Beruflich Dokumente
Kultur Dokumente
www.emeraldinsight.com/1463-7154.htm
BPMJ
17,1 Business process re-engineering
in healthcare management:
a case study
42
Massimo Bertolini
Dipartimento di Ingegneria Industriale, Università di Parma,
Parma, Italy, and
M. Bevilacqua, F.E. Ciarapica and G. Giacchetta
Dipartimento di Energetica, Università Politecnica delle Marche,
Ancona, Italy
Abstract
Purpose – The purpose of this paper is to carry out the business process re-engineering (BPR) of a
surgical ward in a hospital in order to improve the efficiency of the ward.
Design/methodology/approach – This work was developed using a case study on a surgical ward.
In this type of ward, in which scheduled and unscheduled operations often have to coexist and be
managed, ways to minimise patient inconvenience need to be studied. A framework based on
event-driven process chains (EPCs) methodology, the entity-relationship model and discrete event
simulation is presented to define and analyse the current state of a surgical ward and design a future
system. The modelling of the processes, activities and sub-activities, which took up a great amount of
ward resources, allowed a what-if analysis to be developed which simulates various scenarios and
assesses their performance.
Findings – Using Delphi methodology, it was possible to identify a number of areas for improvement:
number of operating sessions, preparation of the operating rooms for each operation, availability of
specific surgical instruments. Moreover, the discrete event simulation approach led to an understanding
of the most efficient management choices.
Originality/value – The decision to use Delphi methodology for the information collection stage
before starting the BPR process is not found in other studies in the literature. Moreover, the use of
models based on EPCs methodology allowed the panel of experts to develop models to examine and
understand the resource requirements of medical assessment units and to provide a framework or
develop standards that hospital developers and clinical managers can consult.
Keywords Business process re-engineering, Case studies, Hospitals, Modelling, Simulation
Paper type Research paper
1. Introduction
It can justifiably be said that healthcare has become an extremely complex sector. There
are an increasing number of medical specialisations and professions, complex therapies
and equipment and often several service units revolve around different organisations
(Øvretveit, 2000).
The tricky problem that has to be addressed is that of finding opportunities for
Business Process Management integration and coordination, while at the same time respecting the field of specialisation
Journal which is fundamental for creating and transferring knowledge, above all in contexts like
Vol. 17 No. 1, 2011
pp. 42-66 hospitals which are highly professional and technological.
q Emerald Group Publishing Limited This problem is not unlike the one faced in other industrial realities where in recent
1463-7154
DOI 10.1108/14637151111105571 years attention has been focused on management tools such as total quality
management (TQM), activity-based management and business process re-engineering Business
(BPR). Some of these tools have also occasionally been applied to the healthcare sector process
with often contradictory results.
One empirical study carried out by Lim et al. (1999) showed that 80 per cent of the re-engineering
hospitals in Singapore have adopted some aspects of quality management so as to
provide a service which is more oriented towards customer satisfaction. However,
another empirical study conducted by the same authors (Lim and Tang, 2000) 43
concerning the quality expected and perceived by the patients for the services offered by
the hospitals in Singapore showed that the quality of the services is generally less than
the level of quality which the patients expect. Moreover, 40 per cent of the patients
interviewed defined the quality of the service as insufficient or very bad.
In the USA in 1993, although more than 40 per cent of the hospitals involved in the
Joint Commission on Accreditation of Healthcare Organizations had adopted some
aspects of the quality improvement programme (Reeves and Bedner, 1993; Chaufournier
and St Andree, 1993), critics stated that the quality in most of these hospitals was less
than satisfactory (Nance, 1995).
There are several reasons for this lack of success. Geber (1992) underlined that
doctors are unwilling to accept change and that administrators have a short-term
outlook; Morrison and Heineke (1992) and Boerstler et al. (1996) have underlined that
there is resistance due to lack of motivation in doctors, nurses and other staff. Other
important factors are certainly the failure of healthcare providers to understand
customer requirements or simply that management quality practices have not been
correctly implemented.
Simulation models have been used extensively in literature to study healthcare
operations (Barnes and Quiason, 1997; Sanchez et al., 2000). According to Banks et al.
(2001), one of the main reasons that simulation is becoming a popular technique in
healthcare problem solving is because simulation may be used for dynamic (rather
than static) analysis of the situation, thus presenting stakeholders with a more realistic
picture of the situation.
A number of simulation models have been designed to manage the waiting list for
critical resources, including organs for transplant. Ratcliffe et al. (2001) describe the use
of simulation to model policies for allocating cadaveric livers to patients awaiting
transplants. Wujciak and Opelz (1993) present a study aimed at analysing policy options
for allocating cadaveric kidneys. Dexter and Traub (2002) use a simulation methodology
to suggest next case scheduling policies in operating rooms functioning in parallel with
flexible end times.
Simulation has been used extensively to model operations within surgical units to
improve efficiency and reduce wait times. Blake et al. (1991) describe a model simulating
the flow of surgical patients that was used to test the impact of a master surgical
schedule on inpatient nursing workload. Bowers and Mould (2004) describe a simulation
model to test the potential for increasing operating room utilisation by scheduling
deferrable elective patients into planned orthopaedics blocks.
Simulation has also been frequently applied in publicly financed healthcare systems
to analyse waiting lists for elective procedures. Everett (2002) develops a “what-if”
simulation as a decision support tool to allow managers to experiment with different
resource levels to determine their impact before implementation. Vasilakis and
BPMJ El-Darzi (2001) show that a lack of social services was to blame for a recurring winter
17,1 bed crisis in a British hospital.
Jun et al. (1999) have identified two main areas for the use of simulation, namely, the
management of patient flow and resource allocation. Lagergren (1998) adds to these by
identifying a number of areas for modelling (in general) in healthcare: epidemiology,
healthcare systems design, healthcare systems operation and medical decision making.
44 Although there has been an extensive amount of simulation applied to the healthcare
sector in recent years. Baldwin et al. (2004) use the literature and expert opinion to make
the claim that “the immense potential of simulation has not yet been realised in practice”.
Whilst analysing the expert opinion to understand why this is the case, they highlight
the need to mix modelling techniques more readily.
In this paper, a study conducted in the Neurosurgery Ward of Parma Hospital using
quality management and BPR techniques is reported. The aim in carrying out the
study was to indicate the most critical aspects in ward management processes and to
propose alternative solutions for improving the service offered to the patients.
A framework based on event-driven process chains (EPCs) methodology and discrete
event simulation is used to define and analyse the current state of the neurosurgery ward
and to design a future state of the ward focused on improving service quality and
workflow. The application of simulation in healthcare is not as widely perceived for
problem solving as it is in other application areas. This might be due to the way
simulation is applied in healthcare modelling, as it follows a traditionally based
engineering approach (Baldwin et al., 2004). This may not be a problem in itself; however,
healthcare systems are often complex, because they involve multiple decision makers
and thus understanding and communication between various stakeholders is potentially
problematic. Problem understanding and efficient means of communication can widely
contribute to the solution; consequently a Delphi technique approach is used in this
paper to enhance such understanding and communication. Using this methodology,
it was possible to identify a number of areas for improvement: number of operating
sessions, preparation of the operating rooms for each operation, availability of specific
surgical instruments and so on.
The reminder of the paper is organised as follows. In Section 2, a brief literature
review on the BPR and EPCs techniques is presented. Section 3 is divided into two parts:
the Section 3.1 describes the case study and the modelling of the processes and
sub-processes in the neurosurgery ward, while in Section 3.2 the simulation process is
reported. Section 4 describes the main critical areas in the ward processes using the
Delphi method and new scenarios are proposed and assessed.
Finally, conclusion section reports the main features encountered during the study.
Starting point
Definition of
objectives
Process
representation
Feedback (AS-IS)
Process
representation
(AS-IS)
Some activities which required significant ward resources were analysed in greater
detail. The division of the sub-processes allowed the development of a “what-if” study
which simulated various scenarios. The “management of elective patients” is a process
in which “elective” refers to the operation which can be scheduled and if necessary
postponed for a few days without endangering the life of the patient. The procedure for
this type of patient is characterised by putting the name on a waiting list which generally
happens after a period of observation. These patients arrive on the ward from various
places such as other hospitals or private clinics. The hospital waiting list is managed by
the hospital IT services (SIO). The process “management of surgical operations”
concerns the scheduled surgical activity of the ward, i.e. operations on elective patients.
Scheduling this type of operation starts with consultation of the waiting list. Having
selected the names these patients are contacted and are generally admitted to the ward
on the following day. On average there are about three/four scheduled surgical
operations every day. All “patient management processes” were modelled and analysed
although in this paper only the process “management of patients on arrival” is presented
(Section 3.1.1), in order to highlight the BPR method.
Patient
management
Management of patients
Management of patients Patient
needing further Management of
to be kept undergoes
clinical and emergencies
in observation surgical operation Figure 3.
laboratory investigation
Value-added chain
Level 2 Level 2 Level 2 Level 2
BPMJ 3.1.1 Patient management: management of patients on arrival. “Patients on arrival”
17,1 includes all those patients who are not admitted to hospital but who need neurosurgical
medical assessment. These patients are likely to arrive from accident and emergency
department (A&E) or from other wards and may later be admitted to the neurosurgery
ward. As can be seen in Figure 4, the neurosurgeon makes a preliminary assessment of
the patient’s clinical condition and, on the basis of the information derived from this
48 examination, may decide for one of the following types of action:
(1) patient to be kept in observation;
(2) patient needing further clinical and laboratory investigation;
(3) emergency; and
(4) patient to be re-directed.
(1) Management of patients to be kept in observation. After informing the patient of the
need to be kept in observation the hospitalisation procedure is started leading to
Patient
proposed
Level 1
Clinical
assessment
Patient needing
Patient
further Emergency Other destination
in observation
investigation
Management of patients
Management of Management of
needing
patients in observation emergencies
further
investigation
Figure 4. Patient
Level 1 – “management of discharged
patient on arrival”
admission of the patient to the ward. The period of observation generally leads to one of Business
three scenarios: neurological deterioration, stationary conditions or patient improvement. process
The first case, neurological deterioration, is a serious situation requiring emergency
radiological examination, on the basis of which a diagnosis will be formulated which may re-engineering
or may not involve surgery. A recommendation for surgery, subsequent to neurological
deterioration, determines the need to operate immediately. In fact, after examination by
the anaesthetist the surgical operation is carried out (Figure 5). The end of the operation is 49
the start of the post-operative stay in hospital, which ends when the patient is discharged
from the ward. On the contrary, when the diagnosis does not require surgery after
neurological deterioration, the patient will be kept in observation for the following period
in which three events may occur: further neurological deterioration, stationary conditions
or improvement of the clinical condition.
In the event of either a stationary situation or improvement in the patient’s clinical
condition during observation, after a further stay in the ward a diagnosis will be
formulated which may or may not recognise the need for the patient to undergo surgery.
If surgery is not needed the patient will be transferred or discharged and subsequently
leave the hospital. On the contrary, if surgery is recommended the patient is described as
“elective”, that is to say needs to be operated on not urgently but in the middle/long-term.
Elective patients may therefore be discharged or transferred, according to their clinical
conditions, and later leave the ward.
(2) Management of patients who need further investigation. As can be seen in
Figure 6, after informing the patient of the need to carry out further investigation, the
hospitalisation procedure starts. Having admitted the patient, the tests needed will be
requested and carried out. The subsequent findings may determine one of two different
situations: impossibility to formulate a diagnosis, leading to the need to carry out new
analyses or formulation of a diagnosis.
The formulation of a diagnosis may or may not indicate the need for surgery. We will
first examine the situation of diagnosis requiring surgery and then the case in which no
surgery is required. Subsequent to the diagnosis requiring surgery it is necessary to
decide whether to operate immediately or to wait. In the latter case, we have an elective
patient who can be discharged and leave the ward. On the contrary, if it is necessary to
operate immediately the pre-surgery process is set in motion and the operation is
performed. At the end of the operation, the post-operative hospitalisation starts, ending
when the patient leaves the ward. If the diagnosis does not recommend surgery, the
patient must be discharged, transferred to another ward or kept in the ward for a period
of observation. The first two possibilities involve activation of the respective procedures,
which end when the patient leaves the ward. On the contrary, the patient kept in
observation calls for the sub-process named “patient in observation”. In this case, the
path is exactly the same as the one followed for patients on arrival who are considered
patients to be kept in observation. “Patients kept in observation” and “management
of patients kept in observation” are two very similar sub-processes. In fact, the only
difference is that the former lacks the hospitalisation procedure (the patients who
activate this microprocess have in fact already been admitted to the ward).
(3) Management of emergencies. As can be seen in Figure 7, the first thing that happens
to a patient who is recognised as an emergency case is the formulation of the diagnosis
with recommendation for surgery and examination by the anaesthetist. At this stage,
the hospitalisation procedure is activated in parallel with preparation for surgery. In fact,
BPMJ Patient needing
17,1 observation
Level 2
Communication to
patient need
for periodof
observation
Hospitalisation
50 decision
Nurse
Bed
Hospitalisation SIO
procedure
Doctor Clinical
record
Patient
hospitalised
Clinical
observation
of patients
Radiological
examination
Hospitalisation
continues
No No
Surgical Elective
surgical surgical
recommendation patient
recommendation recommendation
Examination by
anaesthetist
Start preparation
for operation Decision-making
Surgical instrument process
technician
Nurse
Operating Surgical
roon operation
Doctor
Patient can be Patient to be
Anaesthetist discharged tranferred
Patient
Discharge
End of Death of Doctor Doctor transferred to
procedure
operation patient other ward SIO
Bed
Figure 5.
Level 2 – “management of Patient
patients in observation” leaves ward
Patient
needs
Business
further
investigation
Level 2
process
Communicate to
patient need
for further
re-engineering
investigation
Hospitalisation
decision
Nurse
Hospitalisation SIO
51
Bed
procedure
Doctor Clinical
record
Patient
hospitalised
Request for
analysis
Analysis
planned
Analysis
developed
Analysis
completed
Results of
analysis
Possibility to
Need for further
make
analysis
diagnosis
Diagnosis
made
Surgical No
recommendation surgical
recommendation
Decision
Decision-making
hoperate
process
immediately
Surgical instrument
technician
Surgical Decision-making
Doctor process Patient transferred
operation Discharge Patient in
to other
procedure observation
ward
Anaesthetist
Patient can
be discharged
Level 3
Doctor SIO
Doctor
Bed
End of Death of
Discharge
operation patient
procedure
SIO
Post-operative Bed
Death
hospitalisation Bed procedure Bed
SIO
Figure 6.
Level 2 – management of
Patient leaves patient who need further
ward
investigation
BPMJ
17,1 Emergency
Level 2
Surgical
recommendation
52
Patient to be
operated
Examination by
anaesthetist
Doctor
SIO Doctor
Patient Clinical
Anaesthetist End of
hospitalised record operation
End of Death of
operation patient
Post-operative
Death
hospitalisation Bed
Bed procedure
There are many procedures suggested in literature for constructing a point estimate
and a confidence interval (CI) for the steady-state mean v ¼ E(Y) of a simulation output
process Y1, Y2 . . . , for instance Meketon and Schmeiser (1984) introduced the method
of overlapping batch means, Bischak (1988) studied the idea of weighted batch means,
Fishman (1978) developed the autoregressive method.
In this work was proposed a replication/deletion approach. This method is based on n
independent replication of length m observations. This method tends to suffer from bias
in the point estimator v^ , while the other approaches are based on one long replication, and
tend to have a problem with bias in the estimator Varðv^ Þ of the variance of the point
estimator v^ .
Initially, there was a simulation start-up phase. To calculate this period of time, also
known as “warm-up” the method proposed by Welch (1983) was applied. This phase
allows the model to reach a steady state. A warm-up period of l ¼ 25 days was chosen
on the basis of Figure 8.
In order to analyse steady-state performance from the output of the simulation the
replication/deletion approach (Law and Kelton, 1991) was used. The method was
BPMJ 4
17,1
applied for obtaining a point estimate and CI for the steady-state mean v ¼ E(Y).
Only those observations beyond the warm-up period l ¼ 25 in each replication are used
to form estimates; n ¼ 10 replications of the simulation were carried out each of length
m ¼ 365 days. Let Yji be the number of surgical operations per day (elective and
emergency operations) carried out and let Xj be given by:
Pm
Y ji
X j ¼ i¼lþ1 for j ¼ 1; 2; . . . ; n
ðm 2 l Þ
Xj are independent and identically distributed random variables with E(Xj) < v, and
an approximate 100(1-a) per cent CI for v is given by[1]:
rffiffiffiffiffiffiffiffiffiffiffi
S 2 ðnÞ
XðnÞ ^ tn21;12a=2 1
n
With a 95 per cent CI, we obtained v ¼ Xð10Þ ¼ 3:246 and:
rffiffiffiffiffiffiffiffiffi
0:21
Xð10Þ ^ t9;0:975 ¼ 3:246 ^ 0:328
10
this is an acceptable precision because is about 10 per cent of the steady-state mean.
The initial n runs of m observations were used both to determine l and to construct a
CI; in this case because m is much larger than l the observations beyond the warm-up
period l do not contain significant bias relative to v.
For the validation of the model, so as to verify the ability to reproduce with
reasonable precision the real trend in the ward activities, the main variable chosen was
the number of surgical operations per day carried out.
In order to validate the simulation model the output of the simulation has been
compared with the historical data (of the same year) collected from neurosurgery ward.
For the days between l and m the difference between real value of operations (Xi) and
predicted value of operations (Yi)[2] has been assessed; then were calculated the mean
absolute deviation (MAD), mean absolute percentage error (MAPE), BIAS, tracking
signal (TS) and correlation coefficient (R) values. In this work, the formulae used to
assess the accuracy of the simulation are shown in Appendix 2. Table I shows the results
of the simulation concerning “elective operations” and “emergency operations”.
The MAD values indicate that the average error in the simulation model developed is Business
between 0.72 and 0.21 for the “elective operations” and “emergency operations”, process
respectively. Moreover, the MAPE values indicate that, in terms of percentages of real
values, this error is of about 18.53 and 19.08 per cent. The bias value fluctuates around 0 re-engineering
and therefore the error is truly random and not biased one way or the other. The tracking
signal value for any period is not outside the range ^ 3, indicating that the simulation
result is not biased and is neither underforecasting (TS below 2 3) nor overforecasting 55
(TS above þ 3). All the performance indices show that simulation output is in agreement
with the number of operations carried out in the neurosurgery ward.
The processes analysed bring to light some fundamental constraints and
considerable complexity. The limited number both of people involved in the processes
and of spaces/plants used during the procedures, in fact make the system extremely
critical. The simulations have shown for example that the anaesthetists are the most
critical point. The complexity is connected with the intricacy which is normal in hospital
ward management procedures and with the division into macroprocesses of some basic
sub-processes such as: admission procedure, discharge procedure, surgical operation
and post-operative hospitalisation.
4. Delphi methodology
The approach proposed in this work has tried to take into account the real problems of a
surgical ward, considering problems connected with the availability of human
resources, space, plants and finances. An ad hoc panel of experts was created in order to
encourage communication and meetings during which the members could contribute
their knowledge and information about the processes. The panel was made up of seven
participants, and included two academics, whose research studies are mainly focused on
BPR, one head physician, two doctors, one nurse and one representative from Health
Authority Administration. This number of participants, which at first sight may seem
rather large, derives from the Delphi technique (Linstone and Turoff, 1975) adopted for
working with panels. The Delphi technique is a structured process which investigates a
complex or ill-defined issue by means of a panel of experts. This methodology proves to
be an appropriate design for this type of research and permits individual opinions to be
obtained within a structured group and using a communicative process. The panel
worked for a period of about two weeks, and the sessions were planned on a three-round
Delphi process. At first a series of statements concerning the requirements of ward
processes was generated individually and anonymously by the experts. The panel was
involved in developing models for the activities of the neurosurgery ward and in defining
the critical points in the processes and possible “what-if” scenarios. All the statements
were then collected and delivered to the members of the panel, who were required to
indicate their level of agreement; answers were finally fed back to the panel.
The study carried out allowed the identification of so-called “bottlenecks”. The critical
aspects which came to light are indicated in Table II:
Number of operating sessions This number may not be sufficient if compared with the
real number of patients who have to undergo surgery.
This is connected with: availability of the operating
rooms (technical or electrical failures or problems
56 involving the equipment used slow down or make the
use of the operating room impossible on that day);
presence of sufficient medical, nursing or auxiliary staff
to meet requirements; time for carrying out the single
operations (in fact it must be remembered that some
neurosurgical operations last for a long time and that,
when scheduled, occupy the operating room for the
whole session on that day, thereby increasing the
waiting list time for other patients)
Preparation of the operating rooms for each Each surgical operation, whether simple and short or
operation complex, requires a clean working environment which
is comfortable for the patient and above all for the staff
that work there. It must also be equipped with
everything needed at each stage of the operation. These
stages require the presence and cooperation of an
adequate number of people and the use of special
equipment. If the number of people is not sufficient or if
there are failures the time needed becomes even longer,
thereby delaying the start of the following session
Availability of special surgical instruments In order to carry out some types of surgical operation
specific surgical instruments as well as the basic
provisions may be necessary. These must therefore be
ordered by the staff in charge, delivered and finally
tested by the Health Physics Department. In fact,
authorisation is needed before this equipment can be
used. This contributes to making the operation waiting
time longer
Availability of beds in intensive care Before starting a surgical operation which, because of
its own complexity or because of the clinical condition
of the patient, requires post-operative hospitalisation in
intensive care, the medical staff (surgeon and
anaesthetist) must consult the staff of the intensive care
unit and make sure that there is a bed available on the
day of the operation. Because of the limited resources
and beds available in intensive care (ten in the
reanimation room and six in post-operative intensive
care), as well as the unpredictability of emergencies
(traumatology, cardiac and pulmonary emergencies),
an operating session is likely to be changed or even
postponed because of a lack of adequate post-operative
monitoring. All this contributes to slowing down the
scheduled operations. During the simulations carried
out, 12 per cent of the total number of people contacted
in a year were discharged and then contacted again
because of the lack of a bed available in the reanimation
Table II. room
Delphi analysis (continued)
Bottlenecks Description
Business
process
Transfer of treated patients to other wards After having received neurosurgical treatment a patient
or hospitals may be transferred to another ward or hospital to
re-engineering
continue and complete the hospitalisation. However, if
the final destination ward has no beds available the
transfer is delayed for an indefinite period of time. This
situation naturally means a protracted stay in the
57
neurosurgery ward for patients who no longer need
specific neurosurgical treatment but continue to occupy
beds which could have been used for new patients. The
simulation carried out showed that a patient waits for a
bed in another ward for two days, 22 hours. This aspect
has a considerable influence on the efficiency of the
ward, since, because the coordination between wards is
not perfect, it limits a priori the possibility to admit
patients who are waiting to be operated
Unpredictable surgical complications These lead to protracted hospitalisation
Waiting time for check ups and further Analyses carried out for check ups or further
investigations investigations which must be carried out have both
planning and execution times. These waiting times
often become longer, above all because of a lack of
machinery or staff
Physiatric assessment for post-operative The physiatric assessment is unlikely to be carried out
rehabilitation at the time it is requested. In fact the neurosurgeon who
decides that the patient needs a physiatric assessment
will usually have to forward a written request to the
Physiatry Service. On average this type of request is
satisfied within a few days. The above described
procedure leads to a waiting time for the patient and a
protracted stay in the hospital
Unpredictability of emergencies The unexpected arrival of an emergency may lead to
delays in the treatment of elective patients. This is due
to the fact that a surgical emergency immediately
occupies one of the two operating rooms available for
this ward, thereby postponing the operating sessions
scheduled for that day. Postponed operating sessions
cannot always be made up the same day, and therefore
generate further delays. One immediate visible effect of
this is that the waiting list of patients due to be operated
on becomes longer. For this reason the simulation tried
to calculate the overall delay time deriving from the
various scheduled elective operations. During the year
of simulation the following results were obtained for
delay time of elective patients: 17 days, 2 hours, 43
minutes Table II.
Several simulation runs were carried out for each of the proposed scenarios recording the
increase of predicted operations in the year between To-Be and As-Is situations.
The uncertainty was calculated using statistical inference. Standard deviation and a
95 per cent CI was computed for the difference between the operations with new scenario
and operations with the As-Is situations. The results are summarised in Table III.
The values of standard deviation and CIs show a low uncertainty in results.
It is possible to make a general analysis of the results since the observations are
similar for the different cases. The simulation brings to light the fact that it is impossible
to obtain a real benefit by acting only on one single aspect. In general, it was possible to
obtain an increase in the total number of operations which varies on average from 3 to
23.9 per cent. There are many factors which justify a result of this type. The situation
examined, the hospital ward, is an extremely complex system, characterised by
variables which are largely correlated to each other and therefore in no way can be
examined considering each aspect as a single element isolated from the others. To clarify
this statement, the single scenarios are discussed below, highlighting the correlations
which exist between the various aspects:
In general, it can be stated that the combination of different scenarios improves the
situation although the benefits are fewer than the sum of the increases in the number of
operations for the single scenarios. This happens since there is overlapping of the
benefits deriving from different scenarios.
Notes Pn Pn
2
Xi X i 2 XðnÞ
1. XðnÞ ¼ i¼1 ; S 2 ðnÞ ¼ i¼1
Pn n n21
j¼1 Y ji
2. Y i ¼ for i ¼ l; . . . ; m
n
3. At the moment the Italian laws provide for freeze of new appointments in the public sector. Business
4. The anaesthetists are in Anaesthesia and Resuscitation Operative Unit and their shifts process
concern, by turns, all hospital surgery wards.
re-engineering
References
Al-Mashari, M. and Zairi, M. (1999), “BPR implementation process: an analysis of key success
and failure factors”, Business Process Management Journal, Vol. 5 No. 1, pp. 87-112. 63
Baldwin, L.P., Eldabi, T. and Paul, R.J. (2004), “Simulation in healthcare management: a soft
approach (MAPIU)”, Simulation Modelling Practice and Theory, Vol. 12, pp. 541-57.
Banks, J., Carson, J.S. and Nelson, B.L. (2001), Discrete-event System Simulation, 3rd ed.,
Prentice-Hall, Upper Saddle River, NJ.
Barjis, J. (2008), “The importance of business process modelling in software system design”,
Science of Computer Programming, Vol. 71, pp. 73-87.
Barjis, J. (2009), “Collaborative, participative and interactive enterprise modeling”, LNBIP,
Vol. 24, pp. 651-62.
Barnes, C.D. and Quiason, J.L. (1997), Success Stories in Simulation in Health Care. WSC _97,
Association for Computing Machinery, New York, NY, pp. 1280-5.
Bischak, D.P. (1988), “Weighted batch means for improved confidence intervals for steady-state
process”, PhD dissertation, Department of Industrial and Operation Engineering,
University of Michigan, Ann Arbor, MI.
Blake, J.T., Carter, M.W., O’Brien-Pallas, L.L. and McGillis-Hall, L. (1991), “A surgical process
management tool”, in Greenes, R. (Ed.), 8th World Congress on Medical Informatics,
International Medical Informatics Association, Vancouver, BC.
Boerstler, H., Foster, R.W., O’Connor, E.J., O’Brien, J.L., Shortell, S.M., Carman, J.M. and Huges, E.F.X.
(1996), “Implementation of quality management conventional wisdom versus reality”,
Hospital & Health Services Administration, Vol. 41, pp. 143-59.
Bowers, J. and Mould, G. (2004), “Managing uncertainty in orthopaedic trauma theatres”,
European Journal of Operational Research, Vol. 154 No. 3, pp. 599-608.
Chaufournier, R.L. and St Andree, C. (1993), “Total quality management in an academic health
centre”, Quality Progress, Vol. 26 No. 4, pp. 63-6.
Davenport, T.H. (1993), Process Innovation: Reengineering Work through Information
Technology, Harvard Business School Press, Boston, MA.
Davenport, T.H. and Beer, M. (1995), “Managing information about process”, Journal of
Management Information Systems, Vol. 12 No. 1, pp. 57-80.
Davenport, T.H. and Short, J.E. (1990), “The new industrial engineering: information technology
and business process redesign”, Sloan Management Review, Vol. 31 No. 4, pp. 11-17.
Dexter, F. and Traub, R.D. (2002), “How to schedule elective surgical cases into specific operating
rooms to maximize the efficiency of use of operating room time”, Anesth Analg, Vol. 94
No. 4, pp. 933-42.
El Sawy, O.A. (2001), Redesigning Enterprise Processes for e-Business, McGraw-Hill, Boston, MA.
Everett, J.E. (2002), “A decision support simulation model for the management of an elective
surgery waiting system”, Health Care Manage Science, Vol. 5 No. 2, pp. 89-95.
Fishman, G.S. (1978), Principles of Discrete Event Simulation, Wiley, New York, NY.
Geber, B. (1992), “Can TQM cure health care?”, Training, Vol. 29 No. 8, pp. 25-34.
Hammer, M. (1990), “Reenginering work: don’t automate, obliterate”, Harvard Business Review,
Vol. 68 No. 4, pp. 104-12.
BPMJ Jun, J.B., Jacobsonand, S.H. and Swisher, J.R. (1999), “Application of discrete-event simulation in
health care and clinics: a survey”, Journal of the Operational Research Society, Vol. 50,
17,1 pp. 109-23.
Lagergren, M. (1998), “What is the role and contribution of models to management and research
in the health services? A view from Europe”, European Journal of Operational Research,
Vol. 105, pp. 257-66.
64 Law, A.W. and Kelton, W.D. (1991), Simulation Modelling & Analysis, McGraw-Hill, Boston, MA.
Lim, P.C. and Tang, N.K.H. (2000), “The development of a model for total quality healthcare”,
Managing Service Quality, Vol. 10 No. 2, pp. 103-11.
Lim, P.C., Tang, N.K.H. and Jackson, P.M. (1999), “An innovative framework for health care
performance measurement”, Managing Service Quality, Vol. 9 No. 6, pp. 423-33.
Linstone, H.A. and Turoff, M. (1975), The Delphi Method Techniques and Application,
Addison-Wesley, London.
Meketon, M.S. and Schmeiser, B.W. (1984), “Overlapping batch means: something for nothing?”,
Proceedings of the 1984 Winter Simulation Conference, Dallas, pp. 227-30.
Morrison, P.E. and Heineke, H. (1992), “Why do health care practitioners resist quality
management?”, Quality Progress, Vol. 25 No. 4, pp. 51-5.
Nance, J.L. (1995), Managed Care: The New Paradigm, Plenum, New York, NY.
Øvretveit, J. (2000), “Total quality management in European healthcare”, International Journal of
Health Care Quality Assurance, Vol. 13 No. 2, pp. 74-9.
Persson, A. (2001), “Enterprise modelling in practice: situational factors and their influence on
adopting a participative approach”, PhD dissertation, Stockholm University, Stockholm.
Ratcliffe, J., Young, T., Buxton, M., Eldabi, T., Paul, R., Burroughs, A., Papatheodoridis, G. and
Rolles, K. (2001), “A simulation modelling approach to evaluating alternative policies for
the management of the waiting list for liver transplantation”, Health Care Manage Science,
Vol. 4 No. 2, pp. 117-24.
Reeves, C.A. and Bedner, D.A. (1993), “What prevents TQM implementation in healthcare
organisations”, Quality Progress, Vol. 26 No. 4, p. 41.
Sanchez, S.M., Ferrin, D.M., Ogazon, T., Sepulveda, J.A. and Ward, T.J. (2000), “Emerging issues
in healthcare simulation”, Proceedings of the WSC _00, Association of Computing
Machinery, New York, NY, pp. 1999-2003.
Stirna, J., Persson, A. and Sandkuhl, K. (2007), “Participative enterprise modeling: experiences
and recommendations”, in Krogstie, J., Opdahl, A.L. and Sindre, G. (Eds), CAiSE 2007 and
WES 2007. LNCS, Vol. 4495, Springer, Heidelberg, pp. 546-60.
Tumay, K. (1995), “Business process simulation”, Proceedings of the 1995 Winter Simulation
Conference, Washington, DC, pp. 55-60.
van Dongen, B.F., van der Aalst, W.M.P. and Verbeek, H.M.W. (2005), “Verification of EPCs: using
reduction rules and Petri nets”, Proceedings of the 17th Conference on Advanced Information
Systems Engineering, Porto (in this Source the Authors Reveals Flaws in EPC Models).
Vasilakis, C. and El-Darzi, E. (2001), “A simulation study of the winter bed crisis”, Health Care
Manage Science, Vol. 1 No. 2, pp. 143-9.
Welch, P.D. (1983), “The statistical analysis of simulation results”, in Lavenberg, S.S. (Ed.),
The Computer Performance Modelling Handbook, Academic Press, New York, NY,
pp. 268-328.
Wujciak, T. and Opelz, G. (1993), “Computer analysis of cadaver kidney allocation procedures”,
Transplantation, Vol. 55 No. 3, pp. 516-21.
Further reading Business
Keller, G., Nuttgens, M. and Scheer, A.W. (1992), “Semantische Processmodellierung auf der process
Grundlage Ereignisgesteuerter Processketten (EPK)”, Veroffentlichungen des Instituts fur
Wirtschaftsinformatik, Heft 89, University of Saarland, Saarbrucken, in German. re-engineering
Kelton, W.D. and Law, A.W. (1983), “A new approach for dealing with the start-up problem in
discrete event simulation”, Naval Research Logistics Quarterly, Vol. 30, pp. 641-58.
65
Appendix 1
The EPC is a dynamic model which connects the static resources of the system (systems, data,
organisation, etc.) and organises them so as to arrive at a sequence of activities or tasks
(the process) which create value for the company.
An EPC shows the chronological sequence of the company processes, in the shape of chains of
events or functions. An event activates a function which in turn creates one or more new events.
Each function is therefore characterised by an initial event and a final event which, respectively,
correspond with the input and output of the function itself.
By event we refer to an important change in state in the company process. It may consist in an
external change which gives rise to the process (for example, the receipt of an order from a client),
an internal change (for example, the production of a specific type of goods), or the final output of the
process which has external effects (for example, the order delivered to the consumer).
Unlike the functions, which need a certain amount of execution time, the events are connected
with a specific moment in time.
In reality, the processes are often not simple chains of events and functions which alternate in
sequence, but may in fact be alternative paths followed in order to perform a company task.
The decisions which change the flow of the process are always made on the basis of the
functions, but to represent the possible results and the various events that may lead to the
execution of a function it is necessary to introduce some rules.
There are three basic logical operators which have slightly different uses according to
whether they follow or precede the functions, as described in Table AI.
It is also possible to add to the process model, as a chain of events and functions, a set of
information, generally called resources, which concerns: the organisation; the application
systems; the data; the know-how; the information providers; the products; the aims and the
measures; and the general resources. For example, considering the function develop the order it
OR Decision OR Start OR
One or more paths may be followed as a Each Event, or combination of Events, will
result of the decision give rise to the Function
The tracking signal (TS) is the ratio of the bias and the MAD and is given as follows:
BIAS
TS ¼ :
MAD
Finally, the correlation coefficient (R) is calculated as:
P
ð1=ðm 2 l ÞÞ m2l i¼1 ð yi 2 y Þ · ðxi 2 x Þ
R ¼ rffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffi
P r ffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffi
P ;
m2l 2 m2l 2
i¼1 ðxi 2 x Þ =m 2 l · i¼1 ð yi 2 y Þ =m 2 l
1 X m2l
1 X m2l
for x ¼ jxi j and y ¼ j yi j
m 2 l i¼1 m 2 l i¼1
Corresponding author
M. Bevilacqua can be contacted at: m.bevilacqua@univpm.it