Beruflich Dokumente
Kultur Dokumente
POWER PLANTS
BY
DEPARTMENT OF
ELECTRICAL AND COMPUTER ENGINEERING
Approved _________________________
Adviser
Chicago, Illinois
May 2011
ii
ACKNOWLEDGEMENT
for the continuous support of my Master of Science study and research, for his patience,
motivation, enthusiasm, and immense knowledge. His guidance helped me in all the time
of research and writing of this thesis. I could not have imagined having a better advisor
I would also like to express my pleasure to the working conditions at the Galvin
Library, Illinois Institute of Technology that allows graduate students to reach large
education, encouragement and prayers even if they are thousands of miles far away from
me.
iii
TABLE OF CONTENTS
Page
ACKNOWLEDGEMENT ....................................................................................... iii
ABSTRACT ............................................................................................................. x
CHAPTER
1. INTRODUCTION ............................................................................. 1
2. CONSTRUCTION MANAGEMENT
PROJECT DELIVERY ...................................................................... 12
Contingencies ........................................................... 18
iv
3. TECHNICAL CONSIDERATIONS .................................................. 28
4. METHODOLOGY ............................................................................. 66
6. CONCLUSION ................................................................................. 91
BIBLIOGRAPHY .................................................................................................... 95
v
LIST OF TABLES
Table Page
2.1 Benefits of the Parties ....................................................................................... 16
3.3 Gas Turbine Power Output Elevation Correction Factors for Locations .......... 58
5.1 Characteristic NOx emissions of a CCGT plant with and without SCR ........... 71
5.8 Cost and Development Schedule of a 2x1 Combined Cycle Plant ................... 81
5.10 Investment Cost of a 2x1 Combined Cycle Plant (additional costs) .............. 84
5.11 Total Project Investment Cost of a 2x1 Combined Cycle Plant ..................... 85
vi
LIST OF FIGURES
Figure Page
1.1 The Relationships between the Research Topics. ............................................. 9
vii
LIST OF SYMBOLS
Symbol Definition
A/E Architect/Engineer
AC Alternative Current
AGC Associated General Contractor of America
AIA American Institute of Architects
BOO Build Own Operate
BOOT Build Own Operate Transfer
BOT Build Operate Transfer
BOP Balance Of Plant
BTU British Thermal Unit
CCGT Combined Cycle Gas Turbine
CM Construction Management
CO2 Carbondioxide
CPM Construction Project Management
CT Combustion Turbine
DBOM Design Build Operate Maintain
DC Direct Current
DCS Distributed Control System
DNO Distribution Network Operator
DOE US. Department Of Energy
EIA Energy Information Administration
EPC Engineering, Procurement and Construction
GADS Generating Availability Data System
GE General Electric
GW Gigawatt
GHG Greenhouse Gas
HRSG Heat Recovery Steam Generator
HV High Voltage
viii
I&C Instrumentation & Control
IEA International Energy Agency
KW Kilowatt
KWH Kilowatt Hours
KV Kilo Volt
LHV Low Heating Value
MW Megawatt
MWH Megawatt Hours
MVA Mega Volt Ampere
NERC North American Electric Reliability Corporation
NO Nitrogen Oxide
O&M Operation & Maintenance
OEM Original Equipment Manufacturers
PAC Process And Control
PE Preliminary Engineering
PVC Plastic Polyvinyl Chloride
SCR Selective Catalytic Reduction
ST Steam Turbine
WECC Western Electricity Coordinating Council
ix
ABSTRACT
benefits in terms of cost and time for owners of a construction project. Professional
includes not only the management services but also the interdisciplinary information and
data sharing. So the CM can use these presented information of a proposed project before
and during power plant construction from the technical point of view. However, there is
This study determines whether there is a need for updating the duties and
power plant construction management profession, introduces CCGT (combined cycle gas
turbine) power plant technologies, evaluates previous and existing datas on power plant
construction regarding their usage in CM practice in terms of cost, and presents the
updated duties and responsibilities of the CM. A case study is also conducted to identify
the costs of a current power plant. Based on the collected information’s and case study, it
is determined that the CM is highly needed in power plant industry that runs even in the
recession periods. On the other hand, the management functions of the power plant
industry are still deficient. This study does not include a specific chapter that defines
However, new approaches and practical application results are presented from the very
x
1
CHAPTER 1
INTRODUCTION
Since the industrial revolution energy has begun to have a very important and
fundamental role in the world. Today, energy has become even more essential for
residence, business industry and so on. It is therefore obvious that production of this
energy and consumption of this produced energy are some of the most important
activities of human life. Since those activities have increased, the power plant
construction market has become one of the important players worldwide. A nation’s
significantly affect the number of existing power plants and construction sites. The
question of, how efficiently the construction process of a power plant is managed today,
is still a challenging factor that determines the success of the attempt. This success
depends on many parameters and variables such as time and technology. For an efficient
of the parties and changes in technology with regards to power plant construction.
2
in the late 1960’s. It is generally accepted that the term reached a professional meaning
after 1970, when organizations like the Associated General Contractors of America
profession (AGC 1972) and by drawing standard forms of agreement between owners
includes data analysis; cost analysis, simulation and estimation issues. With regards to a
power plant, it also deals with management to optimize time, infrastructure, safety and
The roots of this type of construction run much deeper than these issues. The
construction of a power station dates back to 1878, when Thomas Edison developed and
sold a commercially viable replacement for gas lighting and heating using locally
generated and distributed direct current (DC) electricity. The world’s first public
electricity was provided in late 1881, when the streets of Surrey in Godalming, UK were
lit by electric light. It was driven by a Siemens alternator. Those first steps of power
generation were then improved by the usage of alternative current (AC) electricity after
1887 and the invention of the larger systems called three phase power generation in 1983.
These two major developments in power plant technology led to remarkable changes in
electricity for basic human life, governments and companies increased the number and
3
the size of their power plants. As time went on, the price of energy became more of an
issue. The economical considerations using kilowatt hours (kWh) in dollars became the
main focus. As an obvious result of this kWh in dollars governments and companies were
encouraged to find an alternative type of source to produce electricity such as hydro, coal,
wind, oil (petroleum), nuclear and so on. All these different energy sources developed
their own associated generating technology, and construction management and have their
countries by both private and public owners. Since the 1960’s and 1970’s construction
services offered by contractors and designers has increased both in national and
funds, the control of the scope of the work, and effective project scheduling. It also
encompasses the avoidance of delays, changes and disputes, project design enhancement,
The interests of power plant construction and construction companies are the
same. Generating megawatt hours (MWh) is only a means to an end. While a new plant is
being constructed or while an existing one is being renovated the most important
parameter is time. The complete project, from its inception to start-up phase requires a
detailed and scheduled plan, along with a personnel team and respective responsibilities
time is the critical parameter for the construction of a power plant irrespective of the type
of generation.
By the time; the project phase moves to the field, everything about the
construction planning should be complete. At this point, it is both risky and too late to
One of the first decisions to be made is how the project will be structured.
Generally utilities design the specifications and open bids for the work. After evaluation
of bids, the most cost effective contractor will be awarded the job and the utility’s
construction group will manage the contractors. This is generally based on the cost and it
gives utilities total control of the process. On the other hand reliable power generation is
more than mere profitability. Power system reliability has become an important issue for
the utilities and their investors. This is due to fact that the profitability for the utility’s
addition to reliability, utility management began to look for more cost-effective ways to
manage construction projects. This led directly to contracting groups with architect and
engineering firms for the development of the field construction activities. Since many of
these architect and engineering firms were often involved in multiple power plant
construction projects at any given time, this situation resulted in lower design and
construction management costs than if the utility self-performed. This has become a
discussion.
5
encouraged more and more cost control over the construction. This has led to the creation
of new types of power generators and independent power producers. These independent
power producers were focused on selling electricity at a profit, with their selling prices
reflecting the supply and demand of the electric power system. Therefore, they are much
more focused on controlling costs and schedule, especially when building new power
plants. This case has led to more innovative project delivery methods.
era. But, since the government is not involved in power generation, build-operate-transfer
and similar type of project delivery methods have lost their importance in a very short
Investors are forcing owners and contractors to become extremely cost conscious
and take responsibility for not only the building of the power plant but also its output
efficiency.
One of the technical results of these project delivery methods is the major shift in
the basic type of power plant being constructed. Their efficiency also started to be taken
into account. It has led to a shift from large steam driven turbines to smaller gas fired
turbines that can handle rapid load shifts at higher machine efficiencies. These types of
power plants can be delivered, installed and commissioned much sooner than other large
fast start-up of a power plant, fast load output adjustment and predictable to possible
natural gas fired power plants, and technical issues such as duties and responsibilities,
changes in these actions, and determine whether there is a need for updating these duties
power plant is being constructed or an existing one is being renovated, rules being
followed and the objective of each rule have to be determined carefully. Such rules may
include the schedule of the construction, time, field construction works, regulatory issues,
All of these steps will be studied on the basis of construction of a power plant
with natural gas. Natural gas oriented generation technology using combustion-cycle gas
turbines (CCGT) and how its’ construction is done will be studied in this paper. This is
the second objective of this thesis. After the construction analysis of a power plant,
discussion on consequences that are related to economics and reliability issues will also
be studied as the third objective of this thesis. The final goal of this thesis is to develope
duties and responsibilities, and determines whether there is a need for updating these
technology. Since this issue itself involves many other approaches in civil engineering,
this topic is only mentioned briefly and it is not within the main scope of this thesis.
plant, all required steps to build up a power plant will be discussed and important
remedial actions will be explained based on the phases of the construction. After defining
this construction period of a power plant, the considerations of technical issues will be
presented such as project delivery structure, sourcing the resources, contingency analysis,
schedule and constraints, site managing, selection of technology, site selection, materials
(prefabricated as modules or site fabrication). Then the third objective of this thesis
mentioned above is discussed to point out the economical effects of the selected
technology that has been constructed and its reliability effects after construction is
completed. The discussion will be based on the number of generation units, and the
generating capacities in megawatts (MWs) studied in case study. The site selection of the
power plant to be constructed or renovated is also taken into account in the Chapter 2 .
Figure 1.1 represents the process and relationship between the three main scopes
of this study: technical considerations, economics, and reliability. Today, power plant
used for project development, deregulated market, thus the reliability issue and
consideration now. Reliability issues and defined regulation to utilities or owners directly
define the selection of the technology that is going to be constructed such as the
generating capacity of the plant or the number of units based on their individual
bigger megawatts or construct generating units in smaller megawatts. In the latter case,
more units has to be built in order to meet desired demand. The selection of smaller or
bigger generating units affects the overall reliability of the system based on their
individual scheduled outages, forced outages or capacity factors. These relationships are
on the economics of the whole construction process and this lead inturn to greater care of
the planning process. Reliability and economics are impacting parameters to the
construction planning, but their effects on the power plant during the operation of the
Considerations
Reliability Economics
Reliable or cost-effective
This thesis consists of six chapters. After an introduction to the study in Chapter
management, compares the construction management project delivery system with other
traditional project delivery systems, defines the integrated project delivery system and
literature review. Chapter 3 includes technical considerations and electrical based project
delivery. Chapter 4 describes the methodology used in pursuing the objective of the study
and the details on the construction of a power plant which is defined in Chapter 3 from
this thesis. Methodology defines the parameters and the variables of a power plant that
Chapters 2 to 4 present the foundation of the study with respect to the literature
search. In Chapter 5, a case study of this thesis is shown. An example of the construction
of a power plant is investigated. Because of high thermal efficiency, low initial cost, high
reliability, relatively low gas prices and low air emissions, combines-cycle gas turbines
have been the new type of choice for bulk power generation for over a decade. There are
also other attractive attributes related to it such as, significant operation flexibility, the
availability of inexpensive power rate increments during the peak period operation of the
(CCGT) power plant. Finally in Chapter 6, the conclusions of the study and
recommendations for further research are also presented in this chapter. Figure 1.2
Chapter – 1
Introduction
Chapter – 2
CM Project Delivery
Chapter – 6
Chapter – 5
Conclusions &
Chapter – 3
Case Study
Recommendations
Technical Considerations
Chapter – 4
Methodology
CHAPTER 2
achieving high quality at minimum cost and time (Clough and Sears 2005). Construction
project management is the overall planning, co-ordination and control of a project from
functionally and financially viable project that will be completed on time within
authorized cost and to the required quality standards. Project management is the process
management (CPM) is project management that applies to the construction sector (3rd
applied in every kind of construction sector. The power plant construction approaches
have been changing since the last 25 years. Investors for a power plant project don’t
make money till the time of startup of this project or in other words construction period
of both a new power plant and a renovated one. This period has to be managed
professionally and it requires a scheduled plan, a clear definition of success, money, and
a skilled management and technical team. This process defines the success of rest of the
construction process.
13
method. Under the traditional Design-Bid-Build system, the owner contracts first with a
design consultant to 'design' the project, then solicits 'bids' from general contractors based
on the completed design and, finally, contracts with a general contractor to 'build' the
project. Under the Design-Build system, the owner solicits proposals based on a
statement of requirements and then contracts with a single entity to both 'design' and
'build' the project under a single contract. The CM project delivery system is different
from either of these two systems in that the owner contracts separately, but not always,
with a design consultant and with a firm whose primary expertise is construction
management. The owner procures the management services of the CM prior to or early in
the design phase. This enables the CM to provide significant cost, schedule,
design team.
The CM project delivery system has become the major project delivery systems
the design/build project delivery system is affected by problems such as lack of fiduciary
relationship with the designer, difficulty of pricing design in the beginning, difficulty of
managing complex projects, no checks and balances between contractor and architect,
owner left to fend for himself versus the contractor, creating potential for reduced quality,
increased potential for conflict between owner and architect/engineering (A/E) firm, and
process, places the owner in the middle of disputes between the contractor and design
14
professionals, does not allow the owner to know the cost of the construction until bids are
finalized, and intensifies the potential for change orders. The process requires a
significant economic commitment by the owner at the front end of the project by
requiring the owner to pay for the design before soliciting bids for the construction of the
project. Because the plans and specifications are completed prior to bidding, there is a
potential that bids for construction may exceed the owner's budget and hence it may
require the owner to either re-design or abandon the project. The inability of A/Es to give
an accurate estimate for the job and the limited management abilities of contractors are
factors that make the CM delivery system quite appealing. The failure of traditional
methods to meet the owner’s time, cost and quality objectives is one of the reasons why
Without CM project delivery, generally only one group takes control the overall
control of the project for the design-bid-build delivery method. Specifications of a project
are defined by this group which we call utilities in power industry then bidding process
takes place. After evaluations of the bids, due to cost effective approach, the most cost
effective group has the power to manage the contractors and third-party companies via
Reliability and the price of power are now considered together for determination
of this project delivery system and its management. To be able to reach more cost
effective management during the construction and planning process, the utilities started to
share their activities with another group called architect/engineer (A/E). This led directly
to contracting with architect/engineer firms for the development of the specifications, the
solicitation of the contractor bids and many times, for the management of the field
15
construction activities. Since many of the architect/engineering firms were often involved
in multiple power projects at any one time, their personnel developed economies of scale
that resulted in lower design and construction management costs than if the utility self-
Delivery methods to be used for the actual construction work should also be
evaluated with risk analysis. This is also a very detailed process involving geographical
location, funding, seasonal period of construction based on its phase. On the other hand
risks after completion of the project has to be considered for such factors as maintenance
costs, trouble shooting during the operation of the system and warranty based on legal
applications. As a result of these risk analyses and depending on the project, the
following project delivery methods are chosen: build-operate transfer (BOT), build-own-
(DBOM). These innovative project delivery methods became more attractive after cost
controlled sale of electricity and focus is based on selling electricity at a profit. This cost-
controlled and profit based power generation idea brought out the kind of power
producers all over the world led to the usage of those innovative project delivery
methods.
(OEM). These parties and their benefits are shown in Table 2.1.
16
OEMs Able to collect operation datas that helps improve their technology.
An opportunity for long-term relationship with the owner.
Next we will go into more details after the definition of construction management,
and its delivery system. At the very beginning of the each project, this specific project
has to be identified and designed based on its technology and regulatory issues associated
with that project. Then it is approved and budgeted. Parties then define one of the project
delivery method discussed above. After responsibilities of the parties are defined, the one
who will deal with the construction of the new power plant has to take more steps from
this point on. The most important one at the very beginning of the whole process is to
establish construction management and technical team based on the delivery method
chosen. This construction management and technical team may be derived from the
17
owners, OEMs or third parties. Because of a long period of power plant construction this
teams, work force in general, should be provided by the owner. But an owner supplied
work force is not enough due to technical considerations and the complexity of the power
plant technology; therefore OEM’s support should be sought by the owner during the
construction. This kind of working condition which promotes the cooperation of owner’s
technical team, electrical engineers, and OEMs specialist, will definitely increase the
skills of the owner’s team. The owner’s team and OEMs specialists will have a better
Electrical engineers assigned for this job are expected to have a general idea of the
overall operating system. An electrical engineer has to have a great understanding over
the operation of mechanical, hydraulic systems as well as the overall electrical system of
the plant. This construction phase of a power plant is a great chance for the owner’s
engineers training. Based on the project delivery method, maintenance of the operating
power system may be assigned to the OEM with an agreement and price associated to it.
This leads both parties to a better communication during the operation period of the
constructed power plant. But there is a key point that has to be taken into account.
In addition to finding the required people with the necessary skills, at the time
power projects, which are usually long terms, individuals may leave for personal reasons,
they may be replaced for performance reasons, or they may be rotated for company
(Hessler 2005).
18
plans associated to them are the other important element that has to be strongly
encouraged in power plant construction. In general contingency plans help to control the
construction management process, control project risks and maintain the financial
stability of power plant project. From the construction management point of view;
for unforeseen design or construction costs in the project. Contingency funds are usually
included in the construction budget (Risner 2010). At the early days of power plant
construction when the regulated utilities have the control of the overall power system,
risk management and consideration of contingencies were not so important. During those
days the most important action was the completion of the project. But after economics
being involved into the construction era and after the deregulated market, this approach
has totally changed. Increased economic responsibilities between the parties, new
for each individual party, made them more susceptive and more conscientious about the
possible claims that they may face during the construction of a power plant.
enforcement of contract language, especially on larger projects that is bigger than $100
Engineers try their best to develop a set of construction drawings before the field
works. However, there are almost always omissions or errors in/for their designs or
sometimes owner may decide to make last minute changes for electrical project. For
instance the owner may want to change the location of the cable trays, or the location of
19
the transformer which is totally different than the projected work. These are all possible
and common issues that may be faced during the construction of a plant. In this kind of
case architect/engineer must literally go back to the drawing and make revisions. This
situation may have some other consequences due to fact that the results of the errors may
be faced during the on-going project, and then the architect/engineer rather than the
contingency, program contingency which is number of ongoing project at the same time,
and possible delays on project. All these definitions are not in the main scope of this
study but we can generalize them from the power plant construction point of view.
Therefore, a project delivery structure should also consider these possible contingencies,
so these unforeseen contingencies can have an acceptable rate for the financier of the
project and the owner of the project. The owner’s needs have to be satisfied such as
reliability of the whole ongoing process, service or replacement of the turbines and
generators and transformers which have an important weight on the budget. Owner and
financier may share this contingency together which brings a comfort to the insurance
companies. This is also another result of the contingency planning for the construction
era. All parties have effects on each other, so this also builds a better relationship and
Table 2.2. These areas have to be taken into consideration before and during the
construction of a power plant where highly specific and technical case should be
considered more general such as decision management. However, none is more important
than another. Each one contributes in its own way to complete performance, and
construction manager. There are mainly twelve areas of knowledge for construction
management. It is clear that, there may be additions and deductions to these areas based
on the needs of the owner (Haltenhoff 1998). The twelve areas of knowledge which
Table 2.2 shows the definitions for each area of construction management from
both civil engineering and electrical engineering points of view regarding power plant
construction.
21
management means from the viewpoint of power plant construction. But a complete
project delivery of a power plant includes all elements such as program development,
maintenance. Project delivery begins with planning and analysis and it ends when the
whole project is constructed. Each stage has its own individual components that include
Program Development
Project Development
Project Delivery System
Construction Management
Maintenance
Program development is the first stage of the power plant construction, and occurs
before the start of a specific project. Project development begins with power system
26
planning at the state and local levels. Plans are developed to identify power needs and
outline a system of power plant facilities and services to meet those needs for the
proposed region and possible interconnection to other grids. Project priorities are
determined. This issue includes money, reliability and technology which will be
discusses in the next chapter of this thesis. Management decisions are taken such as scope
of the project, schedule and budget. For these three steps construction managements body
stage for power plant construction projects. Projects are further defined with a work plan,
timeline and project design. Here there is an important step that has to be taken for the
successful future of the project. Project leaders based on their specializations must be
assigned from the very beginning of the active process. Those specializations are
generally civil engineers, electrical engineers and mechanical engineers which are guided
by a skilled project manager. Those groups may be composed of the owner’s workforce
for private power plant constructions. Then, based on technology, location and
based on final plans and specifications. CM first considers the issues before the on-site
work begins such as bonds, insurance, and subcontractor compliance. These issues are
not explained here because they are not in the objective of this thesis. After these actions
are taken then on-site work begins. The contractor begins construction that is responsible
for furnishing materials and doing the required work according to the construction plans
27
and specifications. After the on-site work is completed by the contractor a final project
documentation is submitted. For the following process the project manager ensures all
on-site construction and other work required under the contract with the other project
leaders who have their own technical specialization. For a better project delivery
maintenance is also included too, but duration of this maintenance period should be at
most 5 years and it should be done by the constructor. Aim is to combine construction
period with the very first operation years of the power plant. If any malfunction occurs
based on technology or on the some phase of the construction that affects the operation of
the system (e.g. a lower efficiency via air inlets, outlets) then both sides of the contract
will be responsible to each other. This completes the project delivery system.
28
CHAPTER 3
TECHNICAL CONSIDERATIONS
Technical issues based on power plant construction are more focused on electrical
technologies, equipments, and associated infrastructure is defined after long and detailed
previously.
First of all, these technologies and equipments are discussed and then their
turbines and their effects on construction process are introduced. Those electrical,
mechanical infrastructure and technical specifications are expressed in terms of gas fired
turbines. Economical reviews to these technical factors are taken into account for
location of a projected power plant and its distance from the major fuel resources is also
an important issue from construction point of view and economics. All these issues will
be discussed in this part; and Chapter 3 will be concluded with these studies.
29
companies; utilities and non-utilities (EIA 2000). Electric utilities are defined as either
privately owned companies or publicly owned agencies that engage in the supply
are privately owned companies that generate power for their own use and/or for sale to
utilities and others. Power plants are operated by electric utilities, based on generation
technology. Utilities must meet the load requirements. There are three major load types:
base, intermediate and peak loads. Peak load generating units are normally smaller plants
using combustion gas turbines and those types of units can be brought into service
quickly and they are used to meet the system requirement during the highest load.
Intermediate load generating units meet system requirements that are greater than base
load but less than peak load. Intermediate load units are used during the transition
Base load generating units are generally used to satisfy all base load of the
system. They run continuously and generally produces constant rate of electricity. But
these large units cannot be brought on line or taken off line quickly because of high start
up costs and time. At this point combined cycle power plants were built to substitute the
large base load units with focus on higher efficiency, lower initial costs, high reliability,
low gas emissions, and so on. A large number of constructions were expected during the
early years of 1990s. But due to significant increase in gas prices and changing market
conditions in deregulated markets, many combined cycle power plants are now being
operated as intermediate plants and even with daily cycling. This led utilities to construct
30
smaller combined cycle power plants but a large number of then to satisfy reliability
cycle power plant construction, this situation led technology producers to come up
Before the technology study of the combined cycle power plants, the main
construction schedule,
geographical location (distance to the resources, elevation of construction site and its
effect on the efficiency, and distance to the transmission lines and etc.),
view, basic generating systems’ comparisons can be seen in the following figures. These
approaches give a very basic understanding and comparisons between thermal generating
technologies. For a combined-cycle power plant this principle can be defined by looking
at its efficiency during the thermal process. This high-efficiency thermal process gives an
answer to the question of; why combined-cycle power plants are being constructed.
Naturally, the efficiencies of real processes are lower since there are losses
involved. A distinction is drawn between energetic and exergetic losses. Energetic losses
are mainly heat losses (radiation and convection), and are thus energy that is lost to
processes. Exergetic losses, on the other hand, are internal losses caused by irreversible
processes in accordance with the second law of thermodynamics (Traupel 1977). Major
distinction is determined by both heat being supplied to the cycle and temperature of the
waste heat. These are called losses and occur during the heat exchanges. The best way to
improve the efficiency of the process is to reduce these losses which can be accomplished
by raising the maximum temperature in the cycle, or by releasing the waste heat at as low
more attractive. Since these two considerations are not possible to make by using only
one cycle, it thus seems reasonable to combine two cycles. One cycle is to make higher
process temperatures and the other cycle is to get as low temperature as at the waste heat
of the system. Table 3.1 shows the process and exhaust temperatures of gas turbines and
steam turbines.
possible high efficiency from the thermal processes. Table 3.2 makes this comparison
more clearly with the associated number to each power plant. These indicators shown in
Table 3.2 can be used as an indicator for the quality of a thermal process. Combined
cycle power plants are more promising than the single cycle plants. Steam power plants
with reheat process also have lower thermal process quality and construction of these
steam power plants with reheat process is quite sophisticated. With their higher
theoretical Carnot efficiency (10 to 15 points higher) and less complex installation and
construction phase of the auxiliary units such as heat recovery and water treatment, these
numbers make clear just how interesting the combined-cycle power plants are based on
Different Plant Systems: Figure 3.1 shows the steam-electric (thermal) generating units
which are typically the large base load units. Steam produced in a boiler turns a turbine to
drive an electric generator. Fossil fuels such as coal, petroleum and petroleum products,
natural gas or other gaseous fuels and other combustible fuels, such as biomass are
Figure 3.2 shows that gas turbines and combustion engines use hot gas from
burning fossil fuels, rather than steam, to turn a turbine that drives a generator.
Figure 3.3 shows combined cycle plants that first use gas turbines to generate
power and then use the waste heat in a steam-electric generator to produce more
34
electricity, thus combined- cycle plants make more efficient use of heat energy in fossil
fuels. New technologies are improving the thermal efficiency of combined cycle power
plants to 50% to 60% thermal efficiency. This encourages construction of new plants.
Figure 3.4 shows cogenerators, also known as combined heat and power
generators, are facilities that utilize heat for electricity generation and for another form of
useful thermal energy (steam or hot water), for manufacturing processes or central
heating. There are two types of cogeneration systems; bottom-cycling and top-cycling. In
first and a waste-heat recovery boiler recaptures the unused energy and uses it to drive a
produces steam to drive a turbine generator to produce electricity, and steam leaving the
spin a shaft connected to generator to produce electricity, and the waste heat from the
burning fuel is recaptured in a waste-heat recovery boiler for use in direct heating or
Every industrial plant strives to keep production costs as low as possible, and
power plants are no exception in this regard. Political factors and environmental
protection legislation impose certain limits on this goal, but economy of operation still
remains the most important criterion when selecting what type of power plant to build
(Kehlhofer 1991). All types of power plants explained above must be able to deal with
the changes and challenges of liberalized and deregulated markets. Nowadays operational
combined-cycle power plants are still in active process and seem to be still attractive in
the next decade from the viewpoint of efficiency and economic. Also there are
operational effects that encourage new investments. Some of the main advantages for the
combined-cycle power plants which are related to its operational flexibility include fast
36
start-up and shutdown, fast load changes and load ramps, high start-up reliability and
load predictability, frequency control and ancillary services. Since these are not in the
combined-cycle power plants. There were no operational and real efficiency datas of
these plants at the very beginning of this technology during 1980s and 1990s. But now
utilities have more chance to access many information based on operation of combined-
cycle plants. Those utilities that have their own plant have their own operating data.
These data led technology producers to come up with better solutions since the last 10
years. Now it can be said that it’s a proven mature technology. As technologies related to
gas fired power plant matures, now their construction is far from being an issue. The
and the source of materials are important. For example, turbine installation, required for
control boards and power control modules are an important issue based on source of these
equipment, i.e., whether they are supplied (produced) locally or imported. Considerations
power plants in a decade now. Challenge on construction is to have the right resources
power plants are manufactured on a worldwide basis. Private manufacturers and material
generators, control drives, fuel control elements, steam turbine generators and
condensers, pumps, valves, electrical and electronic controllers. All the equipment’s
technical details and specifications are defined in the contract and negotiations. The same
available locally vs. what need to be imported vs. the cost and time trade-offs.
plant and they even might be cost effective and decrease the labor work during the
valves, instrumentation, tubing, cable tray, and junction boxes in the plant, a structural
base and supports. To have those bases and supports, these would be preassembled or as
sub-modules and then field assembly should be made to create the bigger modules. Other
than structural modules, the electrical modules follow the same criteria and ways. But
electrical installation and commissioning takes at least 20 % to 30% percent of the total
and systems include the main panels, control panels, motor control panels of defined
and interconnection issues are mainly related to the location of the plant and to the future
Skilled engineers and technicians are the key point for this part of the construction
process.
3.2.2 Power Plant Construction Schedule: The construction management and project
delivery methods are discussed in Chapter 2.1. Basically, project management is a subset
Execution and Control. Combined-cycle power plants had large number of interlinked
activities. It is therefore, necessary to have a plan that gives overall view of how the
whole project work will proceed and which activities are more important than others and
basically a schedule based on Critical Path Method and shows only the major activities
with their interdependence, start/end dates, allowable delays (floats) and criticalities. The
critical path in a schedule is the longest chain of successive related activities without any
float i.e. allowable delay and therefore decides the total completion period of the project
out, then Level-II as aggregate of Level-III schedules, and finally Level-I or Master
downwards schedule, empirical Level-I schedule is first prepared taking into account the
constraints in the project, like time, climate & weather etc. Level-II and Level-III
39
schedules are then prepared which are in conformity with Level-I. Finally, all three
power plants, normally downwards scheduling has to be done. It gives a better overall
control of the constructions process. This approach can be actively applied in many
power plant constructions which also clearly determine the responsibilities of the sides of
the contractors due to its overall coverage over all construction steps which are explained
below.
Participant groups and various subcontractors will be responsible for the site
engineering support for the project design documents and is available for meeting and
architect/engineering groups is that they are responsible for issuing design change notices
which is a critical issue when the construction phase comes to an end. Subcontractors
provide equipment, materials and labor to complete all phases of the construction and
installation of the plant. But technical labors who are responsible for the electrical
installation such as electrical engineers and skilled technicians can be provided by the
follows;
40
Auxiliary systems (air intake system, starting system and fuel system)
Site Utilities
Insulation
installations. The equipment and its filed applications are discussed in Section 3.2.2.5 of
this thesis.
Figure 3.5 shows both overall project scheduling period and construction schedule
period. A constant construction management must be provided for all these construction
increased. Also the third part inspections should be subcontracted by owner/utilities. This
knowledge is missing, the subcontractor may divert site management’s attention from the
daily work activities, which can result in less effective site managing and increased costs.
3.2.2.1 Site Preparation: Background of the site planning and development hasn’t been
plant construction is not unique due to its location, owner’s approach to the site planning
and the size of the project. For a successful site planning and development, advanced site
management for module fabrication, module delivery, assembly of these modules and
outfitting and power island construction. One important issue is to have support facilities
42
that are required for off-site module fabrication and assembly. Once these are obtained
then focus is on the site, because large spaces are needed for storage, prefabrication and
schedule. If lay-down areas are not available for storage, prefabrication and pre-assembly
of electrical and mechanical equipments, the site construction schedule will be affected.
To be able to start effectively the preparation process, the construction site should
be equipped with the field mid-voltage and low-voltage electricity that is going to be
terminated after the completion of the project. This mid-voltage projects are generally
prepared by the third parties during the pre-project engineering phase of the construction
process.
required and when it’s required. Then, it’s simply a matter of applying the contractually
agreed process to set up the temporary transformer, feed it, and distribute from it (Hessler
2005).
3.2.2.2 Foundations: The function of the foundation is to maintain the engine at its
correct initial elevation and to keep the rotating shafting in permanent alignment
(Kauffmann 1977). Foundations for the turbines and generators must be designed during
the planning stage for the facility building. The foundation designer should require test
checks of soil compaction at the site, with vibration techniques, a soil profile down to
refusal, and determination of soil load-bearing ability. This will provide the basis for a
43
size of the engines and soil specifications should be implemented as soon as the site
preparation is completed. In all cases, foundations for turbines and generators must be
both economic and effective. Figure 3.6 shows the elastic supports with steel frames and
equipment this would be usually a steel frame. Larger generators usually have a concrete
foundation that is often provided to prevent the dynamic and static forces into the subsoil
forces into subsoil and therefore may affect the building and its surroundings which
finally results with vibration problems. There are two consequences for foundations of
engines;
Therefore, uncoupling the machine foundation which is done previously from the
substructure using spring and elastic elements may give more effective results on the
transmission of dynamic forces. This elastic support system with a steel frame has many
44
of the foundation and therefore the size of the foundation can be substantially decreased.
If local predicted small earthquakes take place and a resettlement occurs due to these
earthquakes, the readjustment of the spring elements can be done easily during the
transform voltages for delivery of electricity to homes and businesses (Alameda 2006).
Foundation of a substation within a power plant is not a big challenge. During the
construction phase, cable channels which lie under the floor level or foundation should be
planned for future projections. Enough free space and free working space should be
considered in the channels during the planning phase. Accumulator room that is required
during an emergency to activate switches and lighting and room for the neutral grounding
resistors for the high voltage transformers are also included in the project. Earthing
copper mesh and earthing electrodes should be placed before and during the foundation
works of both power plant and substation. Soil resistivity measurements, location of
lightning conductor and placement of lightning electrodes should be done before the
completion of foundation work. It should cover all sites of the power plant. Figure 3.7
gives an example on one of the coverage areas of lightning electrodes for a geothermal
plant and its subsequent facilities of CO2 and greenhouse facilities. Soil resistivity
measurement is 0.04 Ohms which is a very acceptable rate of resistivity for the selection
of lightning equipments.
45
under equipment erection title. Since this topic is not in the main scope of this thesis,
detailed erection techniques and their operation schedules are not described here. Main
components that are used within the combined-cycle power plant include combustion gas
turbine, electrical generators (for steam turbine and combustion gas turbines), boiler,
exhaust units, steam transport pipes, condenser, steam turbine and chimney. Figure 3.8
illustrates these components of a combined-cycle gas turbine (CCGT) power plant and its
of one gas turbine generator and one steam turbine generator. It is called “1x1
construct power plants that use two or even three gas turbine generators and heat
recovery steam generators (HSRG) feeding a single but larger steam turbine generator.
46
These kind of systems are called “2x1” configuration based on their numbers of gas
turbine generators.
from gas turbines and 1/3 from the steam turbine. Gas turbines are generally two or more,
but there is generally only one steam turbine. Design of power plants before the
construction is based on their efficiency. There are many factors that affect efficiency
such as; size of the turbines, elevation, gas prices, predicted operation load of the power
plant. But in general, the efficiency of the gas turbines are highly load dependent,
whereas the steam turbine is more flexible when compared to the combustion gas
turbines. To avoid running on low efficiency, a power plant should be planned with
several smaller turbines if load for each turbine is an important design criterion. This
criterion changes the whole picture of a power plant from the viewpoint of engineering
design and construction phases. In such a combined-cycle power plant, units should be
47
operated d at optimal load. Due to results of these issues an important part in designing
the power plant is to determine the optimal number and sizes of combustion gas turbines.
An optimal design of components is made based on the type of generation for instance;
whether it is a base load power plant or peak load power plant. This design issue also has
effects on construction costs of a power plant which are discussed in the following
Gas turbines are normally standard equipment due to very high development
costs. Steam turbines come in a wide range, and it is not difficult to find a suitable one to
match the gas turbines (Bolland 2003). Construction schedule is obviously accelerated
with more but smaller gas turbines to run the system on optimum load to meet the
efficiency explained above. Once the required foundations and power houses are built
with a well planned allocation of workers, the erection of two or three gas turbines can be
started at the same time. Other main components that are included into design and
3.2.2.4 Pipe supports and piping: Within industry, piping is a system of pipes used to
convey fluids (liquids and gases) from one location to another. A power plant is generally
described on its turbines, generators, and steam turbines and so on. All these units are
48
connected to each other with the pipes. Design and process of a pipe group or system is
power plant is a mesh of pipe systems where air, steam, gas, and water are processed. It is
one of the most important phases of the construction phase. Piping work requires high
skills on welding and mechanical. Piping process literally takes long time. It starts with
the site preparation and continues till the end of the construction process. At the very
beginning of piping, drain systems and associated rain/drain infrastructure of the power
plant site is prepared. Then before the site works, connection process to the main gas
transportation lines/storage facilities that are operated by private companies in the region
is started. After site preparation and foundation processes are completed in the field, main
Pipe line components are known as fittings, valves and other devices, typically
sense and control the pressure, flow rate and the temperature of the transmitted fluid.
These sense and control systems come with an electrical background. If a power plant
site is considered a quite large one, the cabling issue for these electrical equipments has
to be done carefully. Sub-modules or infield process control panels might be needed for a
reliable operation and control of the pipe lines. Due to electrical head start, cable tray
should be mounted at the same time with the piping works. This definitely accelerates the
rest of the electrical work to be done during the following construction phases.
cycle power plant can be classified from the start process of power generation to the last
step which is exhaust gas. The equipment include air intake systems, combustion gas
49
turbines, electrical generator connected to the combustion gas turbine, boiler, water and
gas circulating pipe system, steam turbines, and another electrical generator which is
Air Intake: Air intake systems provide clean air into the compressor. During continuous
operation the impurities and dust from the air in take deposits on the compressor blades.
This reduces the efficiency and output of the plant. The air filter in the air intake system
prevents this. Today most of the gas turbines are able to operate successfully in a wide
variety of climates and environments due to inlet air filtration systems that are
specifically designed to suit the plant location while also considering the impact of local
air quality variation on the system design. Under normal conditions the inlet system has
the capability of processing the air by removing contaminants to levels below what are
harmful to the compressor and turbine. Filtration systems, however, are not 100%
effective and an increase in the inlet contaminant concentration level will generally result
in an increase in the contaminant level of the air discharging from the filters. In some
degree that additional precautions may be necessary and require optional filtration or
power plant is also affected by these factors. The following information gives an idea on
the composition of particulates; therefore this gives another reason for selection and
wide ranging and will vary considerably with local emission sources. There are, however,
general patterns within the US that show in western regions the particulates generally
50
consist of carbon and nitrates and in the eastern region the particulates are largely
composed of carbon and sulfates (United States Environmental Protection Agency 2004).
Selection of filters for the air intake system is also an important process that has to be
taken into account before the construction phase. Some of the selection criteria are
nominal air flow rate , maximum air flow rate , initial pressure drop
special feature that allows customized solutions. These modules can be flexibly adapted
to match local and system based specifications involved during the construction period.
The modules are assembled completely beforehand, and need only be bolted or welded
together, therefore this process facilitates erection and decrease the installation costs.
This concept also allows to develop standardized air intake systems that is going to suit to
a particular range of turbines. Especially stainless steel should be used for the housing of
the air intake systems. This stainless steel manufactured housing and filter frames avoid
salt corrosion for the plants which are located at the coast or close to the coastal region.
All other modules of the air intake systems are added on to this basic housing. Other than
this, another solution can be presented by installing these modules in already existing
building.
Starting System: Starting system provides the initial momentum for the gas turbine to
reach the operating speed. A gas turbine in a power plant runs at 3000 rpm for the 50 Hz
grid and 3600 rpm for the 60 Hz grid. During starting process the speed has to reach 60%
for the turbine to work on its on inertia. Simple method is to have a starter motor with a
torque converter to bring the heavy mass of the turbine to the required speed. For large
51
turbines this means a big capacity motor. For gas turbines, the latest trend is to use
generator itself as the starter motor with suitable configuration. These applications
increase the operation flexibility of the turbine and generator. And it also enables to
handle more compact unit in a power plant. Otherwise auxiliary starting systems are
introduced to the plant and this increases the complexity of the operation field that results
in more possible faults, man work and maintenance and operation costs. For instance, in
some places where there is no other start up power available, such as ship or an off-shore
Fuel System: fuel system prepares a clean fuel for burning in the combustor. Gas
turbines normally burn natural gas but also fire diesel or distillate fuels. Erection of
burner system and ignition system requires great significance. All safety procedures and
precaution steps have to be followed during the construction period. Although most of the
fuel system units such as heaters, filters, and control valves have quite mature technology
and design, fuel gas system installation should be taken with care by the specialized
construction group.
Safety interlocks are the most important items. A control valve regulates the
amount of fuel burned. A filter prevents entry of any particles that may clog the burners.
External heaters are used to heat the gas for better combustion. For the liquid fuels high
pressure pumps are introduced into the construction, which pumps fuel to the required
pressure level for fine atomization of the fuel fir burning. Figure 3.9 shows these
auxiliary systems in a gas turbine power plant that was mentioned above.
52
Figure 3.9 Auxiliary Systems in a Gas Turbine Power Plant (Khemani 2009)
Exhaust System: Different than other gas turbines, construction of diverter damper is
introduced in combined-cycle gas turbines. This unit is used to change the flow of gasses
to the heat recovery boilers instead if the outlet stacks. Diverter dampers are installed
between the gas turbines and the heat recovery boilers and this improves the generating
flexibility of the plant as, for example, both gas turbines can produce electricity in the
event of a steam turbine shutdown or both gas turbines and the steam turbine can produce
electricity in the event of a boiler shutdown. The control of the diverter damper can be
operated remotely from the power plants control room or manually from the local panel.
Included in the control panel are safety switches, power transformers, local control
switches for the fan, actuator and valves. In the past the electronic control for this system
was simply to fully open or close the damper. Recent developments in the industry have
53
led to using the diverter as a trottling device to bring the heat recovery steam generator
(HRSG) up to speed faster. These new electronic control designs and mechanical designs
have led utilities to achieve rated load faster during the operation period of a combined-
Generally, the distance from the control room is not too much, and communication cables
are not affected by the length but the electromagnetic field. But nowadays control is
made more commonly with the AC low voltage control that eases the field cabling work.
If there is no feedback prepared to check the position of the dampers then manual
operations are a necessity. In this kind of situations, a safe operation area should be
prepared during the construction phase that is going to allow workers to operate the
3.2.2.6 Site Utilities: construction process is not only composed of in-field works. Site
utilities should be installed to the site boundary and connected with a fully coordination
of scheduled field work. These utilities are steam, temporary electricity for the field
work, water supply, boiler feed water, natural gas and so on. Each of these actions should
application scenarios. If any of these utilities lays back from the construction schedule, at
this stage, it creates very big delays. Generally third parties provide these actions, so their
schedule and work plant should be prepared very carefully by the all parties of the
54
contract. A construction manager must always stay in touch with the third parties and
3.2.2.7 Insulation: The insulation work generally involves the insulation of pipe fittings,
valves, and flanges as specified in the design documents by the contractor company. The
types of materials that are used during the construction depend upon whether the
types of desired piping materials and fittings may also govern the type of material
actually used. Underground piping outside of buildings may be cast-iron soil pipe,
galvanized steel, concrete or plastic polyvinyl chloride (PVC) pipe. Underground piping
within buildings may also be of cast iron, galvanized steel, lead, or PVC; however, cast
iron and PVC are the most popular materials used. Aboveground piping within buildings
consists of either one of or a combination of the following: brass or copper pipe, cast iron
or galvanized wrought iron, galvanized steel or lead. Exposed pipes in power plants are
typically insulated with materials made of hydrous calcium silicate that meet or exceed
government standards for fire retardation from 100 to 1200 degrees Fahrenheit, low heat
conductivity and vapor retardation (low smoke properties). Fiberglass pipe insulation is
also designed for power plants. It is fire rated to withstand 850 degrees Fahrenheit and
3.2.2.8 PAC Test and Start Up: The process and controls (PAC) test starts by following
the completion of the plant installation. This test can be scheduled from one month to a
couple of months to be able to make observations over the whole system after
55
construction is completed. During this period technical support is provided b the sides of
the contractors and this technical support varies in many different disciplines which may
include electrical and mechanical specialists, air and gas system specialists and so on.
During PAC period all drawing and revised projects should be checked again. Because
during the construction period project might not be updated properly, this is also another
important task. This test doesn’t mean start-up of power plant. The plant start up is
3.2.3 Geographical location: Today’s modern power plants are much easier to locate
than the larger old-style power plants because they are smaller and no longer cooled by
water. The country’s power needs could be met by locating a new power plant anywhere
in the region. But there are still factors that help to determine where to construct a new
power plant. Based on power plants location, distance from the main natural gas pipe
lines and high voltage transmission lines, distance from fuel resources, distance to the
water resources, air temperature of the regions, elevation of projected power plant, and
peak loads and periods of these peak loads of the projected region, these factors can be
considered.
on each particular component. Failure to understand adequately and include the effects of
high altitude in the application of the equipment may result in its poor performance,
premature aging and/or failure (Nelson 1984). Since the gas turbine is an air-breathing
engine its performance is changed by anything that affects the density and/or mass flow
56
of the air intake to the compressors. Ambient weather conditions are the most obvious
changes from the reference conditions of 59F/15C and 14.7psia/1.013bar. Figure 3.10
shows how ambient temperature affects the output, heat rate, heat consumption, and
exhaust flow of a single-shaft MS7001 gas turbine. Each turbine model has its own
efficiencies as well as air mass flow (GER-3567H). Gas turbines are constant volume
mass flow dependent engines. Their exhaust flow and temperatures vary with ambient
temperature and barometric pressure. As the ambient temperature decrease, the gas
turbine will experience a low heat-rate and will result in an increase in power output. In
addition; steam production and steam turbine output vary with the gas turbines exhaust
gas flow and temperature supplied to the HRSG. The steam turbine should be sized so
that their rated flow should match the steam turbine production.
reduces as the site elevation increases. While the resulting airflow and output decrease
proportionately, the heat rate and other cycle parameters are not affected. A standard
Effect of altitude is generally used for the design issues of the turbines but beside
design issues; it also affects the operating efficiency of a power plant based on selected
altitudes ambient temperature as shown in Table 3.3. That’s why elevation is a factor that
plant. But this altitude is not a major factor in this decision. Another example is given for
elevation adjustment for power output as follows. Table 3.3 shows the power output
(WECC) locations based on standard gas turbine altitude correction curve. Locations are
Table 3.3 Gas turbine power output elevation correction factors for locations (Northwest
Power Planning Council 2002)
Location Elevation (ft) Power Putput Factor
Buckeye, AZ (nr. Palo Verde) 890 0.972
Caldwell, ID 2370 0.923
Centralia, WA 185 0.995
Ft. Collins, CO 5004 0.836
Great Falls, MT 3663 0.880
Hermiston, OR 640 0.980
Livermore, CA 480 0.985
Wasco, CA (nr. Kern County 345 0.990
plants)
Winnemucca, NV 4298 0.859
condenser cooling appears to be an issue of increasing importance for the locations where
there is no abundant water resources. Distance to the water resources, such as a river or a
lake, affects decisions during the planning phase of construction and its schedule.
construction of dry cooling systems are discussed below. It also may result with higher costs
in terms of pipe supports and piping equipment that carries cooling water from water
resource to power plant and vice versa. If the distance increases, the size of the required
pumps for the cooling system that runs the pipes lines will increase, and therefore the
Cooling towers are generally used to achieve an effective cooling of the processed
water in power plants. A cooling tower is an equipment used to reduce the temperature of a
water stream by extracting heat from water and emitting it to atmosphere. Cooling towers
59
make use of evaporation whereby some of the water is evaporated into a moving air stream
and subsequently discharged into atmosphere. As a result, the remainder of the water is
cooled down significantly. Cooling towers are able to lower the temperatures more than
devices that use only air to reject heat, like huge radiators, and are therefore more cost-
There are different methods for cooling such as “wet cooling” and “dry cooling”.
These two technologies are introduced to a power plant based on its size, planned budget,
water availability of the constructed power plant’s region and etc. Wet and dry cooling
technologies are explained as follows. Wet cooling occurs in all conventional cooling towers,
and it is commonly used in large systems due to its low initial cost and low sink
all devices that reject heat by heating the incoming air. Dry cooling is commonly used in
60
smaller applications, but all dry systems have following issues: higher fan costs, higher sink
temperatures (therefore lower system efficiency and higher power consumption), great
above and they have no associated water treatment costs. Since focus is on the large
combined-cycle power plants construction wet cooling and associated cooling towers are
the main objective at this point. Also construction and implementation of combination of
wet and dry cooling is newly introduced in today’s investments where both options are
applicable.
Materials are chosen to enhance corrosion resistance, reduce maintenance, and promote
reliability and long service life. Galvanized steel, various grades of stainless steel, glass
fiber, and concrete are widely used in tower construction as well as aluminum and
plastics for some components (Bureau of Energy Efficiency 2004). The basic components
of a cooling tower that should be taken care of during the construction phase include
frame and casing, fill, cold water basin, air inlet, louvers, nozzles and fans. Frame and
casing of larger towers are mode of concrete. Glass fiber is also used for cooling tower
casings and basins because they extend the life of the cooling tower and provide
protection against harmful chemicals. These structural frames support casings, motors,
fans and other components. Fills are used to facilitate heat transfer by maximizing water
air contact. Cold water basin, during the construction period, should be located at the
bottom of the tower or near the tower. Mainly a basin receives the cooled water that
flows down through the tower and fills. Air inlet; it is the point of entry for air entering
61
the tower. Based on the design of the tower air inlet is constructed whether at the entire
side if the tower (cross-flow design) or it can be located at the lower part of the sides or at
the bottom of the tower (counter-flow design). Louvers; are constructed based on the
design of the cooling tower. Many counter flow tower design do not require louvers. The
purpose of louvers is to equalize air flow into the fill and retain the water within the
cooling tower. Nozzles; spray water to wet the fill, therefore a uniform distribution at the
top of the fill is essential to achieve proper wetting of the entire fill surface. During the
construction these nozzles can be fixed and spray in a round or square patterns, or they
can be part of a rotating assembly. For the nozzles plastics are widely preferred, and
many nozzles are made of PVC, polypropylene and glass filled nylon. Generally hot-
Cooling towers for power plants can be categorized in two types: the natural draft
and mechanical draft towers. Natural draft cooling towers are mostly for large heat duties
and they require large concrete structures that are expensive to construct. Its height is up
to 200 meters with its concrete tower shell. They are also called hyperbolic cooling
towers which make use of difference in temperature between the ambient air and hotter
air inside the tower. Due to the layout of the tower no fan is required. Natural draft
towers tower are separated in two parts based on its construction design which are cross
flow natural draft and counter flow natural draft cooling towers.
Mechanical draft cooling towers have large fans to force or draw air through circulated
water. Mechanical draft towers are available in a large range of capacities. During the
construction, towers can be either factory built or field erected. For example, concrete
62
towers are only field erected. Therefore site preparation, piping and access to the site
Many towers are constructed so that they can be grouped together to achieve the
desired capacity. Thus, many cooling towers are assemblies of two or more individual
cooling towers or “cells”. The number of cells they have, e.g., eight-cell tower, often
refers to such towers. Multiple-cell towers can be lineal, square, or round depending upon
the shape of the individual cells and whether the air inlets are located on the sides or
Figure 3.13 Cross Flow Natural Figure 3.14 Counter Flow Natural
Draft Cooling Tower (Gulf Coast Draft Cooling Tower (Gulf Coast
Chemical Inc. 1995) Chemical Inc. 1995)
63
Distance to the fuel sources: Moving natural gas from where it is purchased to the
power plants where it is going to be turned into electricity is an ever present challenge for
regulated market operations. For a power plant that is constructed too far from the main
gas transportation lines, the following considerations should be taken into account for a
reliable and safe operation: Negotiation with the suppliers and market companies, daily
and future’s financial transactions, nominated and scheduled supplies are required to
reduce exposure to pipeline penalties, risk management policies concerning natural gas
Location of natural gas pipelines are not a significant factor for selecting a
construction site. The U.S. natural gas pipeline network is a highly integrated
transmission and distribution grid that can transport natural gas to and from nearly any
Table 3.5 Lower 48 States of highly integrated pipeline network (EIA 2007)
Regions States
Northeast CT, DE, MA, MD, ME, NH, NJ, NY, PA, RI, VA, VT, WV
Midwest IL, IN, MI, MN, OH, WI
Southeast AL, FL, GA, KY, MS, NC, SC, TN
Southwest AR, LA, NM, OK, TX
Central CO, IA, KS, MO, MT, NE, ND, SD, UT, WY
Western AZ, CA, ID, NV, OR, WA
power plant that is going to be constructed is located close the to main electricity
transmission lines. The operational activities of a power plant and reliability issues are
affected by its location. These operational activities are not in the scope of this thesis.
64
From the construction point of view, the locations of a power plant with respect to its
distance to the transmission lines affect the substation of this power plant to be projected
may require higher rate of power transformers and different types of high voltage circuit
breakers and etc. Thus, higher investment costs for the substations of power plants have
to be taken into account during the planning period of a power plant to be constructed.
Again, if a plant is also far from the main transmission lines, then additional network
should be constructed between the substation of the power plant and main transmission
line. But this is not a common situation, because most of the power plants are located
close to the transmission lines. Different power generating technologies such as solar
power plants or wind farms may be far from transmission lines because of their specific
available resources regions. These energy resources are usually located in areas with
good sun irradiation or good wind characteristics. The following key aspects have to be
studied for transmission network connection and substation construction projects which
can be studied with the construction management body of knowledge study which was
potential generation connection points and connection method for the proposed
plant generation,
budgetary price,
65
based on this capacity the import/export requirements for the generation and
Once these key aspects are studied before the contract period, a grid connection
plan is proposed in terms of cost, provision of power plant auxiliary supplies, obtaining
plans for constructing any additional infrastructure that may be required for the
connection, and obtaining grid connection for the planned completion date of the
proposed power plant with minimum system reinforcements (London Power Associates
2009). This plan is more focused on the field works and based on studied final key
CHAPTER 4
METHODOLOGY
The current and future projected cost of new electricity generation capacity is
critical information for development of energy projections and analysis. The cost of new
power plant plays an important role in determining the mix of capacity additions that will
serve growing loads in the future. Because cost of construction and fuel to be used may
be substituted, these considerations become more feasible in term of economics. The cost
of new power plant also helps to determine how new capacity competes against existing
capacity. Current and projected future power plant construction costs of energy related
This study aims to provide a summary of main findings of a CCGT power plant
and its construction, including a comparison of the new estimates on construction cost
information regarding the “overnight” and “all-in” cost for CCGT generation technology.
The cost estimates for the proposed technology were developed for generic facility of a
specific size and configuration, and assuming a location without unusual constraints or
infrastructure needs. This case study does not include a cogeneration technology within
power plant.
The inclusion or exclusion of various components of costs can have a large impact
on overall cost estimates. This includes categories of civil and structural costs (e.g.
allowance for site preparation, drainage, underground utilities, and buildings), project
indirect costs (e.g. a construction contingency), and owners costs (e.g. development costs,
67
legal fees, insurance costs, property taxes during construction, and the electrical
interconnection costs, including a plant switchyard and tie in nearby transmission) (DOE
4.1.1 Capital Cost: Capital cost estimate is developed on 7-F Class gas turbine bases
CCGT power plant with a specific size and configuration, and assuming a location
without unusual constraints or infrastructure needs. Cost estimate was developed based
on assumed costs in 2010 on an overnight and all-in capital cost basis. In each cost
estimate, the total project engineering, procurement and construction (EPC or Turnkey)
This approach does not always result in the lowest cost of construction; but it does
result in an achievable cost of construction. These cost considerations which are given
4.1.2 Operation and Maintenance (O&M) Expenses: O&M expenses consist of non-
fuel O&M costs (or direct operation of the proposed power plant), owner’s expenses, and
fuel rated expenses. Direct O&M costs include the following categories; Fixed O&M
expenses, Variable O&M, and Major Maintenance. Fixed O&Ms do not vary
significantly with generation. Variable O&M expenses are related to the production
extended outage, and it varies with electrical generation or the number of plants start-ups
CHAPTER 5
This chapter describes the technical characteristics and cost and performance
assumptions for a new natural gas combined-cycle gas turbine power plant. The intent is
to characterize a power plant based on its location, facility descriptions and basic
discussed in more details when compared to the previous chapter. There are three
objectives which are process and technology status for constructing a power plant, costs,
and economics and reliability issues for pre-construction and post-construction period,
recognizing that each plant is unique and those of actual projects may differ from these
assumptions. These assumptions may be helpful in the assessment of other issues where
production e.g. base load or peak load. The main rule is that operational flexibility is
expensive. The main consideration in the design process is the choice of the optimal set
of gas turbines (Alstad - Foss 2004). For each combination of fuel cost, load factor and
capacity factor, there is an economical pressure and temperature of steam which will
result in the lowest cost of power. There is a tradeoff between increasing the efficiency
due to increase in steam pressure and temperature and the additional investment in
equipment required for the purpose (Bolland 2003). A deeper approach on the CCGT
power plants helps to get more understanding on this case study from technology point of
view. CCGT plants offer maximizing efficiency, minimizing emissions and a great
70
approach to environmental issues when compared with the gas fired thermal plants.
Overall, 20% of the world’s electricity production is based on natural gas. The electricity
natural gas. In the United States, the total generating capacity is approximately 1000 GW,
of which 395 GW is based on gas. CCGT is the dominant gas-based technology for
intermediate and base-load power. A CCGT plant consists of one or more gas turbine
electricity generators equipped with heat recovery steam generators (HRSGs) to capture
heat from the gas turbine exhaust. Steam produced by the HRSGs power a steam turbine
generator to produce additional electric power. It’s an important design criterion that
CCGT plants respond relatively fast to changes in supply (from base-load capacity) and
demand. Technological developments aim to increase the efficiency by raising the gas
turbine inlet temperature and simultaneously decrease the investment cost and emissions
expected to increase from today’s 52-60% (lower heating value, LHV) to some 64% by
2020. But there is a fact that even if new CCGT power plants constructed till 2020, they
will have only 18% of global electricity output by 2020 and 15% by the 2030 due to
today’s projections. And when compared to the coal-fired power plants, CCGT plants
have much lower specific investment costs. They emit roughly half as much CO2 per
kWh as coal-fired power plants. Non greenhouse gas (GHG) emissions e.g. SO2, NOx
(nitrogen oxide), and particles are also relatively low. The best available CCGT power
plants emit approximately 50% less CO2 and up to nine times less NOx per kWh than the
coal fired power plants. The emission of NOx of a CCGT plant may be reduced by
71
application of SCR (Selective Catalytic Reduction of NOx). Table 5.1 provides the
characteristic data of NOx of a CCGT plant without and with SCR (IEA 2009). SCR
technology is used for the reduction of NOx from gas fired units. This technology is
capable of reducing nitrogen oxides with an efficiency of up to 95%. As the energy costs
rise along with environmental awareness, additions of SCRs to the systems will become
more common in order to keep energy production cost effective and the environment
clean.
Table 5.1 Characteristic NOx emissions of a CCGT plant with and without SCR (IEA
2009).
Combined Cycle plant Combined Cycle
Fuel Unit
(no SCR) plant with SCR
NOx ] 52.5 23
emission 45 20
0.30 0.13
At the beginning of this chapter it is mentioned that; “choosing the optimal design
of components is made based on the type of production e.g. base load or peak load”.
Based on this information, and due to their low specific investment costs but relatively
high fuel costs (natural gas) compared to coal-fired plants, CCGT plants are generally in
lower demand in terms of long term economical expectations, which means they are
operated in intermediate rather than in base load. The opposite approach is also true for
the coal-fired power plants. This explains why they will have only 18% of global
electricity output by 2020 and 15% by the 2030 with respect to today’s projections.
Due to high price of construction materials and equipment and the increasing
demand for new CCGT plants the investment cost of a CCGT power plant has increased
CCGT plants may decline from $1100/kW in 2010, to $1000/kW in 2020, and to
$900/kW in 2030, according to International Energy Agency. The annual operation and
costs, i.e. $44/kW/a in 2010, $40/kW/a in 2020 and $36/kW/a in 2030. Representative
45/MWh for natural gas (IEA 2009). This information on CCGT power plant is presented
in a tabular form in Table 5.2, Table 5.3, Table 5.4 and Table 5.5.
Output Electricity
Technologies CCGT
Efficiency, % 52-60%
Technical lifetime, yr 30
Nox, g/MWh 30
73
Based on the above information, a case study on CCGT power plant is presented
in detail next.
A 2x1 configuration using F-class natural gas turbine technology with production
switchyard for electrical interconnection, cooling towers for cooling the steam turbine
condenser, a water treatment facility and control and maintenance facilities are
considered in terms of cost for the construction of this 2x1 configuration, 540 MW
CCGT power plant. Location of the proposed power plant is assumed not far from the
main natural gas transportation lines and high voltage power transmission lines, therefore
74
issues related to the Chapter 3.2.3 do not have any additional influences on the
construction phase of the plant and the investment cost of the plant. One of the
consequences of this matter is shorter construction period and lower technical costs
are assumed to be applied to FA-class gas turbine which are 14.7 psia, 59 degree
Fahrenheit and 60% relative humidity. The generating capacity of 540MWs is obtained
at this ISO conditions. A 2x1 configuration combined-cycle plant consists of two F-class
gas turbine and generators and a steam turbine generator which is one of the most
common technologies in use for large size CCGT power plants since the last ten years.
Since two gas turbines and HRSGs are used, a large steam turbine generator is used.
Larger plant sizes result in economies of scale for construction and operation, and designs
augmentation features, including inlet air chilling and duct firing (direct combustion of
natural gas in the heat recovery steam generator). Duct burners use supplementary firing
to increase the heat energy of a gas turbine’s exhaust, making it possible to increase the
output of a HRSG. Most of the modern combined-cycle plants are designed for baseload
operation using duct burners. Generally, duct firing provides electrical output at lower
capital cost. It is therefore often utilized during the peaking hours of load. For example,
gained by duct firing. The main issue is not the thermal efficiency of duct fire, which is
75
much lower than the base combined-cycle plant’s thermal efficiency. But the cost of duct
firing is low and other than that; the additional electrical output can be valuable during
Pipeline natural gas is the fuel of choice because of relatively stable prices which
may be guaranteed at forecasted gas price by the pipe line operator companies,
deliverability and low air emissions. Therefore there is no need to build storage for back-
up fuel. Generally distillate fuel oil is used as back up fuel, however, its use for this
purpose has become less common during the last decade because of additional emissions
of sulfur oxides. A periodic testing is needed in this case to ensure proper operation on
fuel oil which has increased turbines maintenance that caused by fuel oil during the
operation. This results to an increase in the scheduled outages of the system and
eventually decreases the plant availability. It is now more common to ensure fuel
required for cooling the steam condenser, therefore it is assumed that the power plant is
planned to be constructed near a water resource, e.g. lake or river. Actually water
consumption can be reduced by use of dry (closed cycle) cooling. But this is not the case
in our study. In addition to this, the use of dry cooling has a negative influence on cost
Electrical and Control Systems: The 2x1 configuration conventional CCGT hast two
combustion turbines (CT) and one steam turbine (ST) electric generator. The generators
for the CTs are 60 Hz and rated at approximately 215 MVA with an output voltage of 18
kV. The ST electric generator is 60 Hz and rated at approximately 310 MVA with an
76
voltage bus in the conventional CCGT via dedicated generator circuit breaker, generator
increases the voltage from electric generators from 18 kV to interconnected high voltage.
This CCGT power plant is controlled using a Distributed Control System (DCS). The
DCS provides centralized control of the facility by integrating the control systems
provided with each individual CT and associated electric generator, ST and associated
electric generator, and the control of Balance-of-Plant (BOP) systems and equipment.
The proposed CCGT power plant is based on the General Electric 7FA gas turbine
generator in 2x1 configuration. The base load capacity is 540 MWs and the plant includes
an additional 70 MWs of power augmentation using duct burners. The plant is fueled
with pipeline natural gas using a firm gas transportation contract with capacity release
explained in Chapter 3.2.3 of this thesis. After plant facility description and basic
the following groups should be defined from the construction management point of view
that which was previously discusses and explained in details in Chapter 2.2. Parties
involved in this plant construction are financiers, owners, insurers and original equipment
consumer-owned utility: 5%
investor-owned utility: 5%
77
Financing assumptions for these project developers are shown in Table 5.6. Long term
Another important step is to define the “technical performance” of the power plant
before the project period. Net power to be generated, operating limits of the power plant,
scheduled outages, forced outages, system availability and etc. are defined with the
plant are shown in Table 5.7. Both the financial and technical negotiations are made
during the contract period. Once the contract negotiations are over and all parties have
come to terms, on both technical and economic conditions, it is time to start the job. The
78
first step will be to set up the job site. Actually, the whole purpose of the site preparation
is to facilitate the management process. During the process of managing project in field
all of the steps are discussed in detail. Some example are the amount of man power
required for each specific stage of the construction phase based on schedule; allocation of
construction equipments in the field such as units, modules, auxiliary generators. Safety
precautions are well determined and requirement education and information support is
given to the workers. At this stage of the construction a site manager is highly
process, and relationship with the third parties. This site manager has not too much to do
with technical works. This position is needed for a better construction management
during the very beginning of the site work, because delays caused by miscommunication
due to lack of management skills may cause delays on overall project which means a late
Heat rate New & clean (Btu/kWh): Baseload is new & clean rating for GE
(HHV, net, 6880 baseload; 9290 207FA/ Lifetime average is new &
ISO incremental duct firing; 7180 clean value derated by 2.2%.
conditions) full power. Degradation estimates are from GE.
Lifetime average (Btu/kWh): Duct firing heat rate is
7030 baseload; 9500 recommmendation.
incremental duct firing; 7340
full power.
80
Elevation See Table 3.3 for power Based on standard gas turbine altitute
adjustment output correction factors for correction curve.
for power different elevations. Power
output output factor: 0.985
After financial assumption and technology are specified cost and development
schedule is prepared. At the very beginning of this development schedule studies are
made with respect to draft project study and concluded with the final project study where
all parties reach an agreement. Table 5.8 shows the costs of the 2x1 configuration CCGT
At the very beginning of this thesis, the economics on a power plant and its
relationship with the technical considerations and reliability issue have been mentioned
and an illustration of this relationship is presented at Figure 1.1 in Chapter 1. Here, the
investment cost of a 2x1 configuration CCGT power plant is defined. The components of
the investment cost of this power plant are based on, installed capital equipment,
contractors’ engineering and construction costs that are involved into construction,
connection to cooling water, connection to a gas terminal, spare parts and etc. These
parameters are given and used for determination of economics of a power plant. Their
year’s investment cost datas are investigated (last 10 years) before this table of economic
is constructed. Construction cost of the power plant is yielded here in terms of $/kW.
While the cost of this construction is estimated, an equilibrium market conditions are
considered where the supply of goods are equal to their demand. Since there is neither
surplus nor shortage in the power market, there is no innate tendency for the price of the
items to change. Beside its cost project time is also determined at this stage.
Table 5.8 Cost and development schedule of a 2x1 combined cycle plant (page 1 of 2)
Cost &
Data Explanations
Schedule
Development Baseload configuration: Excludes financing fees and interest
& $945/kW overnight; durinnf construction. Assumes
construction $1038/kW all in. “equilibrium” market conditions.
(D&C) cost Power augmentation Values are based on new & clean
configuration: $878/kW rating.
overnight; $964/kW
all in.
Table 5.8 Cost and development schedule of a 2x1 combined cycle plant (page 2 of 2)
Cost &
Data Explanations
Schedule
Interconnectio $15.00/kW/yr Includes scheduling, system control
n and regional and dispatch, and reactive supply and
transmission voltage control ancillary services.
costs Busbar effects are omitted. Value is
based on new & clean rating.
Overnight cost: Overnight cost is an estimate of the cost at which a plant could be
constructed assuming that the entire process from planning through completion could be
accomplished in a single day. This concept is useful to avoid any impact of financing
issues and assumptions on estimated costs. Starting from overnight cost estimates,
electricity modeling explicitly takes account of the time required to bring each generation
technology and the costs of financing construction in the period before a plant becomes
operational.
Technical & cost datas for the proposed case study are shown in Table 5.7 and
Table 5.8. A comparison between our case study and datas from the US Energy
Information Administration for the same technology F-class gas CCGT power plant is
Figure 5.1 Cost Datas for F-Class CCGT Power Plant (EIA 2011)
Plant
Characteristics Plant Costs
Nominal Heat Overnight Fixed O&M Variable O&M
Capacity Rate Capital Cost Cost Cost
(kilowatts) (Btu/kWh) (2010 $/kW) (2010$/kW) (2010 $/MWh)
Conventional CCGT
(EIA 2010) 540.000 7.050 $978 $14,39 $3,43
CASE STUDY
(2011) 540.000 6.880 $945 $12,10 $4,70
83
Net delivered gas prices are subject to change based on incremental pipeline
capacity costs. Delivered gas prices are generally expressed in variable cost terms
(Btu/kWh). Actually, a portion of the price will be fixed, and will have to be paid
whether or not the plant is operating. It is assumed that the firm pipeline transportation
component of the fuel price is a fixed payment, but that portion of this payment can be
recaptured through the capacity release market. Therefore the only fixed portion of the
fuel price with respect to power plant dispatch decisions is the portion of the fuel
transportation cost that is not recoverable in the capacity release market. Here, it is
assumed that the total firm transportation costs comprise 90% of the delivery costs. And
it is assumed that 10% of this cost can typically be captured in the capacity release
market. This approach is proposed to the power plants where sales of electricity produced
are granted and to those where alternative pipeline transportation pipelines are available
as an option. Figure 5.2 shows the historical information on U.S. wellhead gas prices in
U.S. dollars per thousand cubic feet on a yearly basis between 1999 and 2010.
9
8
US $/thousand cubic feet
7
6
5
4
3
2
1
0 US wellhead gas prices
1998
2005
1996
1997
1999
2000
2001
2002
2003
2004
2006
2007
2008
2009
2010
84
Table 5.9 and Table 5.10 give a clear definition on cost associated with each
element that is considered during the construction of a CCGT power plant. And finally
Table 5.10 Investment cost of a 2x1 combined cycle plant (additional costs)
In % of
Additional costs $ USD (x1000)
Turnkey cost
Turnkey contr. 5.0% 20486
Table 5.11 Total project investment cost of a 2x1 combined cycle plant
Total investment cost $ USD (x1000)
Turnkey costs 409730
Additional costs 181277
combined cycle power plant is around 590 million U.S. dollars. It should be noted that
this cost rate is increasing every year based on energy costs and capital costs. In other
words the two major factors that are increasing the cost of electric generation are
increased fuel cost and increased cost for new construction. On the other hand price may
decrease if the technology used becomes more mature and the output efficiency is
likely to grow in the future. While new technologies will have an important impact, they
are not likely to be a complete solution for all of our energy issues, and therefore resource
planning will continue to be made on long-term periods because of the numbers of years
required to plan, develop and construct facilities. Almost every two decades there has
been a strong economic growth period and periods of recession. Under the effects of
these circumstances, planners must ensure an adequate and reliable supply of electricity
for customers at all usage levels regardless of any short-term economic fluctuations.
Therefore, forecasting should be taken into account during the periods of strong
economic growth, with high customer demand. At these extreme periods reliability issue
should be discussed with the construction of new power plants. Since the future is
86
include high and low, facilities, fuels and environmental costs which helps to create a
safe and more reliable power market (Minnesota Office of Energy Security and the
cover a range of foreseeable load-growth outcomes and should be taken into account for
uncertainty with achievable conservation levels and potentially significant industrial load
growth. The forecast of energy need should include projected power plant construction
5.3.1 Reliability from generation point of view: The main goal of generation
planning is to meet the electrical energy needs of the customers at the least cost safely,
reliably and on equal basis. Generation planning deals with future decisions which have
include: Fuel prices, investment costs, unit operation, regulatory developments and etc.
The probability of consumers being disconnected for any reason can be reduced
constraint can be violated although the system may be very reliable. On the other hand
underinvestment leads to the opposite situation. It is evident therefore that the economic
and reliability constraints can be competitive, and this leads to difficult managerial
decisions at both planning and operating phases (Billinton and Allan 1996). Increased
investment means; an investment plan for a new power plant on the planning phase or
adding new units such as HRSGs or duct burners to an existing plant on the operating
phase. Reliability of a system is also related to the investment cost. To be able to achieve
87
a higher reliability for the generating unit to be constructed, additional investment costs
has to be incurred. The relationship between the reliability of a system (R) and the
Reliability (R)
Based on Figure 5.3, as the incremental cost (∆C) is increased, an increase in the
reliability (∆R) is observed. But there is an important point that can be learned from
Figure 5.3. Although the reliability increases with the investment cost, this situation is
actually limited, because the increment level for the reliability decreases when investment
cost increases. Basically it’s very expensive to increase reliability based on investment
continuously.
In this chapter investment costs, and the effects of fuel prices are investigated
from a construction point of view. For the reliability issue, unit operation or influence of
deregulated electricity markets each generator can have an influence on prices. Since
electricity demand is both time varying and uncertain, the time varying character of
electricity demand is often represented by load duration curve, the inverse of which can
incorporate overall uncertainty for the underlying demand. Power system planning with
respect to generation planning uses different methods such as; “Levelized bus-bar”,
“screening curve analysis” and evaluation of power system reliability” (Stoll 1989).
These methods are not discussed in this thesis since they are not the main focus of this
thesis.
electricity has encouraged more and more cost control over the construction. This led to
the creation of a new kind of power generators and independent power producers. These
independent power producers were focused on selling electricity at a profit, with their
selling prices reflecting the supply and demand of the electric power system. Therefore,
they were much focused on controlling costs and schedule, especially when building new
power plants which also affected the reliability of the system. Investors were forcing
owners and contractors to become extremely cost conscious and take responsibility for
not only the building of the power plant but also its output efficiency. One of the technical
results of these applications has led to a major shift in the basic type of power plant being
constructed. It led to a shift from large steam driven turbines to smaller gas fired turbines
that could handle rapid load shifts at higher machine efficiencies. These types of power
plants could be delivered, installed and commissioned much sooner than other large
turbines. As the power plants became smaller or again large but with multiple turbines
and generators associated to them, reliability calculations has changed. Instead of losing
large generating capacities, now smaller generating capacities are lost which led to an
increase on reliability of the overall system. Scheduled outages when compared to large
old power generating units became lower. Economically expensive power plants can also
89
be substituted with the new technologies which help increase the reserve capacity to
Within CCGT power plant Heat Recovery Steam Generators (HRSGs) also takes
an important role. A HRSG yields additional power which is aimed to be but on the other
hand it may decrease the availability of the system. Unsatisfactory reliability and
durability problems occur during the full range of operation of a CCGT power plant such
as at partial loads, at shut-downs and at restarts from diverse pre-start conditions. The
biggest reason of this situation is based on the selection of HRSGs. The selection is
usually from the lowest bidder. To be able to succeed in the competitive market, HRSG
designs which just meet the requirements of purchasers’ specifications and boiler design
code. Design enhancements that improve reliability and durability at even a small cost are
discouraged because most purchasers will give no credit for durability and select the
lowest bidder (Pearson and Anderson 1999). This one time investment on HRSGs affects
Reliability issue for a new CCGT power plant is affected by economics of this
power plant, and vice versa. But reliability is more affected by the technical
considerations and technologies that are selected for a power plant. This is generally a
one way relationship between reliability and technical considerations. Finally it can be
said that there are two main factors should be taken into account: the cost of reliability
able to achieve a certain level of reliability. And the worth of reliability is the economical
CHAPTER 6
CONCLUSION
important issue. This administrative approach to the power plant construction helps
engineers, managers and different parties involved into this process. Technical
information based on the proposed plant technology also helps make critical decisions
with the consideration of high management skills; during the planning phase and
money if they are taken with the technical considerations, because once parties start to
involve field work such as site preparation, erection of building, building turbines and
etc., there is no way back and every decision taken may be money saving or may cause
the loss of a huge amount of money that directly affect the construction cost and
schedule.
The CM is one of the key people in a construction team. The CM’s knowledge of
industry and the CM’s expertise in several management functions are critical in the
success of a project. However, most CMs use traditional methods to perform their duties.
this thesis is to investigate the construction attiributes of natural gas fired power plants,
and technical issues related to technology and construction. While a new power plant is
being constructed the steps being followed and the objective of each step is determined
and examined such as schedule of the construction, time, field construction works,
generation technology to be used. All of these steps (e.g. erection of HRSG for a CCGT
92
power plant) were studied on the basis of the construction cost of a power plant that is
Basically, traditional management process is divided into three part.The first part
is the project delivery method and sourcing the available resources for construction.
Planning process is then achieved that includes many issues such as risk management,
Setting up the site is the next. In fact, the whole purpose of the site setup is to facilite the
management process. Thought and great effort are given to the administrative
requirements, the actual site project management tools that will be used, the purchasing
process, the quality and its control, and the safety managed. The second part is again
managing as we discussed but here the most important is the schedule of the construction.
Control of the manpower, tools and equipment, and site services are major components
that results in succesfull power plant construction management. The third part is
composed of interdisciplinary project works such as the melting pot of electrical and
mechanical projects. Revision of the updated projects is also another action of the third
part of management process which leads the whole process to a succesfull end and to a
this thesis, since these actions define the general situtation of an on-going construction
process. Computer softwares enables engineers to enter all this information to make a
better evalution during the planning phase. Feasible and time saving applications are
made from the very begining from constructual material selection to complicated
integrated sytem cost analysis based on used technology and site equipments by using
programs such as CAD. Building Information Technology (BIM) is a new era for CMs
93
where they can be educated and make field application based on BIM that enables a
better material allocation and a better launch to different databases and their evaluation
Cost always takes the first place for any kind of investment. After determination
and investigation of costs related to power plant construction, we can say that investment
costs for power plant (a CCGT plant in this thesis) will keep almost the same as 2010
data which is close to $1100/kW for the next ten years. Projected future cost of a CCGT
power plant is $1000/kW at 2020 and $900/kW at 2030. Based on case study in Chapter
5., it can be said that the primary sources of the increase in construction costs are (1)
material input cost, including the cost of raw materials such as steel and as well as
increased cost of components manufactured from these raw materials (e.g. transformers,
turbines, pumps); (2) price of fuel; (3) market for large construction project managent.
Increase worldwide demand for new generating and other electric infrastructure projects,
particularly in China, has been cited as a significant reason for recent escalation in the
construction cost of new power plants. Despite these higher costs, utilities will continue
to invest in baseload generation. This increasing cost in the next decade may result in an
additional effort to develop more mature and efficent turbines. But we have not reached
this level yet, therefore this situation eventually will effect costumers, because the cost of
electricity from new plants will be higher than that from existing plants.
Beside other main parameters that affect the cost, the additional costs associated
the constructions phase can be managed by CM methods. This method helps avoid
unexpected costs during construction period and ensures a reliable construction period. A
safe and trustable construction environment also helps decrease the overall cost. Through
94
risk analysis that is conduct with cost analysis, the risks that affect the levelized
investment cost of a power plant other than the capital investment cost can be decreased
BIBLIOGRAPHY
AIA. (1973). Standard For of Agreement Between Owner and Construction Manager.
American Institute of Architects, Document B-801, Washington, DC.
Alstad, M. R., Foss, T.J, (2004). Investment Analysis of CCGT Power Plants
Norwegian University of Science and Technology, Trondheim.
Baldick, R., (1999). Introduction to Electric Power Systems for Legal and
Regulatory Professionals. Course Materials, The University of Texas at Austin.
Billinton, R., Allan, R.N., (1996). Reliability Evaluation and Power Systems.
Second Edition, Plenum Press, New York, NY
Bobick, T.G., (2004). Falls Through Roof and Floor Openings and Surfaces,
Including Skylights: 1992 –2000. Journal of Construction Engineering and
Management 130(6), 895–907.
Bolland, O., (2003). TEP9 Thermal Power Cycles and Cogeneration. Lecture notes at
Norwegian University of Science and Technology, Trondheim.
96
Demirci, F.S., (2008). AKCA Energy Lightning System Design Report. Technical
Education Paper. Saraykoy, Denizli, September 2008.
EPA, United States Environmental Protection Agency., (2004). “The Practical Pollution
Report. Current Understanding of Air Quality and Emissions through 2003 , EPA
454 –R-04-002, December 2004.
International Energy Agency, IEA OECD (2009). Energy Technology System Analysis
Program. www.etsap.org, Technology Brief E02, September 2009
Retrieved March 31, 2011, from
http://www.etsap.org/E-techDS/EB/EB_E02_Gas_fired%20power_gs-gct.pdf
Jannadi, M.O. & Assaf, S., (1998). Safety Assessment in the Built Environment of
Saudi Arabia.” Safety Science, 29(1), 15–24.
Kauffmann, M.W. (1977). Set guidelines for engine foundations. Turbines and diesels
Power, October 1977
Kehlhofer, R., (1991). Combined-Cycle Gas & Steam Turbine Power Plants.
Published by The Fairmont Press, Inc.
Khemani, H.,(2009). How Does a Gas Turbine Power Plant Work? The Auxiliary
Systems. Retrieved March 29, 2011, from
http://www.brighthub.com/engineering/mechanical/articles/25424.aspx
Nelson, P.N., (1984). High Altitude Considerations For Electrical Power Systems
and Components. IEEE Transactions on Industrial Applications, Vol IA-20, No 2.
March/April 1984.
Schatteman, D., Herroelen, W., Van de Vonder, S. & Boone, A., (2008). Methodology
for integrated Risk Management and Proactive Scheduling of Construction Projects.
Journal of Construction Engineering and Management, 134(11), 885-893.
Pearson, M., Anderson,W.R., (1999). Reliability And Durability From Large Heat
Recovery Steam Generators. Proc. Instn. Mech. Engrs. Vol 213, Part A. Page:
151-168
Russel, A.D., Chiu, C.Y. & Korde, T., (2009). Visual representation of construction
management data. Automation in Construction, 18(8), 1045-1062.
SAVE International. (2001). Value methodology standard. Retrieved May 14, 2010,
from
http://www.value-eng.org/manuals/vmstd.pdf.
Stoll, H., (1989). Least-Cost Electricity Utility Planning. New York: John Wiley 1989
U.S Department Of Energy., (2010). Updated Capital Cost Estimated for Electricity
Generation Plants. U.S. Energy Information Administration, Office of Energy
Analysis, November 2010. Washington, DC.
Wilkes, C., (2007). Power Plant Layout Planning – Gas Turbine Inlet Air Quality.
“Journal of General Electric Company”, GE Energy, Greenville, SC.