (Rs.) (Rs.) Amount (Rs.)
Mejia-Kly
LILO at IISCO
Burnpur Feeder Total
1 2 3 a b 4=a+b 5 6 7 8
10 Providing & laying in position Reinforced Cement
concrete work in pyramid & chimney of tower
foundation & plinth, with coarse sand & 20mm.
& down stone aggregates of approved quality,
well graded, washed and screened including
cost of supply & transport of all materials to site,
mixing, laying, vibrating, curing etc.complete
including hiring, erection, supporting, striking out,
cleaning etc.of steel muff boxes, but excluding
the cost of reinforcement as per drawings,
specifications &directions with :
a) Concrete mix 1:2:4 Cum 5 3 8
b) Concrete mix 1:1.5:3 Cum 660 110 770
c) Concrete mix 1:1:2 Cum 560 5 565
11 Providing & laying in position Reinforced Cement
concrete work in stepped foundation & plinth,
with coarse sand & 20mm, & down stone
aggregates of approved quality, well graded,
washed and screened including cost of supply &
transport of all materials to site, mixing, laying,
vibrating, curing etc. complete but excluding the
cost of reinforcement and formwork as per
drawings., specifications & directions with:
a) Concrete mix 1:2:4 Cum 5 2 7
b) Concrete mix 1:1.5:3 Cum 150 8 158
c) Concrete mix 1:1:2 Cum 75 60 135

Page 4 Signature with stamp of Bidder


EDCON/EHV/L-37-38 Erection Schedule
Service Tax
Unit Rate Total Amount Rate Service Tax
Sl. no. Description of Items Unit Provisional Quantity (Rs.) (Rs.) (Rs.) Amount (Rs.)
Mejia-Kly
LILO at IISCO
Burnpur Feeder Total
1 2 3 a b 4=a+b 5 6 7 8
12 Providing & laying in position Reinforced Cement
concrete work with coarse sand & 20 mm. &
down stone aggregates of approved quality,
well graded, washed and screened including
cost of supply & transport of all materials to
site, mixing, laying, vibrating, curing etc. complete
but excluding the cost of reinforcement and
formwork as per drawings, specifications &
directions in superstructure with
a) Concrete mix 1:2:4 Cum 2 1 3
b) Concrete mix 1:1.5:3 Cum 8 4 12
c) Concrete mix 1:2:4 Cum 0 0 0

13 Supplying, Fabricating,Transporting, assembl- MT 3.2 0 3.2


ing, placing & fixing in position,Holding down /
foundation steel bolts including threading as
required etc.complete with 2 (two) nos. of nuts.
The 200 mm top portions of bolt are to be
be galvanised.
14 Transporting, Assembling & Erecting of 220 kV MT 610.5 104 714.5
tower members / structures at site with
contractor's own tools & tackles, crane & la-
bour, including fitting, checking, punching & tack
welding of all bolts, nuts and/ or connections
upto bottom cross-arm including aluminium
painting of tack welded bolts & nuts etc., fitting &
fixing of Number plate,Danger plate, Phase plate,
Circuit plate,Bird guard, Anti-climbing devices etc.
complete as per drgs, specifications &
directions.

Page 5 Signature with stamp of Bidder


EDCON/EHV/L-37-38 Erection Schedule
Service Tax
Unit Rate Total Amount Rate Service Tax
Sl. no. Description of Items Unit Provisional Quantity (Rs.) (Rs.) (Rs.) Amount (Rs.)
Mejia-Kly
LILO at IISCO
Burnpur Feeder Total
1 2 3 a b 4=a+b 5 6 7 8
15 Providing, supplying and laying of 20cm thick Sq.m. 100 10 110
second class brick pitching (brick on edge over
one brick flat pitching) on slopes of embankment
canal etc. in 1:4 cement mortar curing preparing
base to proper level of slope, with weep holes
at a spacing of 1.8 metre horizontally and 0.9
metre vertically or as shown in the drawing
complete (with pointing 1:3)
16 Providing, supplying and laying of rouble pitch- Cum 75 5 80
ing (thickness varying from150m to 300m) with
stone boulder including hand packing and
caulking with cement concrete (1:3:6), 0.15
cu.m. per cu.m. of boulder pitching with 20mm
and down stone chips including making weep
holes at a spacing of 180 cm. horizontally and
90 cm. vertically including rough dressing of
the slope for pitching, packing of the back of
weep holes etc. complete
17 Providing, supplying and laying of random rubble Cum 25 5 30
pitching with stone boulder of approved quality
and size and packed as per direction etc.
complete.
18 Dismantling, taking out, removing, stacking, dispo-
sal of unserviceable materials and transportation
of salvaged items to specified DVC Stores,
including loading/ unloading etc.all complete of
following substructures and superstructures at
all elevations as per direction of Engineer-in-charge:
a) R.C.C. work including stacking of reinforcement Cum 1 0.5 1.5
b) 1:3:6 or richer mix Cement concrete work Cum 0.5 0.3 0.8
c) 1:4:8 or leaner mix Cement concrete work Cum 0.5 0.3 0.8
d) Masonary work in cement mortar Cum 0 0 0
e) Steel work in built-up sections including dismembering MT 1 0.5 1.5

Page 6 Signature with stamp of Bidder


EDCON/EHV/L-37-38 Erection Schedule
Service Tax
Unit Rate Total Amount Rate Service Tax
Sl. no. Description of Items Unit Provisional Quantity (Rs.) (Rs.) (Rs.) Amount (Rs.)
Mejia-Kly
LILO at IISCO
Burnpur Feeder Total
1 2 3 a b 4=a+b 5 6 7 8
19 Carrying out necessary field test for soil
samples, preparation and submission of soil
testing report in triplicate giving results of
investigation and related reasons qualitatively,
expected settlement and recommendation
for bearing capacity at different level by
conducting laboratory test on soil samples
as per relevant practice:
a) Determination of crushing strength of soil Nos. 1 1 2
samples
b) Determination of modulus of sub-grade reaction Nos. 0 0 0
(k), modulus of elasticity (E), Poisson's Ratio( m )
c) Moisture absorption test and porosity Nos. 0 0 0
d) Bulk density, natural moisture content,dry Nos. 3 1 4
density, relative density and specific gravity.
e) Standard Penetration Test(SPT) Nos. 5 2 7
20 Grounding of 220 kV Tower with
a) GI pipe, GI flats etc. as per drawing, exclusive per set 61 6 67
cost of all materials to be supplied by DVC free
of cost but including cost of storing, handling &
transporting to site complete as per drawing,
specifications and directions.
b) Counter poise earthing exclusive cost of all per set 4 1 5
material to be supplied by DVC free of cost but
including excavation and backfill & levelling &
cost of materials to site complete as per
drawing, specifications and directions.

Page 7 Signature with stamp of Bidder


EDCON/EHV/L-37-38 Erection Schedule
Service Tax
Unit Rate Total Amount Rate Service Tax
Sl. no. Description of Items Unit Provisional Quantity (Rs.) (Rs.) (Rs.) Amount (Rs.)
Mejia-Kly
LILO at IISCO
Burnpur Feeder Total
1 2 3 a b 4=a+b 5 6 7 8
21 Stringing and sagging of 6 nos. power Km 18.5 1.2 19.7
conductors(AAAC Zebra)(61/3.31mm)
including hoisting of insulators and fixing on the
towers, erection of hardware sets, jointing of
conductors, running out and pulling out of
conductors and tensioning and clipping in with
clamps, fixing of vibration dampers and or
preformed armour rods, number plates, danger
plates, step bolts and anticlimbing devices with
barbed wire etc.,erection of jumpers at the
section/angle towers and hoisting & fixing of
the suspension insulator, stringing for jumper
connection etc.complete in all materials to the
site per route Kilometer of the 220 kV line.(AAAC
zebra conductor,insulators,hardwares &clamps,
repair sleeves, vibration dampers, pre-formed
armour rods, compression joints, non-tension
joints, danger plate, number plate & step bolts
to be supplied by DVC free of cost)
22 Stringing and sagging of one no.earth wire Km 18.5 0 18.5
(7/3.15mm) quality galvanized steel wire
including laying string, tensioning, clamping,
jointing etc.complete including storing, handling,
transporting of all materials of site per route
Kilometer of the 220 kV line (including fixing of
hardwares, vibration damper and/or armour
rods)(Steel ground wire, hardware and clamps,
vibration dampers, armour rods, compression
joints to be supplied by DVC free of cost)

Page 8 Signature with stamp of Bidder


EDCON/EHV/L-37-38 Erection Schedule
Service Tax
Unit Rate Total Amount Rate Service Tax
Sl. no. Description of Items Unit Provisional Quantity (Rs.) (Rs.) (Rs.) Amount (Rs.)
Mejia-Kly
LILO at IISCO
Burnpur Feeder Total
1 2 3 a b 4=a+b 5 6 7 8
24 Service charges to get the following proposal
cleared as mentioned inspec.
a) Railway Clearance per Xing 1 1 2
b) PTCC Clearance
i) for Mejia-Kly LILO at Burnpur S/Stn LS
ii) for IISCO feeder LS
c) Forest Clearance(optional)
i) for Mejia-Kly LILO at Burnpur S/Stn LS
ii) for IISCO feeder LS

TOTAL

Note: LS indicates Lump Sum. Bidder is requested to quote separately for Mejia-Kly LILO and IISCO feeder against sl. No. 25 (a) and (c).