Beruflich Dokumente
Kultur Dokumente
DEWAN BAIDURI
WISMA SUMBER AIR
KEMENTERIAN SUMBER ASLI DAN ALAM SEKITAR
PUTRAJAYA
PRESENTED BY
TN. HJ. HIDZRAMI BIN HJ. SHAMSUL ANWAR
DISTRICT ENGINEER
DEPARTMENT OF IRRIGATION AND DRAINAGE, KERIAN
Bukit Merah Lake Brief
22 -23rd Febuary 2010 NRE Putrajaya
DID, KERIAN
CONTENT OF PRESENTATION
1. INTRODUCTION
2. DESCRIPTION OF THE LAKE
3. MANAGEMENT OF THE LAKE AND ITS BASIN
4. MAJOR IMPACT STORIES OF THE LAKE
5. MAJOR LAKE BASIN GOVERNANCE ISSUES
6. KEY CHALLENGES TO LAKE GOVERNANCE
1.0 INTRODUCTION
4. Known for the original sanctuary for the Arowana Malayan Gold
- the high quality fresh water fish in the world .
Physical Parameters
Saddle Dam 1
Bukit Merah Dam comprises a main dam, 2 saddle dams, a gated service spillway,
a gated auxiliary spillway and an intake structure
2. Description Of The Lake
Bukit Merah Lake Brief
22 -23rd Febuary 2010 NRE Putrajaya
Main Infrastructures
Main Dam – modified homogeneous earth filled embankment
• Spillways
• To safely convey
discharge past the dam
without unacceptable
damage at RL +30.00 ft
South Spillway
(max discharge 15,000 ft3/s)
North Spillway
(max discharge 5,000 ft3/s)
DID, KERIAN
Downstream view of the intake structure that conveys irrigation and domestic
water supply to the main conveyances
Ara River
Based on Malaysia Science University Research Study Team conducted in 2007 & 2008
has concluded the following the water balance parameters:-
Based on 2008 USM’s studies the water balance inflow and outflow summarization can be tabulated as follows:-
Water Balance (Inflow & outflow ( monthly average- 2008)
800
700
600
500 Runoff(mm)
400 Rainfall (mm)
300 Evaporation (mm)
200
100
0
Nov
Jan
June
July
Feb
April
August
Sept
Oct
Mac
May
Dec
Retention Time
RETENTION TIME = Volume of lake / Outflow rate
RETENTION TIME = 83 million m3/2498851.9m3/day , (actual average supplied = 29m3/s /day)
= 33 Days
DID’s daily average Q discharge requirement to the irrigation area = 1000 ft3/s or
= 28 m3/s for 24,000hectares
NATIONAL SEMINAR ON MANAGING LAKE S AND THEIR
BASIN FOR SUSTAINABLE USE:CURRENT STATUS OF
DID, KERIAN SELECTED LAKES IN MALAYSIA 22-23 FEB 2010
Bukit Merah Lake Brief
22 -23rd Febuary 2010 NRE Putrajaya
200 7
6
150 5
4
100 3
50 2
1
0 0
4/1/1998
10/18/1998
5/6/1999
11/22/1999
6/9/2000
12/26/2000
7/14/2001
1/30/2002
8/18/2002
3/5/2003
9/21/2003
4/8/2004
10/25/2004
5/13/2005
11/29/2005
6/16/2006
1/2/2007
7/21/2007
2/6/2008
8/24/2008
Rainfall Water level
Levels recorded higher in the months of March-Mei and Oct – Nov correlates
with higher precipitation during these period
Bukit Merah Lake Brief
22 -23rd Febuary 2010 NRE Putrajaya
13.9ton/day
Based on bathymetric
Survey conducted in
1964,1984 & 1998
Sedementation occupies 10-15%
Est’d annual load /yr = 49,600ton/yr of the lake’s volume
Bukit Merah Lake Brief
22 -23rd Febuary 2010 NRE Putrajaya
Chlorophyta
Euglenophyta
Prrrhophyta
Chrysophyta
Cynophyta
Chloromonadophyta
1. Irrigation
4. Fisheries Facilities
5. Tourism Facilities
Parameters to consider
South Spillway
(max discharge 15,000 ft3/s) 3.0 Flood Control Management
Had experienced severe drought Jun 2009 levels hit lowest ever recorded
at RL 20.3ft.
No rice field area damaged – yield increased –due to long sun light
period – longer photosynthesis process.
Malayan Gold
Estimated 40% of the watershed area – Northern/Eastern portion covered by floating and aquatic
vegetation – especially near both Merah and Kurau River Mouth
No detail studies have been carried out to determine the rate of water useage/area by these so
called aquatic plants but it is believed to have an impact to the lake’s storage capacity. – over 104
years of undisturbed growth
believed to
vegetation growth
or sedimentation Kurau River
area
• Lately DID had out sourced the clearing work by open tender to
private contractors in phases
2006-2007 - Phase I : RM 7,289,400
2008-2009 Phase II : RM 5,521,500
2nd Major Impact Stories – Major Land Clearing By Privately Own Property
Major private lands clearing adjacent to lake for replanting purposes which have
an impact to lake’s water quality and sedimentation problems.
2nd Major Impact Stories – Major Land Clearing By Privately Own Property
Milky color
forest reserve
4800hectares
1000ha cleared
Despite the problems faced by the existing track’s alignment, the train’s
authority still proceed with new NEDTP’s alignment following at the side of
the existing track
Under the NEDTP, level is raised to another 2 m-, DID plan to raise lake level in future planning.
RM100m(USD 31m) budget bid for 10th Malaysia Plan for the upgrading of Bukit Merah Dam . New
double track build on concrete viaduct to promote free flow of water underneath
But in order to promote the free flow underneath the viaduct the existing track
has to be removed which the KTMB’s consortium didn’t budget for in their initial
tender. It is estimated another USD 1m required for the removal cost.
Discussions still underway on who and how the removal of these tracks need
to be carried out.
Water quality degradation became concerned as the turbidity increased near the
construction’ site
Other than turbidity water quality index raising concerned, oil spill problems from
the pilling pontoons occasionally monitored in the lake, imposed certain threats
to the domestic and irrigation water supply downstream.
Backfilling inside the lake for casting yard and storage for
constructions materials
About 5 hectares of backfilling inside the lake were approved by the government
in order for the NEDTP’s contractor to have working space for the project
NATIONAL SEMINAR ON MANAGING LAKE S AND THEIR
BASIN FOR SUSTAINABLE USE:CURRENT STATUS OF
DID, KERIAN SELECTED LAKES IN MALAYSIA 22-23 FEB 2010
Bukit Merah Lake Brief
22 -23rd Febuary 2010 NRE Putrajaya
Since the location of the operation is too close to the lake , same environmental
control requirements are imposed to the sand operators such as installation of
silt curtain and oil residue traps within the operation vicinity. Occasional checkings
on the leakages along the curtain traps are done from time to time by both
parties(DID and sand operators)
Perak State Gov – decided to alienate 1670 acres of government land and another
100 acres inside the lake to MK Land Properties developer to develop BMLTR
in the 90s’
Water cruises
Water Chalets
Initial condition - no development within 100m buffer from the watershed @RL+28.5ft
to safe guard the riparian zones and filter layer
4 ft
RL+28.5ft
DID has no authorities on the lake/ & the basin but given responsibilities
for lake/river maintenance and operation
On top of that the development working structure and state land used controlled
development have covered and touched six(6) focus areas till the year 2020 of
Planning strategies.They are:-
BML
1.0 JKKK – Village Action And Security Committee – one of most powerful
level of local participation = headed by village head(appointed by the state
highest representative political ruling party and co chaired
with Penghulus or Chieftains, a District Office representative
Knowledge and information on related acts, legislatives and guidelines which can be
regulated and related to lake basin management:-
1) Irrigation Areas Act 1953(1989)
2) Drainage Works Act 1954(1988)
3) Third National Agricultural Policy(1998-2010)
4) National Land Code 1965 and Waters
5) Water Act 1920 (Cap 146)(1989)
6. Local Government Act (1976) Peninsular
7. Earthwork Bylaw, Street Drainage And Building Act 1974 (1994)
8. Town and Country Planning Act 1976
9. Environmental Quality Act 1874 (1985)
10. Environmental Quality Regulations (Prescribed premises, Sewerage and Industrial
Effluent); Crude Palm Oil (1977), Sewerage And Industrial Effluent (1979) etc
11. Environmental Quality Order 1987(Environmental Impact Assessment – Prescribed Activities)
12. Land Conservation Act 1960
13. National Forestry Act 1984 (Forestry Rules 1986)
14. Mining Enactment 1936
15. Fisheries Act 1963(1985)/ Inland Fisheries Act
16. MASMA – URBAN STORM MANAGEMENT MANUAL
5.5.1 MASMA
DID had implemented MASMA – URBAN STORM MANAGEMENT MANUAL
implemented since 2001- approved by Prime Minister’s Cabinet
12% of the lake basin catchment – small urban development – MASMA can be
implemented – environmental friendly drainage design – control at source
5.5.2 ESCP – Erosion and Sedimentation Control Plan
Also applies under MASMA requirement for urban development.
Rubber plantation- smallholder – land converted to rubber – able to get replanting grant
from RISDA – RM2500/acre -
Palm Oil replanting – land converted to palm oil – FELCRA – assist loan financing –
Deduction in stages – small sum - in yearly dividends to the smallholders.
BM Lake basin area- covers > 40% by rubber and palm oil –projected by 2020
NATIONAL SEMINAR ON MANAGING LAKE S AND THEIR
BASIN FOR SUSTAINABLE USE:CURRENT STATUS OF
DID, KERIAN SELECTED LAKES IN MALAYSIA 22-23 FEB 2010
Bukit Merah Lake Brief
22 -23rd Febuary 2010 NRE Putrajaya
6.1.2 One Stop Center Committee – each district has its own OSC Committee –
processing all development applications submitted by private developer to
develop an agricultural land to be converted to building purposes = MASMA
applies here.- only relevant technical department attending this OSC meetings –
DID, PWD, Fire and Rescue Department, Water Works, Town and Rural Planning
Department, Department of Environment. This committee was formed under the
Ministry Of Housing and Local Government
6.1.3 Double Electrified Track Train Project Committee = monitor the project
progress and assists the consortium to avoid delays and negative impact to the
environment by giving comments and suggestions to the consortium
State Level – State River Committee has been formed – for a start
Chaired by an Executive State Councilor – politically appt
A task force on Ops Lumpur or Anti Siltation Flash Floods Ops – papers
drafted by this committee to present in the State Govt EXCO Meeting-highest level
of state approval authority – final draft preparation
State issued guidelines – district levels to form River Sand Extraction Permit Committee
Penghulus or the chieftains may bring matters pertaining complaints and grouses
from these VSAC to the DAC meetings if necessary
Govt officer may attend the VSAC if being invited to clarify certain issues or to
inform new procedures or regulations to be implemented in the basin which may
involve them directly or indirectly.
Related govt officials – can attend or invite – RISDA or FELCRA smallholders or the
officers concerned to discuss the concerned environmental issues which relate to
their actions if necessary – esp focus on replanting issues
NATIONAL SEMINAR ON MANAGING LAKE S AND THEIR
BASIN FOR SUSTAINABLE USE:CURRENT STATUS OF
DID, KERIAN SELECTED LAKES IN MALAYSIA 22-23 FEB 2010
Bukit Merah Lake Brief
22 -23rd Febuary 2010 NRE Putrajaya
DID had carried out Bythemetric survey – 1968, 1984 & 1998
– USM’s assisted on analysis of comparison made
– siltation status – 10%-15% of the lake’s total volume
-watershed area – before DID quoted – 48km2 –actually only 33km2
- vegetation cover analysis – 40%-45% of the watershed area.
Able to plan for future improvement of the storage capacity – knowing present
limitation and capacity – able to improve present operation prosedures
Due to limitation of area of development and funding – lake basin – upper catchment -
MASMA/ESCP – not widely accepted – govt projects but widely applied to privates.
Resettlement housing programmes for the hardcore poor- poor respond to MASMA
Unfortunately after 15 years since launched only 20% of the alienated area –developed
overdue tax collection =RM 6m.