1. Introduction
According to the ERI no. 03 item 1 and 2, the hoarding layout & the construction
period for Phase 1 works at Buffer Halls are revised to suit the new requirements.
In order to reduce the interference to passenger, SFK will divide the works in phase 1
into 2 portions (A & B). The working period for Portion A is from 1 September 08 to
6 October 08. For the portion B, the working period is from 4 October, 08 to 17
November, 08. The detail is shown on the Appendix A.
3. Hoarding Arrangement
4. Type of Hoarding
There has two type of hoarding; one is 3.2m height hoarding which will be installed
outside the buffer hall areas. For the 2.4m height hoarding with fire resistant sheet, it
will install within the buffer areas.
The outlook of the hoarding is shown on the appendix D & E. For the detailed
hoarding design & calculation, it will be submitted separately.
5. Counters Relocation