Beruflich Dokumente
Kultur Dokumente
Materials Management
A. Generally
Materials management is an important element
in project planning and control.
Materials represent a major expense in
construction (40% to 60% of the cost of all
construction works-these percentages vary
according to the type of works being
undertaken and the exact methods of
construction)
1
Example:
If materials are purchased early,
• Capital may be tied up and interest
charges incurred on the excess inventory
of materials.
• Materials may deteriorate during storage
or be stolen unless special care is taken.
For example, electrical equipment often
must be stored in waterproof locations.
Delays and extra expenses may be incurred if
materials required for particular activities are
not available.
Accordingly, insuring a timely flow of material
is an important concern of project managers.
Materials management:
• During the monitoring stage in which
construction is taking place.
• Decisions about material procurement-
during the initial planning and scheduling
stages.
The availability of materials may greatly
influence the schedule in projects with a fast
track or very tight time schedule:
2
Sufficient time for obtaining the necessary
materials must be allowed.
In some case, more expensive suppliers or
shippers may be employed to save time.
Efficient materials management involves:
3
contractor has no choice but to purchase and
use the materials as specified in the contract.
In other areas, such as Turnkey Contract,
choice of materials is left to the discretion of
the contractor and the contractor in this case
must have a full knowledge of possible
substitutes both between and within materials
groups in order to maximize his profit.
The contractor needs to search for alternative
materials which either match all the existing
properties of the current material but yield a
lower unit cost, or else provide additional
properties for the same unit cost.
He is also required to have the knowledge of
the available suppliers for the various materials
in the market.
4
On the other hand, if the materials purchased
exceed the actual amount required for the
work, there will be wastage of the material
which involves over expenditure and also
unnecessary storage costs.
5
iii. Cause access problem around site –
especially when the items are bulky, such
as brick and sand, and the site is not
properly organized.
Some of the materials may have to be
removed altogether and this leads to
additional cost to the contractor.
iv. Cause increase in storage cost – bigger
storage facilities may be required or else
some of the suppliers have to be kept
somewhere else at considerable extra
expense.
6
Where materials are late in arriving on site,
they may:
i. Cause costly delays in the construction
program – Labour cost increases as the
workforce remains idle because of non
delivery of key materials and also the
production morale will be damaged due to
frequent stoppage of work.
7
i. Specific instruction on each order –
delivery will not be needed until a
certain date.
8
The whole quantity could be ordered in
advance and with the generous supply to
spare.
Rigid control would not be necessary as the
application of such control could cost more
than the value of the materials themselves.
9
i. Large quantities are required in
relatively short notice – as a result of a
variation for example. The contractor has
to place order as soon as the need arises
and he must also identify the alternative
source of supply for the material in the
market.
10
Advantages:
11
B. Purchasing Procedures
Construction firms who typically produce
higher profit margins, pay much more
attention to purchasing materials and often
employ specialist staff to carry out purchasing
and to ensure that materials are procured at
the lowest possible cost.
A competent purchasing department is very
important to the overall organization and a
prerequisite for the successful and profitable
completion of any job.
12
The Purchasing Cycle
a) Contractor/user/buyer who starts the
purchasing cycle
13
b) Supplier selection by contractor
14
collection of several competitive quotations.
Normally, the criteria for the selection of a
supplier are:
15
The specifications in the purchase order
consist of two parts:
• Invoicing instructions.
16
One such set of purchase conditions may
include the following:
• Definitions – buyer, seller, goods,
contract etc.
17
18
Example of Purchase Order Form
ii. Specification of Goods
19
d) Supplier Receipt
e) Expediting by Contractor
20
The expeditor’s main tasks are:
21
asking supplier to confirm that he is
going to meet delivery commitment.
22
f) Delivery by Supplier
23
i. The account department so that
payment of the supplier’s invoice can
be made
24
The stock records must be updated to show
the addition of the new arrivals into stock
holding.
C. Storage Procedures
Storage forms the last link in the material
control chain.
25
Storage Procedures
26
a) Accommodation – requirements for
floor space, shelving, stockyards, etc.
27
purchasing activities from the purchasing
department.
28
c) Location – the ability to find the
goods when they are needed.
29
An item can be found easily,
provided that the part number is
known.
Example: 12mm diameter stopcock
in pigeon hole a/1 i.e: by matching
part-number with the address of
the item.
30
Example of a stock index form
d) Preservation – problems of limited
shelf-life, contamination and storage
environment.
31
Goods in soft packages such as cement,
lime etc and goods in tin such as paint,
adhesive etc. should also be handled
carefully and hook must never be used
when dealing with these materials.
32
g) Security – prevention of theft, willful
damage or misallocation.
33