Beruflich Dokumente
Kultur Dokumente
Advanced
June 16, 2004 Energy Strategies, Inc.
2
Objectives of a Generation Project
Provide Local Reliability
Maintain an Economic Resource Portfolio
Ensure Stable Electric Cost and Power
Supply
Facilitate Economic Development in the City
of Alameda
Maintain Power Content Label in the Supply
Portfolio
Meet Future Need in a Timely Manner
Advanced
June 16, 2004 Energy Strategies, Inc.
3
Key Information Sought Through RFQ
Technical Feasibility?
Economic at Scale useful to Alameda P&T?
Business Models for a Project?
Interest among Vendors?
Is MSW gasification and power production
competitive with other alternatives?
Advanced
June 16, 2004 Energy Strategies, Inc.
4
The RFQ Team
Advanced Energy Strategies, Inc.
Overall project management
Economic analysis
Final Report
URS Corporation
Engineering assessment
Technical Report
Alameda P&T Staff
Project guidance
Advanced
June 16, 2004 Energy Strategies, Inc.
5
What is MSW Gasification?
Chemical conversion of MSW into synthetic gas in a controlled
process
Four technologies:
Pyrolysis: No oxygen,
Temperatures 750 - 1650° F
Gasification: Limited oxygen (< stoiciometric),
Advanced
June 16, 2004 Energy Strategies, Inc.
6
Gasification is Not Incineration
Incineration (burning):
“Oxidizing” Environment – oxygen rich
• Combines simple compounds into more complex compounds
Creates complex oxides, including dioxins and furans
Rejected by Alameda P&T in the 1980s
Gasification:
Reducing Environment – very little or no oxygen used
Breaks complex compounds down into simpler compounds
Destroys toxics including dioxins and furans
Advanced
June 16, 2004 Energy Strategies, Inc.
7
Gasification Process: 3 Stages
Advanced
June 16, 2004 Energy Strategies, Inc.
8
Approach of the RFQ
Issued
Round 1 - April 2003
Round 2 - June 2003
Advanced
June 16, 2004 Energy Strategies, Inc.
9
Three Areas of Findings from the RFQ
Technology
MSW Gasification technology is viable
• Will produce electricity reliably
• Can be permitted in California
MSW Gasification technology is commercialized
(just barely)
• Technology will improve as it is deployed
• Mitigation of construction and operating risks will need to
be addressed
Advanced
June 16, 2004 Energy Strategies, Inc.
10
Three Areas of Findings from the RFQ
Economics
Capital costs higher than most generation
technologies
• Includes the cost of fuel preparation
• Project receives revenue for accepting the fuel
Highly dependent on alternative costs
• Gas fired generation
• Landfilling MSW
Current alternative costs make MSW gasification
economic
• Alternative costs have been rising
• Confirmation requires a defined project
Advanced
June 16, 2004 Energy Strategies, Inc.
11
Three Areas of Findings from the RFQ
Institutional
Law & Regulation are lagging technology development
California legislation began addressing this in 2002
• Gasification recognized as different from incineration
Definition of gasification does not fit the technology
• Significant issue for thermal conversion technologies
• May not be a large problem for bio conversion
Did not define a role for gasification in MSW processing
• Gasification is a renewable technology
• Technology and life-cycle reports mandated
Additional legislation will be needed
Advanced
June 16, 2004 Energy Strategies, Inc.
12
Development Path Alternatives
Power Combined Thermal Bio- Monitor
Purchases Cycle Conversion Conversion Developments
Technology
Viability Well Well Confirmed Needs -
Established Established Confirmation
Maturity Very Mature Very Mature Not Mature Not Mature -
Risk Mitigation Contract Terms Turnkey Needs Need May be -
Construction Attention Limited
Applicability to Not Meet Local Too Large; Good Fit Not Viable for up to 2
Alameda P&T Reliaability Gas Pressures Except for Determined years
Goal Low; Not meet Siting
Renewable Difficulties
Goal Within Alameda
Institutional
New MSW Regulations n/a n/a Required May Moderate
Accommodate Participation
Legislative Definiation n/a n/a Modification Probably Moderate
Required Adequate Participation
Local MSW Plan n/a n/a Modification Modification Moderate
Required Required Participation
Project Requirements
MSW Supply n/a n/a Untested Untested Defer
Site for Project n/a Some Difficulty Difficult Difficult Defer
Advanced
June 16, 2004 Energy Strategies, Inc.
13
Gasification of MSW is a Good Fit for
Alameda P&T
Advanced
June 16, 2004 Energy Strategies, Inc.
14
Recommendations
Advanced
June 16, 2004 Energy Strategies, Inc.
15