FACULTY OF GEOINFORMATION
AND REAL ESTATE
SGU2053 ENGINEERING SURVEY : GROUP 3

DETAIL SURVEY
AT FACULTY OF
CIVIL
ENGINEERING
(D03)
AHMAD IKRAM BIN OTHMAN
900319-11-5023
AQIFFARHAN BIN ABDULLAH
900319-12-5061
MOHD HANIFAH BIN HARUN
890310-11-5573
MUHAMMAD AZMEER BIN HAJI ROSLI
900816-14-5143
MUHAMMAD FAEZAL BIN ABDUL HAMID
900215-12-6457
MUHAMMAD IZZUDDIN BIN MOHD ROBANI
890330-01-6521
Page | 3

TABLE OF CONTENT

TABLE OF CONTENT......................................................................................3
1 INTRODUCTION..........................................................................................4
2 PROCEDURES..............................................................................................4
2.1 TRAVERSE................................................................................................................4
2.2 ESTABLISH DATUM...................................................................................................5
2.3 DETAIL SURVEY........................................................................................................8
2.4 PROCEDURE OF LEVELING PROJECT.........................................................................8
3 RESULT AND DATA....................................................................................11
3.1 TRAVERSE..............................................................................................................11
3.2 LEVELLING..............................................................................................................14
3.3 DETAILING..............................................................................................................16
Page | 4

1 INTRODUCTION
Title : Detail Survey
Location : Faculty of Civil Engineering, Universiti Teknologi Malaysia,
81310 UTM Johor Bahru, Johor, Malaysia
Duration : 25 February 2011 till 04 April 2011

2 PROCEDURES
2.1 TRAVERSE

1. Our group members arrive at UKK Laboratory at 7.30 a.m. in the morning to collect
all the equipment.
2. After all the equipment and tools has been checked, we moved to our site which is
located at D03 (FKA).
3. When we arrived, we start plan our work so it will be done smoothly.
Page | 5

4. Do the traverse work for seven stations.


5. Seven wooden pegs were set up at seven different places as a station. Make sure that
the station can be seen from the two nearest station.
6. Two prisms were set up at the Station 1 and Station 3.
7. A total station was set up at the Station 2. Key in the coordinate of the Station 2.
8. The horizontal bearing we set after the bearing was key in manually.
9. The total station was pointed to the Station 1 that has a prism and it was pointed by
using the collimator. In this process, the total station must be in ‘circle left’.
10. Make sure the total station cross-hair is centred on prism. Measure the
distance between Station 2 and Station 1.
11. Then, the total station was pointed to the Station 3.
12. The total station cross-hair has centred on prism in Station 3.
13. The reading of the bearing and the distance was recorded.
14. The procedure from 8 to 13 was repeated by using total station in ‘circle right’
position. For this process, no need to save the data because it just to check the bearing
and distance.
15. The procedure from 6 to 14 was repeated by using different station such as the total
station was set at 3, 4, 5 and others station in clockwise direction.
16. The distances between the stations were measures by cantering cross-hair on
prism.

2.2 ESTABLISH DATUM

 9 station GPS was established by staff UKK along Jalan Amal.

 All station has the value of coordinate in GDM 2000 and Cassini GDM 2000.

 Our group have selected of GPS 2 and GPS 3 as reference for produce a datum in our
traverse.

 The location of GPS 2 is at left side of Jalan Amal and near with block D05 and D04,
and the location of GPS 3 is at left side of Jalan Amal and nearly with of block D04
and D01.

GPS 2
Page | 6

Coordinate GDM 2000

Utaraan (M) 172693.19

Timuran (M) 626988.402

Cassini GDM 2000

Cassini-U (m) -53183.796

Cassini-T (m) 8719.7161

GPS 3
Page | 7

Coordinate GDM 2000

Utaraan (M) 172663.565

Timuran (M) 626884.521

Cassini GDM 2000

Cassini-U (m) -53213.4807

Cassini-T (m) 8615.8363


Page | 8

2.3 DETAIL SURVEY

1. First, take out the total station and put on the level tripod at station
2, so it prevent from fell down.
2. Centring the bubble directly into the middle by rotting the foot screw. To centring the
bubble tube it needs to rotate into specific positions during the centring process.
3. Check whether both bubbles are centre or not. We also need to check picket which is
the setup is on the permanent station.
4. First step, switch on the total station and choose total station function.
5. The total station is pointed to the Station 1. The horizontal angle, height of the
instrument, height of the prism with tripod and with pole is measured .
6. Then, the total station is pointed to the station 3.
7. After that, the total station is pointed to any permanent mark such as tree, corner of
the building, road or drain. The draft plan of the permanent mark such as station is
sketched.
8. Then all the reading which is horizontal angle, horizontal distance are recorded.
9. The process is continued until all permanent marks that around the point are recorded,
at least 10 spot heights.
10. Steps 2 until 8 are repeated for all station.

2.4 PROCEDURE OF LEVELING PROJECT

1. The location of the starting point of the fly-levelling, which is BM (G09, Geodetic
station) was identified.

2. The fore staffs was located on the assigned BM and the back staff was located in the
way so that the back sight and fore sight distances were approximately equal, with the
digital level was setup at the midpoint of back staff and fore staff. As the figure
below:
Page | 9

3. The distance of the back staff to the digital level and from the digital level to the fore
staff was measured by using step count.

4. Then, the digital level shot on the fore staff.

5. After finish shot on the first sight, we go through to the second sight which is back
sight which is on the first station in levelling route.

6. Then target the digital level and then shot to the back staff on the station 1.

7. After finish for the first station, change the location of the digital level to the station 1
and bring forward the staff on the back sight to the next station which is station 2.

8. All the measurements that have been taken automatically save in the memory card
that is located in digital level itself.

9. Back sight and fore sight reading were also recorded manually into field book as a
checking.

10. The levelling work was carried out till station 3 which is at station 1 at our loop on the
traversing .So that reduced level that we get from BM carried out to the third station
and establish as the Temporary Bench Mark (TBM) for our next detailing project.
P a g e | 10
P a g e | 11

3 RESULT AND DATA


3.1 TRAVERSE
SURVEY TRAVERSE AFTER C CORRECTION

STATION BEARING ADJUSTMENT OF CORRECT COORDINATES


DISTANCE Latitude depart STN
Fr. To deg. min sec Latitude Depart Latitude Depart U E

1 172693.190 626988.402

1 2 49.558 00 00 00 49.558 0.000 0.0032 0.0000 49.561 0.000 2 172742.751 626988.402


2 3 80.329 94 40 12 -6.540 80.062 0.0052 0.0000 -6.535 80.062 3 172736.216 627068.464
3 4 26.900 99 42 03 -4.533 26.515 0.0017 0.0000 -4.531 26.515 4 172731.685 627094.980
4 5 25.343 167 44 07 -24.765 5.384 0.0016 0.0000 -24.763 5.384 5 172706.922 627100.363
5 6 16.571 245 06 36 -6.974 -15.032 0.0011 0.0000 -6.973 -15.032 6 172699.949 627085.331
6 7 33.821 262 20 47 -4.504 -33.520 0.0022 0.0000 -4.502 -33.520 7 172695.447 627051.812
7 1 63.450 267 57 29 -2.261 -63.410 0.0041 0.0000 -2.257 -63.410 1 172693.190 626988.402
SUM 295.972 -0.019 0.000 0.019 0.000 0.000 0.000

LINEAR MISCLOSURE = 1: 15562


P a g e | 12

SURVEY TRAVERSE AFTER C AND M CORRECTION

ADJUSTMENT
STATION BEARING CORRECT
DISTANCE latitude depart OF STN COORDINATES
Fr. To deg. min sec Latitude Depart Latitude Depart U E
1 172716.707 626862.997
1 2 49.558 346 37 02 48.212 -11.470 0.0031 -0.0007 48.215 -11.471 2 172764.922 626851.526
2 3 80.329 81 17 14 12.168 79.402 0.0050 -0.0012 12.173 79.401 3 172777.096 626930.927
3 4 26.900 86 19 05 1.727 26.844 0.0017 -0.0004 1.729 26.844 4 172778.825 626957.771
4 5 25.343 154 21 09 -22.846 10.969 0.0016 -0.0004 -22.844 10.969 5 172755.980 626968.740
5 6 16.571 231 43 38 -10.264 -13.009 0.0010 -0.0002 -10.263 -13.010 6 172745.717 626955.730
6 7 33.821 248 57 49 -12.140 -31.567 0.0021 -0.0005 -12.138 -31.567 7 172733.579 626924.163
7 1 63.450 254 34 31 -16.876 -61.165 0.0040 -0.0009 -16.872 -61.166 1 172716.707 626862.997
SUM 295.972 -0.019 0.004 0.0185 -0.0044 0.000 0.000

LINEAR MISCLOSURE = 1: 15562

SURVEY TRAVERSE DATUM


P a g e | 13

ADJUSTMENT
STATION BEARING CORRECT
DISTANCE latitude depart OF STN COORDINATES
Fr. To deg. min sec Latitude Depart Latitude Depart U E
172693.19
101 626988.402
0
- -
10 - 0.000
102 107.089 254 04 58 102.98 -0.0020 -29.371 102.98 102 172663.81
1 29.369 5
3 3 9 626885.419
10 0.000 172706.23
103 47.790 332 34 00 42.416 -22.018 -0.0009 42.415 -22.017 103
2 2 4 626863.402
10 0.000 172716.70
104 10.481 357 47 01 10.473 -0.405 -0.0002 10.473 -0.405 104
3 1 7 626862.997
10 0.000 172733.58
105 63.450 74 34 31 16.876 61.165 -0.0012 16.875 61.165 105
4 3 2 626924.162
10 0.000 172752.94
106 66.628 73 06 05 19.367 63.751 -0.0012 19.366 63.751 106
5 3 8 626987.913
10 - 0.000 172731.54
107 26.128 144 59 07 14.992 -0.0005 -21.399 14.992 107
6 21.399 1 8 627002.905
10 - 0.000 172693.19
101 41.008 200 42 43 -14.503 -0.0008 -38.358 -14.503 101
7 38.358 2 0 626988.402
SUM 362.574 0.007 -0.002 -0.0067 0.001 0.000 0.000
8

LINEAR MISCLOSURE = 1: 51861


P a g e | 14

3.2 LEVELLING

LevelPak Level Line Report


Project : leveling
Generated : 10/02/2011 at 15:24:15
Unit : Meter
Level Line : Group 03 Line 001
Heights : Downloaded

Active Pt Name Back Tp. Fore Dist Height Correction Corrected


Height

x 1 22.894
x 1 0.27491 29.94
x 1 2.71833 30.38 1 x.000833
=
x 1 20.451 0.000833 20.451833
x 1 1.59597 29.66
x 2 1.12328 27.92 2 x.000833
=
x 2 20.924 0.001667 20.925667
x 2 1.65710 30.06
x 3 1.30591 20.80 3 x.000833
=
x 3 21.275 0.002499 21.277499
x 3 1.38291 25.62
x 4 1.77162 25.59 4 x.000833
=
x 4 20.886 0.0033332 20.919332
x 4 1.42975 21.34
P a g e | 15

x 5 2.01607 23.11 5 x.000833


=
x 5 20.300 0.0041665 20.3041655
x 5 2.92871 31.34
x 6 0.33977 33.14 6 x.000833
=
x 6 22.889 0.0049998 22.8939998
Total Dist = 328.89

Height at the BM at first reading – Height at the BM at last reading = 22.894 – 22.889
Diff. in Height = 0.005

Diff. in Height = 0.005


No. of stations 6
Correction of Height = 0.0008333

Tolerance = 0.020√ (Total Distance (in km))

=0.020√ (328.89/1000)
= 0.065778 m
P a g e | 16

3.3 DETAILING