1 ) Project Outline
2) Tunnel Building with the TBM
3) Survey Methodology
a: Pre-construction Stage
b: Construction Stage
~ Double Zigzag Traverse
~ Tunnel Guidance System
c: Post-construction Stage
4) Conclusion
Engineering Survey System in TBM Tunnel Construction Engineering Survey System in TBM Tunnel Construction
1
Down Li
ne 1.7 Km
Lok Ma Chau 2 m
1.4 K
3
Up Lin
e 1.7 Km
1) TBM 2) Backup Gentries
4 m
1.4 K Sheung Shui
nnel
3.1 Km TBM Tu
•Total 6.2Km (1.7+1.4+1.7+1.4Km) of tunnel was laid by TBM
Engineering Survey System in TBM Tunnel Construction Engineering Survey System in TBM Tunnel Construction
2) Tunnel Building with the TBM 2) Tunnel Building with the TBM
Ground Surface
Underground Surface
TBM ne l
(Tun g)
Ring te Linin
c r e
Con
Engineering Survey System in TBM Tunnel Construction Engineering Survey System in TBM Tunnel Construction
1
2) Tunnel Building with the TBM 2) Tunnel Building with the TBM
As the TBM thrusted forward, more tunnel As the TBM thrusted forward, more tunnel
concrete lining was put at the back of the concrete lining was put at the back of the
machine. machine.
2) Tunnel Building with the TBM 2) Tunnel Building with the TBM
1800mm
1800mm
Engineering Survey System in TBM Tunnel Construction Engineering Survey System in TBM Tunnel Construction
2) Tunnel Building with the TBM 2) Tunnel Building with the TBM
ine
ead L
Overh
ay
lkw
Wa
Rail
Ra
Wal
il
The lining of the tunnel was formed by a continuation built up of the rings kwa
y
Engineering Survey System in TBM Tunnel Construction Engineering Survey System in TBM Tunnel Construction
2
2) Tunnel Building with the TBM 3a) Survey Methodology - Pre-construction Stage
What is the Prime Objective of
+75mm
Surveying of a TBM Tunnel ?
Construction Tolerance
+/-75mm
Engineering Survey System in TBM Tunnel Construction Engineering Survey System in TBM Tunnel Construction
Fixed Station
Known Station New Station
New Station Line of Sight
Engineering Survey System in TBM Tunnel Construction Engineering Survey System in TBM Tunnel Construction
3b) Survey Methodology - Construction Stage 3b) Survey Methodology - Construction Stage
• Transfer of control station at surface At the tunnel level of the TBM Launching Shaft
Primary
Control Station
At Surface
TB
M
La
Sh unch
aft ing
Secondary
Control Station
Engineering Survey System in TBM Tunnel Construction Engineering Survey System in TBM Tunnel Construction
3
3b) Survey Methodology - Construction Stage 3b) Survey Methodology - Construction Stage
• The control station was moved ahead by traverse to reach the • The traverse continued above the gentry to reach the Laser
last gentry. Station located behind the TBM.
Video Laser Control Last gentry Control
Target Station Station
Station
TBM
Erected
segments
Last gentry
Engineering Survey System in TBM Tunnel Construction Engineering Survey System in TBM Tunnel Construction
3b) Survey Methodology - Construction Stage 3b) Survey Methodology - Construction Stage
Horizontal Control Station and Benchmark
Horizontal Control by Double Zigzag Traverse The same horizontal control station and
benchmark were used throughout the
+/-10m RESECTION Station project.
ng
ni - At first, the horizontal control station in
Li
el form of a bracket was installed at the
nn
+/-250m Tu lower part of tunnel.
+/-250m
- The station was then plumbed up to the
Walkway
+/-250m
roof of tunnel.
ark
+/-250m
hm
nc - The benchmark was set above the walkway.
Be
ADVANTAGES A Double Zigzag Traverse leg consisted of two control Walkway - The bracket was removed to make way
stations at each end. for the construction work.
Redundant survey measurements to eliminate the gross error.
Each traverse leg by itself became a quadrilateral. Invert slab
- The station was transferred onto the
More availability of line of sight from one station to the other for walkway from the roof station and it would
a quick set up AofDouble
station Zigzag Traverse
fixing by methodlinked up the quadrilateral
of RESECTION. Bracket
last beyond the end of the project.
to form a rigid network.
Engineering Survey System in TBM Tunnel Construction Engineering Survey System in TBM Tunnel Construction
3b) Survey Methodology - Construction Stage 3b) Survey Methodology – Tunnel Guidance System
Benchmark 3 z
Benchmark 1 Benchmark 4
Benchmark 2 The Laser Station shoots the
prism target affixed to the Video
bulkhead of TBM. Target
TBM
y
+/-180m +/-180m +/-180m Laser Station
Prism x
Benchmarks were established at every 100th Ring and
they were180m apart.
Engineering Survey System in TBM Tunnel Construction Engineering Survey System in TBM Tunnel Construction
4
3b) Survey Methodology – Tunnel Guidance System 3b) Survey Methodology – Tunnel Guidance System
• Determination of the ORIENTATION OF THE TBM x • Summary
1. XY Plane ist
Laser tw Video 1. The Laser Station determined the 3D position of the TBM
The Laser Station shines onto Target 2. The Video Target determined the twist in XY plane.
the Video Target to measure the y
Plan 3. The Inclinometer 1 determined the roll in XZ plane.
twist of the TBM.
4. The Inclinometer 2 determined the tilt in YZ plane.
Engineering Survey System in TBM Tunnel Construction Engineering Survey System in TBM Tunnel Construction
3b) Survey Methodology – Tunnel Guidance System 3b) Survey Methodology – Tunnel Guidance System
In-house Remote Support In-house Remote Support
Computer Computer Computer Computer
Data Data
processin processin
g g
Engineering Survey System in TBM Tunnel Construction Engineering Survey System in TBM Tunnel Construction
3b) Survey Methodology – Tunnel Guidance System 3b) Survey Methodology – Tunnel Guidance System
In-house Remote Support In-house Remote Support
Computer Computer Computer Computer
Data Data
processin processin
g g
Engineering Survey System in TBM Tunnel Construction Engineering Survey System in TBM Tunnel Construction
5
3b) Survey Methodology – Tunnel Guidance System 3b) Survey Methodology – Tunnel Guidance System
In-house Remote Support In-house Remote Support
Computer Computer Computer Computer
Data Data
processin processin
g g
Engineering Survey System in TBM Tunnel Construction Engineering Survey System in TBM Tunnel Construction
3b) Survey Methodology – Tunnel Guidance System 3b) Survey Methodology – Tunnel Guidance System
In-house Remote Support In-house Remote Support
Computer Computer Computer Computer
Data Data
processin processin
g g
Engineering Survey System in TBM Tunnel Construction Engineering Survey System in TBM Tunnel Construction
3b) Survey Methodology – Tunnel Guidance System 3b) Survey Methodology – Tunnel Guidance System
6
3b) Survey Methodology – Tunnel Guidance System 3b) Survey Methodology – Tunnel Guidance System
Thrusting Jacks Articulation Jacks
6mm
15mm
The Articulation Jacks allow the TBM to twist and turn flexibly
Current Design Current Cutter and advance forward in the direction of the design tunnel axis.
Projected Design Tunnel Tunnel Center Head Center
Center in 10m ahead
Engineering Survey System in TBM Tunnel Construction Engineering Survey System in TBM Tunnel Construction
3b) Survey Methodology – Tunnel Guidance System 3b) Survey Methodology – Tunnel Guidance System
Thrusting Jacks Articulation Jacks Thrusting Jacks Articulation Jacks
Erected Rings Shield Tail Shield Front Erected Rings Shield Tail Shield Front
The Articulation Jacks allow the TBM to twist and turn flexibly The Articulation Jacks allow the TBM to twist and turn flexibly
and advance forward in the direction of the design tunnel axis. and advance forward in the direction of the design tunnel axis.
Engineering Survey System in TBM Tunnel Construction Engineering Survey System in TBM Tunnel Construction
3b) Survey Methodology – Tunnel Guidance System 3b) Survey Methodology – Tunnel Guidance System
Thrusting Jacks Articulation Jacks Thrusting Jacks Articulation Jacks
Erected Rings Shield Tail Shield Front Erected Rings Shield Tail Shield Front
The Articulation Jacks allow the TBM to twist and turn flexibly The Articulation Jacks allow the TBM to twist and turn flexibly
and advance forward in the direction of the design tunnel axis. and advance forward in the direction of the design tunnel axis.
Engineering Survey System in TBM Tunnel Construction Engineering Survey System in TBM Tunnel Construction
7
3b) Survey Methodology – Tunnel Guidance System 3b) Survey Methodology – Tunnel Guidance System
Thrusting Jacks Articulation Jacks Thrusting Jacks Articulation Jacks
Erected Rings Shield Tail Shield Front Erected Rings Shield Tail Shield Front
The Articulation Jacks allow the TBM to twist and turn flexibly The Articulation Jacks allow the TBM to twist and turn flexibly
and advance forward in the direction of the design tunnel axis. and advance forward in the direction of the design tunnel axis.
Engineering Survey System in TBM Tunnel Construction Engineering Survey System in TBM Tunnel Construction
3b) Survey Methodology – Tunnel Guidance System 3c) Survey Methodology – Post- construction Stage
1. Articulation Jack An 8 points Wriggle Survey is carried out on
Elongation
Shield Tail Shield Front the as built profile of the tunnel lining
Erected Rings
1) For construction tolerance check
2) For dimension tolerance check of the diameter
TBM Axis
(+/- 75mm)
1
8 2
6 4
The elongation of all jacks and the shield tail clearance are measured by
sensors and sent to the computer to derive the position of ring just erected.
5
Engineering Survey System in TBM Tunnel Construction Engineering Survey System in TBM Tunnel Construction
21-Jun-04 Kwu Tung to Chau Tau excess excess north 51,000 low
Train 23-Dec-04
Up Track (1.7Km) 25mm in 30mm in 1 in 5mm too
Shung Shui to Kwu Tung shortage shortage north 44,000 low
Up Track (1.4Km) 9mm in 10mm in 1 in 6mm too
08-Apr-05 Kwu Tung to Chau Tau shortage shortage north 104,000 low
Engineering Survey System in TBM Tunnel Construction Engineering Survey System in TBM Tunnel Construction
8
4) Conclusion Ring Built Out of Tolerance (+/-75mm)
Length of tunnel Length of tunnel constructed outside the
constructed within the Allowable Construction Tolerance (+/-75mm)
Location
Allowable Construction
Tolerance (+/-75mm) Factor A Factor B Factor C
Down Track (1.7Km) 1681m (97.5%) 16m 16m 11m
Shung Shui to Kwu Tung
Down Track (1.4Km)
1472m (99.7%) ~ ~ 4m
Kwu Tung to Chau Tau
Up Track (1.7Km)
1617m (93.8%) 57m ~ 50m
Shung Shui to Kwu Tung
Up Track (1.4Km)
1470m (99.9%) ~ ~ 2m
Kwu Tung to Chau Tau