Beruflich Dokumente
Kultur Dokumente
FOUNDATIONS:
Intended to house 1,400 pupils by 2002, and replacing two existing schools, Immanuel
is a large institution with, inevitably, a strong impact on its surroundings, though this 1200x350mm reinforced concrete strip foundation, to a depth of 550mm below frost
was ameliorated, to some extent, by the contours of the site. The nature of a line of existing grond level. concrete strenht clas 30N/m.
secondary school, with laboratory, IT and other specialised facilities, is at odds with
the more folksy image of the school, evoked, for example, by some of the celebrated
Hampshire primary schools or by Allford Hall Monaghan Morris's Great Notley school RISING WALLS:
(AJ 4.11.99). external leaf: 215mm blockwork rising wall to external ground level. at ground level
The client saw the development of a strong sixth form as a prime objective and wanted junction 2 courses of 150mm sopabar cement blocks are constructed to form the
this to be expressed in the project, with the provision of a clearly-defined centre for fixing point for the natural stone plinth.
senior pupils. Finally, the use of part of the premises by the local community outside
school hours, was seen as inevitable and, indeed, desirable and had to be provided
internal walls: 150mm blockwork rising wall through height of building.
for in the designs.
Immanuel is described as a college, and the layout of the buildings has a collegiate
feel, with buildings around a central quadrangle, containing a hard-surface play- cavity: cavity at rising wall is 100mm.
WALL CONSTRUCTION:
as yet. Inevitably, perhaps, the route into
the building lies across a car park, thence into a generously scaled entrance hall. The 32mm western red cedar cladding boards, pre treated and pressure impregnated to
first of a series of lifts is provided here for use by the disabled the school is 100 per be fixed with stainless steel fixings.fixed onto 50x50mm treated softwood timber
cent accessible. battens at 800mm centers. top of battens is splayed to prevent poolin of water on
The sixth-form domain, symbolised by the projecting circular common-room block, is to battens. breather membrane is fixed to timber frame below battens, and is sealed at
one side, together with staff room, library and IT suites. The main school block is all penetrations with sealent tape, on 100X44mm treated softwood timber frame
accessed via a glazed bridge spanning the central court. It leads to 'the street', the studs at 400mm centers, timber frame to be fixed back to bloackwork using cross
social and operational heart of the school, defining the main level of the complex and nailing techniquie with hilti gun using stainless steel fixings. a high density insulation
some 56m in length. Classroom and laboratory blocks and the canteen (which forms is used to fill between timber studs. internal leaf comprimises of 150mm blockwork
the fourth side of the quadrangle) open off this spine. The fall of the land allows for two with10mm mortar joints. internal finishes are 12mm plaster board with a 3mm
levels of classrooms below. painted plaster skim finish.
Internally, Immanuel has a lightness and transparency far removed from the
conventional school environment. This is not just a matter of raising spirits, but equally, FLOOR CONSTRUCTION:
it seems, of ensuring proper supervision Immanuel has its share of 'difficult' pupils. floor finish is 3mm vinyl, colour to clients specifications, to be fully adhered to 65mm
Since the school opened its doors last autumn, the damage caused to plaster wall concrete screed, onto seperation layer between screed and insulation. 150mm
surfaces in some common areas, for example, has led to the imposition of a Portaflek insulation required, to be placed onto radon barrier. 150mm reinforced concrete
coating which is less attractive but far more durable. In the central 'street', concrete slab, with a concrete strenght class of 25N/m, on layers of 200mm well compacted
blockwork, tinted the hue of red Cheshire sandstone, provides a highly practical small aggregate hardcore.
alternative. The general impression, indeed, is of a building designed for heavy wear
and intensive use.
FIRST FLOOR CONSTRUCTION:
Exposed steel roof elements, the use of strong colours (blue in the science labs, for
example) and the successful management of natural light, produce spaces which are floor finish is 3mm vinyl fully adhered to top of composite deck, 300mm of
enjoyable and workmanlike, while lacking obvious frills the canteen is a particularly reinforced concrete, poured into temporary proped slimline deep steel deck, profile
dynamic interior. In contrast, the chapel (or 'sanctuary'), located off the main assembly thickness of 1.4mm. edge stops to be welded on all sides, and shear bolts are used
hall, is a rather bleak place, with nothing numinous about it though it was a of steel beams. where the edge stop finishes, a fire stopping insulation must be
significant element in the client brief. incorporated to prevent spread of fire between floors. all composite decks
supported from steel U.B to engineer specified sizes.
Project director Mark Pettit concedes compromises in detailing. The timber fire-doors
which subdivide 'the street' are far more intrusive than the architect's preferred
metal-framed versions would have been but the latter fell victim to budget ROOF CONSTRUCTION:
constraints. Skirting details too have a clumsy and ill-considered appearance. No Trocal fully adheared single ply membrane, to be lapped and sealed min 150mm at
architect with experience of schools expects much respect for his work, but the all upstands and penetrations, on 18mm marine ply deck, on 175x75mm treated
decision to entirely strip Halliday Clark's library at Immanuel of its fittings, within a year softwood rafters, which are fixed to U.B using welded metal cleats, tolerances of
of installation, seems perverse. 10mm allowable for horizontal and vertical discripencies. 15mm cement board is
fixed to underside of s.w roof rafters, to which a 3mm plaster skim coat is applied,
final internal roof finish.
The above is and extract from A.J magazine, dated 27.09.2001
author: Powell, Kenneth. FLASHINGS:
all flashing are proprietary polyester powder coated aluminium flashings, fixed to
s.w timber battens using stainless steel fixings. all flashings have a nosing drip
protruding a min.. of 25mm away from finished facades.
STRUCTURAL STEELWORK:
all internal structural steelwork to be painted with intusment paint, all baseplate and
external fixings to be stainless stel M24 full threaded bolts with lock nuts.
EXTERNAL DRAINAGE:
A diameter 100mm perforated drain is buried within a trench 250mm wide of small
pea gravel around the perimeter of the building, and is 80mm below ground level.
VENTILATION:
A 30mm ventilation cavity is achieved throughout the height of the facade, allowing
for ingrees and egress of air at window opes. insect mesh is fixed at all ventilation
openings.
STRUCTURE:
Immanuel College has been constructed as a number of structurally independent
blocks interconnected with walkways. The timber bridge in the centre of the teaching
blocks has a 16m span and comprises 'Ekki' hardwood lattice trusses, supported on
steel columns at one end, and a reinforced concrete retaining wall at the other. To the
underside of the bridge is a curved concrete ground-bearing amphitheatre for summer
assemblies or lessons.
The school comprises several classroom blocks, an assembly hall, sports hall, canteen
and administration block. Many of the classrooms have exposed galvanised trusses
and hot-rolled purlins upon which a sound-absorbent roof deck by Plannja is laid. Most
non-teaching blocks have curved roofs supported by steel trusses.
British Steel 'Slimfloor' construction was used for structural floors to minimise
floor-to-floor heights reducing height (for planning purposes) and costs. Composite
floor construction also enabled the use of larger spans for smaller beams, to create the
larger open spaces.
Cladding materials include natural stone, cedar boarding, painted render, glazed
curtain-walling and composite cladding panels.
As the school is on a sloping site, a 'terracing' approach was adopted, creating various
levels that could then be supported with reinforced-concrete retaining walls. Natural
features, such as site levels and tree positions, were retained as far as possible.
Foundations were generally pad and strip footings on natural boulder clay.
Name:
Student no.
Kevin O'Brien
20028940
Title: Building Case Study
Course: AT3 Building: Immanuel College, Secondary School
Module: Construction Technology
Date: 01.12.2009 Location: Thackley, Bradford, West Yorkshire, England.
Lecturer: Loy Lee Architects: Halliday Clark
proprietary polyester powder coatd trocal single-ply membrane
aluminium capping detail. roof covering fully adhered to
ply deck below.
152x89mm U.B
256x256mm U.B
floor construction:
3mm vinyl flooring on
65mm concrete screed on
seperation layer on
150mm h.d insulation on
radon barrier, on
150mm concrete slab on
layers of 200mm well compacted h.c
Name:
Student no.
Kevin O'Brien
20028940
Title: Building Case Study
Course: AT3 Building: Immanuel College, Secondary School
Module: Construction Technology
Date: 01.12.2009 Location: Thackley, Bradford, West Yorkshire, England.
Lecturer: Loy Lee Architects: Halliday Clark