Beruflich Dokumente
Kultur Dokumente
2 4 May 2005
NEWSLETTER
Planning processes
INDICATED PROBABLE
Three distinct levels of planning are
recognised in developing the reserves:
MEASURED PROVEN
• Life-of-mine plan (LOM),
• Long-term planning (LTP), which
GEOTECHNICAL, MINING, ECONOMIC, METALLURGICAL, MARKETING,
follows from the LOM, and
ENVIRONMENTAL, SOCIAL AND GOVERNMENTAL FACTORS MAY CAUSE MATERIAL
• Short-term planning, (STP) which in TO MOVE BETWEEN RESOURCES AND RESERVES
turn follows from the LTP. Figure 2. Classification of confidence levels
Each of these stages of planning represent
different levels of risk and have different having a production cost greater than the All figures are presented in present-day
objectives. It follows therefore that the cut-off value. The specification of this cut-off value terms and represent the
planning criteria for each planning phase cost is related to an acceptable risk. marketability of the ore reserve on the
should be different. Typical financial criteria that are in world market in competition to other
common use, such as net present value reserves. Figure 3 can therefore be used
Life-of-mine plan (LOM) in the marketing strategy of the mine
(NPV) or internal rate of return (IRR), are
Development of the LOM plan is the first which leads to strategic decision making
insensitive to the boundary limit location.
step in the planning process and has the and provides the communication medium
These criteria are most sensitive to the
following objectives: between marketing, management
price assumed for the product, the
• define the inventory of ore reserve that production schedule for mining, as well as and planners.
is mineable within the assumed the assumed discount rate. Since the In this figure, it is assumed that the cost of
economic parameter, mining schedule, i.e. the order in which production represents the minimum in
• define the production capacity for the the ore and waste blocks are removed, is terms of the present technology for
remaining life of mine, still unknown at this stage, these criteria operations.The function of the mine
• define the infrastructure requirements, cannot be used effectively for this planning department is to constantly
• determine the fixed capital costs, and purpose. When defining the total
• provide information for strategic inventory available for exploitation, it is
decision making. important that every block be afforded
an equal opportunity to contribute to
To achieve these objectives, certain
the profitability.
planning criteria need to be adopted.
Assuming different cut-off costs, the total
Cut-off cost planning criteria inventory available in each incremental
The cut-off cost criteria can be defined cost can be calculated and presented on
as follows: a curve as shown in Figure 3.The average
The LOM pit limits are such that no ore is cost of mining to within this cut-off cost is
mined which will result in the final product represented by the average cost curve.
Figure 3. Reserve marketability
Copyright
© Copyright 2005. Australian Centre for Geomechanics (ACG),The University of Western Australia (UWA). All rights reserved. No part of this newsletter may be reproduced,
stored or transmitted in any form without the prior written permission of the Australian Centre for Geomechanics,The University of Western Australia.
Disclaimer
The information contained in this newsletter is for general educational and informative purposes only. Except to the extent required by law UWA and the ACG make no
representations or warranties express or implied as to the accuracy, reliability or completeness of the information contained therein.To the extent permitted by law, UWA and
the ACG exclude all liability for loss or damage of any kind at all (including indirect or consequential loss or damage) arising from the information in this newsletter or use of
such information.You acknowledge that the information provided in this newsletter is to assist you with undertaking your own enquiries and analysis and that you should seek
independent professional advice before acting in reliance on the information contained therein.
Scheduling
Accepting that the mining will proceed
along a basis of a defined cost of
production in terms of final product, many
potential scheduling options exist.
A series of sequential pushbacks can now
be planned and ranked in increasing order
of cost of production. Inventory that has
been defined for each of the pushbacks
can be scheduled in terms of production
cost.The only variables that can be
managed are the head grade and the
stripping ratio, which ultimately determine
the operating costs. Scheduling the
Continued on page 4
Figure 4.World producer cost curve
Strategic Mining focus to achieve long- During this seminar, tactical and
term goals by proactively strategic approaches to mining
addressing potential industry will be explored through
risks, gaps and uncertainties comprehensive case studies.
Tactical Mining focus to achieve short- The seminar will provide a forum
term goals. The uncertain nature for industry to share their
and inherent risks in mining experiences, their successes and
tend to generate a reactive also some of the opportunities
approach that may have been missed due to
a lack of a long-term focus. Best
SEMINAR OBJECTIVE – to practices and long-term planning
promote best practices in processes will be comprehensively
strategic planning activities in discussed. This unique seminar will promote best practices in strategic planning
Australian mines.
Mining is a long-term business that SEMINAR THEMES
requires extremely high levels of Management of financial risks and • mine site facilities
investment. It also presents significant risks mining project uncertainties • shaft versus decline
related to uncertainties, but potentially • geotechnical and ore reserves/ • equipment
extraordinary financial rewards for resources risks Production strategies and mining
shareholders, industry stakeholders and • geotechnical risks (slope stability, considerations
society.To maximise these rewards over rockbursts, caving and non-caving, • mining methods (low cost versus
the lifetime of our precious (but limited) tailings storage facility, etc.) risks; block caving in hard rock)
minerals assets, long-term planning • metallurgical (ore recovery) • use of mine fill
processes must be implemented.The • natural disasters • stope extraction strategies
temptation to access short-term gains at • political environment • open pit pushbacks
the expense of longer term benefits must Human resources and • deep pit versus underground
be minimised. infrastructure Enabling technologies and R&D
When the minerals sector is at the • skills shortage and retention of • mine automation
bottom of the “boom cycle”, companies personnel • in-cycle shotcrete
may address the economic challenge by • professional development and • thin spray-on liners
implementing common, short-term training • rapid development mining
measures such as cost-cutting. When times • contract versus owner operators • seismic risk management
are buoyant, the pressure is on to take full • consultants and corporate memory
advantage of the high mineral values,
foregoing the benefits of adequate human
resources or an established infrastructure.
Call for Papers
Some mining corporations actively
Submit your abstract by 3 October 2005
counteract short-term drivers by having
the resources and processes in place to
provide effective and measurable strategic A series of three international seminars on Strategic versus Tactical Approaches in Mining
planning. The benefits of such an approach are planned for 2005–2007.The first seminar will be held in South Africa in September
can easily be measured in billions of dollars 2005. Following the 2007 seminar, to be held in Canada, the ACG will produce a hard
for global mining companies. bound publication featuring the best papers from the 2005–2007 seminars.
Please email Josephine for more information, acg@acg.uwa.edu.au
One of the greatest challenges facing the requirements of their lease. For tailings
global mining industry is the issue of storage facilities, for example, the amount
of the bond is AUD$12,000 per hectare. SEMINAR THEMES
economic and socially acceptable closure
• regulatory expectations and
of mine sites.The increasing attention Planning for land rehabilitation and site
legal requirements
being paid by the media to the legacy closure from an early stage of a mining
• financing closure
of abandoned mine sites has focussed operation is an important way of
public interest on mine closure issues. decreasing the cost of the process. • case studies on mines that have
In response, legislators and regulators are already been relinquished
It is also important to have clearly defined,
implementing various financial instruments • rehabilitation and success criteria
unambiguous and appropriate criteria
to provide surety that closure will be for what constitutes acceptable closure. • planning for closure
affordable.These are often underpinned Approval for future mining projects will • managing acid drainage
by various rehabilitation criteria that must more likely be obtained if the industry • addressing community concerns and
social impacts
• landform evolution
• primary successions and ecosystem
developments
• pedogensis on covers and wastes
More than 50 papers from leading
local and international mine closure
practitioners and strategists are
expected to be presented at this
unique, world-first mining event.
For more information, please contact
Josephine Ruddle at the ACG at
acg@acg.uwa.edu.au
The 1st International Seminar on Mine Closure will provide an international forum for an exchange of ideas
on what constitutes acceptable closure
Dr Kevin Rosengren,
principal, Kevin
Rosengren &
Associates
Surface Support in Mining editors: John Hadjigeorgiou,Yves Potvin and Dick Stacey
In 2003, a group of professionals lead by Kugan Kuganathan and Adrian Lang have
Adrian Lang recognised the lack of seen the editors (Yves Potvin, Ed Thomas, Handbook on
readily accessible information of this and Andy Fourie) create a unique and Mine Fill content
very complex and multifaceted mining practical tool for engineers. • Introduction
discipline. While there was a plethora of • Basic fill materials
To obtain your copy, please contact the
mine fill information dispersed through • Geomechanics of mine fill
ACG via acg@acg.uwa.edu.au
conference proceedings, journal articles • Fluid mechanics
and industry reports, there was no • Hydraulic fill
Industry Sponsors • Rock fill
current one-stop reference source.
The ACG gratefully acknowledges the • Paste fill
The ACG set about to develop a
support of the Handbook on Mine Fill • Other fill types and practices
practical, invaluable tool for all mining
Sponsors. • Hazards, risks and environment
professionals to utilise when addressing
• Emerging technologies and
mine fill considerations. current research
Contributions from leading authorities • Glossary
such as Tony Grice, Angus Henderson, • Extensive reference list
ACG Update
International events, publications launched, new research projects commenced … the ACG team have been
kept busy developing tools and knowledge to aid industry to improve mine safety.
The last six months have been particularly university background, Jill is a great asset to
challenging with our small crew presenting the ACG.
Ground Support 2004 and RaSiM6, and 2005 has already proven to an exciting
producing a number of publications, year for the ACG/UWA PhD candidates.
research deliverables and training videos. John Albrecht submitted his thesis entitled
It has been well worth it! Response and Delineating Rockburst Damage to
feedback from mining professionals Underground Development Subjected to
throughout the world clearly indicate that Seismic Loading in February. Supervised by
Congratulations Dr Michelle Owen!
our activities have had a positive impact Yves Potvin, John’s thesis originated from
on industry.
the ACG’s Mine Seismicity and Rockburst
Early this year Melissa McFetridge, our
Risk Management research project.
Administrative Assistant, decided a change
of pace was needed and that it was The ACG was thrilled to see former
time to fly the coop to embark on a ACGer Michelle Owen on her whirlwind
nursing degree. trip to Australia in March. Based in
Washington, USA, Michelle is a senior civil
The ACG is delighted to welcome
engineer with Bechtel. Michelle returned
onboard Jill Hollinshead. Jill joined the
home to present a paper at the RaSiM6
Centre as the new Administrative Assistant
Symposium and to graduate with
in January. With her enthusiasm, excellent
a doctorate from The University of
communication skills, event management
Jill Hollinshead has joined the ACG team as the Western Australia.
and public relations experience, and strong Administrative Assistant
The Black Star Open Cut commenced extensometers, which will provide the Acknowledgment
operations towards the end of 2004 and necessary correlation data for linking The significant contributions made by the
thus is in the early stages of development. seismic activity with physical deformation. sponsors (MERIWA, WMC and Xstrata
The chosen monitoring site is on the east This unique ACG research project aims Zinc), both in the project justification and
wall at the final pitwall position, which to develop innovative solutions that could funding, and the efforts of the site
Xstrata have deemed critical from an become critical to the success of future personnel, are gratefully acknowledged.
infrastructure perspective (see Figure 5). deep open pit operations within Australia For more information about High
The Black Star site offers a unique and overseas.The direct benefits of Resolution Seismic Monitoring in Open
opportunity to monitor, from a enhanced slope monitoring capabilities Pit Mines, please contact Gordon Sweby
stress/deformation perspective, the will be more aggressive slope design and via acg@acg.uwa.edu.au
progression of the pit floor with depth, a diminished risk of failure.The early
and the interaction with underground detection of slope failure will also
voids (Figure 5). The pitwall is extensively allow for tactical response to avoid the
monitored with movement detection loss of slopes.
Gordon Sweby,
project leader,
Australian Centre for
Geomechanics
Do we have your
correct address?
For free copies of the ACG
newsletter and updates on
Centre activities and initiatives,
please notify the ACG of any
corrections to your contact
details, including email address.
Email: acg@acg.uwa.edu.au
Tel + 61 8 6488 3300
Fax + 61 8 6488 1130
Figure 5. Black Star Open Cut (Stage 2 pit design) as viewed from the SE. The planned sensor holes and
triaxial (blue) and uniaxial (purple) positions are as shown relative to known underground voids
Mining induced seismicity and associated While attractive for different reasons, larger insight into future events in that cluster.
ground control problems have a long stopes and larger windows both generate Seismicity often (not always) reveals its
history in Kalgoorlie’s Golden Mile. a concentration of energy and may suffer character early, in smaller events and
Documented seismicity at Mt Charlotte catastrophically in case of unanticipated lesser damage, giving time to study why it
mine goes back to March 1965, only three circumstances. As engineers, we generally is happening, and how to respond. Quite
years after bulk mining methods were anticipate stability using calculation and simply, if seismicity is monitored and
introduced to the mine. About 80 events computer simulation. The paradox is that analysed, seismic hazard can begin to be
of Richter magnitude 2 or greater have the better the calculations or computer understood. By contrast, no monitoring
been recorded there since bulk mining simulations, and therefore the more trim system means no history and no learning.
started. Understandably, large events make and perfect the constructions, the less they
Seismicity also shows elements of chaotic
managers, planners and engineers nervous, can survive the unpredictable.
behaviour. Chaos theory deals with the
sometimes to the point of closing mines Thinking about and doing the computations
behaviour of certain nonlinear dynamic
down.They rightly ask “why, and if so how, is just the middle step. The lesson for those
systems that are sensitive to initial
could mining still be done safely and involved in seismic issues in mines is to also
conditions. For example, cyclones are
profitably in this mine?” But knowledge think carefully about the first step
sensitive to small changes in air
gained by linking seismic monitoring to (documenting the data) and the third
temperatures. As excellently described by
seismic management has allowed the mine (practical seismic management allowing for
to survive. variations, errors and unknowns). Lee et al (1989) for the Mt Charlotte
environment, “Stopes, Stresses, and
Gothic cathedrals and gold mines Fortunately for miners, rock surrounding
Structures” make up the initial conditions
Time spent learning from history is never the excavations has bulk, which by design
influencing a seismic event:
or accident can permit stable equilibrium.
wasted. An inspiring essay by Vaudeville
The ancient stonemasons also tried to • the pre-existing rockmass constitutive
(1999) travelled back 700 years to the
avoid instability by adding bulk to their properties, namely the pre-mining
Gothic Cathedral constructions of the
designs. Each arch or column was figured stress regime, the rock properties, and
13th and 14th centuries. Stability of those
with ten times the calculated minimum the geological faults and structures, and
edifices depended on the constituent
necessary cross-sectional area, so that a • the imposed excavations – geometry,
parts forming a system, all parts being
ten times stress concentration due to position, mining sequence, and blasting
necessary, and some being proactive
design or construction irregularities or procedure.
(flying buttresses and arches), and all
other circumstances could be met This suggests that analysis of the above
obeying the laws of mechanics.
without exceeding the perceived strength
Yet some constructions have collapsed, initial conditions and the resulting
of the stone.
while others still stand, showing that seismicity can be expected to improve
unexpected catastrophic instability was a Documenting the data the ways of effectively managing mine
real issue. Interestingly, we can recognise Seismic events may appear random, but seismicity.The initial conditions are not
mine seismicity also as catastrophic occur in clusters that show some fractal known to the required resolution to be
instability. What does this parallel teach? characteristics, i.e. clusters are self-similar able to predict individual chaotic
Further, we note that Gothic Cathedral (subsets in time or space look like the rockbursts. However, the gross boundaries
windows over the years became larger, whole) and are independent of scale of the initial conditions can be identified
reducing massive stone walls to fragile (they look similar when zoomed in). and studied to examine how they affect
interstitial pillars. The mining parallel of Fractal character over time means that seismicity on a global, as opposed to
chasing percentage extraction is clear. analysis of cluster subsets gives valuable individual basis.
Figure 1. Unclustered events – shown by magnitude Figure 2. Clustered events – represent 65% of the since 1995 have returned intriguing but
total number of events but 96% of the seismic
energy recorded
low resolution data hinting at multiple
stress changes of up to 1 MPa over
Collecting seismic event data is a joint I had a natural advantage at Mt Charlotte time, changes apparently unrelated
effort between computers and engineers. – a good study mine, with essentially only to mining.
Using the fractal character of seismicity one rock type and two dominant fault • Electromagnetic emissions (EME)
to advantage, some form of clustering and structure orientations.This simplicity experiment – during a mass blast, an
of events is essential. Clustering can cut allows better perception of the attempt was made to relate seismic
thousands of events to only dozens of importance of other parameters. events to EME associated with
clusters (see Figures 1 & 2). The continuity of over 12 years at the fracturing of rock.
A work schedule to ensure clustering mine was long enough to see several • B-Value History Path Chart – clustered
is done and a good system for the complete stoping cycles, and to see the seismicity data is processed to generate
collection of underground observation results of designs and plans made some a cluster history path.This uses the
and stope history data is paramount. years previously. Nearly 11 years of this familiar “b-value” gradient and the
A monthly reconciliation of workplace time was with the invaluable support of “Mmax” magnitude intercept to
visits is wise, to compare design a seismic monitoring system. characterise a cluster over successive
expectations with actual performance, Beware optimism. Engage the services time intervals (see Figure 3). Trends
and generate feedback. As the months of a good but pessimistic consultant and can be clearly seen and linked to
pass, a history of stope performance is ensure regular reviews of work. stoping milestones. Large changes in
built up – exactly what is needed for Have many visitors and listen to them. b-value and Mmax occur over time
later analysis of seismic response. It is not a case of “I’ve heard it all as seismic domains are crossed. It is
before” which really means “I am not necessary to define seismic domains
Formulating design principles
interested in changing, so why bother?” (just like geotechnical domains) for
Turning the collected data into design
Rather it is “How can I take another step different temporal sources, as well as
principles or rules for a mine is quite
forward?” No-one has time to make all spatial sources. (Note – Mmax is just
achievable:
the mistakes themselves. the x-axis intercept, not necessarily the
• attempt to construct graphs, charts largest event that can occur!)
and maps based on the data – this Keep very good stope record systems
to manage the problem of changing • Objective measures of excavation initial
crystallises the thinking process,
personnel and loss of historical conditions. Psychological studies have
• run experiments to follow up on ideas found that individuals tend to make
mining knowledge.
or trends. Trials, tests, research and irrational decisions, based on many
changes are normal, and Examples of research undertaken at
factors which need not include all or
• investigate mistakes to be sure of Mt Charlotte include:
only the relevant information. People
their causes. • Stress change monitoring experiment – have a tendency to subjectively
HI cells at the base of Cassidy shaft
Continued on page 16
Introduction Paste fill operators were initially trained to indicator of the water content, and if the
Experience has shown that paste fill use a combination of the instrumentation cement dosage is held constant, slump
performance is sensitive to the quality of feedback and slump test results to control provides an indication of the water:cement
the paste fill. Therefore, an effective the mix. However, operator training ratio.The higher the slump the higher the
quality control program is necessary to strongly emphasised the consequences of water:cement ratio. High slump paste fill
ensure that paste fill consistently meets paste line blockages and the message was therefore acts to reduce the effect of
the design requirements. Further, the frequently reinforced by management. the binder.
data obtained from the quality control Therefore, in response to slight elevations
in line pressure, operators tended to add Slump recommendations
process provides the feedback necessary
water to the paste fill mix regardless of The following recommendations were
to optimise the paste fill mix design.
the measured slump. The outcome was implemented to improve the quality
A case study detailing an audit of the
that the actual slump of the paste fill was control of the paste fill slump:
paste fill system at a mine in Northern
often higher than the design slump and • Training now emphasises the
Ontario, Canada is used to emphasise
this negatively impacted on the strength importance of achieving the paste fill
quality control concerns that are common
developed in the paste fill. mix design as well as explaining how
to many operations. The audit covered
the slump, water content and
most aspects of the paste fill system, from
Data analysis and performance water:cement ratio are interrelated and
the paste plant design and operation to
implications how they influence both the
placement control, and management
Slump data recorded in August 2003 and reticulation and paste performance.
approaches.This article focuses on quality
January 2004 and summarised in Figure 1 • Development of an internal audit
control issues relating to slump and
shows that the paste plant consistently system that routinely reviews the slump
strength. The case study illustrates how
failed to achieve the design slump, usually data to evaluate the overall
the auditing process can provide the
producing paste fill with a slump of performance of the paste fill plant and
information feedback loop vital to
8.5 inches (22 cm) and higher. makes necessary adjustments.
improving the overall paste fill system.
Paste fill strength is sensitive to the • Development of an internal audit
Slump quality control water:cement ratio.The lower the system to evaluate the overall
Slump is the focus of the existing quality water:cement ratio the greater the performance of the paste fill plant to
control program as it is easy to measure strength that develops. Slump is an determine if other factors are
and significantly influences paste fill
reticulation and strength characteristics.
160
If the paste is too viscous (low slump
value) it may be difficult to pump and can 140
lead to a build-up of pressure and failures
in paste delivery lines. Conversely, if the 120
paste fill has a low viscosity (high slump
No. of Tests
Figure 3. Summary of the UCS test data for 3% binder paste fill Figure 4. Summary of the UCS test data for 4.5% binder paste fill
It was an outstanding success, with over seminar, each session included a keynote
270 delegates from around the world address and a general reporter’s address, all
attending the event. With the production of which are included in the published
of copper in Chile set to expand at seminar proceedings.
around 5.8% over the next few years A noticeable development at this seminar
and with increasing pressures on water was the increasing number and diversity of
resources and concerns about the risks case studies that were presented from sites
and liabilities posed by traditional tailings that are implementing thickened tailings at
storage facilities, it was clearly an ideal full scale.The days of only reporting on
time for an event dealing with alternative laboratory and pilot scale tests, useful as
strategies for mine waste management. these studies are, are clearly over.The very
The two-day seminar consisted of valuable experiences of operators present
at the seminar added great value to the The ACG is pleased to present for the first time in
presentations by speakers from around this series of International Seminars on Paste and
the world, followed by sessions of discussion periods as well as to the Thickened Tailings, the proceedings in an attractive
information contained in the seminar hard bound format.These proceedings provide a
vigorous debate in which many of the useful source of reference material in this rapidly
concerns of the local industry were proceedings. Difficulties experienced, as well growing area of tailings management
clearly expressed. It seems that some of as successes achieved, were openly
the major concerns within Chile about presented and debated, adding to the value seminar, taking in the full spectrum of
the adoption of thickened tailings systems provided by the seminar. tailings management activities in the
are the enormous volumes that would Another noticeable aspect of Paste 2005 Chilean copper industry.This included
have to be handled (volumes of tailings in was the rapid and continuing development visits to closed and operating tailings
excess of 100 000 tonnes per day are of technology that is making the storage facilities, conventional thickener
relatively common) and the lack of economical and large-volume preparation systems, an operational pilot plant
proven ability to adequately thicken such and transportation of thickened tailings an thickener that included large outdoor
large volumes, the liquefaction potential achievable reality. Papers were presented flume tests and a spectacular ‘tailings
of thickened tailings and the lack of on advances in the design and operation cascade’, which forms part of a 86 km
appropriate legislation within Chile of thickeners as well as advances in long concrete channel transporting tailings
recognising the potential use of thickened pumping technology, an example being the from the mine to the storage site.The
or paste tailings. Whilst these topics may possible pumping of relatively high yield day was rounded off by a wonderful
be particularly relevant to Chile, they stress tailings using centrifugal pumps. lunch at the Cauquenes Thermal Springs
were clearly of relevance to many A variety of alternative strategies for resort, where problems of “waist”
other delegates, as demonstrated in managing thickened tailings once they management were attended to by most
the discussion sessions. reach the tailings storage facility were also delegates.
presented and a number of novel To obtain your copy of the 8th
The opening keynote address was given by
concepts emerged.
Professor David Boger of The University of International Seminar on Paste and
Melbourne, who gave a talk entitled,‘Tailings An exceptionally well-organised technical Thickened Tailings proceedings, please
waste minimisation, rheology and the triple visit was arranged for the final day of the contact the ACG.
bottom line’.This address set the tone for
the seminar, where highly technical aspects
relating to the rheology of thickened tailings
were debated alongside issues of
environmental responsibility and corporate
stewardship.The seminar was divided into
sessions dealing with rheology and
thickening, tailings transport, surface
disposal, and mine backfilling. Aside from
the papers that were presented at the
Paste 2005 presented an insight into tailings activities in Chile
OK, so it is a bit of a stretch to claim that hydraulic fill. Over 30 mines currently use
Europe is the birthplace of mining, but paste backfill and a number of these are
numerous modern mining projects have to located in Europe.
deal with Roman remains when assessing While mining engineers were marvelling
environmental impact! The pyrite belt in about the advantages of paste backfill,
southern Spain and Portugal has been The plant at Neves Corvo feeds both
those involved in the disposal of tailings
providing copper and tin for over two borehole and truck, indicating one of the
on surface were also finding advantages
millennia, and judging by the recent flurry advantages of paste backfill – the ability to
with reducing the water content in the
of new mines and projects (Aguablanca, batch the paste via ready-mix truck to a
tailings. The use of thickened tailings on
Las Cruces, Aguas Tenidas and Lomero remote borehole, in this case, some 3 km
surface was pioneered in the 1970s and
Poyatos) the region will continue to be a from the plant. In 2001, the Zinkgruvan
interest in such applications has
major European mining centre. Mine in Sweden commissioned a highly
increased rapidly in recent years, given
automated 90 tph paste backfill plant.
Paste backfill is not alien to the European the advantages with respect to stability,
mining industry and the Bad Grund mine reduced footprint, and water conservation. The most recent addition to the
in Germany developed one of the first European paste backfill portfolio was the
Paste backfill in Europe Lisheen Mine in Ireland. At 150 tph, the
paste systems in the world during the
After the closure of the Bad Grund mine plant is the largest paste backfill plant
1980s. The system involved a highly
in 1987, paste backfill briefly continued at constructed in Europe. The plant was
controlled mixture of tailings and coarse
Bad Bleiburg in Austria until the mine commissioned in 2004 and a site visit to
aggregate up to 30 mm diameter, pumped
closed due to exhaustion of reserves. the surface plant facility is proposed as
underground using piston pumps at
A thickened tailings backfill plant was part of the 9th International Seminar on
pressures in excess of 100 Bar.
constructed at the Galmoy Mine in 1997 Paste and Thickened Tailings, to be held in
The system provided excellent quality
and paste backfill reappeared in Europe in Limerick, Ireland, in April 2006.
tight fill at relatively low cement contents.
1998 when the Cayeli Mine in Turkey
Paste technology is now widely accepted, A number of mines (existing and
constructed a 90 tph plant. At about the
especially for large stopes where the proposed) are currently investigating
same time, the Neves Corvo Mine in
ability to continuously pour cemented paste backfill in Finland, Sweden, Ireland,
Portugal initiated strength and flow loop
backfill can dramatically improve cycle Spain and Greece and it is likely that
testing leading to the commissioning of
times when compared with conventional more plants will be constructed and
their 100 tph backfill plant in 1999.
commissioned in Europe in the
coming years.
The Aughinish Alumina Ltd's bauxite refinery, located on the southern bank of the Shannon estuary in western Ireland
Creating Cost Effective Rockdumps and Stockpiles 26–27 May 2005 Hotel Ibis, Perth,WA
Advanced Geomechanics in Underground Mines 2–5 August 2005 Hotel Ibis, Perth,WA
• Sirovision-3D Mapping for Open Pit and Underground
Applications 2 August 2005
• Numerical Modelling and Seismic Monitoring 3 August 2005
• New Developments in Ground Support 4 August 2005
• Flac3D Numerical Modelling 5 August 2005
Blasting for Stable Slopes 6–7 October 2005 Hotel Ibis, Perth,WA
Underground Mining Methods Seminar Series
Open stope mining and caving geomechanics 25–28 October 2005 Hotel Ibis, Perth,WA
Tailings & Paste Management, and
Decommissioning & Water Management 30 Nov–2 Dec 2005 Hotel Ibis, Perth,WA
2nd International Seminar on Strategic
versus Tactical Approaches in Mining 8–10 March 2006 Novotel Langley, Perth,WA
1st International Seminar on Mine Closure 13–15 September 2006 Sheraton Perth Hotel, Perth,WA
Regional and on-site courses on demand throughout 2005:
• Management and Operation of Tailings Storage Facilities
• Ground Control at the Mine Face Training Course
• Practical Rock Engineering Skills Development
Ground control systems, rockmass characterisation, geomechanical stope design
Australian Centre for Geomechanics PO Box 3296 – Broadway, Nedlands, Western Australia, AUSTRALIA 6009
Ph. + 61 8 6488 3300 Fax. +61 8 6488 1130 acg@acg.uwa.edu.au www.acg.uwa.edu.au