Beruflich Dokumente
Kultur Dokumente
DECLARATION
This Tender Report is prepared by the undersigned for the above project and all
reviews made are based on the Tender Documents received only.
1
1.0 INTRODUCTION
2
1.3 CONSULTANTS FOR THE PROJECT:
c) Building Works
e) Mock-up Units
The tender is based on Bills of Quantities which form part of the contract in
accordance with the “Agreement and Conditions of PAM Contract 2006 –
Private Edition with Quantities”. No adjustment in the tendered sum will be
allowed. However, if there are changes in the scope of works ordered by the
Employer, these will be treated as variations and adjustments to the tendered
sum. The tendered rates will be used as a basis for valuation of such
variations.
3
4.0 CALLING OF TENDER
All tenderers were required to submit their tenders on the stipulated time viz.,
not later than 12 noon on 24th March 2011 at the office of:
The tenders were opened at the office of Messrs. Sime Darby Property Berhad
(Contract Management Department). All the Ten (10) tenderers that
responded to the invitation, submitted their tenders on or before the stipulated
date and time.
All the tender documents were then reverted to the office of the Consulting
Quantity Surveyor on 24th March 2011. The detailed analysis and tender
evaluation focused on five (5) lowest tenders only as other five (5) tenderer’s
offer were higher. It is unlikely that the offer will be neither considered for
acceptance nor beneficial to the Employer. The tabulation of the tenders
received arranged in ascending order is depicted in Table 1 of Page 5. (Refer
also Schedule of Tender Opening)
There was one (1) no. Addendum issued and all the ten tenderers have
included it in their tender.
4
5
Table 1 - Tenders Received in Ascending Order
Tender Tender
Tender Tender
Sum (RM) Sum (RM)
Sum (RM) Sum (RM)
with 60 Completio with 60 Completio
24 Month 24 Month
Code Tenderer Position Month n Period Month n Period Remarks
Defect Defect
Defect (Weeks) Defect (Weeks)
Liability Liability
Liability Liability
Period Period
Period Period
PA BUILDERS
6/10 1 21,788,000.00 25,668,000.00 23,993,311.21 48 27,873,311.21 48
SDN BHD
AL AMBIA SDN
2/10 2 22,210,895.91 - - -
BHD - -
6
Fixed Completion Open Completion Period
Period
JALLCON SDN
10/10 6 23,980,000.00 25,880.000.00
BHD
7
Arithmetical checks were carried out on all tenders. Errors were found in all the
tenders. The errors were due to mistakes in multiplying, addition and transfer. The
errors subsequently change the tenderer’s position. The tenders, the corrected tender
sum and their revised position are depicted below.
8
Original Tender Corrected Arithmetical Check
Original Remarks
Code Tenderer Sum Tender Sum Revised
Position
( RM ) ( RM ) Position
Error (RM) %
AIMA
1/10 CONSTRUCTION 27,574,685.30 9 27,577,301.02 +2,615.72 +0.0095 9
SDN. BHD
BUMIMETRO Arithmetical
9/10 CONSTRUCTION 29,190,073.80 10 30,314,446.63 +1,124,372.83 +3.8519 10 Error –
SDN BHD General
Summary
The Tendered Sum shall be the basis of acceptance of tender and not the Corrected
Total. Any error found, shall be rationalized prior to signing of Contract.
9
6.0 ANALYSIS AND EVALUATION OF TENDERS
6.1 Tender documents duly filled in and a formal offer made (Sufficiency of
Tenders submitted).
6.3 Pricing all sections of the tender documents and Bills of Quantities.
All tender documents are checked to ensure that tenderers had made valid
and proper offers. A full checklist/analysis is given in the following appendices:
The tenderer made a valid and proper offer and complied with all major tender
requirements. The tenderer submitted a complete tender.
The Tenderer submitted the lowest offer and the arithmetical error are found
but the error does not affect the contractor’s ranking. The tenderer’s overall
offer is within the acceptable margin of +/- 10%, i.e. 9.05% higher than the
QS estimate.
11
Tenderer Difference Percentage
Description Qs Estimate
(RM) with estimate Difference %
Building
Works
External
Works Within 131,267.00 135,996.40 -4,699.40 -3.46
Lot Boundary
Mechanical &
Electrical 1,000,469.00 2,272,000.00 -1,271,531.00 -55.97
Works
Prime Cost
Sum & 818,000.00 800,000.00 +18,000.00 +2.25
Provisional
Sum
12
7.0 COMMENTS ON THE SUBMISSION (CONT’D)
The pricing for Preliminaries is higher i.e. 20.57% higher than the QS
estimate. The preliminaries price at RM 1,109,305.11 or 5.60% of the tender
sum is considered acceptable.
The overall cost for building works is higher, i.e. Type A (+18.63%) and Type
B (+18.47%) higher than the QS estimate.
The cost per m2 GFA for typical unit (intermediate unit) is RM80.67 is higher
than the QS estimate which is RM67.95.
The following rates are considered high that caused the major difference
between the tenderer and the QS estimate :-
The rates/pricing for Infrastructure Works is higher, i.e. 28.45% higher than
the QS estimate.
The rates/pricing for External Telephone Infra and Street Lighting Service
- 5.50% lower than the Engineer estimate.
The pricing for Mechanical and Electrical works is higher, i.e -55.97% lower
than the Engineer estimate.
13
7.2 Tenderer 2/10 – AL AMBIA SDN. BHD.
Corrected
Tender Sum Original Revised
Tender Sum Error
(RM) Position Position
(RM)
The tenderer made a valid and proper offer and complied with all major tender
requirements.
The tenderer submitted the second lowest offer with the arithmetical error of
+RM816, 248.97, mainly due to wrong M&E transfer. Their corrected tender
amount is actually higher at RM 23,027,144.88 but the error does not change
the tenderer’s ranking. The tenderer’s overall offer i.e. 11.17% higher than
the QS estimate.
14
Tenderer Difference Percentage
Description Qs Estimate
(RM) with estimate Difference %
Building
Works
External
Works Within 153,909.30 135,996.40 +17,912.90 +13.17
Lot Boundary
Mechanical &
Electrical 626,362.00 2,272,000.00 -1,645,638.00 -72.43
Works
Lighting and
Telephone 432,475.80 360,650.02 +71,825.78 +19.92
Infrastructure
Prime Cost
Sum &
Provisional 824,000.00 800,000.00 +24,000.00 +3.00
Sum
15
7.0 COMMENTS ON THE SUBMISSION (CONT’D)
The pricing for Preliminaries is generally lower i.e. 10.18% higher than the
QS estimate. The preliminaries price at RM 1,013,644.00 or 4.98% of the
tender sum is considered acceptable.
The total cost for building works is higher, i.e. Type A (+15.11%) and Type B
(+15.06%) higher than the QS estimate.
The following rates are considered high that caused the major difference
between the tenderer and the QS estimate :-
Difference
Rate (RM) Amount (RM) Total Amount (RM)
Item Qty Unit with QS
(RM)
QS Tenderer QS Tenderer QS Tenderer
Fwk to
sides of 188 8.00/m 17.00/m 1,504.00 3,196.00 71 106,784.00 226,916.00 120,132.00
slab
Half slab 80 75.00/m² 88.80/m² 6,000.00 7,105.00 71 426,000.00 504,384.00 78,384.00
100mm
16 5.00/m 16.90/m 80.00 270.40 71 5,680.00 19,198.40 12,518.40
skirting
175mm
23 9.00/m 28.80/m 32.80 276.00 71 14,697.00 47,030.40 32,333.40
riser
Nosing 23 5.00/m 26.10/m 115.00 600.30 71 8,165.00 42,621.30 34,456.30
Half bwl 102 28.00/m² 41.20/m² 2,856.00 4,202.20 71 202,776.00 298,370.40 95,594.40
Acotec wall 190 55.00/m² 70.10/m² 10,450.00 13,319.00 71 741,950.00 945,649.00 203,699.00
16
7.0 COMMENTS ON THE SUBMISSION (CONT’D)
400mm x
400mm 78 47.00/m² 80.10/m² 3,666.00 6,247.80 71 260,286.00 443,593.80 183,307.80
tiles
Pegola 4 120.00/no 1,062.60/no 480.00 4,250.40 71 34,080.00 301,778.40 267,698.40
The cost per m2 GFA for typical unit (intermediate unit) is RM78.03 is higher
than the QS estimate which is RM67.95.
The rates/pricing for Infrastructure Works are higher, i.e. 65.33% higher than
the QS estimate.
The rates/pricing for External Telephone Infra and Street Lighting Service
19.92% higher than the Engineer estimate.
The pricing for Mechanical and Electrical works is very high, i.e -72.43% lower
than the Engineer Estimate some arithmetical error during transfer to general
summary.
17
7.3 Tenderer 7/10 – GLOBAL GLOBE SDN. BHD.
Corrected
Tender Sum Original Revised
Tender Sum Error
(RM) Position Position
(RM)
The tenderer made a valid and proper offer and complied with all major tender
requirements.
The tenderer’s overall offer is i.e. 13.12% higher than the QS estimate which
is 3rd lowest tenderer. There is an error of +RM772,968.00 or +3.4199%
mainly due to wrong M&E transfer. The error when corrected changed the
contractor’s ranking from 3rd to 4th.
18
7.0 COMMENTS ON THE SUBMISSION (CONT’D)
Building
Works
External
Works Within 270,990.50 135,996.40 +134,994.10 +99.26
Lot Boundary
Mechanical &
Electrical 560,190.00 2,272,000.00 -1,711,810.00 -75.34
Works
Lighting and
Telephone 393,061.00 360,650.02 +32,410.98 +8.99
Infrastructure
Prime Cost
Sum &
Provisional 806,000.00 800,000.00 +6,000.00 +0.75
Sum
The pricing for Preliminaries is generally lower i.e. -31.52% lower than the QS
estimate. The preliminaries price at RM 630,000.00 or 2.98% of the tender
sum is considered low.
The total building works is i.e. Type A (22.65%) and Type B (22.74%) higher
than the QS estimate
The following rates are considered high that caused the major difference
between the tenderer and the QS estimate :-
Half bwl 102 28.00/m² 36.00/m² 2,856.00 3,672.00 71 202,776.00 298,370.40 95,594.40
Acotec wall 190 55.00/m² 70.10/m² 10,450.00 13,319.00 71 741,950.00 945,649.00 203,699.00
20
7.0 COMMENTS ON THE SUBMISSION (CONT’D)
Broom
34 5.00/m² 45.00/m² 170.00 1,540.00 71 12.070.00 108,630.00 96,560.00
finish
Pebble
8 40.00/m² 150.00/m² 320.00 1,200.00 71 22,720.00 85,200.00 62,480.00
wash
Gate 1 1,000.00/no 2,000.00/no 1,000.00 2,000.00 71 71,000.00 142,000.00 71,000.00
21
7.0 COMMENTS ON THE SUBMISSION (CONT’D)
The cost per m2 GFA GFA for typical unit (intermediate unit) is RM83.73 is
higher than the QS estimate which is RM67.95.
The rates/pricing for Infrastructure Works are higher, i.e. 53.72% higher than
the QS estimate.
The rates/pricing for External Telephone Infra and Street Lighting Service
8.99% higher than the Engineer estimate.
The pricing for Mechanical and Electrical works is lower, i.e -75.34% lower
than Engineer Estimate and some arithmetical error during transfer to general
summary.
Corrected
Tender Sum Original Revised
Tender Sum Error
(RM) Position Position
(RM)
The tenderer made a valid and proper offer and complied with all major tender
requirements.
The tenderer’s overall offer is i.e. 19.22% higher than the QS estimate.
There is an error of +RM1,155.80 or +0.0049% mainly due to amount transfer
to summary. The error when corrected changed the contractor’s ranking from
4th to 5th.
22
Tenderer Difference Percentage
Description Qs Estimate
(RM) with estimate Difference %
Building
Works
External
Works Within 185,862.90 135,996.40 +49,866.50 +36.67
Lot Boundary
Mechanical &
Electrical 1,205,221.00 2,272,000.00 -1,066,779.00 -46.95
Works
Prime Cost
Sum & 824,000.00 800,000.00 +24,000.00 +3.00
Provisional
Sum
23
7.0 COMMENTS ON THE SUBMISSION (CONT’D)
The pricing for Preliminaries is generally higher i.e. 152.23% higher than the
QS estimate. The preliminaries price at RM 2,320,502.10 or 11.22% of the
tender sum is considered high.
The total building works is i.e. Type A (17.78%) and Type B (17.70%) higher
than the QS estimate
The following rates are considered high that caused the major difference
between the tenderer and the QS estimate :-
Half bwl 102 28.00/m² 43.00/m² 2,856.00 4,386.00 71 202,776.00 311,406.00 108,630.00
900mm
83 350.00/m 695.00/m 29,050.00 57,685.00 - - - 28,635.00
wide drain
750mm
23 290.00/m 650.00/m 6,670.00 14,950.00 - - - 8,280.00
wide ditto
600mm
195 230.00/m 570.00/m 44,620.00 110,580.00 - - - 65,960.00
wide ditto
450mm
53 175.00/m 583.00/m 9,275.00 30,899.00 - - - 21,624.00
wide ditto
Ditto, exc
222 140.00/m 514.00/m 31,080.00 114,108.00 - - - 83,028.00
1.5m
Precast
1,344 120.00/m 448.00/m 161,280.00 602,112.00 - - - 440,832.00
block drain
DIsposal 11,961 5.00/m³ 20.00/m³ 58,131.00 239,220.00 - - - 179,415.00
The cost per m2 GFA GFA for typical unit (intermediate unit) is RM79.84 is
higher than the QS estimate which is RM67.95.
The rates/pricing for Infrastructure Works are higher, i.e. 43.06% higher than
the QS estimate.
The rates/pricing for External Telephone Infra and Street Lighting Service
22.79% higher than the Engineer estimate.
The pricing for Mechanical and Electrical works is lower, i.e -46.95% lower
than Engineer Estimate.
Corrected
Tender Sum Original Revised
Tender Sum Error
(RM) Position Position
(RM)
The tenderer made a valid and proper offer and complied with all major tender
requirements.
The tenderer’s overall offer is i.e. 19.43% higher than the QS estimate.
26
Tenderer Difference Percentage
Description Qs Estimate
(RM) with estimate Difference %
Building
Works
External
Works Within 173,514.46 135,996.40 +37,518.06 +27.59
Lot Boundary
Mechanical &
Electrical 1,243,540.11 2,272,000.00 -1,028,459.89 -45.27
Works
Prime Cost
Sum & 824,000.00 800,000.00 +18,000.00 +2.25
Provisional
Sum
27
7.0 COMMENTS ON THE SUBMISSION (CONT’D)
The pricing for Preliminaries is generally higher i.e. 41.30% higher than the
QS estimate. The preliminaries price at RM 1,300,000.00 or 5.99% of the
tender sum is considered acceptable.
The total building works is i.e. Type A (24.30%) and Type B (23.84%) higher
than the QS estimate
The following rates are considered high that caused the major difference
between the tenderer and the QS estimate :-
Half bwl 102 28.00/m² 40.73/m² 2,856.00 4,154.46 71 202,776.00 294,966.66 92,190.66
Precast
1,344 120.00/m 511.00/m 161,280.00 686,784.00 - - - 525,504.00
block drain
2100mm x
2100mm 1 2,600.00/no 3,741.40/no 2,600.00 3,741.40 - - - 1,141.40
bricksump
1950mm x
1950mm 6 2,300.00/no 3,482.20/no 13,800.00 20,893.20 - - - 7,093.20
ditto
1650mm x
1650mm 2 1,600.00/no 2,975.78/no 3,200.00 5,951.56 - - - 2,751.56
ditto
1500mm x
1500mm 3 1,100/no 1,880.29/no 3,300.00 5,640.87 - - - 2,340.87
ditto
Ditto exc
1.5m but n.e 29 1,300.00/no 2,734.86/no 37,700.00 79,310.94 - - - 41,610.94
3.0m
1200mm x
7 900.00/no 1,540.46/no 6,300.00 10,783.74 - - - 4,483.22
1200mm
750mm x
750mm 47 75.00/no 230.43/no 3,525,00 10,829.74 - - - 7,304.74
cover slab
600mm x
170 48.00/no 211.33/no 8.160.00 35,926.10 - - - 27,766.10
600mm ditto
450mm x
170 27.00/no 200.10/no 4,590.00 34,017.00 - - - 29,427.00
450mm ditto
29
7.0 COMMENTS ON THE SUBMISSION (CONT’D)
The cost per m2 GFA GFA for typical unit (intermediate unit) is RM84.03 is
higher than the QS estimate which is RM67.95.
The rates/pricing for Infrastructure Works are higher, i.e. 56.17% higher than
the QS estimate.
The rates/pricing for External Telephone Infra and Street Lighting Service
10.97% higher than the Engineer estimate.
31