Beruflich Dokumente
Kultur Dokumente
Project
John Parker, Technical Director WSP Cantor Seinuk, describes the challenges of
working on the foundations of the tallest building in Europe
The Shard at London Bridge will not only be the tallest building in such like. It is surrounded by a concrete secant piled wall; the floor
Europe, it will also be one of the most distinctive. Its 310m high, slabs are also constructed in reinforced concrete.
tapering shape and glass cladding will provide a unique addition to The lowest slab is 13.34m below ground level and acts as a raft
London’s skyline when it is completed in 2012 (Fig 1). to transfer building loads into the bearing piles. Under the main
Although the shape of the building is unusual, it is ideal for its core it is 3m thick; elsewhere it is generally reduced to 1.5m. A
mixed use occupancy. Deep floor plates at the lower levels are drainage layer beneath the raft reduces uplift pore pressures.
provided for office tenants, medium sized floor plates at mid-height London Bridge station is constructed on Victorian brick arches
suit the restaurants and hotel, while the smallest floors at the top which, in some cases, are very close to the secant wall. In order to
of the building allow natural light to penetrate through the safeguard these assets a complex monitoring system has been
residential apartments. At the highest point (the ‘spire’) is a viewing specified by WSP Geotechnics. This uses a combination of
gallery, from which the public will be able to enjoy spectacular automatic and manual monitoring to report movements in Network
views across the capital. Rail structures and tracks, and in other surrounding buildings. An
Piling for the building began in March 2009 following the Emergency Preparedness Plan details the actions to be taken in
demolition of the 26-storey Southwark Towers. Engineer WSP the event that movements are greater than predicted by WSP’s
Cantor Seinuk and architect Renzo Piano Building Workshop have ground movement assessment (GMA).
designed a building for client Sellar Property Group that completely The Jubilee Line passes the site near the northern edge.
fills the site adjacent to Network Rail’s station. Main contractor
Mace and its subcontractors have a complex logistical task to
build the tower, while avoiding disruption to the busy station. A 1 The Shard as it will appear on the London skyline
(Photo: Sellar Properties)
view of the site in June 2009 is shown in Fig 2. 2 The site in June 2006, with three piling rigs working
(Photo: Nicola Evans, WSP Cantor Seinuk)
Basement 2a The site from above taken from New London Bridge
House to the north of the Shard
The Shard has a three storey basement occupied by plant rooms, 3 Opposite: Plunge column alignment rig
a mechanical car stacker, ‘back of house’ rooms for the hotel and (Photo: Nicola Evans, WSP Cantor Seinuk )
New piles have been positioned to avoid the London Underground Stratum Approx depth to base of stratum below ground level
exclusion zone, and the GMA shows that effects on the tunnel are
minimal. Other nearby London Underground assets include two Made ground / alluvium 4.5m
long-disused shafts on the line of the western secant wall. One, a River terrace gravels 9m
stair shaft, had been filled with concrete in the 1950s, with some of
the stair steelwork left in place. Because it would not be possible London Clay 31m (west) / 35m (east)
to cut through the steel with the piling rig, the entire shaft was
Woolwich and Reading beds 45m (west) / 51m (east)
removed from within a temporary works coffer dam. The other, a
lift shaft, was filled with foam concrete before boring the secant Thanet sands 59m (west) / 63m (east)
piles. A disused tunnel, which previously provided access to the
shafts from the rest of London Bridge Underground station, was Chalk Not proven
also filled with foam concrete to avoid the risk of damage during Table 1: Sequence of strata
piling and basement excavation.
Top-down construction
The Shard basement is being built ‘top down’. This allows
substructure and superstructure construction to proceed
simultaneously, giving considerable programme benefits. In
addition, by installing slabs as excavation proceeds, the deflection
of the secant wall, and the risk of movement in the surrounding
structures, are both minimised. The sequence is complex but can
be summarised as follows:
– Install secant piles, bearing piles and plunge columns, working
from ground level (Fig 4).
– Construct level 00 (ground floor) slab, leaving an opening
around the core and moling holes for removal of spoil.
– Excavate to B2 level (the slab at B1 does not cover the whole
basement; it is also safer to excavate double storey heights
2a
4 5
6 7
4 Sequence: piles and plunge columns core, and avoid eccentricity between the core centroid and the
installed from ground level centroid of the group of plunge columns. This was further
5 Sequence: level 00 cast; core started from B2 complicated by the need to position plunge columns away from
6 Sequence: B2 cast; plunge columns propped
from B3; steelwork started core openings, and to ensure that the new piles did not clash with
7 Sequence: completed building (Photos: John existing pile shafts. After some iteration a suitable arrangement
Parker, WSP Cantor Seinuk was devised. The surprisingly high accuracy of the CAD overlay of
the existing pile drawing led to only minor changes after the
Southwark Towers pilecaps were demolished; nevertheless the pile
when working top down). group was re-analysed in order to ensure that pile loads and
– Build a section of the core at B2 and commence the slipform. settlements would be acceptable.
The core is supported on plunge columns, using large numbers
of shear studs (Fig 5) Conclusion
– Cast the B2 slab, again leaving an opening around the core. The foundations for the Shard at London Bridge present a
– When the slipform has passed ground level, fill in the central challenge for designers and contractors because of the size and
opening and tie the core to the level 00 slab. weight of the building, the presence of existing under-reamed
– Meanwhile, excavate to B3 level. The depth of the raft slab and piles, and the proximity of Network Rail and other infrastructure.
the B3-B2 storey height effectively provide a double height Careful design and close teamwork by structural and geotechnical
space. engineers, architects, main contractor and piling subcontractor has
– When the slipform has passed level 08, commence steel led to a practical and efficient result.
erection.
Credits:
– Cast the B3 slab; brace the core plunge columns laterally from Client: Sellar Property Group Ltd
the slab (Fig 6). Structural and geotechnical engineer: WSP Cantor Seinuk
Architect: Renzo Piano Building Workshop
– Complete the core walls from B3 to B2, fill in the B2 slab Associate architect: Adamson Associates
opening and remove the plunge column bracing. At this stage Building services engineer: Arup
Cost consultant: Davis Langdon
the slipform will be at about level 30, with the steelwork a few Project manager: Turner and Townsend
floors beneath. Main contractor: Mace
Piling subcontractor: Stent Foundations
– A section through the lower part of the completed building is Concrete subcontractor: Byrne Brothers
shown in Fig 7. Steel subcontractor: Severfield Reeve
It is believed that plunge columns have not previously been used
to support the core of a major building. The main challenge was in
positioning them so as to provide a balanced support beneath the